This is the accessible text file for GAO report number GAO-08-786 
entitled 'FAA Airspace Redesign: An Analysis of the New York/New 
Jersey/Philadelphia Project' which was released on August 29, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Congressional Requesters: 

United States Government Accountability Office: 
GAO: 

July 2008: 

FAA Airspace Redesign: 

An Analysis of the New York/New Jersey/Philadelphia Project: 

GAO-08-786: 

GAO Highlights: 

Highlights of GAO-08-786, a report to congressional requesters. 

Why GAO Did This Study: 

In September 2007, after 9 years of evaluation and a cost of over $53 
million, the Federal Aviation Administration (FAA) announced it would 
begin implementing a new airspace structure for the New York/New 
Jersey/Philadelphia metropolitan area. According to FAA, this redesign 
of routes leading to and from commercial airports will fully integrate 
the airspace in the region, produce $300 million annual savings, and 
reduce delay by 20 percent once fully implemented. Critics disagree and 
cite potential increases in aircraft noise and other adverse 
environmental impacts. GAO was asked to examine: (1) the extent to 
which FAA followed legal requirements for its environmental review, (2) 
the extent to which FAA’s methodology in assessing operational and 
noise impacts was reasonable, and (3) the likelihood FAA will meet its 
projected time frames and costs of implementation. GAO’s legal analysis 
covered applicable federal laws, regulations, court decisions, and FAA 
orders. GAO’s analysis of FAA’s methodology was based on criteria 
established through review of federal policy, FAA’s guidance, prior GAO 
reports, and standards from the aviation and analytical community. With 
the assistance of the National Academy of Sciences, GAO identified 
experts in the fields of environmental policies and procedures, 
airspace operations, and aircraft noise measurement and obtained their 
views on relevant aspects of FAA’s methodology. 

What GAO Found: 

GAO evaluated FAA’s compliance with the National Environmental Policy 
Act (NEPA) and environmental justice directives in conducting the New 
York/New Jersey/Philadelphia Airspace Redesign project. In assessing 
compliance, GAO used established court precedent applying these 
requirements, as well as the standard of review for agency actions 
established by the Administrative Procedure Act (APA), which is 
deferential to agency decision making. Courts interpret the APA 
standard—whether an agency’s actions were “arbitrary, capricious, an 
abuse of discretion, or otherwise not in accordance with law”—as 
mandating that an agency act reasonably in carrying out NEPA’s 
requirements and that the agency’s ultimate decisions be reasonable and 
not arbitrary and capricious. GAO reviewed FAA’s compliance with 
respect to five key issues: the statement of the project’s purpose and 
need, the evaluation of alternatives, consideration of the project’s 
environmental effects, public participation, and environmental justice 
matters. GAO selected these issues based on public concerns raised 
during and after the NEPA process, congressional interest, the views of 
experts we interviewed, and GAO’s evaluation of the range of concerns 
presented. 

Applying these legal requirements and the APA’s reasonableness 
standard, GAO concluded that FAA complied with applicable NEPA 
requirements and related environmental justice directives. First, the 
statement of the project’s purpose and need—which defines the objective 
of the project and which, in this case, was to increase the efficiency 
and reliability of the airspace while enhancing safety and reducing 
delays—was reasonable. The statement was reasonable in scope, as it was 
not defined too narrowly or too broadly, and it reasonably excluded 
noise reduction. Second, FAA developed a reasonable range of 
alternatives to the redesign and appropriately evaluated these 
alternatives. As required, FAA included a no-action alternative to 
serve as a baseline, as well as alternatives that would achieve the 
project’s purpose and need. FAA also discussed options eliminated from 
detailed analysis, and explored and objectively evaluated the remaining 
alternatives. Third, FAA acted reasonably in not analyzing the indirect 
environmental effects of potential growth resulting from the redesign. 
Because FAA found the redesign in itself would not increase traffic 
demand and flight operations, it did not consider the potential 
environmental impacts of these system improvements. In the aviation 
context, courts have uniformly upheld similar decisions by FAA where, 
as in this case, the purpose of the project was not to induce growth 
and the project did not include capacity-enhancing construction, such 
as the addition of a runway. Fourth, FAA reasonably involved the public 
throughout the environmental review process. It took actions required 
to ensure public outreach including conducting an early and open 
process, providing notice of and holding public meetings, and 
soliciting and responding to public comments. Fifth, FAA satisfied 
environmental justice directives in Executive Order 12898 and related 
guidance and Orders. FAA prepared an analysis that identified minority 
and low-income populations significantly impacted by the proposed 
redesign, and determined whether the impact on these populations was 
disproportionate. FAA also involved these individuals throughout the 
environmental review process. In addition, FAA mitigated these 
significant impacts by altering arrival procedures and departure 
headings, raising arrival altitudes, and other related measures. 

FAA’s methodology to assess operational and noise impacts was 
reasonable, based on FAA’s guidance for conducting airspace redesigns, 
standards from the aviation and analytical community, and the opinion 
of independent aviation operational and noise experts. FAA’s guidance 
suggests activities for conducting a redesign’s operational analysis 
and establishes specific guidelines for conducting a noise analysis. 
FAA generally adhered to this guidance in conducting the redesign, in 
that FAA generally followed its process for conducting operational 
analyses and used the noise modeling tool and metric specified in its 
guidance. In addition, according to experts, FAA used experienced 
contractors, the best available modeling tools, and appropriate data. 
For example, according to FAA and experts we interviewed, the data 
sources, such as FAA radar flight track data, U.S. Geological Survey 
terrain data, and U.S. Census Bureau data, are industry standard and 
generally recognized as providing reliable information. However, GAO 
and experts also identified some ways in which the methodology could be 
improved for future redesign projects. For example, when evaluating the 
alternatives, FAA did not analyze various economic impacts, such as 
implementation costs. GAO identified two types of analyses—an 
uncertainty analysis and a benefit-cost analysis—that could have 
benefited decision makers and the public in future redesign efforts. An 
uncertainty analysis would provide more information about the level of 
uncertainty associated with conducting the operational analysis, while 
a benefit-cost analysis would provide more information about the 
impacts of various alternatives. 

FAA has not developed a detailed implementation plan for the New 
York/New Jersey/Philadelphia Airspace Redesign with a schedule, and 
therefore GAO was unable to determine whether FAA would meet its 
projected timetable. In addition, the final project configuration and 
costs are unknown since FAA has not determined the type of equipment 
and software that will be needed and FAA is currently reviewing whether 
to house operations for the redesigned airspace in existing FAA 
facilities, a new facility, or a consolidated facility. Given that the 
redesign represents a complex and comprehensive change to the region’s 
airspace, GAO believes it is important to conduct evaluations of the 
redesign after each implementation step to ensure proper 
implementation. A potential strategy that could be used by FAA is an 
adaptive management strategy, which is a process that promotes flexible 
decision making as outcomes from management actions become understood. 

What GAO Recommends: 

GAO recommends that FAA develop and follow a detailed implementation 
plan for the New York/New Jersey/Philadelphia Airspace Redesign that 
includes a time and cost schedule and follow a post implementation 
evaluation plan that includes an adaptive management strategy. In 
addition, GAO recommends that for future airspace redesign projects, 
FAA conduct an uncertainty analysis of key assumptions and inputs to 
provide information on the level of confidence of the estimated impacts 
and conduct a benefit-cost analysis for the purpose of evaluating 
redesign alternatives. 

A draft was provided to DOT and FAA. While DOT said it does not agree 
with everything in the draft, due to pending litigation, DOT declined 
to specify its areas of agreement or disagreement. DOT provided 
technical comments that we incorporated as appropriate. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-786]. For more 
information, contact Susan Fleming, 202-512-2834, flemings@gao.gov or 
Susan Sawtelle, 202-512-6417, sawtelles@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

FAA Complied with Key Legal Requirements in Conducting Its 
Environmental Review for the Regional Airspace Redesign: 

Methodology Used to Assess Key Impacts Was Reasonable, However 
Additional Analyses Could Have Benefited Decision Making and the 
Public's Understanding: 

Lack of Detailed Implementation Plan Raises Questions about Time Frames 
and Costs: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: FAA's Legal Compliance with Key NEPA Requirements and 
Environmental Justice Directives: 

Appendix III: Operational Comparison of Alternatives: 

Appendix IV: Summary of the Integrated Airspace Alternative with ICC: 

Appendix V: Comments from the Department of Transportation: 

Appendix VI: GAO Contacts and Staff Acknowledgments: 

Tables: 

Table 1: Summary of Public Participation Opportunities during the EIS 
Process: 

Table 2: List Of Experts Providing Input During Our Review: 

Figures: 

Figure 1: Map of Regions with Major Airports and Satellite Airports 
Included in FAA's Analysis: 

Figure 2: General Representation of a Cross Section of the Different 
Air Traffic Control Facilities and Procedures: 

Figure 3: Timeline of FAA's New York/New Jersey/Philadelphia Airspace 
Redesign Project: 

Figure 4: Alternatives Considered under the FAA New York/New Jersey/ 
Philadelphia Airspace Redesign EIS: 

Figure 5: Example of Departures without and with Dispersal Headings: 

Figure 6: Simplified Representation of the Methodology Used by FAA to 
Assess Operational and Noise Impacts: 

Figure 7: Description of FAA's Estimated 20 Percent Reduction in 
Airport Delay: 

Figure 8: Description of the 12 Million Minutes Saving in Delay 
Savings: 

Abbreviations: 

APA: Administrative Procedure Act: 

ATC: Air Traffic Control: 

ATO: Air Traffic Organization: 

CAASD: Center for Advanced Aviation System Development: 

CEQ: Council on Environmental Quality: 

DNL: Day-Night Average Sound Level: 

DOT: Department of Transportation: 

EIS: environmental impact statement: 

FAA: Federal Aviation Administration: 

FFRDC: Federally Funded Research and Development Center: 

FHWA: Federal Highway Administration: 

FICON: Federal Interagency Committee on Noise: 

Handbook: FAA Airspace Management Handbook: 

ICC: Integrated Control Complex: 

JFK: John F. Kennedy International Airport: 

LaGuardia: LaGuardia Airport: 

NATCA: National Air Traffic Controllers Association: 

NEPA: National Environmental Policy Act: 

Newark: Newark Liberty International Airport: 

NextGen: Next Generation Air Transportation System: 

NIRS: Noise Integrated Routing System: 

NJCAAN: New Jersey Coalition Against Aircraft Noise: 

Philadelphia: Philadelphia International Airport: 

RNAV: Area Navigation (technology): 

SEL: Sound Exposure Level: 

TAAM: Total Airspace and Airport Modeler: 

Teterboro: Teterboro Airport: 

TRACON: Terminal Radar Approach Control: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

July 31, 2008: 

The Honorable James Oberstar: 
Chairman: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

The Honorable Jerry Costello: 
Chairman: 
Subcommittee on Aviation: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

The Honorable Robert Andrews: 
The Honorable Joseph Sestak: 
House of Representatives: 

In September 2007, after 9 years of evaluation and a cost of over $53 
million, the Federal Aviation Administration (FAA) announced that it 
would implement a new airspace structure for the five major airports 
[Footnote 1] and several regional airports serving the New York/New 
Jersey/Philadelphia metropolitan area.[Footnote 2] According to FAA, 
the expected growth in the region's air travel contributed to the need 
for the airspace redesign, the goal of which is to increase the 
efficiency and reliability of the region's airspace, while maintaining 
safety. The efficient operation of the airspace is important, since the 
region's airports are critical to the nation's aviation system. For 
example, because the New York metropolitan area airports provide 
service to one of the most populated urban areas in the United States, 
as well as to substantial commercial air traffic,[Footnote 3] any 
delays in this region tend to ripple throughout the National Airspace 
System. The region's airspace, therefore, has become a critical 
chokepoint, and any resulting problems have substantial national 
impacts. FAA believes that the redesigned airspace will have several 
important benefits, including reducing airport delays, increasing the 
balance of air traffic controller workloads and operational 
flexibility, and maintaining the throughput of airports. FAA estimates 
that when compared to the current airspace structure, the redesigned 
airspace will produce $300 million annual savings in direct costs and 
will reduce delay by 20 percent once fully implemented.[Footnote 4] 
However, many in the region's local communities disagree that the 
redesign will yield these benefits and worry that the redesign will 
substantially increase aircraft noise and produce other environmental 
impacts, both in communities already affected and in areas where 
aircraft traditionally have not flown. A number of critics maintain 
that FAA's decision to implement the new airspace structure is based on 
a flawed process and a predetermined outcome. For example, some critics 
question the methodology FAA used to develop the different alternatives 
evaluated in the airspace redesign and maintain that FAA did not fully 
assess nonairspace alternatives, such as requiring airlines to pay 
additional fees for airport use during peak demand times. Based on 
these and other objections, state and local governments and citizen 
groups have filed 13 separate lawsuits challenging the redesign, based 
primarily on FAA's alleged failure to comply with the National 
Environmental Policy Act (NEPA).[Footnote 5] While this litigation is 
pending, FAA has begun implementation of the redesign, with initial 
steps starting on December 19, 2007.[Footnote 6] Full implementation is 
estimated to be completed by 2012. 

You asked us to review FAA's airspace redesign project for the New 
York/New Jersey/Philadelphia region. Accordingly, this report focuses 
on the following questions: 

1. To what extent did FAA follow key legal procedures and requirements 
in conducting its environmental review? 

2. To what extent was the methodology used by FAA to assess the 
operational and noise impacts reasonable? 

3. What is the likelihood that FAA will meet its project time frames 
and costs of implementing its airspace redesign project? 

To address our three research questions, we reviewed documents 
associated with the New York/New Jersey/Philadelphia Airspace Redesign, 
including the draft and final environmental impact statements (EIS) and 
selected appendices, underlying technical reports and analyses, and the 
administrative record filed by FAA with the court in the pending 
litigation. We also obtained and analyzed information from a variety of 
other sources, including previous FAA airspace redesigns similar to 
this project and other aviation evaluations and studies.[Footnote 7] We 
interviewed officials from the Department of Transportation (DOT) and 
from FAA's headquarters and eastern regional office, including 
representatives of FAA's airspace redesign team. We also contacted 
other stakeholders, including FAA's principal contractors[Footnote 8] 
for the operational and noise analyses, the Port Authority of New York 
and New Jersey, City of Philadelphia Department of Aviation, other 
participants in the EIS process, trade organizations for the aviation 
industry, the national air traffic controller's union, and community 
groups in the region. 

To assess the extent to which FAA followed key legal procedures and 
requirements in conducting its environmental review, we reviewed 
applicable federal laws, regulations, executive directives, and court 
decisions, as well as FAA and DOT Orders and FAA and Council on 
Environmental Quality (CEQ) guidance. We then conducted a legal 
analysis to determine FAA's compliance with respect to five key issues: 
the statement of the project's purpose and need, evaluation of 
alternatives, consideration of the project's environmental effects, 
public involvement, and environmental justice matters. We selected 
these five issues based on public concerns raised during and after the 
EIS process,[Footnote 9] congressional interest, the views of experts 
we interviewed, and GAO's evaluation of the range of concerns 
presented. To examine the extent to which the methodology used by FAA 
to assess the operational and noise impacts was reasonable, we compared 
FAA's methodology to criteria we established through review of federal 
policy, FAA guidance, prior GAO reports, and standards from the 
aviation and analytical community. In addition, with the assistance of 
the National Academy of Sciences, we identified experts in the fields 
of EIS policies and procedures, airspace operations and system 
modeling, and aircraft noise measurement and mitigation. These experts 
reviewed selected portions of the EIS related to FAA's operational and 
noise analysis. We then interviewed these experts within their area of 
expertise to obtain their views on the extent to which FAA followed 
applicable procedures and requirements, and on the methodology used by 
FAA to assess the operational and noise impacts. See appendix I for a 
list of the experts we interviewed. 

As agreed with you, we did not prepare a new EIS or develop and analyze 
new alternatives to the airspace redesign. We conducted this 
performance audit from July 2007 to July 2008 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

Results in Brief: 

Our evaluation of FAA's compliance with NEPA in conducting the New 
York/New Jersey/Philadelphia Airspace Redesign was based on established 
court precedent applying NEPA and its implementing regulations, and the 
standard of review for agency actions established by the Administrative 
Procedure Act (APA), which is deferential to agency decision making. 
Courts interpret this APA standard--whether an agency's actions were 
"arbitrary, capricious, an abuse of discretion, or otherwise not in 
accordance with law"--as requiring that an agency act reasonably in 
carrying out NEPA's requirements and that the agency's ultimate 
decisions be reasonable and not arbitrary and capricious. We reviewed 
FAA's compliance with respect to five key issues: the statement of the 
project's purpose and need, evaluation of alternatives, consideration 
of the project's environmental effects, public involvement, and 
environmental justice matters. We selected these five issues based on 
public concerns raised during and after the EIS process, congressional 
interest, the views of experts we interviewed, and GAO's evaluation of 
the range of concerns presented. 

Applying these NEPA requirements and the APA's reasonableness standard 
to these five key issues, we concluded that FAA complied with 
applicable NEPA and related requirements and environmental justice 
directives. First, the statement of the project's purpose and need-- 
which defines the objectives of the project and which, in this case, 
was to increase the efficiency and reliability of the airspace while 
maintaining safety and reducing delays--was reasonable. The statement 
was reasonable in scope because it was not defined too narrowly or too 
broadly, and it reasonably excluded noise reduction. Second, FAA 
developed a reasonable range of alternatives to the redesign and 
appropriately evaluated these alternatives. As required, FAA included a 
no action alternative, which served as the baseline, as well as 
alternatives that would achieve the project's purpose and need. FAA 
also discussed options it eliminated from detailed analysis, and 
explored and objectively evaluated the remaining alternatives. Third, 
FAA acted reasonably in not analyzing the indirect environmental 
effects of potential growth resulting from the redesign. Because FAA 
found that the redesign in itself would not increase traffic demand and 
flight operations, it did not consider the potential environmental 
impacts of these system improvements. In the aviation context, the 
courts have uniformly upheld similar decisions by FAA where, as in this 
case, the purpose of the project was not to induce growth and the 
project did not include capacity-enhancing construction, such as the 
addition of a runway. Fourth, FAA reasonably involved the public 
throughout the environmental review process. It took the actions 
required to ensure appropriate public outreach, including conducting an 
early and open process, providing notice of and holding public 
meetings, and soliciting and responding to public comments. Fifth, FAA 
satisfied environmental justice directives in Executive Order 12898 and 
implementing CEQ guidance and DOT Orders. FAA prepared an analysis that 
identified minority and low-income populations significantly impacted 
by the proposed redesign and determined whether the impact on these 
populations was disproportionate. FAA also involved these individuals 
throughout the environmental review process. In addition, FAA mitigated 
these significant impacts by altering arrival procedures and departure 
headings, raising arrival altitudes, and other related measures. 

FAA's methodology to assess the operational and noise impacts was 
reasonable, based on FAA's guidance for conducting airspace redesigns, 
standards from the aviation and analytical community, and the opinions 
of experts we interviewed. FAA's guidance suggests activities for 
conducting a redesign's operational analysis and establishes specific 
guidelines for conducting a noise analysis. We found that FAA generally 
adhered to this guidance, generally following its process for 
conducting operational analyses and using the noise modeling tool and 
metric specified in its guidance. In addition, independent experts we 
interviewed generally agreed that FAA used experienced contractors and 
used the best available tools to model the operational and noise 
impacts of the airspace redesign. Furthermore, we found no evidence 
that the data used are unreliable, and experts interviewed generally 
agreed that FAA used data that were appropriate and standard to the 
industry and chose metrics to measure the operational impacts that were 
reasonable and aligned with the objectives of the airspace redesign. 
For example, according to FAA and experts we interviewed, such data 
sources as FAA radar flight track data, U.S. Geological Survey terrain 
data, and U.S. Census Bureau data are industry standard and generally 
recognized as providing reliable information. On the basis of generally 
accepted economic principles and practices, expert opinions, past FAA- 
sponsored airspace redesigns, and prior GAO reports, we also identified 
some limitations in FAA's methodology that, if addressed, would provide 
more information for decision makers and the public. We and the experts 
we interviewed do not believe these limitations are substantial enough 
to warrant redoing the analyses, but rather, would help identify ways 
in which FAA's methodology could be improved in future airspace 
redesigns. These limitations are not matters that FAA is required by 
law to address. One limitation is that because FAA assumed that traffic 
demand and flight operations would not increase in response to airspace 
system improvements--specifically, delay reductions and operating cost 
savings--FAA did not account for the potential effect of the system 
improvements in its operational analysis. FAA also did not fully assess 
the uncertainty associated with each alternative's estimated impacts: 
FAA did not consider a range of values for key assumptions and inputs, 
even though some key inputs, such as the aviation demand forecast, are 
inherently uncertain. In addition, when evaluating the alternatives, 
FAA did not analyze economic impacts, such as implementation costs, the 
effect of the alternatives on the airlines, passengers' time value, or 
the effect of noise on the quality of life of residents living near the 
airports. FAA did not estimate the economic impacts of noise in part 
because the agency is not required under CEQ regulations to do so. We 
identified two analyses that, while FAA is not required by law or 
guidance to conduct, could benefit decision makers and the public. 
First, an uncertainty analysis that examines a range of key assumptions 
and inputs, such as the aviation demand forecast, would provide 
additional information on the potential range of the redesign's impact 
to decision makers and the public. Second, a benefit-cost analysis, 
which assesses the benefits and costs of each alternative compared to 
the status quo, would have provided decision makers and the public with 
more information on whether the estimated benefits of the redesigned 
airspace justify its costs. 

Based on the information available to date, we are unable to fully 
assess the likelihood that FAA will meet its projected five-year 
implementation time frame or determine the costs of the airspace 
redesign project. Although FAA internal guidance recommends that an 
implementation plan--including specific implementation activities, such 
as establishing a project schedule or planning for potential 
challenges--be developed immediately after approval of the airspace 
redesign, FAA has not developed a detailed implementation plan that 
outlines these specific activities. However, even though FAA does not 
have a detailed implementation plan available, FAA began limited 
implementation at Philadelphia and Newark on December 19, 2007. Without 
a more detailed implementation plan, we cannot determine whether FAA is 
likely to meet its projected schedule or how it will deal with 
potential challenges. In addition, for two principal reasons, the final 
project configuration and costs are unknown. First, although FAA will 
use currently available equipment and software, FAA has not determined 
the type or amount that will be needed to support the common automation 
platform for air traffic controllers. Second, FAA is currently 
reviewing whether the common automation platform, which will allow 
different air traffic controllers to communicate with each other, will 
be housed in existing FAA facilities, a new facility, or in a 
consolidated facility. If FAA decides to house this platform in a new 
facility, FAA officials stated that a final cost estimate for the new 
facility will not be available until late 2008, and is not projected to 
be completed until 2015, 3 years after FAA has estimated full 
implementation of the airspace project. Given that the redesign 
represents a complex and comprehensive change to the region's airspace, 
the agency also should consider how it plans to conduct evaluations of 
the redesign. One potential strategy for FAA to employ is adaptive 
management, which is a process that promotes flexible decision making 
as outcomes from management actions become understood, and is a 
strategy that GAO has recommended for other federal agencies. 
Furthermore, adaptive management is recognized by the CEQ and other 
federal agencies as a useful strategy. 

To improve FAA's implementation of the New York/New Jersey/Philadelphia 
Airspace Redesign, we are recommending that the Secretary of the 
Department of Transportation direct the Acting Administrator of the 
Federal Aviation Administration to develop and follow a detailed 
implementation plan and postimplementation evaluation plan using an 
adaptive management strategy for this airspace redesign. To improve 
FAA's effectiveness and accountability in conducting future airspace 
redesigns we are recommending that the Secretary of the Department of 
Transportation direct the Acting Administrator of the Federal Aviation 
Administration conduct uncertainty analyses and benefit-cost analyses 
when evaluating the potential effect of future airspace redesigns. 

In commenting on a draft of this report, DOT stated that it was pleased 
that the GAO review concluded the actions taken by FAA with regard to 
NEPA were reasonable. However, DOT also noted that while it did not 
necessarily agree with everything in the draft report, it is 
constrained from offering a detailed analysis of the draft report at 
this time, as the matters the report covers are the subject of pending 
litigation (see app. V for DOT comments). DOT provided technical 
comments that we incorporated as appropriate. 

Background: 

For several reasons, the New York/New Jersey/Philadelphia airspace is 
unique and highly complex. First, numerous airports are located within 
a small geographic area, including some of the nation's most important 
major airports. In the New York City metropolitan area alone, there are 
four major airports, including New York's John F. Kennedy International 
Airport (JFK) and LaGuardia Airport (LaGuardia) and New Jersey's Newark 
Liberty International Airport (Newark) and Teterboro Airport 
(Teterboro). Philadelphia International Airport (Philadelphia) is 
located less than 100 miles southwest of New York City. The region also 
has numerous satellite airports,[Footnote 10] which provide substantial 
aviation service to Connecticut, New Jersey, southeastern New York, and 
eastern Pennsylvania (see fig. 1). Second, the region's airports 
provide service to a very large air travel market. Since the New York 
metropolitan area has one of the largest urban populations in the 
United States, there is a substantial market for air travel, which is 
serviced by many domestic and international airlines. Third, three of 
these airports--JFK, Newark, and Philadelphia--serve as hubs for major 
U.S. airlines[Footnote 11] to connect passengers to other flights. 
Finally, both LaGuardia and JFK have been slot controlled[Footnote 12] 
in the past. In January 2007, the authority to issue slot restrictions 
at LaGuardia and JFK airports expired;[Footnote 13] however, due to the 
increased congestion and flight delays at LaGuardia, JFK, and Newark, 
FAA has imposed temporary slot controls at these airports with the goal 
of preventing an increase of scheduled flights during peak demand 
times. 

Figure 1: Map of Regions with Major Airports and Satellite Airports 
Included in FAA's Analysis: 

[See PDF for image] 

This figure is a map of regions with major airports and satellite 
airports included in FAA's analysis, as follows: 

JFK: John F. Kennedy Intl.
LGA: La Guardia: 
EWR: Newark Liberty Intl. 
PHL: Philadelphia Intl. 
TEB: Teterboro: 
ABE: Allentown/Lehigh Valley Intl. 
ACY: Atlantic City Intl: 
BDR: Bridgeport/Igor I. Sikorsky Memorial: 
CDW: Caldwell/Essex County: 
ISP: Islip/Long Island: 
LDJ: Linden Airport: 
WRI: McGuire AFB: 
MMU: Morristown Municipal: 
HVN: New Haven/Tweed-New Haven: 
SWF: Newburgh/Stewart Intl. 
PNE: Northeast Philadelphia: 
FRG: Republic Airport; 
TTN: Trenton/Mercer County: 
FOK: Westhampton Beach/The Francis S. Gabreski: 
HPN: White Plains/Westchester County: 
ILG: Wilmington/New Castle County: 

Source: FAA. 

[End of figure] 

According to FAA, the current airspace structure--which basically has 
remained the same since the 1960s[Footnote 14]--is inefficient and 
cannot meet future travel demands without increasing delays. The 
airspace was designed for lower air traffic volumes and different types 
of aircraft, and is characterized by complex, highly interrelated 
departure and arrival routes. FAA maintains that there is a need to 
redesign the region's airspace because the current structure cannot 
efficiently address the increased air traffic levels, the use of new 
aircraft types, and emerging technologies to control air traffic. In 
addition, because specific routes used by aircraft taking off from one 
airport overlap routes from other airports, safety-related 
inefficiencies ensue. Severe weather conditions also may hinder 
aircraft's access to departure routes at certain airports. According to 
FAA, the complexity of the airspace also has contributed to 
inefficiencies in the air traffic management for the region. To provide 
air traffic management for the region's airspace, FAA uses a variety of 
air traffic control facilities and predetermined and coordinated 
procedures and routes. Each ATC facility has a specific--and different-
-area of responsibility for the overall management of the regional 
system. Figure 2 depicts a cross section of the different air traffic 
control facilities and procedures. 

Figure 2: General Representation of a Cross Section of the Different 
Air Traffic Control Facilities and Procedures: 

[See PDF for image] 

This figure is a general representation of a cross section of the 
different air traffic control facilities and procedures, as follows: 

1. Routes: FAA uses predetermined and coordinated procedures and routes 
during the entire flight of the aircraft starting with its departure 
from the origin airport, through its en-route flight, and ending with 
landing at its destination airport. 

2. En-route: The phase that occurs between terminal areas, including 
the climb, cruise, and descent phases of the flight. Air traffic 
controllers at Centers control the aircraft during this phase of the 
flight. 

3. Arrival posts: At the arrival posts, Center air traffic controllers 
hand off the aircraft to TRACON air traffic controllers.[A] 

4. Terminal airspace: TRACON facilities are responsible for directing 
aircraft movement in the airspace approximately 50 miles from the 
airport. TRACON facilities direct aircraft to the assigned route and 
specific altitude. 

5. Airport traffic control towers (ATCT): ATCTs manage aircraft on the 
ground, and the arrival and departure of aircraft into airports. ATCTs 
control aircraft during the initial moments after takeoff and prior to 
landing, when the aircraft is within approximately 5 nautical miles of 
the airport and up to approximately 3,000 feet above the airport. 
Handover of flights are coordinated between ATCT and TRACON 
controllers. 

6. Departure headings: ATCT controllers will direct aircraft to use 
specific departure headings, routes, and altitudes during its takeoff 
and then shortly after takeoff. 

7. Separation rules: Separation rules are the required spacing between 
aircraft. This spacing may be vertical, lateral, longitudinal, and 
visual. Different separation rules apply to different aircraft. 

8. Departure gates: Transition areas within the TRACON boundaries where 
aircraft are directed and transferred to another controller. 

9. Departure fixes: At the departure fixes, TRACON controllers hand 
over the aircraft to Center controllers. 

10. Overflights: Aircraft whose flights originate or terminate outside 
the controlling facility’s area. 

Source: GAO (data); Art Explosion (images). 

[A] Terminal Radar Approach Control (TRACON)--An FAA air traffic 
control facility that uses radar and two-way radio communication to 
provide separation of air traffic within a specific geographic area in 
the vicinity of one or more large airports. 

[End of figure] 

In April 1998, FAA launched the nation's first-ever coordinated, 
comprehensive National Airspace Redesign program with goals of moving 
aircraft more efficiently and more safely through the airspace system. 
The goals of this program are identified in the National Airspace 
Redesign Strategic Management Plan,[Footnote 15] and include 
maintaining system safety, decreasing system delay, increasing system 
flexibility, increasing system predictability, and increasing user 
access. The Airspace Management Program Office is responsible for 
airspace redesign project planning and ensuring that planning goes 
beyond the design phase and includes an execution and implementation 
focus. Other organizations also are involved in the national airspace 
redesign efforts, such as the Environmental Protection Agency, which 
reviews and publicly comments on the adequacy of FAA's analysis of 
environmental impacts. 

In 1998, as part of its National Airspace Redesign program, FAA 
initiated the New York/New Jersey/Philadelphia Airspace Redesign. To 
redesign the airspace, FAA uses its Airspace Management Handbook 
(Handbook)--which describes step-by-step procedures for airspace design 
management--to guide the overall management of the redesign project and 
must follow applicable environmental laws and regulations. The Handbook 
provides FAA guidance on all phases of the redesign project from 
characterizing the initial problem to conducting the operational 
analysis for the airspace redesign to postimplementation 
evaluation.[Footnote 16] FAA also is required to comply with 
NEPA.[Footnote 17] NEPA requires that a detailed EIS be prepared for 
all major federal actions significantly affecting the quality of the 
human environment.[Footnote 18] To implement NEPA, CEQ has promulgated 
regulations that set forth specific requirements that all federal 
agencies must adhere to in the EIS process. Among other things, CEQ 
regulations require an EIS to (1) specify the purpose of and need for 
the federal action, (2) describe the environment that will be affected, 
(3) identify alternatives to the proposed action and identify the 
agency's preferred alternative(s), (4) present the environmental 
impacts of the proposed action (including the direct and indirect 
effects and cumulative impacts), (5) identify any adverse environmental 
impacts that cannot be avoided should the proposed action be 
implemented, and (6) identify any irreversible and irretrievable 
commitment of resources that would occur should the proposed action be 
implemented. Agencies also must make diligent efforts to involve the 
public throughout the EIS process.[Footnote 19] For additional 
direction on implementing NEPA and CEQ regulations, FAA developed 
Orders[Footnote 20] that govern, among other things, its EIS process. 
In addition, Executive Order 12898,[Footnote 21] accompanying CEQ 
guidance, and DOT Order 5610.2[Footnote 22] set forth environmental 
justice directives, which FAA must adhere to in conducting its 
environmental review. The executive order directs agencies to address 
"disproportionately high and adverse human health or environmental 
effects of [an agency's] programs, policies, and activities on minority 
populations and low-income populations…."[Footnote 23] 

Figure 3 shows some of the key dates in the preparation of FAA's 
airspace redesign and the EIS for the New York/New Jersey/Philadelphia 
project. 

Figure 3: Timeline of FAA's New York/New Jersey/Philadelphia Airspace 
Redesign Project: 

[See PDF for image] 

The timeline is depicted as follows: 

1999-2000: 
September 22, 1999–February 3, 2000 - FAA held prescoping workshops for 
the public. 

2000: 
July - FAA issued prescoping report. 

2001: 
January 22 - Notice of Intent to prepare an EIS for NY/NJ/PHL Airspace 
Redesign published in the Federal Register. 

February 7–May 24 - FAA conducted formal scoping public meetings. 

2002: 
March - FAA issued scoping report. 

2002-2005: 
FAA conducted operational and environmental analysis for redesign. 

2005: 
December 30 - EPA published Notice of Availability of draft 
environmental impact statement (DEIS) in Federal Register; DEIS public 
comment period closed. 

2006: 
February 7 – May 2 - FAA conducted public meetings for DEIS. 

May 30 - FAA extended DEIS public comment period by 30 days. 

July 1 - DEIS public comment period closed. 

2007: 
March 23 - FAA selected the preferred alternative. 

April 6 - FAA issued Noise Mitigation Report. 

April 6 – May 11 - Public comment period for Noise Mitigation Report. 

April 23 – June 28 - FAA conducted public meetings on the Noise 
Mitigation Report. 

August 3 - EPA published Notice of Availability of final environmental 
impact statement (FEIS) in Federal Register. 

September 5 - FAA issued Record of Decision (ROD). 

September 28 - FAA issued corrected ROD. 

Source: GAO and FAA. 

[End of figure] 

After determining that it would prepare an EIS, and following 5 years 
of scoping and options development, in December 2005, FAA issued a 
draft EIS for public comment that identified four basic alternatives. 
The first alternative, mandated by NEPA as a baseline, was the Future 
No Action Alternative, which represents what the airspace structure 
would be if the airspace redesign did not occur. The second 
alternative, the Modifications to Existing Airspace Alternative, would 
have made only slight adjustments within the existing airspace. That 
is, this alternative would have maintained the current boundaries of 
the control tower, the Terminal Radar Approach Control (TRACON) 
facility, and the Center facility. The third alternative, the Ocean 
Routing Airspace Alternative, would have sent all departing flights 
from Newark over the Raritan Bay to the Atlantic Ocean before turning 
them back over land to head to their departure gates. The main purpose 
of this alternative was to reduce the noise impacts on the citizens of 
New Jersey. The final alternative was evaluated using two versions. The 
Integrated Airspace Alternative Variation without Integrated Control 
Complex (ICC) would have changed the current boundaries of the 
airspace, to the extent possible, but would have done so with the 
existing ATC facilities and equipment. The second version, the 
Integrated Airspace Alternative Variation with ICC, would have fully 
integrated the airspace using a common automation platform for ATC 
equipment. It also may have involved consolidating air traffic 
controllers into a consolidated facility.[Footnote 24] Figure 4 
provides a summary of the different alternatives, the eight evaluation 
criteria applied to each alternative, and the measures or "metrics" 
used to compare each alternative. 

Figure 4: Alternatives Considered under the FAA New York/New Jersey/ 
Philadelphia Airspace Redesign EIS: 

[See PDF for image] 

The following information is presented in the figure: 

Future No Action Airspace Alternative: 
Maintains the current airspace structure. 

Modification to Existing Airspace Alternative: 
Modifies existing airspace but maintains the current boundaries of the 
ATC facilities. 

Ocean Routing Airspace Alternative: 
Sends all Newark departing flights over the Raritan Bay to the Atlantic 
Ocean before routing flights back over land to head to their departure 
gates. 

Integrated Airspace Alternative: 
Combines the New York TRACON airspace with portions of surrounding 
Centers’ airspace to permit more seamless operations without a common 
automation platform or a consolidated facility. 

Integrated Airspace Alternative Variation without Integrated Control: 
Combines the New York TRACON airspace with portions of surrounding 
Centers’ airspace to permit more seamless operations with a common 
automation platform and the possibility of a consolidated facility. 

Evaluation Criteria: Reduce complexity; 
How Measured: 
* Jet route delays plus time below 18,000 feet: Measures over a 24-hour 
period average flight delay and average flight time for a departing 
aircraft to reach 18,000 feet altitude. 
* Arrival distance below 18,000 feet: Measures average distance 
traveled by an arriving aircraft from 18,000 feet altitude to landing. 

Evaluation Criteria: Reduce voice communication; 
How Measured: 
* Maximum interfacility handoffs per hour: Measures number of 
controller-to-controller communications an hour to transfer aircraft 
responsibility from one ATC facility to another. 

Evaluation Criteria: Reduce delay; 
How Measured: 
* Traffic weighted arrival delay 2011 and traffic weighted departure 
delay: Measures the difference in estimated time required for an 
aircraft to arrive or depart absent any delays and to arrive or depart 
under a specific alternative. 

Evaluation Criteria: Balance controller workload; 
How Measured: 
* Equity of west gate fix traffic counts: Measures the balance of 
aircraft traffic among departure fixes—where aircraft responsibility is 
handed over between ATC towers—in a particular departure gate—the 
transition area within TRACON boundaries. 

Evaluation Criteria: Meet system demands and improve user access to 
system; 
How Measured: 
* End of day’s last arrival push: Measures time when the final bank of 
scheduled flights from all study area airports enters the TRACON 
system. 

Evaluation Criteria: Expedite arrivals and departures; 
How Measured: 
* Time below 18,000 feet: Measures average flight time spent descending 
or climbing per flight in a 24-hour period. 
* Change in route length per flight: Measures the difference in 
distance flown between Future No Action Airspace Alternative and each 
alternative. 
* Change in block time: Measures average departure gate to arrival gate 
flight time in a 24-hour period. 

Evaluation Criteria: Flexibility in routing; 
How Measured: 
* Minutes of delay saved per flight per day: Measures modeled delay 
caused by waiting out or flying around a 4-hour weather disruption 
divided by the total number of flights. 

Evaluation Criteria: Maintain airport throughput; 
How Measured: 
* Arrival maximum sustainable throughputs: Measures number of landings 
per hour. 
* Departure maximum sustainable throughputs: Measures number of 
takeoffs per hour. 

Source: GAO and FAA. 

[End of figure] 

FAA recommended the Integrated Airspace Alternative Variation with ICC 
as its preferred alternative, as it scored highest on 10 of the 13 
metrics FAA used to compare the alternatives. Appendix III provides the 
full operational comparison of the alternatives. Because the preferred 
alternative involves integrating the New York TRACON and portions of 
the surrounding Centers' airspace, air traffic controllers will be able 
to reduce aircraft separation rules from 5 miles to 3 miles over a 
larger geographical area than the current airspace structure allows. In 
addition, the preferred alternative will modify other key airspace 
components. Appendix IV provides a more detailed summary of the 
Integrated Airspace Alternative Variation with ICC. Under this 
alternative, for example, FAA will be able to increase the number of 
departure headings air traffic controllers can assign to aircraft 
during take-offs, and adjust the routes air traffic controllers can 
assign aircraft during their final approach to an airport. Figure 5 
shows an example of departures without and with dispersal headings 
(increasing the number of departure headings). 

Figure 5: Example of Departures without and with Dispersal Headings: 

[See PDF for image] 

This figure is an illustration of departures without and with dispersal 
headings. Without dispersal headings, the separation distance is 3 
miles. Separation distance is just over 1 mile with dispersal departure 
headings. 

Source: GAO (data); Art Explosion (images). 

Note: These separation distances are based on normal conditions with 
similar types of aircraft. Separation distances can be increased 
depending on certain weather conditions or if smaller aircraft are 
taking off after a large-body aircraft. 

[End of figure] 

After the preferred alternative was announced, FAA initiated a noise 
mitigation study to develop measures to alleviate, to the extent 
possible, the noise impacts associated with the preferred alternative. 
The study identified several mitigation measures for analysis--some of 
which were later incorporated into the preferred alternative based on 
the results of this analysis. The mitigation measures changed some 
aspects of the preferred alternative, including reducing the number of 
departure dispersal headings, shifting certain departure routes, and 
changing certain arrival altitudes. According to FAA, the mitigation 
measures incorporated into the preferred alternative would not 
substantially reduce the operational gains that FAA believes would 
occur once the mitigated preferred alternative is fully implemented. 
For example, at Philadelphia, FAA originally planned to increase the 
number of new departure dispersal headings on one of its runways from 
one to six, which would have allowed air traffic controllers to 
decrease the time between aircrafts on take-offs and increase the 
number of departures in a given amount of time. However, FAA's analysis 
of the mitigation measures recommended that the number of headings 
could be reduced from six to three headings, while minimizing the loss 
of operational efficiency. The preferred alternative with mitigation 
measures was identified as the selected project in FAA's Record of 
Decision, which was issued on September 5, 2007.[Footnote 25] 

FAA officials have projected a 5-year time frame for full 
implementation of the redesigned airspace, which will be implemented in 
four stages. According to FAA, each stage will take 12 to 18 months to 
implement; elements that do not require large-scale changes to the 
current airspace structure will be implemented first, while more 
complex changes will be implemented later. For example, during the 
first stage, implementation focuses on procedural changes, such as 
adjusting the departure dispersal headings at three of the major 
airports. FAA implemented the use of additional departure dispersal 
headings at Philadelphia and Newark as of December 19, 2007. 

FAA Complied with Key Legal Requirements in Conducting Its 
Environmental Review for the Regional Airspace Redesign: 

Our evaluation of FAA's compliance with NEPA and related requirements, 
in conducting the airspace redesign, was based on established court 
precedent applying NEPA and its implementing regulations. In deciding 
whether an agency adequately carried out these requirements, a court 
uses a standard of review articulated in the APA, which is deferential 
to agency decision making--whether an agency's actions were "arbitrary, 
capricious, an abuse of discretion, or otherwise not in accordance with 
law."[Footnote 26] Courts interpret this APA standard as requiring that 
an agency act reasonably in carrying out NEPA's requirements and that 
the agency's ultimate decisions be reasonable and not arbitrary and 
capricious. We reviewed FAA's compliance with respect to five key 
issues: the statement of the project's purpose and need, evaluation of 
alternatives, consideration of the project's environmental effects, 
public involvement, and environmental justice matters. We selected 
these five issues based on public concerns raised during and after the 
EIS process, congressional interest, the views of experts we 
interviewed, and GAO's evaluation of the range of concerns presented. 
Applying these NEPA requirements and the APA's reasonableness standard, 
we concluded that FAA complied with respect to these five key issues. 
Our detailed legal analysis is contained in appendix II and is 
summarized below. 

FAA's Statement of Purpose and Need Complied with Requirements: 

FAA's statement of purpose and need, which defined the objectives and 
parameters of the project, complied with NEPA requirements. FAA 
developed the following purpose and need statement: 

"The purpose of the airspace redesign is to increase the efficiency and 
reliability of the airspace structure and ATC system. The need is to 
accommodate growth in aircraft operations while maintaining safety, 
mitigating delays, and accommodating changes in the types of aircraft 
using the system."[Footnote 27] 

CEQ regulations require that FAA "…briefly specify the underlying 
purpose and need to which the agency is responding in proposing the 
alternatives including the proposed action."[Footnote 28] Additionally, 
FAA Order 1050.1E requires that the purpose and need statement 
"…present the problem being addressed … and essentially provide the 
parameters for defining a reasonable range of alternatives to be 
considered."[Footnote 29] FAA specified the purpose and need and 
defined the parameters of the project such that a reasonable number of 
alternatives could be developed--the statement was not too narrowly or 
too broadly defined. During the EIS process, members of the public and 
certain advocacy groups supported the inclusion of noise minimization 
in the redesign's stated purpose. According to FAA officials, although 
the agency was aware that noise was an important issue to the public 
from the onset of the EIS process, it is not FAA's policy to minimize 
noise impacts for one community at the expense of another. FAA noted in 
the final EIS that its highest priority must be to maintain a safe and 
secure airspace. Based on our legal review, we find FAA's decision to 
exclude noise from the purpose and need to be reasonable, in part, 
because NEPA does not require agencies to elevate environmental 
concerns--in this case noise--over other appropriate considerations. 
Rather, NEPA requires only that agencies consider the environmental 
impacts of their actions as part of their decision making. FAA's 
decision also is consistent with court precedent, including a court 
decision upholding an FAA purpose and need statement excluding noise 
from a major airport expansion, even though the project would have 
caused significant noise impacts.[Footnote 30] 

FAA's Range and Evaluation of Alternatives Complied with Requirements: 

FAA complied with the various NEPA requirements for evaluating the four 
alternatives, including the selected project, during the EIS process. 
In the EIS, the agency included a no action alternative and discussed 
alternatives eliminated from detailed analysis. In addition, the 
evaluated alternatives were responsive to the agency's purpose and need 
and were reasonably developed, rigorously explored, and objectively 
compared to each other throughout the EIS. 

* Representation of a baseline of current airspace conditions in an 
alternative. By including a Future No Action Alternative, FAA complied 
with the requirement[Footnote 31] to provide a no action alternative 
that provided a baseline of current conditions to which the other 
alternatives were compared. 

* Discussion of alternatives eliminated. FAA "briefly discussed the 
reasons…"[Footnote 32] for alternatives that were evaluated but 
subsequently eliminated from detailed consideration in the EIS. 
[Footnote 33] For example, during the formal scoping period, there was 
public support for the development of alternatives that included either 
alternate modes of transport or improvements to airport infrastructure 
(such as additional runways at Philadelphia) as means to reduce delays 
or improve operational efficiency. In addition, during subsequent 
public comment periods stakeholders suggested other alternatives, such 
as peak hour demand controls. Within the EIS, FAA explained that while 
it had considered these alternatives, it ultimately eliminated them 
because they did not meet the purpose of reducing the inefficiencies of 
the airspace. 

* Assessment and evaluation of reasonable alternatives. In order to be 
"reasonable," the range of alternatives must first be responsive to the 
purpose and need.[Footnote 34] Our review showed that to develop the 
alternatives, FAA worked with modelers and air traffic controllers in 
an iterative and collaborative process specifically to design 
alternatives that were feasible within the parameters of the redesign's 
purpose and need. Furthermore, FAA used the project's purpose and need 
to evaluate the alternatives, both quantitatively and qualitatively, as 
each evaluative criterion informed an aspect of the stated purpose and 
need. Some community stakeholders and government officials criticized 
the range of alternatives considered, pointing out that FAA did not 
include an alternative that focused on noise reduction. However, FAA 
officials explained that as noise reduction was not among the defined 
purposes of the redesign, it did not have to be considered when 
developing the alternatives. Furthermore, with the inclusion of the 
noise mitigation for the preferred alternative, FAA believes it 
minimized environmental impacts, such as noise, to the extent possible 
while continuing to address the purpose and need. Despite stakeholder 
concerns, as noted above, we find FAA was responsive to the project's 
purpose and need, which did not include noise reduction; additionally, 
the selected project, which did include noise mitigation measures, 
minimized noise impacts to the extent possible while still addressing 
the project's purpose and need.[Footnote 35] 

* Alternatives' comparative merits. To comply with the CEQ regulation, 
alternatives also must be discussed in reasonable detail;[Footnote 36] 
there must be a rigorous exploration of each alternative.[Footnote 37] 
As demonstrated by the thorough discussion throughout the EIS, FAA 
substantially evaluated each of the four primary alternatives, 
including both operationally--discussing routing procedures, reduction 
of complexity, delay, voice communication, and balancing controller 
workload--and in terms of the alternative's environmental consequences. 
FAA also compared the alternatives using specified criteria and 
presented the alternatives in summary comparison tables, thereby 
enabling "reviewers [to] evaluate [the alternatives'] comparative 
merits."[Footnote 38] 

FAA's Decision Not to Consider Environmental Effects of the Potential 
Growth Inducement Resulting from Airspace Redesign Complied with 
Requirements: 

FAA complied with NEPA in its decision not to analyze the environmental 
effects of a potential increase in capacity resulting from the regional 
airspace redesign. CEQ regulations require that within the EIS process, 
an agency must consider the direct and indirect effects and cumulative 
impacts of a proposed action when evaluating the environmental 
consequences.[Footnote 39] Indirect effects,[Footnote 40] which are 
reasonably foreseeable future effects caused by the current project, 
may include growth-inducing effects, among others. FAA did not analyze 
the indirect effects of potential growth resulting from the redesign 
because it found that the redesign would not in itself create a growth- 
inducing effect or increase capacity. Therefore, FAA concluded that 
such an analysis was not required. Members of the public and government 
agencies criticized FAA's decision, stating that the efficiencies 
gained from a redesigned airspace would lead to an increase in capacity 
and consequently would increase air traffic and emissions. In other 
words, an indirect effect would occur as a result of the redesigned 
airspace. 

We found that FAA's decision not to consider these potential indirect 
environmental effects was reasonable under court decisions applying 
these NEPA requirements. In the aviation context, courts have uniformly 
upheld similar decisions by FAA not to analyze the effects of induced 
growth where the purpose of the project was not growth inducing and did 
not add runway capacity. The U.S. Court of Appeals for the Ninth 
Circuit, for example, ruled that FAA complied with NEPA even though it 
did not consider the possible growth-inducing effects of altering 
arrival procedures at Los Angeles International Airport, where there 
would be no changes to the airport's infrastructure. The court 
explained that although growth might certainly be foreseeable, "the 
project was implemented in order to deal with existing problems; the 
fact that it might also facilitate further growth is insufficient to 
constitute a growth-inducing impact…" under CEQ regulations.[Footnote 
41] Likewise in this case, the purpose of the regional airspace 
redesign was to increase the efficiency and reliability of the existing 
airspace structure and ATC system--not growth inducement--and the 
project does not add runway capacity. Therefore, we found that FAA was 
not required to analyze potential environmental effects of increased 
growth that might result from the airspace redesign. 

FAA Complied with Public Participation Requirements: 

FAA complied with NEPA requirements to make "…diligent efforts to 
involve the public…"[Footnote 42] during the EIS process by (1) 
conducting an early and open process to determine the scope of issues, 
[Footnote 43] (2) providing notice of and holding public meetings, 
[Footnote 44] and (3) soliciting and responding to public comments. 
[Footnote 45] We determined that FAA used an "early and open" process, 
as demonstrated by an extensive prescoping campaign: 31 "prescoping" 
workshops were conducted prior to the formal scoping period[Footnote 
46] which drew 1,174 attendees and prompted 712 written comments. As 
with the scoping meetings, according to FAA, the purpose of these 
meetings included improving public understanding of the project and 
increasing FAA's understanding of public issues that would need to be 
addressed as part of the redesign process. For these meetings, as well 
all other public meetings conducted for the redesign, FAA advertised in 
local media outlets for upcoming meetings and developed a mailing list 
to send notifications about public meetings and periodic updates on the 
redesign.[Footnote 47] FAA continued to conduct public meetings and to 
solicit public comments for the scoping and draft EIS periods by 
holding 58 public meetings that drew over 2,000 attendees. In addition, 
FAA held seven public meetings during the Noise Mitigation Report 
comment period, drawing the largest number of participants--2,200. 
According to FAA officials, meeting locations for the different phases 
of the EIS process were selected based on multiple criteria including 
site suggestions from government officials and their staffs, proximity 
to areas that would be by the proposed action, and FAA's goal to hold 
at least one meeting in each affected state.[Footnote 48] 

During the EIS process, public comments included criticism that the 
meeting locations were not widely dispersed around the affected states. 
There also was criticism that the comment period for the Noise 
Mitigation Report was too short and that there were too few public 
meetings regarding this report, which addressed one of the most 
controversial and technically complex issues of the redesign. As 
demonstrated in table 1, although FAA held the fewest number of public 
meetings for this phase of the EIS process, the meetings had the 
highest number of attendees. FAA officials stated that they recognized 
that noise mitigation issues would attract a lot of public attention. 
Despite stakeholder concerns, we concluded that FAA complied with their 
requirements.[Footnote 49] 

FAA also solicited public comments and considered and responded to 
comments, as required by CEQ regulations, in an adequate manner. 
[Footnote 50] The public comment period for the Scoping and Noise 
Mitigation periods lasted at least 30 days. For the draft EIS comment 
period, FAA extended the initial 5-month comment period by 30 days to 
allow the public more time to submit its comments. FAA also solicited 
public comments at the public meetings and accepted them during the 
public comment periods via U.S. mail and e-mail. Receiving numerous 
public comments, FAA categorized and responded to all substantive 
comments for the draft EIS comment period in the final EIS. Based on 
FAA's solicitation and response to public comments received throughout 
the EIS process, we concluded FAA's actions complied with requirements. 
See table 1 for a summary of public participation opportunities during 
the EIS process. 

Table 1: Summary of Public Participation Opportunities during the EIS 
Process: 

Phase: Prescoping; 
Total number of public meetings: 31; 
Time period for public meetings (days): 135; 
Total number of public attendees: 1,174; 
Length of comment period (days): [Empty]. 

Phase: Scoping; 
Total number of public meetings: 28; 
Time period for public meetings (days): 107; 
Total number of public attendees: 1,031; 
Length of comment period (days): 159. 

Phase: Draft EIS; 
Total number of public meetings: 30; 
Time period for public meetings (days): 85; 
Total number of public attendees: 1,166; 
Length of comment period (days): 184. 

Phase: Noise Mitigation; 
Total number of public meetings: 7; 
Time period for public meetings (days): 67; 
Total number of public attendees: 2,200[A]; 
Length of comment period (days): 36. 

Sources: GAO and FAA. 

[A] The source documentation cites that "over 2,200 people" attended 
the noise mitigation meetings. As a specific number was not included by 
FAA in its documentation, GAO used the number that was listed--2,200. 

[End of table] 

FAA Complied with Environmental Justice Directives: 

FAA complied with environmental justice directives set forth in 
Executive Order 12898,[Footnote 51] accompanying guidance,[Footnote 52] 
and DOT Order 5610.2,[Footnote 53] including (1) identifying and 
addressing, as appropriate, disproportionately high and adverse 
environmental impacts of the proposed action on minority and low-income 
populations and (2) eliciting public involvement from minority and low- 
income populations during the EIS process. Understanding that potential 
significant noise impacts could result from the alternatives, FAA 
identified and addressed any disproportionately high and adverse human 
health or environmental impacts on minority and low-income populations 
in the study area. First, FAA used U.S. Census Bureau block data to 
identify the areas that could be significantly impacted by noise. Then, 
FAA determined whether the impact on minority and low-income 
populations was disproportionate.[Footnote 54] While certain areas were 
identified as locations with significant environmental impacts to 
minority and low-income populations, the mitigation measures outlined 
in the selected project reduced the expected impacts by 2011 to below 
significant levels, as defined by FAA's standard of noise exposure. 
Therefore, FAA concluded that no additional measures were needed to 
minimize noise impacts for the identified minority and low-income 
populations. By conducting this assessment, FAA met the directive to 
identify and address disproportionate significant impacts on low-income 
and minority populations. [Footnote 55] 

To comply with DOT Order 5610.2 and guidance accompanying Executive 
Order 12898, FAA elicited opportunities for public involvement of 
minority and low-income populations for the public meeting periods of 
the EIS. As the final EIS described, prior to the start of the public 
meeting periods, the agency worked with congressional offices to 
determine appropriate locations that would accommodate the specific 
needs of minority and low-income populations. According to FAA 
officials, a number of meetings during each public meeting period of 
the EIS process were held in locations accessible by public transit. 
Additionally, public meetings throughout the EIS process period were 
held in low-income and minority communities. Foreign language 
translators were also provided at certain meetings and information was 
presented in a variety of formats. Lastly, FAA published advertisements 
for the draft EIS public meetings in specialized local foreign language 
media throughout the redesign's affected states. Thus, FAA complied 
with requirements outlined in Executive Order 12898 and related 
guidance and Orders. 

Methodology Used to Assess Key Impacts Was Reasonable, However 
Additional Analyses Could Have Benefited Decision Making and the 
Public's Understanding: 

FAA's methodology to assess the operational and noise impacts was 
reasonable, based on FAA's guidance for conducting airspace redesigns, 
standards from the aviation and analytical community, and opinions of 
experts we interviewed. We used FAA's guidance--specifically the 
Handbook and FAA Order 1050.1E--to establish criteria to examine FAA's 
methodology. The Handbook suggests activities for conducting a 
redesign's operational analysis. In addition, FAA Order 1050.1E 
establishes specific guidelines for conducting its noise analysis. We 
found that FAA generally adhered to its guidance in conducting the 
redesign. Specifically, FAA generally followed the process outlined in 
its Handbook and used the noise modeling tool and metrics specified in 
FAA Order 1050.1E. In addition, experts we interviewed generally agreed 
that FAA used experienced contractors, used best available tools to 
model the operational and noise impacts of the airspace redesign, used 
data that were appropriate and standard to the industry, and chose 
metrics to measure the operational impacts that were reasonable and 
aligned with the objectives of the airspace redesign. However, based on 
generally accepted economic principles and practices, expert opinions, 
past FAA-sponsored airspace redesigns, and prior GAO reports[Footnote 
56] we identified four limitations in FAA's operational and noise 
analyses and an additional limitation in not analyzing economic impacts 
when evaluating the alternatives. Based on our analysis and the 
opinions of experts we interviewed, we do not believe that these 
limitations are substantial enough to warrant redoing the analyses, but 
help identify ways in which FAA's methodology could be improved in 
future airspace redesigns. Consequently, we identified two types of 
analyses--uncertainty analyses and benefit-cost analyses--that, 
although not required by law, would provide more comprehensive 
information for decision makers and may increase public understanding 
of FAA's process and decision making in future airspace redesigns. 

Methodology Used to Assess Operational and Noise Impacts Was 
Reasonable: 

FAA's methodology to assess the operational and noise impacts was 
reasonable, based on FAA's guidance for conducting airspace redesigns, 
standards from the aviation and analytical community, and opinions of 
experts we interviewed. To examine FAA's methodology, we focused on 
five components--process, contractors, modeling tools, data, and 
metrics--which we identified from FAA's guidance, interviews with FAA 
officials and experts, and prior GAO reports.[Footnote 57] 
Specifically, we found that FAA generally followed the process outlined 
in its Handbook and used the noise modeling tool and metric specified 
in FAA Order 1050.1E. In addition, FAA used experienced contractors 
and, according to experts we interviewed, the best available modeling 
tools in its operational and noise analyses. Furthermore, we found no 
evidence that the data used are unreliable, and experts interviewed 
generally agreed that FAA used data that were appropriate and standard 
to the industry and chose metrics to measure the operational impacts 
that were reasonable and aligned with the objectives of the airspace 
redesign. 

Process: FAA generally followed the process outlined in its Handbook. 
Airspace studies are generally iterative and involve substantial 
professional judgment. FAA formulated alternatives for redesigning the 
airspace through an iterative process with FAA's airspace redesign 
team[Footnote 58] and MITRE (the organization responsible for the 
operational analysis). Initially, as outlined in FAA's Handbook, 
conceptual ideas were developed based on the project's objectives. Then 
using an operational modeling tool, the conceptual ideas were simulated 
to check that they were technically feasible. If there were parts of 
the conceptual design that did not work as evidenced through the 
modeling, the design was adjusted, and the new design was simulated. 
This iterative process was used in designing the Modifications to 
Existing Airspace Alternative and the two variations of the Integrated 
Airspace Alternative.[Footnote 59] 

Once the conceptual alternatives were designed, FAA collaborated with 
MITRE to develop simulation models for each alternative to measure the 
operational impacts. Performance metrics,[Footnote 60] which are 
selected based on the project's objectives, were used to measure the 
operational impacts, or system improvements, of each alternative. As 
discussed in the Handbook, the purpose of the metrics is to allow FAA 
to evaluate and compare the alternatives, which contributed directly to 
FAA's decision. The Total Airspace and Airport Modeler (TAAM) was the 
primary tool used to model the alternatives' operations and quantify 
the operational impacts in terms of the performance metrics. Additional 
modeling tools were used to supplement the operational analysis. FAA, 
MITRE, and air traffic controllers validated each operational design 
through an iterative process, as outlined in the Handbook, to ensure 
that the models would provide reliable results by reviewing the model 
output, making adjustments, and continuing that process until there was 
agreement that the design was valid. 

After the operational designs were validated, the four alternatives 
were evaluated for environmental impacts, and the results were included 
in the draft EIS. In conducting the noise analysis, FAA collaborated 
with its environmental contractors and MITRE to develop scenarios for 
each alternative to measure the noise impacts in terms of a cumulative 
noise metric. The Noise Integrated Routing System (NIRS) model was the 
primary tool used to measure the noise impacts. While developing the 
input for the noise model, quality assurance checks were conducted by 
the modelers to help assure accuracy in the model output. Using an 
iterative process, FAA's airspace redesign team, the environmental 
contractors, and MITRE reviewed portions of the input for the noise 
model and output from the operational simulations and validated them 
against one another to help ensure consistency between the operational 
and noise analyses. 

FAA selected the Integrated Airspace Alternative Variation with ICC as 
its preferred alternative because, according to FAA, it best met the 
project's objectives. However, after selecting the preferred 
alternative, FAA began the process of identifying measures to mitigate 
the noise impacts associated with the preferred alternative. This 
process again was iterative and involved identifying potential noise 
mitigation strategies and using operational and noise modeling tools to 
measure the operational and noise impacts. The potential noise 
mitigation measures were continually adjusted and evaluated until 
measures were identified that would reduce noise impacts without 
substantial adverse impact on operational efficiency. Several noise 
mitigation measures were incorporated into the preferred alternative, 
resulting in the mitigated preferred alternative--the Integrated 
Airspace Alternative Variation with ICC and mitigation measures. In the 
Record of Decision, FAA identified this alternative as its selected 
project. 

The operational and noise models required substantial amounts of data. 
As highlighted in the Handbook, some data were used as direct inputs to 
the models, such as the airport and runway configurations for the 
airports, while other data were used as supporting data when developing 
the model inputs. For example, in the noise analysis, a sample of radar 
data was analyzed to develop the locations of the terminal and en route 
flight tracks. In addition, numerous assumptions were required for the 
operational and noise analyses. FAA and its contractors made 
assumptions not only when developing the simulations (including the 
simulations' scope and detail), but also when developing the data 
inputs, including the aviation demand forecast. For example, the 
operational models included details down to the airport level based on 
the judgment that the redesign has the possibility of improving 
flexibility of runway use. In addition, while developing the aviation 
demand forecast, which is a key input to the models, numerous 
assumptions were made, including assumptions about future traffic 
demand and the introduction of new aircraft. Figure 6 represents a 
simplified representation of FAA's methodology used to assess 
operational and noise impacts. 

Figure 6: Simplified Representation of the Methodology Used by FAA to 
Assess Operational and Noise Impacts: 

[See PDF for image] 

Developed alternatives: 
FAA developed alternatives through an iterative process with FAA’s 
airspace redesign and contractors. 

Chose performance metrics: 
FAA chose quantifiable performance metrics based on the evaluation 
criteria, which were based on the project’s purpose and need. 

Collected data: 
Numerous data were collected to support development of operational and 
noise models, including airport runway configurations, forecasted 
operations levels, and flight tracks. 

Analyzed alternatives for operational impacts: 
Each alternative was analyzed using a simulation model, which 
quantified the operational impacts in terms of the selected performance 
metrics. 

Analyzed mitigation measures for noise impacts: 
Each alternative was analyzed for noise impacts using a set of noise 
modeling tools, which quantified noise in terms of a cumulative noise 
metric. 

Selected preferred alternative: 
FAA selected the preferred alternative by comparing the operational 
impacts of each alternative to assess which alternative best met the 
project’s purpose and need. 

Identified potential noise mitigation measures: 
FAA identified potential noise mitigation measures for the preferred 
alternative to avoid, minimize, rectify, reduce, eliminate, or 
compensate for significant and reportable noise impacts. 

Analyzed mitigation measures for operational impacts: 
Potential noise mitigation measures were analyzed for operational 
impacts. 

Analyzed alternatives for noise impacts: 
Noise mitigation measures that did not result in significant adverse 
operational impacts were analyzed for noise impacts. 

Developed mitigated preferred alternative (selected project): 
The preferred alternative was modified by incorporating noise 
mitigation measures that reduced noise without significant adverse 
operational impacts. 

Source: GAO and FAA. 

[End of figure] 

Contractors: Key to our finding that FAA's contractors were reasonable 
is the contractors' substantial experience conducting FAA-sponsored 
aviation studies. Experience is important because both operational and 
noise analyses inherently involve substantial professional judgment, 
including determining the detail included in the model to validating 
the model and interpreting the results. For example, the Handbook 
states that some of the key consequences of airspace changes may not be 
captured well by models and that a model's quantitative metrics often 
need to be supplemented with a qualitative review by knowledgeable 
experts. For this reason, one expert we interviewed stated that the 
results of a study depend on the contractor's expertise. MITRE, the 
organization that conducted the operational analysis, is well-respected 
in the industry, according to experts we interviewed. MITRE's aviation 
program has a long-standing relationship with FAA, as evidenced by its 
designation as a Federally Funded Research and Development Center, and 
according to MITRE representatives, has generally conducted FAA's more 
complex airspace redesigns. One expert highlighted that over the years, 
MITRE has improved the main modeling tool used in the operations 
analysis to create more valid simulations. Metron Aviation, Inc., a 
contractor responsible for about half of the noise modeling, developed 
the NIRS model for FAA and has worked on several airspace studies, 
including the Potomac Consolidated TRACON Facility Airspace Redesign 
and the Chicago Terminal Airspace Project. Landrum & Brown and Northrop 
Grumman, the contractors responsible for the other half of the noise 
modeling, also have experience with airspace projects. 

Modeling tools: The experts we interviewed agreed that FAA used 
generally accepted tools to model the operational and noise impacts of 
the airspace redesign. TAAM, the primary operations modeling tool, is 
used to model airspace, airports, and traffic flows. Some experts said 
that TAAM was generally the best tool to use for this airspace 
redesign. It allows for fast-time simulation and analysis of changes to 
route or sector structure, procedures, and traffic levels. For that 
reason, FAA and aviation stakeholders, such as airport owners, also 
have used TAAM to model airport and airspace operations. 

Noise analysis experts that we interviewed uniformly agreed that the 
NIRS modeling tool was the best available tool for this multiairport 
airspace redesign. NIRS is capable of evaluating complex air traffic 
designs involving high-altitude routing, broad-area airspace changes 
affecting multiple airports, and other airspace modifications in the 
terminal and en route environments. While this airspace redesign 
presented noise exposure in terms of 1 metric, NIRS is capable of 
computing 13 predefined noise metrics. NIRS was first released as a 
prototype model in 1998 and has been used in two previous FAA airspace 
studies (the Potomac Consolidated TRACON Facility Airspace Redesign and 
the Chicago Terminal Airspace Project). In addition, FAA Order 1050.1E 
states that the NIRS model must be used for noise analysis of regional 
airspace studies. 

Data: Based on our examination of the data sources and steps taken by 
FAA and its contractors to ensure the completeness and accuracy of the 
data, we found that data used in this airspace redesign (such as the 
airport runway configurations and flight tracks) were appropriate and 
standard to the industry. While we did not conduct our own reliability 
assessments for any data used by FAA, our review disclosed no evidence 
that these data are unreliable. According to FAA and experts we 
interviewed, the data sources are industry-standard and generally 
recognized as providing reliable information. For example, most of the 
data were obtained from governmental sources, such as the radar flight 
track data, U.S. Geological Survey terrain data, and U.S. Census Bureau 
data. Data obtained from nongovernmental sources (such as the Official 
Airline Guide, Airframe Manufacturers Forecast, and other aviation and 
population forecasting studies) were primarily used to support aviation 
demand forecasting, rather than as direct inputs for modeling. While 
FAA did not employ specific procedures to test these data's 
reliability, according to FAA and its contractors, basic professional 
care was undertaken. After data were obtained, generally in electronic 
format to avoid data entry errors, FAA and its contractors took 
additional steps to ensure that the data were complete and accurate. 
For example, FAA and its contractors conducted consistency checks 
throughout the analyses. According to FAA, consistency checks were used 
to identify discrepancies between data sets that, if identified, were 
then reviewed and rectified. In addition, consistency checks were 
conducted on model inputs that were developed. For example, in the 
noise analysis, a sample of radar flight track data was analyzed to 
develop the locations of the terminal and en route flight tracks and 
the flight track dispersions,[Footnote 61] which were used as direct 
inputs to the noise model. Furthermore, two experts we interviewed 
noted that the use of actual radar data in the noise analysis was a 
good practice. 

Metrics: FAA generally used appropriate metrics to measure the 
operational noise impacts. According to the Handbook, the selection of 
performance metrics should be linked to development of the 
alternatives, as well as the project's objectives. For this airspace 
redesign, FAA used several performance metrics from the Handbook's list 
of standard performance metrics. For example, the Change in Route 
Length per Flight metric is correlated to the Handbook's Average 
Arrival Flight Distance metric. The Handbook states, however, that the 
standard performance metrics do not preclude the use of additional 
metrics. For this airspace redesign, FAA also selected and customized 
additional performance metrics based on the airspace redesign's 
specific goals of improving user access and increasing flexibility. 
Experts that we interviewed generally agreed that the performance 
metrics used to measure the operational impacts were reasonable and 
aligned with the project's objectives. One expert also said that 
customizing performance metrics was a good practice because the effects 
of the changes made in the airspace redesign could then be isolated. 

To measure noise exposure, FAA used the Day-Night Average Sound Level 
(DNL) metric that, under FAA Order 1050.1E, must be used as the primary 
noise metric.[Footnote 62] DNL averages the magnitude of sound levels 
generated by all individual events occurring during a 24-hour period, 
with a 10-decibel penalty for noise events occurring during typical 
sleeping hours (between 10:00 p.m. and 7:00 a.m.) To assess the 
significance of the noise impacts, FAA used the generally accepted 
method, which sets a significant noise impact threshold criteria based 
on a dose-response relationship--the correlation of DNL to the 
percentage of population highly annoyed by recurring noise sound 
events. The correlation shows that the percentage of people highly 
annoyed by noise exposure increases significantly above DNL of 65 
decibels. Some aviation noise consultants, however, have noted 
disadvantages of DNL as a metric to measure noise, and suggest the use 
of supplemental metrics that measure the frequency and intensity of 
individual noise events, which may provide a more adequate measure of 
aviation noise as experienced by people. In 1992, after a comprehensive 
review of measurement approaches, the Federal Interagency Committee on 
Noise (FICON) concluded there were no other metrics of sufficient 
scientific standing to replace DNL, and consequently DNL is used by all 
federal agencies when analyzing airport-related noise in environmental 
assessments and impact statements.[Footnote 63] This conclusion was 
still valid as of 2000, according to the chairman of the Federal 
Interagency Committee on Aviation Noise,[Footnote 64] which focuses on 
aviation research related to noise. Although FICON recommended in 1992 
continuing the use of the DNL noise metric as the principal means of 
describing airport noise exposure, the Federal Interagency Committee on 
Aviation Noise recognized in 2002 that supplementing this description 
with noise analyses based on alternative metrics would provide valuable 
information that is not easily captured by DNL, and that the use of 
some supplemental noise metrics can provide a more meaningful estimate 
of impacts than a single DNL estimate. 

Our Review Identified Limitations, Which Had They Been Addressed, Would 
Have Provided More Comprehensive Information for Decision Makers and 
the Public: 

Based on generally accepted economic principles and practices, expert 
opinions, past FAA-sponsored airspace redesigns, and prior GAO reports, 
[Footnote 65] we identified four limitations in FAA's operational and 
noise analyses and an additional limitation in not analyzing the 
economic impacts when evaluating the alternatives. We and the experts 
we interviewed do not believe that the limitations identified are 
substantial enough to warrant redoing the analyses. Addressing these 
limitations would have provided more comprehensive information for 
decision makers and may have increased public understanding of the 
process and decision. For example, although not required, FAA did not 
fully assess the uncertainty associated with its estimated impacts--
that is, it did not consider a range of values for key assumptions and 
inputs--even though some key inputs, such as the aviation demand 
forecast, are inherently uncertain. In addition, although FAA was not 
required to analyze the economic impacts (such as implementation costs 
or the effect of noise on the quality of life of residents living near 
the airports) when evaluating the alternatives, GAO has previously 
highlighted the importance of analyzing economic impacts for agency 
decision making. 

FAA Did Not Account for the Potential Effect of Delay Reductions and 
Operating Costs Savings on Passengers and Airline Traffic: 

Because FAA assumed that traffic demand and flight operations would not 
increase in response to airspace system improvements--specifically, 
delay reductions and operating cost savings--FAA did not account for 
the potential effect of system improvements in its operational 
analysis. While our legal review found that FAA's decision to not 
analyze the potential increase in capacity in its EIS is reasonable 
from a legal standpoint, we believe that FAA's assumption that traffic 
demand and flight operations would not change as a result of system 
improvements poses a methodological limitation. FAA estimated that the 
airspace redesign will reduce airport delay by about 20 percent and 
annual operating costs by about $285 million once implemented (see fig. 
7 for the calculation and context of the 20 percent delay reduction). 
Despite these estimated reductions, however, FAA assumed that traffic 
demand and flight operations would not change as result of system 
improvements.[Footnote 66] 

Figure 7: Description of FAA's Estimated 20 Percent Reduction in 
Airport Delay: 

[See PDF for image] 

FAA projected that the selected project will reduce airport delays by 
20 percent once fully implemented. While the scope of our study did not 
include a validation of FAA’s estimates, we describe below additional 
information about FAA’s projected delay reduction and how FAA 
calculated the 20 percent airport delay reduction for the selected 
project because the detailed calculations were not included in 
documentation that FAA provided to the public. 

* The 20 percent delay reduction is the difference in airport delay in 
2011 between the selected project and the Future No Action Alternative, 
not a reduction from today’s airport delay. 

* This airspace redesign addresses delays within FAA’s control—that is, 
delays in the National Airspace System, as well as flexibility in 
severe weather. Thus, some causes of delay, such as air carrier and 
security delay, will not be reduced as a result of this project. 

* The 20 percent airport delay reduction was calculated by combining 
the minutes of delay in clear weather (arrival delay, departure delay, 
and jet route delay) and severe weather (route flexibility). The 
difference in minutes of delay in 2011 between the selected project and 
the Future No Action Alternative was then translated into a percentage. 

* Estimated delay reduction for the redesign is not equal for all 
airports—that is, delay reductions at some airports will be 
significantly greater than at others. In addition, some airports (most 
notably LaGuardia) will continue to experience significant airport 
delays. (See the table below for estimated airport arrival and 
departure delays.) 

Table: Airport Arrival and Departure Delays in 2011: 

Airport: JFK, Arrivals; 
Future No Action Alternative (minutes per flight): 3; 
Integrated Airspace with ICC (minutes per flight): 1.7; 
Difference (minutes per flight): -1.3; 
Percentage difference: -43%. 

Airport: JFK, Departures; 
Future No Action Alternative (minutes per flight): 11.7; 
Integrated Airspace with ICC (minutes per flight): 9.4; 
Difference (minutes per flight): -2.3; 
Percentage difference: -20%. 

Airport: LaGuardia, Arrivals, 
Future No Action Alternative (minutes per flight): 53.7; 
Integrated Airspace with ICC (minutes per flight): 49.4; 
Difference (minutes per flight): -4.3; 
Percentage difference: -8%. 

Airport: LaGuardia, Departures; 
Future No Action Alternative (minutes per flight): 74.7; 
Integrated Airspace with ICC (minutes per flight): 65; 
Difference (minutes per flight): -9.7; 
Percentage difference: -13%. 

Airport: Teterboro, Arrivals; 
Future No Action Alternative (minutes per flight): 6.4; 
Integrated Airspace with ICC (minutes per flight): 5.3; 
Difference (minutes per flight): -1.1; 
Percentage difference: -17%. 

Airport: Teterboro, Departures; 
Future No Action Alternative (minutes per flight): 2.2; 
Integrated Airspace with ICC (minutes per flight): 2.2; 
Difference (minutes per flight): 0; 
Percentage difference: 0%. 

Airport: Philadelphia, Arrivals; 
Future No Action Alternative (minutes per flight): 14.6; 
Integrated Airspace with ICC (minutes per flight): 14.3; 
Difference (minutes per flight): -0.3; 
Percentage difference: -2%. 

Airport: Philadelphia, Departures; 
Future No Action Alternative (minutes per flight): 8.2; 
Integrated Airspace with ICC (minutes per flight): 7.4; 
Difference (minutes per flight): -0.8; 
Percentage difference: -10%. 

Airport: Newark, Arrivals; 
Future No Action Alternative (minutes per flight): 34; 
Integrated Airspace with ICC (minutes per flight): 26.7; 
Difference (minutes per flight): -7.3; 
Percentage difference: -21%. 

Airport: Newark, Departures; 
Future No Action Alternative (minutes per flight): 20.1; 
Integrated Airspace with ICC (minutes per flight): 13; 
Difference (minutes per flight): -7.1; 
Percentage difference: -35%. 

[End of table] 

Source: HAO; GAO analysis of FAA data (table) 

Note: The table in fig. 7 does not include jet route delay or route 
flexibility used in FAA's calculation of the 20 percent airport delay 
reduction. 

[End of figure] 

FAA's assumption that travel demand will not increase, however, is 
contrary to economic theory and FAA internal guidance.[Footnote 67] 
Based on economic theory, because delays impose costs on airlines (by 
requiring them to operate their aircraft for longer periods and use 
more fuel) and on passengers (by requiring them to spend more time in 
delayed aircraft), a reduction in delays and an airline's operating 
costs would reduce the total price (or cost) of air travel.[Footnote 
68] The reduced total price of air travel would generally provide 
airlines with an incentive to lower fares (that is, they would be able 
to provide the same volume of service at a lower price) and because 
travelers will generally fly more at lower prices, the reduction in 
price could induce an increase in the amount of travel demanded by 
passengers, all else the same. FAA also failed to provide economic 
evidence to support its underlying rationale that traffic demand and 
flight operations will not change as a result of system improvements 
because the demand for air travel in the New York area is "price 
inelastic" (that is, relatively unresponsive to price changes). 
[Footnote 69] FAA guidance, experts we interviewed, and our own 
previous work indicate that the responsiveness of travelers to changes 
in travel price depends on factors such as distance traveled, nature of 
the trip (nonbusiness versus business), and the availability of 
substitute travel modes (for example, rail). Specifically, FAA's 
benefit-cost guidance for capacity-related airport projects (for 
example, building a new runway) indicates that the demand for travel 
over shorter distances and travel by nonbusiness travelers is price 
elastic (that is, relatively responsive to changes in price).[Footnote 
70] In addition, an economist in the aviation industry whom we 
interviewed noted that air travelers who use the New York and 
Philadelphia airports have multiple travel options, especially options 
that compete with short-distance flights, and as a result, demand for 
air travel on these routes is relatively elastic. Our prior work also 
indicates that passenger rail competes with short-distance flights, 
such as the New York to Washington, D.C., market.[Footnote 71] 

We also question FAA's underlying rationale that flight operations 
would not increase as a result of the airspace redesign because the 
redesigned airspace does not increase overall system capacity. 
Specifically, FAA explained that the capacity of the entire airspace 
system--which includes the airspace, runways, and airport terminals--is 
determined by the element in the system with the least capacity, which, 
for the New York metropolitan area, is the capacity of the airport 
runways. Because this redesign does not increase runway capacity, FAA 
concluded that operations would not increase. However, FAA's National 
Airspace Capital Investment Plan states that an objective of this 
airspace redesign project is to increase capacity to meet projected 
demand and reduce congestion.[Footnote 72] In addition, officials from 
the Port Authority of New York and New Jersey--which operates JFK, 
LaGuardia, and Newark--said that this redesign could increase capacity 
and that additional operations at these airports could be achieved. 
Finally, most of the experts that we interviewed believe that the 
capacity in the airspace would increase, which could allow for 
additional operations. Most of these experts, however, also stated that 
any increase in system capacity resulting from the redesign would 
likely be relatively small, such that any increase in new operations 
would also be small. One expert that we interviewed stated that there 
needs to be a major increase in the capacity, such as a new runway, 
before airlines would substantially increase their operations. Also, 
airlines could use a larger aircraft, with more available seats, 
instead of increasing the number of operations. While we believe this 
was a methodological limitation, it is uncertain what the net effect of 
the airspace redesign will be since the final results will depend upon 
the actions of the airlines and passengers in responding to the 
estimated delay reduction and operating cost savings. 

FAA Did Not Fully Account for Future Use of New Technology in the Noise 
Analysis: 

FAA's assumptions in the noise analysis did not fully account for the 
future use of Area Navigation (RNAV) technology.[Footnote 73] 
Specifically, FAA modeled RNAV procedures in the noise analysis of the 
mitigation measures for the preferred alternative, but did not model 
RNAV in the noise analysis used to compare the alternatives, which is 
inconsistent with the operational analysis. RNAV is designed to allow 
aircraft to fly a more precise track, thus examining the effect of RNAV 
on noise impacts could have provided more precise information for 
decision makers and the public. FAA said that it modeled RNAV for some 
mitigation measures of the preferred alternative because mitigation of 
noise impacts could be improved by using RNAV procedures. In the noise 
analysis used to compare the alternatives, however, FAA did not model 
RNAV because FAA said it did not know whether all aircraft using a 
particular route would be equipped with RNAV technology; FAA also did 
not predict which flight tracks airlines would choose. Thus, FAA 
officials said that they did not want to model anything that was not 
guaranteed to be implemented. Our review, however, showed that FAA had 
some indication as to which routes would be used with RNAV because some 
tracks in the operational models were designed to be RNAV compatible. 
An expert whom we interviewed further explained that because FAA had 
designed flight tracks to be more efficient for the purposes of this 
airspace redesign, it could be expected that airlines would use RNAV on 
those tracks that are most efficient. Furthermore, it would be 
reasonable to assume that RNAV will be used within the time frame of 
this airspace redesign because as one expert explained, RNAV reduces 
fuel burn and reduces flight time. FAA's own estimate reflects that 
about 80 percent of operations at the top 35 busiest airports in the 
National Airspace System are estimated to be RNAV capable.[Footnote 74] 

FAA officials also said that RNAV was not modeled in the noise analysis 
because the amount of dispersion depends on a route's designated 
accuracy value,[Footnote 75] which is decided during development of the 
route procedure. According to FAA and its contractors, however, the 
effect of using RNAV in the noise analysis would have created a more 
concise concentration of flight tracks over specific geographic areas 
and would have concentrated noise under these tracks. Therefore, in 
most cases, RNAV may have resulted in fewer people impacted by noise 
but to a greater degree, depending on the location of the RNAV route. 
FAA included some RNAV procedures as noise mitigation measures, 
however. For example, when RNAV is used in the river approach to 
Philadelphia, the flight tracks are concentrated over the river, in 
effect reducing the number of people impacted by noise, as well as 
concentrating the higher noise levels over nonpopulated areas. Experts 
with whom we discussed FAA's use of RNAV said that examining the effect 
of RNAV procedures on the noise impacts could have provided more 
accurate information on the noise impacts. One expert, however, 
considered the FAA's assumption to not fully model RNAV in the noise 
analysis conservative given the uncertainty of the extent to which RNAV 
would become a key part of the airspace system. 

FAA Did Not Assess the Effect of Noise Using Supplemental Noise 
Metrics: 

FAA only assessed noise impacts using a single cumulative noise metric 
that is required under FAA guidance, where additional metrics, not 
required by law or guidance, that measure noise in other ways--called 
supplemental noise metrics--would have provided information that may be 
more readily understood by decision makers and the public than the DNL 
metric.[Footnote 76] As mentioned previously in this report, the 
Federal Interagency Committee on Aviation Noise recognized in 2002 that 
supplementing the DNL cumulative noise metric with alternative noise 
metrics would provide valuable information that is not easily captured 
by DNL, and the use of some supplemental noise metrics can provide a 
more meaningful estimate of physical impacts than a single DNL 
estimate. For example, Sound Exposure Level (SEL)[Footnote 77] and Time-
Above[Footnote 78] are recognized as appropriate metrics for evaluating 
physical impacts associated with noise, such as sleep disturbance and 
speech interference.[Footnote 79] According to FAA representatives, 
supplemental noise metrics were not calculated because the size and 
complexity of this regional airspace redesign would have made their 
inclusion in the EIS more confusing to the public. FAA has, however, 
calculated supplemental metrics, including SEL and Time-Above, in 
previous airspace redesigns.[Footnote 80] While experts we interviewed 
recognized that presenting supplemental metrics in this EIS would have 
been challenging, they said that it was possible, and one expert 
explained that in some cases, it may have helped FAA more easily 
respond to public concerns. One expert said that limiting the 
information to discrete areas may have made presenting supplemental 
metrics in the EIS more manageable. For example, FAA could have 
reported single-event noise levels only for schools or the most common 
or loudest aircraft. In previous airspace redesigns where FAA 
calculated supplemental metrics, they reported the supplemental metrics 
only for areas that experienced noise impacts above a selected DNL 
value. 

FAA Did Not Fully Assess Uncertainty Associated with Estimated Impacts 
of the Alternatives: 

FAA did not fully assess the uncertainty associated with the estimated 
impacts--that is, it did not consider a range of values for the key 
assumptions and inputs--even though some inputs are inherently 
uncertain.[Footnote 81] Rather, when assessing the estimated impacts of 
the four alternatives, FAA generally used point estimates to represent 
traffic demand in 2006 and 2011, such as a point estimate for the 
future fleet mix and traffic levels. As a result, FAA's analysis 
implies greater precision about the redesign's impacts than is 
warranted. Assessing the uncertainty associated with the key 
assumptions and inputs would have provided a range of estimated 
impacts. 

As FAA's own Handbook recognizes, questions are likely to be raised 
about analyses based on uncertain assumptions, and "one way to protect 
a study's integrity … is to develop a few scenarios that reflect 
alternative assumptions for key uncertain elements,"[Footnote 82] that 
is, perform a sensitivity analysis. We heard a range of opinions from 
experts we interviewed about assumptions made in the airspace 
redesign's demand forecast. Two experts said that the demand forecast 
did not fully account for new classes of aircraft, such as the change 
in use of air taxis or regional jets, while one expert noted that the 
forecast did not account for changes in the airlines' hub-and-spoke 
operations. Other experts disagreed with assumptions about airline 
yields or the effects of fuel costs. What most experts that we 
interviewed shared, however, was the belief that FAA should have 
assessed uncertainty by evaluating how changes in key assumptions made 
in the demand forecast would affect the estimated impacts of the 
alternatives. 

FAA did, however, conduct a very limited sensitivity analysis to assess 
the uncertainty associated with one element of the forecasted fleet mix 
and one comparative analysis. According to FAA, based on the results of 
the limited sensitivity analysis, the relative ranking for the 
alternatives did not change. In 2006, FAA--in recognizing that the 
aviation industry had changed since the forecast was conducted-- 
conducted a comparative analysis of some elements of its 2006 forecast 
with the observed levels in 2005 and some elements of the 2011 forecast 
of Philadelphia traffic to the 2012 forecast used for the Capacity 
Enhancement Plan.[Footnote 83] This comparative analysis did not assess 
the uncertainty associated with estimated impacts, but, rather, 
assessed the accuracy of parts of the 2006 and 2011 forecasts developed 
for the airspace redesign. Through the comparative analysis, FAA 
determined that some of the forecasted elements were essentially 
correct (for example, the traffic counts for the 2006 forecast were 6 
percent to 8 percent higher than the 2005 observed levels for the major 
airports in the region)[Footnote 84] while some were inaccurate (for 
example, the estimated fleet mix).[Footnote 85] Based on the results of 
this comparative analysis, FAA determined that the number of regional 
jets at Newark needed further analysis and as a result, conducted a 
very limited sensitivity analysis by increasing the estimated 
proportion of regional jets at Newark in 2006 and recalculating the 
operational impacts for each alternative in 2006. According to FAA, the 
results of the limited sensitivity analysis showed that the relative 
ranking of the alternatives was not affected by the change. 

FAA Did Not Analyze Economic Impacts when Evaluating the Alternatives: 

The criteria used to evaluate the alternatives did not include economic 
impacts, such as implementation costs, the effect of the alternatives 
on the airlines, passengers' time value, or the effect of noise on the 
quality of life of residents living near the airports. According to 
experts interviewed, considering these impacts could have been helpful 
for decision makers because it would have provided more information for 
FAA to better assess whether the estimated benefits of the alternatives 
(relative to the Future No Action Alternative) justified the estimated 
costs. Experts we interviewed also said that a fuller discussion of the 
airspace redesign's potential costs may have increased stakeholders' 
understanding of FAA's decision and, in turn, made FAA's decision more 
palatable to the public. FAA, however, is neither required to, nor 
precluded from, considering these impacts in its decision under CEQ 
regulations. 

Implementation costs: Some experts we interviewed noted that FAA did 
not assess implementation costs when comparing the alternatives with 
the Future No Action Alternative. According to FAA, because 
implementation costs, such as facility or training costs, would be the 
same for all alternatives, their inclusion in the operational analysis 
would not have affected FAA's decision. For example, FAA said that the 
cost for training air traffic controllers is an ongoing agency cost; 
that is, training will occur independently of the airspace redesign. 
However, because the selected project, unlike the other alternatives, 
will require a common automation platform,[Footnote 86] its 
implementation costs[Footnote 87] will be different from the other 
alternatives' implementation costs. Furthermore, although 
implementation costs were not explicitly analyzed when comparing the 
alternatives, FAA suggested in the airspace redesign's operational 
technical report that costs and benefits were assessed. Specifically, 
the operational technical report states that the Integrated Airspace 
with ICC is the only alternative "worth the effort and expense of 
implementing an airspace redesign of this magnitude."[Footnote 88] 

Other economic impacts: We also found that FAA did not assess other 
economic impacts, such as the effect of the alternatives on the 
airlines, passengers' time value, or the effect of noise on the quality 
of life of residents living near the airports. FAA representatives said 
they did not measure the economic impact on airlines or passenger time 
value because they were trying to keep the analysis "clean," and did 
not believe that those impacts were part of the NEPA process. In 
addition, FAA did not estimate the economic impacts of noise, in part 
because they are not required under CEQ regulations to conduct a 
benefit-cost analysis, and noise reduction was not part of the airspace 
redesign's purpose and need.[Footnote 89] While methods to determine 
the economic costs associated with noise impacts are not firmly 
established, economists have used methods for assessing the economic 
impact of changes in noise.[Footnote 90] For example, according to one 
expert we interviewed, FAA could have estimated property devaluation 
associated with noise using the DNL cumulative noise metric calculated 
in the noise analysis. Although not required under CEQ regulations, FAA 
would have had a more comprehensive picture of the trade-offs for each 
alternative had it assessed these economic impacts. 

Uncertainty Analyses and Benefit-Cost Analyses Could Benefit Decision 
Makers and the Public: 

We identified two analyses that would have provided decision makers and 
the public with more comprehensive information. For example, an 
uncertainty analysis using a range of values for key assumptions and 
inputs, such as future demand and operations levels, would have 
provided decision makers and the public with a range of projected 
impacts. In addition, a benefit-cost analysis, which could have been 
used to assess the economic trade-offs between each airspace redesign 
alternative and the status quo, could provide more comprehensive 
information for decision makers to determine whether the estimated 
benefits associated with redesigning airspace justify the costs, and 
provide more transparency in the decision-making process to increase 
the public's understanding. 

Uncertainty Analysis Would Provide Information on the Range of the 
Redesign's Impacts: 

An uncertainty analysis that examined a range of key assumptions and 
inputs, such as the aviation demand forecast and the future use of 
RNAV, would have been useful. For example, a sensitivity analysis (a 
way to assess uncertainty) is used to change the values for key 
assumptions and to assess the effect on the estimated impacts, thereby 
providing decision makers and the public with information to understand 
the sensitivity of the results to changes in the assumptions. The 
analysis can be used to assess the uncertainty associated with the 
estimated impacts--that is, provide a range of projected impacts. The 
basic approach is to vary key assumptions, estimates, and forecasts 
systematically over appropriate ranges and to measure the impact on the 
results. In some cases, the relative impact of competing alternatives 
may be altered as a result of the sensitivity analysis, while in others 
it will not. As we stated in a prior section, FAA did not conduct a 
full sensitivity analysis on the demand forecast's key assumptions but 
only a limited analysis to assess uncertainty in the number of regional 
jets at Newark. FAA reported that the results of this limited 
sensitivity analysis showed that the relative ranking of the 
alternatives was not affected by the change.[Footnote 91] 

An uncertainty analysis is common for evaluations of projects that will 
have future impacts. For example, a 2007 report on the region's travel 
demand used a sensitivity analysis to assess the effect of low, 
baseline, and high scenarios for its 2025 forecast.[Footnote 92] In 
addition, FAA's Handbook recommends a sensitivity analysis when 
conducting airspace studies and evaluating airspace alternatives. 
Specifically, the Handbook recommends a sensitivity analysis be 
performed "even if assumptions have a strong basis in precedence and 
factual information. Other assumptions are known to be inherently 
uncertain from the beginning because they are based on imperfect or 
incomplete information. This is clearly the case for all future events, 
such as the level and characteristics of the future traffic demand 
since the future cannot be predicted precisely."[Footnote 93] Experts 
interviewed said that given the inherent uncertainty associated with 
projecting future events, when feasible, uncertainty should be 
assessed. Several experts told us that a sensitivity analysis could 
have been used for key factors in the operational analyses.[Footnote 
94] For example, a sensitivity analysis could have been performed on 
aircraft fleet operations at the region's smaller airports to account 
for the growing segment of business jet operations. 

Benefit-Cost Analysis Would Provide Information on Whether Estimated 
Benefits Outweigh Estimated Costs: 

A benefit-cost analysis, which can be used to assess the benefits and 
costs associated with each alternative compared to the status quo, 
would have provided decision makers and the public with more 
comprehensive information on whether the estimated benefits of the 
selected project justified its costs. Benefit-cost analyses are used to 
identify the alternative, if any, that maximizes the net benefits 
(benefits minus costs) relative to the status quo. The alternative that 
maximizes net benefits is economically justified. The analysis also can 
be used to identify how the benefits and costs associated with each 
alternative are distributed across different subpopulations or income 
groups. 

FAA stated that it did not conduct a benefit-cost analysis for the 
airspace redesign because the agency was not required to do so. 
[Footnote 95] GAO believes, based on prior work, that benefit-cost 
analyses can provide valuable information for decision makers and 
should be considered in analyzing transportation investments.[Footnote 
96] While conducting benefit-cost analyses requires an investment in 
time and resources, FAA uses benefit-cost analyses in making other 
investment decisions, such as the Next Generation Air Transportation 
System (NextGen) projects. Moreover, FAA has guidance for conducting 
benefit-cost analyses for airport projects and investment analyses for 
air traffic control procurements.[Footnote 97] FAA requires benefit- 
cost analyses in granting discretionary airport improvement program 
funds and for investment analysis for air traffic control procurements. 
In addition, the Office of Management and Budget requires benefit-cost 
analyses for new regulations. The Air Traffic Organization (ATO), which 
includes the division that develops airspace redesigns, also includes a 
division that is charged with assessing investments for the air traffic 
control system. FAA's Office of Aviation Policy and Plans conducts 
benefit-cost analyses on investment and regulatory decisions and 
discretionary Airport Improvement Program grants.[Footnote 98] 

Furthermore, only after FAA selected the final alternative did it 
assess the economic benefits associated with the selected project. 
Specifically, in describing the benefits of the airspace redesign to 
the public, FAA stated that the selected project would result in 12 
million minute delay savings (see fig. 8 for further discussion) and a 
reduction of up to $285 million[Footnote 99] in annual operating costs, 
when compared to the Future No Action Alternative. These benefits were 
calculated using FAA's economic values for investment decisions, which 
are used in FAA's benefit-cost analyses for investment and regulatory 
decisions.[Footnote 100] However, the dollar amounts for delay savings 
were done only for airline operating costs and not for others such as 
delay savings to passengers. Moreover, because FAA did not estimate 
costs, the information on benefits cannot be used to assess whether the 
selected project is economically justified. 

Figure 8: Description of the 12 Million Minutes Saving in Delay 
Savings: 

[See PDF for image] 

FAA stated in press releases that there will be a projected annual 12 
million minutes in delay savings. We present this description because 
FAA did not include an explanation of the calculation in the documents 
it released to the public. 

* This measure was developed as a means to communicate the delay 
benefits of the redesigned airspace to the public. FAA officials said 
that because this measure only reflects delay, it is not a useful 
measure in evaluating the different alternatives. Furthermore, it was 
developed after FAA made its decision. 

* The 12 million minutes is not a straight multiplier of the average 
minutes delay savings—which FAA estimates to be 3 minutes of arrival 
delay per flight—by the number of operations at the airports. Rather, 
the 12 million minutes was calculated from 4 performance 
metrics—traffic-weighted arrival delay, traffic-weighted departure 
delay, departure airspace delay, and delay savings from flexibility-of 
the 13 metrics used in the operational analysis to compare the 
alternatives. FAA multiplied the daily per flight savings by the number 
of affected flights and then annualized the savings for each of the 
four metrics. The total savings calculated for all four metrics was 
approximately 12 million minutes (see table below). 

* In one press release, FAA stated that the 12 million minutes savings 
were for the four major metropolitan airports—JFK, LaGuardia, Newark, 
and Philadelphia. However, the operational analysis included other 
satellite airports. 

Table: Calculation of 12 Million Minutes Savings: 

Metric: Minutes saved per flight for arrival; 
Minutes saved: 2,948; 
Number of operations: 3,558; 
Annualizing factor: 368; 
Annual savings (minutes/year): 3,860,145. 

Metric: Minutes saved per flight for departures; 
Minutes saved: 4,113; 
Number of operations: 3,566; 
Annualizing factor: 368; 
Annual savings (minutes/year): 5,398,744. 

Metric: Minutes saved per flight for departure airspace delay; 
Minutes saved: 0.49; 
Number of operations: 3,566; 
Annualizing factor: 368; 
Annual savings (minutes/year): 643,021. 

Metric: Minutes saved per flight for routing flexibility; 
Minutes saved: 12.60; 
Number of operations: 3,566; 
Annualizing factor: 36; 
Annual savings (minutes/year): 1,617,538. 

Total minutes saved: 11,519,448. 

[End of table] 

Source: GAO; FAA (table). 

[End of figure] 

FAA's limited economic analysis focused only on select benefits of only 
one alternative--the selected project--and does not account for costs. 
A comprehensive benefit-cost analysis would have increased transparency 
about the range of potential economic impacts of the airspace redesign. 
For example, a benefit-cost analysis that estimated the economic impact 
on passengers, airlines, and residents living near the airports, would 
have allowed a decision maker to assess which alternative, if any, 
would maximize net benefits, and to identify how the benefits and costs 
are distributed among population or income groups. As one expert 
explained, it is difficult to identify from the operational analysis 
the beneficiaries of the system improvements. For example, system 
improvements, such as reducing delay, benefit passengers and airlines, 
but other improvements, such as reduce voice communications and balance 
controller workload, benefit the ATC system. 

Experts we spoke with indicated that a benefit-cost analysis for the 
airspace redesign would have been useful. For example, one expert noted 
that the list of system improvements and metrics in the alternatives 
analysis focused on impacts related to efficiency, while the 
implementation costs were not included. In addition, if the economic 
impacts of noise had been included, costs could have varied by 
alternative. For example, FAA estimated that the Ocean Routing Airspace 
Alternative would result in fewer people impacted by noise compared to 
other alternatives. If the economic effect of noise, approximated by a 
change in home values due to aviation noise, had been taken into 
account, then an alternative like the Ocean Routing Airspace 
Alternative might have performed better than the other alternatives on 
this metric. In addition, the potential economic effect on passengers 
and airlines also would have been assessed in a comprehensive benefit- 
cost analysis. For example, the effect of delay on passengers could 
have been assessed using the value of passenger time lost or gained as 
a result of the airspace redesign. 

Lack of Detailed Implementation Plan Raises Questions about Time Frames 
and Costs: 

Based on the information available to date, we are unable to determine 
whether FAA will meet its projected 5-year implementation time frame, 
what the final project configuration and implementation costs will be, 
and any details regarding FAA's postimplementation evaluation plan. For 
example, FAA has not yet developed a detailed implementation plan that 
includes a schedule of when the new redesigned airspace will be in 
place. Additionally, FAA has not yet determined the type or amount of 
equipment or software that will be needed to implement the project. 

Lack of Detailed Implementation Plan Raises Questions on FAA Meeting 
Its 5-Year Completion Goal: 

FAA is in the process of preparing an implementation plan, and 
therefore, we are unable to determine whether FAA can meet its 
projected 5-year implementation time frame, overcome potential 
obstacles to implementation, and transition from the current airspace 
structure to the redesigned structure. FAA is responsible for ensuring 
that the selected project is implemented in a manner that avoids any 
interruption in air traffic services and minimizes disruptions to air 
traffic. To ensure that new airspace redesign projects are successfully 
implemented, FAA's Handbook lays out specific activities for 
transitioning between the current airspace structure and the redesigned 
airspace. Based on our prior work[Footnote 101] and the experts we 
interviewed, we have identified three specific activities recommended 
in FAA's Handbook and one additional activity emphasized by our experts 
that we believe are important to include in an implementation plan to 
successfully implement the redesigned airspace. 

* Scheduling. FAA's Handbook recommends preparing a schedule that 
identifies the exact time that the new redesigned airspace will be in 
place so that all affected FAA regions and facilities, airports, 
airlines, air traffic controllers, and general aviation pilots can 
prepare for the change. For example, a major component of the 
redesigned airspace is the integration of the airspace, which will 
allow air traffic controllers to use the terminal separation rules over 
a larger geographical area. Although FAA acknowledges that integrating 
the airspace will require new procedures and potentially reallocation 
of staff, there is no detailed information on when these procedures 
will be implemented, how ATC staff may be reallocated, and what type of 
air traffic controller training will be required. Without this 
information, it is difficult for the agency to clearly track and report 
progress, as well as to ensure timely implementation. In our prior 
work,[Footnote 102] we have highlighted the importance of developing an 
implementation timeline to build momentum and show progress from day 
one. For example, to help federal agencies implement successful 
transformation of their cultures in a transparent and accountable 
manner, a key implementation step is to make implementation goals and 
timelines public. 

* Risk mitigation. According to the Handbook, as part of its 
implementation plan, FAA should identify potential risks and develop a 
risk mitigation plan to minimize the impact if the risk does occur. 
FAA, however, has not developed risk mitigation strategies to deal with 
potential challenges that may arise during the redesign's 
implementation. Without details on proposed risk mitigation, it is 
unclear whether FAA has taken steps to identify possible risk factors. 
FAA officials noted that there are a number of separate FAA projects 
and initiatives that, while not directly linked to the airspace 
redesign project, will influence how FAA implements the airspace 
redesign. For example, FAA has not decided whether it will house the 
new common automation platform in existing facilities, a new facility, 
or a consolidated facility. In some of our prior work,[Footnote 103] we 
have recommended that agencies should develop a risk analysis to show 
the potential impacts if task and milestones are not achieved, develop 
methods to accurately evaluate and measure the progress of 
implementation, and develop contingency plans should task and 
milestones not be met. FAA does not have such plans in place for 
implementing the redesign. Furthermore, if there is no consideration of 
risk mitigation, FAA may be unable to minimize potential risks. 

* Transition planning. The Handbook also recommends that FAA identify 
the steps that need to be taken to transition between the current 
airspace to the redesigned airspace in a transition plan that includes 
key decision points along the way. Transitional plans provide details 
on the activities and time schedules for the transition from the 
current airspace to the redesigned airspace. The purpose of these plans 
includes ensuring that services associated with the airspace and 
airports continue throughout implementation and that the multiple users 
of the airspace--such as pilots, FAA personnel, and air traffic 
controllers--are aware of the ongoing changes. Given this redesign's 
high level of complexity and multiple implementation stages, 
transitional planning could be beneficial to FAA's implementation. 
However, FAA has not developed a transitional plan for the redesign's 
implementation. We have highlighted in a prior GAO report[Footnote 104] 
that FAA should include proper transition planning when implementing 
highly technical and complex projects that involve numerous 
stakeholders, such as NextGen. For example, in February 2008, we 
testified that FAA faces a number of management challenges--such as 
better aligning costs with revenue--in its transition to NextGen. 
[Footnote 105] 

* Monitoring. It is important for FAA to monitor the implementation 
throughout the transition process to ensure that FAA is actually 
implementing the changes in the airspace that were identified in the 
selected project. We have reported in prior GAO work[Footnote 106] that 
monitoring efforts can help agencies transition to new systems. For 
example, as FAA transitions to NextGen, we believe it will be critical 
for FAA to monitor and address equipment outages to ensure the safety 
and efficiency of the current ATC system. In addition, experts we spoke 
with also believe that monitoring is an important step for implementing 
the airspace. For example, one expert interviewed by GAO stated that 
FAA should get a current baseline of information on the airspace, and 
continue to monitor and evaluate throughout implementation. Another 
expert interviewed by GAO also stated that both operational and noise 
impacts should be assessed (as part of monitoring and evaluation) to 
further enhance management of the implementation. Although FAA has 
already begun implementing the redesign, it is unclear how the agency 
will monitor and evaluate the process since there is no monitoring plan 
in place. Periodic monitoring and evaluation will both ensure that FAA 
is complying with the operational and environmental objectives outlined 
in the selected project, as well as increase the project's 
accountability and transparency. 

Final Project Configuration and Costs Are Unknown: 

FAA has not determined the final project configuration and costs. Based 
on our prior work,[Footnote 107] it is critical for an agency to have a 
full understanding of project costs to ensure that implementation is 
successful. For example, by understanding project costs, agencies can 
ensure they have the required resources. However, FAA has not yet 
determined the costs due, in part, to two reasons. First, although FAA 
officials have stated that they will be using currently available 
technology and software, FAA has not determined the type or amount of 
equipment and software that will be needed to implement the common 
automation platform for the ICC. Second, it is still unclear whether 
the ICC will be housed in existing FAA facilities, a new facility, or 
in a consolidated facility. Under FAA's Facility Replacement Program, 
FAA is reviewing whether to build a new TRACON facility for the New 
York region. However, FAA officials estimated that the final decision 
as to whether to approve the design and construction of a new TRACON 
will be made sometime in September 2008, but it will not include costs 
estimates. Cost estimates will require FAA to make specific decisions 
on the location of the TRACON, the size of the facility, and any 
supporting infrastructure requirements. If FAA approves the 
construction of a new TRACON, the final cost estimate for this new 
facility will not be available until September 2011 when the contract 
is to be awarded, and the new facility is not projected to be completed 
until September 2015--3 years after FAA has estimated full 
implementation of the selected project. 

An Adaptive Management Strategy May Help FAA Successfully Evaluate the 
Implementation of the Redesign: 

Although the redesign's implementation is planned to take multiple 
years, FAA's Handbook offers few actions and steps for the agency to 
use for a postimplementation evaluation of the redesign. Given that the 
redesign represents a complex and comprehensive change to the region's 
airspace, it is important for FAA to determine how it plans to conduct 
evaluations of the redesign. One potential strategy is adaptive 
management. As defined by the National Research Council, adaptive 
management is a process that promotes flexible decision making in the 
face of uncertainties, as outcomes from management actions and other 
events become understood. Adaptive management is recognized by CEQ and 
other federal agencies as a valuable strategy.[Footnote 108] For 
example, in 2007, CEQ issued a guide[Footnote 109] that recognizes the 
value of adaptive management when there are uncertainties in the 
prediction of the impacts or outcome of project implementation. GAO 
also has recommended adaptive management, and practices like it, as a 
strategy for other federal agencies. For example, we recommended that 
the U.S. Department of Agriculture adopt a systematic application of 
adaptive management principles and develop a monitoring program for 
Yellowstone's bison[Footnote 110] to improve its overall management of 
the program. Adaptive management elements that FAA could use include 
implementing a monitoring program to systematically obtain information 
about the management objectives identified in the selected project and 
communicating and engaging the results with key stakeholders. This 
approach also would emphasize FAA's accountability and transparency to 
its stakeholders. In addition, a 2004 FAA paper describes elements for 
using adaptive management.[Footnote 111] One expert interviewed by GAO 
stated that a benefit of using an adaptive management strategy as a 
review tool, both to assess operational and environmental impacts, is 
the effect it could have on the design and development of future 
airspace redesigns. 

Conclusions: 

When conducting its airspace redesign, FAA complied with legal 
requirements under NEPA and environmental justice directives for the 
identified five key issues. In addition, FAA's methodology to assess 
operational and noise impacts was reasonable. Nonetheless, we found 
that FAA's methodology contained some limitations that if addressed in 
future efforts, could improve FAA's decision making and the public's 
understanding of FAA's decision and process. In particular, FAA could 
undertake two types of analyses--uncertainty analyses and benefit-cost 
analyses--in future airspace redesigns to help avoid limitations 
similar to those identified during our evaluation. An uncertainty 
analyses would provide decision makers and the public information on 
the extent to which estimated impacts may vary under alternative 
assumptions. As highlighted in our study, the realization of the 
redesign's operational benefits are dependent on the accuracy of key 
assumptions--particularly the aviation demand forecast. FAA has already 
established through a comparative analysis that the traffic counts for 
the 2006 forecast are higher than the 2005 observed levels; thus, while 
an uncertainty analysis might not have resulted in a change in the 
relative ranking of the alternatives, our confidence that the level of 
estimated benefits will be realized is reduced. A benefit-cost 
analysis, although not required, could provide more comprehensive 
information for FAA to assess whether the estimated benefits associated 
with redesigning airspace justify the costs. More information on the 
trade-offs would also increase transparency in FAA's decision for the 
public, thus, in turn, likely making the decision more understandable. 
Although a benefit-cost analysis would require an investment in time 
and resources, FAA conducts these types of analyses for other 
investment decisions, such as ATC procurements and new regulations, and 
has specific guidance for them. In addition, economists have used 
methods to estimate the economic impact of changes in noise, and 
supplemental noise metrics, which provide different information about 
noise impacts not captured by DNL, are recognized as appropriate 
methods for analyzing physical impacts. 

Our study also raises concerns about FAA's future actions for this 
airspace redesign. Despite implementing the initial steps of the 
redesigned airspace last December, FAA has not published a detailed 
implementation plan. The lack of such a plan raises concerns that FAA 
may not meet its estimated implementation time frame, be able to deal 
with potential obstacles, or be able to transition from the current 
airspace structure to the redesigned structure. Furthermore, it is 
important for FAA to determine how it plans to evaluate the 
implementation, which would help FAA ensure that the operational and 
environmental objectives are met and increase the project's 
transparency and accountability. One strategy used by other federal 
agencies for evaluating a project's implementation is the adaptive 
management strategy. Adaptive management is a strategy that recognizes 
the need for flexibility and would allow for modification of the 
redesigned airspace if the results of future research indicate a need 
for change, as long as these changes do not significantly affect the 
quality of the human environment. This strategy would include 
implementing a monitoring program to collect information and 
communicating and engaging with key stakeholders. 

Recommendations for Executive Action: 

To improve FAA's effectiveness and accountability in implementing the 
New York/New Jersey/Philadelphia Airspace Redesign, we recommend that 
the Secretary of the Department of Transportation direct the Acting 
Administrator of the Federal Aviation Administration to take the 
following two actions for the New York/New Jersey/Philadelphia Airspace 
Redesign: 

* Develop and follow a detailed implementation plan that includes a 
time and cost schedule, risk mitigation plan, transition planning, and 
monitoring and evaluation plan. 

* Follow a postimplementation evaluation plan that includes an adaptive 
management strategy for monitoring implementation of the redesign and 
communicating the results to key stakeholders. 

To improve FAA's effectiveness in conducting future airspace redesigns, 
we recommend that the Secretary of the Department of Transportation 
direct the Acting Administrator of the Federal Aviation Administration 
to take the following actions in developing and implementing future 
airspace redesigns: 

* Conduct an uncertainty analysis of key assumptions and inputs-- 
particularly on elements within aviation demand forecasts. The analysis 
should be used to assess the extent to which the estimated impacts for 
the airspace redesign alternatives would change using different values 
for key assumptions and inputs and to provide information on the level 
of confidence in the project's estimated impacts and the relative 
ranking of the alternatives. 

* Conduct a benefit-cost analysis for the purpose of assessing the 
economic effect of alternatives for airspace redesigns (including the 
status quo). Such an analysis should include an assessment of the key 
impacts associated with redesigning the airspace, including 
implementation costs and, as appropriate, the economic effect 
associated with noise. 

Agency Comments: 

We provided a draft of this report to the Department of Transportation 
for its review and comment. In commenting on a draft of this report, 
DOT stated that it was pleased to see that the GAO review concluded the 
actions taken by FAA with regard to NEPA were reasonable. DOT also 
noted that while it did not necessarily agree with everything in the 
draft report, it is constrained from offering a detailed analysis of 
the draft report at this time, as the matters the report covers are the 
subject of pending litigation. DOT also provided technical comments 
that we incorporated as appropriate. 

As agreed with your office, unless you publicly announce the contents 
of this report earlier, we plan no distribution until 30 days from the 
report date. At that time, we will send copies of this report to 
interested congressional committees, the Secretary of Transportation, 
and other interested parties. We also will make copies available to 
others upon request. In addition, the report will be available at no 
charge on the GAO Web site at [hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions about this report, please 
contact Susan Fleming at (202) 512-2834 or flemings@gao.gov or Susan 
Sawtelle at (202) 512-6417 or sawtelles@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Individuals making key contributions to 
this report are listed in appendix VI. 

Signed by: 

Susan A. Fleming: 
Director, Physical Infrastructure Issues: 

Signed by: 

Susan D. Sawtelle: 
Managing Associate General Counsel: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

In assessing the Federal Aviation Administration's (FAA) airspace 
redesign of the New York/New Jersey/Philadelphia region, the report 
addresses the following questions: (1) To what extent did FAA follow 
applicable key legal procedures and requirements in conducting its 
environmental review? (2) To what extent was the methodology used by 
FAA to assess the operational and noise impacts reasonable? (3) What is 
the likelihood that FAA will meet its project time frames and costs of 
implementing its airspace redesign project? 

To address our three research questions, we reviewed documents 
associated with the New York/New Jersey/Philadelphia Airspace Redesign, 
including the draft and final environmental impact statements (EIS) and 
selected appendices, underlying technical reports and analyses, and the 
Administrative Record filed by FAA with the court in the pending 
litigation. We also obtained and analyzed information from a variety of 
other sources, including federal laws, regulations, executive 
directives, and court decisions; FAA and the Department of 
Transportation (DOT) Orders and FAA and Council on Environmental 
Quality (CEQ) guidance; the final EISs for three previous FAA-sponsored 
airspace redesigns determined to be similar to this project;[Footnote 
112] prior GAO work; and other aviation evaluations and studies. We 
interviewed officials from DOT, the Environmental Protection Agency, 
the Port Authority of New York and New Jersey, City of Philadelphia 
Department of Aviation, and FAA's headquarters and eastern regional 
offices, including representatives of FAA's airspace redesign team and 
its principal contractors for the operational and environmental 
analyses. We also contacted other stakeholders, including a trade 
organization for the aviation industry, the national air traffic 
controller's union, and local governments and community groups in the 
region. 

To assess the extent to which FAA followed key legal procedures and 
requirements, we reviewed applicable federal laws, regulations, 
executive directives, and court decisions, as well as FAA and DOT 
Orders and FAA and CEQ guidance, to establish criteria by which to 
compare FAA's actions. We then conducted a legal analysis to determine 
whether FAA complied with five key issues for the airspace redesign to 
include the statement of the project's purpose and need, evaluation of 
alternatives, consideration of the project's environmental effects, 
public involvement, and environmental justice matters. We selected 
these five issues based on public concerns raised during and after the 
EIS process, congressional interest, the views of experts we 
interviewed, and GAO's evaluation of the range of concerns presented. 
To examine the extent to which the methodology used by FAA to assess 
the operational and noise impacts was reasonable, we reviewed FAA's 
methodology for conducting the operational and noise analyses. We 
compared FAA's methodology to criteria we established through our 
review of federal policy, FAA guidance, prior GAO reports, and 
standards from the aviation and analytical community, including 
generally accepted economic principles and practices, and statistical 
principles. 

In addition, with the assistance of the National Academy of Sciences, 
we identified 11 experts in the fields of EIS policies and procedures, 
airspace operations and system modeling, and aircraft noise measurement 
and mitigation. These experts reviewed selected portions of the EIS 
related to FAA's operational and noise analysis. We interviewed these 
experts within their area of expertise to obtain their views on the 
extent to which the FAA followed applicable procedures and 
requirements, and on the methodology used by FAA to assess the 
operational and noise impacts. (Table 2 identifies the list of 
participating experts.) 

Table 2: List Of Experts Providing Input During Our Review: 

Expert: Hamsa Balakrishnan, Assistant Professor of Aeronautics and 
Astronautics, Massachusetts Institute of Technology; 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: Mike Ball, Orkand Corporation Professor of Management Science, 
Decision and Information Technologies Department, University of 
Maryland; 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: William Dunlay, Director, Jacobs Consultancy; 
Area(s) of expertise: EIS policies and procedures. 

Expert: Charles Etter, Staff Scientist, Gulfstream Aerospace Company; 
Area(s) of expertise: Aircraft noise measurement and mitigation. 

Expert: Bill Jeffers, Senior Director, ARINC, Inc. (retired); 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: Margaret Jenny, Chief Executive Officer, MJF Strategies, LLC; 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: Vincent Mestre, Principal, Mestre Greve Associates, Inc.; 
Area(s) of expertise: Aircraft noise measurement and mitigation. 

Expert: Clint Oster, Professor, School of Public and Environmental 
Affairs, Indiana University; 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: Neil Planzer, Vice President of Air Traffic Management 
Strategy, The Boeing Company; 
Area(s) of expertise: Airspace operations and system modeling. 

Expert: John Putnam, Partner, Kaplan Kirsch & Rockwell; 
Area(s) of expertise: EIS policies and procedures. 

Expert: Ian Waitz, Jerome C. Hunsaker Professor of Aeronautics and 
Astronautics, Massachusetts Institute of Technology; 
Area(s) of expertise: Aircraft noise measurement and mitigation. 

Source: GAO. 

[End of table] 

To determine the likelihood that FAA will meet its project time frames 
and costs of FAA's airspace redesign, we reviewed documents associated 
with the redesign's impacts, time frames, and direct costs, and met 
with FAA to discuss plans for project implementation. We also reviewed 
prior GAO work related to environmental reviews and project 
implementation. 

As agreed with you, we did not conduct a new EIS, or develop and 
analyze new alternatives to the airspace redesign. We conducted this 
performance audit from July 2007 to July 2008 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

[End of section] 

Appendix II: FAA's Legal Compliance with Key NEPA Requirements and 
Environmental Justice Directives: 

Introduction and Summary of Conclusions: 

As part of GAO's review of the FAA's airspace redesign for the New 
York/New Jersey/Philadelphia region, we examined FAA's legal compliance 
with certain requirements of the National Environmental Policy Act 
(NEPA), 42 U.S.C. §§ 4321 et seq., and with the environmental justice 
directives of Executive Order 12898, "Federal Actions to Address 
Environmental Justice in Minority Populations and Low-Income 
Populations," 59 Fed. Reg. 7629 (Feb. 16, 1994). Specifically, based on 
public concerns raised during and after the EIS process,[Footnote 113] 
congressional interest, the views of experts we interviewed, and GAO's 
evaluation of the range of concerns presented, we reviewed FAA's 
compliance with respect to five issues: 

* whether FAA's purpose and need statement in its EIS for the airspace 
redesign was reasonable; 

* whether FAA developed a reasonable range of alternatives to the 
redesign and rigorously explored those alternatives in the EIS; 

* whether FAA reasonably decided not to analyze environmental effects 
of a potential increase in growth resulting from the redesign; 

* whether FAA reasonably involved the public in its environmental 
review process; and: 

* whether FAA appropriately considered environmental justice issues in 
its environmental review process. 

Based on the information available to us and for the reasons discussed 
below, we conclude that FAA met NEPA and Executive Order 12898 
requirements in conducting the airspace redesign with respect to these 
issues.[Footnote 114] 

Background: 

As discussed in greater detail in this report, in 1998, FAA launched a 
comprehensive national airspace redesign effort to more efficiently and 
safely move aircraft through the nation's airspace system. As a part of 
this program, FAA initiated the New York/New Jersey/Philadelphia 
airspace redesign in 1999. For a federal project of this magnitude, FAA 
must comply with NEPA and implementing regulations issued by CEQ, as 
well as FAA's own NEPA Orders and guidance.[Footnote 115] FAA also must 
follow environmental justice directives set forth in Executive Order 
12898. After determining that NEPA required an EIS for the project, FAA 
issued a draft EIS in December 2005. Following public hearings and a 
public comment period, FAA issued a final EIS in July 2007 and, based 
on the final EIS, issued a Record of Decision in September 2007, 
designating one of its redesign alternatives as the selected project. 
FAA has begun implementing this project and anticipates that it will 
take 5 years to complete implementation. Among other things, an EIS 
must: (1) address the purpose of and need for the proposed action; 
[Footnote 116] (2) identify alternatives to the proposed action; 
[Footnote 117] and (3) present the reasonably foreseeable environmental 
impacts of the proposed action, including the direct and indirect 
effects and cumulative impacts.[Footnote 118] Furthermore, throughout 
the environmental review process, an agency must make diligent efforts 
to involve the public[Footnote 119] and, to the greatest extent 
practicable and as appropriate, must identify and address any 
disproportionately high and adverse human health or environmental 
effects of its activities on minority and low-income 
populations.[Footnote 120] We address FAA's compliance with each of 
these requirements in turn. 

Issues and Analysis: 

1. Was FAA's purpose and need statement reasonable? 

As discussed below, FAA's statement of the purpose and need for the 
airspace redesign was reasonable and therefore complied with NEPA 
requirements. It satisfied the statutory and regulatory requirements as 
they have been applied by the courts--the statement was not too 
narrowly or broadly defined--and it reasonably excluded noise reduction 
as a purpose. 

NEPA Requirements: 

CEQ regulations implementing NEPA require an agency to include in the 
EIS a statement specifying the purpose of and need for the project-- 
commonly referred to as a "purpose and need statement." In particular, 
40 C.F.R. § 1502.13 requires that the agency include a statement to 
"briefly specify the underlying purpose and need to which the agency is 
responding in proposing the alternatives including the proposed 
action." Further, FAA Order 1050.1E, section 506(d) requires the 
purpose and need statement to "present the problem being addressed ... 
and essentially provide the parameters for defining a reasonable range 
of alternatives to be considered." As the courts have explained, an 
agency "bears the responsibility for defining at the outset the 
objectives of an action." Citizens Against Burlington, Inc. v. Busey, 
938 F.2d 190, 195-96 (D.C. Cir. 1991), cert. denied, 502 U.S. 994 
(1991). The scope of the project, as articulated by the agency, informs 
the alternatives it considers and guides its decision-making process. 
In determining whether an agency has complied with NEPA, courts grant 
substantial deference to an agency's actions as required by the 
Administrative Procedure Act.[Footnote 121] With respect to the purpose 
and need statement in particular, courts generally apply a "rule of 
reason" and uphold the statement as long as it is reasonable. City of 
Alexandria v. Slater, 198 F.3d 862, 867 (D.C. Cir. 1999), cert. denied, 
531 U.S. 820 (2000). The agency can neither define a project's purpose 
and need so narrowly that there is only one logical alternative to 
accomplish it, nor so broadly that an infinite number of alternatives 
would accomplish its goals. Citizens Against Burlington, 938 F.2d at 
196 (upholding FAA approval of airport expansion). An agency complies 
with NEPA if it meets these procedural requirements. 

FAA Actions: 

FAA initiated a redesign of the New York/New Jersey/Philadelphia 
region's airspace as a first step in its national airspace redesign 
effort to accommodate air traffic growth while maintaining safety and 
mitigating delays, and to accommodate changes in the types of aircraft 
using the airspace system. FAA's basic objective was to create a system 
to better manage traffic and capacity in the region, and to replace the 
air traffic system designed in the 1960s. FAA noted that while the 
volume of traffic and the type of aircraft used have changed 
considerably since that time, the basic structure of the airspace has 
stayed the same, and emerging technologies have not been taken into 
account. 

To increase the efficiency and reliability of the airspace structure 
and air traffic control (ATC) system in the New York/New Jersey/ 
Philadelphia region, FAA began by identifying a formal purpose and need 
for the airspace redesign. To do this, MITRE's Center for Advanced 
Aviation System Development (CAASD)--a Federally Funded Research and 
Development Center sponsored by FAA--identified problems and 
performance shortfalls. In a parallel effort, FAA developed focused 
leadership teams, composed of experts from throughout the United 
States, who began a systematic effort to identify airspace 
inefficiencies and solutions to ensure national integration of local 
efforts.[Footnote 122] Based on these efforts, FAA developed the 
following purpose and need statement: 

"The purpose of the airspace redesign is to increase the efficiency and 
reliability of the airspace structure and ATC system. The need is to 
accommodate growth in aircraft operations while maintaining safety, 
mitigating delays, and accommodating changes in the types of aircraft 
using the System."[Footnote 123] 

FAA has identified these same objectives--increased efficiency and 
safety--for several of its previous airspace redesign projects, such as 
the Potomac Consolidated Terminal Radar Approach Control (TRACON) 
[Footnote 124] in the Washington/Baltimore area and the Chicago 
Terminal Airspace Project. FAA's purpose and need statement for the New 
York/New Jersey/Philadelphia airspace redesign established the overall 
criteria against which different alternatives were examined (see 
section 2 below). Notably, FAA did not include noise reduction as part 
of the project's formal purpose and need. As FAA explained in the final 
EIS: "Noise reduction is not a component of the purpose and need for 
the proposed action. Reduction of noise is not appropriately identified 
as a purpose because it is not FAA policy to reroute aircraft to reduce 
noise levels in one community at the expense of another."[Footnote 125] 
Rather, according to FAA, the "first consideration and highest priority 
in defining the Purpose and Need for any proposed action is to serve 
the public interest by exercising its authority to assign, maintain, 
and enhance safety and security of the national airspace (per 49 U.S.C. 
§ 40101(d))."[Footnote 126] This is consistent with FAA's statement of 
its mission: to provide the safest, most efficient aerospace system in 
the world.[Footnote 127] 

Nonetheless, there was considerable public controversy regarding the 
potential noise effects of FAA's redesign and, as the project 
progressed, congressional committees urged FAA to consider noise 
impacts and mitigation where appropriate.[Footnote 128] FAA took 
several such actions, beginning with a commitment in its early scoping 
meetings to reduce noise where possible--for instance, by increasing 
altitudes, dispersing or concentrating routes where appropriate, 
reducing fly time, and routing aircraft over less noise-sensitive 
areas.[Footnote 129] Additionally, FAA included a detailed analysis of 
noise impacts for each alternative considered in detail[Footnote 130] 
and included one alternative--the Ocean Routing Alternative--that would 
have reduced noise overall. Finally, FAA included proposed mitigation 
measures along with its preferred alternative, and issued a separate 62-
page noise mitigation report.[Footnote 131] As FAA noted in the final 
EIS, however, the airspace redesign was not a cure-all for aircraft-
related noise problems in the region.[Footnote 132] 

Analysis: 

FAA's purpose and need statement for the airspace redesign complied 
with NEPA requirements. FAA's statement defined the parameters of the 
project, as required by 40 C.F.R. §1502.13. It also satisfied the 
requirements courts have developed in evaluating agency statements of 
purpose and need. FAA did not define the project's purpose so broadly 
that it generated an infinite number of alternatives, as demonstrated 
by its exclusion of such options as airport infrastructure 
modification, congestion management measures, and alternate modes of 
transportation[Footnote 133] (see section 2 below). Nor did FAA define 
the purpose so narrowly that only one alternative would be 
satisfactory, as evidenced by the fact that it could be met by multiple 
alternatives (see section 2). While FAA ultimately selected a single 
alternative that best met the project's purpose and need, more than one 
alternative would have done so. 

FAA also acted reasonably in excluding noise reduction as part of the 
project's formal purpose and need statement. As noted, in analyzing the 
environmental impacts of the proposed redesign, FAA gave substantial 
consideration to possible noise effects. It was nevertheless reasonable 
to exclude noise reduction as a formal objective of the redesign, 
because NEPA "does not require agencies to elevate environmental 
concerns over other appropriate considerations." Baltimore Gas & 
Electric Co. v. NRDC, 462 U.S. 87, 97 (1983); see also Strycker's Bay, 
above, 444 U.S. at 227. Rather, through NEPA's requirement that 
agencies prepare an EIS for all major federal actions significantly 
affecting the environment, the statute requires only that agencies 
consider the environmental impacts of their actions as part of their 
decision making, not that they use environmental impacts as the 
deciding factor. Kleppe v. Sierra Club, above, 427 U.S. at 409. 

Courts have approved other purpose and need statements that excluded 
environmental concerns. In City of Alexandria v. Slater, above, for 
example, the D.C. Circuit evaluated the purpose and need statement 
prepared by the Federal Highway Administration (FHWA) for the planned 
replacement of the Woodrow Wilson Bridge in the Washington, D.C., area. 
The agency's statement focused primarily on traffic and safety 
concerns, rather than on environmental concerns such as noise. In 
finding the agency's purpose and need statement to be reasonable, the 
court stated that "[t]he proper question to ask at the outset of a NEPA 
inquiry is not whether the [FHWA] focused on environmental goals but 
rather ...whether its stated objectives were reasonable. It seems 
rather obvious to us that it is not unreasonable in articulating its 
objectives for an agency to 'focus primarily on transportation and 
safety issues' when replacing a massively congested and structurally 
unsound bridge." 198 F.3d at 867-68. Similarly, in Citizens Against 
Burlington, above, the D.C. Circuit approved FAA's EIS for a major 
airport expansion that would cause significant noise impacts, even 
though FAA's stated purpose and need focused only on creating a new 
cargo hub, and did not mention noise mitigation. 

By contrast, in California v. DOT, 260 F. Supp. 2d 969 (N.D. Cal. 
2003), the court rejected FAA's purpose and need statement in its 
environmental assessment of a major airport expansion, because it was 
so narrow that it effectively eliminated consideration of any 
significant environmental effects. While FAA stated that the purpose of 
the expansion was simply to "provide the necessary runway length to 
safely allow [larger aircraft] ...to operate at the Airport," and the 
court agreed that such a narrow purpose might result in no significant 
environmental impacts, in fact, the record showed the project's very 
purpose was to induce growth by attracting thousands of additional 
tourists to a local ski resort. The court therefore rejected FAA's 
"myopic view of the airport project" and, based on this and other 
reasons, required a full EIS to be prepared. Id. at 974. 

As in City of Alexandria and Citizens Against Burlington, the issue 
with respect to the New York/New Jersey/Philadelphia Airspace Redesign 
is not whether FAA included environmental concerns in its purpose and 
need statement, but whether the agency's purpose and need statement was 
reasonable. As discussed above, we conclude it was, because it 
identified the problem being addressed and thus essentially provided 
the parameters for defining a reasonable range of alternatives to be 
considered, as the regulations and FAA's Orders require.[Footnote 134] 
This is not a case like California v. DOT, where the facts belie the 
agency's stated purpose. 

Finally, the congressional committee reports directing FAA to consider 
or mitigate the project's noise impacts[Footnote 135] did not create a 
legal requirement to include noise reduction or mitigation as part of 
the project's formal purpose and need. The D.C. Circuit noted in 
Citizens Against Burlington, above, that in formulating a statement of 
purpose and need, agencies "should always consider the views of 
Congress, expressed, to the extent that the agency can determine them, 
in the agency's statutory authorization to act, as well as in other 
congressional directives." 938 F.2d at 196. FAA did consider the "views 
of Congress" in developing the project's purpose and need--it complied 
with the mandate in 49 U.S.C. § 40101(d) to give the highest priority 
to enhancing the safety and efficiency of the national airspace. FAA 
also considered the congressional report statement directing FAA to 
address noise issues it its New York/New Jersey/Philadelphia Airspace 
Redesign, by conducting detailed technical noise analyses and including 
noise mitigation measures for the selected project. These report 
directives did not, however, legally bind FAA to include noise 
mitigation as a purpose of the redesign because they were not 
contained, or incorporated by reference, in enacted legislation. See 
generally Cherokee Nation of Oklahoma v. Leavitt, 543 U.S. 631, 646 
(2005); Lincoln v. Vigil, 508 U.S. 182, 192 (1993); GAO, Consolidated 
Appropriations Act, 2008--Incorporation by Reference, B-316010 (Feb. 
25, 2008). 

4. Did FAA develop a reasonable range of alternatives to the proposed 
redesign and rigorously explore those alternatives in the EIS? 

As discussed below, FAA developed a reasonable range of alternatives 
and rigorously explored those alternatives, as required by NEPA. The 
agency included a no action alternative and reasonable alternatives 
outside the agency's current legal jurisdiction, and discussed 
categories of alternatives it ultimately eliminated from more detailed 
analysis. In addition, the alternatives were responsive to the agency's 
purpose and need and were reasonably developed, rigorously explored, 
and objectively evaluated, supporting a fully informed and well- 
considered decision. 

NEPA Requirements: 

NEPA section 102(2)(C)(iii) requires an EIS to include alternatives to 
the proposed action. 42 U.S.C. § 4332(2)(C)(iii). In implementing this 
requirement, CEQ regulations mandate, among other things, that agencies 
shall: "(a) Rigorously explore and objectively evaluate all reasonable 
alternatives ...; (b) Devote substantial treatment to each alternative 
considered in detail including the proposed action ...; (c) Include 
reasonable alternatives not within the jurisdiction of the lead agency; 
and (d) Include the no action alternative." 40 C.F.R. § 1502.14. In 
addition, FAA's NEPA Orders recognize that analysis of alternatives: 

"...is the heart of the EIS. It presents a comparative analysis of the 
no action alternative, the proposed action, and other reasonable 
alternatives to fulfill the purpose and need of the action.... 
Reasonable alternatives not within the jurisdiction of the lead agency 
should be considered. The FAA may include alternatives proposed by the 
public or other agencies. However, they must meet the basic criteria 
for any alternative: it must be reasonable, feasible, and achieve the 
project's purpose...." 

FAA Order 1050.1E, Section 506e. Again, courts grant substantial 
deference to agency actions and apply a "rule of reason" when 
evaluating an agency's range of alternatives. Vermont Yankee Nuclear 
Power Corp. v. NRDC, 435 U.S. 519 (1978); NRDC v. Morton, 458 F.2d 827 
(D.C. Cir. 1972). NEPA requires only that the agency weigh all 
reasonable alternatives and come to a "fully informed" and "well- 
considered" decision. North Slope Borough v. Andrus, 642 F.2d 589, 599 
(D.C. Cir. 1980). See also Vermont Yankee, 435 U.S. at 558; NRDC v. 
Hodel, 865 F.2d 288, 294 (D.C. Cir. 1988). "This 'rule of reason 
governs both "which alternatives the agency must discuss, and the 
extent to which it must discuss them."'" City of Grapevine, 17 F.3d at 
1506 (citation omitted) (emphasis in original). 

A project's purpose and need statement guides the appropriate range of 
alternatives to be considered by an agency. In turn, the chosen range 
of alternatives must achieve the proposed action's purpose and need, 
and the preferred alternative must be the one that best satisfies those 
parameters. See Citizens Against Burlington, above. It is the agency 
itself that must determine the alternatives to be considered and how 
extensive the treatment of those alternatives should be. Vermont 
Yankee, 435 U.S. at 558. Although the choice of alternatives is a 
matter of agency discretion, the alternatives must be "bounded by some 
notion of feasibility." Id. at 551. A court must uphold an agency's 
decision so long as "the alternatives are reasonable and the agency 
discusses them in reasonable detail." Citizens Against Burlington, 938 
F.2d at 196. 

FAA Actions: 

FAA began its identification of alternatives by considering five 
categories of potential alternatives: (1) alternate modes of 
transportation and communication; (2) changes in airport use, including 
additional infrastructure; (3) congestion management measures; (4) 
improved air traffic control technology; and (5) airspace redesign. 
[Footnote 136] Of these five categories, only the airspace redesign 
category met FAA's purpose and need, and the agency therefore 
eliminated the other categories from further consideration.[Footnote 
137] FAA then formed the Airspace Redesign Team working group, charged 
with designing and evaluating conceptual airspace redesign 
alternatives. The Airspace Redesign Team was composed of 
representatives from each of the affected FAA ATC facilities (New York 
TRACON, Philadelphia TRACON, New York Center, Washington Center and 
Boston Center), as well as representatives from ATC facilities outside 
the study area. In addition to internal coordination among working 
group representatives, FAA solicited and considered input from 
airlines, airport operators, and other air transportation stakeholders. 
[Footnote 138] Recommendations also were received from RTCA, Inc., a 
nonprofit corporation that functions as a Federal Advisory Committee 
and develops industry consensus regarding air traffic management 
issues.[Footnote 139] The Airspace Redesign Team explored four broad 
airspace redesign concepts--Four Corner-Post, Modifications to Existing 
Routing, Ocean Routing, and Clean Sheet--that met a series of nine 
objectives.[Footnote 140] Four basic airspace redesign alternatives 
were then developed for detailed consideration, ranging from the Future 
No Action Airspace Alternative (maintaining the status quo) to the 
Integrated Airspace Alternative Variation with Integrated Control 
Complex (creating a more fully integrated airspace). These alternatives 
met the purpose and need, reflected public concern about the airspace 
redesign, or were required by NEPA.[Footnote 141] In the final EIS, FAA 
recommended the Integrated Airspace Alternative Variation with 
Integrated Control Complex (ICC) as the preferred alternative, and in 
its September 2007 Record of Decision, named this alternative, together 
with noise mitigation measures, as the selected project.[Footnote 142] 

FAA conducted detailed analyses of each of the four basic alternatives. 
The primary evaluative tool used was the Total Airspace and Airport 
Modeler (TAAM), a fast-time simulation tool that can model ground, 
terminal, and en-route airspace environments. Under FAA's instruction, 
MITRE's CAASD used TAAM to simulate all of the alternatives and measure 
their operational impacts. The area's eight airports likely to be most 
affected by the airspace redesign were included in the model in detail. 
In addition, for each alternative, FAA conducted an analysis of the 
noise impacts resulting from redesign-related changes in air 
operations. 

FAA used a specific set of criteria to evaluate and compare each 
alternative, both quantitatively and qualitatively. Alternatives were 
evaluated based on two types of criteria--operational viability and 
operational efficiency--to determine how well each alternative met the 
purpose and need.[Footnote 143] In its evaluation of each alternative, 
FAA summarized the changes that would occur at specific airports under 
each alternative, and then evaluated and compared each alternative 
using the criteria. An analysis of the noise impacts also was conducted 
for each alternative.[Footnote 144] 

Analysis: 

FAA's range of alternatives complied with NEPA because: (a) FAA 
included a no action alternative and reasonable alternatives outside 
the agency's jurisdiction and discussed the categories of potential 
alternatives eliminated from detailed analysis; (b) the alternatives 
were responsive to the agency's purpose and need; and (c) the 
alternatives were reasonably developed, rigorously explored, and 
objectively evaluated, which supported a fully informed and well- 
considered decision. 

As noted, FAA considered four basic alternatives in detail, including a 
"no action" alternative as required by CEQ regulations.[Footnote 145] 
Additionally, FAA considered, although eventually eliminated from 
detailed analysis, categories of alternatives outside the agency's 
jurisdiction, for instance, use of satellite airports and improvements 
to airport infrastructure, also as required by CEQ regulations. 
[Footnote 146] 

Further, these alternatives were responsive to the purpose and need 
statement, and FAA engaged in a detailed and collaborative process to 
ensure this result. This process included development of the Airspace 
Redesign Team, solicitation of input from facilities outside the study 
area as well as various stakeholders, and exploration of broad concepts 
using specific objectives. In addition, FAA used the project's purpose 
and need to evaluate the four alternatives both quantitatively and 
qualitatively. Each evaluative criterion flowed from an aspect of the 
stated purpose and need. 

Finally, the iterative process used by FAA and the detail and 
consideration given to the development and exploration of the 
alternatives suggest that FAA's range and scope of alternatives was 
"well-informed" and developed and that the agency came to a "well- 
considered" decision. FAA engaged in a detailed process to develop and 
explore a range of alternatives. In creating the Airspace Redesign 
Team, which then collaborated with outside and industry stakeholders 
and RTCA, the agency sought to gather all potential input and 
objectively develop feasible alternatives with both a regional and 
national focus. Additionally, once the alternatives were winnowed down, 
FAA engaged in another detailed process which modeled these 
alternatives. FAA's last step was to evaluate the alternatives based on 
criteria developed to meet the project's purpose and need. This 
process, which took several years to complete, contributed to an 
objective, well-developed, and well-considered range and scope of 
alternatives. The exploration of the alternatives based on the criteria 
also was rigorous. FAA conducted quantitative and qualitative 
evaluations, which are discussed at length in the EIS. FAA summarized 
the changes that would occur at specific airports under each 
alternative and then evaluated the alternative using the criteria. FAA 
also conducted an analysis of the noise impacts for each alternative. 
Under the governing "rule of reason" standard, these actions produced a 
reasonable range of alternatives, which were rigorously explored. 
[Footnote 147] 

3. Did FAA reasonably decide not to analyze environmental effects of 
the potential growth resulting from its airspace redesign? 

As discussed below, FAA complied with NEPA in deciding not to analyze 
environmental effects of the potential growth resulting from its 
airspace redesign. In the aviation context, courts have uniformly 
upheld FAA's decision not to analyze the effects of induced growth or 
induced capacity where the project's purpose was not to induce growth 
and the project did not entail construction of additional runway 
capacity. 

NEPA Requirements: 

One of NEPA's overarching requirements is that the agency consider and 
discuss the environmental effects of its proposed action. 40 C.F.R. §§ 
1502.16, 1508.7. This includes considering all direct and indirect 
effects and cumulative impacts of an action. Id. CEQ regulations define 
"indirect effects" as reasonably foreseeable effects caused by the 
action which appear later in time or farther in distance. 40 C.F.R. § 
1508.8(b). This includes growth-inducing effects and other effects 
related to induced changes in the pattern of land use, population 
density or growth rate, and related effects on air and water and other 
natural systems, including ecosystems. Id. 

FAA Actions: 

A number of external stakeholders involved in the New York/New Jersey/ 
Philadelphia Airspace Redesign argued that the greater efficiencies 
resulting from a redesign of the airspace would necessarily and 
foreseeably lead to an increase in air traffic volume, and that FAA 
therefore was required to analyze the environmental effects of this 
induced traffic. FAA disagreed, stating that the airspace redesign 
itself--which does not include infrastructure improvements such as 
additional runways--would not induce growth, and thus the agency was 
not required to (and did not) analyze the environmental impacts of such 
growth. As FAA explained in its response to comments, the airspace 
redesign "does not increase capacity. It increases the efficiency with 
which existing capacity is used ...."[Footnote 148] Similar statements 
were part of the Administrative Record.[Footnote 149] 

Analysis: 

FAA complied with NEPA in deciding not to analyze the potential growth- 
inducing effects of the airspace redesign, because the purpose of the 
redesign is neither to induce growth, nor create additional runway 
capacity.[Footnote 150] In cases where the project's purpose did not 
include growth inducement and where the project did not create 
additional runway capacity, courts have routinely upheld FAA's decision 
not to analyze the effects of induced growth. 

In Seattle Community Council Federation v. FAA, 961 F.2d 829, 836 (9th 
Cir. 1992), for example, the U.S. Ninth Circuit Court of Appeals found 
that because planned rerouting procedures at Seattle-Tacoma 
International Airport were designed to enhance the safety and 
efficiency of existing traffic rather than to induce growth, and 
involved no physical infrastructure changes, NEPA did not require FAA 
to address the environmental effects of an increased number of flights 
that might indirectly result from such efficiency improvements. In 
upholding FAA, the court emphasized the project's stated purpose of 
improving safety and efficiency, the same as FAA's purpose and need 
here. Although the challenges in Seattle Community Council related to 
FAA's failure to prepare an EIS, rather than the adequacy of an EIS as 
in the airspace redesign situation, the underlying issue is the same. 

Similarly, in Morongo Band of Mission Indians v. FAA, 161 F.3d 569 (9th 
Cir. 1998), FAA proposed to alter arrival procedures at Los Angeles 
International Airport without making changes to the airport's physical 
infrastructure. Relying in part on Seattle Community Council, the Ninth 
Circuit ruled that FAA complied with NEPA even though its pre-EIS 
environmental assessment did not consider possible growth-inducing 
effects of its action. The court explained that while "growth certainly 
may be a foreseeable indirect effect of the [project]..., the project 
was implemented in order to deal with existing problems; the fact that 
it might also facilitate further growth is insufficient to constitute a 
growth-inducing impact under 40 C.F.R. §1508.8(b)." Id. at 580 
(emphasis added). And in City of Los Angeles v. FAA, 138 F.3d 806 (9th 
Cir. 1998), the court found that FAA had given the requisite "hard 
look" at the environmental effects of a terminal expansion project at 
Burbank-Glendale-Pasadena Airport that did not include additional 
runways, even though FAA did not consider expansion's growth-inducing 
effects. The court relied in part on the fact that FAA's technical 
forecasts of air transportation demand and airfield capacity should be 
accorded significant deference. Id. at 807, n.2. 

Finally, in City of Olmsted Falls v. FAA, 292 F.3d 261 (D.C. Cir. 
2002), the U.S. D.C. Circuit Court of Appeals rejected a challenge to 
FAA's plan to move an existing runway at Cleveland Hopkins 
International Airport as part of an airport redevelopment project. The 
city argued that FAA had improperly failed to consider increased air 
emissions that would result from increased airport capacity. The court 
found FAA's actions were reasonable, however, even though FAA did not 
consider increased capacity, because as FAA determined, air travel 
demand and increased capacity were independent of rerouting the runway. 
(As the court phrased FAA's argument, "In other words, 'if you don't 
build it, they will come anyway.'" Id. at 272.) As in City of Los 
Angeles, the court relied in part on the fact that "FAA's expertise in 
forecasting air transportation demand and airfield capacity are areas 
where courts accord significant deference." Id. at 272 (citations 
omitted). 

These cases are unlike California v. DOT, 260 F. Supp. 2d 969 (N.D. 
Cal. 2003), discussed in section 1 above. There, the court found that 
FAA's decision not to analyze the environmental effects of a 
substantial growth-inducing expansion of a small town airport violated 
NEPA. In contrast to the present case, the expansion project in 
California would have extended and strengthened the airport's runway, 
created an air carrier apron, added access roads and parking, and 
constructed a passenger terminal complex. As noted above, the 
California court found that the very purpose of the expansion was to 
induce growth, by attracting thousands of additional tourists to a 
local ski resort. Distinguishing the projects in Seattle Community 
Council and City of Los Angeles because they each occurred in "a large 
city with substantial established commercial air service," the court in 
California emphasized that the project there involved "expansion of an 
airport to accommodate regular commercial air service, where none 
currently exists, in a scenic, mountain region with unique, largely 
undeveloped natural resources." 260 F. Supp.2d at 977. As the court 
concluded, "suffice it to say that [FAA's] argument that the airport 
project is growth-accommodating rather than growth-inducing ...is 
belied by the record." Id. at 976-77. Because FAA had failed to take a 
hard look at the project's environmental consequences, the court found 
that the agency's decision not to conduct an EIS was unreasonable, and 
ordered a halt to the project until an EIS was completed. 

We believe FAA's decision not to analyze potential growth-inducing 
effects of the New York/New Jersey/Philadelphia Airspace Redesign is 
akin to Seattle Community Council, City of Los Angeles, and City of 
Olmsted Falls and distinguishable from California v. DOT. As discussed 
in section 1 above, the purpose of the airspace redesign is to increase 
the efficiency and reliability of the airspace system while maintaining 
safety. The purpose is not, as in California v. DOT, to induce growth 
or enhance runway capacity, and the redesign does not, as in 
California, involve any additional physical infrastructure. In 
addition, in the current case, FAA specifically found that growth would 
not result from the project itself, a technical judgment similar to 
those accorded deference by City of Los Angeles and City of Olmsted 
Falls. Further, the project will, as in Seattle Community Council and 
City of Los Angeles, affect a region already saturated with air 
traffic. Under existing law, therefore, FAA was not required to analyze 
the potential indirect effects of increased growth that may result from 
the redesign. 

4. Did FAA reasonably involve the public in the environmental review 
process? 

As discussed below, FAA complied with NEPA in reasonably involving the 
public in its environmental review process. FAA conducted an early and 
open process and made substantial efforts to involve the public 
throughout the environmental review process. It also sponsored a 
reasonable number of public meetings and provided the public with 
adequate advance notice. Finally, FAA considered and responded to 
comments in an adequate manner. 

NEPA Requirements: 

CEQ regulations and FAA Order 1050.1E implement NEPA requirements for 
public participation. The regulations require that agencies involve the 
public in a number of different ways. An agency should begin by 
conducting an "…early and open process for determining the scope of 
issues related to a proposed action"[Footnote 151] and make "diligent 
efforts to involve the public…"[Footnote 152] throughout the 
environmental review process. To this end, the regulations require that 
an agency "provide public notice of NEPA-related ... public meetings 
... and the availability of environmental documents..."[Footnote 153] 
and hold or sponsor public meetings whenever appropriate or in 
accordance with statutory requirements...[Footnote 154] so as to 
solicit appropriate information from the public.[Footnote 155] Finally, 
in receiving information from the public, the regulations require an 
agency to "assess and consider comments both individually and 
collectively, and ...respond ...stating its response in the final 
statement ...." [Footnote 156] 

FAA Order 1050.1E provides further guidance on how FAA should comply 
with the foregoing regulations. As relevant here, the order provides 
that "at the earliest appropriate stage of the action and early in the 
process of preparing NEPA documentation, the responsible ... official 
... must provide pertinent information to the affected community and 
agencies and consider the affected communities' opinions…"[Footnote 
157] To accomplish this, the order specifies that FAA must provide the 
public with an opportunity to review and comment on the draft EIS and 
must formally respond to those substantive public comments in the final 
EIS.[Footnote 158] Additionally, the order emphasizes the discretion 
granted to FAA in this area by stating that there is "...no standard 
approach to public scoping…"[Footnote 159] and "...no requirements for 
a scoping meeting or for a specific number of meetings";[Footnote 160] 
nonetheless, "…it is important that FAA facilitate public participation 
in [the scoping process]..."[Footnote 161] 

FAA Actions: 

FAA involved the public in an extensive prescoping process for the 
airspace redesign. This included holding 31 prescoping public meetings, 
referred to as "Airspace Redesign Workshops," as a strategy to begin 
public education on airspace redesign, concepts, and expected benefits 
of the project.[Footnote 162] A total of 1,174 people attended the 
workshops and 712 comments were submitted. Further, during the formal 
scoping period, FAA held 28 meetings throughout the study area with the 
purpose of educating the public on the purpose and need of the project. 
A total of 1,031 people attended the scoping meetings and 901 comments 
were submitted and presented in a Scoping Report. This was followed by 
a formal public comment period, which was extended to solicit further 
public participation. During the public comment period, FAA conducted 
30 public meetings in the five states affected by the redesign's 
proposed alternatives. Subsequently, FAA issued a Noise Mitigation 
Report on the preferred alternative and solicited public input on the 
report by holding seven additional meetings, with at least one meeting 
in each state affected by the preferred alternative. 

FAA also advertised the meetings in local media through newspaper 
advertisements, press releases, and public service announcements. 
Additionally, FAA compiled a running list of all participants at each 
meeting and sent any subsequent announcements to those individuals by 
postcard, e-mail, or other means. FAA held its initial meetings in 
potentially affected communities and held its draft EIS and noise- 
mitigation meetings in areas where the most significant impacts of the 
airspace redesign would be felt. These meeting locations were 
accessible by public transit and were located to generate the most 
participation. (As discussed in section 5 below, the meeting locations 
also satisfied environmental justice directives.) At each meeting, FAA 
provided handouts and visual maps and displayed videos to assist the 
public in understanding the process. Representatives from FAA, 
including air traffic controllers and contractors, were on hand at 
scoping, draft EIS and noise-mitigation meetings to explain the project 
and answer questions. Throughout the EIS process, FAA solicited public 
comments and responded to each substantial comment, as required by CEQ 
regulations.[Footnote 163] Comments could be made at public meetings as 
well as by U.S. mail and e-mail. The public comment periods lasted at 
least 30 days and in some cases were extended to accommodate additional 
public participation.[Footnote 164] 

Analysis: 

Making a determination whether the public has been adequately involved 
in the EIS process is "a fact-intensive inquiry made on a case-by-case 
basis." Biodiversity Conservation Alliance v. Bureau of Land Mgmt., 404 
F. Supp. 2d 212, 220 (D.D.C. 2005). In this case, FAA conducted an 
early and open process and made considerable efforts thereafter to 
involve the public in the environmental review process. The prescoping 
campaign designed by the agency garnered extensive public participation 
and comments. The large number of meetings held in accessible areas in 
the study area (chosen to elicit the largest number of attendees) 
reflects FAA's efforts to educate the public about the redesign and 
address concerns, gather information, and solicit comments early in the 
process. FAA drew large crowds at the 31 meetings and received numerous 
formal public comments. Further, FAA made substantial efforts to 
involve the public in the formal scoping period, post-draft EIS period, 
and post-noise mitigation period, by similarly conducting another round 
of public meetings (65 in total), which educated the public on 
additional elements of the project. Meetings were accessible, they drew 
a substantial audience, and yielded a substantial number of public 
comments. Additionally, in each of these stages, FAA engaged in an open 
campaign to invite the public's attendance and comments by advertising 
through various media and keeping a running list of attendees. FAA also 
carefully chose locations which would contribute to this open process-
-accessibility for all and locations which would generate the most 
participation. Finally, FAA structured its meetings so that the public 
could learn about the process in various formats and ask questions of 
FAA and its contractors. These factors all contributed to the conduct 
of an "early and open process" and the use of "diligent efforts" to 
involve the public, as the CEQ regulations require, including 
sponsoring a reasonable number of public meetings (96 in all) and 
providing adequate notice of those meetings in various forms. 

FAA solicited public comments in various forms and responded to 
comments consistent with its responsibilities outlined in its Order. 
FAA solicited comments at public meetings and accepted them via U.S. 
mail and e-mail, as well. Public comment periods lasted 30 days or 
longer, and some were extended to garner additional public 
participation. FAA advised that it responded to all substantive 
comments received in the final EIS,[Footnote 165] directly addressing 
the question presented and showing consideration of concerns. Based on 
FAA's solicitation efforts and responses to substantive comments in the 
final EIS, FAA efforts met CEQ procedural regulations and FAA Order 
1050.1E. While there is no set process for addressing public 
participation requirements, in our view, FAA adequately addressed the 
issue consistent with NEPA regulatory requirements. 

5. Did FAA reasonably consider environmental justice issues in its 
environmental review process? 

As discussed below, in its EIS review process for the New York/New 
Jersey/Philadelphia Airspace Redesign, FAA satisfied the key 
environmental justice directives contained in Executive Order 12898, 
CEQ guidance documents, and DOT Orders. FAA prepared an analysis that 
identified minority and low-income populations significantly impacted 
by the proposed redesign and determined whether the impact on these 
populations was disproportionate. FAA also involved these individuals 
throughout the environmental review process. In addition, FAA mitigated 
these impacts through alteration of the preferred alternative, which 
included reducing the number of departure dispersal headings, shifting 
certain departure routes, and changing certain arrival altitudes. 

Executive Order 12898 and Other Requirements: 

Executive Order 12898, "Federal Actions to Address Environmental 
Justice in Minority Populations and Low-Income Populations," provides 
that "...each Federal agency shall make achieving environmental justice 
part of its mission by identifying and addressing ...disproportionately 
high and adverse human health or environmental effects of its programs, 
policies, and activities on minority populations and low-income 
populations…." Id. Sec. 1-101. The Presidential memorandum accompanying 
issuance of the Executive Order emphasized the importance of 
considering these effects when an environmental analysis is required 
under NEPA. See "Memorandum For the Heads of All Departments and 
Agencies, Re: Executive Order on Federal Actions to Address 
Environmental Justice in Minority Populations and Low-Income 
Populations," Comprehensive Presidential Documents No. 279 (Feb. 11, 
1994). CEQ, which oversees federal agency compliance with Executive 
Order 12898, has developed guidance to assist agencies in meeting their 
responsibilities under the order. See Environmental Justice: Guidance 
Under the National Environmental Policy Act (Dec. 10, 1997) (hereafter, 
CEQ Guidance). DOT also has issued an order to guide implementation of 
the Executive Order, which sets broad environmental goals.[Footnote 
166] 

By their terms, the Executive Order and implementing documents provide 
agencies with considerable flexibility in seeking to achieve these 
environmental justice goals. The Executive Order, for example, states 
that agencies shall make environmental justice part of their missions 
"to the greatest extent practicable and permitted by law…[and]…as 
appropriate ...." The CEQ Guidance describes its terms as flexible and 
serving as "...a point of departure, rather than a conclusive direction 
in applying the terms of the executive order,[Footnote 167] and 
recognizes "there is no standard formula for how environmental justice 
issues should be identified or addressed."[Footnote 168] There also is 
not a particular formula by which to address these in an EIS; agencies 
simply must present such concerns in a manner that is "...clear, 
concise, and comprehensible..."[Footnote 169] 

Against this backdrop of flexibility, Executive Order 12898 and these 
related documents direct agencies to make efforts to ensure the 
involvement of low-income and minority populations as part of the 
agency's consideration of the environmental impacts of its actions. The 
CEQ Guidance, for example, states that "...agencies should assure 
meaningful community representation ...and endeavor to have complete 
representation of the community as a whole ...as early as possible if 
it is to be meaningful."[Footnote 170] To this end, an agency should 
"...provide opportunities for effective community participation in the 
NEPA process, including ...improving the accessibility of public 
meetings, crucial documents, and notices"[Footnote 171] and "develop 
effective public participation strategies, ...acknowledge and seek to 
overcome linguistic, cultural, institutional, geographic, and other 
barriers to meaningful participation, and should incorporate active 
outreach to affected groups."[Footnote 172] 

The CEQ Guidance recommends consideration of these impacts at various 
stages of the environmental review process. In the scoping process, the 
CEQ Guidance suggests an agency "seek input from low income populations 
and minority populations ...as early in the process as information 
becomes available"[Footnote 173] by use of "...local resources, 
community and other non-governmental organizations, and locally 
targeted media."[Footnote 174] The following are cited as examples of 
ways to help inform the public during the scoping process: providing "a 
description of the proposed action," "maps, drawings, and other 
appropriate material or references," "an agency point of contact," and 
"timely notice of locations where comments will be received or public 
meetings held."[Footnote 175] 

Further, to solicit public participation, the CEQ Guidance recommends 
"...adaptive or innovative approaches to overcome linguistic, 
institutional, cultural, economic, historical, or other potential 
barriers to effective participation ...."[Footnote 176] Suggestions for 
developing a public participation strategy include: "translation of 
major documents...";[Footnote 177] "...opportunities for limited-
English speaking members of the affected public to provide comments 
throughout the NEPA process;"[Footnote 178] use of different media 
(e.g., size, formats);[Footnote 179] and "use of locations and 
facilities that are local, convenient, and accessible to ...low-income 
and minority communities ..."[Footnote 180] Finally, when analyzing 
alternatives, the CEQ Guidance suggests an agency consider "...the 
views it has received from the affected communities, ...the magnitude 
of environmental impacts associated with alternatives that have a less 
disproportionate and adverse effect on low-income populations and 
minority populations" and "...community views in developing and 
implementing mitigation strategies."[Footnote 181] 

FAA Actions: 

Throughout its environmental review process for the New York/New 
Jersey/Philadelphia Airspace Redesign, FAA sought to ensure the 
involvement of low-income and minority populations who would be 
significantly affected by the redesign. FAA conducted an environmental 
justice assessment to identify where those populations were located, 
[Footnote 182] and determined that minority populations near LaGuardia, 
Newark, and Philadelphia would experience significant noise impacts 
under what ultimately became the preferred alternative. Beginning in 
the prescoping phase, therefore, and continuing through the noise-
mitigation report phase, FAA held public meetings about the redesign in 
areas accessible by public transit and in low-income and minority 
communities, such as Newark, N.J., with disproportionately high and 
adverse noise impacts. FAA provided translators at these meetings to 
facilitate communication about the project and used different forms of 
media--maps, printouts, and video presentations, in addition to live 
speakers--to convey the elements and effects of the project. The 
meetings were publicized by advertisements in multiple publications, 
including local foreign language media, and by outreach to church 
leaders and community organizations. The public could submit comments 
to FAA at these targeted meetings. All of these measures were in 
addition to FAA's general public information and public comment 
opportunities for the redesign, as discussed in section 4 above. 

FAA concluded that there would be a disproportionate impact on minority 
populations near LaGuardia and Newark; however, with mitigation 
measures, these impacts would be eliminated. In addition, FAA concluded 
that there would be significant (though not disproportionate) impacts 
on minority populations near Philadelphia, but these would be 
eliminated once the redesign was fully implemented by 2012.[Footnote 
183] FAA also considered another alternative--the Ocean Routing 
Alternative--that would have eliminated noise impacts on these 
populations altogether but, as noted, that alternative was not selected 
because it did not meet the redesign's purpose and need. 

Analysis: 

FAA satisfied the environmental justice requirements of Executive Order 
12898 and the related CEQ and FAA regulations and guidance. As 
described in the final EIS, FAA conducted an assessment to identify 
minority and low-income populations that would be significantly 
affected by the redesign, determined whether the impact on these 
populations was disproportionate, and involved those populations 
throughout the environmental review process with sensitivity to issues 
that could affect their level of participation. As Executive Order 
12898 and CEQ guidance require, FAA engaged in reasonable initiatives 
to ensure these populations had the chance to participate in the review 
process, for example, by holding meetings in areas accessible by public 
transit and in those communities most significantly affected by the 
project. FAA also adhered to directives to overcome cultural and 
linguistic barriers and involve community and nongovernmental 
organizations in the notification process, by publicizing public 
meetings in various publications in both English and foreign language 
formats. When conducting these meetings, FAA heeded the directive to 
convey project information in various formats, by using maps, 
printouts, video, and speakers, as well as the Internet. These efforts 
generated a large number of comments from the affected populations, and 
FAA adequately responded to each substantive comment in the final EIS. 

Finally, FAA considered these populations in developing its 
alternatives, as the CEQ Guidance requires, by considering potential 
noise impacts on these communities and considering the Ocean Routing 
Alternative that would have eliminated disproportionately high and 
adverse noise impacts. FAA also mitigated the preferred alternative, 
thereby eliminating significant noise impacts no later than full 
implementation, in compliance with the CEQ Guidance requiring 
consideration of community views in developing and implementing 
mitigation strategies. These efforts and activities met the 
requirements of Executive Order 12898, CEQ Guidance, and the other 
directives "to the greatest extent practicable and permitted by law..." 
and "as appropriate..." 

[End of section] 

Appendix III: Operational Comparison of Alternatives: 

Purpose and Need Evaluation Criteria: Reduce complexity; 
How Measured: Jet route delays + time below 18,000 feet (minutes); 
Alternative: Future No Action: 12; 
Alternative: Modifications to Existing Airspace: 12; 
Alternative: Ocean Routing Airspace: 12; 
Alternative: Integrated Airspace without ICC: 11; 
Alternative: Integrated Airspace with ICC: 10. 

Purpose and Need Evaluation Criteria: Reduce complexity; 
How Measured: Arrival distance below 18,000 ft (nautical miles); 
Alternative: Future No Action: 96; 
Alternative: Modifications to Existing Airspace: 95; 
Alternative: Ocean Routing Airspace: 99; 
Alternative: Integrated Airspace without ICC: 96; 
Alternative: Integrated Airspace with ICC: 102. 

Purpose and Need Evaluation Criteria: Reduce voice communications; 
How Measured: Max interfacility hand-offs per hour; 
Alternative: Future No Action: 525; 
Alternative: Modifications to Existing Airspace: 525; 
Alternative: Ocean Routing Airspace: 521; 
Alternative: Integrated Airspace without ICC: 529; 
Alternative: Integrated Airspace with ICC: 382. 

Purpose and Need Evaluation Criteria: Reduce delay; 
How Measured: Traffic weighted arrival delay 2011 (minutes); 
Alternative: Future No Action: 22.9; 
Alternative: Modifications to Existing Airspace: 22.6; 
Alternative: Ocean Routing Airspace: 23.6; 
Alternative: Integrated Airspace without ICC: 22.8; 
Alternative: Integrated Airspace with ICC: 19.9. 

Purpose and Need Evaluation Criteria: Reduce delay; 
How Measured: Traffic weighted departure delay 2011 (minutes); 
Alternative: Future No Action: 23.3; 
Alternative: Modifications to Existing Airspace: 20.9; 
Alternative: Ocean Routing Airspace: 29.5; 
Alternative: Integrated Airspace without ICC: 20.8; 
Alternative: Integrated Airspace with ICC: 19.2. 

Purpose and Need Evaluation Criteria: Balance controller workload; 
How Measured: Equity of west gate fix traffic counts; 
Alternative: Future No Action: 0.37; 
Alternative: Modifications to Existing Airspace: 0.37; 
Alternative: Ocean Routing Airspace: 0.37; 
Alternative: Integrated Airspace without ICC: 0.34; 
Alternative: Integrated Airspace with ICC: 0.30. 

Purpose and Need Evaluation Criteria: Meet system demands and improve 
user access to system; 
How Measured: End of day's last arrival push (time); 
Alternative: Future No Action: 23:54; 
Alternative: Modifications to Existing Airspace: 23:54; 
Alternative: Ocean Routing Airspace: 23:54; 
Alternative: Integrated Airspace without ICC: 23:54; 
Alternative: Integrated Airspace with ICC: 23:00. 

Purpose and Need Evaluation Criteria: Expedite arrival and departures; 
How Measured: Time below 18,000 ft (minutes); 
Alternative: Future No Action: 18.5; 
Alternative: Modifications to Existing Airspace: 18.2; 
Alternative: Ocean Routing Airspace: 18.8; 
Alternative: Integrated Airspace without ICC: 18.2; 
Alternative: Integrated Airspace with ICC: 18.6. 

Purpose and Need Evaluation Criteria: Expedite arrival and departures; 
How Measured: Change in route length per flight (nautical miles)[A]; 
Alternative: Future No Action: 0.0; 
Alternative: Modifications to Existing Airspace: 0.0; 
Alternative: Ocean Routing Airspace: 4.5; 
Alternative: Integrated Airspace without ICC: - 1.2; 
Alternative: Integrated Airspace with ICC: 3.7. 

Purpose and Need Evaluation Criteria: Expedite arrival and departures; 
How Measured: Change in block time (minutes per flight)[A]; 
Alternative: Future No Action: 0.0; 
Alternative: Modifications to Existing Airspace: -0.9; 
Alternative: Ocean Routing Airspace: 3.9; 
Alternative: Integrated Airspace without ICC: - 1.0; 
Alternative: Integrated Airspace with ICC: -1.4. 

Purpose and Need Evaluation Criteria: Flexibility in routing; 
How Measured: Delay saved per flight per day; 
Alternative: Future No Action: 0.0; 
Alternative: Modifications to Existing Airspace: 0.0; 
Alternative: Ocean Routing Airspace: 0.0; 
Alternative: Integrated Airspace without ICC: 0.0; 
Alternative: Integrated Airspace with ICC: 12.6. 

Purpose and Need Evaluation Criteria: Maintain airport throughput; 
How Measured: Arrival max sustainable throughputs; 
Alternative: Future No Action: 223; 
Alternative: Modifications to Existing Airspace: 223; 
Alternative: Ocean Routing Airspace: 223; 
Alternative: Integrated Airspace without ICC: 223; 
Alternative: Integrated Airspace with ICC: 238. 

Purpose and Need Evaluation Criteria: Maintain airport throughput; 
How Measured: Departure max sustainable throughputs; 
Alternative: Future No Action: 238; 
Alternative: Modifications to Existing Airspace: 239; 
Alternative: Ocean Routing Airspace: 221; 
Alternative: Integrated Airspace without ICC: 240; 
Alternative: Integrated Airspace with ICC: 245. 

Source: FAA. 

[A] A negative value indicates a new decrease in the category. 

[End of table] 

[End of section] 

Appendix IV: Summary of the Integrated Airspace Alternative with ICC: 

Airport: JFK; 
Changes from the Future No Action Alternative: 
* North departure gate shifted 15 miles northeast;
* New distant procedures for aircraft heading to the North departure 
gate;
* West departure gate extended to the north and to the south;
* New procedures for aircraft heading to the West departure gate;
* Future No Action Ocean departure gate split into Ocean and South 
departure gates;
* New distant procedures for aircraft heading to the Ocean departure 
gate;
* New procedures for aircraft heading to the South departure gate;
* North arrival post shifted 5 miles southeast;
* New distant procedures for aircraft arriving from the North arrival 
post;
* East arrival post shifted northwest;
* New procedures for aircraft arriving from the East arrival post;
* South arrival post shifted to the northeast;
* New procedures for aircraft arriving from the South arrival post. 

Airport: LaGuardia; 
Changes from the Future No Action Alternative: 
* East departure gate shifted east;
* North departure gate shifted 15 miles northeast;
* New procedures for aircraft heading to the North departure gate;
* West departure gate extended to the north and to the south;
* New procedures for aircraft heading to the West departure gate;
* South departure gate shifted to the northwest;
* New procedures for aircraft heading to the South departure gate;
* North arrival post shifted 30 miles east;
* New procedures for aircraft arriving from the North arrival post;
* West arrival posts shifts to coincide with Future No Action South 
arrival post;
* New procedures for aircraft arriving from the west to coincide with 
the South arrival post;
* West arrival flow split into two arrival flows, one to the north and 
one to the south;
* New departure headings for aircraft departing Runway 4 to the North 
departure gate;
* New departure headings for aircraft departing Runway 4 to the East 
departure gate. 

Airport: Newark; 
Changes from the Future No Action Alternative: 
* New departure headings for all runways and all gates;
* East departure gate shifted to the east;
* New procedures for aircraft heading to East departure gate;
* North departure gate shifted to the northeast;
* New procedures for aircraft heading to the North departure gate;
* West departure gate expanded to the north and south;
* New procedures for aircraft heading to the West departure gate;
* South departure gate shifted to the southwest;
* New procedures for aircraft heading to the South departure gate;
* New Ocean departure gate;
* New procedures for aircraft heading to the Ocean departure gate;
* North arrival post moved to 50 miles north of Newark airport;
* New procedures for aircraft arriving from the North arrival post;
* West arrival post shifted to be near Greenville, New York;
* West arrival flow split into two arrival flows, one to the north and 
one to the south;
* New procedures for aircraft arriving from the South arrival post;
* Use of both parallel runways for arrivals. 

Airport: Teterboro; 
Changes from the Future No Action Alternative: 
* Departure gates match those of Newark Integrated Airspace with ICC;
* New distant procedures for aircraft heading to the North departure 
gate; 
* New distant procedures for aircraft heading to the West departure 
gate;
* New distant procedures for aircraft heading to the South departure 
gate;
* West arrival post shifted 15 miles south;
* New procedures for aircraft arriving from the West arrival post;
* New procedures for aircraft arriving from the West arrival post from 
the vicinity of Yardley, Pennsylvania. 

Airport: Westchester County Airport; 
Changes from the Future No Action Alternative: 
* North departure gate shifted 15 miles northeast;
* New distant procedures for aircraft heading to the North departure 
gate;
* West departure gates extended to the north and to the south;
* New procedures for aircraft heading to the West departure gate; 
* South departure gate shifted to the west;
* New departure procedures for aircraft departing to the South gate;
* North arrival post shifted to the east;
* New distant procedures for aircraft arriving from the North gate;
* New distant procedures for aircraft arriving from the south. 

Airport: Philadelphia; 
Changes from the Future No Action Alternative: 
* West departure gate expanded to the northwest;
* New procedures for aircraft heading to the West departure gate;
* East departure gate is shifted to the east;
* New procedures for aircraft heading to the East departure gate;
* West arrival post shifts to the northeast;
* New distant procedures for aircraft arriving from the West arrival 
post;
* New departure headings for aircraft heading to the North, East, West, 
Southwest, and South departure gates;
* Additional route added to North arrival post. 

[End of table] 

Source: FAA. 

[End of section] 

Appendix V: Comments from the Department of Transportation: 

U.S. Department of Transportation: 
Office of the Secretary of Transportation: 
Assistant Secretary for Administration: 
1200 New Jersey Avenue, SE: 
Washington, DC 20590: 

June 19, 2008: 

Ms. Susan Fleming: 
Director, Physical Infrastructure Issues: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20458: 

Dear Ms. Fleming: 

Representatives from the Federal Aviation Administration (FAA) and the 
Office of the Secretary have reviewed the GAO draft report, "FAA 
Airspace Redesign: An Analysis of the New York/New Jersey/Philadelphia 
Project." While we are pleased to see that the GAO review concluded the 
actions taken by FAA with regard to the National Environmental Policy 
Act were reasonable, the Department does not necessarily agree with 
everything in the draft report. However, we are constrained from 
offering a detailed analysis of the draft report at this time, as the 
matters it covers are the subject of pending litigation. Specifically, 
there are currently 12 consolidated lawsuits before the U.S. Court of 
Appeals for the District of Columbia Circuit that challenge one or more 
aspects of the airspace redesign project. 

Neither the 73 Petitioners, nor the Federal Respondents, have yet 
submitted briefs on the merits. Therefore substantive comments with 
regard to the GAO draft report could potentially prejudice our ability 
to defend this project in litigation. 

We appreciate the opportunity to review the draft report. Please 
contact Mr. Martin Gertel, Director of Audit Relations, on (202) 366-
5145 with any questions. 

Sincerely, 

Signed by: 

Linda J. Washington: 

[End of section] 

Appendix VI: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Susan A. Fleming, (202) 512-2834, flemings@gao.gov: 

Susan D. Sawtelle, (202) 512-6417, sawtelles@gao.gov: 

Staff Acknowledgments: 

In addition to the individuals named above, Paul Aussendorf, Assistant 
Director; Lauren Calhoun; Heather Dowey; Tim Guinane; David Hooper; 
Delwen Jones; Maureen Luna-Long; Sara Ann Moessbauer; Tim Schindler; 
and Gretchen Snoey made key contributions to this report. Also 
contributing to the report were Richard Johnson and Josh Ormond. 

[End of section] 

Footnotes: 

[1] The five major airports include New York's John F. Kennedy 
International Airport (JFK) and LaGuardia Airport (LaGuardia), New 
Jersey's Newark Liberty International Airport (Newark) and Teterboro 
Airport (Teterboro), and Pennsylvania's Philadelphia International 
Airport (Philadelphia). 

[2] Airspace for this project is the navigable area used by aircraft 
for purposes of flight. In addition, FAA maintains infrastructure for 
the National Airspace System to include FAA air traffic control (ATC) 
system, which relies on an extensive array of information technology 
systems, including radars, automated data processing, navigation, and 
communication equipment; and ATC facilities. 

[3] In 2006, over 100 million passengers used JFK, LaGuardia, and 
Newark, alone. 

[4] The estimated benefits are based on FAA's operational analysis for 
2011; however, full implementation is not estimated to be completed 
until 2012. 

[5] Twelve of the 13 lawsuits are based primarily on NEPA grounds and 
have been consolidated in the U.S. Court of Appeals for the D.C. 
Circuit under the lead case, County of Rockland v. FAA, No. 07-1363. 
The other lawsuit, County of Delaware v. USDOT, No. 07-1385 (D.C. 
Cir.), challenges the redesign based on FAA's allegedly improper 
implementation of the Clean Air Act. 

[6] The court in the NEPA litigation has denied requests that FAA 
temporarily stop implementation while the lawsuits are being resolved. 

[7] The three similar FAA-sponsored redesigns included the Expanded 
East Coast Plan (1995), Chicago Terminal Airspace Project (2001), and 
Potomac Consolidated TRACON Facility Airspace Redesign (2002). These 
were determined to be most similar to the New York/New Jersey/ 
Philadelphia Airspace Redesign project because they all included an 
EIS, changes to air traffic routes involving multiple airports, and an 
analysis of noise impacts. 

[8] In this report, the term "contractors" refers to organizations used 
to conduct the operational and environmental analyses. This includes 
MITRE, the organization that was responsible for conducting the 
operational analysis. MITRE is a not-for-profit corporation, which 
operates a Federally Funded Research and Development Center (FFRDC) 
sponsored by FAA--the Center for Advanced Aviation System Development. 
An FFRDC is a unique organization that assists the U.S. government with 
scientific research and analysis, development and acquisition, and 
systems engineering and integration. FFRDCs are charged with addressing 
long-term problems of considerable complexity, analyzing technical 
questions with a high degree of objectivity, and providing creative and 
cost-effective solutions to government problems. 

[9] Although we took stakeholder concerns expressed after the NEPA 
process into account when developing our five key issues, a court may 
consider a petitioner to have waived their right to challenge issues 
that were not raised during the process. 

[10] For this airspace redesign project, FAA included in its study area 
16 satellite airports, including (1) Allentown/Lehigh Valley 
International, (2) Atlantic City International, (3) Bridgeport/Igor I. 
Sikorsky Memorial, (4) Caldwell/Essex County, (5) Westhampton Beach/The 
Francis S. Gabreski, (6) Islip Long Island MacArthur, (7) Linden, (8) 
Morristown Municipal, (9) Newburgh/Stewart International, (10) New 
Haven/Tweed-New Haven, (11) Northeast Philadelphia, (12) Republic, (13) 
Trenton/Mercer County, (14) White Plains/Westchester County, (15) 
Wilmington/New Castle County, and (16) McGuire Air Force Base. There 
are other airports physically located within the region, but they were 
not included in FAA's operational analysis because they do not have a 
significant amount of Instrument Flight Rule traffic, thus there would 
be little or no change to their operations as a result of the proposed 
action. Instrument Flight Rule traffic from these other airports was 
included in the environmental analysis as overflights. 

[11] For example, JetBlue Airlines uses JFK as its hub airport, U.S. 
Airways uses Philadelphia as its hub airport, and Continental Airlines 
uses Newark as one of its hub airports. 

[12] To minimize congestion and reduce flight delays, FAA promulgated 
the High Density Rule in 1968, 14 C.F.R. § 93, Subpart K, which set 
limits on the number of take-offs or landings--referred to as "slots"-
-that can occur during certain periods of the day at four congested 
airports--Chicago's O'Hare, Ronald Reagan Washington National, and New 
York's JFK and LaGuardia. 

[13] Wendell H. Ford Aviation Investment and Reform Act for the 21st 
Century, also referred to as AIR-21, Pub. L. No. 106-181, 114 Stat. 
108, Section 231, April 5, 2000. 

[14] In the mid-1980s, a plan to improve airspace efficiency in and 
around the New York metropolitan area was implemented. The Expanded 
East Coast Plan focused on developing common departure routes out of 
the New York metropolitan area. The plan, which included changes to 
routes and procedures above 3,000 feet, was implemented in phases in 
1987 and 1988. Based on the public reaction to the Expanded East Coast 
Plan, FAA recognized that the New York/New Jersey/Philadelphia Airspace 
Redesign had the potential to be controversial based on potential 
environmental impacts. 

[15] The National Airspace Redesign Strategic Management Plan was 
developed collaboratively by local facility and regional air traffic 
specialists, Air Transport Association representatives, and the 
National Air Traffic Controllers Association (NATCA). The plan works in 
conjunction with the March 16, 2001, FAA/NATCA Memorandum of 
Understanding regarding the National Airspace Redesign. In 2005, when 
the National Airspace Redesign transitioned to the Airspace Management 
Program, FAA terminated the assignments for NATCA representatives to 
the National Airspace Redesign. 

[16] There are two versions of the Handbook. The Airspace Management 
Handbook Version 1 was first published in 1999 and consists of three 
parts--the Airspace Management Handbook: Checklist; the Airspace 
Management Handbook: Guidelines; and the Airspace Management Handbook: 
Metrics. In December 2005, FAA published Version 2.2, which combines 
all of the content of the previous documents and includes supporting 
information for safety risk management considerations. The steps 
established in these handbooks include (1) characterizing the extent of 
the airspace problem, (2) performing an initial evaluation (scoping), 
(3) initiating an airspace study, (4) conducting an airspace study, (5) 
summarizing and presenting the results of the airspace study, (6) 
implementing the recommended changes, and (7) evaluating the final 
implementation of the airspace redesign to ensure changes made to the 
airspace accomplished the redesign's intended goal. Because the FAA 
airspace redesign project was initiated in 1998, we are basing our 
review on Version 1. 

[17] 42 U.S.C. §§ 4321 et seq. 

[18] NEPA section 102(c), 42 U.S.C. § 4332(c). An EIS is not required 
for all federal actions. Actions that do not individually or 
cumulatively have a significant effect on the human environment may be 
categorically excluded. 40 C.F.R. § 1508.4. Additionally, an EIS is not 
required for projects for which a project-specific Environmental 
Assessment discloses no significant impact. 40 C.F.R. § 1508.9. 

[19] 40 C.F.R. § 1506.6. 

[20] At the start of the airspace redesign in 1998, FAA Order 1050.1D, 
Environmental Impacts: Policies and Procedures, was the current 
guidance. The Order was updated to FAA Order 1050.1E, Environmental 
Impacts: Policies and Procedures, on June 8, 2004, and again on March 
20, 2006, to FAA Order 1050.1E, Chg 1. 

[21] Executive Order 12898, Federal Actions to Address Environmental 
Justice in Minority Populations and Low-Income Populations, 59 Fed. 
Reg. 7629 (Feb. 16, 1994). 

[22] DOT Order 5610.2, Environmental Justice in Minority and Low-Income 
Populations. 

[23] Executive Order 12898, Sec. 1-101. 

[24] In this airspace redesign, ICC refers to the existence of a common 
automation platform in existing facilities, a new facility, or a 
consolidated facility. A common automation platform refers to a single 
radar data processing system and the information it provides to 
controllers. It includes shared displays on screens, radar, data 
processing and presentation, and communications. 

[25] FAA issued a corrected version of the Record of Decision on Sept. 
28, 2007 after FAA identified several items in the original document 
that were omitted or incorrect due to editing mistakes. 

[26] 5 U.S.C. § 706(2)(A). 

[27] Draft EIS, p. 2-2; final EIS, p. 2-2. 

[28] 40 C.F.R. § 1502.13. 

[29] FAA Order 1050.1E, section 506(d). 

[30] Experts we interviewed also agreed that the scope of the purpose 
and need was reasonable. 

[31] 40 C.F.R. § 1502.14(d). 

[32] 40 C.F.R. § 1502.14(a). 

[33] An agency's discussion of alternatives will be upheld as long as 
the alternatives are reasonable and are discussed in reasonable detail. 
Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 196 (D.C. 
Cir. 1991), cert. denied, 502 U.S. 994 (1991). 

[34] See Citizens Against Burlington, Inc., 938 F.2d at 196. 

[35] In addition, experts interviewed by GAO agreed that the 
alternatives were feasible and met the purpose and need of the project. 

[36] See Citizens Against Burlington, Inc., 938 F.2d at 196. 

[37] 40 C.F.R. § 1502.14(a). 

[38] 40 C.F.R. § 1502.14(b). 

[39] 40 C.F.R. §§ 1502.16, 1508.7. 

[40] 40 C.F.R. § 1508.8(b). 

[41] Morongo Band of Mission Indians v. FAA, 161 F.3d 569, 580 (9th 
Cir. 1998); see also Seattle Community Council Federation v. FAA, 961 
F.2d 829 (9th Cir. 1992) (re-routing of flights at Seattle-Tacoma 
International Airport involving no infrastructure changes did not 
require FAA analysis of environmental effects of increased flights that 
may indirectly result from efficiency improvements). 

[42] 40 C.F.R. § 1506.6(a). 

[43] 40 C.F.R. § 1501.7. 

[44] 40 C.F.R. § 1506.6(b) and (c). 

[45] 40 C.F.R. § 1506.6(d), 40 C.F.R. § 1503.1(4) and 40 C.F.R. § 
1503.4. 

[46] FAA stated that its decision to hold prescoping meetings was due 
to prior experiences with airspace redesign and a desire to better 
educate the public on airspace redesigns. 

[47] FAA's contractors stated the mailing list kept the same names 
throughout the various EIS periods and added new names and addresses to 
the master list during the process. 

[48] FAA stated that the mailing list developed during the Expanded 
East Coast Project was used to contact members of the public about the 
airspace redesign. 

[49] Experts we interviewed also stated that FAA's involvement of the 
public throughout the EIS process was sufficient given the scope and 
complexity of the redesign. 

[50] 40 C.F.R. §§ 1503.1(4), 1503.4, 1506.6(d). 

[51] Executive Order 12898, Federal Actions to Address Environmental 
Justice in Minority Populations and Low-Income Populations, Feb. 11, 
1994. 

[52] CEQ, Environmental Justice: Guidance under the National 
Environmental Policy Act, Dec. 10, 1997. 

[53] DOT 5610.2, Environmental Justice in Minority and Low-Income 
Populations. 

[54] Congressional members and citizens raised concerns about FAA's 
environmental justice assessment around Newark Liberty Airport during 
the public comment period for the draft EIS. 

[55] In the final EIS, FAA stated that the definitions of "minority" 
and "low-income" populations in Order DOT 5610.2 were broad. Therefore 
the agency also used definitions from the CEQ to more narrowly define 
the two populations. 

[56] GAO, Surface Transportation: Many Factors Affect Investment 
Decisions, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-744] 
(Washington, D.C.: June 30, 2004); GAO, Highway and Transit 
Investments: Options for Improving Information on Projects' Benefits 
and Costs and Increasing Accountability for Results, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-05-172] (Washington, D.C.: Jan. 
24, 2005); and GAO, Intercity Passenger Rail: National Policy and 
Strategies Needed to Maximize Public Benefits from Federal 
Expenditures, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-15] 
(Washington, D.C.: Nov. 13, 2006). 

[57] GAO, Bureau of Reclamation: An Assessment of the Environmental 
Impact Statement on the Operations of the Glen Canyon Dam, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO/RCED-97-12] (Washington, D.C.: 
Oct. 2, 1996); GAO, Army Corps of Engineers: An Assessment of the Draft 
Environmental Impact Statement of the Lower Snake River Dams, 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO/RCED-00-186] 
(Washington, D.C.: July 24, 2000); GAO, Oregon Inlet Jetty Project: 
Environmental and Economic Concerns Still Need to Be Resolved, 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-02-803] (Washington, 
D.C.: Sept. 30, 2002); GAO, Assigning Air Traffic Control Costs to 
Users: Elements of FAA's Methodology Are Generally Consistent with 
Standards but Certain Assumptions and Methods Need Additional Support, 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-76] (Washington, 
D.C.: Oct. 19, 2007). 

[58] FAA's airspace redesign team initially included air traffic 
controllers in the study area and neighboring areas. 

[59] The Future No Action Alternative was included in the evaluation as 
required by NEPA and CEQ regulations. The Ocean Routing Airspace 
Alternative was developed by the New Jersey Citizens for Environmental 
Research, Inc., at the request of the New Jersey Coalition Against 
Aircraft Noise (NJCAAN) and was evaluated as a potential alternative 
due to long-standing concerns of the NJCAAN. 

[60] As defined in FAA's Handbook, metrics are parameters, algorithms, 
or formulas used to quantify system performance, and they are measured 
either directly in the National Airspace System or in models of the 
National Airspace System. 

[61] Flight track dispersion occurs because flights do not all follow 
the same exact path. There is natural variation of flight tracks based 
on operational factors, such as pilot variation and weather conditions. 

[62] Use of this metric also has been upheld by courts. See City of 
Grapevine v. DOT, 17 F.3d 1502, 1508 (D.C. Cir. 1994); Sierra Club v. 
DOT, 753 F.2d 120, 128 (D.C. Cir. 1985). 

[63] FICON, Federal Interagency Review of Selected Airport Noise 
Analysis Issues, August 1992. 

[64] FICON was the predecessor of the Federal Interagency Committee on 
Aviation Noise. 

[65] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-744], 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-172], and 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-15]. 

[66] The flight operations forecast is based on the traffic demand 
forecast. 

[67] See "FAA Airport Benefit-Cost Analysis Guidance," Office of 
Aviation Policy and Plans, FAA, Dec. 15, 1999. FAA officials told GAO 
that this guidance does not apply to airspace redesign projects. 
Nonetheless, the officials agreed that the economic principles embodied 
in the guidance are generally applicable. 

[68] Total price includes air fare and travel time. 

[69] More specifically, inelastic demand means that a 1 percent change 
in price results in a less-than-proportionate change in demand, and 
elastic demand means that a 1 percent change in price results in a 
greater-than-proportionate change in demand. By holding traffic demand 
constant across alternatives, FAA essentially assumed that demand is 
perfectly inelastic or completely unresponsive to price changes. 

[70] FAA's guidance also states that investments that lower average 
delay at an airport will generally induce some customers who formerly 
avoided the airport to use it, thereby placing new demands on the 
facility and eroding some delay savings. The guidance also states that 
if the project reduces delay in excess of an average of 1 minute per 
operation, then travel demand forecasts should be adjusted. The 
guidance states that as a rule of thumb, one 2 percent increment should 
be simulated for each 3-minute savings. In addition, the guidance 
states that it is DOT policy that passengers recognize small time 
savings and can use them effectively. Therefore, a relatively small 
time savings should be valued at the same rate as longer time savings. 

[71] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-15]. 

[72] National Airspace System Capital Investment Plan FY 2008-2012. 

[73] RNAV enables aircraft to fly on any desired flight path within the 
coverage of ground-or-space-based navigation aids, within the limits of 
the capability of the self-contained systems, or a combination of both 
capabilities. As such, RNAV aircraft have better access and flexibility 
for point-to-point operations. 

[74] FAA's 2006 Roadmap for Performance-Based Navigation. 

[75] For example, typically route procedures that are designated with 
an accuracy value of 2 (designated RNAV-2), require aircraft to be 
within 2 nautical miles of their assigned flight path 95 percent of the 
flight time. 

[76] These metrics also can be calculated using the same noise modeling 
tools used to calculate DNL. The noise model is capable of calculating 
up to 13 noise metrics, some of which include the supplemental metrics 
mentioned by the experts. 

[77] Sound Exposure Level, or SEL, metric is used to measure noise 
exposure for a single aircraft flyover. It identifies the cumulative 
sound that a person is exposed to during the event if the sound were 
compressed into 1 second of time. 

[78] The Time-Above metric can identify how much time during a 
designated time period--such as a day--the noise exposure levels will 
exceed a specified decibel level. The sound level must be specified-- 
for example, 60 decibels. This method can then determine the length of 
time during a 24-hour period that noise levels will exceed 60 decibels. 

[79] According to FICON. 

[80] FAA calculated supplemental metrics in the Potomac Consolidated 
TRACON Facility Airspace Redesign and the Chicago Terminal Airspace 
Project. 

[81] For example, a key input into the operational analysis was the 
travel demand forecast--an inherently uncertain input because future 
conditions cannot be precisely predicted. 

[82] Airspace Management Handbook, Version 1, p. 21. 

[83] DOT, FAA, Office of System Capacity, 2001 Aviation Capacity 
Enhancement Plan, December 2001. 

[84] An expert interviewed said that this level of difference appeared 
reasonable. 

[85] Specifically, the forecast underestimated airlines' use of 
regional jets and the level of air traffic at many regional airports. 

[86] A common automation platform refers to a single radar data 
processing system and the information it provides to controllers. It 
includes shared displays on screens, radar, data processing and 
presentation, and communications. 

[87] FAA officials do not currently know what the costs will be to 
develop the common automation platform. 

[88] App. C of the final EIS, p. 10-4. 

[89] Even though reduction of noise was not part of the purpose and 
need for the airspace redesign, thus not a criterion in the decision- 
making process, FAA emphasized that noise impacts were considered. 
Specifically, FAA explained that it considered noise after selecting 
the preferred alternative by identifying measures to mitigate the noise 
impacts associated with the preferred alternative. Several noise 
mitigation measures were incorporated into the preferred alternative, 
which according to FAA, would result in the mitigation of all 
significant noise impacts by 2011. As determined by FAA, "significant" 
noise impacts occur if a proposed action would result in a minimum 1.5 
DNL increase where noise exposure already exceeds 65 DNL or would 
exceed 65 DNL after the increase. FAA also explained that it did not 
use noise metrics when comparing alternatives because there are no 
established standards for significance of noise reduction. For 
instance, there is no standard to answer the question, "Which is 
better: reducing the noise impacts for 1,000 people by 3 decibels, or 
reducing the noise impacts for 500 people by 5 decibels?" 

[90] These methods include hedonic price techniques, which can be used 
to measure the effect of economic attributes like noise on housing 
values. 

[91] FAA also did some comparative analyses that involved comparing 
some elements of the 2006 forecast with the observed levels in 2005 and 
some elements of the 2011 forecast for Philadelphia traffic with the 
2012 forecast used in the Capacity Enhancement Plan. 

[92] FAA Regional Air Service Demand Study, Summary Report. Sponsored 
by FAA, The Port Authority of New York and New Jersey, New York State 
Department of Transportation, and Delaware Valley Regional Planning 
Commission, May 2007. 

[93] Handbook, p. 21. FAA's Benefit-Cost Analysis Guidance also 
recommends the use of sensitivity analysis. 

[94] Experts noted that a sensitivity analysis would have less of an 
effect on a noise analysis than on an operational analysis. As one 
expert noted, this is because traffic on one day will not significantly 
impact the noise model, which reflects annual average conditions. In 
addition, according to this expert, there would need to be a 35 percent 
to 40 percent error in the traffic forecast to affect DNL. 

[95] Although not required, a benefit-cost analysis is permitted under 
CEQ regulations. Under 40 C.F.R. § 1502.23,. "if a cost-benefit 
analysis relevant to the choice among environmentally different 
alternatives is being considered for the proposed action, it shall be 
incorporated by reference or appended to the [EIS] as an aid in 
evaluating the environmental consequences." The regulation further 
states that when a cost-benefit analysis is prepared, the EIS should 
discuss the relationship between that analysis and any analyses of 
unquantified environmental impacts, values, and amenities. The 
regulation states that the merits and drawbacks of the alternatives 
need not be displayed in a monetary cost-benefit analysis and should 
not be when there are important qualitative considerations. 

[96] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-744] and 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-172]. 

[97] FAA Airport Benefit-Cost Analysis Guidance, Office of Aviation 
Policy and Plans, FAA, Dec. 15, 1999 and FAA Web page entitled "The FAA 
Acquisition System Toolset, AMS Policy vs. Guidance," [hyperlink, 
http://fast.faa.gov] (accessed March 15, 2008). FAA, along with the 
U.S. National Aeronautics and Space Administration Transport Canada, 
also is sponsoring research to develop analytical tools to assess the 
benefits and costs of different environmental policies and research and 
development investment strategies. One area of research is focusing on 
how to monetize the health and welfare impacts of aviation noise, local 
air quality, and climate effects to enable a robust cost-benefit 
analysis of policy alternatives. 

[98] We recognize that the guidance does not apply to the Air Traffic 
Organization, which includes the FAA division responsible for airspace 
redesigns. 

[99] FAA reported in the Record of Decision that the airspace redesign 
would reduce annual operating costs by $248 million and severe weather 
delay costs by another $37 million, totaling $285 million. However, in 
a letter to Senator Robert Menendez in February 2008, FAA estimated 
that there would be $300 million annual savings in direct operating 
costs. FAA stated that the higher reduction in annual operating costs 
was due to an increase in jet fuel prices. 

[100] Economic Values for FAA Investment and Regulatory Decisions, A 
Guide. Prepared by GRA Incorporated for the FAA Office of Aviation 
Policy and Plans (Washington, D.C., Dec. 31, 2004). 

[101] GAO, Results-Oriented Cultures: Implementation Steps to Assist 
Mergers and Organizational Transformations, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-03-669] (Washington, D.C.: July 
2, 2003); GAO, Intercity Passenger Rail: Issues Associated with the 
Recent Settlement between Amtrak and the Consortium of Bombardier and 
Alstom, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-152] 
(Washington, D.C.: Dec. 1, 2004); GAO, United States Coast Guard: 
Improvements Needed in Management and Oversight of Rescue System 
Acquisition, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-623] 
(Washington, D.C.: May 31, 2006); GAO, Telecommunications: Full 
Adoption of Sound Transition Planning Practices by GSA and Selected 
Agencies Could Improve Planning Efforts, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-06-476] (Washington, D.C.: June 
6, 2006); GAO, 2010 Census: Costs and Risks Must be Closely Monitored 
and Evaluated with Mitigation Plans in Place, GAO-06-822T (Washington, 
D.C.: June 6, 2006). 

[102] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-669]. 

[103] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-152]. 

[104] GAO, Next Generation Air Transportation System: Progress and 
Challenges Associated with the Transformation of the National Airspace 
System, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-25] 
(Washington, D.C.: Nov. 13, 2006). 

[105] GAO, Federal Aviation Administration: Challenges Facing the 
Agency in Fiscal Year 2009 and Beyond, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-08-460T] (Washington, D.C.: Feb. 
7, 2008). 

[106] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-152], 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-76], and GAO, Next 
Generation Air Transportation System: Status of the Transition to the 
Future Air Traffic Control System, [hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-07-784T] (Washington, D.C.: May 9, 2007). 

[107] See [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-460T] 
and GAO, National Airspace System: Transformation Will Require Cultural 
Change, Balanced Funding Priorities, and Use of All Available 
Management Tools, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-
154] (Washington, D.C.: Oct. 14, 2005). 

[108] The strategy is already used by some federal, state, and local 
agencies, such as the South Florida Ecosystem Restoration Task Force. 

[109] The guide does not establish new requirements and does not 
constitute formal CEQ guidance. 

[110] GAO, Yellowstone Bison: Interagency Plan and Agencies' Management 
Need Improvement to Better Address Bison-Cattle Brucellosis 
Controversy, [hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-291] 
(Washington, D.C.: Mar. 7, 2008). 

[111] See "Environmental Management Systems and NEPA Adaptive 
Management" available at [hyperlink, 
http://www.faa.gov/regulations_policies/policy_guidance/envir_policy] 
(accessed on May 29, 2008). 

[112] The three similar FAA-sponsored redesigns included the Expanded 
East Coast Plan (1995), Chicago Terminal Airspace Project (2001), and 
Potomac Consolidated Terminal Radar Approach Control (TRACON) Facility 
Airspace Redesign (2002). These were determined to be most similar to 
the New York/New Jersey/Philadelphia Airspace Redesign project because 
they all included an EIS analysis, changes to air traffic routes 
involving multiple airports, and analysis of noise impacts. 

[113] Although we took stakeholder concerns expressed after the NEPA 
process into account when developing our five key issues, a court may 
consider a petitioner to have waived their right to challenge issues 
that were not raised during the process. 

[114] In conducting our analysis, we relied on FAA's draft and final 
Environmental Impact Statements and its Record of Decision, and the 
Administrative Record filed by FAA with the D.C. Circuit in December 
2007 in the County of Rockland litigation (hereafter, Administrative 
Record). 

[115] Section 102(2)(C) of NEPA requires all federal agencies to 
prepare an EIS for "major Federal actions significantly affecting the 
quality of the human environment ...." 42 U.S.C. §§ 4332(2)(C). CEQ's 
NEPA regulations are set forth at 40 C.F.R. Part 1500 et seq.; FAA's 
NEPA requirements and guidance are set forth in FAA Order 1050.1E and 
in the FAA Airspace Redesign Handbook. 

[116] 40 C.F.R. § 1502.13. 

[117] 42 U.S.C. § 4332(2)(C)(iii); 40 C.F.R. § 1502.14. 

[118] 42 U.S.C. § 4332(2)(C)(ii); 40 C.F.R. §§ 1502.16, 1508.7, 1508.8. 

[119] 40 C.F.R. § 1506.6. 

[120] Executive Order 12898, Sec. 1-101. 

[121] Agency compliance with NEPA is evaluated according to § 10 of the 
Administrative Procedure Act (APA), 5 U.S.C. § 706, which provides that 
a court may "hold unlawful and set aside agency action, findings, and 
conclusions found to be arbitrary, capricious, an abuse of discretion 
or otherwise not in accordance with the law." This standard grants 
deference to agency decisions, with courts presuming that an agency's 
action is valid. See Vermont Yankee Nuclear Power Corp. v. NRDC, 435 
U.S. 519 (1978); Citizens to Preserve Overton Park v. Volpe, 401 U.S. 
402 (1971); City of Olmsted Falls v. FAA, 292 F.3d 261 (D.C. Cir. 
2002); North Slope Borough v. Andrus, 642 F.2d 589 (D.C. Cir. 1980). To 
determine whether an agency's action was "arbitrary or capricious," 
courts assess whether the agency came to grips with the obvious 
ramifications of its approach and addressed them in a reasoned fashion. 
See NRDC v. EPA, 859 F.2d 156 (D.C. Cir. 1988). This requires an 
examination of the relevant data and an articulation of a satisfactory 
explanation for its action--including "a rational connection between 
the facts found and the decision made." Id. at 209 (citations omitted). 
In the NEPA context, this "arbitrary and capricious" standard has been 
interpreted as requiring an agency act reasonably in carrying out 
NEPA's requirements (applying a "rule of reason") or that an agency 
take a "hard look" at the environmental consequences of its proposed 
actions. See, e.g., Citizens Against Burlington, 938 F.2d at 196 
(upholding FAA approval of airport expansion); City of Grapevine v. 
DOT, 17 F.3d 1502, 1504 (D.C. Cir. 1994), cert. denied, 513 U.S. 1043 
(1994) (same). As long as an agency meets this standard, a court should 
not substitute its own judgment, and the agency's action should be 
affirmed. Kleppe v. Sierra Club, 427 U.S. 390, 410 n.21 (1976) 
(upholding the Department of the Interior's decision not to conduct 
comprehensive EIS on speculative proposals). In addition to its basis 
in the APA, this deference stems from NEPA's imposition of procedural 
rather than substantive requirements--NEPA's purpose is to ensure that 
government agencies consider environmental consequences and act on full 
information, and that interested groups have access to such 
information, but NEPA does not mandate a particular environmental 
result. Sierra Club v. United States Forest Service, 46 F.3d 835, 837 
n.2 (8th Cir. 1995). "Once an agency has made a decision subject to 
NEPA's procedural requirements, the only role for a court is to insure 
that the agency has considered the environmental consequences ..." 
Strycker's Bay Neighborhood Council, Inc. v. Karlen, 444 U.S. 223, 227- 
28 (1980). 

[122] See Administrative Record, Document No. 9358, MITRE Report, 
"Eastern U.S. Problem Assessment and Multi-Cen." Among other things, 
MITRE modeled and simulated all alternatives for the airspace redesign 
project. 

[123] Draft EIS, p. 2-2; final EIS, p. 2-2. 

[124] A TRACON is an air traffic control facility that uses radar and 
two-way radio communication to separate air traffic within a specific 
geographic area in the vicinity of one or more large airports. 

[125] Final EIS pp. 1-25. 

[126] Final EIS pp. 1-21. In 49 U.S.C. § 40101(d), Congress declared 
national policy to be that FAA shall: "(1) assign, maintain, and 
enhance safety and security [as] the highest priorities in air 
commerce; ...and (4) control the use of the navigable airspace and 
regulate civil and military operations in that airspace in the interest 
of the safety and efficiency of both of those operations ...." 
(Emphasis added.) 

[127] See [hyperlink, http://www.faa.gov/about/mission/] (accessed on 
May 5, 2008). FAA has certain general noise reduction authority, see 14 
C.F.R. Part 150, but noise reduction is not part of FAA's statutory 
mission. 

[128] See S. Rep. No. 108-146, at 22 (2003), accompanying S. 1589 ("As 
FAA moves forward with its redesign program in the New York/New Jersey 
and Philadelphia area, the Committee encourages FAA, where appropriate, 
to consider air noise impacts as part of the redesign effort."). See 
also S. Rep. No. 107-224, at 43 (2002), accompanying S. 2808. 
Additionally, certain appropriations committee reports stated that FAA 
may not use funds for its New York/New Jersey/Philadelphia redesign 
NEPA review "as long as the FAA fails to consider noise mitigation," 
see H.R. Rep. No. 108-792, at 1366 (2004), accompanying H.R. 4818. See 
also H.R. Rep. No. 109-307, at 136 (2005), accompanying H.R. 3058; H.R. 
Rep. No. 109-307, at 136 (2005), accompanying H.R. 3058. Cf. H.R. Rep. 
No. 108-671, at 16 (2004), accompanying H.R. 5025 (stating FAA may not 
use funds for NEPA review of New York/New Jersey/Philadelphia redesign 
"unless the FAA formally declares noise mitigation to be a primary 
objective of the redesign project.") (statement not included in 
conference report). 

[129] Final EIS, pp. 1-25, 1-26. 

[130] Final EIS, p. ES-2. 

[131] Noise Mitigation Report, FAA, Apr. 6, 2007. 

[132] Final EIS, pp. 1-26. 

[133] Final EIS, pp. 2-8. 

[134] The experts we interviewed also found that FAA's purpose and need 
statement was reasonable and that the agency did not need to include 
noise or environmental concerns in its objectives. 

[135] See footnote 16 above. 

[136] Final EIS, p. ES-2. 

[137] Final EIS, p. 2-8. 

[138] Final EIS, p. 2-9. 

[139] Final EIS, p. 2-9. 

[140] These objectives included reducing airspace congestion, reducing 
environmental impacts, where possible, and accommodating projected 
growth. Final EIS, pp. 2-9 - 2-11. 

[141] The alternatives considered in detail were the Future No Action 
Airspace Alternative (required by NEPA), the Modifications to Existing 
Airspace Alternative, the Ocean Routing Airspace Alternative, and the 
Integrated Airspace Alternative Variation with, and without, Integrated 
Control Complex (ICC) (ICC refers to a common automation platform). 
Final EIS, p. ES-4. FAA considered the Ocean Routing Alternative, even 
though it did not meet the purpose of increasing the efficiency and 
reliability of the New York/New Jersey/Philadelphia airspace, because 
of long-standing concerns of New Jersey Citizens Against Aircraft 
Noise, a citizens group. Final EIS, pp. 2-10, 2-11. 

[142] App. IV to this report describes the selected project in more 
detail. 

[143] Operational viability refers to whether a particular airspace 
redesign is workable and thus safe; criteria include reduced airspace 
complexity and reduced voice communications. Operational efficiency 
refers to how well a particular design works; criteria include reducing 
delay, balancing controller workload, meeting system demand, improving 
user access to the system, expediting arrivals and departures, 
increasing flexibility in routing, and maintaining airport throughput 
(throughput is explained in note 36 below). 

[144] Final EIS, Chapter 4. 

[145] 40 C.F.R. § 1502.14(d). 

[146] 40 C.F.R. § 1502.14(c). 

[147] Although we conclude FAA's selection and analysis of alternatives 
met the legal requirements of NEPA, we nevertheless have identified 
deficiencies in FAA's analysis. See pp. 36-45 of this report. 

[148] Final EIS, Appendix N, p. 1164. FAA further explained: 
"Throughput is not the same as capacity. Throughput is the actually 
achieved number of aircraft using a resource in a given time. It is 
measured by counting aircraft, whether in a real system or a simulated 
one. Capacity is the theoretical maximum number of aircraft that could 
use a resource in a given time. It is measured by surveying, queuing 
simulations, or mathematical models. A decrease in throughput does not 
mean a reduction in the number of flights; it means that delays 
increase. Likewise, an increase in throughput does not mean an increase 
in flights, it means a decrease in delays. When throughput is below 
capacity, the system is inefficient. Reducing the difference between 
the throughput and the capacity is the purpose of this airspace 
redesign ...." Id. 

[149] See Administrative Record Document No. 8239, Meeting minutes with 
NY DOT, Dec. 17, 2003 ("airspace redesign is not related to increasing 
capacity because the capacity of the system is currently limited by the 
pavement (runways) at the airports. Airspace redesign produces a more 
efficient system and reduces delay."). 

[150] While we believe FAA's decision not to assess environmental 
impacts from possible growth from the redesign would likely survive 
challenge as a legal matter, particularly given the deferential 
standard of review, we nevertheless find FAA's induced-growth analysis 
contained several limitations, as discussed at pp. 36-40 of this 
report. 

[151] 40 C.F.R. § 1501.7. 

[152] 40 C.F.R. § 1506.6(a). 

[153] 40 C.F.R. § 1506.6(b). 

[154] 40 C.F.R. § 1506.6(c). 

[155] 40 C.F.R. §§ 1503.1(4), 1506.6(d). 

[156] 40 C.F.R. § 1503.4(a). 

[157] FAA Order 1050.1E, § 208b. 

[158] FAA Order 1050.1E, §§ 208d, 508(g). 

[159] FAA Order 1050.1E, § 208c. 

[160] FAA Order 1050.1E, § 505a. 

[161] FAA Order 1050.1E, § 208c. 

[162] Final EIS Table 6.1; Record of Decision, pp. 28, 48. 

[163] A summary of the public comments and FAA's responses to these 
comments are contained in appendices N and Q of the final EIS. 

[164] Additional detail on the public comment periods is contained in 
table 1, p. 26. 

[165] See final EIS, appendices N and Q. 

[166] DOT Order 5610.2; 62 Fed. Reg. 18377 (Apr. 15, 1997). 

[167] CEQ Guidance, p. 5. 

[168] CEQ Guidance, p. 8. 

[169] CEQ Guidance, p. 10. 

[170] CEQ Guidance, p. 9. 

[171] Presidential Memorandum, p. 1. 

[172] CEQ Guidance, p. 9. 

[173] CEQ Guidance, pp. 10-11. 

[174] CEQ Guidance, p. 11. Examples of how agencies should enhance 
their outreach include the use of religious organizations, newspapers, 
radio, and other media, civic associations, community and social 
service organizations, labor organizations, and the internet and other 
electronic media. 

[175] CEQ Guidance p. 12. 

[176] CEQ Guidance, p. 13. 

[177] CEQ Guidance, p. 13. 

[178] CEQ Guidance, p. 13. 

[179] CEQ Guidance, p. 13. 

[180] CEQ Guidance, p. 13. 

[181] CEQ Guidance, pp. 15-16. 

[182] FAA first identified the census blocks significantly impacted by 
aircraft-related noise and determined the minority composition and 
median income of those census blocks based on prospective census data 
for 2011. See final EIS, tables 3.8, 3.9, showing minority populations 
in the study area and poverty population statistics. To determine 
whether there would be a high and adverse impact to a low-income 
community, the median income of the significantly impacted census 
blocks was compared to the poverty-level income. Additionally, FAA used 
CEQ's definition of a minority population. FAA then determined whether 
a low-income or minority community subjected to a high and adverse 
human health or environmental impact was disproportionately affected, 
deemed to occur when an environmental impact is either predominantly 
borne by a low-income or minority population or is more severe in 
magnitude than the impact on the non-low-income or nonminority 
populations. See final EIS, pp. 4-43, 4-44. 

[183] See final EIS, Chapter 4 and Appendix I. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: