OPERATING EXPERIENCE WEEKLY SUMMARY 93-42
                       October 15 through 21, 1993


     The purpose of the Office of Nuclear Safety (NS) Operating Experience (OE) Weekly
     Summary is to enhance safety throughout the Department of Energy (DOE) complex
     by promoting feedback of operating experience and encouraging the exchange of
     information among DOE nuclear facilities.  The OE Weekly Summary is distributed
     for information only.  No specific actions or responses are required solely as a
     result of this document.

     Readers are cautioned that review of the OE Weekly Summary should not be relied
     upon as a substitute for a thorough review of the interim and final Occurrence
     Reports.

     The following events were reviewed during the week of October 15 through 21, 1993.

    ITEM                                               PAGE

    1. LOSS OF AIR HANDLING SYSTEMS                        2
    2. RADIOACTIVE CONTAMINATION OF WRISTS                2
    3. SUSPECT/COUNTERFEIT PARTS                          4
    4. FIRE ON ROOF OF ERWIN URANIUM FUEL FABRICATION FACILITY      5
    5. WATER MAIN RUPTURED BY BACKHOE                     6


    ADDITIONAL INFORMATION RELATED TO FOLLOWUP ACTIVITIES

    1. UPDATE ON RADIOACTIVE LEAD SHIPMENT TO SMELTING COMPANY      7
    2. ADDITIONAL INFORMATION FROM UNITED KINGDOM OPERATING 
       EXPERIENCE                                         8


    FINAL REPORTS - SUMMARIES

    1. FINAL REPORT ON EMERGENCY GENERATOR BATTERY CHARGING 
       SYSTEM EVENT AT ROCKY FLATS BUILDING 559         10
    2. FINAL REPORT ON THE DIESEL GENERATOR EVENT AT 
       ROCKY FLATS BUILDING 779                         11







    1. LOSS OF AIR HANDLING SYSTEMS

       On October 19, 1993, a worker at the Mound Plant inadvertently cut the pneumatic air
       control lines for Building 50 ventilation dampers, causing the ventilation system to shut
       down.  This caused the loss of differential pressure control within the remaining facility
       which violated a limiting condition of operation.  Facility personnel discontinued all work
       when the violation occurred in accordance with the limiting condition-of-operation action
       statement.  The worker was removing obsolete equipment in accordance with an
       approved work package when the lines were cut.  At the time of the event, there were
       no operations involving plutonium, and no material was released.  Continuous air
       monitors and the stack monitor remained operational.

       Prior to the event, the worker received a work package that included photographs
       depicting the equipment to be removed.  Facility personnel have not determined whether
       the worker performed an activity outside the scope of the work package or if the work
       package was deficient.  They convened a formal investigation committee to determine
       the root, direct, and contributing causes of the occurrence.

       There have been numerous cases at DOE facilities where work was performed outside
       the scope of maintenance or modification packages or where work packages were not
       explicit.  The incidents resulted in workers inadvertently cutting energized wires, core
       drilling into electrical conduit, and performing unauthorized modifications to systems. 
       These events continue to emphasize the need for thorough work planning and control. 
       Unplanned, negative consequences to facility safety and operation can be avoided by
       fully understanding the potential effects of planned work on interrelated systems and
       components.  In addition, these events underscore the importance of staying within the
       scope of approved work documents.  Workers need to have a thorough understanding
       of the bounds of work activity prior to initiating work.


    2. RADIOACTIVE CONTAMINATION OF WRISTS

       On October 15, 1993, fixed and loose alpha skin contamination measured at up to 10,000
       dpm/100cm2 was detected on each wrist of an employee at the Oak Ridge Y-12 Plant. 
       After repeated washings, one wrist was wrapped because 1,200 dpm/100cm2 fixed
       contamination remained on it.  The contamination was below the Y-12 Plant action limit
       of 1,000 dpm/100cm2 within two days.  A whole-body count indicated no internal
       contamination, and the results were being confirmed by urinalysis.  (ORPS Report ORO--
       MMES-Y12DEFPGM-1993-0089)

       Facility personnel reconstructed the worker's activities and determined that he probably
       became contaminated the previous day while filling bottles with uranium solution. 
       However, the contamination was not detected during exit frisking with a hand-held survey
       instrument nor by a hand monitor, both of which were located at the boundary control
       station.  After discovering the contamination during a routine survey the next day, health
       physics technicians instructed the employee to wash his wrists.  After two washings,
       4,000 dpm/100cm2 fixed contamination remained on the right wrist.  Health services
       personnel performed further decontamination efforts on the individual that lowered the
       contamination on the wrist to 1,200 dpm/100cm2, and covered the wrist with wrapping. 
       As a precautionary measure, health physics personnel surveyed the employee's home,
       clothing, and automobile and found contamination measuring 400 dpm/100cm2, which is
       below the plant limit, on the cuffs of the shirt worn the day before.

       Facility personnel investigated the incident and determined that the uranium solution
       probably splashed onto the worker's rubber gloves, spread to the surgical gloves
       underneath, and was deposited on the wrists while he removed the gloves.  Site
       personnel indicated the worker was not wearing plastic sleeves on his wrists, which would
       have provided additional protection.  Facility personnel did not determine why the
       contamination was not detected.  The worker was surveyed at the boundary control
       station by another individual using a hand-held frisker, a technique referred to as the
       buddy system.  The hand monitor, also at the boundary control station, surveys only what
       is placed on top of it, which is normally only the hand.  To minimize the potential of a
       similar event, facility personnel planned to implement the use of plastic wrist sleeves
       when filling bottles with uranium solution and to conduct classes on proper removal of
       anti-contamination clothing.

       Personnel at other DOE facilities reported many other instances of wrist contaminations. 
       The wrist area is particularly susceptible to contamination because it is frequently close
       to contaminated materials and is at a transition point for anti-contamination clothing, often
       becoming exposed.  Wrist contaminations have been caused by careless removal of
       protecting clothing, insufficient protective clothing, inadequate taping of gloves, and
       extreme heat and perspiration that caused tape and gloves to loosen.  In some cases,
       formal written procedures defining minimum protective clothing for certain operations were
       not in place.

       These events underscore the need for personnel at DOE facilities to ensure that the wrist
       area is adequately protected for the work being performed.  Personnel should use extra
       protective clothing, such as multiple layers of gloves and plastic sleeves, when the
       potential for wrist contamination is high; management should formally define the need for
       extra clothing for particular tasks when practical.  Workers should also use caution when
       removing anti-contamination clothing, particularly gloves, to prevent transferring
       contamination from protective clothing to the skin.  Appendix 3C of DOE/EH-0265T,
       Radiological Control Manual, provides guidelines on selection and removal of protection
       clothing, including detailed sequences for removing a full and double set of protective
       clothing.  Appendix 3D provides guidelines for personnel monitoring with hand-held
       survey instruments which, according to the Appendix, should be posted adjacent to
       monitoring instruments in accordance with Article 338.8 of the Manual.

       While reviewing this event, NS noted that Y-12 management recently changed
       radiological conduct practices to improve detection of contamination mechanisms. 
       Previously, workers washed their hands before surveying for contamination.  Current
       practice is to survey before washing, which, although resulting in an increased number
       of identified and reported contamination-related occurrences, is helping facility personnel
       to identify contamination sources and reduce actual contamination events.





    3. SUSPECT/COUNTERFEIT PARTS

       NS reviewed six incidents reported between October 18 and 20, 1993, involving
       identification of suspect/counterfeit equipment at DOE facilities.  On October 18, Johnson
       Controls, Inc., personnel at Oak Ridge National Laboratory (ORNL) reported discovering
       suspect fasteners on a snap-on puller cab, a crane, and a compressor.  The suspect
       fasteners were grade 5 and 8 bolts with KS, A, hollow triangle, and blank head markings. 
       Facility personnel replaced the bolts on the puller cab, and removed the other equipment
       from service until the suspect bolts were replaced.  (ORO--JCI-JCI2005HES-1993-003/4/5)

       On October 19, warehouse personnel at the Pantex Plant identified a lot of 300 suspect
       fasteners (nuts) received on September 29, 1993, from a distributor in Chicago along with
       the manufacturer (San Shing, Taiwan) inspection certificate.  Pantex procurement
       department personnel contacted the DOE Albuquerque Operations Office in reference to
       foreign-made fasteners and were advised that fasteners manufactured by Pacific rim
       countries should be considered suspect.  The fasteners were segregated and secured
       in a locked cabinet until they were either destroyed or proven to meet applicable
       standards.  (ALO-AO-MHSM-PANTEX-1993-0056)

       On October 19, personnel at ORNL reported discovering suspect fasteners in equipment
       located in a general stores building.  The suspect fasteners were discovered on a sliding
       door support, a manlift, and racks supporting spools of electrical cables.  Most of the
       suspect fasteners discovered at ORNL were grade 5 and 8 fasteners with KS head
       markings.  Fasteners with hollow triangle, J, and blank head markings have also been
       discovered at ORNL.  Facility personnel reported that skilled craftsmen at ORNL are
       trained to identify suspect fasteners and are involved along with the Quality Department
       in the effort to remove suspect parts from service.  As an example of their contribution,
       craftsmen voluntarily inspected and purged bench stock at several workstations of known
       suspect fasteners.  (ORO--MMES-X10QUALITY-1993-0001/3/4/5)

       On October 18, 1993, Quality Assurance personnel at the Hanford 100 Area K-Basins
       discovered that the original factory markings on three piping unions were stamped over
       with suspect hand tool markings.  Facility personnel issued a non-conformance report to
       document the potentially fraudulent material and returned the rejected material to the
       vendor.

       These events illustrate the increasing level of awareness at DOE facilities of the potential
       for counterfeit and suspect parts and the importance of identifying them and removing
       them from service.  Increased awareness and efforts on this issue is important because
       failure of deficient fasteners could result in personnel injury, equipment damage, or failure
       of nuclear safety-related equipment designed to prevent or mitigate the consequences
       of an accident.  As demonstrated at ORNL, training as many people as possible to
       identify suspect/counterfeit parts will help raise awareness and expedite the identification
       and removal of such parts, resulting in improved safe operation of DOE facilities.

       In previous OE Weekly Summaries, NS referenced various DOE and commercial industry
       documents related to identifying, assessing, and disposing of suspect and counterfeit
       fasteners (OEWSs 92-11,12,14,16,25,26, 93-05,11,20,26,30,40).  Environment, Safety, and Health
       Bulletin 92-4 (DOE/EH-0266), Department of Energy (DOE) Quality Alert -- Counterfeit
       Parts, provides guidance on identification, testing, precautions, and disposition of suspect
       counterfeit fasteners and electrical circuit breakers at DOE facilities.  NRC Generic Letter
       89-02 Actions to Improve the Detection of Counterfeit and Fraudulently Marketed
       Products, provides information on programs that the Nuclear Regulatory Commission
       considered effective in detecting counterfeit or fraudulently marked products and assuring
       the quality of procured products.  The document also lists numerous NRC Bulletins and
       Information Notices concerning non-conforming materials and equipment and instances
       of inadequate dedication of equipment for safety-related applications.  Other related
       documents include:

          General Accounting Office Report RCED-91-6, Nuclear Health and Safety:
           Counterfeit and Substandard Products Are a Government Wide Concern;
          Industrial Fasteners Institute Research Report, False Grade 8 Engineering
           Performance Marks on Bolting and Improper Marking of Grade 8 Nuts; and
          Customs Service Report, Fastener Identification Markings.


    4. FIRE ON ROOF OF ERWIN URANIUM FUEL FABRICATION FACILITY

       On October 13, 1993, personnel at the Uranium Fuel Fabrication facility in Erwin,
       Tennessee, declared an alert when a fire occurred on the roof of a building containing
       uranium processing equipment.  At the time of the event, workers were heat sealing
       rubberized material on the roof, and, during this process, the fiberboard or wood ignited. 
       Facility personnel reported that the smoke was drawn into the building because of the
       negative pressure maintained in the building.  No radioactive materials were released. 
       Site personnel quickly extinguished the fire and downgraded the event to an unusual
       event in accordance with the emergency plan.  (NRC Event 262215)

       There have been similar events at DOE facilities involving maintenance activities on roofs
       that resulted in fires.

          On April 8, 1993, a worker at the Sandia National Laboratory was using a high-
           speed metal saw to cut corrugated metal panels on a supply air fan penthouse on
           a roof when the fiberglass insulation began to smolder.  The worker and his
           foreman did not adequately plan and discuss the potential problems and
           implications of cutting through fiberglass insulation with a high-speed metal saw
           blade.  In this instance, the fiberglass insulation backing on the panels should have
           been pulled away from the metal prior to the cutting procedure.  (ORPS Report ALO-
           KO-SNL-NMFAC-1993-0007)

          On May 29, 1991, sparks from workers welding structural supports on a roof at the
           Princeton Plasma Physics Laboratory caused roof insulation to smolder. 
           Investigators determined the "Hot Flame Permit" for welding was issued without
           considering the effect the welding might have on combustible material that was part
           of the roof.  The combustible material was on the opposite side of the corrugated
           metal roof material, which was itself next to the welding operation.  Either heat
           conduction or sparks started a small fire.  (ORPS Report CH-PA-PPPL-PPPL-1991-1009)

          On March 21, 1991, personnel at the Fernald site using an oxygen/acetylene torch
           ignited foam insulation during permitted work on a roof penthouse floor of a
           laboratory building.  Event investigators determined that the fire blanket was
           inadequate to prevent total spark penetration and the crawl-space type environment
           prevented full view of the cutting area by the fire watcher, contributing to the cause
           of the fire.  (ORPS Report ORO--WMCO-FEMP-1991-0019)

          On September 19, 1990, Idaho Chemical Processing Plant workers were welding
           heating and ventilation equipment on the roof of the Process Improvement facility
           when roof insulation caught fire.  Facility personnel determined that the workers
           failed to provide adequate shielding over the opening between the roof flashing and
           the structural steel penetrating the roof.  As a result, weld spatter entered the
           opening and ignited the roof insulation.  (ORPS Report ID--WINC-ICPP-1990-0004)

       These events underscore the importance of fire hazard permits and proper planning of
       work activities when cutting, welding, or grinding on roofs.  For these activities, workers
       should be trained in the hazards of welding and flame cutting and the duties of a fire
       watch.


    5. WATER MAIN RUPTURED BY BACKHOE

       On October 18, 1993, a worker at the Los Alamos National Laboratory ruptured a ten-
       inch water main, releasing approximately 40,000 gallons of potable water.  The 100
       pounds per square inch of water pressure from the ruptured pipe caused rocks and water
       to hit a nearby building, breaking window glass, causing water damage to the interior of
       the building, and slightly injuring a worker standing nearby.  Water also sprayed onto the
       roof and entered the building through air conditioning ducts, soaking ceiling tiles and
       accumulating on floors.

       Workers were conducting maintenance on an underground gas line when the incident
       occurred.  They had located the water main below and perpendicular to the gas line, but
       the spotter and backhoe operator were unaware of an abandoned valve extending from
       the main.  The backhoe snagged the valve, causing the rupture.  Workers shut off the
       water supply which caused a water outage that affected the building fire protection
       system.  Facility personnel classified the event as an unusual occurrence because of the
       performance degradation of the fire protection system.  (ORPS Report ALO-LA-LANL-
       SERVICESS-1993-0027)

       Numerous events were reported by DOE facilities involving damage to underground
       cable, piping, conduits, and structures during excavations.  NS reported many of these
       occurrences in previous OE Weekly Summaries.  Several of the events in this category
       could have resulted in personnel injury.

          On September 16, 1993, personnel at the Idaho Chemical Processing Plant
           discovered that a worker had severed the 480-volt buried cable with a fence post. 
           The cable supplied temporary power to a crane.  Workers installing the fence posts
           apparently did not properly check the excavation permit prior to driving the posts. 
           In addition, the cable was buried only two feet deep and was not identified by
           marker flags.  (ORPS Report ID--MKF-MKNE-1993-0001)
    
          On September 15, 1993, at the Savannah River Effluent Treatment Facility, a
           worker damaged an underground pipe while drilling for a soil sample.  Facility
           personnel conducted a critique and determined that the causes included failure to
           prepare an excavation permit, relocation without proper follow-up of the drilling
           stakes approximately 20 feet south of the originally surveyed location, and lack of
           established work control procedures.  (SR--WSRC-ETF-1993-0005)

          On October 10, 1992, personnel at the Los Alamos National Laboratory ruptured
           an underground natural gas line with a backhoe.  Even though workers obtained
           an approved excavation permit and all utilities were properly marked for location,
           depth of the piping could not be properly measured with available instruments and
           facility personnel failed to follow procedures requiring manual exploration prior to
           machine excavation.  Piping was buried only 10 to 12 inches below the surface. 
           (ORPS Final Report ALO-LA-LANL-PHYSTECH-1991-1009)

          On September 14, 1992, an underground natural gas pipeline ruptured when it was
           struck by a backhoe during an electrical utility relocation project at the Lawrence
           Livermore Berkeley Laboratory.  Facility personnel previously surveyed the area for
           underground obstructions in accordance with procedures, but a change in the job
           order altered locations.  The workers failed to survey the new area and
           subsequently punctured an underground gas line with the back hoe.  (ORPS Report
           SAN--LBL-OPERATIONS-1992-0007)

          On September 20, 1991, at the Grand Junction Operations facility, a worker
           severed a 13,000-volt underground power cable one foot below the surface while
           removing mill tailings at a Uranium Mill Tailings Remedial Action Site.  Facility
           drawings incorrectly showed the cable buried 4 feet deep and encased in concrete. 
           (ORPS Report ID--GEO-GJO-1991-1019)

       Occurrence reports describing similar events note that facility procedures do not always
       require documentation of temporary utilities or excavation permits for all excavation work. 
       These events demonstrate the necessity to thoroughly investigate the possibility of
       underground obstructions prior to commencing excavations.  A review of plant facility
       drawings may not be adequate for locating underground cables, conduits, tanks, or
       piping.  In addition, personnel may not be able to obtain information from record drawings
       necessary to assure correct marking of buried utilities.  Workers should use hand tools
       to excavate around utilities.  Security and telecommunication personnel should be
       consulted prior to commencing digging operations for assistance in locating buried
       components.  Facility personnel should assure that procedures controlling excavations
       provide detailed instructions concerning steps associated with the location of underground
       obstructions.


    ADDITIONAL INFORMATION RELATED TO FOLLOWUP ACTIVITIES


    1. UPDATE ON RADIOACTIVE LEAD SHIPMENT TO SMELTING COMPANY

       NS reported an event in OE Weekly Summary 93-41 that occurred on October 4, 1993,
       at the Argonne National Laboratory - East facility.  Personnel discovered that
       approximately 250,000 pounds of scrap lead was shipped to a commercial smelting
       company without a Health Physics review.  Heath Physics personnel performed a survey
       of the remaining material at the lead storage facility and identified lead bricks with
       activation levels as high as 1x10-10 curies/gram.  NS reported that approximately 40,000
       pounds of the scrap shipped off site was not smelted and that it would be surveyed by
       Health Physics personnel prior to further processing.  On October 15, 1993, NS received
       updated information that no contamination/activation was detected on the remaining scrap
       material.  Facility personnel stated that determination of the root cause, corrective
       actions, and lessons learned is still being investigated.  (ORPS Report CH-AA-ANLE-ANLESSD-
       1993-0001)


    2. ADDITIONAL INFORMATION FROM UNITED KINGDOM OPERATING EXPERIENCE

       As part of an cooperative information-sharing agreement between the United States
       Department of Energy and the United Kingdom, the operating experience information
       presented in this section was excerpted from the Statement of Nuclear Incidents at
       Nuclear Installations published by the Health and Safety Executive, London, England. 
       The report describes incidents at nuclear installations during the second quarter of 1993. 
       A copy of the entire news release may be obtained by contacting:  Library, Health and
       Safety Executive, Room 021, Baynards House, 1 Chepstow Place, London W2 4TF,
       telephone 011-44-071-243 6000, fax 011-44-071-727 6268.


       1.  INCIDENT 93/2/1

           WINDSCALE AND CALDER WORKS (BRITISH NUCLEAR FUELS)

           On 18 May 1993 a planned inspection was carried out of the drums stored in
           a building known as B300 on the Sellafield site and a pool of syrupy liquid was
           observed on the floor.  The liquid appeared to originate from a single drum but
           two adjacent drums were also affected.  The drums concerned were of mild
           steel construction and contained plutonium contaminated waste arising from
           operations on the site.  No release of airborne activity had occurred nor was
           there any contamination of personnel.

           Following discovery of the event, BNFL made arrangements to sample the
           liquor and prevent any further spread beyond the already affected area.  The
           analysis of the liquor indicated that approximately 0.5 TBq (unquote: or 13.5
           curies) of alpha activity had leaked out.  This quantity is in excess of column
           7 of Schedule 2 of the Ionising Radiations Regulations 1985.  The event was
           reported to the HSE's Nuclear Installations Inspectorate (NII) on the evening
           of 18 May and subsequently to the President of the Board of Trade.  BNFL
           classified the incident as International Nuclear Event Scale (INES) Level 2.

           During the next few days BNFL carried out detailed investigations to establish
           the drum history and the material present in each drum.  In addition the
           sequence of recovery operations and decontamination of the area was
           planned.  A methodology was established and the safety implications
           considered by BNFL in accordance with conditions attached to the nuclear site
           license.  The operations to recover the drums were successful and the
           affected area decontaminated.  The leaking drum has been doubly contained
           and along with the two other drums placed in an area removed from other
           drums within the store and where regular inspection can be undertaken.  No
           contamination of personnel occurred during these recovery operations which
           were completed on 4 June 1993.

           BNFL have investigated the cause of the incident and NII are monitoring the
           investigation and will follow up on actions arising from the BNFL report and
           their own studies.


       2.  INCIDENT 93/2/4

           CHAPELCROSS (BRITISH NUCLEAR FUELS)

           During refuelling operations on 26 May 1993 on Reactor 2 an employee was
           momentarily exposed to radiation from an irradiated fuel element during an
           unusual sequence of operations which followed from a component failure on
           the grab in the fuelling machine which is used to handle fuel elements.

           An investigation by HSE's Nuclear Installations Inspectorate (NII) has shown
           that the unusual sequence of operations, although permitted by written
           operating instructions, challenged the installed system of plant interlocks to the
           extent that they failed to prevent radiation exposure to the employee. 
           Modifications to the plant and changes to working procedures are now to be
           made to prevent similar occurrences.

           It is fortunate that the employee only incurred a radiation dose of 1.1 mSv
           during this deviation from normal operation practice.  (The annual legal dose
           limit to the whole body as set out in schedule 1 part 1 of the Ionising Radiation
           Regulations 1985 is 50 mSv with an overall requirement also to keep radiation
           exposure as low as is reasonably practicable).


       3.  INCIDENT 93/2/5

           SELLAFIELD (BNFL)

           The last quarterly statement of incidents set out the circumstances of an
           incident at BNFL Sellafield, in which a Quality Assurance Inspector sustained
           a cut to his elbow, whilst inspecting a weld in an enclosed cell on a plutonium
           transfer line.  At that time, biological monitoring was still in progress and it was
           not possible to provide an assessment of the dose he had received.  This
           work has now been completed and BNFL have reported that the person
           concerned has received a committed dose equivalent to the bone surfaces of
           628.6 mSv.  This is in excess of the annual dose limit for a single organ as set
           out in schedule 1 part II of the Ionising Radiations Regulations.


           The Nuclear Installations Inspectorate has conducted its own review of the
           incident and concurs with BNFL that the most likely cause was the presence
           of a sliver of glass, of unknown origin, in the working environment.  NII have
           concluded that no further regulatory action is warranted in this instance.


       Note:
       The International Event Scale referenced in the Health and Safety Executive document
       was designed by an international group of experts convened jointly by the International
       Atomic Energy Agency and the Nuclear Energy Agency of the Organization for Economic
       Co-operation and Development.  The purpose of the Scale is to promptly and consistently
       communicate to the public the safety significance of reported events at nuclear
       installations.  Events are classified at seven levels, with lower levels 1 through 3 termed
       incidents and upper levels 4 through 7 termed accidents.  Events that have no safety
       significance are classified as level 0/below scale and are termed deviations.  Each level
       has specific criteria relating to events in terms of off-site impact, on-site impact, and
       defense-in-depth degradation.  Examples of classified events include the 1986 Chernobyl
       accident (level 7), the 1979 Three Mile Island accident (level 5), and the 1989 fire at the
       Vandellos nuclear power plant in Spain (level 3).



    FINAL REPORTS - SUMMARIES

       This section of the OE Weekly Summary discusses events that have been filed as Final
       reports on the ORPS. These events contain new or additional lessons learned that may
       be of interest to personnel within the DOE complex.  The description of each event, its
       causes and lessons learned are edited from the original ORPS Final report.


    1. FINAL REPORT ON EMERGENCY GENERATOR BATTERY CHARGING SYSTEM
       EVENT AT ROCKY FLATS BUILDING 559

       On June 22, 1993, two maintenance electricians at Rocky Flats Building 559 discovered
       an out-of-tolerance float current supplied to batteries that provide current for starting the
       emergency diesel generator.  Facility personnel measure the float current monthly as part
       of the limiting condition-of-operation surveillance on the emergency diesel generator.  The
       current flow rate was 953 milliamp (mA), which exceeded the charging current
       parameters of 21 and 479 mA.  Incident investigators attributed the direct cause to an
       external phenomenon when a high ambient temperature caused a high charging current
       to the emergency diesel starting batteries.  They determined that a contributing cause of
       this occurrence was an inadequate procedure that did not clarify the fact that a high
       current charge rate alone cannot be indicative of a degradation in long term battery
       condition and performance without some indication of low cell voltage.  Facility personnel
       initiated one of the corrective actions to issue a document modification request requiring
       a reading of battery cell voltages when the battery charger current flow rate exceeds the
       upper tolerance limit of 479 mA.  (ORPS Reports RFO--EGGR-ANALYTOPS-1993-0088)

       Another corrective action involved distribution of a lessons learned letter to address the
       issues identified as a result of this incident.  The following was excerpted from the letter.

           The batteries and associated charger were replaced during the Resumption
           effort, and utilize a maintenance-free style of battery.  Manufacturers
           recommendations are used to describe the expected parameters for an
           acceptable surveillance.  There have been numerous surveillance failures
           caused by the lack of definition of appropriate criteria in the surveillance
           procedures.  This is another example of that same problem.  The procedure
           acceptance criteria for float current were carefully addressed for the very low
           current values experienced at optimum conditions, because of previous
           experience with measuring very low currents.  The minimum value was
           established as just above the minimum capability of the measurement device
           to confirm that current flow existed.  The upper value was established based
           exclusively on the manufacturers calculated value for optimal conditions, and
           no allowance was taken for fluctuations in ambient conditions.

           This occurrence pointed out that additional data must be gathered if the float
           current is above the optimal value, so that the time operability of the starting
           batteries can be determined.  In this case the ambient temperature of the
           room was higher than normal, and the float current was responding to battery
           bank current demand.  Subsequent battery cell tests indicated that the
           batteries were in a fully operable condition.  The procedure was revised to
           incorporate appropriate tests if float current is found above optimal value. 
           Surveillance procedures of Preventive Maintenance procedures must
           incorporate an adequate set of tests to verify the operability of equipment, and
           must not only repeat manufacturers recommendations that are normally based
           on a given set of conditions.


    2. FINAL REPORT ON THE DIESEL GENERATOR EVENT AT ROCKY FLATS BUILDING
       779

       On June 15, 1993, operators at Rocky Flats Building 779 observed unacceptable
       fluctuations in the speed of the emergency diesel engine.  They classified the event as
       an unusual occurrence because of degradation of Class A equipment.  Incident
       investigators attributed the direct cause to deficiencies in the design of the diesel fuel
       transfer system that caused the fuel pump to provide inadequate fuel oil flow to the day
       tank.

       A system engineer identified these deficiencies during the testing of the generator six
       months prior to the incident, but facility procedures were not changed to incorporate
       corrections.  The systems engineer determined there was a large margin of error between
       the actual fuel oil day-tank level and the indicated level in the sightglass during operation
       of the emergency diesel generator.  He attributed the level discrepancy to a combination
       of the dynamic properties of the system and installation of the sightglass between the
       emergency diesel fuel pump suction piping and the atmospheric vent piping for the day
       tank.  The engineer observed that when the actual tank level reached approximately one-
       third, the indicated level in the sightglass was zero, thus providing a direct flow path from
       the day-tank atmospheric vent to the emergency diesel fuel oil pump suction, which
       resulted in a sudden and complete loss of fuel oil pressure.

       The emergency diesel is fed from the gravity-fed day tank, which holds 11.75 gallons of
       fuel, and the emergency diesel burns approximately 30 gallons of fuel per hour operating
       under a full load.  The systems engineer noted that the pump used for this test was not
       capable of maintaining sufficient fuel in the day tank to maintain an uninterrupted supply
       to the emergency diesel.  Therefore, the tank level dropped to one-third, allowing air into
       the fuel supply lines.  Facility personnel stated that the engineer's report was not made
       formally into a document and transmitted to Operations personnel, thus, the problem was
       not corrected.  Incident investigators attributed the root cause for the occurrence to facility
       management for not taking proper steps to correct the problems after the engineering
       evaluation identified the problems and the necessary action to correct the situation.

       The systems engineer informed Engineering management of the deficiency in the fuel
       pump through his weekly report highlighting the study performed six months earlier.  He
       distributed the report to Operations personnel to close out a work package and to facility
       personnel who requested the original study.  On June 24, 1993, facility personnel
       completed the systems engineer's recommendations to improve the reliability of the fuel
       oil transfer system.  (RFO--EGGR-ANALYTOPS-1993-0084)



       SAFETY NOTICES UNDER DEVELOPMENT

        Note:    The Office of Nuclear Safety encourages input related to the development of Safety
                 Notices.  If you have any questions, comments, or information concerning events or
                 issues similar to the following, please contact Mr. Dick Trevillian, Office of Nuclear Safety
                 at (301) 903-3074.

        1. NS has identified a number of events related to the loss of annunciators and other
           safety-related equipment because of problems involving 120-VAC/125-VDC systems
           at DOE and commercial facilities.  NS is reviewing potential generic problems
           associated with the adequacy of 120-VAC/125-VDC systems at DOE facilities.

        2. NS is developing a Safety Notice concerning problems with Uninterruptible Power
           Supplies (UPS).

        3. NS is considering development of a Safety Notice related to control of work at
           electrical substations and switchyards.

        4. NS is working with Lawrence Livermore National Laboratory and DOE-SF personnel
           to develop a Safety Notice on cracking in ventilation ducting.

        5. NS is considering developing a Safety Notice related to fuel oil supplies for
           Emergency Diesel Generators (EDGs).

        6. NS is developing a Safety Notice to address uses of independent verification for
           equipment positioning.

        7. NS is developing a Safety Notice related to maintaining important alarm and
           monitoring systems at facilities undergoing transition and decontamination and
           decommissioning.



        SAFETY NOTICES PREVIOUSLY ISSUED

        Safety Notice No. 91-1, "Criticality Safety Moderator Hazards," September 1991

        Safety Notice No. 92-1, "Criticality Safety Hazards Associated With Large Vessels,"
        February 1992

        Safety Notice No. 92-2, "Radiation Streaming at Hot Cells," August 1992

        Safety Notice No. 92-3, "Explosion Hazards of Uranium-Zirconium Alloys," August 1992

        Safety Notice No. 92-4, "Facility Logs and Records," September 1992

        Safety Notice No. 92-5, "Discharge of Fire Water Into a Critical Mass Lab," October
        1992

        Safety Notice No. 92-6, "Estimated Critical Positions (ECPs)," November 1992

        Safety Notice No. 93-1, "Fire, Explosion, and High-Pressure Hazards Associated with
        Drums and Containers," February 1993

        Safety Notice No. 93-2, "Control of Temporary Modifications," September 1993

    Copies of NS Safety Notices may be requested from:  Nuclear Safety Information Center,
    Office of Nuclear Safety, U.S. Department of Energy, Room S161, GTN, Washington, DC 
    20585