This is the accessible text file for GAO report number GAO-07-755T 
entitled 'Capitol Visitor Center: Update on Status of Project's 
Schedule and Cost as of April 17, 2007' which was released on April 24, 
2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on the Legislative Branch, Committee on 
Appropriations, House of Representatives: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 1:30 p.m. EDT: 

Tuesday, April 24, 2007: 

Capitol Visitor Center: 

Update on Status of Project's Schedule and Cost as of April 17, 2007: 

Statement of Terrell G. Dorn, Director, 
Physical Infrastructure Issues: 

GAO-07-755T: 

Madam Chair and Members of the Subcommittee: 

I appreciate the opportunity to be here today to assist the 
Subcommittee 
in monitoring progress on the Capitol Visitor Center (CVC) project. My 
remarks will focus on (1) the Architect of the Capitol's (AOC) 
construction progress since the last CVC hearing on March 13, 2007; and 
(2) the project's expected cost at completion and funding 
status.[Footnote 1] 

Today's remarks are based on our review of schedules and financial 
reports for the CVC project and related records maintained by AOC and 
its construction management contractor, Gilbane Building Company; our 
observations on the progress of work at the CVC construction site; and 
our discussions with the CVC team (AOC and its major CVC contractors), 
AOC's Chief Fire Marshal, and representatives from the U.S. Capitol 
Police. We also reviewed AOC's construction management contractor's 
periodic schedule assessments, potential change order log, and weekly 
reports on the progress of interior wall and floor stonework. In 
addition, we reviewed the contract modifications made as of April 11, 
2007. 

At the last CVC hearing, we reported that our assessment of the 
project's schedule and expected cost at completion was somewhat 
constrained because the CVC team was still analyzing the impact on the 
project's schedule and cost of recently identified changes required for 
certain components of the fire protection and security systems. AOC 
completed its analysis of the schedule on April 10 and extended its 
estimate of the project's completion date by about 2 months, from March 
2008 to June 2008. However, as of April 11, when we cut off our work to 
meet the congressional deadline for submitting written testimony, AOC's 
construction management contractor had not yet issued its analysis of 
the sequence 2 contractor's March 2007 schedule. With very little time 
to assess AOC's schedule analysis and without the construction 
management contractor's analysis of the project's March 2007 schedule, 
we could not thoroughly assess AOC's new scheduled project completion 
date or the project's estimated cost at completion. Thus, we are basing 
our remarks on the information available to us, and on our analysis of 
that information, as of April 11, 2007, recognizing that our views 
could change as more information becomes available. 

Summary: 

Since the March 13, 2007, CVC hearing, the CVC team has continued to 
move the project's construction forward, but AOC has extended the 
project's scheduled completion date by about 2 months, to June 
2008,[Footnote 2] and further delays are possible. This delay was 
attributable to problems with activities on the project's critical 
path--the fire protection system.[Footnote 3] During the past month, 
the CVC team has made progress on the project's heating, ventilation, 
and air-conditioning (HVAC) system, interior wall stone and ceiling 
installation, and other interior and exterior construction work. AOC 
will be able to meet or come close to meeting its new scheduled project 
completion date only if the CVC team promptly makes significant 
improvements in its execution of the project and the project's 
schedule. To date, AOC's implementation of actions identified in its 
November 2006 action plan has not been completely effective in 
curtailing additional schedule slippages. Furthermore, ongoing 
communication and coordination breakdowns between the contractors and 
AOC's Chief Fire Marshal, as well as the large number of proposed 
change orders (over 450 as of February 2007), continue to present risks 
to the project's completion time frames and costs. For example, because 
of inadequate communication and coordination, some above-ceiling fire 
protection equipment has to be inspected, even though the ceilings are 
already in place, risking damage to ceilings and additional work if the 
inspections reveal deficiencies. Most of the new construction change 
order proposals that the project continues to generate each month are 
relatively small compared with the project's total cost; however, a 
subcontractor has expressed concerns about the cumulative effect of 
these proposals on subcontractors' cash flows and on the ability of 
subcontractors to complete their work on schedule. 

As we reported at the last CVC hearing, we previously estimated that 
the total cost of the entire CVC project at completion would likely be 
about $592 million without an allowance for risks and uncertainties, 
and over $600 million with such an allowance. Because of the 
uncertainty over the project's expected completion date, we have not 
updated these estimates. To date, about $538.4 million has been 
approved for obligation for CVC construction, including about $7.4 
million in fiscal year 2007 appropriations. For fiscal year 2007, AOC 
has also received an additional appropriation of $36.4 million for the 
CVC project, which AOC has not received approval to obligate. AOC has 
not indicated how much of the additional money is needed for 
construction or operations. AOC has also requested $20 million in 
fiscal year 2008 CVC construction appropriations to cover remaining 
costs, and we estimate that AOC may need further appropriations in 
future fiscal years for construction changes and claims. 

Construction Is Progressing, but Issues Related to the Fire Protection 
System Have Delayed the Project's Scheduled Completion by About 2 
Months: 

According to AOC's construction management contractor, in dollar terms, 
the overall CVC project is 93 percent complete, compared with 91 
percent reported complete at the March 13 CVC hearing. Eighteen of the 
CVC's 23 air handling units were reportedly operating full time as of 
April 11, and work has progressed in the East Front. As of April 11, 
AOC's Chief Fire Marshal had essentially approved the shop drawings for 
all but one of the CVC project's fire alarm system elements. 

Schedule Slippage Has Continued, and AOC Faces Challenges in Meeting 
the New Project Schedule: 

The schedule for the CVC project's critical path activity--fire alarm 
and smoke control system--has slipped about 2 months since the 
Subcommittee's last CVC hearing, reportedly because several fire alarm 
system activities are taking longer than expected to complete. 
Additionally, the subcontractor responsible for installing the fire 
alarm system has indicated that because of contractual issues affecting 
its receipt of payments and delays in work that must be done by other 
subcontractors before it can complete its work, it may not be able to 
continue work at the scheduled pace. 

According to two indicators of construction progress we have been 
tracking--the completion dates for certain work activities and the pace 
of wall stone installation--the project is not likely to be completed 
by June 2008 unless the actions AOC is taking to improve its schedule 
performance are more effective in stopping schedule slippages: 

As shown in table 1, the sequence 2 contractor missed the completion 
dates for the majority of the work activities being tracked, although 
these dates have not been revised to be in line with AOC's latest 
schedule analysis. Specifically, the contractor completed 6 of 17 
activities on time and completed 3 other activities late. AOC said that 
it did not expect the contractor to meet many of the scheduled 
completion dates because, in AOC's view, many of these dates were no 
longer realistic. According to AOC, it has revised the completion dates 
for the activities to be tracked for future CVC hearings to be in line 
with its schedule analysis. 

Table 1: Activities Being Tracked for the Capitol Visitor Center, March 
13 through April 11, 2007: 

Activity: Lobby paneling; 
Location: Visitor Auditorium; 
Scheduled completion: 3/13/2007; 
Actual completion: 2/28/2007. 

Activity: Cabinets, buffet and servery; 
Location: Food Service; 
Scheduled completion: 3/15/2007; 
Actual completion: 3/05/2007. 

Activity: Ceiling installation; 
Location: Senate Upper Level; 
Scheduled completion: 3/16/2007; 
Actual completion: 3/19/2007. 

Activity: Riser cable installation; 
Location: Life Safety; 
Scheduled completion: 3/23/2007; 
Actual completion: 4/4/2007. 

Activity: Wall stone area #1; 
Location: East Front Principal; 
Scheduled completion: 3/28/2007; 
Actual completion: 3/23/2007. 

Activity: Floor stone; 
Location: West Lobby & Assembly; 
Scheduled completion: 3/28/2007; 
Actual completion: 3/23/2007. 

Activity: Riser cable termination; 
Location: Life Safety; 
Scheduled completion: 3/30/2007; 
Actual completion: [Empty]. 

Activity: Insulation testing cables; 
Location: Life Safety; 
Scheduled completion: 3/30/2007; 
Actual completion: 4/4/2007. 

Activity: Install fabric ceiling panels; 
Location: Exhibit Gallery; 
Scheduled completion: 3/30/2007; 
Actual completion: [Empty]. 

Activity: Plaster ceiling; 
Location: East Front Ground; 
Scheduled completion: 4/4/2007; 
Actual completion: [Empty]. 

Activity: Testing and balancing AHU #2&17; 
Location: Orientation Theaters; 
Scheduled completion: 4/5/2007; 
Actual completion: 3/07/ 2007. 

Activity: Check out wiring termination @ equipment; 
Location: Life Safety; 
Scheduled completion: 4/6/2007; 
Actual completion: [Empty]. 

Activity: Testing and balancing AHU #10/11/22; 
Location: Dining Room / Kitchen; 
Scheduled completion: 4/6/2007; 
Actual completion: [Empty]. 

Activity: Upholstered wall system; 
Location: Visitor Auditorium; 
Scheduled completion: 4/10/2007; 
Actual completion: [Empty]. 

Activity: Testing and balancing AHU #13; 
Location: Auditorium Visitor Lobby; 
Scheduled completion: 4/10/2007; 
Actual completion: [Empty]. 

Activity: Frame VP bulkheads; 
Location: LOC Tunnel; 
Scheduled completion: 4/11/2007; 
Actual completion: 3/19/2007. 

Activity: Fabric ceiling panels; 
Location: Orientation Lobby; 
Scheduled completion: 4/11/2007; 
Actual completion: [Empty]. 

Source: AOC and its construction management and sequence 2 contractors. 

[End of table] 

The project continues to experience delays in near-critical activities. 
Because AOC's construction management contractor had not yet issued its 
schedule analysis for March 2007, we did not have complete information 
on the sequence 2 contractor's performance in meeting scheduled 
completion dates for all of the project's near-critical activities 
during the month. However, information provided at the CVC team's 
weekly schedule meetings indicated that slippages continued to occur in 
a number of near-critical activities, including the CVC's HVAC system 
and East Front work. Although AOC's extension of the project's 
scheduled completion date generally provides more time to complete the 
near-critical activities, significant additional delays in certain 
areas, such as ceiling installation, could delay the project's overall 
completion date if they slow work on the critical path, such as fire 
alarm device installation. 

The pace of wall stone installation in the East Front has varied, first 
exceeding and then falling short of the expected average of 70 pieces 
of wall stone per day. For several weeks, the masons were installing an 
average of about 80 pieces of wall stone per day, but during the weeks 
of March 26 and April 2, they installed an average of 47 and about 55 
pieces per day, respectively. The pace of installation slowed because 
the sequence 2 contractor has been installing steel to support the 
remaining wall stone. AOC expects the pace to pick up after the support 
steel is installed. Failure to maintain the stone installation schedule 
could further delay the installation of East Front fire alarm devices, 
since the ceilings that the devices hang from cannot be completed until 
the walls are installed. 

Project Continues to Face Risks and Uncertainties: 

Problems in completing the installation, integration, operation, and 
testing of complex, major building systems, including the fire alarm, 
security, and HVAC systems, remain the most significant risk facing the 
project's schedule. Delays continue, and technical problems remain a 
risk until these systems have been installed, integrated, and 
successfully tested. Moreover, problems with these systems may not be 
evident until their final acceptance testing. In addition, significant 
delays have occurred because of breakdowns in communication and 
coordination between AOC's Chief Fire Marshal and the CVC team. This 
past month, for example, it was discovered that the sprinkler system 
was not inspected as required before some ceilings were closed in, even 
though the Chief Fire Marshal and the CVC team were meeting at least 
once a week. Although this breakdown may not affect the project's new 
June 2008 completion date, given the additional time AOC has included 
in the schedule for risks and uncertainties, some closed ceilings must 
be opened so that the sprinkler system can be inspected, and additional 
above-ceiling work may be needed if problems are found. Given the 
project's history, the risk of additional communication and 
coordination breakdowns between AOC's Chief Fire Marshal and the CVC 
team remains, and such breakdowns could affect the project's overall 
completion date. 

As of April 11, 18 of the CVC's 23 air handling units were reportedly 
providing conditioned air to their designated spaces full time. The 
remaining 5 units were reportedly ready to operate as soon as the 
initial control programming could be installed, spaces for the units 
could be prepared or cleaned, and in some cases, other work could be 
completed. All 23 units still require some work, such as initial or 
final air flow testing and balancing, connection to the fire alarm 
system, punch-list work, and commissioning.[Footnote 4] The CVC team 
expects the HVAC system's commissioning to be completed by the fall of 
2007, but some activities are taking longer than planned, and the 
achievability of this time frame is not certain. Risks include 
insufficient manpower, technical problems that could arise given the 
sophistication of the system (e.g., stair pressurization), coordination 
problems among subcontractors, equipment damage due to excessive dirt 
or moisture from a lack of air flow in some nonoperational units, and 
slippages in space readiness. Although 18 units were operating full 
time, the spaces being served by only 9 units were reported to be 
completely ready and clean as of April 11. 

Another important risk, which we have consistently cited, is the number 
of proposed change orders during sequence 2, which has continued to 
grow even at this relatively late stage in the project. Proposed change 
orders that result in contract modifications for new work or rework 
could delay the project's scheduled completion, as well as increase the 
project's costs. Even though the dollar value of recent change 
proposals has been relatively small compared with the project's total 
cost, the unabated increase in the number of change proposals is cause 
for concern. As of February 2007, there were over 450 such proposals. 
Over the past 6 months AOC has settled an average of about 20 proposed 
change orders per month. At this rate, it would take almost 2 years, 
long after the project's construction is supposed to be complete, to 
settle all of the change proposals, even if no new change proposals 
were issued. Furthermore, completing the project before reaching 
agreement on all the change proposals could require contractors to 
complete some work before agreeing on a final price for the work or on 
all contractual terms. As a result, some subcontractors might 
experience cash flow problems that could affect their financial 
stability. In addition, a subcontractor's cash flow problems might 
delay progress on the project if the subcontractor was unable to 
provide the manpower needed to maintain the expected pace of 
construction. A major subcontractor responsible for installing the fire 
alarm system recently expressed concerns to AOC about cash flow issues 
due to the large number of proposed change orders. Figure 1 illustrates 
the steady increase in proposed change orders, together with AOC's 
progress in settling them. 

Figure 1: Proposed Change Orders Submitted for Sequence 2, March 2006 
through February 2007: 

[See PDF for image] 

Source: AOC's construction management contractor. 

[End of figure] 

Cost Estimate Remains Unchanged, but Additional Funds Have Been 
Provided and More Are Likely to Be Needed: 

Our estimate of the project's cost at completion remains the same as we 
reported at the last CVC hearing--$592 million without provision for 
risks and uncertainties and over $600 million with such provision. As 
we previously reported, the $592 million estimate is rough, and we have 
not updated the $600 million estimate to reflect our assessment of the 
cost impact of risks and uncertainties. 

To date, about $538.4 million has been approved for obligation for CVC 
construction, including about $7.4 million in fiscal year 2007 
appropriations. In fiscal year 2007, AOC has received an additional 
appropriated amount of $36.4 million for the CVC project, which AOC has 
not yet received approval to obligate. AOC has not indicated how much 
of the additional money is needed for construction or operations. AOC 
has also requested $20 million in fiscal year 2008 CVC construction 
appropriations to cover remaining costs. In addition to this requested 
fiscal year 2008 funding, we estimate that AOC may need further 
appropriations in future fiscal years for construction changes and 
claims. 

Madam Chair and  members of the Subcommittees, this completes my 
prepared statement. I 
would be pleased to answer any questions that you or Members of the 
Committees may have. 

Contacts and Acknowledgments: 

For further information about this testimony, please contact Terrell 
Dorn at (202) 512-6923. Other key contributors to this testimony 
include Shirley Abel, Lindsay Bach, Maria Edelstein, Elizabeth 
Eisenstadt, Jeanette Franzel, Jackie Hamilton, Bradley James, David 
Merrill, Joshua Ormond, and Bernard Ungar. 

FOOTNOTES 

[1] GAO, Capitol Visitor Center: Update on Status of Project's Schedule 
and Cost As of March 13, 2007, GAO-07-601T (Washington, D.C.: Mar. 13, 
2007). 

[2] This date does not allow time for installing artifacts in the 
exhibit gallery or preparing for operations. 

[3] The critical path is the single longest path of activities through 
a project's schedule. Each day of delay in the critical path could 
delay the completion of the entire project. Near-critical paths are the 
next longest paths through the project's schedule. 

[4] Commissioning is a systematic process to ensure, by verification 
and documentation, that all of a facility's systems perform 
interactively as designed and intended to meet the owner's operational 
needs. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: