Medford Record of
Decision and Resource Management Plan
Acronyms and Abbreviations
Glossary
Medford Record of Decision
Medford District Resource
Management Plan Table of Contents:
- Tables
- Maps
- Appendices
|
Appendix D. Best Management
Practices
Table of Contents
I. |
Introduction |
151 |
|
A. |
Purpose |
|
151 |
|
B. |
Organization and Use |
|
151 |
II. |
Watershed
Analysis |
|
152 |
III. |
Project Planning
and Design |
|
152 |
|
A. |
Planning |
|
152 |
|
B. |
Design |
|
152 |
|
C. |
Maps/Contract
Requirements |
|
152 |
|
D. |
Cumulative Impacts |
|
153 |
IV. |
Riparian Reserves |
|
154 |
V. |
Wetlands |
|
154 |
VI. |
Fragile Soils |
|
155 |
|
A. |
Roads |
|
155 |
|
B. |
Timber Harvest |
|
156 |
|
C. |
Silviculture |
|
156 |
|
D. |
Wildfire |
|
157 |
|
E. |
Rights-of-Way |
|
157 |
VII. |
Roads and
Landings |
|
157 |
|
A. |
Planning |
|
157 |
|
B. |
Location |
|
157 |
|
C. |
Design |
|
158 |
|
|
1. |
General |
|
158 |
|
|
2. |
Surface Cross Drain
Design |
|
159 |
|
|
3. |
Permanent Stream
Crossing Design |
|
159 |
|
|
4. |
Temporary Stream
Crossing Design |
|
160 |
|
|
5. |
Low Water Ford
Stream Crossing Design |
|
160 |
|
D. |
Construction |
|
160 |
|
|
1. |
Roadway Construction |
|
160 |
|
|
2. |
Permanent Stream
Crossing Construction |
|
161 |
|
|
3. |
Temporary Stream
Crossing Construction |
|
161 |
|
|
4. |
Low Water Ford
Stream Crossing Construction |
|
162 |
|
E. |
Landings |
|
162 |
|
F. |
Road Erosion Control |
|
162 |
|
G. |
Road
Renovation/Improvement |
|
163 |
|
H. |
Road Maintenance |
|
163 |
|
I. |
Dust Abatement |
|
164 |
|
J. |
Road Access
Restrictions |
|
164 |
|
K. |
Road and Landing
Decommissioning |
|
165 |
|
L. |
Water Source
Development |
|
165 |
|
M. |
Rock Quarry
Reclamation |
|
165 |
VIII. |
Timber Harvest |
|
166 |
|
A. |
Yarding Methods |
|
166 |
|
|
1. |
Cable |
|
166 |
|
|
2. |
Tractor |
|
166 |
|
|
3. |
Helicopter |
|
166 |
|
|
4. |
Horse |
|
167 |
|
B. |
Erosion Control for
Timber Harvest |
|
167 |
|
|
1. |
Waterbars |
|
167 |
|
|
2. |
Revegetation of
Disturbed Areas |
|
168 |
IX. |
Silviculture |
|
168 |
|
A. |
Site Preparation |
|
168 |
|
|
1. |
Gross Yarding |
|
168 |
|
|
2. |
Prescribed Fire -
Broadcast Burn |
|
168 |
|
|
|
a. |
General Guidelines |
|
168 |
|
|
|
b. |
Firelines |
|
169 |
|
|
3. |
Prescribed Fire -
Piling |
|
169 |
|
|
|
a. |
Hand Piling |
|
169 |
|
|
|
b. |
Tractor Piling |
|
169 |
|
B. |
Fertilization |
|
170 |
X. |
Special Forest
Products |
|
170 |
|
A. |
Roads |
|
170 |
|
B. |
Harvest |
|
171 |
XI. |
Mineral
Development |
|
171 |
|
A. |
Locatable Operations |
|
171 |
|
B. |
Saleable Operations |
|
172 |
XII. |
Livestock Grazing |
|
172 |
XIII. |
Wildfire |
|
172 |
|
A. |
Prevention |
|
172 |
|
B. |
Suppression |
|
173 |
|
C. |
Rehabilitation |
|
173 |
XIV. |
Watershed
Restoration |
|
174 |
|
A. |
Roads |
|
174 |
|
B. |
Riparian Vegetation |
|
174 |
|
C. |
In-Stream Habitat
Structures |
|
174 |
|
D. |
Uplands |
|
175 |
|
Table 1 - A Guide
for Placing Common Soil and Geologic Types into
Soil Erosion
and Soil Infiltration Classes to Space Lateral
Road Drainage Culverts |
|
176 |
|
Table 2 - A Guide
for Maximum Spacing of Lateral Drainage Culverts
by
Soil Erosion Classes and Road Grade |
|
177 |
Best management practices (BMPs) are required by the
Federal Clean Water Act (as amended by the Water Quality
Act of 1987) to reduce nonpoint source pollution to the
maximum extent practicable. BMPs are considered the
primary mechanisms to achieve Oregon water quality
standards.
Best management practices are defined as methods,
measures, or practices selected on the basis of
site-specific conditions to ensure that water quality
will be maintained at its highest practicable level. BMPs
include, but are not limited to, structural and
nonstructural controls, operations, and maintenance
procedures. BMPs can be applied before, during, and after
pollution-producing activities to reduce or eliminate the
introduction of pollutants into receiving waters (40 CFR
130.2, EPA Water Quality Standards Regulation).
Nonpoint sources of pollution result from natural
causes, human actions, and the interactions between
natural events and conditions associated with human use
of the land and its resources. Nonpoint source pollution
is caused by diffuse sources rather than from a discharge
at a specific single location. Such pollution results in
alteration of the chemical, physical, and biological
integrity of water. Erosion from a harvest unit or
surface erosion from a road are some examples of nonpoint
sources.
The BMPs in this document are a compilation of
existing policies and guidelines and commonly employed
practices designed to maintain or improve water quality.
Objectives identified in this BMP Appendix also include
maintenance or improvement of soil productivity and fish
habitat since they are closely tied to water quality.
Selection of appropriate BMPs will help meet Aquatic
Conservation Strategy objectives during management action
implementation. Practices included in this Appendix
supplement the Standards and Guidelines from the SEIS ROD
and they should be used together.
This document is organized by management activities
plus separate sections that address activity planning and
design, riparian reserves, wetlands, and fragile soils.
Objectives are stated under each management activity
followed by a list of practices designed to achieve the
objectives.
BMPs are selected and implemented as necessary based
on site-specific conditions to meet water quality, soil,
or fish objectives for specific management actions. BMPs
and Standards and Guidelines from the SEIS ROD may be
modified to meet site specific situations. This Appendix
does not provide an exhaustive list of BMPs. Additional
nonpoint source control measures may be identified during
watershed analysis or during the interdisciplinary
process when evaluating site-specific management actions.
Implementation and effectiveness of BMPs need to be
monitored to determine whether the practices are
correctly designed and applied to achieve the objectives.
BMPs will be adjusted as necessary to ensure objectives
are met.
Review and update of this Appendix will be an ongoing
process. Updates will be made as needed to conform with
changes in Bureau of Land Management policy, direction,
or new information.
Information on watershed analysis is found in many
documents including the Standards and Guidelines on p.
B-20 in the SEIS ROD, the FY 1994-96 Watershed Analysis
Guidelines, A Federal Agency Guide for Pilot Watershed
Analysis, and BLM Information Bulletins Nos. OR-93-478,
OR-93-605, and OR-94-106. This analysis is intended to
enable watershed planning that achieves Aquatic
Conservation Strategy objectives. Watershed analysis will
serve as the basis for BMP design during project-specific
planning.
Objective: |
To include soil
productivity, water quality, and hydrologic
considerations in project planning. |
Practices: |
1. |
Use information from watershed
analysis to prepare project level plans. |
|
2. |
Use timber production capability
classification (TPCC) inventory to identify areas
classified as fragile due to slope gradient, mass
movement potential, surface erosion potential,
and high ground water levels. |
|
3. |
Use the planning process to
identify, evaluate, and map potential problems
(e.g., slump prone areas, saturated areas and
slide areas) that were not addressed in the
watershed analysis. |
|
4. |
Analyze watershed cumulative
impacts and provide mitigation measures if
necessary to meet water quality requirements (see
section III.D.). |
|
5. |
Use watershed analysis
information to determine potential for natural
and activity-created high intensity wildfires at
the project level. Reduce potential for high
intensity wildfires through proposed management
activities. |
Objective: |
To ensure that
management activities maintain favorable
conditions of soil productivity, water flow,
water quality, and fish habitat. |
Practices: |
1. |
Design proposed management
activities to mitigate potential adverse impacts
to soil and water. Evaluate factors such as soil
characteristics, watershed physiography, current
watershed and stream channel conditions, proposed
roads, skid trails, logging system design, etc.,
to determine impacts of proposed management
activities. |
|
2. |
Design mitigation measures if
adverse impacts to water quality/quantity or soil
productivity may result from the proposed action. |
Objective: |
To identify riparian
reserves to be protected and to ensure their
protection on the ground. |
Practices: |
Include the
following on activity maps and/or contracts: |
|
1. |
Locate all stream channels,
lakes, ponds, reservoirs, and wetlands (springs,
bogs, etc.) with appropriate riparian reserves on
project map and/or contracts. |
|
2. |
Include protection required for
identified water bodies on project maps and/or
contracts. |
Objective: |
To minimize
detrimental impacts on water and soil resources
resulting from the cumulative impact of land
management activities within a watershed. |
Practices: |
1. |
Coordinate
scheduling of management activities such as
timber sales, road construction, and watershed
restoration activities with other landowners in
the watershed. |
|
2. |
Use watershed
analysis results to identify watersheds with a
high level of cumulative impacts. |
|
|
a. |
Use the following
general guidelines to delineate watersheds for
cumulative impacts analyses. |
|
|
|
1) |
Natural drainage boundaries. |
|
|
|
2) |
Third to fifth order drainages
(approximately 500 to 10,000 acres). |
|
|
|
3) |
Lower boundary location based on
a state-designated beneficial use. |
|
|
b. |
The extent to which
any or all of the following criteria exist would
determine which watersheds have a high risk for
water quality degradation due to cumulative
impacts. The criteria are not listed in order of
priority. |
|
|
|
1) |
Highly erodible soils (i.e.,
subject to surface erosion, landslides, or
slumps). |
|
|
|
2) |
Large percent of forest
vegetation harvested. |
|
|
|
3) |
Large area of compacted soil. |
|
|
|
4) |
Large percent of nonrecovered
openings in transient snow zone. |
|
|
|
5) |
High sedimentation potential. |
|
|
|
6) |
Poor to fair channel stability
or condition. |
|
|
|
7) |
Poor to fair riparian condition
(nonfunctional or functional-at risk with
downward trend). |
|
|
|
8) |
High impact from catastrophic
event (e.g., wildfire). |
|
|
|
9) |
High road density. |
|
|
|
10) |
Potential for adverse impact on
a beneficial use. |
|
|
|
11) |
Monitoring data shows that water
quality does not meet state water quality
standards. |
|
|
|
12) |
Beneficial use impairment
identified in DEQ's nonpoint source assessment
and 305 (b) reports. |
|
3. |
For watersheds
identified as having a high risk for water
quality degradation, an intensive evaluation
should follow the initial analysis and include
the nature of the problem, the cause of the
problem, and a specific plan with objectives and
alternatives for recovery and mitigation. Water
monitoring may also be initiated to validate the
conclusion of the impact analysis and to
establish baseline data. |
|
4. |
Based on
site-specific conditions, select and apply
special management practices such as the
following to mitigate water quality impacts in
high risk watersheds. |
|
|
a. |
Develop and
implement a watershed/riparian restoration plan
and encourage coordination with landowners. |
|
|
b. |
Require plans of
operation for mining and rights-of-way. Require a
management plan for grazing. |
|
|
c. |
Defer the watershed
from management activities which would
potentially degrade water quality for
approximately five years. Reanalyze the
watershed. |
|
|
d. |
Increase widths of
riparian reserves. |
|
|
e. |
Utilize ecosystem
based concepts (as defined in the resource
management plan) for timber harvest. |
|
|
f. |
Require helicopter
logging. |
|
|
g. |
Require full
suspension cable yarding. |
|
|
h. |
Require seasonal
restrictions with no waivers for timber falling
and yarding. |
|
|
i. |
Minimize existing
and prevent additional road caused impacts: |
|
|
|
1) |
reduce road density; |
|
|
|
2) |
minimize road width and clearing
limits; |
|
|
|
3) |
require transport of excavated
materials to appropriate disposal site (end
hauling); |
|
|
|
4) |
prohibit new road construction; |
|
|
|
5) |
no unsurfaced roads; |
|
|
|
6) |
require seasonal restrictions
with no waivers for construction, renovation, and
hauling; |
|
|
|
7) |
require special low impact
maintenance and construction techniques; |
|
|
|
8) |
no roadside brushing/grubbing
with excavator; |
|
|
|
9) |
no blading and ditch pulling in
the winter unless essential to provide drainage; |
|
|
|
10) |
rock ditch lines; |
|
|
|
11) |
pull back sidecast from road
construction and recontour roadway; |
|
|
|
|
and |
|
|
|
12) |
remove culverts and reshape
drainageway crossings. |
|
|
j. |
Restrict or
officially close the watershed to off-highway
vehicle use and enforce the closure. |
|
|
k. |
Implement regular
compliance reviews on all activities in the
watershed. |
|
|
l. |
Assess trade-offs
between wildfire suppression impacts and wildfire
damage; plan suppression levels accordingly.
Limit use of heavy equipment during wildfire
suppression. |
Objective: |
To meet the Aquatic
Conservation Strategy objectives in the Standards
and Guidelines on p. B-11 in the SEIS ROD. |
Practices: |
1. |
Comply with interim riparian
reserve widths described in the Standards and
Guidelines on p. B-12 and p. C-30 in the SEIS ROD
until completion of watershed analysis. |
|
2. |
Follow the Standards and
Guidelines for riparian reserves on p. C-31 in
the SEIS ROD. |
Objective: |
To meet the Aquatic
Conservation Strategy objectives in the Standards
and Guidelines on p. B-11 in the SEIS ROD. |
Practices: |
1. |
Comply with interim riparian
reserve widths described in the Standards and
Guidelines on p. B-12 and p. C-30 in the SEIS ROD
until completion of watershed analysis. |
|
2. |
Follow the Standards and
Guidelines for riparian reserves on p. C-31 in
the SEIS ROD. |
Objective: To minimize surface disturbance on fragile
suitable commercial forestland.
The BMPs in this section are to be used in addition to
those in other sections.
Four categories of fragile soils sensitive to
surface-disturbing activities are identified in Medford
District's timber production capability classification
(TPCC):
Fragile Slope
Gradient (FG) |
These sites consist of steep to
extremely steep slopes that have a high potential
for surface ravel. Gradients commonly range from
60 to greater than 100 percent. |
Fragile Mass Movement (FP) |
These sites consist of deep
seated, slump, or earth flow types of landslides
with undulating topography and slope gradients
generally less than 60 percent. Soils are derived
from volcanic tuffs or breccias. |
Fragile Surface Erosion (FM) |
These sites have soil surface
horizons that are highly erodible. Soils are
derived from granite or schist bedrock. |
Fragile Groundwater (FW) |
These sites have high water
tables where water is at or near the soil surface
for sufficient periods of time that vegetation
survival and growth are affected. |
|
1. |
Planning |
|
|
Practice: |
Avoid fragile soils
when planning road systems. |
|
2. |
Design |
|
|
Practices: |
1. |
Design haul roads with rock
surface on FM, FP, and FW soils. |
|
|
|
2. |
Use slotted risers, trash racks,
or over-sized culverts to prevent culvert
plugging on FM and FP soils. |
|
3. |
Erosion Control |
|
|
Practices: |
1. |
Stabilize cutbanks, fillslopes,
and ditchlines on FM soils using methods such as
vegetation (grass seeding, deep rooted plants,
etc.), terracing, rock buttressing, and rock
armoring ditchlines. |
|
|
|
2. |
Stabilize cutbanks on FP soils
using rock buttressing. |
|
|
|
3. |
Decommission or obliterate
temporary spur roads as appropriate for
site-specific condition using methods such as
scarifying the road bed, planting tree seedlings
or grass, restoring the natural ground contour,
and water barring. |
|
4. |
Maintenance |
|
|
Practice: |
Minimize ditch
cleaning on FM and FP soils to retard slumping of
road and cutbanks. |
|
5. |
Access
Restrictions |
|
|
Practice: |
Block unsurfaced
roads on fragile soils to prohibit motorized
vehicle use. |
|
1. |
Yarding Methods -
Cable |
|
|
Practices: |
1. |
Use full or partial suspension
when yarding on FG, FM, and FW soils. |
|
|
|
2. |
Construct hand waterbars in
cable yarding corridors on FM soils where gouging
occurs immediately after use according to
guidelines in section VIII.B.1. |
|
|
|
3. |
Restrict yarding and hauling to
dry season (generally May 15 to October 15) on
FM, FP, and FW soils. |
|
2. |
Yarding Methods -
Tractor |
|
|
Practice: |
Avoid tractor
yarding. |
|
3. |
Yarding Methods -
Helicopter |
|
|
Practice: |
Employ helicopter
yarding to avoid or minimize new road
construction on fragile soils. |
|
1. |
Prescribed Fire -
Underburn |
|
|
Practice: |
Prescribe cool burns
and only burn in the spring on FG and FM soils. |
|
2. |
Prescribed Fire -
Piling |
|
|
a. |
Hand |
|
|
|
Practices: |
1. |
Put slash in yarding corridors
on FG and FM soils to control erosion, allowing
adequate space to plant trees. |
|
|
|
|
2. |
Burn handpiles on FG and FM
soils only if they prevent planter access. |
|
|
b. |
Machine |
|
|
|
Practice: |
Avoid machine piling
or ripping on FM, FP, and FW soils. |
|
1. |
Suppression |
|
|
Practices: |
1. |
Apply suppression on fragile
soils based on environmental and operational
conditions that exist at time of ignition. |
|
|
|
2. |
Limit the use of tractors and
other major surface-disturbing activities on all
fragile soils. |
|
2. |
Rehabilitation |
|
|
Practice: |
Assure prompt
rehabilitation on fragile soils through seeding
or planting of native species. |
|
Practices: |
1. |
Avoid facility construction on
FM and FP soils. |
|
|
2. |
Design rights-of-ways to
minimize surface disturbance on FM and FP soils. |
|
Objective: |
To plan road systems
that meet resource objectives and minimize
detrimental impacts on water and soil resources. |
|
Practices: |
1. |
Use an interdisciplinary team to
develop an overall transportation system. |
|
|
2. |
Establish road management
objectives that minimize adverse environmental
impacts. |
|
|
3. |
Avoid fragile and unstable
areas. |
|
|
4. |
Encourage use of BMPs where not
specifically required in reciprocal right-of-way
agreements. |
|
Objective: |
To minimize soil
erosion, water quality degradation, and
disturbance of riparian vegetation. |
|
Practices: |
1. |
Locate roads on stable positions
(e.g., ridges, natural benches, and flatter
transitional slopes near ridges and valley
bottoms). Implement extra mitigation measures
when crossing unstable areas is necessary. |
|
|
2. |
Avoid headwalls, midslope
locations on steep unstable slopes, seeps, old
landslides, slopes in excess of 70 percent, and
areas where the geologic bedding planes or
weathering surfaces are inclined with the slope. |
|
|
3. |
Locate roads to minimize heights
of cutbanks. Avoid high, steeply sloping cutbanks
in highly fractured bedrock. |
|
|
4. |
Locate roads on well-drained
soil types. Roll the grade to avoid wet areas. |
|
|
5. |
Locate stream crossing sites
where channels are well defined, unobstructed and
straight. |
|
1. |
General |
|
|
Objective: |
To design the lowest
standard of road consistent with use objectives
and resource protection needs. |
|
|
Practices: |
1. |
Base road design
standards and design criteria on road management
objectives such as traffic requirements of the
proposed activity and the overall transportation
plan, an economic analysis, safety requirements,
resource objectives, and the minimization of
damage to the environment. |
|
|
|
2. |
Consider future
maintenance concerns and needs when designing
roads. |
|
|
|
3. |
Preferred road
gradients are 2 to 10 percent with a maximum
grade of 15 percent. Consider steeper grades in
those situations where they will result in less
environmental impact. Avoid grades less than 2
percent. |
|
|
|
4. |
Road Surface
Configurations |
|
|
|
|
a. |
Outsloping - sloping the road
prism to the outside edge for surface drainage is
normally recommended for local spurs or minor
collector roads where low volume traffic and
lower traffic speeds are anticipated. It is also
recommended in situations where long intervals
between maintenance will occur and where minimum
excavation is desired. Outsloping is not
recommended on gradients greater than 8 to 10
percent. |
|
|
|
|
b. |
Insloping - sloping the road
prism to the inside edge is an acceptable
practice on roads with gradients more than 10
percent and where the underlying soil formation
is very rocky and not subject to appreciable
erosion or failure. |
|
|
|
|
c. |
Crown and Ditch - this
configuration is recommended for arterial and
collector roads where traffic volume, speed,
intensity and user comfort are a consideration.
Gradients may range from 2 to 15 percent as long
as adequate drainage away from the road surface
and ditchlines is maintained. |
|
|
|
5. |
Minimize excavation
through the following actions: use of balanced
earthwork, narrow road width, and endhauling
where slopes are greater than 60 percent. |
|
|
|
6. |
Locate waste areas
suitable for depositing excess excavated
material. |
|
|
|
7. |
Conduct slope
rounding on tops of cut slopes in clayey soils to
reduce sloughing and surface ravel. Avoid this
practice in erosion classes I,II,VII and VIII
(see Table 1). |
|
|
|
8. |
Surface roads if
they will be subject to traffic during wet
weather. The depth and gradation of surfacing
will be determined by traffic type, frequency,
weight, maintenance objectives, and the stability
and strength of the road foundation and surface
materials. |
|
|
|
9. |
Provide vegetative
or artificial stabilization of cut and fill
slopes in the design process. Avoid establishment
of vegetation where it inhibits drainage from the
road surface or where it restricts safety or
maintenance. |
|
|
|
10. |
Prior to completion
of design drawings, field check the design to
assure that it fits the terrain, drainage needs
have been satisfied, and all critical slope
conditions have been identified and adequate
design solutions applied. |
|
2. |
Surface Cross Drain
Design |
|
|
Objective: |
To design road
drainage systems that minimize concentrated water
volume and velocity and therefore to reduce soil
movement and maintain water quality. |
|
|
Practices: |
1. |
Design cross drains
in ephemeral or intermittent channels to lay on
solid ground rather than on fill material to
avoid road failures. |
|
|
|
2. |
Design placement of
all surface cross drains to avoid discharge onto
erodible (unprotected) slopes or directly into
stream channels. Provide a buffer or sediment
basin between the cross drain outlet and the
stream channel. |
|
|
|
3. |
Locate culverts or
drainage dips in such a manner to avoid discharge
onto unstable terrain such as headwalls, slumps,
or block failure zones. Provide adequate spacing
to avoid accumulation of water in ditches or
surfaces through these areas. |
|
|
|
4. |
Provide energy
dissipators (e.g., rock material) at cross drain
outlets or drain dips where water is discharged
onto loose material or erodible soil or steep
slopes. |
|
|
|
5. |
Place protective
rock at culvert entrance to streamline water flow
and reduce erosion. |
|
|
|
6. |
Use the guide for
drainage spacing by soil erosion classes and road
grade shown in Tables 1 and 2. |
|
|
|
7. |
Use drainage dips in
place of culverts on roads that have gradients
less than 10 percent or where road management
objectives result in blocking roads. Avoid
drainage dips on road gradients greater than 10
percent. |
|
|
|
8. |
Locate drainage dips
where water might accumulate or where there is an
outside berm that prevents drainage from the
roadway. |
|
|
|
9. |
When sediment is a
problem, design cross drainage culverts or
drainage dips immediately upgrade of stream
crossings to prevent ditch sediment from entering
the stream. |
|
|
|
10. |
Rolling gradients is
recommended in erodible and unstable soils to
reduce surface water volume and velocities and
culvert requirements. |
|
3. |
Permanent Stream
Crossing Design |
|
|
Objective: |
To prevent stream
crossings from being a direct source of sediment
to streams thus minimizing water quality
degradation; to provide unobstructed access to
spawning and rearing areas for anadromous and
resident fish. |
|
|
Practices: |
1. |
Use pipe arch
culverts on most fishery streams. Use bottomless
arch culverts and bridges where gradients greater
than 5 percent, stream discharge, and value of
the fishery resource dictate special engineering
considerations necessary to ensure uninterrupted
fish passage. |
|
|
|
2. |
Minimize the number
of crossings on any particular stream. |
|
|
|
3. |
Where feasible,
design culvert placement on a straight reach of
stream to minimize erosion at both ends of the
culvert. Design adequate stream bank protection
(e.g., rip-rap) where scouring would occur. Avoid
locations that require a stream channel to be
straightened beyond the length of a culvert to
facilitate installation of a road crossing. |
|
4. |
Temporary Stream
Crossing Design |
|
|
Objective: |
To design temporary
stream crossings that minimize disturbance of the
stream and riparian environment. |
|
|
Practices: |
1. |
Evaluate the
advantages and disadvantages of a temporary
versus permanent crossing structure for access to
the area during all seasons over the long term in
terms of economics, maintenance, and resource
requirements. |
|
|
|
2. |
Design temporary
structures such as prefabricated temporary timber
bridges, multiple culverts with minimum fill
height, cattleguard crossings, or log cribs to
keep vehicles out of the stream. |
|
|
|
3. |
Minimize the number
of temporary crossings on a particular stream. |
|
|
|
4. |
Avoid temporary
stream crossings on fishery streams. |
|
5. |
Low
Water Ford Stream Crossing Design |
|
|
Objective: |
To design low water
fords that minimize disturbance of the stream and
riparian environment. |
|
|
Practice: |
Use only when site
conditions make it impractical or uneconomical to
utilize a permanent or temporary crossing
structure. |
|
|
Objective: |
To create a stable
roadway while minimizing soil erosion and
potential water quality degradation. |
|
1. |
Roadway
Construction |
|
|
Practices: |
1. |
Limit road
construction to the dry season (generally between
May 15 and October 15). When conditions permit
operations outside of the dry season, keep
erosion control measures current with ground
disturbance to the extent that the affected area
can be rapidly closed/blocked and weatherized if
weather conditions warrant. |
|
|
|
2. |
Manage road
construction so that any construction can be
completed and bare soil can be protected and
stabilized prior to fall rains. |
|
|
|
3. |
Confine preliminary
equipment access (pioneer road) to within the
roadway construction limits. |
|
|
|
4. |
Construct pioneer
road so as to prevent undercutting of the
designated final cutslope and prevent avoidable
deposition of materials outside the designated
roadway limits. Conduct slope rounding at the
first opportunity during construction to avoid
excess amounts of soil being moved after
excavation and embankment operations are
completed. |
|
|
|
5. |
Use controlled
blasting techniques that minimize amount of
material displaced from road location. |
|
|
|
6. |
Construct
embankments, including waste disposal sites, of
appropriate materials (no slash or other organic
matter) using one or more of the following
methods: |
|
|
|
|
a.
b.
c. |
layer placement (tractor
compaction),
layer placement (roller compaction), and
controlled compaction (85 to 95 percent maximum
density). |
|
|
|
|
Slash and organic
material may remain under waste embankment areas
outside the road prism and outside units planned
for broadcast burning. |
|
|
|
7. |
Avoid sidecasting
where it will adversely effect water quality or
weaken stabilized slopes. |
|
|
|
8. |
Provide surface
drainage prior to fall rains. |
|
|
|
9. |
Clear drainage
ditches and natural watercourses of woody
material deposited by construction or logging
above culverts prior to fall rains. |
|
2. |
Permanent Stream
Crossing Construction |
|
|
Practices: |
1. |
Confine culvert
installation to the low flow period (generally
June 15 to September 15) to minimize
sedimentation and the adverse effects of sediment
on aquatic life. |
|
|
|
2. |
Divert the stream
around the work area to minimize downstream
sedimentation. |
|
|
|
3. |
Install culverts as
close to zero percent slope as possible on
fishery streams but not in excess of 0.5 percent.
Place culverts in the streambed at the existing
slope gradient on larger nonfishery streams.
Place energy dissipators (e.g., large rock) at
the outfall of culverts on small nonfishery
streams to reduce water velocity and minimize
scour at the outlet end. |
|
|
|
4. |
Countersink culvert
6 to 8 inches below the streambed to minimize
scouring at the outlet. Increase culvert
diameters accordingly. |
|
|
|
5. |
Limit activities of
mechanized equipment in the stream channel to the
area necessary for installation. |
|
|
|
6. |
Place permanent
stream crossing structures in fishery streams
before heavy equipment moves beyond the crossing
area. Where this is not feasible, install
temporary crossings to minimize stream
disturbance. |
|
|
|
7. |
Place rip-rap on
fills around culvert inlets and outlets. |
|
3. |
Temporary Stream
Crossing Construction |
|
|
Practices: |
1. |
Where possible,
limit the installation and removal of temporary
crossing structures to only one time during the
same year and within the prescribed work period.
Installation and removal should occur between the
low flow period (generally June 15 to September
15). |
|
|
|
2. |
Use backfill
material that is as soil-free as practicable over
temporary culverts. Whenever possible use washed
river rock covered by pit run or one inch minus
as a compacted running surface. |
|
|
|
3. |
Spread and reshape
clean fill material to the original lines of the
streambed after a crossing is removed to ensure
the stream remains in its channel during high
flow. |
|
|
|
4. |
Use log cribbing in
tractor logging units when it is impractical to
use a culvert and rock backfill material. Remove
upon completion of logging the unit. |
|
|
|
5. |
Limit activities of
mechanized equipment in the stream channel to the
area that is necessary for installation and
removal operations. |
|
|
|
6. |
Remove stream
crossing drainage structures and in-channel fill
material during low flow and prior to fall rains.
Reestablish natural drainage configuration. |
|
4. |
Low Water Ford Stream
Crossing Construction |
|
|
Practices: |
1. |
Restrict
construction and use to low flow period
(generally June 15 to September 15). |
|
|
|
2. |
Use washed
rock/gravel or concrete slab in the crossing. |
|
|
|
3. |
Apply rock on road
approaches within 150 feet of each side of the
ford to prevent washing and softening of the road
surface. |
|
Objective: |
To minimize soil
disturbance, soil erosion, soil productivity
losses, and water quality degradation. |
|
Practices: |
1. |
Locate landings at approved
sites. |
|
|
2. |
Avoid placing landings adjacent
to or in meadows or other wetland areas. |
|
|
3. |
Clear or excavate landings to
minimum size needed for safe and efficient
operations. |
|
|
4. |
Select landing locations
considering the least amount of excavation,
erosion potential, and where sidecast will not
enter drainages or damage other sensitive areas. |
|
|
5. |
Deposit excess excavated
material on stable sites where there is no
erosion potential. Construct waste disposal sites
according to guidelines in VII.D.1. |
|
|
6. |
Restore landings to the natural
configuration or shape to direct the runoff to
preselected spots where water can be dispersed to
natural, well-vegetated, gentle ground. |
|
Objective: |
To limit and
mitigate soil erosion and sedimentation. |
|
Practices: |
1. |
Apply protective measures to all
areas of disturbed, erosion-prone, unprotected
ground, including waste disposal sites, prior to
fall rains. Protective measures may include water
bars, water dips, grass seeding, planting deep
rooted vegetation, and/or mulching. Armor or
buttress fill slopes and unstable areas with rock
which meets construction specifications. See
section VIII.B.1.
for water bar (water dip) spacing and
construction guidelines. |
|
|
2. |
Use seasonal restrictions on
unsurfaced roads. |
|
Objective: |
To restore or
improve a road to a desired standard in a manner
that minimizes sediment production and water
quality degradation. |
|
Practices: |
1. |
Improve flat gradients to a
minimum of two (2) percent or provide raised
subgrade sections (turnpike) to avoid saturation
of the road prism. |
|
|
2. |
Reconstruct culvert catchbasins
to specifications. Catchbasins in solid rock need
not be reconstructed provided water flow is not
restricted by soil, rock, or other debris. |
|
|
3. |
Identify potential water
problems caused by off-site disturbance and add
necessary drainage facilities. |
|
|
4. |
Identify ditchline and outlet
erosion caused by excessive flows and add
necessary drainage facilities and armoring. |
|
|
5. |
Replace undersized culverts and
repair damaged culverts and downspouts. |
|
|
6. |
Add additional full-rounds,
half-rounds, and energy dissipators as needed. |
|
|
7. |
Correct special drainage
problems (e.g., high water table, seeps) that
effect stability of subgrade through the use of
perforated drains, geotextiles, or drainage bays.
|
|
|
8. |
Eliminate undesirable berms that
retard normal surface runoff. |
|
|
9. |
Restore outslope or crown
sections. |
|
|
10. |
Avoid disturbing backslope while
reconstructing ditches. |
|
|
11. |
Surface inadequately surfaced
roads that are to be left open to traffic during
wet weather. |
|
|
12. |
Require roadside brushing be
done in a manner that prevents disturbance to
root systems (i.e., avoid using excavators for
brushing). |
|
Objective: |
To maintain roads in
a manner that protects water quality and
minimizes erosion and sedimentation. |
|
Practices: |
1. |
Provide basic custodial care to
protect the road investment and to ensure minimal
damage to adjacent land and resources. |
|
|
2. |
Perform blading and shaping to
conserve existing surface material, retain the
original crowned or outsloped self-draining cross
section, prevent or remove rutting berms (except
those designed for slope protection) and other
irregularities that retard normal surface runoff.
Avoid wasting loose ditch or surface material
over the shoulder where it can cause stream
sedimentation or weaken slump prone areas. Avoid
undercutting backslopes. |
|
|
3. |
Keep road inlet and outlet
ditches, catchbasins, and culverts free of
obstructions, particularly before and during
winter rainfall. However, keep routine machine
cleaning of ditches to a minimum during wet
weather. |
|
|
4. |
Promptly remove slide material
when it is obstructing road surface and ditchline
drainage. Save all soil or material useable for
quarry reclamation and stockpile for future
reclamation projects. Utilize remaining slide
material for needed road improvement or place in
a stable waste area. Avoid sidecasting of slide
material where it can damage, overload, saturate
embankments, or flow into downslope drainage
courses. Reestablish vegetation in areas where
more than 50 percent of vegetation has been
destroyed due to sidecasting. |
|
|
5. |
Retain vegetation on cut slopes
unless it poses a safety hazard or restricts
maintenance activities. Cut roadside vegetation
rather than pulling it out and disturbing the
soil. |
|
|
6. |
Remove snow on haul roads in a
manner that will protect roads and adjacent
resources. Remove or place snow berms to prevent
water concentration on the roadway or on erodible
sideslopes or soils. |
|
|
7. |
Patrol areas subject to road or
watershed damage during periods of high runoff. |
|
Objective: |
To minimize movement
of fine sediment from roads; to prevent
introduction into waterways of chemicals applied
for dust abatement. |
|
Practices: |
1. |
Use dust palliatives or surface
stabilizers to reduce surfacing material loss and
buildup of fine sediment that may wash off into
water courses. |
|
|
2. |
Closely control application of
dust palliatives and surface stabilizers,
equipment cleanup, and disposal of excess
material to prevent contamination or damage to
water resources. |
|
Objective: |
To reduce road
surface damage and therefore minimize erosion and
sedimentation. |
|
Practices: |
1. |
Barricade or block roads using
gates, guard rails, earth/log barricades,
boulders, logging debris, or a combination of
these methods. Avoid blocking roads that will
need future maintenance (i.e., culvert cleaning,
slide removal, etc.) with unremovable barricades.
Use guardrails, gates, or other barricades
capable of being opened for roads needing future
maintenance. |
|
|
2. |
Provide maintenance of blocked
roads in accordance with design criteria. |
|
|
3. |
Install waterbars, cross drains,
cross sloping, or drainage dips if not already on
road to assure drainage. |
|
|
4. |
Scarify, mulch, and/or seed for
erosion control. |
|
Objective: |
To reduce soil
compaction, minimize or reduce sedimentation, and
improve site productivity by decommissioning
roads and landings and rehabilitating the land. |
|
Practices: |
1. |
Rip temporary spur roads and
landings by an approved method to remove ruts,
berms, and ditches while leaving or replacing
surface cross drain structures. |
|
|
2. |
Return roads or landings not
needed for future resource management to resource
production by revegetating with native species.
Apply mulch and fertilizer where appropriate. |
|
Objective: |
To supply water for
various resource programs while protecting water
quality and riparian vegetation. |
|
Practices: |
1. |
Design and construct durable,
long-term water sources. |
|
|
2. |
Avoid reduction of downstream
flow which would detrimentally effect aquatic
resources, fish passage, or other uses. |
|
|
3. |
Direct overflow from
water-holding developments back into the stream. |
|
|
4. |
Locate road approaches to
instream water source developments to minimize
potential impacts in the riparian zone. Apply
rock to surface of these approaches to reduce the
effects of sediment washing into the stream. |
|
|
5. |
Avoid use of road fills for
water impoundment dams unless specifically
designed for that purpose. Remove any blocking
device prior to fall rains. |
|
|
6. |
Construct water sources during
the dry season (generally between May 15 and
October 15). |
|
Objective: |
To minimize sediment
production from quarries and associated crusher
pad developments susceptible to erosion due to
steep sideslopes, lack of vegetation, or their
proximity to water courses. |
|
Practices: |
1. |
Prior to excavation, remove
topsoil and place at a site with minimal erosion
potential. Stockpile topsoil for surface dressing
during the post-operation rehabilitation. |
|
|
2. |
Use culverts and rip-rap for
crusher pad drainage when necessary. |
|
|
3. |
Stabilize quarry cutbanks and
general quarry area. |
|
|
4. |
Revegetate with native species,
apply mulch, and provide adequate drainage to
minimize erosion. |
|
|
5. |
Rip, waterbar, block, fertilize,
and revegetate access roads to quarries where no
future entry is planned. |
|
1. |
Cable |
|
|
Objective: |
To minimize soil
damage and erosion caused by displacement or
compaction. |
|
|
Practices: |
1. |
Use full or partial suspension
when yarding on erodible or ravel prone areas
where practical. |
|
|
|
2. |
Use full or partial suspension
with seasonal restrictions on areas of high water
tables. |
|
|
|
3. |
Use seasonal restriction if
required suspension cannot be achieved by yarding
equipment. |
|
|
|
4. |
Avoid downhill yarding. |
|
2. |
Tractor |
|
|
Objective: |
To minimize loss of
soil productivity and reduce potential for
surface runoff and subsequent water quality
degradation. |
|
|
Practices: |
1. |
In previously unentered stands,
use designated skid roads to limit soil
compaction to less than 12 percent of the harvest
area. |
|
|
|
2. |
Minimize width of skid roads. |
|
|
|
3. |
For stands previously logged
with tractors, utilize existing skid roads. Rip
all skid roads used in final entry harvest. |
|
|
|
4. |
Rip skid roads discontinuously,
preferably with winged ripper teeth when the soil
is dry. Rips should be spaced no more than 36
inches apart and from 12 to 18 inches deep or to
bedrock, whichever is shallower. Designated skid
roads should be ripped if they will not be used
again until the next rotation. |
|
|
|
5. |
Avoid placement of skid roads
through areas with high water tables. |
|
|
|
6. |
Use appropriate seasonal
restrictions that would result in no off-site
damage for designated skid roads. |
|
|
|
7. |
Allow logging on snow when snow
depth is 18 inches or greater and negligible
ground surface exposure occurs during the
operation. |
|
|
|
8. |
Restrict tractor operations to
slopes less than 35 percent. |
|
|
|
9. |
Construct waterbars on skid
roads according to guidelines in section VIII.B.1. |
|
3. |
Helicopter |
|
|
Objective: |
To minimize surface
disturbance on high risk watersheds. |
|
|
Practice: |
Employ helicopter
yarding to avoid or minimize new road
construction in high risk watersheds. |
|
4. |
Horse |
|
|
Objective: |
To minimize soil
disturbance, soil compaction, and soil erosion. |
|
|
Practices: |
1. |
Limit horse logging to slopes
less than 20 percent. |
|
|
|
2. |
Construct hand waterbars on
horse skid trails according to guidelines in
section VIII.B.1. |
|
|
|
3. |
Limit harvest activity to times
when soil moisture content at a six-inch depth is
less than 25 percent by weight. |
|
1. |
Waterbars |
|
|
Objective: |
To minimize soil
erosion. |
|
|
Practices: |
1. |
Construct adequate
waterbars on skid roads, yarding corridors, and
fire lines prior to fall rains. |
|
|
|
2. |
Use the following
table for waterbar spacing, based on gradient and
erosion class. |
Water Bar Spacing by
Gradient and Erosion Class |
Gradient(%) |
|
High |
|
Water
Bar Spacing (feet)1
Erosion Class2
Moderate |
|
Low3 |
2-5 |
|
200 |
|
300 |
|
400 |
6-10 |
|
150 |
|
200 |
|
300 |
11-15 |
|
100 |
|
150 |
|
200 |
16-20 |
|
75 |
|
100 |
|
150 |
21-35 |
|
50 |
|
75 |
|
100 |
36+ |
|
50 |
|
50 |
|
50 |
1Spacing
is determined by slope distance and is
the maximum allowed for the grade.
2The following guide lists rock
types according to erosion class:
High: |
granite,
sandstone, andesite porphyry,
glacial or alluvial deposits,
soft matrix conglomerate,
volcanic ash, pyroclastics; |
Moderate: |
basalt,
andesite, quartzite, hard matrix
conglomerate, rhyolite; |
Low:
|
metasediments,
metavolcanics, hard shale. |
|
|
|
|
|
3. |
Use the following
techniques to construct waterbars: |
|
|
|
|
a. |
Open the downslope end of the
waterbar to allow free passage of water. |
|
|
|
|
b. |
Construct the waterbar so that
it will not deposit water where it will cause
erosion. |
|
|
|
|
c. |
Compact the waterbar berm to
prevent water from breaching the berm. |
|
|
|
|
d. |
Skew waterbars no more than 30
degrees from perpendicular to the centerline of
the trail or road. |
|
2. |
Revegetation of Disturbed
Areas |
|
|
Objective: |
To establish an
adequate vegetative cover on disturbed sites to
prevent erosion. |
|
|
Practice: |
Use native
vegetation that allows natural succession to
occur. Avoid interference with reforestation
operations. Include application of seed, mulch,
and fertilizer as necessary. Complete prior to
fall rains. |
|
1. |
Gross Yarding |
|
|
Objective: |
To achieve cool burn
on sensitive soils and maintain protective duff
layer. |
|
|
Practice: |
Consider the
following in writing a prescription for gross
yarding to reduce burn intensities: long-term
site productivity, ecosystem dynamics,
regeneration success, prescribed fire
intensities, and smoke emissions. |
|
2. |
Prescribed Fire -
Underburn and Concentration Burn |
|
|
a. General Guidelines |
|
|
Objective: |
To maintain
long-term site productivity of soil. |
|
|
Practice: |
Evaluate need for
burning based on soils, plant community, and site
preparation criteria. Burn under conditions when
a light burn can be achieved (see guidelines
below) to protect soil productivity. |
|
|
|
Category 1 Soils
(highly sensitive): burn only in spring-like
conditions when soil and duff are moist. Maximize
retention of duff layer. Assure retention of
minimum levels of coarse woody debris and
recruitment snags as specified in the Standards
and Guidelines on p. C-40 in the SEIS ROD. |
|
|
|
Category 2 Soils
(moderately sensitive): burn only in spring-like
conditions when soil and duff are moist. Maximize
retention of duff layer. Assure retention of
minimum levels of coarse woody debris and
recruitment snags as specified in the Standards
and Guidelines on p. C-40 in the SEIS ROD. Write
fire prescriptions that reduce disturbance and
duration and achieve low fire intensity. |
|
|
|
Category 3 Soils
(least sensitive): burn to avoid high intensity
(severe) burns to protect a large percentage of
the nutrient capital. Maximize retention of duff
layer. Assure retention of minimum levels of
coarse woody debris and recruitment snags as
specified in the Standards and Guidelines on p.
C-40 in the SEIS ROD. |
Guidelines for Levels of
Prescribed Burn Intensity |
Visual
Characterization |
|
Site-Specific
Results |
|
Proportional Area |
Light burn |
|
The surface duff layer
is often charred by fire but not removed.
Duff, crumbled wood or other woody debris
is partly burned, logs not deeply
charred. |
|
Less than 2 percent is
severely burned. Less than 15 percent is
moderately burned. |
Moderate burn |
|
Duff, rotten wood, or
other woody debris partially consumed;
logs may be deeply charred but mineral
soil under the ash not appreciably
changed in color. |
|
Less than 10 percent is
severely burned. More than 15 percent is
moderately burned. |
Severe burn |
|
Top layer of mineral
soil significantly changed in color,
usually to reddish color; next 1/2 inch
blackened from organic matter charring by
heat conducted through top layer. |
|
More than 10 percent is
severely burned. More than 80 percent is
moderately burned. Remainder is lightly
burned. |
|
|
|
b.
Firelines |
|
|
Objective: |
To minimize soil
disturbance, soil compaction, soil erosion, and
disturbance to riparian reserves. |
|
|
Practices: |
1. |
Construct firelines
by hand on all slopes greater than 35 percent. |
|
|
|
2. |
Utilize one-pass
construction with a brush blade for tractor
firelines. |
|
|
|
3. |
Construct waterbars
on tractor and hand firelines according to
guidelines in section VIII.B.1. |
|
|
|
4. |
No machine
constructed firelines in riparian reserves. |
|
3. |
Prescribed
Fire - Piling |
|
|
a.
Hand Piling |
|
|
Objective: |
To prevent soil
damage due to high burn intensity. |
|
|
Practice: |
Burn piles when soil
and duff moisture are high. |
|
|
b. Tractor Piling |
|
|
Objective: |
To protect soil
productivity and to prevent soil damage due to
compaction, displacement, and high burn
intensity. |
|
|
Practices: |
1. |
Restrict tractor
operations to dry conditions with less than 25
percent soil moisture content in the upper six
inches of soil. |
|
|
|
2. |
Restrict tractors to
slopes less than 20 percent. |
|
|
|
3. |
Construct small
diameter piles or pile in windrows using brush
blades. |
|
|
|
4. |
Avoid piling
concentrations of large logs and stumps. |
|
|
|
5. |
Pile small material
(3 to 8 inches diameter size). |
|
|
|
6. |
Burn piles when soil
and duff moisture are high. |
|
|
|
7. |
Rip entire area to
maintain soil productivity except that occupied
by piles. Use winged ripper teeth and rip on
contour to minimum depth of 12 inches. No ripping
on clayey soils (i.e., soil series 706, 708, 840,
850). |
|
|
|
8. |
Avoid displacement
of duff and topsoil into piles or windrows. |
|
|
|
9. |
Make only two
machine passes (one round trip) over the same
area wherever practical. |
|
|
|
10. |
Use the lowest
ground pressure machine capable of meeting
objectives. |
|
Objective: |
To protect water
quality and to avoid impacts that retard or
prevent attainment of the Aquatic Conservation
Strategy objectives. |
|
Practices: |
1. |
Avoid aerial application when
wind speeds would cause drift. |
|
|
2. |
Locate heliports and storage
areas away from riparian reserves. |
|
|
3. |
No application within riparian
reserves. |
|
|
4. |
Avoid direct application to
ephemeral stream channels. |
|
Objective: |
To prevent erosion
and water quality degradation. |
|
Practices: |
1. |
Utilize seasonal restriction on
harvesting if access is by an unsurfaced road. |
|
|
2. |
Clean all road surfaces,
ditches, and catchbasins of debris from
harvesting. |
|
Objective: |
To minimize soil damage and soil erosion. |
|
Practice: |
Follow practices listed in section VIII.A. |
|
Objective: |
To protect surface and
groundwater quality and to minimize disturbance
to streambanks and riparian habitat within
constraints of Department of Interior, Bureau of
Land Management surface mining regulations. |
|
Practices: |
1. |
Require the claimant to obtain
all required state and federal operating permits. |
|
|
2. |
Comply with seasonal
restrictions on suction dredging identified in
Oregon Guidelines for Timing of In-Water Work to
Protect Fish and Wildlife Resources. |
|
|
3. |
Locate, design, operate, and
maintain sediment settling ponds in conformance
with state Department of Environmental Quality
(DEQ) requirements. |
|
|
4. |
Design, locate, and construct
stream crossings in conformance with practices
described in sections VII.B., VII.C. and VII.D. |
|
|
5. |
Use existing roads, skid trails,
and stream crossings whenever possible. |
|
|
6. |
Apply rock to roads constructed
or reconstructed for vehicular access to the
mining area. Provide roads with adequate
drainage. |
|
|
7. |
Prior to the first wet season,
rip, waterbar, seed, mulch, and barricade
according to BLM specifications all roads and
trails constructed for exploratory purposes that
are unnecessary for the mining operation. |
|
|
8. |
Construct waterbars and
barricade on all natural surface roads and trails
when an operation shuts down for the wet season.
See section VIII.B.1
for guidelines on waterbar spacing and
construction. |
|
|
9. |
Rip, waterbar, seed, mulch, and
barricade all natural surface roads and trails
when the operation terminates. |
|
|
10. |
Construct a berm or trench
between disturbed areas and water courses. |
|
|
11. |
Stockpile topsoil for use during
reclamation of the site. Construct a berm or
trench immediately downslope of the stockpile. |
|
|
12. |
Stabilize and contour the area,
replace topsoil and mulch, seed, and plant the
area with tree seedlings when no further mining
is contemplated. |
|
|
13. |
During the period from October
15 to May 15, contour and mulch disturbed areas
that will not be mined for at least 30 days. |
|
|
14. |
Confine operations to bench
areas rather than allow encroachment on the
stream whenever possible. |
|
|
15. |
Locate and maintain sanitation
facilities in accordance with state DEQ
regulations. |
|
Practices: |
1. |
Locate stockpile sites on stable
ground where the material would not move into
streams or water bodies. |
|
|
2. |
Locate, design, construct, and
close roads, landings, and crusher pads in
accordance with section VII. |
|
Objective: |
To protect,
maintain, or improve water quality,
riparian-wetland areas and upland plant
communities; to achieve properly functioning
riparian ecosystems. |
|
Practices: |
1. |
Consider fencing springs, seeps,
and water developments to protect water quality
and riparian ecosystems. |
|
|
2. |
Ensure rest for plant growth and
vigor during the critical growing period. |
|
|
3. |
Monitor, evaluate, and adjust
livestock management practices to meet resource
objectives. |
|
|
4. |
Resolve management conflicts
through the development of grazing management
plans. |
|
|
5. |
Promote ecological recovery
through appropriate forage utilization levels. |
|
|
6. |
Develop and implement recovery
plans for riparian areas. |
|
Objective: |
To minimize occurrence of severe
intensity wildfires in riparian reserves, on
category 1 soils, and high risk watersheds. |
|
Practice: |
Utilize prescribed burning to
reduce both natural and management related slash
(fuel) adjacent and/or within these areas. |
|
Objective: |
To minimize water
quality degradation while achieving rapid and
safe suppression of a wildfire. |
|
Practices: |
1. |
Apply the appropriate level of
wildfire suppression which considers impacts of
the wildfire as well as the suppression action. |
|
|
2. |
Construct firelines by hand
within riparian reserves. |
|
|
3. |
Apply aerial retardant adjacent
to riparian reserves by making passes parallel to
riparian reserves. |
|
Objective: |
To protect water
quality and soil productivity with consideration
for other resources. |
|
Practices: |
1. |
Utilize vegetation
classification information as the framework for
prescribing rehabilitation activities. |
|
|
2. |
Develop a fire
rehabilitation plan through an interdisciplinary
process. |
|
|
3. |
Select treatments on
the basis of on-site values, downstream values,
probability of successful implementation, social
and environmental considerations (including
protection of native plant community), and cost
as compared to benefits. |
|
|
4. |
Erosion control
seeding should attempt to meet the intent of
ecosystem based management objectives. Use seed
availability information to prioritize erosion
control seeding. First priority should be native
seed sources for grasses and forbs, followed by
annual grasses and forbs, and the lowest priority
should be the use of perennial grasses. |
|
|
5. |
Examples of
emergency fire rehabilitation treatments include: |
|
|
|
a. |
Seeding or planting native
species or other nitrogen fixing vegetation that
accomplishes necessary erosion control and meets
site restoration objectives. |
|
|
|
b. |
Mulch with straw or other
suitable material. |
|
|
|
c. |
Fertilize. |
|
|
|
d. |
Place channel stabilization
structures. |
|
|
|
e. |
Place trash racks above road
drainage structures. |
|
|
|
f. |
Construct waterbars on
firelines. |
Watershed restoration is a key component of the
Aquatic Conservation Strategy and is based on watershed
analysis (see the Standards and Guidelines on p. B-30 and
p. C-37 in the SEIS ROD and appropriate sections in this
document).
See sections VII.F.,
VII.G., and VII.K.
See the Standards and Guidelines p. B-31 and p. C-32
in the SEIS ROD.
|
Objective: |
To minimize damage
to streambanks and riparian habitat during
construction of in-stream habitat improvement
projects. |
|
Practices: |
1. |
Carefully plan access needs for
individual work sites within a project area to
minimize exposure of bare soil, compaction, and
possible damage to tree roots. Utilize existing
trails to the extent practical. |
|
|
2. |
Base design of habitat
improvement structures on state-of-the-art
techniques and local stream hydraulics. |
|
|
3. |
Confine work in the stream
channels to between June 15 and September 15 to
minimize the area of the stream that would be
affected by sedimentation during the low flow
period. |
|
|
4. |
Keep equipment out of streams to
extent possible. |
|
|
5. |
Limit the amount of streambank
excavation to the minimum necessary to ensure
stability of enhancement structures. Place
excavated material as far above the high water
mark as possible to avoid entry into the stream. |
|
|
6. |
Whenever possible obtain logs
for habitat improvement structures from outside
the riparian reserve or at least 200 feet from
the stream channel to maintain integrity of
riparian habitat and streambanks. |
|
|
7. |
Inspect all mechanized equipment
daily to help ensure toxic materials such as fuel
and hydraulic fluid do not enter the stream. |
|
|
8. |
Utilize waterbars, barricades,
and seeding to stabilize bare soil areas. |
|
Objective: |
To increase soil stability,
reduce soil erosion, and improve hydrologic
functions. |
|
Practice: |
Use corrective measures to
repair degraded watershed conditions and
rehabilitate with an ecologically appropriate
vegetative cover that will maintain or improve
soil stability, reduce surface runoff, increase
infiltration, and reduce flood occurrence and
flood damages. |
|