Skip to content.Skip to side navigation. Quick Navigation: Skip to content.Skip to side navigation.
GPO Access Home Page.
Jump to selected topic.
Navigation Bar
About.Help. A-Z Resource List. Locate a Federal Depository Library. Buy Publications. Legislative. Executive. Judicial.
National Archives and Records Administration logo.
Database Features.
Browse
Simple Search
Advanced Search
* Boolean
  * Proximity
Search History
Search Tips
Corrections

Latest Updates

User Info
FAQs
Agency List
e-CFR Main Page
Related Resources
Code of Federal Regulations
Federal Register
List of CFR
Sections Affected
Regulations.gov
Unified Agenda
All NARA Publications
About Government.
Ben's Guide Logo.
Get Adobe Reader

blue pill
e-CFR Data is current as of March 12, 2009


Title 30: Mineral Resources
PART 203—RELIEF OR REDUCTION IN ROYALTY RATES

Browse Next

Subpart A—General Provisions

Source:   63 FR 2616, Jan. 16, 1998, unless otherwise noted.

§ 203.0   What definitions apply to this part?

Authorized field means a field:

(1) Located in a water depth of at least 200 meters and in the Gulf of Mexico (GOM) west of 87 degrees, 30 minutes West longitude;

(2) That includes one or more pre-Act leases; and

(3) From which no current pre-Act lease produced, other than test production, before November 28, 1995.

Certified unsuccessful well means an original well or a sidetrack with a sidetrack measured depth ( i.e. , length) of at least 10,000 feet, on your lease that:

(1) You begin drilling on or after March 26, 2003, and before May 3, 2009, on a lease that is located in water partly or entirely less than 200 meters deep and that is not a non-converted lease, or on or after May 18, 2007, and before May 3, 2013, on a lease that is located in water entirely more than 200 meters and entirely less than 400 meters deep;

(2) You begin drilling before your lease produces gas or oil from a well with a perforated interval the top of which is at least 18,000 feet true vertical depth subsea (TVD SS), ( i.e. , below the datum at mean sea level);

(3) You drill to at least 18,000 feet TVD SS with a target reservoir on your lease, identified from seismic and related data, deeper than that depth;

(4) Fails to meet the producibility requirements of 30 CFR part 250, subpart A, and does not produce gas or oil, or meets those producibility requirements and MMS agrees it is not commercially producible; and

(5) For which you have provided the notices and information required under §203.47.

Complete application means an original and two copies of the six reports consisting of the data specified in 30 CFR 203.81, 203.83 and 203.85 through 203.89, along with one set of digital information, which MMS has reviewed and found complete.

Deep well means either an original well or a sidetrack with a perforated interval the top of which is at least 15,000 feet TVD SS and less than 20,000 feet TVD SS. A deep well subsequently re-perforated at less than 15,000 feet TVD SS in the same reservoir is still a deep well.

Determination means the binding decision by MMS on whether your field qualifies for relief or how large a royalty-suspension volume must be to make the field economically viable.

Development project means a project to develop one or more oil or gas reservoirs located on one or more contiguous leases that have had no production (other than test production) before the current application for royalty relief and are either:

(1) Located in a planning area offshore Alaska; or

(2) Located in the GOM in a water depth of at least 200 meters and wholly west of 87 degrees, 30 minutes West longitude, and were issued in a sale held after November 28, 2000.

Draft application means the preliminary set of information and assumptions you submit to seek a nonbinding assessment on whether a field could be expected to qualify for royalty relief.

Eligible lease means a lease that:

(1) Is issued as part of an OCS lease sale held after November 28, 1995, and before November 28, 2000;

(2) Is located in the Gulf of Mexico in water depths of 200 meters or deeper;

(3) Lies wholly west of 87 degrees, 30 minutes West longitude; and

(4) Is offered subject to a royalty suspension volume.

Expansion project means a project that meets the following requirements:

(1) You must propose the project in a Development and Production Plan, a Development Operations Coordination Document (DOCD), or a Supplement to a DOCD, approved by the Secretary of the Interior after November 28, 1995.

(2) The project must be located on either:

(i) A pre-Act lease in the GOM, or a lease in the GOM issued in a sale held after November 28, 2000, located wholly west of 87 degrees, 30 minutes West longitude; or

(ii) A lease in a planning area offshore Alaska.

(3) On a pre-Act lease in the GOM, the project:

(i) Must significantly increase the ultimate recovery of resources from one or more reservoirs that have not previously produced (extending recovery from reservoirs already in production does not constitute a significant increase); and

(ii) Must involve a substantial capital investment (e.g., fixed-leg platform, subsea template and manifold, tension-leg platform, multiple well project, etc.).

(4) For a lease issued in a planning area offshore Alaska, or in the GOM after November 28, 2000, the project must involve a new well drilled into a reservoir that has not previously produced.

(5) On a lease in the GOM, the project must not include a reservoir the production from which an RSV under §§203.30 through 203.36 or §§203.40 through 203.48 would be applied.

Fabrication (or start of construction) means evidence of an irreversible commitment to a concept and scale of development. Evidence includes copies of a binding contract between you (as applicant) and a fabrication yard, a letter from a fabricator certifying that continuous construction has begun, and a receipt for the customary down payment.

Field means an area consisting of a single reservoir or multiple reservoirs all grouped on, or related to, the same general geological structural feature or stratigraphic trapping condition. Two or more reservoirs may be in a field, separated vertically by intervening impervious strata or laterally by local geologic barriers, or both.

Lease means a lease or unit.

New production means any production from a current pre-Act lease from which no royalties are due on production, other than test production, before November 28, 1995. Also, it means any additional production resulting from new lease-development activities on a lease issued in a sale after November 28, 2000, or a current pre-Act lease under a DOCD or a Supplement approved by the Secretary of the Interior after November, 28, 1995.

Nonbinding assessment means an opinion by MMS of whether your field could qualify for royalty relief. It is based on your draft application and does not entitle the field to relief.

Non-converted lease means a lease located partly or entirely in water less than 200 meters deep issued in a lease sale held after January 1, 2001, and before January 1, 2004, whose original lease terms provided for an RSV for deep gas production and the lessee has not exercised the option under §203.49 to replace the lease terms for royalty relief with those in §203.0 and §§203.40 through 203.48.

Original well means a well that is drilled without utilizing an existing wellbore. An original well includes all sidetracks drilled from the original wellbore either before the drilling rig moves off the well location or after a temporary rig move that MMS agrees was forced by a weather or safety threat and drilling resumes within 1 year. A bypass from an original well (e.g., drilling around material blocking the hole or to straighten crooked holes) is part of the original well.

Participating area means that part of the unit area that MMS determines is reasonably proven by drilling and completion of producible wells, geological and geophysical information, and engineering data to be capable of producing hydrocarbons in paying quantities.

Performance conditions means minimum conditions you must meet, after we have granted relief and before production begins, to remain qualified for that relief. If you do not meet each one of these performance conditions, we consider it a change in material fact significant enough to invalidate our original evaluation and approval.

Phase 1 ultra-deep well means an ultra-deep well on a lease that is located in water partly or entirely less than 200 meters deep for which drilling began before May 18, 2007, and that begins production before May 3, 2009, or that meets the requirements to be a certified unsuccessful well.

Phase 2 ultra-deep well means an ultra-deep well for which drilling began on or after May 18, 2007; and that either meets the requirements to be a certified unsuccessful well or that begins production:

(1) Before the date which is 5 years after the lease issuance date on a non-converted lease; or

(2) Before May 3, 2009, on all other leases located in water partly or entirely less than 200 meters deep; or

(3) Before May 3, 2013, on a lease that is located in water entirely more than 200 meters and entirely less than 400 meters deep.

Phase 3 ultra-deep well means an ultra-deep well for which drilling began on or after May 18, 2007, and that begins production:

(1) On or after the date which is 5 years after the lease issuance date on a non-converted lease; or

(2) On or after May 3, 2009, on all other leases located in water partly or entirely less than 200 meters deep; or

(3) On or after May 3, 2013, on a lease that is located in water entirely more than 200 meters and entirely less than 400 meters deep.

Pre-Act lease means a lease that:

(1) Results from a sale held before November 28, 1995;

(2) Is located in the GOM in water depths of 200 meters or deeper; and

(3) Lies wholly west of 87 degrees, 30 minutes West longitude.

Production means all oil, gas, and other relevant products you save, remove, or sell from a tract or those quantities allocated to your tract under a unitization formula, as measured for the purposes of determining the amount of royalty payable to the United States.

Project means any activity that requires at least a permit to drill.

Qualified deep well means:

(1) On a lease that is located in water partly or entirely less than 200 meters deep that is not a non-converted lease, a deep well for which drilling began on or after March 26, 2003, that produces natural gas (other than test production), including gas associated with oil production, before May 3, 2009, and for which you have met the requirements prescribed in §203.44;

(2) On a non-converted lease, a deep well that produces natural gas (other than test production) before the date which is 5 years after the lease issuance date from a reservoir that has not produced from a deep well on any lease; or

(3) On a lease that is located in water entirely more than 200 meters but entirely less than 400 meters deep, a deep well for which drilling began on or after May 18, 2007, that produces natural gas (other than test production), including gas associated with oil production before May 3, 2013, and for which you have met the requirements prescribed in §203.44.

Qualified ultra-deep well means:

(1) On a lease that is located in water partly or entirely less than 200 meters deep that is not a non-converted lease, an ultra-deep well for which drilling began on or after March 26, 2003, that produces natural gas (other than test production), including gas associated with oil production, and for which you have met the requirements prescribed in §203.35 or §203.44, as applicable; or

(2) On a lease that is located in water entirely more than 200 meters and entirely less than 400 meters deep, or on a non-converted lease, an ultra-deep well for which drilling began on or after May 18, 2007, that produces natural gas (other than test production), including gas associated with oil production, and for which you have met the requirements prescribed in §203.35.

Qualified well means either a qualified deep well or a qualified ultra-deep well.

Redetermination means our reconsideration of our determination on royalty relief because you request it after:

(1) We have rejected your application;

(2) We have granted relief but you want a larger suspension volume;

(3) We withdraw approval; or

(4) You renounce royalty relief.

Renounce means action you take to give up relief after we have granted it and before you start production.

Reservoir means an underground accumulation of oil or natural gas, or both, characterized by a single pressure system and segregated from other such accumulations.

Royalty suspension (RS) lease means a lease that:

(1) Is issued as part of an OCS lease sale held after November 28, 2000;

(2) Is in locations or planning areas specified in a particular Notice of OCS Lease Sale offering that lease; and

(3) Is offered subject to a royalty suspension specified in a Notice of OCS Lease Sale published in theFederal Register.

Royalty suspension supplement (RSS) means a royalty suspension volume resulting from drilling a certified unsuccessful well that is applied to future natural gas and oil production generated at any drilling depth on, or allocated under an MMS-approved unit agreement to, the same lease.

Royalty suspension volume (RSV) means a volume of production from a lease that is not subject to royalty under the provisions of this part.

Sidetrack means, for the purpose of this subpart, a well resulting from drilling an additional hole to a new objective bottom-hole location by leaving a previously drilled hole. A sidetrack also includes drilling a well from a platform slot reclaimed from a previously drilled well or re-entering and deepening a previously drilled well. A bypass from a sidetrack (e.g., drilling around material blocking the hole, or to straighten crooked holes) is part of the sidetrack.

Sidetrack measured depth means the actual distance or length in feet a sidetrack is drilled beginning where it exits a previously drilled hole to the bottom hole of the sidetrack, that is, to its total depth.

Sunk costs for an authorized field means the after-tax eligible costs that you (not third parties) incur for exploration, development, and production from the spud date of the first discovery on the field to the date we receive your complete application for royalty relief. The discovery well must be qualified as producible under part 250, subpart A of this title. Sunk costs include the rig mobilization and material costs for the discovery well that you incurred before its spud date.

Sunk costs for an expansion or development project means the after-tax eligible costs that you (not third parties) incur for only the first well that encounters hydrocarbons in the reservoir(s) included in the application and that meets the producibility requirements under part 250, subpart A of this chapter on each lease participating in the application. Sunk costs include rig mobilization and material costs for the discovery wells that you incurred before their spud dates.

Ultra-deep well means either an original well or a sidetrack completed with a perforated interval the top of which is at least 20,000 feet TVD SS. An ultra-deep well subsequently re-perforated less than 20,000 feet TVD SS in the same reservoir is still an ultra-deep well.

Withdraw means action we take on a field that has qualified for relief if you have not met one or more of the performance conditions.

[63 FR 2616, Jan. 16, 1998, as amended at 67 FR 1872, Jan. 15, 2002; 69 FR 3509, Jan. 26, 2004; 69 FR 24053, Apr. 30, 2004; 73 FR 69504, Nov. 18, 2008]

§ 203.1   What is MMS's authority to grant royalty relief?

The Outer Continental Shelf (OCS) Lands Act, 43 U.S.C. 1337, as amended by the OCS Deep Water Royalty Relief Act (DWRRA), Public Law 104–58 and the Energy Policy Act of 2005, Public Law 109–058 authorizes us to grant royalty relief in four situations.

(a) Under 43 U.S.C. 1337(a)(3)(A), we may reduce or eliminate any royalty or a net profit share specified for an OCS lease to promote increased production.

(b) Under 43 U.S.C. 1337(a)(3)(B), we may reduce, modify, or eliminate any royalty or net profit share to promote development, increase production, or encourage production of marginal resources on certain leases or categories of leases. This authority is restricted to leases in the GOM that are west of 87 degrees, 30 minutes West longitude, and in the planning areas offshore Alaska.

(c) Under 43 U.S.C. 1337(a)(3)(C), we may suspend royalties for designated volumes of new production from any lease if:

(1) Your lease is in deep water (water at least 200 meters deep);

(2) Your lease is in designated areas of the GOM (west of 87 degrees, 30 minutes West longitude);

(3) Your lease was acquired in a lease sale held before the DWRRA (before November 28, 1995);

(4) We find that your new production would not be economic without royalty relief; and

(5) Your lease is on a field that did not produce before enactment of the DWRRA, or if you propose a project to significantly expand production under a Development Operations Coordination Document (DOCD) or a supplementary DOCD, that MMS approved after November 28, 1995.

(d) Under 42 U.S.C. 15904–15905, we may suspend royalties for designated volumes of gas production from deep and ultra-deep wells on a lease if:

(1) Your lease is in shallow water (water less than 400 meters deep) and you produce from an ultra-deep well (top of the perforated interval is at least 20,000 feet TVD SS) or your lease is in waters entirely more than 200 meters and entirely less than 400 meters deep and you produce from a deep well (top of the perforated interval is at least 15,000 feet TVD SS);

(2) Your lease is in the designated area of the GOM (wholly west of 87 degrees, 30 minutes west longitude); and

(3) Your lease is not eligible for deep water royalty relief.

[63 FR 2616, Jan. 16, 1998, as amended at 73 FR 69506, Nov. 18, 2008]

§ 203.2   How can I obtain royalty relief?

We may reduce or suspend royalties for Outer Continental Shelf (OCS) leases or projects that meet the criteria in the following table.

If you have a lease . . .And if you . . .Then we may grant you . . .
(a) With earnings that cannot sustain production ( i.e. , End-of-life lease )Would abandon otherwise potentially recoverable resources but seek to increase production by operating beyond the point at which the lease is economic under the existing royalty rate.A reduced royalty rate on current monthly production and a higher royalty rate on additional monthly production. (See §§203.50 through 203.56.)
(b) Located in a designated GOM deep water area ( i.e. , 200 meters or greater) and acquired in a lease sale held before November 28, 1995, or after November 28, 2000Propose an expansion project and can demonstrate your project is uneconomic without royalty reliefA royalty suspension for a minimum production volume plus any additional production large enough to make the project economic (see §§203.60 through 203.79).
(c) Located in a designated GOM deep water area and acquired in a lease sale held before November 28, 1995 ( Pre-Act lease )Are on a field from which no current pre-Act lease produced (other than test production) before November 28, 1995 ( Authorized field) A royalty suspension for a minimum production volume plus any additional volume needed to make the field economic. (See §§203.60 through 203.79.)
(d) Located in a designated GOM deep water area and acquired in a lease sale held after November 28, 2000Propose a development project and can demonstrate that the suspension volume, if any, for your lease is not enough to make development economicA royalty suspension for a minimum production volume plus any additional volume needed to make your project economic (see §§203.60 through 203.79).
(e) Where royalty relief would recover significant additional resources or, offshore Alaska or in certain areas of the GOM, would enable developmentAre not eligible to apply for end-of-life or deep water royalty relief, but show us you meet certain eligibility conditionsA royalty modification in size, duration, or form that makes your lease or project economic (see §203.80).
(f) Located in a designated GOM shallow water area and acquired in a lease sale held before January 1, 2001, or after January 1, 2004, or have exercised an option to substitute for royalty relief in your lease termsDrill a deep well on a lease that is not eligible for deep water royalty relief and you have not previously produced oil or gas from a deep well or an ultra-deep wellA royalty suspension for a volume of gas produced from successful deep and ultra-deep wells, or, for certain unsuccessful deep and ultra-deep wells, a smaller royalty suspension for a volume of gas or oil produced by all wells on your lease (see §§203.40 through 203.49).
(g) Located in a designated GOM shallow water areaDrill and produce gas from an ultra-deep well on a lease that is not eligible for deep water royalty relief and you have not previously produced oil or gas from an ultra-deep wellA royalty suspension for a volume of gas produced from successful ultra-deep and deep wells on your lease (see §§203.30 through 203.36).
(h) Located in planning areas offshore AlaskaPropose an expansion project or propose a development project and can demonstrate that the project is uneconomic without relief or that the suspension volume, if any, for your lease is not enough to make development economicA royalty suspension for a minimum production volume plus any additional volume needed to make your project economic (see §§203.60, 203.62, 203.67 through 203.70, §§203.73 and 203.76 through 203.79).

[67 FR 1872, Jan. 15, 2002, as amended at 73 FR 69506, Nov. 18, 2008]

§ 203.3   Do I have to pay a fee to request royalty relief?

When you submit an application or ask for a preview assessment, you must include a fee to reimburse us for our costs of processing your application or assessment. Federal policy and law require us to recover the cost of services that confer special benefits to identifiable non-Federal recipients. The Independent Offices Appropriation Act (31 U.S.C. 9701), Office of Management and Budget Circular A–25, and the Omnibus Appropriations Bill (Pub. L. 104–134, 110 Stat. 1321, April 26, 1996) authorize us to collect these fees.

(a) We will specify the necessary fees for each of the types of royalty relief applications and possible MMS audits in a Notice to Lessees. We will periodically update the fees to reflect changes in costs, as well as provide other information necessary to administer royalty relief.

(b) You must file all payments electronically through the Pay.gov Web site and you must include a copy of the Pay.gov confirmation receipt page with your application or assessment. The Pay.gov Web site may be accessed through a link on the MMS Offshore Web site at: http://www.mms.gov/offshore/ homepage or directly through Pay.gov at: https://www.pay.gov/paygov/.

[73 FR 49946, Aug. 25, 2008]

§ 203.4   How do the provisions in this part apply to different types of leases and projects?

The tables in this section summarize the similar application and approval provisions for the discretionary end-of-life and deep water royalty relief programs in §§203.50 to 203.91. Because royalty relief for deep gas on leases not subject to deep water royalty relief, as provided for under §§203.40 to 203.48, does not involve an application, its provisions do not parallel the other two royalty relief programs and are not summarized in this section.

(a) We require the information elements indicated by an X in the following table and described in §§203.51, 203.62, and 203.81 through 203.89 for applications for royalty relief.

Information elementsEnd-of-life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) Administrative information reportXXXX
(2) Net revenue and relief justification report (prescribed format)X
(3) Economic viability and relief justification report (Royalty Suspension Viability Program (RSVP) model inputs justified with Geological and Geophysical (G&G), Engineering, Production, & Cost reports)  XXX
(4) G&G report  XXX
(5) Engineering report  XXX
(6) Production report  XXX
(7) Deep water cost report  XXX

(b) We require the confirmation elements indicated by an X in the following table and described in §§203.70, 203.81 and 203.90 through 203.91 to retain royalty relief.

Confirmation elementsEnd-of-life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) Fabricator's confirmation report  XXX
(2) Post-production development report approved by an independent certified public accountant (CPA)  XXX

(c) The following table indicates by an X, and §§203.50, 203.52, 203.60 and 203.67 describe, the prerequisites for our approval of your royalty relief application.

Approval conditionsEnd-of-life leaseDeep water
ExpansionPre-act leaseDevelopment project
(1) At least 12 of the last 15 months have the required level of productionX
(2) Already producingX
(3)A producible well into a reservoir that has not produced before  XXX
(4) Royalties for qualifying months exceed 75% of net revenue (NR)X
(5) Substantial investment on a pre-Act lease (e.g., platform, subsea template)
(6) Determined to be economic only with relief  XXX

(d) The following table indicates by an X, and §§203.52 and 203.74 through 203.75 describe, the prerequisites for a redetermination of our royalty relief decision.

Redetermination conditionsEnd-of-Life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) After 12 months under current rate, criteria same as for approvalX
(2) For material change in geologic data, prices, costs, or available technology  XXX

(e) The following table indicates by an X, and §§203.53 and 203.69 describe, the characteristics of approved royalty relief.

Relief rate and volume, subject to certain conditionsEnd-of-life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) One-half pre-application effective lease rate on the qualifying amount, 1.5 times pre-application effective lease rate on additional production up to twice the qualifying amount, and the pre-application effective lease rate for any larger volumesX
(2) Qualifying amount is the average monthly production for 12 qualifying monthsX
(3) Zero royalty rate on the suspension volume and the original lease rate on additional production  XXX
(4) Suspension volume is at least 17.5, 52.5 or 87.5 million barrels of oil equivalent (MMBOE)    X
(5) Suspension volume is at least the minimum set in the Notice of Sale, the lease, or the regulations  X  X
(6) Amount needed to become economic  XXX

(f) The following table indicates by an X, and §§203.54 and 203.78 describe, circumstances under which we discontinue your royalty relief.

Full royalty resumes whenEnd-of-life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) Average NYMEX price for last 12 months is at least 25 percent above the average for the qualifying monthsX
(2) Average NYMEX price for last calendar year exceeds $28/bbl or $3.50/mcf, escalated by the gross domestic product (GDP) deflator since 1994  XX
(3) Average prices for designated periods exceed levels we specify in the Notice of Sale or the lease  X  X

(g) The following table indicates by an X, and §§203.55 and 203.76 through 203.77 describe, circumstances under which we end or reduce royalty relief.

Relief withdrawn or reducedEnd-of-life leaseDeep water
Expansion projectPre-act leaseDevelopment project
(1) If recipient requestsXXXX
(2) Lease royalty rate is at the effective rate for 12 consecutive monthsX
(3) Conditions occur that we specified in the approval letter in individual casesX
(4) Recipient does not submit post-production report that compares expected to actual costs  XXX
(5) Recipient changes development system  XXX
(6) Recipient excessively delays starting fabrication  XXX
(7) Recipient spends less than 80 percent of proposed pre-production costs prior to start of production  XXX
(8) Amount of relief volume is produced  XXX

[67 FR 1873, Jan. 15, 2002, as amended at 69 FR 3509, Jan. 26, 2004]

§ 203.5   What is MMS's authority to collect information?

The Paperwork Reduction Act of 1995 (PRA) requires us to inform you that MMS may not conduct or sponsor and you are not required to respond to a collection of information unless it displays a currently valid OMB control number. OMB approved the information collection requirements in this part 203 under 44 U.S.C. 3501 et seq. in two actions. The information collection requirements in §§203.50 through 203.91 are approved under OMB control number 1010–0071, and those in §§203.40 through 203.48 are approved under 1010–0153.

[69 FR 3509, Jan. 26, 2004]

Browse Next