SURFACE TRANSPORTATION BOARD DECISION DOCUMENT | |||
Decision Information | |||
Docket Number:   | FD_30186_2 | ||
Case Title:   | TONGUE RIVER RAILROAD CO.--RAIL CONSTRUCTION AND OPERATION--ASHLAND TO DECKER, MONTANA | ||
Decision Type:   | Decision | ||
Deciding Body:   | Entire Board | ||
Decision Summary | |||
Decision Notes:   | (1) GRANTED THE APPLN. TO CONSTRUCT THE 4-MILE CREEK ALTERNATIVE, WITH CONDS.; (2) DENIED REQUESTS FOR ORAL ARGUMENT; (3) ACCEPTED PREVIOUSLY SUBMITTED MATERIAL; AND (4) GRANTED THE PET. TO REOPEN, REMOVED A PRIOR SEC. 2(C) REQUIR., AND DENIED REQUEST TO REVOKE AUTHORIZATION, IN FD NO'S 30186 AND 30186 SUB 1. | ||
Decision Attachments | |||
103 KB | |||
Approximate download time at 28.8 kb: 1 Minutes | |||
Note: If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
Full Text of Decision | |||
20262 EB
This decision will be printed in the bound volume of the STB
printed reports at a later date.
In Finance Docket No. 30186 (Sub-No. 2), authority is
granted to construct and operate a line of railroad between
Ashland and Decker, MT, using the Four Mile Creek Alternative,
subject to conditions. Finance Docket Nos. 30186 and 30186 (Sub-No. 1) are reopened, a prior condition removed, and new
conditions imposed. Both authorities are conditioned, inter
alia, on a 3-year deadline to complete construction and on
reporting requirements during that period of time.
SUMMARY
The Tongue River Railroad Company (TRRC or the Railroad)
seeks authority to build a 41-mile rail line between Ashland and
Decker, MT. The line would connect with an 89-mile line between
Miles City, MT, and Ashland, that the Railroad was previously
authorized to construct but has not yet built. Together the
130-mile line is to provide a new, shorter route for the carriage
of coal from the Wyoming Powder River Basin to eastern
destinations.
The line would connect with a line of the Burlington
Northern Railroad Company (BN) at both TRRC's southern and
northern termini. The new line would serve a few mines in the
Decker area directly. Otherwise, it is chiefly an alternative
route for coal that already moves over BN. On this record, the
BN has made no commitment to use the proposed line, and has
neither supported nor opposed TRRC's application.
The Railroad has offered two alternative routes for the
proposed construction of the new segment. The first, or TRRC's
"preferred" route, extends from Ashland south following the
Tongue River, then passes about one mile west of the Tongue River
Reservoir. It terminates at a rail line owned by the Spring
Creek Coal Company, which provides access to BN. The extension
along TRRC's preferred route would require five bridges and one
tunnel. Four of the bridges would be 500 feet in length each,
and one 400 feet long. The tunnel would be 600 feet long.
At the request of the Board's Section of Environmental
Analysis (SEA), the Railroad offered an alternative routing,
referred to as the Four Mile Creek Alternative. This route would
extend southeast from Ashland along Four Mile Creek, climbing a
2.31% grade from the Tongue River. It would then turn southward
about three miles from its divergence from the river and continue
on that course to its junction with the proposed extension near
the Tongue River Reservoir.
This decision also considers a petition filed by the Northern Plains Resource Council (NPRC) on November 20, 1995, to reopen and revoke the authorization in Finance Docket Nos. 30186 and 30186 (Sub-No. 1) (ICC served Sept. 4, 1985) (TRRC I). That decision was modified on administrative appeal by the Commission in a decision served May 9, 1986 (TRRC II).
In the Sub-No. 2 proceeding, we will grant the application
to construct and operate the proposed extension over the Four
Mile Creek Alternative Route, subject to environmental conditions
recommended by SEA in Section 5A and B of Chapter 3 of the Final
Environmental Impact Statement (FEIS). In addition, all of this
authority is conditioned on the requirement that TRRC construct
the entire line between Miles City and Decker within 3 years of
the service date of this decision and comply with periodic
reporting requirements during that period of time to keep the
Board apprised of the progress that is being made. In the lead
and Sub-No. 1 proceedings, we will grant the petition to reopen
the proceeding and eliminate one condition, but will otherwise
deny the request to revoke the construction authorization.
During the course of this proceeding, numerous motions and
petitions to file evidence and argument have been submitted.
Numerous motions to strike have also been filed. In the interest
of obtaining the most complete record possible, we will accept
all filings into the record and deny all opposing motions. As
the record is sufficient for us to resolve all issues raised by
the parties, we will deny all outstanding requests for oral
argument in this matter.
First Application. In its application in the lead docket,
originally filed on June 2, 1983 (amended January 2, 1984), TRRC
sought ICC approval for its construction of 89 miles of railroad
between Miles City, MT, and two termini located near Ashland, MT.
The proposed line of railroad was to serve future coal mines in
the Ashland area, and connect with BN's main line at Miles City
for shipment of the coal to eastern and western destinations. In
an initial decision, an Administrative Law Judge (ALJ) approved
the application (TRRC I). NPRC appealed the initial decision.
In TRRC II, the ICC denied both appeals and approved the
application, subject to two conditions.
First, the ICC conditioned TRRC's start of operations upon a
ruling from the Department of the Interior (DOI) that TRRC's
operation of the line would not result in a violation of section
2(c) of the Mineral Lands Leasing Act (MLLA), 30 U.S.C. 202,
which prohibits railroads from holding federal leases or permits
for mining coal. Second, the ICC conditioned approval upon
TRRC's meeting the environmental mitigating conditions contained
in Appendix B to the initial decision.
Second Application. TRRC notified the ICC in January 1989
that it intended to file a second construction application.
Under the National Environmental Policy Act (NEPA) and related
environmental laws, the environmental effects of the proposal
must be considered, and we have thoroughly done so.
The ICC's then Section of Energy and Environment (SEE), now
SEA (hereinafter, all references will be to SEA) published in the
Federal Register a Notice of Intent to Prepare an Environmental
Impact Statement (EIS) addressing the environmental effects of
the project and to hold public scoping meetings.(3) In December
1989, public scoping meetings were held in Montana. At these
meetings, members of the public identified areas of environmental
concern regarding the proposed extension that they believed
needed to be addressed in the EIS. Based on SEA's independent
analysis of the comments received, site visits, and meetings and
correspondence with federal and state agencies, the ICC published
a "final scope" of the EIS in the Federal Register in March 1990.
On June 28, 1991, TRRC filed the application at issue,
seeking approval to construct and operate approximately 41 miles
of railroad running south from Ashland to the Spring Creek/Decker
area. The ICC accepted the application and notice was published
in the Federal Register.(4) Numerous comments both supporting and
opposing the proposed extension were filed, including requests
for an oral hearing.(5)
At the same time, SEA went forward with its requisite hard
look at the environmental consequences of the proposal,
considering the potential environmental impacts associated with
TRRC's preferred route, the Four Mile Creek Alternative, and the
"no-build" alternative. SEA's Draft Environmental Impact
Statement (DEIS) was served on the parties on July 17, 1992.
Hearings on the merits were held in Lame Deer, Forsyth, and Miles
City, MT, and in Sheridan, WY. Post hearing briefs and replies
were requested and filed.(6) On March 17, 1994, SEA issued a
Supplement to the DEIS (SDEIS) and requested comments on it. A
FEIS was served on April 11, 1996. In the FEIS, SEA recommended
the Four Mile Creek Alternative as the environmentally preferable
choice because it would avoid the environmentally sensitive
Tongue River Canyon. Based on SEA's independent analysis of the
project, comments to the DEIS and SDEIS, and the other
information before it, SEA developed appropriate mitigation
conditions addressing potential environmental impacts if either
construction route before the agency were approved.
Following issuance of the FEIS, TRRC filed a petition on
May 3, 1996, asking the Board to take a number of actions that
would, in essence, lead the Board to conclude that the Railroad's
preferred alignment rather than the Four Mile Creek Alternative
recommended by SEA is the environmentally preferable choice. On
May 14, 1996, Director John Wardell, Montana Office, U.S.
Environmental Protection Agency (EPA), filed comments concurring
in SEA's conclusions, but raising questions about the purpose of,
and need for, the project itself. On May 23, 1996, Dr. Stan
Wilmoth of the Montana Historical Society (MHS) filed comments in
which he expressed concern about adverse historic effects
stemming from any construction. On May 31, 1996, Kemper
McMaster, field supervisor for the Fish & Wildlife Service's
(FWS) Montana Field Office, concurred unconditionally with SEA's
conclusion that the Four Mile Creek Alternative was
environmentally preferable to TRRC's preferred route.
As discussed below, we find that, notwithstanding the
potential environmental impacts associated with this proposal,
the present and future public convenience and necessity require
or permit the construction and operation of the Four Mile Creek
Alternative. We agree with SEA that the Four Mile Creek route is
the environmentally preferable construction option and adopt
SEA's environmental analysis and the conclusions reached in the
FEIS. We also agree with SEA that, with the recommended
mitigation, construction and operation of the Four Mile Creek
Alternative should meet applicant's project goals of providing
more efficient service to coal shippers in this area, without
having an unduly severe impact on the environment. Accordingly,
we will impose the environmental conditions recommended by SEA
that are set forth in Appendix B. Additionally, we will require
that TRRC complete construction of the entire line between Miles
City and Decker within 3 years of the service date of this
decision and comply with periodic reporting requirements during
that period of time.
Description. The proposed extension will consist of 41
miles of main track with two passing sidings of about 8,500 feet
and three set-out tracks with a minimum total length of 1,650
feet. As indicated, the line would connect with TRRC's yet-to-be-built Ashland-to-Miles City line and create a north-south
connection between the lines at the Spring Creek/Decker mines and
the BN lines at Miles City. TRRC asserts that the construction
and operation is designed "to capture additional existing coal
traffic originating at the Spring Creek and Decker mines, plus
some tonnage being hauled by BN from the Gillette, Wyoming area."
The line is a short cut for coal traffic moving east. It
shortens the route for that traffic by saving 130 to 160 miles,
depending on where the traffic originates. The existing BN line
runs northwest of the Powder River Basin to intersect BN's east-west line near Billings, MT. According to TRRC, the proposed
130-mile line (the original 89-mile line with the 41-mile
extension) will provide rail service for the first time to the
largest undeveloped reserves (estimated at over 10 billion tons)
of low sulfur sub-bituminous coal in the United States.
In order to provide service between Miles City and Decker,
TRRC states that it will exercise its Ashland option approved in
TRRC I and II. As authorized there, the single track main line
will begin south and west of Miles City and will extend southward
paralleling the Tongue River on the west side to milepost 63.6
(about 64 miles). At that point, it will cross the Tongue River
and continue nine miles on the east side of the river to Ashland.
At about milepost 72.2, the main line will split, with one branch
proposed to parallel the Tongue River 8.9 miles to "Terminus
Point 1," where the construction of the 41-mile segment is
proposed to begin. The other branch was proposed to follow Otter
Creek 7.7 miles to Terminus Point 2.
TRCC has indicated that construction is to be completed in 3
years for the entire alignment, including the permitted rail line
from Miles City to Terminus Point 1 and the extension from
Terminus Point 1 to Spring Creek. The line will consist of a
single track main line with a right-of-way averaging 200 feet.
The alignment will be designed to operate unit coal trains of
about 112-125 cars with a speed of 40-50 miles per hour. TRRC
plans to construct new terminal facilities at Miles City, which
will consist of buildings for crews, operations, and a
headquarters. Three additional tracks 7800 feet long will be
constructed to handle yard activities.
Upon completion of the entire line, TRRC's sole connections
will be with BN. The present route for coal traffic, which
originates in the Powder River Basin and is destined for various
upper midwest points, travels northwest through Sheridan to
Huntley, and then eastward through Miles City. TRRC believes
that it can obtain traffic originating in the Powder River Basin
and, by interchanging and routing the traffic over its line,
reduce the distance for this traffic about 15 percent of the
total rail haul (by 130-160 miles). Traffic originating in the
Powder River Basin will move from the origin, through Sheridan,
then northeasterly to Decker, where BN will interchange the
traffic with TRRC. The coal will then move to Miles City where
it will be interchanged again with BN.
Markets - coal sources and destinations. TRRC states that
the market potential for coal from the Ashland area, where TRRC
is currently authorized to construct and operate a rail line, is
less favorable than it was in 1983.(7) However, it adds that,
because Congress passed the Clean Air Act Amendments in 1990,
there has been an increased interest in low sulfur coal from the
Powder River Basin. Applicant states that, in 1991, BN hauled
over 150 million tons of coal, principally from the Wyoming
Powder River Basin, and that BN has announced a targeted volume
increase of 50 percent by the year 2000. According to TRRC, much
of this increased delivery of coal will originate in Wyoming for
central and lower midwest destinations. TRRC maintains that a
benefit of the shortened mileage to the upper midwest will be to
relieve current and future congestion over the heavily-traveled
BN central corridor via Alliance, NE.
TRRC asserts that the present competitive market reach of
Powder River coal that will use TRRC routing is well-defined,
based on current coal contracts and spot purchases. The railroad
states that the Clean Air Act of 1970 prompted states such as
Minnesota and Michigan to develop statewide or regional
regulations that limited sulfur dioxide emissions for all plants.
According to TRRC, that fact, coupled with cost savings by using
Powder River Basin coal, makes such coal a prime source for
meeting more stringent sulfur dioxide emission standards under
the amended Act.
Applicant states that the present market for the coal that
TRRC would haul consists of electric utilities and industries in
Minnesota, Wisconsin, and Michigan. According to TRRC, in 1991,
the Decker/Spring Creek mines and the Wyoming mines produced over
16.5 million tons of coal, most of which were shipped along the
Sheridan-Hardin-Miles City route. Of this total, approximately
11 million tons were shipped to the Midwest Energy Resources,
Inc. (MER) terminal in Superior, WI, for lake vessel movement
beyond, with the remaining tonnage being shipped on rail or
rail/barge to Minnesota and Wisconsin destinations.
Financial information. The financial evidence of record can
be divided into two broad categories: (1) financial information
relating to the construction and financing of the line; and (2)
information relating to the operations of the line in its first
years of existence. As to the construction phase, TRRC provides
preliminary estimates of the cost of construction and a financing
plan (with related balance sheet and cash flow and income
statement data). With respect to the operations phase, the
railroad provides a 10-year income forecast which is challenged
by NPRC. This information is discussed in more detail in
Appendix A.
TRRC organizational structure. TRRC was formed on June 19,
1981, under the provisions of the Montana Uniform Limited
Partnership Act. The limited partnership is comprised of
Transportation Properties (TP), the general partner, and Tongue
River Holdings, Inc. (TRH), a Montana corporation and the limited
partner. TP is a Montana general partnership comprised of the
following general partners: ThermRail, Inc. (ThermRail), a
Washington corporation, and WesRail, Ltd. (WesRail). WesRail, in
turn, is a Montana limited partnership composed of Wesco
Transportation, Inc. (Wesco) and Bellford & Company.
Applicant states that Wesco Resources, Inc. (Wesco
Resources) of Billings, MT, is the general partner of WesRail and
the parent of Wesco. Through other partnership entities or
relationships, Wesco Resources has surface and coal interests in
Rosebud and Powder River Counties. ThermRail is a subsidiary of
Washington Energy Company (WECO), a Washington Corporation.
Thermal Energy, Inc. (Thermal), another subsidiary of WECO, has
surface and coal interests in Rosebud and Powder River Counties.
Applicant states that none of the partners of TRRC, TP
(ThermRail, WesRail), or TRH has any interest in any federal or
private coal properties. Each of the partners has invested in
TRRC for transportation and investment purposes. The partnership
agreement, signed June 19, 1981, and subsequently amended,
provides for the separate and distinct management and conduct of
the partnership solely through a management committee.
Application at 6.(8)
Position of Parties. A number of parties support the
proposed construction. These include: NERCO Inc., which is the
owner and operator of the Spring Creek Coal Mine at Decker, and a
major U.S. coal producer; the Detroit Edison Company, which is
the corporate parent of NERCO; MER, another subsidiary of Detroit
Edison, which operates a rail to water transfer facility in
Superior, WI (in 1991, MER transloaded in excess of 11 million
tons of Powder River Basin coal); Dairyland Power Cooperative,
which is an operator of four electric generating stations that
distribute electricity to 28 rural electrical cooperatives in
Wisconsin, Illinois and Minnesota; OXY USA, Inc., which owns
surface and coal leases in the Otter Creek area; the Cook
Mountain Partnership, a Montana general partnership, which owns
about 465 million tons of mineable coal reserves; and Montco,
which is a Montana general partnership that proposes to mine coal
along the 89-mile segment previously approved. Montana Governor
Marc Racicot, Montana's United States Senators Max Baucus and
Conrad Burns, Montana State Senators Marian Hanson, Tom Zook and
Jessica Stickney (representing districts which include Miles
City), the Custer County Commissioners (Miles City is in Custer
County) and the City Council of Miles City support the proposed
construction. Former Montana Governor Stan Stevens and former
Congressman Ron Marlenee also submitted letters in support.
Several parties oppose the proposed construction. These
include: NPRC, which is a coalition of ranchers,
environmentalists, and other interested persons (NPRC has raised
both economic and environmental arguments against the proposed
construction); the Northern Cheyenne Tribe, which owns and
occupies the Northern Cheyenne Reservation in Southeast Montana
(the proposed extension would adjoin the eastern boundary of the
reservation, including Birney Village which is adjacent to the
proposed line); the Northern Cheyenne have requested the
imposition of conditions to mitigate the impact on the
reservation of the construction and operation of the line; the
Crow Tribe, which receives revenue from BN for an easement for
its Sheridan-Hardin Line through the Crow Indian Reservation in
Montana (the Crow are concerned that the proposed construction
would divert traffic and reduce Crow revenues from the easement);
and OW Ranch, which includes 17,000 acres northeast of Decker and
is adjacent to the proposed extension (600 head of cattle and
2000 sheep graze on the ranch, which is used chiefly as a hunting
preserve). Rosebud County and the City of Forsyth also oppose
construction of the proposed line because of anticipated adverse
environmental impacts. Labor interests are represented by the
United Transportation Union and the Brotherhood of Locomotive
Engineers. They express concern about the potential for loss of
jobs and the possibility that TRRC might employ nonunion
employees.
Background. On July 17, 1992, SEA issued a DEIS evaluating
the potential environmental effects of TRRC's proposed
construction and operation of the rail line extension. In the
DEIS, SEA thoroughly analyzed the environmental impacts of: (1)
TRRC's preferred alignment, which generally parallels the Tongue
River; (2) the Four Mile Creek Alternative, which would avoid the
Tongue River Dam and a 10-mile section of the river just north of
the Tongue River Dam; and (3) the "no build" alternative.(9) SEA
preliminarily concluded in the DEIS that the Four Mile Creek
Alternative would be less environmentally harmful than TRRC's
preferred alignment if the proposed construction were approved.
SEA noted that TRRC's preferred routing through the approximately
10-mile canyon just north of the dam would affect the ecology of
the river more than any other route because of the narrowness of
the canyon and the resulting proximity of the line to the river
and its bank.
SEA received and considered written comments on the DEIS
from the parties and interested federal, state, local and private
agencies and individuals. SEA also considered statements
presented at the four public hearings conducted in August 1992.
Numerous persons commented at these hearings about the DEIS and
various environmental issues.
Because of concerns raised through the commenting process,
SEA issued a SDEIS on March 17, 1994. There, SEA preliminarily
concluded that the Four Mile Creek Alternative would have more
adverse environmental consequences than TRRC's preferred route.
SEA pointed out that this alternative would result in land
disturbances from cut and fill procedures during construction,
erosion and loss of soil, closer proximity to residences,
deforestation, loss of big game and other wildlife habitat, more
fuel consumption and increased air pollution. SEA received
written comments on the SDEIS from numerous parties.
In its FEIS, SEA again analyzed the two possible
construction alternatives and the "no build" option. In the
FEIS, SEA was persuaded that the Four Mile Creek Alternative
would be the environmentally preferable construction route
because it would avoid the environmentally sensitive Tongue River
Canyon. SEA determined that this alternative would allow TRRC to
meet its project goals of providing more efficient service to
coal shippers in the area without having an unduly severe impact
on the environment. The "no-build" alternative, while
environmentally benign, would not meet those objectives, SEA
explained. SEA's analysis of the three alternatives, which we
adopt, is summarized below.
Four Mile Creek Alternative. TRRC proposed the Four Mile
Creek Alternative as the only acceptable alternative to its
preferred route. The alternative would duplicate TRRC's
preferred route, starting from the terminus on its previously-authorized, but not constructed, 89-mile line in Ashland,
paralleling the river until the confluence of the Tongue River
and Four Mile Creek. It then would leave TRRC's preferred route
and extend southwest along Four Mile Creek, climbing from the
Tongue River. Finally, it would turn southeastward approximately
three miles from the divergence point and continue on that course
to its junction with TRRC's preferred route near the Tongue River
Reservoir. The Four Mile Creek Alternative would be
approximately 10 miles longer than TRRC's preferred route. Like
the preferred route, the Four Mile Creek Alternative would
connect with BN via a rail line owned by the Spring Creek Coal
Company, which provides rail service and connections for Decker-area coal shippers.
In the FEIS, SEA explained that the Four Mile Creek
Alternative would avoid the Tongue River Canyon, which is located
between the Tongue River Dam and the confluence of the Tongue
River and Four Mile Creek. As the river meanders through the
canyon, it provides diverse habitat for aquatic and terrestrial
wildlife. This area of the river has been recognized as
important habitat for migrating and wintering bald eagles.
Additionally, since the mid-1980s, several bald eagles have
nested in the cottonwood trees along this stretch of the river.
Because this portion of the river does not freeze, it also
provides important year-round habitat for bald eagles and
waterfowl. The Four Mile Creek Alternative would avoid adverse
impacts to nesting and wintering bald eagles and wintering
wildfowl. Moreover, because the canyon is narrow, any ranching
and farming operations are close to the river. Some of these
operations would be bisected by TRRC's preferred route. The Four
Mile Creek Alternative would also avoid these impacts.
SEA further pointed out that the Tongue River Reservoir
State Recreation Area and the Tongue River provide popular
recreational, fishing, hunting and scenic opportunities year-round. The region from the reservoir northwards along the river
to its confluence with the Yellowstone River at Miles City is
relatively undeveloped. Because of the canyon's narrow confines,
the variety of plant and animal life and the scenery along this
approximately 10-mile stretch of the river are particularly
noteworthy. The river valley contrasts with the surrounding arid
and rugged hills and buttes. The alternative would avoid
impairing these resources.
SEA also noted that concerns had been raised about the
potential impacts to the river from the construction of the five
railroad bridges and the tunnel that would be required on TRRC's
preferred route within the canyon. These concerns included
potential channelization, erosion and silting, flooding, and
impacts from potential spills during operations. The Four Mile
Creek Alternative would avoid the need to construct the bridges
and tunnel.
SEA further noted that, throughout this environmental review
process, two federal agencies have consistently recommended the
Four Mile Creek Alternative, or the "no build" alternative,
instead of TRRC's preferred route: the U.S. Fish and Wildlife
Service (FWS)(10) and the U.S. Environmental Protection Agency
(EPA).(11) SEA relied on the advice and expertise of these agencies
in analyzing potential environmental impacts and in determining
the environmentally preferable route.
As discussed in the SDEIS and FEIS, SEA recognized that
there could be potential safety risks and other environmental
impacts associated with operation of this alternative route.
Moreover, it would entail land disturbance from cut and fill
procedures during construction, erosion and loss of soil,
deforestation, loss of big game habitat, closer proximity to
residences, more fuel consumption, and increased air pollution.
Because the route would traverse pronghorn habitat, the fenced
right-of-way could inhibit pronghorn daily and seasonal
migration.
With respect to safety, TRRC's principal concern regarding
safe operations was the effect of the steep descending 2.31%
grade on operations by loaded unit trains. In the SDEIS, SEA
indicated that this grade could pose an increased risk for
derailments compared to TRRC's preferred route. But SEA
ultimately concluded that there are design and operating options
by which TRRC could mitigate potential safety problems and that,
despite the difficult grade, loaded train operations could be
safely performed. In reaching this conclusion, SEA consulted
with the Federal Railroad Administration (FRA), which concurred
that the Four Mile Creek Alternative could be operated safely.
Moreover, as SEA noted in the FEIS, TRRC has acknowledged that
operations could be conducted on the alternative route, albeit
not in line with its preferred design and operations parameters,
and with a considerable increase in construction and operating
costs.
SEA acknowledged that there are some other disadvantages
associated with this route. This route would require cut and
fill that could significantly alter and scar the area and change
the natural land configuration for the duration of rail use.
Thus, there would be a potential for erosion and soil loss within
the Four Mile Creek drainage equal to or greater than that for
TRRC's preferred route. The necessity of laying the right-of-way
on the north-facing slopes of the Four Mile Creek drainage would
mean removing ponderosa pine/juniper acreage, habitat for big
game, and breeding bird populations. As described in the SDEIS,
SEA also noted that this route would cross more residential
access roads than TRRC's preferred alignment, and would be as
close as 100 feet to two residences. Moreover, the steeper grade
of this route would require more locomotives during rail
operations, resulting in more fuel consumption and potentially
more air pollution than operations over TRRC's preferred route.
Nevertheless, SEA concluded that the Four Mile Creek
Alternative was the environmentally preferable construction
option and would allow TRRC to meet its project goals of
providing more efficient service to coal shippers in the area
without having an unduly severe impact on the environment.
TRRC Preferred Route. From the terminus on its 89-mile line
from Ashland to Decker, TRRC's preferred route would follow the
Tongue River, generally paralleling the eastern shore until south
of the Northern Cheyenne Indian Reservation, crossing the river
several times and passing to the west of the Tongue River
Reservoir.
SEA noted TRRC's claim that its preferred route, despite the
need to construct five bridges and a tunnel, would be preferable
from an engineering standpoint. As discussed in the DEIS, SDEIS
and FEIS, it would provide a relatively flat grade so that
operations would require fewer locomotives and less fuel, thus
lowering potential fuel emissions. Further, because TRRC's
preferred route would use the flat and even terrain of the Tongue
River Canyon, there would be a reduced risk for train
derailments. Therefore, SEA found that TRRC's preferred route
would be less costly to build and operate than the Four Mile
Creek Alternative.
As SEA explained, however, the principal environmental
disadvantage of TRRC's preferred route is that it would operate
through the environmentally sensitive Tongue River Canyon, and
would require the construction of five bridges and a tunnel in
the canyon. SEA further noted that FWS and EPA, among the
primary federal agencies SEA relies on to assist it in
identifying and evaluating the environmental impacts associated
with proposed construction projects, have consistently advised
against permitting construction of TRRC's preferred route to
avoid damaging this environmentally sensitive canyon.
In its comments on the SDEIS, EPA disagreed with SEA's
preliminary identification of the TRRC preferred route as the
environmentally preferable alternative.(12) FWS notified SEA that
four endangered species could be affected by TRRC's proposed
extension (i.e., either TRRC's preferred route or the Four Mile
Creek Alternative): peregrine falcon, black-footed ferret,
pallid sturgeon, and bald eagle. SEA's detailed analysis under
the Endangered Species Act revealed that the bald eagle could be
adversely affected, although not jeopardized, if TRRC's preferred
route is approved and constructed because the Tongue River Canyon
provides documented habitat for that species.
Because of this potential impact, SEA prepared a Biological
Assessment (BA) analyzing the impacts to this species, and sought
FWS's concurrence with the BA's conclusion that there would be no
undue adverse impact to the bald eagle. According to SEA, FWS
responded in its Biological Opinion (BO) that TRRC's preferred
route would not unduly interfere with the bald eagle recovery
program in Montana. FWS also stated, however, that potential
environmental impacts associated with constructing and operating
the railroad through the Tongue River Canyon would be far more
difficult to mitigate than the overall adverse impacts of the
Four Mile Creek Alternative. FWS stated that none of the adverse
environmental impacts would occur if the "no build" alternative
were selected.
As previously noted, TRRC's preferred route would require
construction of five bridges and a tunnel. When, as here,
construction involves wetlands and/or waters of the United
States, the railroad must obtain a permit under section 404 of
the Clean Water Act. The U.S. Army Corps of Engineers (the
Corps) issues such permits only for the least environmentally
damaging practicable alternative.
According to SEA, although the Corps did not formally
identify a preferred alternative during this EIS process, it did
review the environmental documents to ensure that the EIS
included full disclosure and contained sufficient information for
the Corps to make its permitting decision. In a letter dated
July 29, 1994, the Corps stated that TRRC's preferred route would
have greater impact to the aquatic ecosystem than the Four Mile
Creek Alternative.
SEA added that the Corps requested further information about
wetlands identification and delineation for TRRC's preferred
route and, on review of a further study submitted by TRRC, the
Corps determined that TRRC's preferred route is reasonable, given
safety factors, and that wetlands would not be a significant
issue here. The Corps further stated, however, that a section
404 permit application would be needed for both the proposed
extension and the original 89-mile line, for which the Corps
permit has now expired.
Throughout the environmental review process, SEA received
numerous comments regarding the natural beauty and intrinsic
value of the Tongue River Canyon and the need to protect these
resources. As the comments show, many believe that the
construction and operation of a rail line through this area,
particularly through the canyon, would diminish and possibly
destroy its aesthetic and natural appeal. Commenters have argued
that noise and air pollution would be unwelcome, right-of-way
fencing would inhibit wildlife movement, wildlife would be
stressed and killed by trains, and overall day-to-day train
operations would disturb the tranquility of the area.
SEA noted that the canyon is also popular for fishing and
boating, and other recreation activities. The recreation area is
adjacent to the reservoir and provides camping and picnic
facilities. The reservoir is a popular recreation location, and
the shores and nearby hills provide sites for vacation homes.
Thus, SEA concluded that the TRRC preferred route was not
the environmentally preferable construction option.
The "No Build" Alternative. According to SEA, this
alternative would be environmentally neutral because none of the
environmental impacts associated with either TRRC's preferred
route or the Four Mile Creek Alternative would occur. The "no
build" alternative would preserve the status quo. The present
movement of coal from the Decker mines would be unaffected
because BN is already providing service to these mines via an
alternate route; the present BN movement of coal from Decker
would continue over the existing BN line now serving the Powder
River Basin. This alternative, however, would not permit TRRC to
participate in what it describes as a more efficient and shorter
new movement serving area mines in conjunction with BN.
SEA noted that, although the extension would not be built
under this alternative, the previously authorized 89-mile line
from Miles City to Ashland, designed to serve new mines in
Montana, could still be constructed and operated. TRRC would
still be able to serve the Montco mine, a mine site with an
estimated annual coal production capacity of 38 million tons, and
four other potential mine sites in the Ashland/Birney/Otter Creek
area.
A portion of the existing BN line extends through the Crow
Indian Reservation in Montana. According to SEA, this line is
currently subject to a long term lease involving the Crow Indian
Tribe. It is SEA's understanding that BN may need to renegotiate
this lease to continue its use of the current rail line through
the Crow Indian Reservation. If the lease is not renewed, the
railroad may consider alternatives such as transporting coal over
its southern line through Wyoming. This would add considerable
mileage to upper midwest destinations (and greater fuel use with
associated pollutant emissions) that could be avoided by routing
traffic over the proposed TRRC extension.
SEA's Conclusions. In its FEIS, SEA concluded, based on all
the information available to it and the results of its own
independent investigation, that the Four Mile Creek Alternative
would be the environmentally preferable construction option.
According to SEA, although TRRC's preferred route would be better
from an engineering viewpoint because of the flatter grade, its
advantages would be outweighed by the fact that TRRC's preferred
route would traverse the environmentally sensitive Tongue River
Canyon and would require the construction of several bridges and
a tunnel through the canyon.
SEA also concluded that the Four Mile Creek Alternative is
the only viable construction alternative to TRRC's preferred
route. It would avoid the environmentally sensitive Tongue River
Canyon and the area's recreation resources as well as the need
for blasting near the Tongue River Dam. Moreover, because it
would avoid the need to construct bridges through the Tongue
River Canyon, it would reduce the potential for increased bank
erosion, river channelization, and flooding.
As earlier indicated, however, SEA determined that there
would be some environmental impacts associated with the Four Mile
Creek Alternative. These include a grade that, though safe to
operate, would require strict adherence to operating practices,
increased fuel consumption and air pollution, land disturbance,
habitat and wildlife loss, and proximity to residences. Because
of the 2.31% grade and the need for more engines to negotiate
this grade, the Four Mile Creek Alternative would be more costly
to construct and operate than TRRC's preferred route.
In reaching its conclusions, SEA relied on the Council on
Environmental Quality's (CEQ) regulations that require agencies
to identify a preferable alternative or alternatives, if one or
more exists.(13) Based on this definition, SEA found that the
environmentally preferable alternative here would be the "no
build" alternative, because it would require no new construction
and would not increase environmental impacts. The "no build"
alternative, however, would fail to provide the transportation
benefits for which this project was designed.
SEA ultimately concluded that the Four Mile Creek
Alternative, conditioned upon compliance with the mitigation
conditions specified in Sections A and B of Chapter Three of the
FEIS, would be the least environmentally damaging construction
option. Although the mitigation measures recommended by SEA
would not eliminate all of the environmental impacts identified
with the Four Mile Creek Alternative during the environmental
review process, they would reduce their significance. Because of
the environmental impacts associated with constructing and
operating a railroad line through the canyon, mitigation would be
less effective on TRRC's preferred route. Accordingly, SEA
concluded that construction and operation of the Four Mile Creek
Alternative should meet applicant's projected goals, but not have
an unduly severe impact on the environment.
Public convenience and necessity. Under 49 U.S.C. 10901, we
must determine whether the present and future public convenience
and necessity require or permit the construction and operation of
the proposed Tongue River extension. At the time the application
was filed, 49 U.S.C. 10901(a) of the Interstate Commerce Act
provided that an application to construct and operate a line of
railroad must be approved:
[I]f the Commission finds that the present or future
public convenience and necessity requires or permits
the construction or acquisition (or both) and operation
of the railroad line.
The Staggers Rail Act of 1980 (Staggers Act) had changed the wording of section 10901 to ease the burden of obtaining operating authority.(14) A key purpose of the Staggers Act was to
create a healthy climate for new investment so that sufficient
capital could be attracted to the railroad industry. Congress
stated in section 3 of the Act (H.R. Rept. No. 96-1430, p. 3
(1980), Conference Report) that: "the purpose of this Act is to
provide for the restoration, maintenance, and improvement of the
physical facilities and financial stability of the rail system of
the United States." That includes not just capital to replace
outmoded plant, but also capital to improve the efficiency of the
rail network or to make the industry responsive to shipper demand
for rail service as it arises.
The transportation issues that are raised in rail entry
cases include: (1) whether the applicant is fit, financially and
otherwise, to undertake the construction and provide rail
service; (2) whether there is a public demand or need for the
service; and (3) whether the competition would be harmful to
existing carriers. We have considered each of those issues here.
Financial fitness. The purpose of the financial fitness test is not to protect the carrier or those who elect to invest in the proposed project, but, rather, to protect existing shippers from carrier financial decisions that could jeopardize a carrier's ability to carry out its common carrier obligation to serve the public. See, e.g., Texas & Pac. Ry. v. Gulf, Etc., Ry., 270 U.S. 266, 277-78 (1925), and Texas and New Orleans R.R. Co. v. The North Side Belt Ry. Co., 276 U.S. 475 (1928). Currently, TRRC serves no rail shippers. It is not an operating railroad. If the line were to be built and fail financially, the affected shippers at Decker would return to using BN's prior service over the more circuitous route. Thus, shippers would continue to receive rail service even if this project were to fail.
Even if financial fitness were a major issue here, we
conclude that TRRC's submissions meet the applicable statutory
and regulatory requirements. First, applicant has complied with
the Board's regulations and submitted the required data.
Moreover, as discussed in Appendix A, based on our analysis of
the financial evidence before us here, we conclude that
applicant's income projections show the carrier to be financially
fit and able to construct the line, sustain operations, and
service debt, provided that any cash flow shortfalls in the early
years of operations are funded with additional partnership
capital or advances on transportation changes. We note that, as
with any business transaction, the financial market itself, of
course, will ultimately determine if the project is economically
viable--i.e., private financing approval will depend in part on
current market economics, partners' willingness to contribute
substantial amounts of capital, and other factors that may change
by the time the project is under way.
NPRC argues that TRRC will not be able to meet its financial
obligations because of a lack of potential traffic. Although
NPRC has submitted studies which it believes show a lessened
demand for coal in the midwest and, thus, greatly diminished
income projections for TRRC revenue, we find NPRC's data and
analysis unpersuasive. Our determination here does not hinge on
whether the market is increasing or decreasing for coal in
general, or on Montana and Wyoming compliance coal more
specifically, but on whether TRRC can garner traffic for coal
originating at both Decker and south of its line and destined for
the upper midwest. Even if coal traffic declines, TRRC may well
be able to provide sufficient efficiencies to reach its projected
operating volumes.
Although TRRC may face a formidable task in obtaining the
required permits and securing the traffic, this is part of the
uncertainty inherent in any private-sector business venture. In
any event, with over a quarter of a billion dollars at stake,
TRRC will rely on its ability to garner traffic from the Decker
mines and to interchange other coal traffic with BN before
entering into its financial agreements and beginning actual
construction.(15) In short, we conclude that TRRC has sufficient
financial backing to make the project work, both from partners
that are committed to substantial cash outlays and from a
commercial lending source. Therefore, we find that TRRC is
financially fit.
Public demand or need. We also conclude that TRRC has shown
the public demand necessary to support this application.
Proponents of the project include NERCO, a large coal producer;
Detroit Edison; MER, a subsidiary of Detroit Edison; and
Dairyland, all of whom favor the project because of anticipated
reductions in transportation distances, reductions in costs to
utilities and consumers, and reductions in sulfur dioxide
emissions.(16) Moreover, numerous Montana officials, including the
Governor, both U.S. Senators, and state legislators, support the
proposed line, citing such benefits as increased employment and
development of coal reserves as well as a broadened tax base.
It appears that the potential users of the proposed line are
seriously committed to the project and to its viability. NPRC
has argued that the line is either not viable (alleging a lack of
existing or future demand), or that adequate transportation
services are currently available. However, the demand for this
service is self-evident from the potential users' support of this
application, as the buyers of TRRC's services comprise one of the
cornerstones of TRRC's financing. Moreover, if there is a lack
of public demand for the proposed line, it will not be built. We
also note that the demand for TRRC's services will be more
affected by whether it can offer a more efficient transportation
service in conjunction with BN than BN can now offer on its own
for coal, rather than by whether TRRC can create totally new
markets.
The ICC's announced policy, which is being continued by this
Board, was to eliminate entry barriers by authorizing new
construction to the greatest extent possible. In the past, the
Board's predecessor, the ICC, did what it could to facilitate
investment initiatives and encourage expanded rail service. As
pointed out by TRRC, the potential exists here for applicant to
provide a more efficient service with reduced transportation
costs for the coal shipper. We note, further, that TRRC is
taking on the burdens of a new carrier, including the financing
and the associated risks, to provide more efficient service to
existing markets and, if successful, to additional markets.
Certainly, rail efficiency is an important component of the
overall rail system and we are charged with approving
transactions which improve the efficiency of the rail system
where we can appropriately do so. Cf. Union Pacific Corporation,
et al.--Control and Merger--Southern Pacific Rail Corporation, et
al., Finance Docket No. 32760, Decision No. 44 (STB served Aug.
6, 1996); and Burlington Northern Inc. and Burlington Northern
Railroad Company--Control and Merger--Santa Fe Pacific
Corporation and The Atchison, Topeka and Santa Fe Railway
Company, Finance Docket No. 32549, Decision No. 38 (ICC served
Aug. 23, 1995). This transaction certainly promotes this policy.
Competition with existing carriers. Finally, the issue of
whether the proposed line would harm existing rail services is
not applicable here. The only competition would be with BN, and
then only for a small segment of the total haul. BN has not
participated in this proceeding and has voiced no objection to
the proposed line. And, even if BN were to argue that the
proposed line would provide competition (i.e., routing BN-TRRC-BN
instead of all BN), new construction under the circumstances
would fulfill the national rail transportation policy by
providing "competition and the demand for services to establish
reasonable rates for transportation by rail" (Section 10101a(1)).
Further, this authorization of construction would "ensure the
development and continuation of a sound rail transportation
system with effective competition among rail carriers" (Section
10101a(4)) and foster sound economic conditions in transportation
(Section 10101a(5)).(17)
Balancing environmental concerns. In deciding whether to
authorize the construction and operation of a new line, we must
take into account environmental concerns. As explained in the
DEIS, SDEIS, and FEIS, significant environmental issues have been
raised by this project. We have considered whether to deny the
application because of these concerns but have decided not to do
so. As SEA concluded in the FEIS, the environmentally preferable
option here would be "no build," because it would require no new
construction and operations and would not increase environmental
impacts. However, the "no build" alternative would fail to
provide the transportation benefits for which this project was
designed. We agree with SEA that, with the recommended
mitigation, construction and operation of the Four Mile Creek
Alternative should meet TRRC's project goals of providing more
efficient service to coal shippers in the area, without having an
unduly severe impact on the environment.
We note that, in reaching this conclusion, SEA undertook, as
previously discussed, a comprehensive environmental review,
preparing a full EIS and developing detailed mitigation to
address all significant environmental concerns associated with
the construction and operation of the Four Mile Creek
Alternative. SEA based its analysis on hearings, site visits,
the comments of interested parties and consultations with various
groups (including the Railroad and its consultant). SEA also
took into account the specialized expertise of other federal and
state agencies, including both FWS and EPA, which have
consistently opposed TRRC's preferred alternative and endorsed
either the Four Mile Creek or the "no-build" alternative.
Additionally, SEA examined issues relating to the Endangered
Species Act, the ecological importance of the Tongue River
Valley, and the potential for cumulative impacts on the Tongue
River Reservoir from rail construction and reservoir repairs.
Finally, as noted earlier, SEA took into account CEQ regulations
requiring agencies to identify a preferable environmental
alternative or alternatives, if one or more exists.
After completing its environmental analysis, SEA concluded that, although TRRC's preferred route would be better from an engineering standpoint because of the flatter grade, its advantages would be outweighed by the fact that TRRC's preferred route traverses the environmentally sensitive Tongue
River Canyon, and would require the construction of five bridges
and a tunnel through the canyon. Because of the narrowness of
the canyon and the resulting proximity of the line to the river
and its banks, SEA concluded that TRRC's preferred routing would
affect the ecology of the river more than any other route.
In this regard, SEA noted that, because the river and
associated wetlands are located in an arid region, they are an
oasis in southeastern Montana. It also cited an FWS report about
the Tongue River Reservoir that determined that the river is
already under stress, and that the stream course has been
extensively altered by the reservoir and agriculture. The
result, according to the report, is that the river is becoming
more confined and incised, meanders and oxbows are becoming
isolated, and the riparian habitat along the river is dwindling.
SEA stated that the importance of this aquatic ecosystem for
agriculture, ranching, and recreation is generally well
recognized. SEA also stated that, recognizing the importance of
preserving biodiversity, it made avoiding further disturbance to
this river one of the key objectives of the environmental review
process.
SEA acknowledged that the Four Mile Creek Alternative would
have its own environmental impacts. These include a grade that
would require strict adherence to rigorous operating practices,
increased fuel consumption and air pollution, land disturbance,
and habitat and wildlife loss. The alternative routing would
also run in close proximity to a number of residences. Because
of the grade and the consequent need for more engines, the Four
Mile Creek Alternative would be more costly to construct and
operate than TRRC's preferred route. It would, however, avoid
the environmentally sensitive Tongue River Canyon. It would also
avoid the area's recreation resources and the need for blasting
near the Tongue River Dam. Because there would be no need to
construct bridges through the Tongue River Canyon with this
alternative, SEA concluded that the potential for increased bank
erosion, river channelization, and flooding would be reduced.
The Board's Mitigation Conditions. As noted, SEA developed
detailed mitigation conditions in the FEIS to offset potential
adverse impacts of the construction and operation of the Four
Mile Creek Alternative. TRRC suggested and/or agreed to many of
these mitigation measures. Areas covered by these comprehensive
conditions (which are set forth in Appendix B) include land use
(agricultural, ranching, recreational), social, economic and
transportation concerns, air and noise impacts, safety and fire
prevention, water quality and hydrology, aquatic and terrestrial
ecology(18), Native American concerns, and cultural and historic
resources.
We adopt SEA's recommended mitigation and believe that with
that mitigation (and the addition of reporting requirements and a
construction deadline for the entire line, as discussed below),
the construction and operation of the Four Mile Creek Alternative
should be approved.
We are confident that the interests of affected Native
Americans are protected to the extent possible within our
jurisdiction. Our mitigation addresses Native American concerns
by including measures to offer job opportunities, and to protect
Native American values and cultural resources. For example, TRRC
will be required to appoint a liaison between TRRC management and
the Northern Cheyenne Tribe to assist in ensuring that tribal
members receive an equal opportunity to secure temporary
construction and full-time operational jobs with TRRC.(19) Also,
Native Americans will be asked to assist in the identification of
traditionally-important plants, sacred sites, and cultural
resources.
A key feature of the mitigation plan for the Ashland-Decker
extension is the formation of an Multi-Agency/Railroad Task
Force(20) comprised of this agency and various other federal and
state agencies. The purpose of the agency Task Force will be to
advise, assist and coordinate with TRRC in implementing the
detailed mitigation measures we have imposed to address
terrestrial and aquatic impacts for the Ashland-Decker extension.
In addition to these supervisory functions, the Task Force will
be available to deal with the unanticipated environmental issues
that can arise as this particular project is implemented and
construction begins, specifically including issues related to the
concerns of landowners and Native Americans. The Task Force's
membership will be comprised of specified agencies, but it is
broadly representative. In addition, the Task Force will
consult, as needed, with affected interests, including ranchers,
other landowners, Native Americans, and other federal, state or
private organizations that could provide additional expertise.(21)
TRRC will retain an independent third-party contractor, selected
by SEA, to aid the Board in fulfilling its responsibility as the
lead agency for the Task Force. The contractor will work under
the direct supervision and control of SEA.
Finally, as part of the mitigation plan, we are in the
process of finalizing a Programmatic Agreement (PA) with the
Montana State Historic Preservation Officer (SHPO), the Advisory
Council on Historic Preservation (ACHP), and TRRC to reduce or
eliminate adverse impacts to cultural and historic resources.
This PA is being negotiated in accordance with the requirements
of the National Historic Preservation Act (NHPA). To date, the
SHPO, TRRC, ACHP and the Board have agreed in principle to the
PA's terms. Representatives of the Northern Cheyenne Tribe will
be asked to concur in the agreement, and other affected tribes
will be asked to participate where appropriate. Mitigation
measures addressing potential adverse impacts to Native
Americans, specifically the Northern Cheyenne, are set forth in
both the PA and in other mitigation measures recommended by SEA.
In a letter dated May 23, 1996, Dr. Wilmoth of MHS raised
new historic preservation issues. He states that he believes
that "both a historic Traditional Ranching Cultural Landscape or
District and a Native American Traditional Cultural Landscape or
District would be Adversely Effected by either action
alternative," and that "Effects very likely can not be
mitigated." He further states that the concerns of
traditionalist Native Americans and the "Historic Ranching
community" have not been addressed, requests that the "No Action"
alternative be more completely analyzed, and concludes that there
appears to be no public benefit derived from either construction
alternative.
We disagree. As the record here shows, SEA has given
extensive consideration to both historic preservation and
cultural resource issues in this case. SEA has consulted with
the SHPO, ACHP, the Northern Cheyenne Indians, and the Railroad
throughout the course of this proceeding and the preparation of
the comprehensive PA. We believe that, to the extent possible
within the Board's jurisdiction, the PA is designed to fulfill
the goals and mandates of section 106 of the NHPA and to ensure
the protection of both historic and cultural resources. Dr.
Wilmoth will be able to participate during the final negotiation
and implementation of the PA. This will provide ample
opportunity to address Dr. Wilmoth's concerns.
We disagree with Dr. Wilmoth's suggestion that SEA's
recommended mitigation is inadequate. SEA evaluated the possible
presence of a Native American Traditional Cultural Landscape and
included mitigation to address impacts to such a resource in the
PA. During preparation of the PA, SEA identified a number of
historic and cultural resources that could be mitigated, while
leaving room for the discovery and preservation of additional
resources that may be present but not yet identified. In sum, we
conclude that the PA, if implemented, would protect, to the
extent possible within our jurisdiction, potentially adversely
affected historical and cultural resources.
As indicated above, TRRC has filed a post-FEIS petition in
which it essentially asks us to reject SEA's recommendation and
select the preferred route. In support, applicant argues that
federal and state agencies having primary responsibility for the
project have concurred in the mitigation measures proposed for
its preferred alignment, citing to a Corps letter stating that
the Corps has no concerns about wetlands on the route.(22) TRRC
further argues that, with SEA's recommended mitigation for that
route, no significant environmental impacts would remain.
Although the Corps initially expressed some reservations
about TRRC's preferred route, its final letter to SEA, dated
December 16, 1994,(23) after that agency reviewed the wetlands
delineation report, stated that applicant's preferred alternative
was reasonable, given safety factors, and that wetlands were not
a significant issue. However, the FEIS did not rest its
recommendation primarily upon the Corps' assessment of the
relative impacts of the various routes upon wetlands, nor has
that been a significant factor in our decision here.
Thus, we do not find TRRC's arguments persuasive. The
record before us indicates that construction and operation
impacts associated with building the rail line through the canyon
would be far more difficult to mitigate than those associated
with the Four Mile Creek Alternative.(24) Moreover, even with the
detailed mitigation measures SEA developed for the railroad's
preferred route, and with the completion of additional studies
(the BA and wetlands delineation report), most of the agencies
with which SEA has consulted continue to believe that the Four
Mile Creek Alternative is environmentally preferable to TRRC's
preferred route.
Indeed, we note that EPA and FWS recently reiterated that
this remains their view. In September 1995, fully aware of the
extensive environmental analysis that had been done in this case,
EPA stated that:
The U.S. Environmental Protection Agency, Region
VIII, Montana Office, continues to believe that [the]
Four Mile Creek Alternative is the environmentally
preferred alternative for the Tongue River Railroad,
since it avoids disturbing the environmentally
sensitive section of the Tongue River below the Tongue
River Dam, and eliminates the need to construct five
bridges across the Tongue River and a tunnel. We
believe that the construction and operation of a
railroad along the proposed Tongue River Canyon
alignment in the relatively undisturbed Tongue River
Canyon would result in significant adverse impacts to
recreational, aesthetic, and wildlife values, including
habitat of the threatened bald eagle. We believe the
magnitude of these impacts would be less with the
selection of the Four Mile Creek Alternative, and could
be avoided altogether with the No Action Alternative.
We believe that TRRC's proposed alignment would have
more adverse consequences on the environment than
either the Four Mile Creek Alternative or the No Action
Alternative.(25)
FWS stated initially that: "We know of no potential impacts
to fish and wildlife that are anything close to being of
comparable extent in connection with the Four Mile Creek route.
From a fish and wildlife perspective, the Four Mile Creek route
appears clearly preferable."(26)
Later, well after the completion of the SDEIS, FWS stated
that: "It is the Service's position that construction impacts
associated with building the railroad through the canyon will be
far more difficult to mitigate than adverse impacts associated
with the Four Mile Creek Alternative. Obviously, none of the
adverse environmental impacts would occur if a "No Build"
alternative was selected."(27)
FWS reaffirmed this position in November 1995 when it stated
that its BO referred only to the potential effects on the bald
eagle, and not the overall environmental acceptability of the
proposed project. FWS's opinion regarding the overall
acceptability of the proposed action was addressed in its May 4,
1994 and August 29, 1991 letters.(28) In other words, FWS continues
to believe, even after the completion of its November 1995 BO,
that the construction impacts associated with building the
railroad through the canyon would be far more difficult to
mitigate than adverse impacts associated with the Four Mile Creek
Alternative.
The TRRC Preferred Route Is Not Environmentally Acceptable.
Notwithstanding the record that has been developed, TRRC claims
that the impacts through the canyon can be mitigated, and that we
should approve both that route and the Four Mile Creek
Alternative as environmentally acceptable.(29) TRRC believes that
the mitigation measures recommended by SEA for TRRC's preferred
canyon route are adequate to minimize the impacts of the canyon
alignment and that we should therefore approve TRRC's preferred
routing.
We do not agree. We have carefully examined the record,
including TRRC's data, arguments, and willingness to employ
mitigation measures; the expert analyses and opinions of other
governmental agencies; and SEA's analyses and conclusions
regarding the environmental impacts of the various routings.
TRRC's preferred route along the Tongue River, while preferable
for the relatively flat grade from both engineering and operating
standpoints, plainly is not preferable in other respects.
Regardless of the mitigation measures that we could impose on a
grant of TRRC's preferred route, this route would still require
construction and operation through the narrow 10-mile canyon
north of the Tongue River Dam. This area is so narrow that the
rail line cannot remain on one side of the river, but must cross
several times, necessitating the use of five bridges and a
tunnel. Therefore, we agree with SEA that severe environmental
degradation is likely to occur, and that this degradation could
not be effectively mitigated. As SEA points out, inevitable
ecological impacts to the river would occur because of the
narrowness of the canyon and the resulting proximity of the line
to the river and its banks.
TRRC mischaracterizes SEA's decision to develop mitigation
measures for TRRC's preferred route as well as the Four Mile
Creek Alternative. SEA was obligated to assess and make
recommendations on all the feasible alternatives before the
Board. Because we can reject SEA's recommendations, SEA was
required to develop mitigation measures for the two feasible
construction alternatives at issue here and to address the "no-build" alternative. The fact that SEA developed mitigation for
TRRC's preferred route does not mean that SEA finds it to be
environmentally acceptable.
We are also mindful that, while NEPA requires us to take a
hard look at the environmental consequences of our decision, it
does not mandate a particular result. Robertson v. Methow, 490
U.S. 332, 350 (1989). Once the adverse environmental effects of
a proposed action have been adequately identified and evaluated,
we may conclude that other values outweigh the environmental
costs.
Here, however, there are good reasons for selecting the Four
Mile Creek Alternative. The record shows that economic and
transportation efficiencies can be achieved through either
construction alternative, as both routings can serve the Decker
mines and the bridge traffic from the Wyoming Powder River Basin.
However, TRRC's preferred routing will have serious, unavoidable
environmental impacts which outweigh any increased costs that
constructing and operating the Four Mile Creek Alternative will
entail. On the other hand, the Four Mile Creek Alternative will
allow TRRC to achieve most of the efficiencies it seeks without
the profound environmental impacts to the Tongue River Reservoir
and the area of the canyon north of the reservoir. We reject the
"no-build" alternative because we believe that the economic and
transportation efficiencies of allowing TRRC's construction and
operation of the Four Mile Creek Alternative outweigh the
potential effects to the environment, as mitigated by the
conditions recommended by SEA and the additional reporting and
construction deadline conditions we will impose. For these
reasons, we will authorize construction and operation of the Four
Mile Creek Alternative with these mitigation conditions.
The petition to reopen/revoke. In its petition, NPRC makes
three arguments that TRRC's authority to build the first segment
should be revoked. TRRC opposes both reopening and revoking the
authorization. We will grant NPRC's petition to reopen TRRC I
and TRRC II, remove one earlier-imposed condition, require that
construction be completed within 3 years, and require that
reports of progress be filed, but otherwise deny the request for
revocation.
NPRC's first argument for revocation is that TRRC's
certificate was conditioned in TRRC I (the initial decision) on
the commencement of construction within 1 year from date of the
initial decision, and applicant did not meet that condition. As
previously discussed, the TRRC II decision imposed two
conditions: the mitigating conditions in Appendix B of the
initial decision and the 2(c) condition precedent to operations.
Moreover, ordering paragraph Number 2 thereof stated that the
"initial decision, as modified here and subject to the
environmental mitigation plan and section 2(c) conditions, is
affirmed." The issue thus is whether the two mitigating
conditions in TRRC II replaced those in TRRC I (including the 1-year condition) or simply modified them. TRRC maintains that the
1 year commencement requirement was nullified in TRRC II.
Additionally, TRRC submitted a chronology of events that it
states are part of the construction process.(30) It believes that
is has undertaken enough of the process (by proceeding with the
permitting and engineering in phase I) to comply with the 1-year
requirement.
We agree with TRRC that, even though no physical
construction began on the authorized route, the actions taken by
TRRC are an integral part of the construction process. Thus we
conclude that, regardless of whether TRRC II removed the 1-year
construction requirement, TRRC has fulfilled it.
The second argument for revocation is that TRRC has not
obtained the necessary 2(c) authorization opinion by DOI as the
Commission required in TRRC II.(31) As stated earlier, section 2(c)
of the MLLA prohibits railroads from holding federal leases or
permits for mining. The issue here is whether, under the then-existing TRRC organization, TRRC could legally provide rail
service while its partners maintained coal leases. TRRC states
that the coal lease in question has been canceled and that the
necessity for a ruling under section 2(c) is no longer required.
Upon further consideration, we have now decided to remove
the section 2(c) condition from the lead docket. We believe that
it is inappropriate to single out any one particular governmental
requirement for which TRRC must submit evidence of compliance.
Whether or not we impose a specific condition, TRRC will have to
comply with all applicable federal statutes and regulations,
including 2(c) authorization, if necessary, prior to commencing
operations over this line. Consequently, the 2(c) condition is
not required. Accordingly, we will issue a modified certificate
of public convenience and necessity to reflect this change and
the additional requirements for progress reports and construction
time limits discussed below.
NPRC's final argument is that, because of substantially-changed circumstances, the economic justification for the
originally authorized segment is no longer valid. In support,
NPRC points to the apparent termination of state and federal
mining permits for the Montco mine. Again, we find no basis for
revocation. Regardless of the status of the Montco mine permits,
the public convenience and necessity finding for the extension is
applicable to the originally-authorized segment as well. Indeed,
we believe that the success of this project will depend upon
applicant's being able to construct and operate the full line
between Miles City and Decker.
Time limits and reporting. We will impose a time limit for
TRRC to construct this entire line (i.e. both the line between
Ashland and Decker and the 89-mile line between Miles City and
Ashland that the Railroad was previously authorized to construct,
but has not yet built). Without definitive action on TRRC's
part, landowners would be unnecessarily affected by the
uncertainty concerning possible condemnation of part of this land
for railroad use. TRRC has stated in the record that it could
build the line within 3 years. We will therefore impose a time
limit of 3 years from the effective date of this decision for
TRRC to complete construction of the entire line. If
construction is not completed by that time, this authority will
lapse.
In order to assure that TRRC makes reasonable progress
toward compliance with that deadline, we will require the
applicant to file reports every 4 months, following the service
of this decision, on the entire line from Decker to Miles City.
The reports should describe the progress that TRRC is making in
implementing the authority we have granted it, including progress
in financing and land acquisition, any difficulties it is
encountering, and a statement as to whether or not it expects to
meet the 3 year time limit. An original and 10 copies should be
filed with the Board and copies should be served on the parties
to this proceeding. In the event that reasonable progress is not
made toward compliance with the 3 year limit, we are putting TRRC
on notice that, if warranted, we may withdraw the authorization
to construct the entire line before the 3-year construction
period has ended.
In Finance Docket No. 30186 (Sub-No. 2), we find that the
present and future public convenience and necessity require or
permit the construction and operation of a line of railroad
described above along the Four Mile Creek Alternative route,
subject to: (1) the environmental mitigation conditions in
Appendix B to this decision; (2) the requirement that TRRC
complete construction of the entire line between Decker and Miles
City within 3 years of the service date of this decision; and (3)
the requirement that TRRC report on its progress every 4 months.
We further find that, while there are potentially
significant environmental impacts associated with both
construction alternatives, it is the Four Mile Creek Alternative,
as conditioned by the environmental mitigation conditions set
forth in Appendix B, that should meet applicant's project goals,
but not have an unduly severe impact on the environment.
In Finance Docket Nos. 30186 and 30186 (Sub-No. 1), we find
that the authority should be continued, subject to: (1) the
removal of the 2(c) condition; (2) the requirement that TRRC
complete construction of the entire line between Decker and Miles
City within 3 years of the service date of this decision, and (3)
the requirement that TRRC report on its progress every 4 months.
It is certified in Finance Docket No. 30186 (Sub-No. 2):
The present and future public convenience and necessity
require or permit construction of the Four Mile Creek Alternative
route and operation by Tongue River Railroad Company of a rail
line from Ashland, MT, to a point near Decker/Spring Creek, MT,
subject to: (1) the environmental mitigation conditions in
Appendix B to this decision; (2) the requirement that TRRC
complete construction of the entire line between Decker and Miles
City within 3 years from the effective date of this decision; and
(3) the requirement that TRRC report on its progress every 4
months.
It is certified in Finance Docket No. 30186:
The present and future public convenience and necessity
require or permit the construction and operation of a line of
railroad described in an ICC decision served May 9, 1986
(including either of the alignments at Miles City and Ashland),
subject to: (1) the mitigating conditions in Appendix B of the
initial decision; (2) the requirement that TRRC complete the
entire line between Decker and Miles City within 3 years from the
effective date of this decision; and (3) the requirement that
TRRC report on its progress every 4 months.
It is ordered:
In Finance Docket No. 30186 (Sub-No. 2):
1. All motions to enter statements, pleadings, and evidence
into the record are granted.
2. All motions to strike evidence and pleadings and
requests for oral argument are denied.
3. The mitigation measures set out in Appendix B are imposed as conditions to this decision.
4. The application to construct the rail line along the
preferred route is denied and the application to construct the
Four Mile Creek Alternative is granted with conditions set out
herein.
5. TRRC shall retain an independent third party contractor,
selected by SEA, to aid the Board in fulfilling its
responsibility as the lead agency for the Multi-Agency/Railroad
Task Force that is part of the mitigation plan for the
Ashland-Decker extension.
In Finance Docket Nos. 30186 and 30186 (Sub-No. 1):
1. The proceeding is reopened.
2. The section 2(c) condition imposed in TRRC II is
removed.
3. NPRC's petition to revoke is denied.
4. The previously authorized construction authority is
extended for a limited period of 3 years from the effective date
of this decision.
5. TRRC must file progress reports every 4 months.
This decision is effective 30 days from its date of service.
By the Board, Chairman Morgan, Vice Chairman Simmons, and
Commissioner Owen.
Vernon A. Williams Secretary
Construction Phase - Preliminary Estimates of Cost. Capital
costs for the construction of the line, including the 41-mile
extension (preferred alignment) are projected to be approximately
$233 million. For the Four Mile Creek Alternative (which has an
additional length of 9.75 miles), costs are projected to be
approximately $241.5 million. Applicant provides a detailed
summary of construction costs in each of the 3 years it would
require to construct the line, assuming approval of TRRC's
preferred alignment. TRRC also furnishes a detailed comparison
of cost for the two extension variants, the preferred alignment
and the Four Mile Creek Alternative.
The projected cost of the original 89-mile segment was
estimated to be between $228 and $229 million in 1984. TRRC's
most recent estimate (1991) places the cost of the extended line
at $233 million. Applicant contends that the small difference
between these two estimates is the result of the use of different
inflation rates in each of the two cost projections. For the
original 89-mile line, the railroad used an 11% inflation factor;
for the longer line, it used a 4% inflation factor.
TRRC also proposes to lease or purchase trackage from BN
from the end of the Spring Creek trackage to enter the East and
West Decker Mines, and advises that it will construct its own
track if it cannot negotiate a lease or purchase arrangement with
BN. No provision for the additional cost of this track is
provided in TRRC's construction cost projections, but TRRC may be
able to negotiate a lease or purchase arrangement with BN. In
that case, there would be no additional cost of construction
other than those estimated. In any event, applicant includes a
contingency allowance of $19 million, which would likely more
than cover any additional cost of constructing track into the
Decker mines.
NPRC does not contest applicant's cost estimates for the
proposed line. NPRC does note, however, that construction of the
Four Mile Creek Alternative would increase the cost of the line,
as well as the railroad's associated debt burden and interest
expense.
Construction Phase - Financing Plan and Related Information.
TRRC proposes to finance construction of the line (plus interest
on the construction loan during the construction period) by: (1)
raising partners' capital equal to approximately 35% of the total
capital needed; and (2) borrowing the remaining 65% of required
capital through the private placement of long-term debt from
commercial banks and institutional lenders. This private
placement of debt would be at competitive market interest rates
with scheduled maturities to coincide with forecasted cash flow
generation. Lenders would have recourse to the railroad's assets
and revenue in the event of default. For purposes of the instant
application, it is assumed that debt capital will be raised under
a 15-year credit facility provided by a syndicate of commercial
lenders.
TRRC's financing plan was developed by the investment
banking firm of Lehman Brothers and is based on a financial
feasibility study developed by Corporate Strategies, Inc. (CSI).
The railroad's financial advisors are confident that prospective
investors will find TRRC to be an attractive investment
opportunity. The railroad furnishes a projected balance sheet
which "gives effect" to its financing plan, reflecting its start-up capital structure and debt service requirements for each of
the first 10 years of operation. For purposes of its financial
forecasts, TRRC assumes that it will commence operations with
approximately $254 million in capital.
NPRC does not challenge TRRC's financing plan. It does,
however, question the railroad's financial viability,
particularly with respect to its ability to generate sufficient
revenue to service the debt it will incur under the financing
plan.
Applicant's financing plan for the extended rail line amends
and supplements the previous plan which was approved by the ICC
in Finance Docket No. 30186 (Sub-No. 1), a related securities
application. Originally, several series of promissory notes with
varying maturities were to be issued, but it is unclear whether
the new plan, described by TRRC's financial advisors, replicates
or supersedes that previous plan.
TRRC's projected balance sheet shows that, at the starting
point of operations (Year 0), the total capital raised roughly
equals the cost of the constructed line and a nominal investment
in equipment and operating property. Road property and buildings
are recorded at a cost of about $227 million, which is $6 million
less than estimated construction costs of $233 million. No
provision has been made for interest during construction which,
it appears, would be rolled in as principal in a term loan of at
least 15 years upon completion of the construction project.
Assuming that 65 percent of the construction costs in each of the
3 years of the construction period were funded with debt at the
implied interest rate of 12.2 percent for the first year of
operations, the railroad would be required to roll over more than
$38 million in interest during construction. Additional interest
expense in the first year of operations would be almost $4.7
million. With this added interest, the $4.6 million dollar loss
projected in the first year of operations would increase in size
to over $9 million. It would also appear that partners' capital,
reported to be $83 million, is overstated by the $38.2 million
representing interest during construction.
As mentioned, TRRC would incur additional construction costs
to construct the Four Mile Creek Alternative and the line to link
with the East and West Decker Mines. No provision is made for
these additional construction costs in TRRC's balance sheet
projections. As discussed below, TRRC would be faced with an
additional capital outlay of about $15 million for the purchase
of helper units needed to negotiate the steeper grades on the
Four Mile Creek Alternative. The railroad's projected balance
sheet does not account for this additional purchase of equipment
and the financing that this purchase would necessitate.
Applicant's balance sheet shows $4 million in subordinated
debt to the partnership which offsets most of TRRC's first year
operating loss and is carried as an additional capital
contribution through year 10 of operations. Although not
specifically discussed in its financing plan, it appears that the
partners are willing to make additional contributions when cash
generation from operations is insufficient to cover the
railroad's debt service requirements.
Because TRRC's projected balance sheet and income statement
do not reflect the full level of capital outlays and associated
financing costs that it may experience, TRRC's capital needs will
probably be greater than represented. But if BN and its shippers
agree to divert traffic to TRRC, it is highly likely that TRRC
will be able to raise needed capital to construct the rail line.
Operation Phase - Income Projections and Financial
Viability. TRRC expects to move 19 million tons of coal in its
initial stages of operation, with an additional 5 to 10 million
tons projected to move over the new line with the opening of the
Montco and other Tongue River Valley coal mines. By the year
2000, TRRC expects to haul 27 million tons, with volume
increasing to 31 million tons by the year 2005.
To demonstrate its financial ability to sustain operations,
TRRC provides in its application a projected income statement for
each of the first 10 years of operations. TRRC projects that
revenues will increase from $34.2 million during the first year
of operations to approximately $74.9 million in year 10.
Operating expenses are expected to total $18.3 million in the
first year and steadily increase to $33.2 million by year 10,
with maintenance-of-way being a major operating expense item.
Except for the first year of operations, the railroad is expected
to be profitable, with projected income exceeding fixed charges
(interest expense) for each of the years 2 through 10.
TRRC's income projections do not reflect the additional
operating costs of running trains on the Four Mile Creek
Alternative. If this alternative route is constructed, according
to applicant, operating costs would rise because of additional
operating time, fuel costs, and locomotive power. Applicant
estimates that direct operating costs would increase by about
$3.2 million annually for the Four Mile Creek Alternative.
NPRC restates TRRC's financial projections developed from
CSI's model to argue that TRRC's business forecasts are based on
unrealistic assumptions and that the carrier would be
unprofitable and unable to service its debt burden. Protestant
had developed three forecast scenarios which are summarized
below.
The first restates TRRC's projections to reflect movement at
the proposed rate levels for coal destined only to the generating
facilities of Detroit Edison, the one customer that protestant
believes might benefit from the new line. These projections
assume that TRRC would be unable to divert any other traffic from
existing routes at the proposed rate levels. It also assumes
that proposed new coal mines along the route would not be
developed because of overcapacity. At the lower tonnage levels
forecast in this scenario, TRRC would fail to generate sufficient
income in each of the first 6 years of operations to meet
interest payments on its long-term debt.
In the second scenario, NPRC projects operating results at
TRRC's proposed tonnage levels, but with rate levels which NPRC
argues are more in keeping with the prevailing market rates.
NPRC argues that these are reflected in what NPRC claims is BN's
average revenue per ton of $1.31 in 1991. At these lower rate
levels, TRRC would lack sufficient income in the first 5 years of
operations to pay interest on long-term debt.
The third scenario shows the amount of tons that would have
to be moved, using NPRC's computation of the average BN per-ton
rate of $1.31, to generate operating revenues necessary to just
cover all expenses and fixed charges, i.e., the break-even level.
These required tonnage figures, NPRC points out, would have to be
significantly greater than those projected by the railroad.
Our analysis of the railroad's income projections is divided
into two parts. In part one, NPRC's arguments about projected
tonnage and rate levels is discussed and analyzed. In part two,
applicant's projections are analyzed in light of representations
made elsewhere in the evidence about expenditures and financing.
Critical to TRRC's financial viability is its ability to
generate sufficient revenue to cover its operating expenses and
service the debt it will incur to finance construction of its
rail line. Projected revenue is a function of two variables,
traffic volume (in tons hauled) and the rate per ton charged. In
its financial projections, TRRC has projected revenue based on
traffic volume and pricing assumptions which NPRC challenges as
being unrealizable. Much of protestant's argument that TRRC's
rail line is a duplicate route and is not economically justified
centers on the long-term market prospects for Western coal. As
such, the argument does not directly address applicant's revenue
projections. In evaluating the reasonableness of TRRC's
projections, our analysis below is necessarily confined only to
those arguments directed to, and which quantifiably challenge,
the railroad's forecast assumptions.
In its 6-year projections, NPRC limits tonnage to only
overhead traffic for Detroit Edison at proposed rate levels on
the claim that this is the only customer that would benefit from
the new route. We believe that this limited perspective
arbitrarily ignores potential business from other sources. As
TRRC correctly notes, NPRC's 6-year forecast excludes traffic
from other shippers, particularly traffic generated on the
proposed route from new mine openings, in the later years of the
forecast. Although TRRC's projected tonnage levels are
necessarily speculative, we believe that NPRC's tonnage figures
are unduly pessimistic. We are mindful, however, that failure to
reach these projected tonnage levels will adversely affect the
railroad's ability to generate sufficient revenue to sustain
operations and service debt.
NPRC argues that, at what NPRC considers to be BN's average
revenue per-ton in 1991, TRRC would incur large losses during its
first 5 years of operations. As a result, the railroad would not
have sufficient revenue to cover interest payments (fixed
charges) to lenders. NPRC also projects the tonnages TRRC would
have to haul to break even using its misstatement of BN's average
per-ton rate, noting that these tonnage levels far exceed those
projected by the railroad. As to the reasonableness of
protestant's projection scenarios, we agree with TRRC that
pegging its rates to BN's average revenue on a per-ton basis is
not relevant in deciding rates at which TRRC might attract
traffic now moving via BN. In our view, significant cost savings
to BN would be an incentive to do business with TRRC. Thus, the
focus should be on BN's costs of moving coal over its longer
route and the cost savings, if any, realizable by shifting its
traffic onto TRRC.
TRRC claims that, at a starting rate per ton of $1.80 in the
first year of operations, BN would realize savings of $2.10 per
ton of coal hauled by using the shorter route. TRRC bases these
savings on an average BN rate of $3.90, which means that the
$2.10 difference is not "savings" from using the shorter route,
but the additional per-ton profit that BN would theoretically
realize. However, BN would not, in fact, earn a profit of $2.10
per ton because it would still be incurring costs of operating
its trains over the TRRC route. In fact, in order for BN to have
an incentive to operate over the TRRC track, its total cost per
ton, including payments to TRRC, would have to be less than it is
currently spending to move traffic over its own longer routing.
Applicant did not furnish any BN cost evidence in its
statements. In the absence of such evidence, we have used BN
system average cost data from the Uniform Rail Costing System
(URCS). These data indicate that BN's cost in 1991 to move
traffic over its own 298 mile route was $2.53 per ton. Assuming
that it has to pay TRRC $1.80 per ton to move traffic over TRRC's
shorter 128-mile route, BN's other costs (the cost of operating
over the shorter route, including fuel, locomotive costs, and
switching charges, but excluding crew wages since TRRC provides
the crews) would have to be less than $0.73 per ton ($2.53 minus
$1.80) to provide it with the incentive to use the TRRC route.
We have computed the per-ton cost of BN train operations to be
$0.74 per-ton using the shorter route. When added to the $1.80
per-ton charge by TRRC, the resulting per-ton cost to BN of $2.54
is marginally higher than the $2.53 cost using the longer line.
However, we expect that there would be other operating savings to
BN not reflected in this analysis of costs associated with
reduced cycle time, i.e., better utilization of equipment. Also,
service may improve because of the shorter route and possible
higher speeds associated with new track. It is also possible
that diversion of traffic to TRRC would relieve congestion, if
any, on BN's existing route. Finally, the potential for new mine
openings along the TRRC route might be attractive to BN if the
coal moving from those mines did not compete with coal moving by
BN from other mining sites.
Neither parties' arguments are sufficiently persuasive to
permit us to definitively and unequivocally conclude whether or
not BN will, in fact, agree to operate over the new line at the
line's projected revenue levels. The question is somewhat
academic, however. In the final analysis BN will provide the
answer.
We have restated TRRC's income projections(32) to take into
account additional capital outlays and costs not accounted for in
applicant's balance sheet and income statement projections. In
each of the first 3 years of operations, the railroad would not
generate sufficient operating income to cover interest expense.
For the 3-year period, the total shortfall would exceed $20
million. Similarly, cash flow (new income plus depreciation
expense) in each of the first 3 years of operations would not be
sufficient to retire long-term debt maturing during that time
frame. Beginning in year four, however, our restatement of
TRRC's income projections show sufficient cash flow generation to
service debt. The only financial problem, therefore, appears to
be any cash flow deficiency in the early years of operations. In
the earlier application, the use of the prepaid freight technique
and additional contributions from the railroad's partners were
established as viable means for overcoming any cash flow problems
that the railroad might encounter. Given the infusion of
additional capital from these sources, we believe that TRRC would
be financially fit and able to sustain operations and manage its
debt burden.
ENVIRONMENTAL MITIGATION CONDITIONS
The recommended mitigation measures set forth below are
based on SEA's independent analysis of the project, comments to
the DEIS, SDEIS, and FEIS, the environmental record, the
Biological Opinion and a proposed Programmatic Agreement (PA),
and conditions either proposed or agreed upon by the railroad.
We have incorporated by reference specified portions of the
proposed Mitigation Plan that was set forth in Appendix A of the
DEIS. The recommended mitigation measures set forth below
reflect the changes discussed in the FEIS, and other clarifying
changes.(33)
(1) TRRC shall negotiate compensation for direct and indirect
loss of agricultural land on an individual basis with each
landowner. TRRC shall assist landowners in identifying and
developing alternate agricultural uses for severed land, where
appropriate. TRRC shall apply a combination of alternative land
use assistance and compensation as necessary and agreed upon
during right-of-way negotiations.
(2) Where capital improvements are displaced, TRRC shall relocate
or replace these improvements or provide appropriate
compensation.
(3) TRRC shall construct right-of-way fencing along the entire
line according to specifications suitable to the landowners and
consistent with industry standards. TRRC shall negotiate special
fencing needs with individual landowners.
(4) TRRC shall install cattle passes (oval, corrugated metal structures, approximately 11 ft. high and 12 ft. wide at the base) along the right-of-way to ensure passage of cattle under the rail line. TRRC shall work with landowners to identify appropriate locations for cattle passes and private grade crossings for equipment.
(5) During final engineering, TRRC shall work with individual
landowners to avoid unnecessary conflict between construction
activities and ranching operations.
(6) TRRC shall confine all construction activities to right-of-way and to the construction camps along the rail line, at
locations to be negotiated between individual landowners and
TRRC.
(7) TRRC shall require its contractors to assure that its
construction camps are orderly. Upon completion of construction,
TRRC shall return the camps to their previously existing use.
(8) TRRC shall appoint a representative, with direct access to
management, to work with primary contractors, subcontractors, and
landowners to resolve problems that develop during construction.
SOCIAL AND ECONOMIC
(1) TRRC shall make available to local governments and to the
Northern Cheyenne Tribe all public data and studies that it is
aware of concerning the facilities and services that may be
required as a result of mine development.
(2) TRRC shall appoint a liaison between TRRC management and the
Northern Cheyenne Tribe to ensure that tribal members receive an
equal opportunity to secure temporary construction and full-time
operational jobs with the railroad.
TRANSPORTATION
(1) During construction, TRRC shall encourage contractors to
provide laborers with daily transportation to the work site from
a central location.
(2) To the extent possible, TRRC shall confine all construction
related traffic to a temporary access road within the right-of-way. Where traffic cannot be confined to this access road, TRRC
shall ensure that contractors make necessary arrangements with
landowners or affected agencies to gain access from private or
public roadways. The access road shall be used only during
construction of the railroad grade, after which construction
shall be confined to the right-of-way.
(3) Where traffic along a public roadway may be disrupted during
construction, TRRC shall comply with all requirements of the
Montana Department of Highways (MDH) or other appropriate
agencies. In the absence of such requirements, TRRC shall
endeavor to maintain at least one lane of traffic open at all
times. Specific plans shall be developed by TRRC, in
coordination with state and local agencies, to assure the quick
passage of emergency vehicles. TRRC shall submit all
construction plans affecting public roadways to MDH for review
and approval.
(4) TRRC shall comply with MDH's Manual of Uniform Traffic
Control Devices for work zone safety.
(5) TRRC shall equip all grade crossings with warning signs and
devices, as deemed appropriate under MDH's Railroad Crossing
Protection Policy.
AIR QUALITY
(1) TRRC shall subject all heavy equipment and vehicles used in
the construction, operation, and maintenance of the railroad to
regular inspection and maintenance to ensure that operation
complies with manufacturer's specifications and that equipment is
running as cleanly and efficiently as possible.
(2) When vegetation is removed from the right-of-way, TRRC shall
clear areas only as necessary to mitigate impacts of wind erosion
and fugitive dust.
(3) Where devegetation has taken place, TRRC shall begin
revegetation as early as possible. Where immediate revegetation
is not possible, TRRC shall implement alternative stabilization
measures such as matting and mulching.
(4) TRRC shall suppress dust at all work areas by using water
trucks, and shall make water available to local landowners,
governmental agencies, or associations for these activities.
TRRC shall conduct dust suppression activities regularly and
frequently during the dry periods.
(5) TRRC shall conduct any open burning in strict accordance with
local or other applicable regulations, and shall obtain all
necessary permits and observe all necessary safety precautions.
NOISE
(1) To the extent practicable, TRRC shall schedule major noise
producing construction activities during the weekday and daylight
hours.
SAFETY
(1) Because of the descending 2.3 percent grade, TRRC shall
strictly adhere to safe railroad operating practices, such as the
use of seven locomotives at no more than 10 miles per hour for
the descent, if appropriate.
(2) TRRC shall adhere to federal and state construction safety
regulations to minimize the potential for accidents. TRRC shall
require its contractors to conduct safety meetings for their
workers and to ensure that each person understands safety
measures and procedures.
(3) TRRC shall develop an internal Emergency Response Plan
consistent with Montana State plans authorized under Title 10,
Montana Code Annotated.(34)
(4) TRRC shall establish cooperative relationships with all federal, state, and local agencies with responsibility for disaster/emergency response. TRRC shall provide operational plans and copies of the emergency response plan identified above to such agencies and incorporate their comments as appropriate.(35)
(5) TRRC shall develop a Wildfire Suppression and Control Plan
for fires occurring on the right-of-way as a result of rail
construction/operations or undetermined causes. TRRC shall
include the measures relating to fire suppression set forth in
the mitigation plan in the DEIS.
(6) TRRC will negotiate the placement of fire suppression
equipment with local ranchers.
(7) TRRC will maintain a serviceable access road and/or access
points along the right-of-way, at locations determined in
consultation with the local fire officials.
(8) TRRC will develop and install a mobile communications system
between the local volunteer fire fighting units, train crews, and
ranchers with property adjacent to the right-of-way.
(9) TRRC shall develop, in cooperation with appropriate federal,
state and local agencies, a plan to prevent spills of oil or
other petroleum products, both during construction and operation
and maintenance. TRRC's plan shall include measures pertaining
to oil spills set forth in the mitigation plan in the DEIS.
(10) TRRC shall develop guidelines based on the tasks to be
accomplished by individual contractors, including: (a) steps
during refueling to guard against overflows, (b) storage of fuel
only in metal storage tanks surrounded by impervious dikes
capable of containing greater than the capacity of the tank, (c)
removal of waste oil to appropriate sites, and (d) maintaining
equipment in good running order and conducting routine
maintenance activities.
(11) If an herbicide spill occurs, TRRC shall respond using the
same general approach discussed above. TRRC shall immediately
contain the spill, notify the appropriate agencies, and implement
appropriate clean-up procedures.
HYDROLOGY AND WATER QUALITY
(1) To assure that overall water quantity and quality are not
unnecessarily altered or diminished by this project, TRRC shall
submit detailed permit applications to the applicable agencies,
including the Corps, local Conservation Districts, the Water
Quality Bureau of the Montana Department of Health and
Environmental Services, and any other applicable agencies.
(2) TRRC shall secure applicable permits from MT DNRC for bridge
crossings over the stream bed of the Tongue River.
(3) TRRC shall consult with EPA to implement EPA's river bank
stabilization methods.
(4) TRRC shall ensure that all culverts and other drainage
structures installed at ephemeral and perennial stream crossings
will be designed to pass the projected 25-year flood.
(5) Where possible, the route shall be designed to avoid the
flood plain. Where the railroad grade does infringe upon the
flood plain, TRRC shall install drainage structures to assure
that the grade does not restrict or reroute the 25-year flood.
(6) Construction of all stream crossings, including bridges and
culverts and activities requiring stream bank encroachments (rip-rap, for example), shall occur during periods of low or no flow
in the streams affected.
(1) TRRC shall participate as a member of the Multi-agency/Railroad Task Force (Task Force), which will advise,
assist and coordinate with TRRC in accomplishing the mitigation
measures set forth in the Mitigation Plan in the DEIS addressing
aquatic and terrestrial ecology.(37)
WILDLIFE
(1) TRRC (in cooperation with MT FWP) will expand its ground and
air survey program to include seasonal surveys showing where
pronghorn are concentrated and their distribution and movement.
From this information, TRRC shall assess and minimize impacts
from the proposed right-of-way.
(2) TRRC will place fencing to accommodate seasonal migration, in
compliance with the BLM Fencing Handbook, to protect ranching
operations, while allowing for pronghorn movement.
CULTURAL RESOURCES
(1) TRRC will comply with the provisions of the proposed PA, see
Appendix G of the FEIS, or a final PA, if one is executed.
(2) TRRC, in the preparation of the cultural resource inventory
described in the PA, shall invite Northern Cheyenne tribal
representatives to identify and compile a list of traditionally-important plants occurring in the area of potential effect and of
gathering sites and access points for these plants. TRRC shall
use this information in considering the need to protect and
assure continuing access to these plants.
TONGUE RIVER DAM RECONSTRUCTION
(1) During construction of the rail line, TRRC shall provide 24-hour a day access to the MT DNRC for the construction and
maintenance of the Tongue River dam either via the construction
of temporary roads and/or flagging devices or by other reasonable
alternatives.
(2) Before construction, TRRC shall coordinate development of the
geotechnical drilling program near the dam with MT DNRC. Once
the results of the drilling are completed, TRRC along with input
from MT DNRC, will determine the best engineering method for
removal of the cut material. If blasting is necessary, the
charges will be designed to insure that there will be no adverse
affect to the integrity of the dam.
1. The ICC Termination Act of 1995, Pub. L. No. 104-88, 109
Stat. 803 (ICCTA), which was enacted on December 29, 1995, and
took effect on January 1, 1996, abolished the Interstate Commerce
Commission (ICC or Commission) and transferred certain rail
functions and proceedings to the Surface Transportation Board
(Board). Section 204(b)(1) of the ICCTA provides, in general,
that proceedings pending before the ICC on the effective date of
that legislation shall be decided under the law in effect prior
to January 1, 1996, insofar as they involve functions retained by
the ICCTA. This decision relates to a proceeding that was
pending with the ICC prior to January 1, 1996, and to functions
that are subject to Board jurisdiction pursuant to 49 U.S.C.
10901. Therefore, this decision applies the law in effect prior
to the ICCTA, and citations are to the former sections of the
statute, unless otherwise indicated.
2. This proceeding also embraces Tongue River R.R.--Rail
Construction and Operation--In Custer, Powder River and Rosebud
Counties, Montana, Finance Docket No. 30186 and Tongue River
Railroad Company--Issuance of Securities, Finance Docket No.
30186 (Sub-No. 1).
3. Where an EIS is required, the ICC's/Board's regulations
require the applicant to consult with SEA 6 months prior to
filing an application. 49 CFR 1105.10. In January 1989, TRRC
informed SEA that it intended to file an application for the
proposed extension. In November 1989, SEA commenced the process
of preparing an EIS, anticipating that TRRC would file the
application within 6 months. However, TRRC did not file its
application until June 1991, 2 years after it was eligible to do
so.
4. 56 FR 37573.
5. We have considered all comments. However, because of the
large number of comments and because many of the comments make
similar arguments, we will not identify each comment separately.
We have addressed all of the issues raised in the comments.
6. Although an ALJ conducted the hearings, the ICC did not
delegate authority to issue an initial decision. In a decision
served December 20, 1993, the ICC stated that "whatever the
benefits that could result from an initial decision would not be
worth the cost in time and the expense in litigation." Decision
at 4.
7. V.S. Victor H. Wood, consultant for applicant, filed
April 29, 1992.
8. Applicant states that, since the TRRC II decision, TP has
acquired the interest of Arch Cartage Corporation (formerly DS
Cartage, Inc.) and Otter Creek Transportation Company.
Application at 7.
9. In the DEIS, SEA concluded that there were no feasible
construction alternatives other than TRRC's preferred route and
the Four Mile Creek Alternative, primarily because of the
difficult terrain. Nothing that has come to light since then
casts doubt on that conclusion.
10. In its May 4, 1994 comments on the SDEIS, FWS reiterated
its initial position regarding the Four Mile Creek Alternative:
Impacts to fish and wildlife resources and to Tongue
River recreation would be less; adverse impacts to
Tongue River Reservoir State Recreation Area would be
avoided; adverse impacts to the scenic canyon would be
avoided; Tongue River crossings would be reduced to
one; less channel disturbance and riparian habitat
impacts; reduced pollution threats in terms of
sedimentation, toxic spills, and herbicide use; reduced
impacts to wintering bald eagles; and fewer adverse
impacts on fish and wildlife.
11. In its comments on the SDEIS dated May 9, 1994, EPA
stated:
The EPA has determined that there are potential
significant adverse environmental impacts associated
with the TRRC's Preferred Alternative that should be
avoided in order to adequately protect the environment.
We believe the magnitude of these impacts would be less
with the selection of the Four Mile Creek Alternative,
and could be avoided altogether with the No Action
Alternative. We believe that TRRC's proposed alignment
would have more adverse consequences on the environment
than either the Four Mile Creek Alternative or the No
Action Alternative.
12. EPA stated:
[T]he TRRC's preferred alternative, which would
require construction of five bridges over the Tongue
River, each of which would require excavation and/or
fill within the stream's high water line, would result
in significant adverse impacts to the chemical,
physical, and biological integrity of the Tongue River.
We also believe that the construction and operation of
a railroad along the TRRC's proposed alignment in the
relatively undisturbed Tongue River Canyon would result
in significant adverse impacts to recreational,
aesthetic, and wildlife values, including habitat for
the bald eagle.
The EPA has determined that there are potential
significant adverse environmental impacts associated
with the TRRC's Preferred Alternative that should be
avoided in order to adequately protect the environment.
We believe the magnitude of these impacts would be less
with the selection of the Four Mile Creek Alternative,
and could be avoided altogether with the No Action
Alternative.
13. See 40 CFR 1502.14(e). The environmentally preferable
alternative is defined by CEQ as that causing the least impact to
the biological and physical environment. It would have the
lowest level of ground-and vegetation-disturbing activities and
would best protect, preserve, and enhance historic, cultural, and
natural resources.
14. The Staggers Act amended 49 U.S.C. 10901 to facilitate
entry into the rail industry. Under the prior section 10901, the
Commission was required to find that the public convenience or
necessity required or would be enhanced by the construction. The
Staggers Act required the Commission to find that the public
convenience and necessity required or permitted it.
15. TRRC stated in its application that it had discussed, but
not concluded, final agreements with BN on matters concerning the
division of rates, trackage connections, and interchange of
traffic. With respect to the interchange of traffic, TRRC
expects to conclude arrangements with BN in accordance with the
standard interchange rules of the Association of American
Railroads. If agreements on the division of rates cannot be
reached, TRRC states that it will offer independent coal
transportation contracts to Miles City from which coal shippers
would negotiate independent transportation contracts with BN to
the destination. Application at 21.
16. As noted earlier, other shippers submitted statements in
support, but their evidence related to the already-approved Miles
City-Ashland segment.
17. See also such agency decisions as Gateway Western Railway
Company--Construction Exemption--St. Clair County, IL, Finance
Docket No. 32158, et al. (ICC served May 11, 1993) and Louisville
& Jefferson Co. & CSX Const. & Oper. Jeff. KY, 4 I.C.C.2d 749,
759 (1988).
18. We note that the Biological Assessment recommended in
condition No. A.9.3.1.1. of the DEIS has already been completed.
19. We note that TRRC agreed to this mitigation, which is
beyond the scope of the mitigation that we would normally impose.
20. The Task Force does not apply to the 89-mile line from
Miles City to Ashland.
21. We encourage the Task Force to use innovative means to
address the issues before it, consistent with the conditions we
have imposed. Any significant changes would need to be approved
by the Board.
22. According to TRRC, 3.8 acres of riparian wetlands would
be affected, and the difference of affected wetlands between the
preferred and alternate routes is .1 acre for either alignment.
23. Letter from Robert S. Nebel, Chief, Environmental
Analysis Branch of the Corps, Omaha, NE.
24. SEA should not be faulted for having changed its position
on which route was preferable during the environmental review
process. It is SEA's responsibility to explore possible
alternatives and to let the public comment on them. The DEIS and
the SDEIS were preliminary documents that allowed SEA and the
public to evaluate all aspects of TRRC's proposed construction
and operation, consider any new evidence, and change or readopt
any preliminary conclusions made during the environmental review
process before reaching a final conclusion. As the DEIS, SDEIS,
and FEIS show, the environmental review process here was
thorough. There was ample public participation, and the reasons
for SEA's final recommendation that the Four Mile Creek
Alternative is the preferable construction option are fully
explained.
25. Letter from John F. Wardell, Director, Montana Office,
EPA, dated September 6, 1995.
26. Letter from Dale Harms, State Supervisor, Montana State
Office, FWS, dated August 29, 1991.
27. Letter from Kemper M. McMaster, Field Supervisor, Montana
Field Office, FWS, dated May 4, 1994. FWS reiterated that its
initial opinion expressed in 1991 had not changed, and that the
construction impacts associated with building the railroad
through the canyon will be far more difficult to mitigate than
adverse impacts associated with the Four Mile Creek Alternative.
FWS's prior comments on the Four Mile Creek Alternative were:
(1) impacts to fish and wildlife resources and to Tongue River
Recreation would be less; (2) adverse impacts to Tongue River
State Recreation Area would be avoided; (3) adverse impacts to
the scenic canyon would be avoided; (4) Tongue River crossings
would be reduced to one; (5) less channel disturbance and
riparian habitat impacts; (6) reduced pollution threats from
sedimentation, toxic spills, herbicide use; (7) reduced impacts
to wintering bald eagles; and (8) Four Mile Creek Alternative
preferable from fish and wildlife perspective.
28. Final BO from Dale Harms, Field Supervisor, Montana Field
Office, FWS, dated November 22, 1995.
29. Petition of applicant filed May 3, 1996. In that
petition, TRRC also requests that we take notice of TRRC's data
which it believes were not considered by SEA in its conclusions;
make no recommendation as to selection of an alignment in a
decision on the merits; and allow TRRC to corroborate coal
projections submitted in May 1994 in rebuttal to NPRC's February
1994 petition to reopen.
30. TRRC stated that the construction for the Miles City-Ashland segment is divided into three phases. Phase I involves
ordering design and engineering studies, and obtaining the
necessary permits and certificates for construction and
operation, negotiating mitigating conditions, and arranging
preliminary financing. Phase II involves all functions relating
to construction, such as purchasing right-of-way, obtaining
materials and equipment, and securing bids from contractors.
Phase III involves obtaining long-term financing, completing
construction, purchasing equipment, and commencing operations.
TRRC II at 3-4.
31. The only court challenge to the grant of the 89-mile line
in TRRC I and TRRC II involved the issue of whether the ICC's
decision violated section 2(c) of MLLA, 30 U.S.C. 202. See
Northern Plains Resource Council v. ICC, 817 F.2d 758 (9th Cir.
1987) (unpublished opinion dismissing the appeal for lack of
standing), cert. denied sub nom. Northern Plains Resource Council
v. United States, 484 U.S. 976 (1987).
32. See Exhibit I, attached.
33. 33 Of course, TRRC must comply with all applicable federal,
state and local regulations to the extent they deal with subjects
other than those covered by the conditions we have imposed here.
34. 34 This includes a roster of agencies and specific persons
to be contacted for specific emergencies, procedures to be
followed by particular rail employees, emergency routes for
vehicles, and location of emergency equipment.
35. 35 These agencies include: Disaster and Emergency Services
Division of the Department of Military Affairs, Helena; rural
fire departments along the route; local ambulance and emergency
medical services and air evacuation services in Billings and
Sheridan; the Montana Department of Health and Environmental
Sciences (especially the Water Quality Board); Montana Department
of Fish, Wildlife and Parks (MT FWP); Montana Department of
Natural Resources and Conservation (MT DNRC); the Northern
Cheyenne tribe; the Bureau of Land Management (BLM) or U.S.
Forest Service; and other local agencies or groups which are
identified as key to disaster response.
36. 36 See Section A.9 of the DEIS Mitigation Plan. This
mitigation shall be implemented to the extent applicable to the
Four Mile Creek Alternative.
37. 37 For reclamation on cut and fill slopes TRRC shall
construct serrations perpendicular to the slope.
|