Minutes of AFE meeting 4/3/01 Fred Borcherding, Alan Bross, George Ginther, Jerry Blazey, Harry Weerts, John Womersley, Hugh Montgomery, Thomas Nunnemann, Paul Grannis In Paul Rubinov's absence, Fred reported the progress in the last few days on differential non-linearity. Board #1 showed little signs of DNL at DAB3. It was taken to Lab 3 where it showed the structures in digital response like board 5 had done, both with light pulses and with CAL inject signals. On return to DAB3, this board #1 showed the DNL structures. Board #2 was modified to adjust terminations on data valid (and data lines). For all tested channels, there was no sign of the DNL symptoms. Studies were conducted on all 8 MCM's of the board. This (right handed) board will be taken to Lab3 tomorrow to run there with sine wave inputs on the CAL input. Board 1 will be brought back to DAB3 to work on its terminations to try to cure it as well. If successful, this board can be operated at Lab3 with light. There was however evidence of feedthrough of the SIFT clock on the SVX readout; it is thought that this clock can be blanked off during readout to cure this problem. The temperature control software is not complete as far as we understand at present (Stefan should comment here). This is the necessary condition for proceeding to discriminator tests with the realistic left- and right-handed boards in Lab 3. The masks needed for testing the discriminator threshold variations are thought to be completed and ready; Paul should comment if this is the case. We set a deadline of Thursday for return of a fixed LH board from DAB3 to Lab3 -- or return of an unfixed board that can still be used for the discriminator output test. In the case that we have no clear fix to the DNL problem, we need to attempt to get an approximate calibration from the channel run with larger SIFT-SVX transfer gain where we think we saw photopeaks. This can give an approximate calibration of the pe/channel constant that can be transferred to other channels by knowing the various VLPC gains. Fred is to make a plan/schedule for testing for the next week, to be shown in the Thursday meeting (see below). Sanmina seems to be near the end of the bare board production phase. They are expected to complete this week. However there are a few issues remaining on components for stuffing. It was suggested that assembly may not begin until Apr. 16, but there is not a definite word here. Sanmina has not officially agreed to wait for our go-ahead, but practically our input on the component issues would seem to assure this. Thomas Nunnemann agreed to work at high priority with Paul Rubinov on testing the boards at the Lab3 cryotest stand. Thomas knows much of the system, including the analysis package for fitting photopeaks. We hope that this addition will help the Lab 3 test procedures. The decision not to pursue spare AFE8 boards for the CFT stereo (CPS) means that at present we have no visible way to complete a full fiber tracker readout without the AFE12 boards. We went through the likely schedule for completion of the AFE12 -- necessarily imprecise. We estimated that 6 weeks are needed to complete AFE12 motherboard prototypes, another month for daughterboards. A month of testing prototypes would be necessary, followed perhaps by a 3 month cycle of board production and assembly and a month or so of testing here. This brings us to near the end of the year without having the capability of tracking in D0. Some expressed dismay. Discussion turned to the possibility of deciding now to defer all work on AFE12, and to decide to instrument at least the CFT stereo/CPS cassettes with AFE8. The FPS, if done with AFE8, would want to have special design modifications to allow the cross-over channels. This modified design, or resuscitation of AFE12, would wait with lower priority until the AFE8 for all CFT was going well. A note outlining the special constraints on the FPS cassettes due to the cross-over channels was prepared by George Ginther and Volker Buescher and is found from the main afe page. In addition to getting the CFT operational as quickly as possible, benefits of such a decision would include the possibility of saving money (AFE8's cheaper than AFE12's), allowing some critical manpower to focus on AFE8 production and tests. Downside factors are the loss of the dual range operation of at least CPS, and difficulties of calibration of the CPS (FPS). We plan a special meeting Thursday to consider this possible decision further. ***Salles DZero at 1-3PM ***