Combined License Applications for New Reactors
Location of Projected New Nuclear Power Reactors
Applications Received
Bell Bend
Bellefonte, Units 3 & 4
Callaway, Unit 2
Calvert Cliffs, Unit 3
Comanche Peak Units, 3 & 4
Fermi, Unit 3
Grand Gulf, Unit 3
Levy County, Units 1 & 2
Nine Mile Point, Unit 3
North Anna, Unit 3
River Bend Station, Unit 3
Shearon Harris, Units 2 & 3
South Texas Project, Units 3 & 4
Victoria County Station, Units 1 & 2
Virgil C. Summer, Units 2 & 3
Vogtle, Units 3 & 4
William States Lee III, Units 1 & 2

Nine Mile Point, Unit 3 Application

Nine Mile Point
Who:   Nine Mile Point Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC (UniStar)

What:   Application for a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (U.S. EPR) designated as Nine Mile Point, Unit 3

When:   September 30, 2008 (date of application submittal)

Where:   UniStar Nuclear Energy's Nine Mile Point site in Oswego, New York

On this page:

Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Date Description
02/09/09 Letter to the NRC - Subject: Nine Mile Point Unit 3 Combined Operating License Application Review Schedule
11/18/08 COL Supplement: FSAR Section 2.5
10/24/08 COL Supplement: Updated Figures for FSAR Chapter 8
09/30/08 UniStar Nuclear Energy transmittal letter for Nine Mile Point COLA
  • Part 1 - General Information
  • Part 2 - Final Safety Analysis Report
  • Part 3 - Environmental Report
  • Part 4 - Technical Specifications
  • Part 5 - Emergency Plan
  • Part 6 - Limited Work Authorization
  • Part 7 - Departures and Exemption Requests
  • Part 8 - Security Plan [This Part contains safeguards information which is with-held from public availability]
  • Part 9 - Proprietary and Sensitive Unclassified Non-Safeguards Information [This Part contains other information which is with-held from public availability]
  • Part 10 - Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) and ITAAC Closure
  • Part 11A - Quality Assurance Program Description
  • Part 11B - AREVA Design Control Document
  • Part 11C - AREVA DCD Supplements
  • Part 11D - NEI References
  • Part 11E - Fuel Rack Supplements
  • Part 11F - Boring Logs

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 09/30/08 - A
Acceptance Review
Acceptance Review Start
10/06/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
12/12/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
TBD
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
 
Phase 2 - SER with Open Items issued
 
Phase 3 - ACRS Review of SER with Open Items Complete
 
Phase 4 - Advanced SER with no Open Items Issued
 
Phase 5 - ACRS Review of SER with no Open Items Complete
 
Phase 6 - Final SER Issued
 
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
 
Phase 2 - Draft EIS issued to EPA
 
Phase 3 - Response to public comments on draft EIS issued
 
Phase 4 - Final EIS issued to EPA
 
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

NRC Documents

Date Description
02/11/09 Notice of Cancellation of Environmental Scoping and February 25, 2009 Public Scoping Meeting
01/26/09 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping
12/12/08 Notification of Docketing and Federal Register Notice
10/22/08 Acknowledgment of Receipt of Application and Federal Register Notice

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety   None Issued Yet  
Environmental   None Issued Yet  

To top of page

Public Meetings

Date Description
  None have been scheduled

To top of page

Contacts

Contacts for the Nine Mile Point COL Application
Safety Project Manager Prosanta Chowdhury
Environmental Project Managers Paul Michalak (Lead PM)
Philip Brandt (Co-PM)
Contact a Public Affairs Officer