This is the accessible text file for GAO report number GAO-03-570T 
entitled 'Department of Energy: Status of Contract and Project 
Management Reforms' which was released on March 20, 2003.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Mr. Chairman and Members of the Committee:



We are pleased to be here today to discuss the status of contract and 

project management reforms in the Department of Energy (DOE). DOE 

spends more money on contracts than any other civilian federal agency 

because it relies primarily on contractors to operate its sites and 

carry out its diverse missions. These missions include maintaining the 

nuclear weapons stockpile, cleaning up radioactive and hazardous waste, 

and supporting basic energy and science research activities. For fiscal 

year 2001, DOE spent about 90 percent of its total annual budget, or 

about $18.2 billion, on contracts. Of that amount, DOE spent about 

$16.2 billion on contracts to manage or operate 28 major DOE sites.



For over a decade, GAO, DOE’s Office of Inspector General, and others 

have identified problems with DOE’s contracting practices and the 

performance of its contractors. Projects were late or never finished; 

project costs escalated by millions and sometimes billions of dollars; 

and environmental conditions at the sites did not significantly 

improve. At the same time, contractors were earning a substantial 

portion of the profit (fee) available under the contract. Because of 

these problems, since 1990 we have designated DOE contract management 

as a high-risk area vulnerable to fraud, waste, abuse, and 

mismanagement.



To address these and other problems, DOE began a series of reforms in 

the 1990s that were intended to, among other things, strengthen DOE’s 

contracting and project management practices, hold contractors more 

accountable for their performance, and demonstrate progress in 

achieving the agency’s missions. In this context, contracting practices 

include, among other things, selecting the type of contract (such as 

fixed-price), deciding whether to ask contractors to compete for the 

contract or offer it only to a single contractor, and determining the 

performance measures that will be used to assess and reward the 

contractor’s performance. Similarly, project management practices 

include, among other things, planning, organizing, and tracking project 

activities and costs; training to ensure expertise of federal project 

managers; and project reporting and oversight.



In addition, in February 2002, DOE’s environmental management team 

launched an improvement initiative that places additional emphasis on 

contracting and project management reforms in the cleanup program, 

which represents almost a third of the department’s overall budget. 

This initiative followed a review by DOE managers, who concluded that 

the waste cleanup program was not achieving the desired results and 

that further improvements were needed to make the program effective, 

including improvements in contracting and project management.



In this context, my testimony today focuses on (1) describing DOE’s 

progress in implementing contracting and project management reforms, 

(2) assessing the extent to which these reforms have resulted in 

improved contractor performance, and (3) providing observations on 

DOE’s latest improvement efforts. My testimony is based on our past 

work in this area as well as the findings of DOE’s Inspector General 

and the National Research Council, who, at DOE’s request, independently 

reviewed DOE’s project management practices.



In summary:



Since the mid-1990s, DOE has made some progress in implementing 

initiatives to improve both its contracting practices and its 

management of projects, but it continues to encounter difficulties in 

implementing these reforms. Contract reform began in 1994 and consisted 

primarily of initiatives in three key areas--developing alternative 

contracting approaches, increasing competition for contracts among 

potential bidders, and using performance-based incentives in the 

contracts. For example, DOE now requires performance-based contracts at 

all of its major sites. These contracts incorporate performance-based 

statements of work and identify performance measures and objectives 

that DOE will use to evaluate the contractors’ performance. DOE has 

also increased the proportion of contractors’ fees tied to achieving 

the performance objectives. Nevertheless, difficulties remain in 

implementing the reforms. For example, numerous studies and reports 

found that DOE’s performance-based contracts had ineffective 

performance measures. DOE continues to modify and test its performance 

measures by, for example, developing multiyear and multisite measures 

that are more closely aligned with the department’s missions. Regarding 

project management reforms, DOE began its reform effort in 1999 in 

response to recommendations from the National Research Council that 

were intended to improve DOE’s oversight and management of projects. 

Among other things, DOE implemented new policy and guidance for 

developing and controlling projects and established a project office to 

lead the initiative. However, in November 2001 the National Research 

Council reported that, although DOE had taken some positive steps to 

address its recommendations, the department still did not adequately 

plan projects before starting them and had no training program for 

federal project managers. DOE is continuing its efforts to implement 

its project management initiative.



While DOE has made some progress in implementing its contracting and 

project management initiatives, available information raises doubts 

about the extent to which these reforms have resulted in improved 

contractor performance. DOE has developed little objective information 

to demonstrate whether the reforms have improved results. However, in 

September 2002, we reported that, based on a comparison of 25 major DOE 

projects in 1996 with 16 major projects in 2001,[Footnote 1] it did not 

appear that DOE’s contractors had significantly improved their 

performance over the period. In both sets of projects, over half had 

both schedule delays and cost increases. And the proportion of projects 

with significant cost increases and schedule delays was actually higher 

in 2001 than in 1996. For example, 38 percent of the projects we 

reviewed in 2001 had doubled their initial cost estimates, compared 

with 28 percent in 1996. Furthermore, problems with individual projects 

and with site operating contracts continue to appear. These include a 

3-year delay and $2.1 billion cost increase to submit the license 

application for the Yucca Mountain waste repository project in Nevada 

and allegations of contractor fraud, waste, and abuse at the Los Alamos 

National Laboratory in New Mexico.



In 2002, we saw DOE’s management team take encouraging steps that could 

help to foster improvements in contract and project management. The 

Environmental Management program, which administers DOE’s waste cleanup 

program, completed a frank and open assessment of problems with the 

program and initiated a number of additional reforms. These initiatives 

included improving contract and project management and streamlining 

business practices. DOE has also been working on agencywide 

initiatives, including developing an integrated budgeting and program 

results information system and placing increased emphasis on human 

capital initiatives to develop the department’s future leaders. 

Although these management actions are encouraging, making these new 

policies a matter of practice will require strong leadership, clear 

lines of accountability and responsibility, and effective management 

systems to monitor results.



Before I discuss these issues in greater detail, I would like to 

explain why improving DOE’s contracting and project management 

practices is so important.



Background:



DOE’s missions include developing, maintaining, and securing the 

nation’s nuclear weapons capability; cleaning up the environmental 

legacy resulting from over 50 years of producing nuclear weapons; and 

conducting basic energy and science research and development. The 

department carries out these diverse missions at over 50 major 

installations in 35 states. DOE’s contractors manage and operate these 

facilities and sites and undertake the construction of new facilities 

under the direction of department employees in program offices at DOE 

headquarters and in its field offices. With a DOE workforce of about 

16,000 employees and over 100,000 contractor staff, the department 

relies heavily on its contractors to accomplish its missions. Because 

DOE spends about 90 percent of its annual budget on contracts, DOE’s 

ability to direct, oversee, and hold accountable its contractors is 

crucial for mission success and overall effectiveness.



In 1990, we designated DOE contract management as a high-risk area 

vulnerable to fraud, waste, abuse, and mismanagement because DOE relies 

on contractors to carry out its missions and because of its history of 

both inadequate management and oversight and failure to hold its 

contractors accountable for results. In our January 2001 report on 

DOE’s major management challenges, we broadened the definition of 

contract management to include both contracting and project 

management.[Footnote 2] This expanded definition reflects our view that 

contracting and project management activities and responsibilities are 

interrelated and that effective performance in both areas is essential 

if DOE is to achieve its mission goals. In January 2003, we reported 

that the high-risk designation for DOE contract management still 

applies.[Footnote 3]



DOE Has Made Progress in Implementing Contracting and Project 

Management Reforms, but Difficulties Remain:



Since the mid-1990s, DOE has made progress in its efforts to improve 

both its contracting practices and its management of projects, but the 

department continues to face problems in implementing these reforms. In 

1994, DOE began evaluating its contracting practices and implementing a 

series of reforms intended to improve results by enhancing contractor 

performance. Because of continued problems with the management and 

oversight of DOE’s projects, the conference report accompanying DOE’s 

fiscal year 1998 Energy and Water Development Appropriations Act 

directed DOE to obtain an independent review of its project management 

capabilities. DOE contracted with the National Research Council 

(Council) for this study, and in 1999 began its project management 

initiative to implement the Council’s recommendations.[Footnote 4]



Contract Reforms Focused on Developing Alternative Contracting 

Approaches, Increasing Competition, and Using Performance-Based 

Contracts:



As we reported in September 2002, the department has made progress in 

implementing three key contract reform initiatives--developing 

alternative contracting approaches, increasing competition, and 

converting to performance-based contracts--although DOE continues to 

encounter challenges in implementing these initiatives.[Footnote 5]



Using Alternative Contracting Approaches:



One of the major focuses of DOE’s contract reform initiative was to 

develop alternatives to the traditional contracts used to manage and 

operate its major sites and facilities. Under these traditional 

“management and operating” contracts, one primary contractor performed 

almost all of the work at a site, the contractor had broadly defined 

statements of work, and DOE reimbursed the contractor for virtually all 

costs. As a result, work under these contracts focused more on annual 

work plans and budgets rather than on specific schedule and cost 

targets for accomplishing work. In implementing alternatives to these 

contracting arrangements, DOE intended to use the best contracting 

alternative given the required work and the objectives and risks 

associated with that work. To accomplish that goal, the department 

encouraged the use of different contracting approaches, such as fixed-

price contracts that would shift the risk for performance to the 

contractor rather than the government, or “closure contracts,” which 

tie the contractor’s fee to cleaning up and closing a site rather than 

meeting annual targets.



However, DOE did not always systematically determine the best contract 

type for a given situation and thus experienced problems with 

implementation. For example, we reported in May 1998 that DOE’s use of 

fixed-price contracting was appropriate when projects were well-defined 

and when uncertainties could be allocated between DOE and the 

contractor.[Footnote 6] When these conditions did not exist, cost 

overruns and schedule delays could occur. DOE has used fixed-price 

contracts for both small, relatively simple projects, such as laundry 

services, as well as for large, complex cleanup projects. We reported 

that this approach was generally not successful in controlling costs on 

large, complex cleanup projects, such as the project to retrieve high-

level tank wastes and prepare the wastes for disposal at DOE’s Hanford, 

Washington, site because of the high level of technical uncertainty and 

risk. To more systematically select the type of contract, DOE has been 

developing and implementing a formal strategy to evaluate contracting 

and financing alternatives and the associated business and technical 

risks before deciding on the best contracting approach.



Increasing Competition:



Federal law generally requires federal agencies to use competition in 

selecting a contractor. However, until the mid-1990s DOE contracts for 

the management and operation of its sites generally fit within an 

exception that allowed for the use of noncompetitive procedures. As 

part of its contract reform initiative, DOE changed its contracting 

rules to set competition as the standard approach to awarding 

contracts. Under these revised regulations, the percentage of major 

site contracts awarded competitively (competed) increased to 56 percent 

as of 2001, up from 38 percent as of 1996. By 2001, 10 of the 11 

contracts that had not been competed were for managing research and 

development centers which are statutorily exempt from mandatory 

competition.[Footnote 7] Despite this exemption, DOE evaluates these 

contracts towards the end of their current contract term to determine 

whether they should be extended or competed.



DOE has thus far decided on noncompetitive extensions for these 

contracts for research and development centers, including some for 

contractors that have experienced performance problems. For example, in 

2001, DOE extended the managing and operating contracts with the 

University of California, the contractor operating Los Alamos and 

Lawrence Livermore National Laboratories. The University of California 

has operated these sites for 50 years or more and is the only 

contractor ever to have operated them. In recent years, we and other 

organizations have reported significant problems with laboratory 

operations and management at these two laboratories--particularly in 

the areas of safeguards, security, and project management.[Footnote 8] 

Although congressional committees and others have called for DOE to 

compete these contracts, DOE so far has opted to address these 

performance problems with specific contract provisions. However, it 

remains to be seen whether DOE will be successful in improving the 

University of California’s performance using this approach.



Using Performance-Based Contracts:



Before DOE initiated its contract reforms, major site contracts 

generally had broad statements of work that focused more on annual 

budgets and work plans rather than specific results to be achieved. 

Fees under these contracts usually consisted of a base amount that was 

guaranteed (fixed) plus an award amount that was paid if the contractor 

met general performance expectations.[Footnote 9] In the mid-1990s, DOE 

began restructuring its major site contracts to use results-oriented 

statements of work and to incorporate performance incentive fees that 

were designed to reward the contractor if it met or exceeded specific 

performance expectations in priority areas. As of 2002, DOE reported 

that all of its major site contracts incorporated performance-based 

techniques to define requirements and measure results. To further 

emphasize the importance of the performance-based approach, DOE has 

increased the proportion of contractor fees tied to achieving the 

performance objectives to 70 percent in fiscal year 2001, from 34 

percent in fiscal year 1996.



Despite this progress, development of good performance measures has 

continued to be a challenge for DOE. Numerous studies and reports found 

that DOE’s performance-based contracts contained ineffective 

performance measures. For example, in 2001, DOE’s Office of Inspector 

General reported on the performance measures in three major site 

contracts.[Footnote 10] According to this report, DOE was not focusing 

on high-priority outcomes, was loosening performance requirements over 

time without adequate justification, and was failing to match 

appropriately challenging contract requirements with fee amounts. The 

department disagreed with this report, stating that it was not 

appropriate to evaluate the overall success of performance-based 

contracts by looking at individual performance measures. However, DOE 

continues to modify and test its performance measures to focus on 

developing performance incentives that are more directly linked to the 

priority missions at a site. For example, DOE has developed multiyear 

incentives in the management and operating contract for the Hanford 

site, and multisite incentives that tie together activities at four 

production sites. Nevertheless, the department acknowledges that it 

must make further progress in this area.



Project Management Reforms Ranged from New Policy and Guidance to an 

Improved System to Track Project Performance:



DOE’s initiative to reform project management stems from 1999 National 

Research Council recommendations for improving DOE project management. 

The Council reported that DOE’s construction and environmental 

remediation projects take much longer and cost about 50 percent more 

than comparable projects by other federal agencies or projects in the 

private sector. It also reported that DOE’s project management 

practices fell far short of best practices in a number of areas, when 

compared with other government agencies and the private sector. The 

areas included DOE’s policies and procedures; documentation and 

reporting; project planning and controls; risk management; project 

reviews, acquisition, and contracting; organizational structure, 

responsibility, and accountability; and the selection, training, and 

skills of personnel.



Since 1999, when DOE established the Office of Engineering and 

Construction Management to lead the project management initiative, the 

department has been working to implement the Council’s recommendations. 

In particular, in 2000, DOE issued a new policy, order, and guidance on 

managing and controlling projects. In 2001, DOE established new 

guidance that required the approval of projects of $5 million and above 

at the assistant secretary level or higher, and a project tracking 

system and monthly status reports on all projects with total costs over 

$5 million. Furthermore, in 2002, DOE established a performance goal 

that 85 percent of its major projects would have less than a 10-percent 

variance in either cost or schedule.



Despite these steps, many implementation challenges remain. In a 

November 2001 follow-up report, the Council noted that although DOE had 

taken positive steps in response to the recommendations in the 1999 

report,[Footnote 11] change had been inordinately slow, and there was 

no evidence that DOE’s project management practices in the field had 

actually improved. Furthermore, DOE still had inadequate up-front 

project planning, no consistent system for evaluating the relative 

risks of projects, and no project management training program in place. 

The Council concluded that DOE was not in control of many of its 

projects and had virtually abdicated its ownership role in overseeing 

and managing its contracts and contractors.



Available Information Raises Doubts About Extent to Which Contract and 

Project Management Reforms Have Improved Contractor Performance:



DOE has little objective information demonstrating whether its reforms 

have resulted in improved contractor performance. Instead of measuring 

outcome-oriented performance results, DOE has primarily gauged progress 

by measuring the implementation of the initiatives and by reviewing 

individual contracts. While DOE can point to examples of success, 

objective performance information on overall results is scarce. Indeed, 

the evidence on DOE major projects that we developed suggests that 

contractor performance may not have improved.



Contractor Performance May Not Have Improved:



In our September 2002 report, as a potential indicator of contractor 

performance, we evaluated changes in cost and schedule for 16 of DOE’s 

major projects as of 2001 and compared them with similar information we 

developed on DOE’s major projects in 1996. We found no indication of 

improved performance; in both groups of projects, over half of the 

ongoing projects were experiencing significant cost increases, schedule 

delays, or both. Furthermore, as shown in table 1, the proportion of 

projects experiencing cost increases of more than double the initial 

cost estimates or schedule delays of 5 years or more increased over the 

6-year period. For example, the initial cost estimate in 1998 for the 

spent nuclear fuels dry storage project at the Idaho Falls site was 

$123.8 million, with a completion date of 2001. In 2002, the cost 

estimate for this project was $273 million, with a completion date of 

2006. Appendix I contains additional information on DOE’s ongoing major 

projects as of December 2001.



Table 1: Cost Overruns and Schedule Delays for Ongoing Projects in 1996 

Compared with Ongoing Projects in 2001:



Number of projects reviewed; Number of projects: 1996: 25[A]; Number of 

projects: 1996: [Empty]; Number of projects: 2001: 16[B]; Number of 

projects: 2001: [Empty].



Projects with a cost estimate of more than double the initial cost 

estimate; Number of projects: 1996: 7; Number of projects: 1996: (28%); 

Number of projects: 2001: 6; Number of projects: 2001: (38%).



Projects with schedule delays of 5 years or more; Number of projects: 

1996: 8; Number of projects: 1996: (32%); Number of projects: 2001: 6; 

Number of projects: 2001: (38%).



[A] We evaluated 34 projects in 1996 with estimated costs greater than 

$100 million. However, nine of the projects were environmental 

restoration projects, and DOE’s original and/or current cost estimates 

did not estimate costs through project completion. In 1998, DOE divided 

these environmental restoration projects into multiple projects at each 

site. Therefore, we excluded these projects from our current analysis.



[B] There are 10 additional projects with total project costs greater 

than $200 million, but those projects had either recently started or 

have been suspended.



Source: GAO.



[End of table]



The projects we reviewed--with estimated costs ranging from $270 

million to $8.4 billion--may not be representative of all DOE 

projects.[Footnote 12] Although this comparison provides only a limited 

measure of contractor performance, it does raise questions about the 

overall impact of DOE’s initiatives on improving contractor 

performance.



Anecdotal Evidence Provides No Overall Measure of Improved Performance:



Most of DOE’s evidence of progress has been anecdotal. On this basis, 

DOE can certainly point to some successes. For example:



Officials at DOE’s Albuquerque operations office pointed out that after 

competing the contract for the Pantex site, the new contractor met 

production levels that were not achieved by the previous contractor.



In a 1999 internal review of its performance-based contracting 

practices,[Footnote 13] DOE reported that “anecdotal evidence supports 

that the proper use of well-structured, performance-based incentives is 

leading to improvements in performance at some DOE sites.” One of the 

examples cited was at Rocky Flats, where DOE reported that contractor 

performance had improved with a new contractor, selected in 1995, and 

with performance-based incentives in the contract.



However, we have identified numerous projects or sites where 

performance problems continued to occur. For example:



The National Ignition Facility at Lawrence Livermore National 

Laboratory in California is designed to produce intense pressures and 

temperatures to simulate in a laboratory the thermonuclear conditions 

created in nuclear explosions. We reported in August 2000 that the 

estimated cost of the facility had increased from $2.1 billion to $3.3 

billion and that the scheduled completion date had been extended by 6 

years to 2008.[Footnote 14] We attributed these major cost and schedule 

changes to inadequate management by the contractor and DOE oversight 

failures.



Paducah, Kentucky, is the site of DOE facilities used to enrich uranium 

for use in nuclear power plants. There is considerable waste material 

on site and significant on-site and off-site ground water 

contamination. In 2000, we reported that DOE’s cleanup plan contained 

several assumptions and uncertainties that could significantly increase 

the time and add billions of dollars to the cost of cleaning up the 

site.[Footnote 15] For example, not all areas needing cleanup were 

included in the plan and assumptions about available funding to address 

the problems were unrealistic.



The Yucca Mountain Site Characterization Project, Nevada, is developing 

a high-level waste repository. The original project baseline estimated 

a total project cost of $6.3 billion and an October 2001 date for 

submitting a license application. DOE’s latest estimate is that the 

license application will not be submitted until December 2004, with an 

estimated cost of almost $8.4 billion. We reported in December 2001 

that DOE had stopped using the baseline to manage the project and was 

using estimates that were never approved or incorporated into the 

official project baseline.[Footnote 16] Using baseline and change 

control procedures is essential to ensuring that the project is being 

managed effectively.



Los Alamos National Laboratory, New Mexico, is one of DOE’s primary 

locations for research on nuclear weapons. Allegations of contractor 

fraud, waste, and abuse and of poor internal controls by the University 

of California, which operates the laboratory for DOE, have surfaced in 

the last few months and have led to numerous investigations (currently 

ongoing) and questions about the adequacy of DOE’s oversight of 

laboratory activities and personnel.



Problems are also beginning to emerge at the Hanford site in Washington 

State, where a contract is in place to address the high-level tank 

wastes. We learned recently that, although the baseline for this $4 

billion project was established in May 2002, as of January 2003, the 

project was already 10 months behind schedule, and the contractor was 

estimating cost increases and other adjustments to the contract that 

could total over $1 billion. DOE withheld provisional fee payments to 

the contractor in January 2003, based on this “unacceptable 

performance.”:



Although interesting and sometimes revealing, anecdotal information 

provides no overall measure of whether the performance of DOE’s 

contractors is improving or getting worse. DOE appears to have 

recognized the limitations of anecdotal information and is taking steps 

to implement a departmentwide project analysis and reporting system. 

Such a system, if successfully implemented, could provide the 

information needed to conduct overall assessments of contractor 

performance.



Achieving Improved Contractor Performance Will Require Commitment and 

Perseverance:



DOE’s most recent management initiatives indicate that the department 

is aware it still has a long way to go in improving contractor 

performance. While the limited progress to date is discouraging, the 

frank admission of problems in the cleanup program and subsequent 

improvement efforts are an encouraging sign. The 2002 “top-to-bottom” 

review of the Environmental Management program concluded that process 

rather than cleanup results had become the basis for cleanup 

approaches, contracts, and performance measures.[Footnote 17] Only 

about one-third of the budget was going toward actual cleanup; the 

remainder was spent on maintenance, support activities, and fixed 

costs. Furthermore, the review team concluded that DOE’s financial 

liability would continue to grow well beyond the $220 billion estimated 

at the time if significant changes to the program were not made. The 

team’s report stated that without higher performance standards and 

breakthrough business processes, cost growth and schedule delays would 

continue to obstruct cleanup, and the risk to workers, the public, and 

the environment would not be reduced.



The report recommended a series of initiatives to address these 

problems. These initiatives include developing an accelerated, risk-

based cleanup strategy; improving contract management and establishing 

more meaningful performance measures for contractors; improving project 

management; and streamlining business practices. In addition, the 

report recommended implementing an effective human capital strategy to 

increase the technical expertise of DOE staff and improve 

accountability for results.



In addition to the efforts of the Environmental Management program, DOE 

is working on improving its agencywide management information systems 

and human capital systems. For example, in 2001, DOE began developing a 

unified planning, programming, budgeting, and evaluation process to 

integrate budget and program results information. Also in 2001, DOE 

began developing a training and certification program for federal 

project management, and strategies to address skill gaps in its 

contracting and project management workforce.



DOE has a long way to go before it can claim that its contracting and 

project management problems are over. As we have reported before, 

making new policy a matter of practice requires strong leadership, 

especially in an organization like DOE, which has diverse missions, a 

confusing organizational structure, and a weak culture of 

accountability.[Footnote 18] But the scope and magnitude of the reforms 

being contemplated in the Environmental Management program indicate to 

us for the first time that the management team has seen and understood 

the full extent of the challenges DOE faces. And because DOE expects to 

spend hundreds of billions of dollars in future years on missions 

important to the well-being of the American people, such as cleaning up 

nuclear wastes and ensuring the safety and reliability of our nuclear 

weapons, there are compelling reasons to ensure that it has in place an 

effective set of contracting and project management practices and 

controls.



- - - --:



Thank you, Mr. Chairman and Members of the Committee. That concludes my 

testimony. I would be pleased to respond to any questions that you may 

have.



Contacts and Acknowledgements:



For further information on this testimony, please contact Ms. Robin 

Nazzaro at (202) 512-3841. Individuals making key contributions to this 

testimony included Carole Blackwell, Bob Crystal, Doreen Feldman, Stan 

Stenersen, Bill Swick, and Arvin Wu.



Appendix I:



Cost and Schedule Performance on DOE’s Major Projects, as of December 

2001:



As we reported in September 2002, table 2 shows the original and 

revised cost estimates and completion dates for ongoing DOE projects 

with estimated costs greater than $200 million. We excluded from the 

table 10 additional DOE projects with estimated costs greater than $200 

million because the projects were suspended or only recently started as 

of December 2001.



Table 2: Original and Revised Cost Estimates and Schedule for DOE 

Projects with Estimated Costs Greater than $200 Million as of December 

2001:







Project name and construction line number[A]: 

Advanced Mixed Waste Treatment Project (97-PVT-2)[C]; Cost: Original 

cost estimate[B]: $1,078.9; Cost: Revised cost estimate: $1,087.7[D]; 

Schedule: Original completion date: December 2002; Schedule: Revised 

completion date: December 2002.



Project name and construction line number[A]: 

Civilian Radioactive Waste Management Program[E]; Cost: Original cost 

estimate[B]: 6,300.0[F]; Cost: Revised cost estimate: 8,394.6; 

Schedule: Original completion date: October 2001[F]; Schedule: Revised 

completion date: December 2004.



Project name and construction line number[A]: 

Dual-Axis Radiographic Hydrodynamic Test Facility (97-D-102)[G]; Cost: 

Original cost estimate[B]: 30.0[H]; Cost: Revised cost estimate: 269.7; 

Schedule: Original completion date: September 1990; Schedule: Revised 

completion date: December 2002.



Project name and construction line number[A]: East 

Tennessee Technology Park Three-Building Decontamination and 

Decommissioning and Recycle Project (OR-493); Cost: Original cost 

estimate[B]: 283.9; Cost: Revised cost estimate: 348.1; Schedule: 

Original completion date: December 2003; Schedule: Revised completion 

date: March 2004.



Project name and construction line number[A]: 

Facilities Capability Assurance Program (88-D-122)[I]; Cost: Original 

cost estimate[B]: N/A[J]; Cost: Revised cost estimate: 445.6; Schedule: 

Original completion date: N/A[J]; Schedule: Revised completion date: 

June 2000.



Project name and construction line number[A]: 

Hanford Tank Waste Treatment and Immobilization Plant (01-D-416); Cost: 

Original cost estimate[B]: 12,488.0[K]; Cost: Revised cost estimate: 

4,350.0; Schedule: Original completion date: 2007; Schedule: Revised 

completion date: 2007.



Project name and construction line number[A]: 

High-Level Waste Removal from Filled Waste Tanks (93-D-187)[L]; Cost: 

Original cost estimate[B]: 88.6[M]; Cost: Revised cost estimate: 

1,550.5; Schedule: Original completion date: September 1999[M]; 

Schedule: Revised completion date: September 2028.



Project name and construction line number[A]: 

Initial Tank Retrieval Systems (94-D-407); Cost: Original cost 

estimate[B]: 245.0[N]; Cost: Revised cost estimate: 274.9; Schedule: 

Original completion date: March 2000[N]; Schedule: Revised completion 

date: December 2015.



Project name and construction line number[A]: 

National Ignition Facility (96-D-111); Cost: Original cost estimate[B]: 

1,073.6; Cost: Revised cost estimate: 2,248.1; Schedule: Original 

completion date: June 2002; Schedule: Revised completion date: 

September 2008.



Project name and construction line number[A]: 

Silos; Cost: Original cost estimate[B]: N/A; Cost: Revised cost 

estimate: 338.1; Schedule: Original completion date: N/A; Schedule: 

Revised completion date: December 2006.



Project name and construction line number[A]: 

Spallation Neutron Source (99-E-334); Cost: Original cost estimate[B]: 

1,332.8; Cost: Revised cost estimate: 1,411.7; Schedule: Original 

completion date: September 2005; Schedule: Revised completion date: 

June 2006.



Project name and construction line number[A]: 

Spent Nuclear Fuel Dry Storage (98-PVT-2)[O]; Cost: Original cost 

estimate[B]: 123.8; Cost: Revised cost estimate: 273.0; Schedule: 

Original completion date: June 2001; Schedule: Revised completion date: 

December 2005.



Project name and construction line number[A]: 

Hanford Spent Nuclear Fuels; Cost: Original cost estimate[B]: 714.8; 

Cost: Revised cost estimate: 1,600.0; Schedule: Original completion 

date: 2001; Schedule: Revised completion date: September 2006.



Project name and construction line number[A]: Tank 

Farm Restoration and Safe Operations (97-D-402); Cost: Original cost 

estimate[B]: 289.2; Cost: Revised cost estimate: 285.3; Schedule: 

Original completion date: June 2005; Schedule: Revised completion date: 

June 2005.



Project name and construction line number[A]: 

Tritium Extraction Facility (98-D-125)[P]; Cost: Original cost 

estimate[B]: 390.7; Cost: Revised cost estimate: 401.0; Schedule: 

Original completion date: June 2005; Schedule: Revised completion date: 

March 2006.



Project name and construction line number[A]: 

Weldon Springs Site Remedial Action Project; Cost: Original cost 

estimate[B]: 357.7[Q]; Cost: Revised cost estimate: 905.2; Schedule: 

Original completion date: September 1995[Q]; Schedule: Revised 

completion date: September 2002.



Source: GAO analysis of DOE and National Research Council data.



[A] Projects that are not funded as construction line items do not have 

project numbers. All costs, unless otherwise specified, are “total 

project costs.” The cost data were obtained from DOE Congressional 

budget requests and other DOE-provided data. The term N/A means cost or 

schedule not available or not yet developed.



[B] For consistency we used, when available, preliminary budget 

estimates submitted to Congress as the basis for original cost 

estimates.



[C] Total project cost for construction projects typically includes 

only the design, construction, and startup costs that precede 

production operations. Total project cost for this project also 

includes estimated costs for over 10 years of production operations and 

other associated costs. The revised completion date refers to 

completion of the construction phase.



[D] The contractor has submitted a “Request for Equitable Adjustment” 

of over $48 million due to a six-month schedule slip the project 

experienced as a result of a delay in the issuance of environmental 

permits. Because the Request for Equitable Adjustment is still under 

review, the $48 million is not included in the revised cost estimate.



[E] The original baseline for this program included construction of the 

exploratory studies facility and, if suitable, a site recommendation 

and a license application. The current scope of the program was 

broadened in 1997 to include all elements of the Civilian Radioactive 

Waste Management Program, which now includes development of license 

application, design and construction of Yucca Mountain Repository, 

licensing interactions with the Nuclear Regulatory Commission, and 

development of a transportation system. The revised completion date is 

only for the license application.



[F] We reported in 1996 that the current cost and completion date for 

the Yucca Mountain Site Characterization Project were $4,300 million 

and March 2002, respectively. In 1997, DOE expanded the project to 

include the entire Civilian Radioactive Waste Management Program.



[G] The original scope of this project at initial authorization in 1988 

included two buildings and two single pulse flash x-ray machines. The 

project has since undergone several changes in scope, which now 

includes three buildings, a containment vessel to reduce emissions to 

the environment, a single pulse machine, and a multiphase machine.



[H] This amount is a total estimated cost from the fiscal year 1988 

Budget Request, which does not include other project costs. Other 

project costs include supporting research and development and plant 

support costs during construction, activation, and startup. There was 

no requirement for a total project cost estimate in 1988.



[I] This project has a few subprojects completing closeout activities 

and two still underway. DOE anticipates additional funding needs and a 

schedule extension to complete the final two subprojects.



[J] We reported in 1996 that the current cost for the Facilities 

Capability Assurance Program was $447 million and the completion date 

was not available. No cost estimate was available when the project was 

originally proposed.



[K] This original cost estimate from the fiscal year 2001 Budget 

Request was based upon the privatization concept and included plant 

operations through fiscal year 2018.



[L] DOE expanded the original scope of this project in fiscal year 1994 

to incorporate three ongoing projects, which increased the total 

project cost from $88.6 million to $828 million and the project 

completion date from 1999 to 2008 in the fiscal year 1996 budget. The 

cost and schedule were revised again in fiscal year 2000 to include, 

among other projects, the equipment and infrastructure required to 

remove the high level waste inventory from nine additional tanks.



[M] We reported in 1996 that the current cost and completion date for 

the High Level Waste Removal project were $828.2 million and September 

2008, respectively. DOE expanded the scope of this project in 1994.



[N] We reported in 1996 that the current cost and completion date for 

the Initial Tank Retrieval System project were $358.2 million and March 

2010, respectively.



[O] The original and revised estimated costs include design, 

construction, startup, and operating costs. The revised completion date 

refers to completion of the construction and startup phase.



[P] In June 2002 DOE’s Office of Inspector General reported that the 

total project cost for the Tritium Extraction Facility could increase 

to as much as $500 million and that the facility may not be completed 

until December 2006.



[Q] We reported in 1996 that the current cost and completion date for 

the Weldon Springs Remedial Action Project were $865.0 million and 

2001, respectively.



[End of table]



(360322):



FOOTNOTES



[1] U.S. General Accounting Office, Contract Reforms: DOE Has Made 

Progress, but Actions Needed to Ensure Initiatives Have Improved 

Results, GAO-02-798 (Washington, D.C.: Sept. 13, 2002).







[2] U.S. General Accounting Office, Major Management Challenges and 

Program Risks: Department of Energy, GAO-01-246 (Washington, D.C.: Jan. 

2001).







[3] U.S. General Accounting Office, Major Management Challenges and 

Program Risks: Department of Energy, GAO-03-100 (Washington, D.C.: Jan. 

2003).







[4] National Research Council, Improving Project Management in the 

Department of Energy (Washington, D.C.: June 1999).







[5] U.S. General Accounting Office, Contract Reform: DOE Has Made 

Progress, but Actions Needed to Ensure Initiatives Have Improved 

Results, GAO-02-798 (Washington, D.C.: Sept. 13, 2002).







[6] U.S. General Accounting Office, Department of Energy: Alternative 

Financing and Contracting Strategies for Cleanup Projects, GAO/RCED-98-

169 (Washington, D.C.: May 29, 1998).







[7] The one exception was the major site contract for the management of 

DOE’s West Valley Demonstration Project in New York state. According to 

DOE procurement officials, the contract has been extended because of 

the limited amount of cleanup work remaining at the site and the lack 

of interest by other contractors to compete for the work.







[8] For example, see U.S. General Accounting Office, Department of 

Energy: Key Factors Underlying Security Problems at DOE Facilities, 

GAO/T-RCED-99-159 (Washington, D.C.: Apr. 20, 1999); U.S. General 

Accounting Office, Nuclear Security: Improvements Needed in DOE’s 

Safeguards and Security Oversight, GAO/RCED-00-62 (Washington, D.C.: 

Feb. 24, 2000); and A Special Investigative Panel, President’s Foreign 

Intelligence Advisory Board, Science at its Best, Security at its 

Worst: A Report on Security Problems of the U.S. Department of Energy 

(Washington, D.C.: June 1999).







[9] The contract fee is the amount DOE pays to the contractor over the 

allowable costs under the contract.







[10] U.S. Department of Energy, Use of Performance-Based Incentives at 

Selected Departmental Sites, DOE/IG-0510 (Washington, D.C.: Jul. 9, 

2001). 











[11] National Research Council, Progress in Improving Project 

Management at the Department of Energy--2001 Assessment (Washington, 

D.C.: Nov. 2001).







[12] As of January 2002, DOE records indicated at least 42 ongoing 

projects with estimated costs greater than $100 million. We did not 

review all of DOE’s capital projects with costs over $100 million 

because of the level of effort that would have been required, since DOE 

does not maintain centralized information on those projects. 

Furthermore, five of the ongoing projects we reviewed in 2001 began 

before the advent of DOE’s contract reform initiatives. 







[13] U.S. Department of Energy, Follow-up Assessment of the 

Effectiveness of Actions Taken to Improve Performance-Based Incentives 

in Performance-Based Management and Management and Integration 

Contracts (Washington, D.C.: Mar. 31, 1999).







[14] U.S. General Accounting Office, National Ignition Facility: 

Management and Oversight Failures Caused Major Cost Overruns and 

Schedule Delays, GAO/RCED-00-271 (Washington, D.C.: Aug. 8, 2000).







[15] U.S. General Accounting Office, Nuclear Waste Cleanup: DOE’s 

Paducah Plan Faces Uncertainties and Excludes Costly Cleanup 

Activities, GAO/RCED-00-96 (Washington, D.C.: Apr. 28, 2000).







[16] U.S. General Accounting Office, Nuclear Waste: Technical, 

Schedule, and Cost Uncertainties of the Yucca Mountain Repository 

Project, GAO-02-191 (Washington, D.C.: Dec. 21, 2001).







[17] U.S. Department of Energy, A Review of the Environmental 

Management Program (Washington, D.C.: Feb. 4, 2002).







[18] U.S. General Accounting Office, Department of Energy: Fundamental 

Reassessment Needed to Address Major Mission, Structure, and 

Accountability Problems, GAO-02-51 (Washington, D.C.: Dec. 21, 2001).