DIVE OPERATIONS
Daily Operations
05:30-06:30 Critical System Startup (ECS, BGS)
06:30-07:30 Pre-test Checklist (Test team: 50 personnel)
Physical Training for Staff (lap swim)
Suit and Tool delivery to tank deck
07:30-08:00 Astronaut Pre-brief by Test Conductor
Daily Physicals
Final Test Setup Prep (2nd Dive Team, Rotation 1)
08:00-08:15 Test Team Pre-dive Briefing
08:15 Test Team Call to Station
08:15-08:40 Suit Donning
08:40-09:00 Subject Immersion and Initial Weigh-out
09:00 Transition of Control of Test from Test Director to Test Conductor
09:00-15:00 Subject Test Procedures
09:00-11:00 1st Dive Team, Rotation 1 (4 divers/subject: 2 safety, 1 utility, 1 camera)
11:00-13:00 2nd Dive Team, Rotation 2
13:00-15:00 1st Dive Team, Rotation 2
15:00-15:15 Subject Recovery and Suit Doffing
(10-minute post-dive observation period)
15:15-15:30 Locker Room
Suit and Tool Recovery and Servicing
15:30-17:00 Debrief (customer feedback evaluations)
15:30-18:30 Reconfiguration Shift, First Dive (3 Hours)
20:00-22:00 Reconfiguration Shift, Second Dive (2 Hours)
22:00-23:00 Post-dive Observation Period (OSHA Requirement)
|
|
|
|
|