FHWA > Engineering > Construction > Construction Guide > Design-Build Project Delivery |
Construction Program GuideDesign-Build Project DeliveryOn December 10, 2002 in response to section 1307 of TEA-21, FHWA published the final rule which established regulations for design-build contracting as 23 CFR Part 636. Subsequent modifications required by section 1503 of SAFETEA-LU resulted in revisions published in a final rulemaking on August 14, 2007. Among the revisions made by SAFETEA-LU were the elimination of the dollar thresholds for "qualified" projects; and permission to release an RFP or award a design-build contract prior to completion of NEPA. Design-build procurement processes which deviate from the requirements of 23 CFR 636 may require an SEP-14 work plan and approval. Authority/Legal Basis
Guidance
PDF files can be viewed with the Acrobat® Reader®
|
Events
More InformationContactJerry Yakowenko Construction Feedback |
|
This page last modified on 11/12/08 |