PhysicsAnalysisSoftware

This WBS was created on 05/29/1999.
 

Project Start Date: Jan 1 '98
Project Finish Date: Apr 17 '02

Task_Table1

WBS Name Duration Start_Date Resource_Names Percent_Complete Scheduled_Work
1 Physics Analysis Software 170 wks Jan 14 '99   8% 367 wks
             
1.1 Root Development and Support 170 wks Jan 14 '99   10% 281 wks
1.1.1 Evaluationa and planning for ROOT improvements and enhancements 14 wks Jan 14 '99 JPP[1.5] 80% 21 wks
1.1.2 Development and integration of new/improved features (in collaboration with world wide ROOT team) 52 wks Apr 22 '99 JPP[2] 10% 104 wks
1.1.3 Long Term Room Support 104 wks Apr 20 '00 JPP[1.5] 0% 156 wks
             
1.2 Commercial product evaluation and integration 16 wks Jan 14 '99 JPP[0.5] 15% 8 wks
1.3 Support for Commercial Products 78 wks May 6 '99 JPP[0.5] 0% 39 wks
             
1.4 LHC++ evaluation and collaboration 78 wks Jan 14 '99 JPP[0.5] 10% 39 wks

Resource_Table1

Name Available FTEs Max # of FTEs Needed
JPP 2.3 3