Cmgt

This WBS was created on 05/29/1999.

This project is transitioning from the development to the support and maintenance phase. This will thus be the last WBS posted. Additional tasks will be handled through the monthly project meetings and presentations to the Run II Computing meetings. The packaging of products into KITS is a maintenance task. Work may occur for case tools - but only if the priority requests occur.

Project Start Date: Jan 1 '98
Project Finish Date: Dec 1 '99

Task_Table1


 
WBS
Name Duration Start_Date Resource %Complete
1 Configuration Management
100 wks
Jan 1 '98
 
55%
1.1 Meetings and Coordination
100 wks
Jan 1 '98
 
50%
1.2 C++ Deployment and Support - Unix/linux only
78 wks
Jun 1 '98
 
48%
1.2.1 KAI Compiler and Debugger 
78 wks
Jun 1 '98 JPP[0.5]
48%
1.2.1.1 Kai packaging, fixing and added value
0 wks
Jun 1 '98
 
100%
1.2.1.2 Kai vendor liaison
50 wks
Dec 14 '98
 
50%
1.2.1.3 Kai Debugger Support
12 wks
Dec 14 '98
 
40%
1.2.2 SGI Compilers
0 wks
Oct 1 '98 JPP[0.2]
0%
1.2.2.1 IRIX C++ V7.2.1 testing and certification
0 wks
Oct 1 '98
 
0%
1.2.3 EGCS ?
25.8 wks
Sep 1 '98 JPP[0.3]
0%
1.2.3.1 EGCS vendor liaison
0 wks
Sep 1 '98
 
0%
1.2.3.2 EGCS testing and certification
0 wks
Jan 1 '99
 
0%
1.2.3.3 EGCS packaging and deployment
0 wks
Mar 1 '99
 
0%
1.2.3.4 Support and consulting
0 wks
Jan 1 '99
 
0%
1.3 NT C++ Compiler Support
0 wks
Jan 1 '98 JPP[0.2]
0%
1.4 SoftRelTools
37.2 wks
Jul 1 '98 JPP
95%
1.4.1 SoftRelTools for KAI 3.3
0 wks
Jul 1 '98
 
100%
1.4.2 SoftRelTools for EGCS
0 wks
Jan 1 '99
 
100%
1.4.3 SoftRelTools ToDo List
24 wks
Oct 1 '98
 
94%
1.4.4 Understand and document error logger
2 wks
Dec 1 '98
 
100%
1.4.5 Develop Dependency Tool 
2 wks
Nov 2 '98
 
100%
1.4.6 Include and integrate package list
0 wks
Oct 1 '98
 
100%
1.5 ups/upd
25.8 wks
Sep 28 '98 JPP[0.2]
80%
1.5.1 Finish upd regression tests
12 wks
Sep 28 '98
 
50%
1.5.2 Document upd and kits
12 wks
Sep 28 '98
 
100%
1.5.3 cdf and d0 distribution scripts
12 wks
Jan 1 '99
 
80%
1.6 Purify
0 wks
Nov 2 '98 JPP[0.05]
100%
1.6.1 Package for KITS
0 wks
Nov 2 '98
 
100%
1.7 NOGO - Insure++
0 wks
Feb 1 '99
 
100%
1.7.1 Get latest version and determine utility
0 wks
Feb 1 '99
 
100%
1.8 Graphical Designer
9.8 wks
Feb 1 '99 JPP[0.3]
10%
1.8.1 GdPro V3.0 testing and deployment
6 wks
Feb 1 '99
 
10%
1.8.2 Add value for reporting
6 wks
Feb 26 '99
 
0%
1.9 Rational Rose - if requested
0.2 wks
Jan 1 '98
 
0%
1.10 Java Support - if requested
13.4 wks
Mar 1 '99
 
80%
1.10.1 Evaluate what versions and Java toolkits to support
4.8 wks
Mar 1 '99
 
80%
1.10.2 Package Java Development Kits and put in Kits
8.8 wks
Apr 1 '99
 
80%
1.10.3 Java debuggers - understand and support
0 wks
May 3 '99
 
0%
1.11 Corba Support - if requested
9 wks
Apr 12 '99
 
30%
1.11.1 Decide which versions of Corba to put in kits
0.2 wks
Apr 12 '99
 
30%
1.11.2 Put Corba in kits
0.2 wks
Jun 11 '99
 
30%

Resource_Table1


 
Name
Available FTEs Max # of FTEs Needed
JPP
2
2.3