3.
Desulfurization Technology
Introduction
The availability of technologies for producing ultra-low-sulfur diesel
fuel (ULSD) was one of the issues raised by the House Committee on Science.
First, do adequate and cost-effective technologies exist to meet the ULSD
standard? Second, are technologies being developed that could reduce the
costs in the future? Last, is it likely that the needed technologies can
be deployed into the market in time to meet the ULSD requirements of the
rule?
A review of the technologies reveals that current technologies can be modified
to produce diesel with less than 10 parts per million (ppm) sulfur. A small
number of refineries currently produce diesel with sulfur in the 10 ppm
range on a limited basis. The existence of the requisite technology does
not ensure, however, that all refineries will have that technology in place
in time to meet the new ULSD standards. Widespread production of ULSD will
require many refineries to invest in major revamps or construction of new
units. In addition to the status of desulfurization technologies, this
chapter discusses possible impediments to their deployment.
Refineries in the United States are characterized by a wide range of size,
complexity, and quality of crude oil inputs. Upgrades at a given refinery
depend on individual circumstances, including the refinerys existing configuration,
its inputs, its access to capital, and its perception of the market. The
sulfur in petroleum products comes from the crude oil processed by the
refinery. Refiners can reduce the sulfur content of their diesel fuel to
a limited extent by switching to crude oil containing less sulfur; however,
sulfur reduction from a switch in crude oil would fall well short of the
new ULSD standard. Refineries will require substantial equipment upgrades
to produce diesel with such limited sulfur.
In order to allow for some margin of error and product contamination in
the distribution system, refineries will be required to produce highway
diesel with sulfur somewhat below 15 ppm. Due to limited experience with
such low-sulfur products, the exact sulfur level that will be required
by refineries is not certain. In the Regulatory Impact Analysis for the
ULSD Rule, the EPA assumed highway diesel production with an average of 7 ppm. Whether production is at 10 ppm or 7 ppm, the same technology would
be used. In general, a relatively lower sulfur content would be achieved
with more severe operating conditions at a higher cost.
Considerable development in reactor design and catalyst improvement has
already been made to achieve ULSD levels near or below 10 ppm. In some
cases low sulfur levels are the consequence of refiners efforts to meet
other specifications, such as low aromatic levels required in Sweden and
California. In other cases refiners have decided to produce a premium
low-sulfur diesel product, as in the United Kingdom, Germany, and California.
These experiences, though limited, provide evidence for both the feasibility
of and potential difficulties in producing ULSD on a widespread basis.
Refineries currently producing ULSD in limited quantities rely on enhanced
hydrotreating technology. Technology vendors expect that this will also
be the case for widespread production of ULSD. The following section focuses
on hydrotreating as the primary means to achieve ULSD levels. A few emerging
and unconventional desulfurization technologies are also discussed, which
if proven cost-effective eventually may expand refiners options for producing
ULSD.
ULSD Production Technologies
Very-low-sulfur diesel products have been available commercially in some
European countries and in California on a limited basis. Sweden was the
first to impose very strict quality specifications for diesel fuel, requiring
a minimum 50 cetane, a maximum of 10 ppm on sulfur content, and a maximum
5 percent on aromatics content. To meet these specifications the refinery
at Scanraff, Sweden, installed a hydrotreating facility based on SynTechnology.48 The Scanraff hydrotreating unit consists of an integrated two-stage reactor
system with an interstage high-pressure gas stripper. The unit processes
a light gas oil (LGO) to produce a diesel product with less than 1 ppm
sulfur and 2.4 percent aromatics by volume. It is important to note that
the Scanraff plant is highly selective of its feedstock to achieve the
ultra-low sulfur content which may not be generalized to most U.S. refineries.
In addition to Sweden, other European countries are encouraging the early
introduction of very-low-sulfur diesel fuel ahead of the shift to a European
requirement for 50 ppm diesel in 2005. The United Kingdom and Germany have
structured tax incentives for the early introduction of 50 ppm diesel fuel
and have discussed incentives for introduction of a 10 ppm diesel fuel.
An example of a European refinery capable of producing diesel fuel for
these markets, is BPs refinery at Grangemouth, United Kingdom, which has
a 35,000-barrel-per-stream-day unit originally designed for 500 ppm sulfur
in 1995.49 The hydrotreater at Grangemouth has a two-bed reactor, no quench,
and operates at about 950 pounds per square inch gauge (psig). Operating
at a space velocity of 1.5 and using a new higher activity AK30 Nobel catalyst
(KF757), the unit is producing 10 to 20 ppm sulfur diesel product. The
feed is primary LGO with a sulfur content of about 1,800 ppm, derived from
a low-sulfur crude. BP reported that on several occasions the feed had
included a small fraction of cycle oil, which resulted in a noticeable
increase in catalyst deactivation rate.
In 1999 Arco announced that it would produce a premium diesel fuel which
Arco termed EC Dieselat its Carson, California, refinery.50 EC Diesel
is a super clean diesel designed to meet the needs of fleets and buses
in urban areas. The reported quality attributes include less than 10 ppm
sulfur, less than 10 percent aromatics, and 60 cetane, among others.51 Arco indicated that the crude slates of the Carson refinery would remain
unchanged, with only the operating conditions modified. The refinery had
to selectively take out a sulfurous, aromatic cycle oil feed stream to
the diesel unit and repeat this every few days for batches. If continuous
production were required, a major capital investment would have to be made.
In April 2000, Equilon also announced that its Martinez refinery in Northern
California could provide ULSD for fleet use in that region of the State.52
The challenge of producing ULSD from feedstocks that are difficult to desulfurize
is well represented by the experience of Lyondell-Citgo Refining (LCR)
at its refinery in Houston, Texas. In 1997 the refinery moved to a diet
of 100 percent Venezuelan crude.53 The gravity of the crude oil was less
than 20 oAPI, and it was highly aromatic. To produce suitable quality low-sulfur
diesel product the refinery had revamped a hydrotreater to SynSat operation
in 1996 and then converted to SynShift in 1998. The revamped hydrotreater
has a capacity of 50,000 barrels per day and consists of a first-stage
reactor operating at 675 psig pressure, a high-pressure stripper, and a
second-stage reactor that uses a noble metal catalyst. The feed to the
unit is a blend of light cycle oil (LCO), coker distillate, and straight-run
distillate (approximately equal volumes) with 1.4 percent sulfur by weight,
70 percent aromatics, and a cetane number of 30. The product has about
40 percent aromatics, a cetane number of 38.5, and sulfur content less
than 140 ppm.
Citgo reported that the LCR hydrotreating unit was the largest reactor
of its type when installed in 1996 and that the volume of catalyst in the
unit, which had been 40,000 pounds in the old unit, had increased to 1.7
million pounds in the revamped unit. The diesel sulfur level produced in
the unit reportedly met the 15 ppm sulfur cap at initial conditions at
start of run, but as the desulfurization catalyst aged, the reactor temperature
had to be revised to achieve target sulfur levels. If the revamped unit
had to consistently meet a 15 ppm diesel sulfur limit, the cycle life could
be greatly reduced from current operation, causing frequent catalyst replacement
and more frequent shutdowns. Under the current mode of operation, the frequency
of catalyst changeout is managed by reducing the cracked stocks in the
feed to the unit. More frequent catalyst changeouts to meet a 15 ppm sulfur
cap reportedly could raise the cost of diesel production.54
Hydrotreating
Conventional hydrotreating is a commercially proven refining process that
passes a mixture of heated feedstock and hydrogen through a catalyst-laden
reactor to remove sulfur and other undesirable impurities. Hydrotreating
separates sulfur from hydrocarbon molecules; some developing technologies
remove the molecules that contain sulfur (see discussion on "Developing
Technologies and Ultra-Low-Sulfur Alternatives"). Refineries
can desulfurize distillate streams at many places in a refinery by hydrotreating
straight-run streams directly following crude distillation, hydrotreating
streams coming out of the fluid catalytic cracking (FCC) unit, and/or hydrotreating
the heavier streams that go through a hydrocracker. Over half of the streams
currently going into highway-grade diesel (500 ppm) are made up from straight-run
distillate streams, which are the easiest and least expensive to treat.
Refineries with hydrotreaters are likely to achieve production of ULSD
on straight runs by modifying catalysts and operating conditions. Desulfurizing
the remainder of the distillate streams is expected to pose the greatest
challenge, requiring either substantial revamps to equipment or construction
of new units. In some refineries the heavier and less valuable streams,
such as LCOs, are run through a hydrocracker. The distillates from the
cracked stocks contain a larger concentration of compounds with aromatic
rings, making sulfur removal more difficult. The need for some refineries
to desulfurize the cracked stocks in addition to the straight-run streams
may play a key role in the choice of technology.
When the 15 ppm ULSD specification takes effect in June 2006, refiners
will have to desulfurize essentially all diesel blending components, especially
cracked stocks, to provide for highway uses. It is generally believed that
a two-stage deep desulfurization process will be required by most, if not
all refiners, to achieve a diesel product with less than 10 ppm sulfur.
The following discussion reviews a composite of the technological approaches
of UOP, Criterion Catalyst, Haldor Topsoe, and MAKFining (a consortium effort
of Mobil, Akzo Nobel, Kellogg Brown & Root, and TotalFinaElf Research).
A design consistent with recent technology papers would include a first
stage that reduces the sulfur content to around 250 ppm or lower and a
second stage that completes the reduction to less than 10 ppm. In some
cases the first stage could be a conventional hydrotreating unit with moderate
adjustments to the operation parameters. Recent advances in higher activity
catalysts also help in achieving a higher sulfur removal rate.55 The second stage would require substantial modification of the desulfurization process,
primarily through using higher pressure, increasing hydrogen rate and purity,
reducing space velocity, and choice of catalyst. To deep desulfurize cracked
stocks, a higher reactor pressure is necessary. Pressure requirements would
depend on the quality of the crude oil and the setup of the individual
refinery.
The level of pressure required for deep desulfurization is a key uncertainty
in assessing the cost and availability of the technology. In its 2000 study, U.S. Petroleum Refining: Assuring the Adequacy and Affordability of Cleaner Fuels, the
National Petroleum Council (NPC) suggested that in order to produce diesel
at less than 30 ppm sulfur, new high-pressure hydrotreaters would be required,
operating at pressures between 1,100 and 1,200 psig.56 Pressures over 1,000
psig are expected to require thick-walled reactors, which are produced
by only a few suppliers (see discussion later in this chapter) and take
longer to produce than reactors with thinner walls. In contrast to NPCs
expectations, EPAs cost analysis reflected vendor information for revamps
of 650 psig and 900 psig units that would not require thick-walled reactors.
The vendors indicated that an existing hydrotreating unit could be retrofitted
with a number of different vessels, including: a reactor, a hydrogen compressor,
a recycle scrubber, an interstage stripper, and other associated process
hardware.57
The amount of hydrogen required for desulfurization is also uncertain,
because the industry has no experience with widespread desulfurization
at ultra-low levels. One of the primary determinants of cost is hydrogen
consumption and the related investment in hydrogen-producing equipment.
Hydrogen consumption is the largest operating cost in hydrotreating diesel,
and minimizing hydrogen use is a key objective in hydrotreating for sulfur
removal. In general, 10 ppm sulfur diesel would require 25 to 45 percent
more hydrogen consumption than would 500 ppm diesel, in addition to improved
catalysts.58 Hydrogen requirements at lower sulfur levels rise in a nonlinear
fashion.
In addition to improvements in design and catalysts, other modifications
to refinery operations can contribute to the production of ULSD. For example,
high-sulfur compounds in both straight runs and cracked stocks lie predominantly
in the higher boiling range of the materials. Thus, reducing the final
boiling point for the streams and cutting off the heaviest boiling segment
can reduce the difficulty of the desulfurization task. If a refiner has
hydrocracking capability, the hydrocracker would be an ideal disposition
for these streams. Some refiners making both high- and low-sulfur distillate
products may be able to allocate the more difficult distillate blend streams
to the high-sulfur product; however, the EPA is in the process of promulgating
Tier 3 non-road engine emission limits around 2005 or 2006, which are expected to be linked to
sulfur reduction for non-road diesel fuel.59
A processing scheme that has been promoted primarily in Asia and Europe
employs a combination of partial hydrocracking and FCC to produce very-low-sulfur
fuels. In this scheme a partial conversion hydrocracking unit is placed
in front of the FCC unit to convert the vacuum gas oil to light products
(distillate, kerosene, naphtha, and lighter) and FCC feed. The distillate
product is low in sulfur (less than 200 ppm) and has a cetane number of
about 50. The cracked stocks produced in the FCC unit are also lower in
sulfur and higher in cetane. The relatively greater demand for distillate
relative to gasoline demand in Europe and Asia and the higher diesel cetane
requirement are more in keeping with the strengths of this process option
than is the case for most U.S. refineries.
A few new technologies that may reduce the cost of diesel desulfurizationsulfur
adsorption, biodesulfurization, and sulfur oxidationare in the experimental
stages of development (see discussion on "Developing
Technologies and Ultra-Low-Sulfur Aternatives"). Although they are being spurred
by the EPA rule, they are unlikely to have significant effects on ULSD
production in 2006; however, they may affect the market by 2010. In addition,
methods have been developed to produce diesel fuel from natural gas and
organic fats, but they still are costly.
NEMS Approach to Diesel Desulfurization Technology
The Petroleum Market Module (PMM) in the National Energy Modeling System
(NEMS)60 projects petroleum product prices, refining activities, and movements
of petroleum into the United States and among domestic regions. In addition,
the PMM estimates capacity expansion and fuel consumption in the refining
industry. The PMM is also revised on a regular basis to incorporate current
regulations that may affect the domestic petroleum market.
The PMM optimizes the operation of petroleum refineries in the United States,
including the supply and transportation of crude oil to refineries, the
regional processing of these raw materials into petroleum products, and
the distribution of petroleum products to meet regional demands. The production
of natural gas liquids from gas processing plants is also represented.
The essential outputs of the model are product prices, a petroleum supply/demand
balance, demands for refinery fuel use, and capacity expansion.
The PMM employs a modified two-stage distillate deep desulfurization process
based on proven technologies.61 The first stage consists of a choice of
two distinct units, which accept feedstocks of various sulfur contents
and desulfurize to a range of 20 to 30 ppm (Table
2). The
second stage also includes a choice of two processing units, which further
deep desulfurize the first-stage streams to a level below 10 ppm. The purpose
of reducing the sulfur level to 20 to 30 ppm in the first stage, rather
than the common goal of 250 ppm or less, is to enable a more accurate representation
of costs for processing streams.
The PMM retains the option of conventional distillate desulfurization when
500 ppm sulfur diesel can still be produced (before June 2010). Because
the PMM models an aggregation of refinery capacities in each of the refinery
regions,62 the above representation of multiple processing options is possible,
although in reality individual refineries may choose one process over the
other on the basis of strategic and economic evaluations.
Individual Refinery Analysis Approach to Diesel Desulfurization Technology
To assess the supply situation during the transition to ULSD in 2006, industry-level
cost curves were constructed for this study and matched against assumed
demand and imports. The cost curves are the result of a refinery-by-refinery
analysis of investment requirements and operating costs for refineries
in Petroleum Administration for Defense Districts (PADDs) I through
IV. The ULSD production costs were estimated for different groups of refineries
based on their size, the sulfur content of the feeds, the fraction of cracked
stocks in the feed, the boiling range of the feed, and the fraction of
highway diesel produced. The capital and operating costs for the different
groups were developed for EIA by the staff of the National Energy Technology
Laboratory (NETL).
For the study, a semi-empirical model was developed to size and cost new
and retrofitted distillate hydrotreating plants for production of ULSD.
Sulfur removal was predicted using a kinetic model tuned to match the limited
literature data available on deep distillate desulfurization. Correlations
were used in the model to relate hydrogen consumption, utility usage, etc.,
to the three major constituents of the distillate pool: straight-run distillate,
cat-cracker light cycle oil, and coker gas oil. (See Appendix D for a discussion
of the assumptions used to construct the model.)
Capital costs ranged from $592 to $1,807 per barrel per day, depending
on the size of the unit, whether it was new or retrofitted, and the percentage
of straight run feedstock (Table 3). A large hydrotreater using only straight-run
distillate derived from high-sulfur crude had the least cost for both new
and retrofitted units. The most expensive units were small hydrotreaters
running 32 percent cracked stocked, about the average proportion of cracked
feedstocks in PADD II.
Expected Developments and Cost Improvements
Recent experience indicates that consistent, high-volume production of
ULSD is a technologically feasible goal, although many refineries could
face major retrofits or new unit construction. The variation in feedstock
concerning both sulfur content and the amount of cracked stock may be influential
in the choice of process option and the cost of desulfurization, which
may also entail a different allocation of streams to products. Although
unconventional desulfurization technologies have been promoted recently
by various vendors, none has made sufficient progress toward the commercial
stage to warrant consideration by most refiners who must start producing
ULSD by June 2006.63
The two-stage desulfurization process can be accomplished through revamping
existing units, building new units, or a combination of both. Several aspects
of unit design are important. Properly designed distribution trays can
greatly improve desulfurization efficiency, in that catalyst bypassing
can make it virtually impossible to produce ULSD. Because hydrogen sulfide
(H2S) inhibits hydrodesulfurization reactions, scrubbing of recycle gas
to remove H2S will improve desulfurization. New design or revamps will
also include gas quench to help control temperature through the reactor.
In the design of a two-stage system, there will be a hot stripper between
the two reactors where ammonia and H2S are stripped from the first-stage
product.
As more commercial evidence and cost information become available for diesel
desulfurization in the next few years, it will be possible to better assess
the technology choicesincluding equipment requirements, operating conditions,
and production logisticsthat most refiners will have to make in order
to meet the new ULSD standards. However, the EPAs tight compliance timetable
for producing ULSD might short-circuit the learning process for refiners
to acquire necessary experience to make cost-effective decisions.64 The many caveats within current vendors statements must be carefully scrutinized,
to avoid overestimating the capability or underestimating the costs for
new or revamped distillate hydrotreating facilities. Most vendors state
that their goal is to use or revamp a client refiners current process
units whenever possible. In trying to reach a 10 ppm or lower sulfur target,
however, many units may be unsuitable or require major capital outlays.
Uncertainty about the level of revamp is a major source of uncertainty
in estimating the cost of the ULSD Rule.
Further consolidation of the refinery industry may achieve better economies
of scale, although some industry analysts have expressed concern that a
shortage of diesel supply could materialize in the short term if some economically
challenged refineries exit the diesel market. Catalyst improvements are
expected to be one of the main factors in reducing operating costs, both
in terms of recycle rate and efficient use of hydrogen. Other factors,
such as the dependence of the refinery on distillates, access to lower-sulfur
crude, level of competition, and ability to upgrade infrastructure, must
also be taken into account. The European experience could also provide
valuable insights for U.S. refineries.
Deployment of Desulfurization Technologies
The deployment of diesel desulfurization technologies will hinge on several
factors, such as the ability and willingness of refiners to invest, the
timing of investment and permitting, the ability of manufacturers to provide
units for all U.S. refineries at once, and the availability of engineering
and construction resources.
One impediment to acquiring desulfurization upgrades may be the willingness
and ability of individual refiners to obtain capital. The EPA estimates
that average investment for diesel desulfurization will cost $50 million
per refinery, slightly more than the estimated $44 million per refinery
required to meet the Tier 2 gasoline sulfur requirement. Most refiners
will invest in the gasoline sulfur upgrade because gasoline is their major
product. Because U.S. refineries typically produce three to four times
as much gasoline as highway diesel fuel, the per gallon investment cost
of ULSD will be three to four times as high.65
In its Regulatory Impact Analysis, the EPA provided an analysis of capital
requirements indicating that the combined annual capital investment for
gasoline and diesel desulfurization would be $2.15 billion in 2004 and
$2.49 billion in 2005.66 The EPA analysis spread the diesel investments
over a 2-year period (to reflect a somewhat more sophisticated schedule
for the expenditure of capital throughout a project) and assumed that
the gasoline investments would be incurred in the year before a unit came
on line. The EPA concluded that this level of investment should be sustainable
by the industry because it is roughly two-thirds of the estimated environmental
investments incurred during 1992-1994, when the industry was responding
to the 500 ppm highway diesel and oxygenated and reformulated gasoline
requirements. Other estimates of ULSD investment costs range from $3 billion
to $13 billion (see Chapter 7).
Although not discussed in the EPAs investment analysis, the 1990s was
a period of rationalization for the refining industry, marked by refinery
sales, mergers, and closures. Between January 1990 and January 1999, 50
of 205 refineries were closed (4 of which were merged wth adjacent refineries).67 The NPC attributes the refinery closures to heightened competitiveness.
Although the environmental requirements of the 1990s cannot be pointed
to as the cause of the closures, they contributed to the inability of some
refineries to compete economically. Refiners who chose not to invest in
the 500 ppm sulfur limit (required for highway diesel since 1993) found
it more economical to shift their existing high-sulfur diesel production
to non-road markets.
Some refiners will be more able than others to obtain capital for Tier
2 gasoline and ULSD projects. Assuming that capital is accessible, a refiners
willingness to invest in ULSD projects will depend on its assessment of
the economics of the market. For instance, a refiner would be less likely
to invest if it believed it could not compete favorably with others because
the investments would result in a higher cost per gallon. History may lead
some refiners to be cautious about investment. In the 1990s refinery upgrades
for meeting reformulated gasoline requirements resulted in excess gasoline
production capacity. As a result, gasoline margins were depressed, making
it difficult for refiners to recoup investments.
Profit margins for ULSD could be depressed if refiners build too much capacity,
and the fear of overinvestment could lead some refiners to delay investment
until more highway diesel production is required. On the other hand, refiners
anticipating inadequate supply of ULSD may choose to invest as early as
possible to benefit temporarily from higher margins and sell credits to
those that do not invest early. The EPA believes that any lack of investment
will be compensated for by the temporary compliance options and credit
trading provisions of the ULSD Rule.
Another possible hurdle to the timely adoption of desulfurization technologies
is the ability of the engineering and construction industries to design
and build diesel hydrotreaters in a timely manner. In addition to providing
diesel hydrotreaters, the same contractors will be providing gasoline desulfurization
units for the Tier 2 gasoline sulfur reduction requirements that will be
phased in between 2004 and 2007. Moreover, engineering and construction
requirements will also be expanding outside the United States. The Canadian
government has committed to harmonizing gasoline and diesel requirements
with the United States. In Europe, refiners will be making upgrades to
meet tighter gasoline and diesel requirements in 2005 and have may incentives
to produce even cleaner fuels for markets in Germany and the United Kingdom (see discussion in Chapter 6).
In its 2000 study, the NPC provided an analysis of the number of construction
projects required for U.S. refiners to provide both gasoline and diesel
fuel meeting a 30 ppm sulfur cap. The analysis concluded that if a diesel
sulfur reduction is required for 2006, implementation would overlap significantly
with the Tier 2 Rule gasoline sulfur reduction, and engineering and construction
resources will likely be inadequate, resulting in higher costs, implementation
delays, and failure to meet the regulatory timelines. The study also concluded
that if a 15 ppm diesel standard is required, further investments in new
units will be required and there will be a significant risk of inadequate
diesel supplies.
The NPC estimated that 89 refineries will require gasoline hydrodesulfurization
units by 2004 and that 89 refineries (presumably the same ones) would make
upgrades for new highway diesel standards and concluded that if the diesel
standard were required within 12 months of completion of Tier 2 gasoline
projects, construction labor shortages could occur. The analysis provided
peak monthly engineering and construction personnel requirements for five
scenarios with different assumptions about the timing and overlap of Tier
2 gasoline and ULSD requirements (Table 4). The scenarios ranged from a
balanced implementation case, in which one-fourth of the required projects
would begin in each quarter of the first year (Scenario A), to highly front-end
loaded cases (Scenarios D and E), in which three-fourths of the projects
would begin in the first quarter of the first year. Scenarios B and C assumed
that refiners would start projects as late as possible.
In the Regulatory Impact Analysis for the ULSD Rule, the EPA conducted
its own analysis of the personnel requirements for design and construction
services related to the overlapping requirements of the Tier 2 gasoline
and ULSD requirements. The analysis provided monthly estimates for each
personnel category, assuming that in a given year 25 percent of the projects
would be completed per quarter. The monthly estimates were used to develop
estimates of the maximum number of personnel required in any given month
for the Tier 2 gasoline program alone and for the gasoline and ULSD programs
together, both with and without a temporary compliance option. The estimates
of the two programs taken together without the temporary compliance option
were about double the employment estimates for the Tier 2 gasoline program
only, in all three job categories. When the temporary compliance option
is taken into account, personnel requirements for the two programs are
only about 30 percent higher than for the Tier 2 gasoline program alone.
Because the largest impact is expected to occur in front-end design, where
30 percent of available U.S. personnel are required, the EPA believes that
the engineering and construction workforce can provide the equipment necessary
for compliance. It appears that the EPAs criterion for the adequacy of
engineering and construction personnel lies somewhere between 30 percent
and 50 percent over the personnel requirements of the Tier 2 requirements
alone.
The EPAs estimates without a temporary compliance option are most consistent
with the timing assumptions of NPCs Scenario A. EPAs analysis indicates
that engineering and construction requirements will be lower given the
temporary compliance option of the ULSD Rule; however, NPC Scenarios D
and E demonstrate that different assumptions about project timing lead
to very different estimates for personnel. The range of personnel estimates shown
in Table 4 highlights the uncertainty of the estimates.
The EPAs analysis assumed that a total of 97 units would be added to make
Tier 2 gasoline and that 121 diesel desulfurization units would be added
for ULSD (Table 5). The expected startup dates for the gasoline and diesel
desulfurization units indicate an overlap of 26 gasoline units and 63 diesel
units in 2006. The 2006 overlap in gasoline and diesel startups is noteworthy
because it is significantly greater than it would have been with ULSD implementation
in any other year except 2004.
Another possible hurdle to implementing technology for the ULSD Rule raised
by the NPC is the ability of manufacturers to provide critical equipment.
As mentioned earlier, the NPC analysis assumed that a sulfur requirement
below 30 ppm would require new deep hydrotreaters with reactor pressures
in the range of 1,100 to 1,200 psig, requiring thick-walled reactors. As
compared with other reactors, the delivery time for thick-walled reactors
is longer and the number of suppliers is more limited. Only one or two
U.S. companies produce thick-walled reactors, whereas four to six can supply
reactors with more typical wall widths. Outside the United States, 10 to
12 companies are able to supply reactors regardless of wall width. This view is at odds with the EPA analysis,
which was based on vendor estimates, with reactor pressures in the range
of 650 to 900 psig.
Another type of critical equipment identified by the NPC is reciprocating
compressors. The NPC indicated that two reciprocating compressors will
be required for each diesel desulfurization project. Reciprocating compressors
will also be required for gasoline desulfurization projects, and the NPC
listed them as the principal constraining factor for the gasoline projects.
Excluding the former Soviet Union, there are only five manufacturers of
reciprocating compressors in the world. Two are in Europe and were assumed
to be occupied with orders for European gasoline sulfur reduction projects
through 2003. The NPC analysis did not account for additional orders from
Canadian desulfurization projects.
Conclusion
Technology for reduction of sulfur in diesel fuel to 15 ppm is currently
available and new technologies are under development that could reduce
the cost of desulfurization. Variations in feedstock sulfur content and
the amount of cracked stock may be very influential in the choice of process
option and cost of desulfurization. Estimates of investment costs related
to ULSD production range from $3 billion to $13 billion. The ability and
willingness of refiners to invest depends on an assessment of market economics.
Experience with upgrades to meet reformulated gasoline requirements in
the early 1990s may lead some refiners to be cautious. The availability
of personnel, thick-walled reactors, and reciprocating compressors may delay
some construction.
Notes |