This is the accessible text file for GAO report number GAO-03-1011 
entitled 'Budget Issues: Alternative Approaches to Finance Federal 
Capital' which was released on August 21, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

On January 13, 2004, this document was revised to add various footnote 
references missing in the text of the body of the document, and to 
enhance the formatting of Table 1 and Appendices II through X.

Report to the Chairman, Committee on the Budget, U.S. Senate:

August 2003:

BUDGET ISSUES:

Alternative Approaches to Finance Federal Capital:

GAO-03-1011:

GAO Highlights:

Highlights of GAO-03-1011, a report to Chairman, Committee on the 
Budget, U.S. Senate

Why GAO Did This Study:

In an era of limited resources and growing mission demands, many 
agencies have turned to approaches other than full up-front funding to 
finance capital. GAO was asked to inventory examples of alternative 
approaches that agencies have employed to finance the capital used in 
their operations.

What GAO Found:

Capital projects are fully funded when Congress provides budget 
authority for the full cost of an asset up front. Such up-front 
funding provides recognition for commitments that are embodied in 
budgetary decisions and maintains governmentwide fiscal control. 
However, providing budget authority for the large up-front costs of 
capital assets creates challenges in an era of resource constraints. 
Agencies have been authorized to use an array of approaches to obtain 
capital assets without full, up-front budget authority. Our work 
identified 10 alternative financing approaches used by one or more of 
13 agencies. These approaches, which are described in our letter, 
are: 

* incremental funding,
* operating leases,
* retained fees,
* real property swaps, 
* sale-leasebacks,
* lease-leasebacks,
* public private partnerships,
* outleases,
* share-in-savings contracts, and
* debt issuance.

From an agency’s perspective, meeting capital needs through 
alternative financing approaches (i.e., not full funding) can be very 
attractive because the agency can obtain the capital asset without 
first having to secure sufficient appropriations to cover the full 
cost of the asset. Depending on the financing approach, an agency may 
spread the asset cost over a number of years or may never even incur a 
monetary cost that is recognized in the budget. From a governmentwide 
perspective, however, as we have reported in the past, the costs 
associated with these financing approaches may be greater than with 
full, up-front budget authority. Regardless of the financing approach—
up-front budget authority or any of the other approaches—agencies 
would receive the same program benefits.

This document summarizes how these approaches are typically structured 
as well as examples of projects financed through these approaches. It 
notes the claimed project benefits from an agency’s perspective and 
some questions associated with each.

www.gao.gov/cgi-bin/getrpt?GAO-03-1011.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Susan J. Irving, 
(202) 512-9142, irvings@gao.gov.

[End of section]

Contents:

Letter:

Appendixes:

Appendix I: Full Funding: 

Appendix II: Incremental Funding:

Appendix III: Operating Leases:

Appendix IV: Retained Fees:

Appendix V: Real Property Swaps:

Appendix VI: Sale-Leaseback: 

Appendix VII: Lease-Leaseback: 

Appendix VIII: Public Private Partnerships: 

Appendix IX: Outleases: 

Appendix X: Share-In-Savings Contracts: 

Appendix XI: Debt Issuance: 

Table: 

Table 1: Alternative Financing Approaches:

Letter August 21, 2003:

The Honorable Don Nickles 
Chairman 
Committee on the Budget 
United States Senate:

Dear Mr. Chairman:

In your March 11, 2003 letter you asked us to report on approaches 
federal agencies have employed to finance capital projects. On June 25, 
2003, we briefed Committee staff on the preliminary results of our 
work. As agreed with your office, this letter summarizes and transmits 
the information provided in that briefing.:

For purposes of this work, capital projects include land, improvement 
projects, and buildings or equipment used in federal operations. It 
excludes investments in high technology assets, such as information 
technology, and assets owned by state and local governments, such as 
highways. We identified alternative financing approaches based on both 
prior GAO work and more current research. Specifically, we queried 
analysts throughout GAO about alternative approaches they had found 
during the course of their work. In addition, we did web-based research 
on publications issued by the Congressional Research Service (CRS), 
Congressional Budget Office (CBO), General Services Administration 
(GSA), and professional research organizations such as RAND. To a very 
limited extent, we obtained clarification on specific examples from 
knowledgeable federal officials. While this work was not intended to 
result in a comprehensive list of all capital financing approaches, we 
believe we identified the major approaches used. For each approach we 
identified, we provide a brief description, examples of how it has been 
used, and the project's benefits from an agency's perspective. We did 
not independently verify the accuracy of this information. Moreover, 
the nature of our review did not result in the identification of 
additional financing costs incurred by the government as a whole due to 
the use of an approach other than full, up-front budget authority. 
Indepth reviews of individual contracts would be necessary to identify 
such costs. Our work was done in Washington, D.C., from November 2002 
through June 2003, in accordance with generally accepted government 
auditing standards.

Capital assets usually cost large amounts of money. In fiscal year 2002 
alone, the federal government invested close to $100 billion in major 
physical capital used in its operations.[Footnote 1] The high cost of 
capital assets creates challenges for budgeting in an era of resource 
constraints.

The requirement that an agency have adequate budget authority before it 
enters into a contract or other obligation for payment was established 
over 100 years ago in the Adequacy of Appropriations Act, 41 U.S.C. § 
11, and the Antideficiency Act, 31 U.S.C. § 1341. The financing 
approach known as full funding has broader requirements than those 
found in these two acts and is enforced by policy rather than 
statute.[Footnote 2] We have advocated the financing approach known as 
full funding as the best way to ensure recognition of commitments 
embodied in budgetary decisions and to maintain governmentwide fiscal 
control. However, agencies have been authorized to use an array of 
approaches to obtain capital assets without full, up-front budget 
authority. In an era of limited resources and growing mission demands, 
many agencies have turned to these alternative approaches as a 
practical way to finance capital, even though over the long run they 
may result in a higher cost to the taxpayer.[Footnote 3]

Summary:

We identified 10 capital financing approaches that have been used by 
one or more of 13 federal agencies (see table 1). From an agency's 
perspective, meeting capital needs through alternative financing 
approaches (i.e., not full funding) can be very attractive because the 
agency can obtain the capital asset without first having to secure 
sufficient appropriations to cover the full cost of the asset. 
Depending on the financing approach, an agency may spread the asset 
cost over a number of years or may never even incur a monetary cost 
that is recognized in the budget. In other words, alternative financing 
approaches can make it easier for agencies to meet mission capital 
demands within the constraints of their appropriation. As we have 
reported in the past, however, from a governmentwide perspective the 
costs associated with these financing approaches may be greater than 
with full, up-front budget authority. Regardless of the financing 
approach used to obtain the capital, agencies would receive the same 
program benefits.

Table 1 below shows an array of approaches that agencies have used to 
finance capital.

Table 1: Alternative Financing Approaches:

Agency: GSA; 
Incremental funding: None; 
Operating lease: PTO building; DOT headquarters; 
Retained fees: Phillip Burton Conf. Center; 
Real property swaps: Albuquerque, NM, federal building and parking; L. 
Mendel Rivers Building; 
Sale-leaseback: Charleston, WV Federal Building; 
Lease-leaseback: None; 
Public private partnerships: Southeast Federal Center; El Paso border 
station; Ronald Reagan Building; Atlanta Food Court; 
Outlease: Tariff Bldg.; McCormack PO Courthouse; Galveston 
customhouse; RRB bldg.; Metcalfe Building; 
Share-in-savings: Energy savings performance contracts ($100s of 
millions in total); 
Debt issuance: None.

Agency: DOD; 
Incremental funding: CVN-21 Aircraft Carriers; Atlantic Intracoastal 
Waterway Bridge; 
Operating lease: USAF Mid-air Refueling Tankers; USAF Operational 
Support Aircraft; 
Retained fees: None; 
Real property swaps: Army Reserves facilities; LAAFB; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: Family housing on bases; Portsmouth 
Shipyard Prison (Navy); Army utilities privatization; 
Outlease: Ft. Sam Houston, Ft. Leonard Wood, Brooks AFB; NAVSEA field 
activities; 
Share-in-savings: None; 
Debt issuance: None.

Agency: VA; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: At least 27 enhanced-use leases; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: Interior; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: Recreation fee demonstration program (NPS, FWS, BLM); 
Real property swaps: Georgetown - Foxhall (proposed); 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: Ft. Mason Foundation; Thoreau Center/
Presidio; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: USDA; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: Recreation fee demonstration program (Forest Service); 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: TVA; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: Combustion turbines; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: Capital acquisitions.

Agency: Coast Guard; 
Incremental funding: Deepwater Program; CGC Alex Haley; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: Maine lights, Coast Guard stations; 
Share-in-savings: None; 
Debt issuance: None.

Agency: DOE; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: Oak Ridge National Laboratory; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: DOT; 
Incremental funding: Northern CA air traffic control system; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: USPS; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: New Brunswick, NJ Civic Square; Rincon 
Center; Grand Central Station; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: State; 
Incremental funding: USAID Annex (Kampala, Uganda); 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; 
Sale-leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: Smithsonian; 
Incremental funding: Castle; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; Sale- leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: None; 
Debt issuance: None.

Agency: Commerce; 
Incremental funding: None; 
Operating lease: None; 
Retained fees: None; 
Real property swaps: None; Sale- leaseback: None; 
Lease-leaseback: None; 
Public private partnerships: None; 
Outlease: None; 
Share-in-savings: HVAC upgrade; 
Debt issuance: None. 

Note: Italics and bold type indicate where details of specific projects 
are included in this document.

[End of table]

The 10 alternative financing approaches we identified are briefly 
described below. In parentheses, we have included a measure of the 
magnitude of the use of each approach based on our research. These must 
be interpreted cautiously, however, since our methodology would not 
identify every instance where alternative financing approaches were 
used.

Incremental funding (about 1/3 of about $92 billion provided for 
civilian capital projects funded through fiscal year 2000) - 
Incrementally funded projects are those for which budget authority is 
provided for only part of the estimated costs of a capital acquisition 
or for part of a usable asset.

Operating leases (about 5 percent of GSA's leases are for 20 years or 
longer) - An operating lease gives the federal government the use of an 
asset for a specified period of time, but the ownership of the asset 
remains with the lessor. The Office of Management and Budget (OMB) 
identifies six criteria (presented in the enclosed briefing) that a 
lease must meet to be considered an operating lease.

Retained fees (5 organizations) - In some cases, agencies have been 
authorized to finance capital projects and improvements with fees 
earned through business-type or market-oriented activities with the 
public.

Real property swaps (7 agreements) - A real property swap is an 
exchange of property owned by the federal government for another 
property owned by either a private entity or a state or local 
government.

Sale-leaseback (1 case) - Under a sale-leaseback agreement, a federal 
agency sells an asset and then leases back some or all of the asset 
from the purchaser.

Lease-leaseback (1 case) - A lease-leaseback agreement between a 
government agency and a private entity may consist of three stages: the 
government agency purchases an asset; the agency then leases out the 
same asset to a private entity for a fixed time period in return for a 
lump sum payment; finally the agency leases back the use of the same 
asset.

Public private partnerships (54 arrangements) - Public private 
partnerships tap the capital and expertise of the private sector to 
improve or redevelop federal real property assets. Ideally, the 
partnerships are designed so that each participant makes complementary 
contributions that offer benefits to all parties.

Outleases (36 cases) - Excess or underused properties are outleased to 
shift the cost of maintenance and restoration to the private sector 
lessee, thus relieving the federal government of these expenses.

Share-in-savings contracts (hundreds of millions of dollars) - Some 
federal agencies work with contractors who purchase and install new 
energy systems in federal buildings. Agencies then pay back the 
contractors over time for the equipment plus a percentage of the energy 
costs saved as a result of the more efficient energy systems and relief 
of in-house maintenance costs.

Debt issuance (1 agency) -A few federal organizations, such as the 
Tennessee Valley Authority, have authority to borrow from the public. 
This authority can be used to finance capital acquisitions.

Organization of Report:

The remainder of this report consists of sections on each of the above 
financing approaches. Each section begins with a brief description of 
the approach, followed by examples of specific projects financed by 
using the approach.

Additional Work To Be Done:

As agreed with your staff, we will further examine examples of some of 
these alternative approaches. A report on this follow-on work will be 
sent to you.


We will send copies of this letter to the Ranking member of the Senate 
Committee on the Budget, the Chair and Ranking Member of the House 
Committee on the Budget, and other committees as appropriate. Copies 
will be made available to others on request. In addition, the report 
will be available at no charge on the GAO Web site at [Hyperlink, 
http://www.gao.gov] http://www.gao.gov.

We appreciate the opportunity to be of assistance. If you or your staff 
have any questions regarding the briefing or this letter, please 
contact me at (202) 512-9142 [Hyperlink, irvings@gao.gov] or Christine 
Bonham, Assistant Director, at (202) 512-9576 [Hyperlink, 
bonhamc@gao.gov]. Other key contributors to this briefing were Carol 
Henn, Maria Edelstein, David Eisenstadt, and Dewi Djunaidy.

Sincerely yours,

Signed by:

Susan J. Irving 
Director, Federal Budget Analysis Strategic Issues:

[End of section]

Appendixes: 

Appendix I: Full Funding: 

A fully-funded capital project receives budget authority up front, 
before a commitment is made, for the project's full estimated cost or 
for a stand-alone stage if the project is divisible into stages and the 
result of that stage is a usable asset.[Footnote 4] We and others have 
advocated full funding for capital asset acquisition as the best way to 
ensure recognition of commitments embodied in budgetary decisions and 
maintain governmentwide fiscal control. The requirement that an agency 
have adequate budget authority before it enters into a contract or 
other obligation for payment was established over 100 years ago in the 
Adequacy of Appropriations Act, 41 U.S.C. § 11, and the Antideficiency 
Act, 31 U.S.C. § 1341. The financing approach known as full funding has 
broader requirements than those found in these two acts and is enforced 
by policy rather than statute.

Fully-funded projects can take the form of new construction, 
renovations, or purchases. New construction of federal buildings is 
generally done through the General Services Administration (GSA). Over 
the last 10 years, GSA's new construction program has focused on 
courthouses and border stations. Purchases typically are not used for 
facilities.

There are two types of leases for which up-front funding is now 
required: lease-purchases and capital leases. A lease-purchase is a 
lease in which the federal government contracts to make annual lease 
payments to a developer and to take ownership of the building at the 
end of the lease period. During the 1980s, Congress authorized agencies 
to enter into lease-purchase agreements in which the annual lease 
payments were recorded in the budget over the lease period. Because 
this is generally more costly to the government than outright purchase 
and because the government is obligated to take ownership of the 
building, the House and Senate Budget Committees, the Office of 
Management and Budget (OMB), and the Congressional Budget Office (CBO), 
in connection with the Omnibus Budget Reconciliation Act of 1990, 
changed the budget scoring rules so lease-purchase budget authority and 
obligations are now scored up front rather than on an annual basis.

Capital leases are those that do not meet the six criteria for an 
operating lease. (See operating leases.) Generally the present value of 
the minimum lease payments over the life of the lease exceeds 90 
percent of the fair market value of the asset at the beginning of the 
lease term. For capital leases, budget authority must be available for 
the net present value of the total cost of the lease before it can be 
signed. Agencies may be reluctant to use capital leases because of this 
scoring requirement.

[End of section]

Appendix II: Incremental Funding:

Incrementally funded projects are those for which budget authority is 
provided for only part of the estimated cost of a capital acquisition 
or part of a usable asset. It erodes future fiscal flexibility for 
programs because funding is needed to complete procurements begun in 
previous years. In addition, it limits cost visibility and 
accountability. However, incremental funding can be attractive to 
agencies that request a particular acquisition in an era of tight 
budgets when the full amount of funding needed may be difficult to 
obtain.

Distortions in the allocation of resources can result when the full 
costs of proposed commitments are not recognized at the time budget 
decisions are made. Incremental funding can be justified, however, for 
high technology capital projects because such projects are often closer 
in nature to research and development, where useful knowledge can be 
obtained even if no additional funding is provided. Space exploration 
equipment would be an example of such a project.

As we reported in February 2001, of the nearly $92 billion provided for 
civilian capital projects funded through fiscal year 2000, about $31 
billion was incrementally funded.[Footnote 5] At that point in time, at 
least $45 billion in additional funds would have been needed to 
complete these projects.

Following are a few examples of incrementally funded projects.

* Northern California Terminal Radar Approach Control facilities,: 

* Alex Haley Conversion Project-Phase II,

* Deepwater, and: 

* Navy CVN-21 Aircraft Carrier Program.

Northern California Terminal Radar Approach Control Facilities:

Financing approach: Incremental funding.

Capital project: Northern California Terminal Radar Approach Control 
facilities.

Department/agency: Federal Aviation Administration.

Description of project:

Terminal air traffic in northern California increased 89 percent from 
1982 to 1998 and is projected to further increase another 42 percent 
from 1998 to 2015. The infrastructure of the Federal Aviation 
Administration's (FAA) air traffic control system--Terminal Radar 
Approach Control (TRACON)--in the northern California area requires 
modernization and expansion to meet the increased traffic demands. For 
example, the Bay, Sacramento, and Stockton TRACONs are in aging 
buildings without sufficient space to grow or transition to modern 
equipment. The Northern California TRACON program constructed a 
facility in Sacramento to consolidate and integrate the approach 
control functions of four northern California TRACONs and some Oakland 
airspace. 

Description of financing approach:

From fiscal years 1996 through 2000, funds were appropriated for the 
consolidated facility. Specifically, funds were used for environmental 
and airspace impact studies, site adaptation, building design and 
construction, air traffic control equipment procurement and 
installation, and program management. However, an estimated $6.7 
million was needed to complete installation and implementation 
activities, program management, new building services, ancillary 
maintenance equipment, and the telecommunications network required to 
consolidate the four TRACON facilities. 

Benefits claimed:

FAA projects that the full northern California TRACON consolidation 
will reduce operation and maintenance costs for consolidated 
facilities, reduce locality pay, and lower costs associated with 
employee turnover. Other potential benefits include fuel and time 
savings resulting from efficient airspace management and route design.

Source: Federal Aviation Administration's FY 2001 President's Budget 
Submission.

Alex Haley Conversion Project-Phase II:

Financing approach: Incremental funding.

Capital project: Alex Haley Conversion Project-Phase II.

Department/agency: U.S. Coast Guard.

Description of project:

Coast Guard Cutter Alex Haley was recently converted to operate in the 
harsh Alaska/Bering Sea. Its primary mission is homeland security, 
search and rescue, and international domestic fisheries enforcement. 
Continuing improvements are being made for crew habitability, operation 
capability, and machinery and personal safety. For example, a 
helicopter hangar was installed to allow deployment of an HH-65 
helicopter. 

Description of financing approach:

The Coast Guard chose a contracting approach that depends on a 
sustained funding stream of over $500 million each year (in 1998 
dollars) for at least the next 20 years. Already, the funding provided 
for the project is less than the amount the Coast Guard had planned. 
The fiscal year 2002 and 2003 appropriations for the project were about 
$28 million and about $90 million below the planned levels, 
respectively. Further, the President's fiscal year 2004 budget request 
for the Coast Guard is not consistent with the Deepwater funding plan. 
If the requested amount of $500 million for fiscal year 2004 is 
appropriated, it would represent another shortfall of $83 million, 
making the cumulative shortfall about $202 million in the project's 
first 3 years. If appropriations hold steady at $500 million (in 
nominal dollars) through fiscal year 2008, the Coast Guard estimates 
that the cumulative shortfall will reach $626 million.[Footnote 6]

Benefits claimed:

By replacing its deepwater fleet through an integrated approach, the 
Coast Guard expects to improve the effectiveness of its operations and 
reduce operating costs. However, delays in the project, which have 
already occurred, could jeopardize the Coast Guard's future ability to 
effectively and efficiently carry out its mission.

Sources:

U.S. General Accounting Office, Coast Guard: Challenges during the 
Transition to the Department of Homeland Security, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO-03-594T] GAO-03-594T (Washington, D.C.: 
Apr. 1, 2003).

Coast Guard: Actions Needed to Mitigate Deepwater Project Risks, 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-01-659T] GAO-01-659T 
(Washington, D.C.: May 3, 2001).

Navy CVN-21 Aircraft Carrier Program:

Financing approach: Incremental funding.

Capital project: Navy CVN-21 Aircraft Carrier Program.

Department/agency: Department of Defense/Navy.

Description of project:

The Navy plans to procure the CVN-21 aircraft carrier in fiscal year 
2007 and commission it into service in 2014. The CVN-21 is an evolved 
version of the Nimitz-class design that will replace the Enterprise 
(CVN-65), which will then be 53 years old.

Description of financing approach:

For fiscal year 2004, the administration proposed continued advanced 
and incremental funding to procure and perform research and development 
work on the ship. The proposed funding for the CVN-21 would spread the 
appropriations over 8 fiscal years, presumably to ease the strain on 
any one year's budget.

Benefits claimed:

Compared to prior aircraft carriers, the CVN-21 would require 
significantly fewer sailors to operate and would feature an entirely 
new and less expensive nuclear reactor plant, a new electrical 
distribution system, and an electromagnetic (as opposed to steam-
powered) aircraft catapult system. In addition, the CVN-21 is projected 
to have lower life-cycle operation and support costs.

Source:

Congressional Research Service, Navy CVN-21 (Formerly CVNX) Aircraft 
Carrier Program: Background and Issues for Congress, RS20643 
(Washington, D.C.: Mar. 21, 2003).

[End of section]

Appendix III: Operating Leases:

An operating lease gives the federal government the use of an asset for 
a specified period of time, but the ownership of the asset does not 
change. The Office of Management and Budget (OMB) identifies six 
criteria that a lease must meet to be considered an operating lease.

* Ownership of the asset remains with the lessor and is not transferred 
to the government at or shortly after the lease.

* Lease does not contain a bargain-price purchase option.

* The lease term does not exceed 75 percent of the estimated economic 
life of the asset.

* The asset is a general-purpose asset and is not built to unique 
specifications of the government lessee.

* There is a private sector market for the asset.

* The present value of the lease payments does not exceed 90 percent of 
the fair market value.

* A lease not meeting any one of the six criteria is considered a 
capital lease.

Operating leases are generally intended to be used for assets that are 
needed for a specified period of time. For self-insuring entities like 
GSA, an operating lease requires that only 1 year's amount of budget 
authority be obtained annually to fund the lease. As the federal 
government's real property manager, GSA provides leased space for most 
agencies. GSA and we agree that ownership is more cost-effective than 
leasing if (1) GSA has a justifiable need for a property over a 20-year 
term, (2) the space requirement is large enough, and (3) the property 
is located in an appropriate market.

We have previously reported that the budget scoring rules have the 
effect of favoring operating leases and, given current budget 
constraints, there is a concern that capital assets are being obtained 
through operating leases rather than through the generally more cost-
effective ownership option. In 2001,we reported on 12 GSA lease 
projects in which the lease term was 
affected by budget scoring.[Footnote 7] While in the short run 
operating leases may appear less costly than ownership options such as 
construction or purchase, for long-term needs construction is generally 
less expensive than leasing. We have previously reported that one 
option to improve scorekeeping would be to treat operating leases that 
are used for long-term needs on the same basis as purchases or 
construction in the budget. This change would require an increase in 
available budget authority.

Following are examples of operating leases used for long-term needs:

* Patent and Trademark Office building in Washington, D.C.,

* Department of Transportation headquarters in Washington, D.C. ,

* Air Force lease of 737 Operational Support Aircraft, and:

* Air Force lease of Boeing 767 tankers.

Patent and Trademark Office (PTO) Lease in Washington, D.C.

Financing approach: Operating lease.

Capital project: Patent and Trademark Office (PTO) lease in 
Washington, D.C.

Department/agency: General Services Administration (GSA).


Description of project:

In 1989, the Patent and Trademark Office (PTO) began working with GSA 
on approaches to meet its long-term space requirements. In August 1995, 
OMB authorized GSA to seek congressional approval to consolidate PTO 
operations at a single location in new leased space. That same year, 
the appropriate Senate and House committees approved the prospectus for 
the lease. The committees authorized the competitive procurement of a 
20-year operating lease for about 2 million square feet for the purpose 
of consolidating PTO.

On June 1, 2000, GSA signed a 20-year lease for approximately 2.2 
million rentable square feet, which were to be built to suit GSA/PTO 
needs and to house 7,100 staff in Alexandria, Virginia. The lease was 
valued at $1.24 billion over 20 years, plus operating expenses and 
taxes. PTO plans to begin moving into the new building in late 2003.

Description of financing approach:

GSA entered into a 20-year operating lease that only required the 
annual payments to be scored in each year of the lease. Thus PTO's 
yearly rent of $62 million would need to be appropriated for each of 
the 20 years as an operating lease.

Benefits claimed:

GSA will be able to consolidate and collocate PTO staff that had 
previously been located in 18 different buildings under 33 different 
leases.

Budgetary observations:

Had the PTO lease been considered a capital lease, the net present 
value of the $1.2 billion in total lease costs would have needed to be 
appropriated to GSA in fiscal year 2003. The Federal Buildings Fund 
would not have been able to absorb the cost of this construction 
project without additional appropriations. We reported that while 
construction would have been an estimated $48 million less costly than 
leasing space for PTO, the award of the PTO lease as an operating lease 
was in accordance with OMB's scoring criteria. We also reported that 
construction was not a viable alternative at the time GSA made the 
decision for the PTO facility because funds were not available to 
provide for government ownership. A PTO official stated that the 
administration and PTO's appropriation committees agreed that a 
competitive lease was the only viable option because neither user fees 
nor taxpayer funding were available to construct or purchase a new PTO 
facility.

Source:

U.S. General Accounting Office, Acquisition of Leased Space for the 
U.S. Patent and Trademark Office, [Hyperlink, http://www.gao.gov/cgi-
bin/getrpt?GAO-01-578R] GAO-01-578R (Washington, D.C.: June 5, 2001).

Department of Transportation (DOT) Headquarters Building:

Financing approach: Operating lease.

Capital project: Department of Transportation (DOT) Headquarters 
Building.

Department/agency: General Services Administration (GSA).

Description of project:

In 2002, GSA reached a deal to sell 11 acres of land at the federally 
owned Southeast Federal Center in Washington, D.C. for $40 million to 
the JBG Companies partnership for the development of a new DOT complex. 
The complex may have multiple buildings and up to 1.35 million rentable 
square feet of office space that GSA will lease for 15 years for DOT 
headquarters operations. DOT is seeking to replace its current leased 
space for which the lease expired March 31, 2000, and to consolidate 
some of its field operations. The DOT locations to be consolidated are 
the Nassif Building (400 7th Street, SW) and the Transpoint Building 
(2100 2nd Street, SW). DOT currently occupies approximately 1.1 million 
occupiable square feet of office and related space at the Nassif 
Building and approximately 450,000 occupiable square feet of office and 
related space at the Transpoint Building.

Description of financing approach:

GSA entered into a 15-year operating lease for a new DOT headquarters 
complex to be built with up to 1.35 million rentable square feet of 
office space. GSA will convey 11 acres of federally owned land at the 
Southeast Federal Center to the private partnership building the new 
office complex.

Benefits claimed:

This lease will replace DOT's current lease and allow it to consolidate 
some of its field offices at one location within current budget 
constraints.

Budgetary observations:

According to GSA officials, during the planning for the Department of 
Transportation lease, it was realized that due to the rental rates in 
Washington, D.C., a 20-year lease would probably not satisfy the 90 
percent scoring criterion for being an operating lease. To address this 
issue, GSA reduced the lease term to 15 years. In addition, OMB 
encouraged GSA to consider financing above-standard items through the 
Federal Buildings Fund or DOT rather than through the lease to reduce 
the lease costs and thus help it meet the requirements for an operating 
lease. The President's 2003 and 2004 budgets included $25 million and 
$45 million respectively for the new DOT headquarters building.

Sources:

U.S. General Accounting Office, Budget Scoring: Budget Scoring Affects 
Some Lease Terms, but Full Extent Is Uncertain, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO-01-929] GAO-01-929 (Washington, D.C.: 
Aug. 31, 2001).

Washington Business Forward, April 2002.

January 19, 2001, letter from OMB to GSA regarding DOT headquarters 
lease; and July 17, 2001, letter from GSA to OMB regarding DOT 
headquarters lease.

Related questions:

* How was the $40 million from the land purchase used?

* Was the $25 million used to buy down the lease so it qualified as an 
operating lease?

* How will the $45 million in the President's 2004 Budget be used if 
appropriated?

Lease of 737 Operational Support Aircraft:

Financing approach: Operating lease.

Capital project: Lease of 737 Operational Support Aircraft.

Department/agency: DOD/Air Force.

Description of project:

The Air Force plans to award a firm, fixed price, multiyear contract to 
Boeing for four leased C-40 aircraft (the military variant of the 
commercial 737). Because the aircraft take 18 to 24 months to build, 
the Air Force plans to lease two used 737 aircraft to provide an 
interim capability. After two new C-40 aircraft are delivered, the used 
737 aircraft would be returned to Boeing to be reconfigured to C-40s 
and then returned to the Air Force.

Description of financing approach:

Under this arrangement, the Air Force would lease three aircraft for 6 
years and the fourth for 5 years. At the end of the lease period, the 
Air Force would have the option to purchase the aircraft for a 
specified negotiated price. It appears that the leases would be 
operating leases and thus the negotiated purchase price would have to 
reflect the value of the planes. If the lease contained a bargain 
purchase price, it would be a lease-purchase and budget authority for 
the entire cost of the lease and purchase would have to be provided up 
front.

Benefits claimed:

The Air Force estimated that it would save $3.9 million (net present 
value) from leasing these four Boeing 737 aircraft compared to the 
outright purchase of the aircraft. This is a savings of about 1 
percent.

Budgetary observations:

The Air Force complied with the OMB criteria in making its case that 
leasing was more advantageous than purchasing. However, relatively 
small changes in assumptions can reduce claimed savings or make leasing 
more expensive. The Congressional Budget Office (CBO) questioned the 
estimated cost to purchase the aircraft, which is a key assumption in 
computing the cost of purchase. The Air Force did not negotiate a 
purchase price and CBO believes it could have negotiated a lower 
purchase price than it used in its analysis, just as it negotiated a 
lower lease price than the initial estimate. Using the Air Force's 
lease data, CBO used a model to work backwards and determine a purchase 
price. CBO found that based on the lease agreement the purchase price 
could be $5 million less per aircraft than the purchase price used in 
the Air Force's analysis. If the Air Force could negotiate a purchase 
price $5 million less than the estimate used, the purchase would save 
about $15 million in net present value terms over the lease. CBO also 
questioned the assumptions for the residual value of the aircraft and 
the cost of self-insurance. Small changes in these assumptions could 
result in leasing being more costly.

Sources:

U.S. General Accounting Office, Discussion points and August 1, 2002 
Congressional Relations memo related to the Air Force lease of 737 
operational support aircraft.

Congressional Budget Office review of report on leasing Boeing 737 
aircraft, July 23, 2002.

Related questions:

* Has this lease been signed?

* What is the negotiated purchase price at the end of the lease?

Leasing of Boeing 767 Tankers:

Financing approach: Operating lease.

Capital project: Leasing of Boeing 767 tankers.

Department/agency: DOD/Air Force.

Description of project:

The Air Force has determined that it needs to replace its KC-135 mid-
air refueling tankers. The Air Force thought it might be able to 
accelerate its refueling tanker replacement efforts in the aftermath of 
September 11, 2001, because commercial aircraft manufacturers were 
faced with the prospect of reduced or canceled orders. Congress 
included language in section 8159 of the fiscal year 2002 Defense 
Appropriations Act allowing the Air Force to establish a multiyear 
pilot program for leasing Boeing 767 aircraft. The Air Force is 
considering leasing Boeing 767 aircraft and converting them to serve as 
tankers. At the end of the lease period, the Air Force would have the 
option to purchase the aircraft for a specified, negotiated price.

Description of financing approach:

The Air Force plans to obtain refueling tankers through an operating 
lease in which budget authority will be scored in each year of the 
lease.

Benefits claimed:

KC-135 tankers will be replaced earlier than expected. GAO reported 
that although there is a long-term requirement to replace the aging 
fleet of KC-135 tankers, the urgency of the need in the short term is 
unclear.

Budgetary observations:

If the aircraft were returned at the end of the 6-year lease period, 
the Air Force tanker fleet would be reduced and the Air Force would 
have to find some way to replace the lost capability even though lease 
payments would have paid almost the full cost of the aircraft. For this 
and other reasons, we have reported that returning the aircraft would 
probably make little sense and the Congress would almost certainly be 
asked to fund the purchase of the aircraft at their residual value when 
the leases expire. In a July 10, 2003, report to the Senate Committee 
on Armed Services, the Air Force estimated that purchasing the aircraft 
would be about $150 million less than leasing, on a net present value 
basis.

Sources:

U.S. General Accounting Office, Military Aircraft: Considerations in 
Reviewing the Air Force Proposal to Lease Aerial Refueling Aircraft, 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-1048T] GAO-03-
1048T (Washington, D.C.: July 23, 2003).

U.S. General Accounting Office, Air Force Aircraft: Preliminary 
Information on Air Force Tanker Leasing, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO-02-724R] GAO-02-724R (Washington, D.C.: 
May 15, 2002).

U.S. General Accounting Office, U.S. Combat Air Power: Aging Refueling 
Aircraft Are Costly to Maintain and Operate, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO/NSIAD-96-160] GAO/NSIAD-96-160 
(Washington, D.C.: August 8, 1996).

[End of section]

Appendix IV: Retained Fees:

Proceeds that result from business-type or market-oriented activities 
with the public, such as the sale or lease of property, are known as 
offsetting collections. The legislation authorizing these collections 
may earmark them for a specific purpose or require them to be 
appropriated in annual appropriation acts before they can be spent. In 
some cases, agencies have been authorized to retain earned fees to fund 
capital projects and improvements.

While retaining fees enables agencies to obtain the funding needed to 
make capital improvements, repairs, and maintenance, it also raises 
questions of equity. International experience with departments 
retaining asset sale proceeds has shown that those that were asset-rich 
continued as such and those that were asset-poor continued to run down 
their asset bases. Since the ability to retain fees results in a shift 
of control over the use of monies from Congress to the agencies, 
Congress would have limited ability to direct the collections to higher 
priority needs.

Following are examples of a few projects funded through retained fees.

* Capital improvements, repairs, and maintenance by federal land 
management agencies and:

* Phillip Burton Conference Center.

Capital Improvements, Repairs, and Maintenance:

Financing approach: Retained fees.

Capital project: Capital improvements, repairs, and maintenance.

Department/agency: Federal land management agencies.

Description of project:

Since 1996, federal land management agencies[Footnote 8] have collected 
over $900 million in recreation fees from the public under an 
experimental initiative called the Recreational Fee Demonstration 
Program. Congress first authorized the program in 1996 for 3 years and 
has extended it four times. The authority to collect these fees expires 
at the end of fiscal year 2004.

Description of financing approach:

The Recreational Fee Demonstration Program permits four land management 
agencies to use new or increased fees collected from visitors to help 
address deteriorating conditions at many federal recreation areas, 
among other things. At least 80 percent of the revenues are to be spent 
at the site that collects the fees; the remaining 20 percent can be 
spent at other sites at the discretion of each agency. To ensure that 
fee revenues remain available for improvements after 2004, the 
administration has indicated it will propose legislation providing 
permanent fee authority.

Benefits claimed:

For many sites, the additional fee revenues increased their annual 
budgets by 20 percent or more. With this infusion of revenues, some 
units with maintenance backlogs could address their unmet needs in 
relatively few years. Other units with small or nonexistent backlogs 
could undertake further development and enhancement.

Sources:

U.S. General Accounting Office, Recreation Fees: Information on Forest 
Service Management of Revenue from the Fee Demonstration Program, 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-470] GAO-03-470 
(Washington, D.C.: Apr. 25, 2003).

U.S. General Accounting Office, Recreation Fees: Demonstration Fee 
Program Successful in Raising Revenues but Could Be Improved, 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO/RCED-99-7] GAO/RCED-
99-7 (Washington, D.C.: Nov. 20, 1998).

Related question:

* What is the effect of inequities between relatively high revenue 
producing National Parks and those that earn relatively less?

Phillip Burton Conference Center:

Financing approach: Retained fees.

Capital project: Phillip Burton Conference Center.

Department/agency: General Services Administration (GSA).

Description of project:

To increase the use of underused space in the Phillip Burton Federal 
Building and U.S. Courthouse in San Francisco,[Footnote 9] GSA 
established a Government Conference and Training Center to operate as a 
self-sustaining center. Facilities are available to both the federal 
community and the public.

Benefits claimed:

The income received from the conference center has been used to further 
enhance the conference center and the tenant agencies in the building. 
Underused space was converted into space that could more effectively be 
used by the federal government and the community.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., February 1999, 10 - 11.

Related questions:

* How was the original construction financed?

* Do the fees charged cover those costs or just operating costs?

* Under what authority may fees be retained?

* Can all the fees be retained or just a portion--what constraints are 
on this?

* Did any tenants need to be relocated as a result of the construction?

* Is there any connection between the construction of the conference 
center and the funding of the plaza in front of the building (plaza 
work done in 1996 through 1999)?

* Were original financing costs repaid?

[End of section]

Appendix V: Real Property Swaps:

A real property swap is an exchange of property owned by the federal 
government with either a private entity or a state or local government 
for another property. In many cases, the property exchanged by the 
federal government has been underused because it is deteriorating. 
Despite a federal property's poor condition, a private entity may 
consider the same property valuable for future development and enter 
into a property swap with the federal government. Under such an 
arrangement, the federal government receives another existing property, 
or the private entity constructs a new facility for the federal 
government equal in value to the land received in exchange.

Property swaps can relieve the federal government of maintenance and/or 
renovation costs and result in a real asset that may be used 
immediately with no additional appropriations required. However, 
determining fair value for the properties exchanged is not always a 
clear-cut process and congressional oversight of these exchanges is 
limited.

While Congress may receive notification of pending swaps, these 
transactions are not reflected in the budget since there are no federal 
government cash flows involved. Congressional budget decisionmakers 
therefore do not have an opportunity to consider whether the value of 
the exchanged property should be reallocated to other competing 
resource needs.

Examples of real property swaps include:

* Los Angeles Air Force Base,

* Albuquerque, NM, federal building and parking,

* Army Reserves fire station,

* Army Reserves Fort Snelling, MN, and:

* L. Mendel Rivers Building, Charleston, SC.

Los Angeles Air Force Base Systems Acquisition Management Support 
Project:

Financing method: Real property swap.

Capital project: Los Angeles Air Force Base Systems Acquisition 
Management Support project.

Department/agency: Department of Defense/Air Force.

Description of project:

The Air Force traded government-owned land on the Los Angeles Air Force 
Base to a private developer in exchange for the design and construction 
of a new 560,000 square foot facility on the base for the Space and 
Missile Systems Center. The new office space will replace the use of 
buildings constructed in 1957 and 1966 that are outdated and vulnerable 
to earthquakes.

Description of financing approach:

The National Defense Authorization Act of 2001 (Pub. L. 106-398) 
authorized the Secretary of the Air Force to sell or lease all or part 
of the real property at Los Angeles Air Force Base (LAAFB). The statute 
also provided that the only consideration that the Air Force could 
receive for the property was "the design and construction on 
[unconveyed] property…of one or more facilities to consolidate the 
Space and Missile Systems Center mission and support functions." 
Furthermore, the Act provided that if the value of the new facility 
received by the Air Force exceeded the value of the property it 
conveyed, then the Air Force should "lease back" the new facility from 
the developer for a period up to 10 years, with the Air Force taking 
title to the facility at the end of the lease period. As of October, 
2002, the Air Force still was negotiating the final terms of the 
contract, which includes a property swap and the probability of a 
lease-purchase agreement to make up the difference in value between the 
new facility and the property conveyed by the Air Force.

Benefits claimed:

The Air Force gains a new office complex at a fraction of the cost of 
independently contracting for a new office complex while the Los 
Angeles area communities gain land for potential development. The Air 
Force is able to dispose of up to 865,000 square feet of substandard 
buildings and eliminate requirements for $130 million to $150 million 
in military construction projects. Furthermore, reduction of the base 
size lowers ongoing operations and maintenance costs by more than $3 
million per year.

Sources:

Comptroller General decisions in the matter of SAMS El Segundo, LLC, B-
291620 and B-291620.2, February 3, 2003.

Albuquerque, NM, Federal Building and Parking:

Financing method: Real property swap.

Capital project: Albuquerque, NM, federal building and parking.

Department/agency: General Services Administration (GSA).

Description of project and financing approach:

The General Services Administration acquired a large city parking 
garage near federal buildings in exchange for two smaller parking areas 
and a partially vacant historic building that was in need of repair. 
GSA had been operating the historic federal building, which was 30 to 
40 percent vacant, at an annual loss of $200,000 and had faced building 
modernization costs of $3 million. Because the exchanges are non-cash, 
it cannot be known whether the exchanged property could have been sold 
competitively for a different value than the properties received in 
exchange.

Benefits claimed:

GSA reports that it improved its real estate portfolio performance. GSA 
will meet a projected federal tenant demand for 450 additional parking 
spaces. The agency relieved itself of a money-losing property and 
millions of dollars in building renovation costs. Money that would have 
been lost or spent on repairs for this building can be reinvested in 
property retained in GSA's portfolio.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 2000, 25-26.

Related questions:

* Do existing federal buildings have enough space to absorb the 
employees that will move from the historic building? If not, where will 
the employees move and at what cost?

* Was this transaction compared to costs of GSA restoring the building 
either by itself or through some other kind of partnership and 
maintaining existing office space? Were competing offers considered?

* How much could the building have sold for independent of this 
arrangement?

* What were the parking arrangements for federal employees prior to 
obtaining the large garage? How do parking costs now compare to the 
prior situation?

* Were the $3 million in repairs already budgeted for in GSA's 
accounts?

* Was any statutory authority required to make this transaction (e.g., 
Historic Building Preservation Act)?

Parks Reserve Forces Training Area Fire Station:

Financing method: Real property swap.

Capital project: Parks Reserve Forces Training Area fire station.

Department/agency: Department of Defense/Army Reserves.

Description of project:

The Army Reserves entered into a real property exchange agreement with 
a private land developer. The Army Reserves conveyed about 11 acres of 
training area land to the developer in exchange for construction of a 
new fire station.

Description of financing approach:

The developer receives land appraised at $1.8 million to construct an 
access road into its new housing development. The Army Reserves 
receives a new fire station valued at $3.9 million. The appraisal 
process is meant to determine the fair market value of the property to 
be conveyed by the Army Reserves. The property received in exchange 
must be at least of equal value and must meet minimal requirements that 
have changed since the old facility was constructed. In order to meet 
this second requirement, the value of the property received may be 
higher than the appraised value of the property conveyed by the Army 
Reserves. Nonetheless the size of the discrepancy raises questions 
about the appraisal process. The initial appraisal of the Army 
Reserves' 11-acres was $75,500 because the land's current condition was 
assessed rather than the most valuable use of the property by a 
developer.

Benefits claimed:

The Army Reserves receives a new fire station without paying out any 
money up front in military construction costs to replace an older, less 
modern station.

Source:

U.S. General Accounting Office, Defense Infrastructure: Changes in 
Funding Priorities and Management Processes Needed to Improve Condition 
and Reduce Costs of Guard and Reserve Facilities, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO-03-516] GAO-03-516 (Washington, D.C.: 
May 15, 2003).

Related questions:

* What are the locations of the old and new fire stations?

* How does the Army Reserves explain the size of the discrepancy in the 
exchanged values?

* What is the appraisal process used to determine the value of the 
property exchanged?

Army Reserves Facilities at Fort Snelling, MN:

Financing method: Real property swap.

Capital project: Army Reserves facilities at Fort Snelling, MN.

Department/agency: Department of Defense/Army Reserves.

Description of project:

The Army Reserves entered into two real property exchange agreements: 
first with the Metropolitan Airport Commission in August 2002; and then 
with the Minnesota Department of Transportation and the Metropolitan 
Council in November 2002. In the first agreement, the Army Reserves 
conveyed 11 acres of property that will be used to expand the runway at 
the Minneapolis-St. Paul International Airport. In return, the Army 
Reserves received a newly constructed maintenance facility in St. 
Joseph, Minnesota. In the second agreement, the Army Reserves conveyed 
seven acres of property in exchange for a 38,000 square foot addition 
to its permanent facility.

Description of financing approach:

In the August 2002 agreement, the Army Reserves conveyed property 
appraised at $1.4 million in exchange for a new maintenance facility 
valued at $1.7 million. In the November 2002 agreement, the Army 
Reserves conveyed property appraised at $2 million in exchange for a 
building addition worth about $5.1 million. Because the exchanges are 
non-cash, it cannot be known whether the exchanged property could have 
been sold for a different value than the properties received in 
exchange.

Benefits claimed:

The Army Reserves receives new building space without having to draw on 
the Defense Department's military construction budget and at a greater 
appraised value than the property given up.

Source:

U.S. General Accounting Office, Defense Infrastructure: Changes in 
Funding Priorities and Management Processes Needed to Improve Condition 
and Reduce Costs of Guard and Reserve Facilities, [Hyperlink, http://
www.gao.gov/cgi-bin/getrpt?GAO-03-516] GAO-03-516 (Washington, D.C.: 
May 15, 2003).

Related questions:

* How does the Army Reserves explain the size of the discrepancy in the 
exchanged values?

* What is the appraisal process used to determine the value of the 
property exchanged?

L. Mendel Rivers Building, Charleston, SC:

Financing method: Real property swap.

Capital project: L. Mendel Rivers Building, Charleston, SC.

Department/agency: General Services Administration (GSA).

Description of project:

The seven-story L. Mendel Rivers building was constructed in 1965 with 
almost 100,000 rentable square feet of space. It has a surface parking 
lot and sits on over two acres of land. Since Hurricane Floyd damaged 
the building in October 1999, it has been totally vacant and its 
tenants have relocated to leased space. The building is contaminated 
with asbestos and GSA has determined that it would be too costly to 
rehabilitate or replace the building. While the Rivers building is 
vacant, GSA still incurs expenses for its basic maintenance and 
utilities. In fiscal years 2002 and 2003, GSA spent about $28,000 to 
operate and maintain the building. Occasionally, GSA rents out the 
parking lot and uses the rental income to help offset some of the 
building expenses.

Description of financing approach:

For a number of years, GSA has been engaged in discussions with the 
City of Charleston to exchange the L. Mendel Rivers site for a new 
building. Under the proposed agreement, the city would construct a new 
building with about 27,000 useable square feet next to the federal 
court complex and a parking garage in which GSA would have 60 parking 
spaces in exchange for the L. Mendel Rivers site. While the building to 
be constructed is much smaller than the L. Mendel Rivers building, the 
new building is in the historic downtown business area where land 
values are higher; appraisals show that the exchange sites are of equal 
value. According to a GSA official, the mayor of Charleston has signed 
a memorandum of understanding with GSA that sets forth the terms and 
conditions for the exchange and the GSA Administrator is expected to 
sign the memorandum in early July. The exchange will not occur until 
independent appraisals show the value of the properties to be exchanged 
are equal in value.

Benefits claimed:

GSA would be relieved of a money-losing property and in return it would 
obtain new office space without needing an appropriation.

Sources:

GSA's Asset Business Plan and interviews with GSA officials.

[End of section]

Appendix VI: Sale-Leaseback:

Under a sale-leaseback agreement, a federal agency sells an asset and 
then leases back some or all of the asset from the purchaser. Agencies 
might consider such an arrangement when the property they are using 
needs renovation or when they need only a fraction of the total 
building space. When building renovations are necessary, sale-leaseback 
agreements may transfer renovation costs to the purchaser of the 
property. The government may then lease back after improvements have 
been made.

Federal agencies generally are not permitted to retain the proceeds 
from the sale of assets unless specific legislation states otherwise. 
In at least one instance, Congress has authorized GSA to credit the 
Federal Buildings Fund with proceeds from the sale of a federal 
building. GSA then leased back a portion of the sold building.

The potential drawback of sale-leaseback agreements is that over the 
long term they may be more expensive, particularly in cases when the 
federal government occupies the entire building. Renovations financed 
by the private sector will always cost more than those financed by 
Treasury borrowing. As a result, the share of the building to be used 
by the federal government can be an important determinant of the value.

We identified one example of a sale-leaseback arrangement in a 
transaction involving a federal building in Charleston, West Virginia.

Charleston, WV, Federal Building:

Financing method: Sale-leaseback.

Capital project: Charleston, WV, Federal Building.

Department/agency: General Services Administration (GSA).

Description of project:

The construction of the Robert C. Byrd U.S. Courthouse in Charleston, 
WV enabled tenants of the federal building at 500 Quarrier Street to 
relocate. Originally, GSA had planned to excess the Quarrier Street 
building after the move but the Social Security Administration (SSA) 
contacted GSA with a space request to consolidate their functions with 
West Virginia's Disability Determination Agency. GSA entered into an 
agreement to sell the 130,000 square foot Quarrier Street building to a 
developer and lease back about 82,000 square feet in the same building 
so that SSA could collocate with the state government agency.

Congress included language in the appropriation bill[Footnote 10] for 
the Byrd Courthouse that approved the sale and leaseback of the federal 
building and allowed GSA to retain funds from the sale of the building 
for the Federal Buildings Fund.

Description of financing approach:

In September 1998, GSA sold the federal building on Quarrier Street to 
a developer for $3.5 million. The developer committed to investing $11 
million to upgrade the facility from Class C to Class A. In exchange, 
GSA committed to lease back a portion of the facility for 20 years.

Benefits claimed:

SSA and GSA both claim benefits from this arrangement. SSA maintains a 
presence in Charleston's central business district and can increase 
productivity by consolidating functions and collocating with West 
Virginia's social service agency. GSA retains funds from the building 
sale and does not directly incur the estimated $11 million cost of 
upgrading the building.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 7.

Related questions:

* What kind of cost benefit analysis did GSA do to compare costs of 
leasing two-thirds of the building vs. doing the repairs itself and 
outleasing the remaining 48,000 square feet to the private sector?

* Where were the SSA employees working before?

* How long does SSA believe it will require the leased space? What are 
the terms of the lease?

* What efficiencies are gained from the new space that is shared with 
the state agency?

* Are there other cases of GSA receiving permission to retain sale 
proceeds?

[End of section]

Appendix VII: Lease-Leaseback:

A lease-leaseback agreement between a government agency and a private 
entity may consist of three stages: the government agency purchases an 
asset; the agency then leases out the same asset to a private entity 
for a fixed time period in return for a lump sum payment; finally, the 
agency leases back the use of the same asset over the same time period 
via incremental payments. For this type of arrangement, the net result 
is similar to the agency entering into a lease-purchase contract since 
the asset is privately financed and paid for incrementally. The agency 
maintains ownership and control of the asset and thus retains both the 
economic benefits and risks related to asset ownership.

We identified three Tennessee Valley Authority (TVA) lease-leaseback 
contracts for combustion turbine units. TVA signed the respective 
contracts in fiscal years 2000, 2002, and 2003.

Combustion Turbines:

Financing method: Lease-leaseback.

Capital project: Combustion turbines.

Department/agency: Tennessee Valley Authority (TVA).

Description of project and financing approach:

TVA, a wholly-owned government corporation, entered into contracts in 
fiscal years 2000, 2002, and 2003 to outlease combustion turbine units 
to private investors in exchange for a lump-sum payment. At the same 
time TVA agreed to lease back the same assets by making regular 
incremental payments over the term of the contract. TVA maintains 
ownership of the generators but it can relinquish the property to the 
private sector at the end of the term. Thus, according to TVA, the 
private sector bears the "residual value" risk of the asset.

Benefits claimed:

According to TVA, entering into the fiscal year 2000 and 2002 lease-
leaseback arrangements could, over time, save the agency approximately 
$50 million. Lease-leasebacks provide financial flexibility to TVA 
because of early buyout and termination options in the contract. TVA 
may terminate its lease if the economic conditions of operating the 
combustion turbine units change at some point during the term of the 
lease. For example, the turbine units may become obsolete, or TVA may 
decide to sell the units because they no longer meet TVA's load 
requirements. Furthermore, TVA can relinquish the property to the 
private entity at the end of the lease term, so that the private entity 
bears the "residual value" risk of the asset.

The $50 million benefit claimed by TVA does not necessarily mean that 
the lease-leaseback was the best financial deal for the government as a 
whole. For example, tax preferences used by the private entity 
represent a cost to the government but not to TVA.

Source:

U.S. General Accounting Office, Tennessee Valley Authority: Information 
on Lease-Leaseback and Other Financing Arrangements, [Hyperlink, http:/
/www.gao.gov/cgi-bin/getrpt?GAO-03-784] GAO-03-784 (Washington, D.C.: 
June 30, 2003).

[End of section]

Appendix VIII: Public Private Partnerships:

Given today's budget constraints, evolving private sector markets and 
the expansion of creative real property development alternatives, 
several agencies have established public private partnerships as a 
means of leveraging the intrinsic equity value of real property. 
Ideally, the partnerships are designed such that each participant makes 
complementary contributions that offer benefits to all parties. Public 
private partnerships tap the capital and expertise of the private 
sector to improve or redevelop federal real property assets.[Footnote 
11] They are considered most appropriate where excess capacity exists 
within the asset and where existing government facilities do not 
adequately satisfy the current or potential future needs.

OMB Circular A-76 describes the federal government's longstanding 
policy to rely on the private sector for needed commercial services. 
Public private partnerships are consistent with this policy so long as 
the product or service provided by the private partner cannot be 
procured more economically by the federal government. Partnerships 
raise questions about what functions are most appropriately performed 
by the federal government.

Proponents of public private partnerships argue that this approach 
provides a realistic, less costly alternative to leasing when planning 
and budgeting for real property needs. Proponents also note that 
federal partners benefit from improved, modernized, and/or new 
facilities plus a minority share of the income stream generated by the 
partnership or use of the asset at a lower cost than a commercial 
lease.

Critics of public private partnerships caution that these ventures are 
not the least expensive means of meeting capital needs, although they 
may appear to be in the short-term. They remind decisionmakers that up-
front payment of appropriated funds is the least expensive way to 
obtain assets. Although partnerships may be more costly, it is possible 
that they could make sense from a mission perspective. However, the 
full costs should be transparent to decisionmakers through inclusion in 
primary budget data.

Following are examples of a few public private partnerships.

* Civic Square II Project,

* Houston Regional Office Collocation,

* Veterans Affairs Office Collocation and Parking Garage, Chicago, and:

* Oak Ridge National Laboratory.

Civic Square II Project:

Financing approach: Public private partnership.

Capital project: Civic Square II project.

Department/agency: U.S. Postal Service.

Description of project:

The main post office in the city of New Brunswick, NJ, which was 
constructed in 1936, had been underused and had accumulated an 
increasing amount of deferred maintenance. Accordingly, the Postal 
Service negotiated a public private partnership that resulted in a 
newly restored Post Office and a facility housing the Middlesex County 
Prosecutor's Office, the New Brunswick Police Department, and an 
underground parking garage. The Post Office leased its land to the 
local government, which contracted for the restoration of the Post 
Office and construction of additional facilities for its own use.

Benefits claimed:

The Postal Service now has a restored Post Office along with 
significant revenue from the ground lease. All federal, city, and 
county offices have benefited from the building through improved 
operations, higher customer satisfaction, and greater employee morale.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 20.

Related questions:

* Who fronted the construction funds?

* Who makes lease payments to whom?

* How long is the life of lease arrangement?

* Was a comparison made between the cost of the federal government 
doing it all and forming the partnership?

Houston Regional Office Collocation:

Financing approach: Public private partnership.

Capital project: Houston Regional Office Collocation.

Department/agency: Veterans Benefits Administration.

Description of project:

The Veterans Benefits Administration (VBA) needed to relocate its 
regional office in order to better serve veterans and their 
beneficiaries throughout southern Texas. The Department of Veterans 
Affairs (VA) negotiated an enhanced-use lease of underused VA medical 
center land to a local developer, which constructed a 140,000 square 
foot state-of-the-art regional office. As part of this arrangement, VA 
signed short-term operating leases to obtain use of the newly developed 
space. The developer also financed, built, owns, and operates 
businesses on the balance of the site.

Benefits claimed:

VA states that this project saved taxpayers over $6 million in 
construction costs and generated an additional $10 million savings in 
operating costs. VA also receives a small share of the developer's 
profits.

Source:

VA's briefing packet on enhanced-use leasing.

Related questions:

* How many years does the lease cover?

* Does VA maintain the master ground lease?

* What happens to the developer-owned businesses at the end of the 
lease life?

Veterans Affairs Office Collocation and Parking Garage, Chicago:

Financing approach: Public private partnership.

Capital project: Veterans Affairs Office Collocation and Parking 
Garage, Chicago.

Department/agency: Veterans Benefits Administration.

Description of project:

The Veterans Benefits Administration sought to avoid high-cost leased 
office space and improve service delivery and accessibility to 
veterans. Moreover, VA Medical Center Westside needed relief from the 
lack of available parking. Accordingly, VA negotiated a long-term 
outlease of six acres of flat parking space to a developer that then 
built and managed a 95,000 square foot office building and a 1,565 car 
parking garage. VA then established short-term operating leases to 
obtain use of the newly developed space.

Benefits claimed:

The average annual cost to VA for the new office space and parking is 
expected to be 50 percent less than comparable market rates.

Source:

VA's briefing packet on enhanced-use leasing.

Related questions:

* What happened to the space that employees used to be in?

* How much is what they are paying compared to what they were paying?

* How long is the term of the outlease?

Oak Ridge National Laboratory:

Financing approach: Public private partnership.

Capital project: Oak Ridge National Laboratory.

Department/agency: Department of Energy.

Description of project:

The Department of Energy (DOE) needed to replace deteriorating 
buildings constructed during World War II with modern facilities at the 
Oak Ridge National Laboratory (ORNL). However, it lacked adequate 
funding to do this.

Description of financing approach:

DOE designated federal land next to ORNL as excess and conveyed it to a 
developer who would process the construction phase requirements from 
bid solicitation through construction completion, on the land conveyed 
by DOE. Although the land in its current state is excess to the needs 
of DOE, the resulting building space to be constructed is needed to 
accomplish DOE's missions. The private developer would finance 
construction and then lease the new buildings to DOE's prime contractor 
for DOE missions.

At the end of the 30-year "payback plus profit" term, the quitclaim 
deed[Footnote 12] conveying the land requires that the private party 
offer no-cost repurchase or reacquisition rights to the federal 
government for the land and facilities. Ultimately, the government must 
reimburse lease payments to DOE's prime contractor. The quitclaim deed 
also contains restrictive language that specifies use of the property 
so as not to compromise the integrity of ORNL by the possible 
bankruptcy of the private developer or by DOE's possible cancellation 
of the lease.

Benefits claimed:

DOE was able to obtain the needed space for its contractors without 
having to obtain up-front funding or special legislation.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., Fall 2002, 6.

Related questions:

* Are DOE's lease reimbursement payments included as part of the 
negotiated payments to the "prime" contractor?

* Why would DOE not claim the property back after the 30-year period is 
completed?

[End of section]

Appendix IX: Outleases:

Federal asset managers are confronted with numerous challenges in 
managing their multibillion dollar real estate portfolio, such as a 
large backlog of deferred maintenance and obsolete, underused 
properties. In response, some agencies have outleased excess or 
underused properties to shift the cost of maintenance and restoration 
to their private sector partners, thus relieving the federal government 
of these expenses.

Historic but run-down properties are prime candidates for outleasing. 
This is because the National Historic Preservation Act authorizes 
agencies to use the lease proceeds of these historic properties to 
defray the costs of maintaining and repairing other historic properties 
they own.

Outleasing historic properties promotes the restoration, repair, and 
maintenance of important national buildings. However, it is unclear 
whether the outright sale of such properties is possible and whether 
selling would accomplish the same purpose with greater economic benefit 
to the taxpayer.

Following are examples of a few outleased projects.

* Cooperative Use Outlease for Food Court;

* Galveston, Texas Customhouse;

* Maine Lights Program;

* U.S. Tariff Building; and:

* McCormack Post Office-U.S. Courthouse.

Cooperative Use Outlease for Food Court:

Financing approach: Outlease.

Capital project: Cooperative use outlease for food court.

Department/agency: General Services Administration (GSA).

Description of project:

Under the National Historic Preservation Act and the Public Buildings 
Cooperative Use Act,[Footnote 13] GSA outleased 17,600 square feet of 
underused space for a restaurant and retail center in the Railroad 
Retirement Board (RRB) building located in Chicago, Illinois. The lease 
had a fixed term of 15 years, with three 5-year renewal options. GSA, 
RRB, the City of Chicago, and the developer also will upgrade the 
sidewalks surrounding the building (new pavers, planters, trees, and 
lamp posts) under GSA's Good Neighbor policy. A similar outlease was 
negotiated at Chicago's Metcalfe Federal Building.

Description of financing approach:

Construction costs of about $10 million were paid by the project 
developer, who is also responsible for the utility, maintenance, 
permits, taxes, and insurance costs for the project. The developer's 
revenue is derived solely from sublease proceeds.

Benefits claimed:

The outlease generates a substantial revenue stream to the Federal 
Buildings Fund --about $10 million over the term of the lease.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 18.

Galveston, Texas Customhouse:

Financing approach: Outlease.

Capital project: Galveston, Texas Customhouse.

Department/agency: General Services Administration.

Description of project:

The Galveston Customhouse is one of the oldest federal buildings west 
of the Mississippi River. While the exterior of the building was in 
good condition, the interior had fallen in disrepair and housed only 
six people. However, it was decided that because of its historic 
significance, the customhouse was not a good candidate for disposal. 
Instead, the building was outleased to the Galveston Historical 
Foundation (GHF) for 60 years. The GHF will preserve and restore the 
customhouse to ensure its historic integrity. Once repairs are made, 
the customhouse will house both the GHF headquarters and a visitor 
center for the historic Strand District of Galveston.

Benefits claimed:

The 60-year lease removes GSA's estimated $162,000 per year cost of 
operating an underused asset. The customhouse also benefits from $1 
million that the GHF has invested in restoration and repair work. 
Finally, the city and Historic Strand District also benefit by the 
continued use and preservation of one of its most significant 
buildings.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 17.

Related questions:

* Was any cost analysis done to consider having GSA renovate the 
building and then move federal employees currently leasing elsewhere 
into the building?

* Has any thought been given to what will happen when the lease expires 
at the end of the 60-year period?

* What happened to the six employees that had been working in the 
customhouse?

Maine Lights Program:

Financing approach: Outlease.

Capital project: Maine Lights Program.

Department/agency: Coast Guard.

Description of project:

With the development of technological aids to navigate merchant and 
sailing vessels, the need for lighthouses has greatly diminished. The 
Coast Guard owns many lighthouses that deteriorate without day-to-day 
upkeep. Moreover, the Coast Guard has become unable to maintain the 
properties at the standards of the state historic preservation 
guidelines given the level of funding for repairs and alterations. The 
Maine Lights Program outleased and divested 28 historic lighthouses to 
organizations that will ensure the maintenance, repair, and care of 
these historically significant properties.

Description of financing approach:

Under the National Historic Preservation Act, the proceeds of these 
leases may be used to offset expenses associated with other historic 
properties owned by the Coast Guard.

Benefits claimed:

This program ensures the lighthouses will maintain their historic 
integrity while allowing the Coast Guard to avoid between $3 to $5 
million in annual repair and maintenance costs. Moreover, lease 
payments defray the costs of other historic preservation efforts.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 5.

U.S. Tariff Building:

Financing approach: Outlease.

Capital project: U.S. Tariff Building.

Department/agency: General Services Administration (GSA).

Description of project:

GSA leased the U.S. Tariff Building, which had been vacant for a number 
of years, to the Kimpton Hotel and Restaurant Group, Inc. (Kimpton 
Group) for 60 years. The Kimpton Group restored the building, 
converting it into a luxury hotel that includes restaurants, retail 
space, and meeting rooms. GSA retains ownership of the 1839-built 
structure under the National Historic Preservation Act, which 
encourages adaptive reuse of public buildings that are no longer needed 
by federal agencies.

Description of financing approach:

GSA contributed $5 million to clean the historic building's exterior, 
repair windows, and install a handicapped accessible elevator. The 
Kimpton Group paid $32 million to renovate the interior of the 
building, using the 20 percent federal historic rehabilitation tax 
credit to finance a portion of the rehabilitation costs.

Benefits claimed:

Rents paid to GSA under the lease support the preservation of other 
historic properties in GSA's inventory. In addition, GSA is relieved of 
the burden of maintaining an unproductive property. Finally, the 
restoration contributes to the revitalization of the surrounding 
neighborhood.

Sources:

GSA press releases. U.S. General Services Administration Signs Lease 
with Kimpton Group on Tariff Building (Nov. 23, 1999) and GSA 
Celebration for Opening of Hotel Monoco (July 2002).

Paper issued by the Heritage Consulting Group, 2002; Preservation 
Online, Hotel Opens in Historic D.C. Building, June 13, 2002.

McCormack Post Office-U.S. Courthouse:

Financing approach: Outlease.

Capital project: McCormack Post Office-U.S. Courthouse.

Department/agency: General Services Administration (GSA).

Description of project:

In the fall of 1998, the federal courts in Boston relocated from the 
John W. McCormack Post Office-U.S. Courthouse to the new U.S. 
Courthouse, leaving a large amount (228,000 square feet) of courtroom 
and court-related space vacant. The Massachusetts State Trials Courts 
agreed to a 5-year lease of this space, in "as is" condition, so that 
it could renovate its own courthouse. With the common functions of the 
federal and state courts, little build out of space was required.

Description of financing approach:

This outlease of space was done under Section 111 of the National 
Historic Preservation Act, which allow funds from outleasing to be used 
to preserve historical properties in the GSA inventory.

Benefits claimed:

This outlease maintains the viability of a historic asset and ensures a 
safe and productive work environment for the State Court of 
Massachusetts.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 5.

Related questions:

* Since the 5 years are just about up, what plans does GSA have for 
this space next? (GSA received $76 million in fiscal year 2002 and $73 
million in fiscal year 2003 for major renovations of this building.):

* What specifically were the funds used for (i.e., what "preservation" 
work was performed other than routine maintenance?):

* Is the post office still located in the building?

[End of section]

Appendix X: Share-In-Savings Contracts:

Energy savings performance contracts, a type of share-in-savings 
contract, finance energy-saving capital improvements for federal 
facilities without an up-front cost to the government. First authorized 
in 1986, these share-in-savings contracts have been used to finance 
hundreds of millions of dollars of energy system upgrades and 
installations. Federal agencies may enter into contracts for as long as 
25 years with contractors who purchase and install new energy systems 
in federal buildings. Agencies then pay back the contractors for the 
equipment plus a percentage of the energy costs saved as a result of 
the more efficient energy systems and relief of in-house maintenance 
costs. Agencies have some flexibility in determining when they take 
ownership of the energy systems. When a contract expires, the federal 
government owns the equipment and retains all of the future savings.

Agencies other than the Department of Defense[Footnote 14] may retain 
50 percent of the energy savings realized from energy savings 
performance contracts (after paying the contractor). The remaining 50 
percent saved is transferred to the Treasury. Savings retained by the 
agency are available for specified energy and water conservation 
projects until expended. However, according to one Department of 
Commerce official, only about 1 per cent of the total energy savings 
has been split between the agencies and the Treasury thus far. This is 
because agencies devote most savings to paying off the cost of 
equipment as soon as possible to reduce financing costs.

Without share-in-savings contracts, Congress would have to appropriate 
hundreds of millions of dollars today to meet currently required energy 
consumption standards.[Footnote 15] Direct purchase of more efficient 
energy systems would allow all future savings to accrue to the 
government, rather than paying out a percentage of the savings to 
private contractors. Also, because a private contractor--which will 
have a higher cost of capital than the federal government--finances the 
capital improvements, share-in-savings contracts are likely to be more 
expensive over the long term than direct federal purchase. There could 
be an additional cost to the government of reduced tax revenues when 
contractors maintain ownership of energy equipment that may be 
amortized. However, such an arrangement usually results in lower 
interest rates for the cost of equipment, according to a Commerce 
Department official.

Examples of Energy Savings Performance Contracts include:

* Eisenhower Center;

* Tucson, AZ, Courthouse; and:

* Department of Commerce HVAC system upgrade.

Eisenhower Center:

Financing approach: Share-in-savings contract.

Capital project: Eisenhower Center.

Department/agency: General Services Administration, Department of 
Energy, and National Archives and Records Administration.

Description of project and financing approach:

The Eisenhower Center is comprised of the Eisenhower family home, 
Dwight D. Eisenhower Presidential Library, and the Dwight D. Eisenhower 
Museum. A contractor installed $300,000 of new equipment to provide 
more efficient management of energy and special lighting with ultra 
violet lens shielding for archive records protection. The contractor 
will be reimbursed for the equipment and its financing costs and also 
receive 50 percent of the energy savings.

Benefits claimed:

With no up-front costs to the government, the Eisenhower Center gets a 
modern energy management and lighting system that will better preserve 
documents.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 8.

Related questions:

* When does ownership of the energy equipment transfer to the 
government?

* How long does the contract run? Is there a plan for maintenance and 
repairs when this contract expires?

* How was the contract's value to the government determined? How does 
this play out in the agency's budget?

* What would it have cost the government to purchase and install the 
new systems?

Tucson, AZ, Courthouse:

Financing approach: Share-in-savings contract.

Capital project: Tucson, AZ, Courthouse.

Department/agency: General Services Administration (GSA).

Description of project:

The General Services Administration awarded an energy savings 
performance contract for the new Courthouse in Tucson, Arizona before 
the building was constructed. This is one of the first times that GSA 
used an energy savings performance contract in the construction of a 
new facility. The original courthouse plans would have cost more to 
implement than Congress had appropriated. Thus, GSA was faced with 
either reducing the size (and functionality) of the building by 1 or 2 
floors or finding a way to finance an integral part of the structure 
outside of the appropriations process.

The winning bidder of the 25-year energy maintenance contract purchased 
and installed a heating and cooling system that was more efficient than 
the system in the original building plans. Energy savings were 
determined according to the kilowatts per hour used by the installed 
system compared to the energy system that was initially planned for. 
GSA took ownership of the energy systems along with the rest of the 
building. Out of the money saved on energy costs, GSA is repaying the 
contractor for the energy systems and then sharing the money saved on 
energy costs with the contractor.

Benefits claimed:

The energy savings performance contract reduced the initial funds 
needed to construct the new courthouse.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., December 1999, 9.

Related questions:

* When does ownership of the energy equipment transfer to the 
government?

* How long does the contract run? Is there a plan for maintenance and 
repairs when this contract expires?

* How was the contract's value to the government determined? How does 
this play out in the agency's budget?

* What would it have cost the government to purchase and install the 
new systems?

Heating, Ventilation, and Air Conditioning System Upgrade:

Financing approach: Share-in-savings contract.

Capital project: Heating, ventilation, and air conditioning system 
upgrade.

Department/agency: Department of Commerce.

Description of project and financing approach:

The Department of Commerce entered into an agreement with the Potomac 
Electric Power Company (PEPCO) to improve the heating, ventilation, and 
air conditioning system, install energy motors, and retrofit chilled 
water pumps. The project costs will be repaid from future energy 
savings.

Benefits claimed:

Commerce gains a more energy-efficient system without any initial costs 
to the government.

Source:

General Services Administration, Real Property Policysite, Office of 
Governmentwide Policy, Best Practices: News and Views on Real Property 
Policy, Special Edition, Washington, D.C., 1997, 4.

Related questions:

* When does ownership of the energy equipment transfer to the 
government?

* How long does the contract run? Is there a plan for maintenance and 
repairs when this contract expires?

* How was the contract's value to the government determined? How does 
this play out in the agency's budget?

* What would it have cost the government to purchase and install the 
new systems?

[End of section]

Appendix XI: Debt Issuance:

The federal government funds its operations in part by borrowing 
through the issuance of securities to the public. Several federal 
organizations, such as the Tennessee Valley Authority (TVA), Federal 
Housing Administration, and Farm Credit System Financial Assistance 
Corporation issue their own agency debt.

The reasons for issuing debt differ considerably from one agency to 
another. The predominant issuer of agency debt is TVA. As of the end of 
2002, TVA had issued 94 percent of the total debt issued by agencies. 
TVA uses the borrowings primarily to finance capital expenditures. As a 
government corporation, TVA operated according to a different set of 
rules than most federal agencies.

Debt Issuance:

Financing Approach: Debt issuance.

Department/Agency: Tennessee Valley Authority.

Description of project:

TVA is a wholly-owned U.S. government corporation and the nation's 
largest public power system. It was created to develop the resources of 
the Tennessee Valley region in order to strengthen the regional and 
national economy and national defense by providing (1) an ample supply 
of power within the region, (2) navigable channels and flood control 
for the Tennessee River System, and (3) agricultural and industrial 
development and improved forestry in the region. TVA's operations have 
typically been divided into the power and nonpower programs. 
Substantially all TVA revenues and assets are attributable to the power 
program. TVA is authorized to issue debt and has primarily financed its 
capital construction by selling bonds and notes to the public. TVA's 
power program is required to be self-supporting from power revenues and 
the issuance of debt.

Description of financing approach:

During the Korean War and the late 1950s, Congress cut back on public 
funding for TVA, and in 1959 Congress authorized TVA to sell bonds on 
the public markets so that it could finance its own power operations. 
TVA has been working to reduce its debt by buying back its bonds. TVA 
has reduced its debt balance from $27.7 billion in 1997 to about $25 
billion in 2002 through the exchange of lower interest bonds for 
outstanding higher interest bonds and redeeming other outstanding 
bonds. TVA continues to buy back its bonds. TVA's borrowing authority 
is limited to $30 billion.

Benefits claimed:

The ability to issue bonds allowed TVA's power system to operate as a 
business, made it responsible for its own financial operations, and 
freed the power operations from dependence on congressional 
appropriations. TVA bonds are backed solely by the revenues of the TVA 
power system; they are not obligations of the U.S. government, nor are 
they guaranteed by the government.

Sources:

Office of Management and Budget, Analytical Perspectives, Budget of the 
United States Government, Fiscal Year 2004.

TVA's Fiscal Year 2002 Annual Report.

(450172):

FOOTNOTES

[1] This amount includes investments in such assets as buildings, 
equipment, and information technology. However, we did not include 
investments in information technology within the scope of this report.

[2] The difference between these two acts and full, up-front funding is 
that the acts apply to individual contracts while full, up-front 
funding applies to a useful segment or an entire project, which may 
involve several contracts. As described by CBO, full funding would 
require budget authority for the construction of a whole ship, even 
though the construction may involve several contracts, while the 
Adequacy of Appropriations and Antideficiency Acts would require budget 
authority for a single contract, for example, to construct the hull of 
the ship.

[3] Because the federal government's financing costs are always less 
than the private sector's, acquiring assets with private sector 
financing may result in a higher cost of capital to the taxpayer.

[4] For more information on this, see U.S. General Accounting Office, 
Budget Issues: Incremental Funding of Capital Asset Acquisitions, GAO-
01-432R (Washington, D.C.: Feb. 26, 2001).

[5] GAO-01-432R.

[6] The $28 million shortfall is expressed in 2002 dollars, the $90 
million shortfall in 2003 dollars, and the $202 million shortfall in 
2004 dollars. The $626 million shortfall is expressed in 2008 dollars.

[7] U.S. General Accounting Office, Budget Scoring: Budget Scoring 
Affects Some Lease Terms, but Full Extent Is Uncertain, GAO-01-929 
(Washington, D.C.: Aug. 31, 2001).

[8] The four land management agencies include the National Park 
Service, Fish and Wildlife Service, Bureau of Land Management, and 
Forest Service. Together, the Park Service and Forest Service collect 
over 90 percent of the fees under the Recreational Fee Demonstration 
Program. In fiscal year 2001, the Park Service collected $126 million 
and the Forest Service collected $35 million.

[9] The Phillip Burton Federal Building was built in 1962. GSA owns and 
manages the building, which houses several agencies. 

[10] 101ST Congress, HR 5241, 1991 Treasury, Postal Service and General 
Government appropriations bill.

[11] Public private partnerships take a variety of forms. In addition 
to some of the partnerships described in this section, other types of 
partnerships might include outleases of real property and share-in-
savings contracts. These partnerships are described in greater detail 
in other sections.

[12] A legal instrument used to release one party's right, title, or 
interest to another without providing a guarantee or warranty of title. 

[13] The National Historic Preservation Act authorizes agencies to 
lease or exchange federal historic properties and retain the proceeds 
to defray the costs of maintaining other federal historic properties. 
The Public Buildings Cooperative Use Act encourages the government to 
develop the highest and best use of pedestrian access areas to federal 
facilities.

[14] The Department of Defense is authorized to retain two-thirds of 
the amount of savings realized from contracted services for energy or 
water conservation. DOD contracts do not tie the amount of payment to 
the contractor to the amount of savings realized as a result of the 
contract activity.

[15] Consumption standards were defined in the Energy Policy Act of 
1992 and then updated in Executive Orders 12902 and 13123.

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: