USACE / NAVFAC / AFCESA / NASA UFGS-02331 (August 2004)
------------------------
Preparing Activity:
USACE (CW)
MasterFormatTM 2004 - 35 41 00
Superseding
UFGS-02331A (July 2004)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated 23 June 2005
Latest change indicated by CHG tags
Section Table of Contents
02331
LEVEE CONSTRUCTION
08/04
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Clearing
1.2.2 Grubbing
1.2.3 Stripping
1.2.4 Satisfactory Materials
1.2.5 Unsatisfactory Materials
1.2.6 Embankment
1.2.7 Backfill
1.2.8 Excavation
1.2.9 Classification of Soils
1.2.10 Degree of Compaction
1.2.10.1 Cohesive Material
1.2.10.2 Cohesionless Material
1.3 SUBMITTALS
1.4 [LUMP SUM] [UNIT] PRICES
1.4.1 Clearing, Grubbing, and Stripping
1.4.1.1 Payment
1.4.1.2 [Measurement
1.4.1.3 Unit of Measure
1.4.2 Excavation
1.4.2.1 [Payment
1.4.2.2 [Measurement
1.4.2.3 [Unit of Measure
1.4.3 Fill Material
1.4.3.1 Payment For Embankment Fill
1.4.3.2 Measurement of Fill Material
1.4.3.3 Unit of Measure
1.4.4 Mortar and Concrete
1.4.4.1 Payment
1.4.4.2 Measurement
1.4.4.3 Unit of Measure
1.4.5 [Settlement Gages
1.4.6 [Core Borings Utilized to Measure Foundation Settlement
1.5 SYSTEM DESCRIPTION
1.6 GENERAL CONDITIONS
1.6.1 Lines and Grades
1.6.2 Conduct of the Work
1.6.3 Embankment and Backfill Materials
1.6.4 Haul Roads
1.6.5 Ramps and Crossings
1.6.6 Runways
1.6.7 Closure of Runways
1.6.8 Stockpiling
1.6.9 Slides and Foundation Failures
1.6.10 Drainage Requirements
1.7 REGULATORY REQUIREMENTS
1.8 PERMITS
1.9 PROJECT SITE CONDITIONS
1.9.1 Protection of Cultural and Natural Resources
1.9.2 Protection of Man-Made Facilities and Natural Features
1.9.3 Historical, Archeological, and Cultural Resources
1.9.4 Subsurface Data
1.10 MERCHANTABLE TIMBER
1.11 SEQUENCE OF WORK
1.11.1 Clearing and Grubbing
1.11.2 Stripping
PART 2 PRODUCTS
2.1 HAUL ROAD MATERIALS
2.2 TYPES OF FILL MATERIALS
2.2.1 [Select Fill
2.2.2 [Impervious Fill
2.2.3 [Pervious Fill
2.2.4 [Random Fill
2.2.5 Random Rock
2.2.6 [Coarse Drainage Gravel
2.2.7 [Fine Drainage Gravel
2.2.8 [Filter Sand
2.2.9 [Bedding
2.2.10 [Topsoil
2.2.11 [Semicompacted Fill
2.2.12 [Uncompacted Fill
2.2.13 [Hydraulic Fill for Berms and Depressed Areas
2.3 [MANUFACTURED PRODUCTS
2.4 GROUTS AND DENTAL CONCRETE
2.5 [STABILIZERS
2.6 SETTLEMENT GAGES
PART 3 EXECUTION
3.1 CLEARING
3.2 GRUBBING
3.3 STRIPPING
3.4 DISPOSITION OF CLEARED, GRUBBED, AND STRIPPED MATERIAL
3.4.1 Windrows
3.4.2 Burning
3.4.3 Burying
3.4.4 Chipping
3.4.5 Removal from Site of Work
3.5 REMOVAL OR PLUGGING OF ABANDONED PIPE AND CONDUITS
3.6 SHORING, SHEETING, AND BRACING
3.7 DEWATERING AND DIVERSION
3.8 EXCAVATION
3.8.1 Over Excavation
3.8.1.1 Outside Limits of Levee Foundations or Structures
3.8.1.2 Within Limits of Levee Foundations or Structures
3.8.2 Inspection Trench
3.8.3 Structures
3.8.4 Channels
3.8.5 Ditches
3.8.6 Slopes and Surcharges
3.8.7 Borrow Areas
3.8.7.1 Government-Furnished
3.8.7.2 Contractor-Furnished
3.8.7.3 Dredged
3.8.8 Cut-Off Trenches
3.8.9 Existing Levees and Spoil Banks
3.8.10 Toe Drains
3.8.11 Utilities
3.8.12 Rock
3.8.13 Riprap and Bedding
3.9 TOLERANCES
3.10 SLIDES
3.11 TRAVERSES
3.12 STOCKPILES
3.13 SURFACE DRAINAGE OF COMPLETED AREAS
3.14 MAINTENANCE OF WORK
3.14.1 Debris Removal
3.14.2 Sediment Removal
3.15 DISPOSITION OF EXCAVATED MATERIALS
3.15.1 Satisfactory Materials
3.15.2 Unsatisfactory Materials
3.16 PREPARATION OF FOUNDATION, PARTIAL FILL SURFACES AND ABUTMENTS
3.16.1 Earth
3.16.2 Rock Foundation
3.16.3 [Benching
3.16.4 [Preloading
3.16.5 [Settlement of Foundation
3.17 [TEST FILL STRIPS]
3.17.1 [General
3.17.2 [Testing and Reporting Requirements for Test Strips
3.18 PLACEMENT AND SPREADING
3.18.1 General
3.18.1.1 Gradation and Distribution
3.18.1.2 Foundations and Partial Embankment Fills
3.18.1.3 Equipment Traffic
3.18.2 Placement on Surfaces Containing Frozen Materials
3.18.3 Placement of Embankment and Backfill Against Rock
3.18.4 Placement of Embankment and Backfill Against Structures
3.18.5 Select Fill
3.18.6 Coarse Drainage Gravel and Filter Sand
3.18.7 Impervious Fill
3.18.8 Pervious Fill
3.18.9 Random Fill
3.18.10 [Random Rock
3.18.11 [Fine Drainage Gravel Placed Around Structures
3.18.12 [Semicompacted Fill
3.18.13 [Uncompacted Fill
3.18.14 Hydraulic Fill
3.18.14.1 Discharge Pipe
3.18.14.2 Discharge Pipe Outlets
3.18.14.3 Control of Materials in Hydraulic Construction
3.18.14.4 Rehandling Hydraulic Material
3.19 MOISTURE CONTROL
3.19.1 General
3.19.1.1 Insufficient Moisture for Suitable Bond
3.19.1.2 Excessive Moisture for Suitable Bond
3.19.1.3 Drying Wet Material
3.19.1.4 Increasing Moisture in Dry Material
3.19.2 Select Fill
3.19.3 Impervious Fill
3.19.4 Pervious Fill
3.19.5 Random Fill
3.19.6 Coarse Drainage Gravel and Filter Sand
3.19.7 Fine Drainage Gravel
3.19.8 Semicompacted Fill
3.19.9 Uncompacted Fill
3.19.10 Hydraulic Fill
3.20 COMPACTION
3.20.1 Compaction Equipment
3.20.1.1 Tamping Rollers
3.20.1.2 Vibratory Rollers
3.20.1.3 Rubber-tired Rollers
3.20.1.4 Hand Operated Compactors
3.20.1.5 Crawler-type Tractors
3.20.1.6 Sprinkling Equipment
3.20.1.7 Miscellaneous Equipment
3.20.2 Compaction of Select Fill
3.20.3 Compaction of Random Fill
3.20.4 Compaction of Impervious Fill
3.20.5 Compaction of Pervious Fill
3.20.6 [Compaction of Random Rock]
3.20.7 Compaction of Semicompacted Fill
3.20.8 Compaction of Uncompacted Fill
3.20.9 Compaction of Hydraulic Fill
3.20.10 [Compaction of Random Fill Within the MSE Walls
3.20.11 Compaction of Coarse Drainage Gravel and Filter Sand
3.20.12 Compaction of Fine Drainage Gravel
3.20.13 Compaction Adjacent to Structures and Utilities
3.20.14 [Additional Rolling for Compaction
3.20.15 [Topsoil
3.21 FIELD QUALITY CONTROL
3.21.1 Clearing, Grubbing, and Stripping
3.21.1.1 Clearing
3.21.1.2 Grubbing
3.21.1.3 Stripping
3.21.2 Excavation
3.21.3 Embankment
3.21.3.1 General
3.21.3.2 Materials Testing
3.21.3.3 Materials
3.21.3.4 Fill Placement
3.21.3.5 Grade and Cross Section
3.21.3.6 Testing by the Government
3.21.3.7 Reporting
02331
LEVEE CONSTRUCTION
NOTE: This guide specification covers the requirements for levee construction
.
Comments and suggestions on this guide specification are welcome and should
be directed to the technical proponent of the specification. A listing of
technical
proponents, including their organization designation and telephone number, is
on the Internet.
Recommended changes to a UFGS should be submitted as a
Criteria Change Request
(CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer choices or locations where
text must be supplied by the designer.
This Guide Specification includes tailoring options, as listed below, for specific
construction requirements. Tailoring tags should be selected based upon project
requirements; i.e., if the proposed project requires only embankments for levee
construction, select only the tailoring option for embankment (TAI OPT=EMBANK);
if the proposed project requires clearing, grubbing, stripping, and excavation
for levee construction, select tailoring options for these requirements (TAI
OPT=CLEAR-GRUB-STRIP, TAI OPT=EXCAV), etc.
TAI OPT=CLEAR-GRUB-STRIP CLEARING, GRUBBING,
AND STRIPPING
TAI OPT=EXCAVAT EXCAVATION
TAI OPT=EMBANK EMBANKMENT
PART 1 GENERAL
NOTE:
This guide specification provides for the installation of settlement
gages for the determination of increases in quantities of embankment materials
resulting from settlement of the embankment foundation during construction and
for payment to the Contractor for such increases in quantities. These provisions
will be included in a project specification when it is determined that settlement
in the range of 5 percent or more of the planned embankment height is anticipated
over a considerable portion of the embankment foundation area. They will also
be used when gages are needed for engineering control purposes. When settlement
gages are to be used the following information will be indicated on the plans:
1. The location of the gages as well as the stations at which zero settlement
will be assumed.
2. The detail construction of the foundation settlement gages to be used.
Any applicable type of gage may be selected.
The requirements for rock as prescribed herein are intended to be used on embankments
involving rock fill sections. Where rock for slope protection is specified,
UFGS-02380A STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR STRUCTURES should
be used.
Approval of testing laboratory is addressed in ER 1110-1-8100, dated 31 Dec
1997, Laboratory Investigations and Testing.
1.1 REFERENCES
NOTE: This paragraph is used to list the publications cited in the text of
the guide specification. The publications are referred to in the text by basic
designation only and listed in this paragraph by organization, designation,
date, and title.
Use the Reference Wizard's Check Reference feature when you add a RID outside
of the Section's Reference Article to automatically place the reference in the
Reference Article. Also use the Reference Wizard's Check Reference feature
to update the issue dates.
References not used in the text will automatically be deleted from this section
of the project specification when you choose to reconcile references in the
publish print process.
The publications listed below form a part of this specification to the extent referenced. The publications are
referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) |
|
AASHTO M 43 | | (1988; R 2003) Sizes of Aggregate for Road and
Bridge Construction |
ASTM INTERNATIONAL (ASTM) |
|
ASTM C 33 | | (2003) Concrete Aggregates |
|
ASTM D 1556 | | (2000) Density and Unit Weight of Soil in Place
by the Sand-Cone Method |
|
ASTM D 1557 | | (2002e1) Laboratory Compaction Characteristics
of Soil Using Modified Effort (56,000 ft-lbf/cu.
ft. (2,700 kN-m/cu.m.)) |
|
ASTM D 2167 | | (1994; R 2001) Density and Unit Weight of Soil
in Place by the Rubber Balloon Method |
|
ASTM D 2216 | | (1998) Laboratory Determination of Water (Moisture)
Content of Soil and Rock by Mass |
|
ASTM D 2487 | | (2000) Soils for Engineering Purposes (Unified
Soil Classification System) |
|
ASTM D 2922 | | (2004) Density of Soil and Soil-Aggregate in
Place by Nuclear Methods (Shallow Depth) |
|
ASTM D 2937 | | (2000e1) Density of Soil in Place by the Drive-Cylinder
Method |
|
ASTM D 3017 | | (2004) Water Content of Soil and Rock in Place
by Nuclear Methods (Shallow Depth) |
|
ASTM D 422 | | (1963; R 2002) Particle-Size Analysis of Soils |
|
ASTM D 4253 | | (2000) Maximum Index Density and Unit Weight
of Soils Using a Vibratory Table |
|
ASTM D 4254 | | (2000) Minimum Index Density and Unit Weight
of Soils and Calculation of Relative Density |
|
ASTM D 4318 | | (2000) Liquid Limit, Plastic Limit, and Plasticity
Index of Soils |
|
ASTM D 4643 | | (2000) Determination of Water (Moisture) Content
of Soil by the Microwave Oven Method |
|
ASTM D 5195 | | (2002) Density of Soil and Rock In-Place at
Depths Below the Surface by Nuclear Methods |
|
ASTM D 698 | | (2000ae1) Laboratory Compaction Characteristics
of Soil Using Standard Effort (12,400 ft-lbf/cu.
ft. (600 kN-m/cu. m.)) |
U.S. ARMY CORPS OF ENGINEERS (USACE) |
|
EM 385-1-1 | | (2003) Safety -- Safety and Health Requirements |
1.2 DEFINITIONS
NOTE: Add applicable definitions.
1.2.1 Clearing
Clearing shall consist of the removal and satisfactory disposal of all [above ground and below ground ]trees,
downed timber, snags, slash, brush, garbage, trash, debris, fencing, and other items occurring in the designated
areas to be cleared.
1.2.2 Grubbing
Grubbing shall consist of the removal and satisfactory disposal of stumps, roots larger than [_____] mm inches
in diameter, and matted roots from the designated grubbing areas. Grubbing also includes filling of holes from
the grubbing operation.
1.2.3 Stripping
Stripping shall consist of the removal and satisfactory disposal of crops, weeds, grass, and other vegetative
materials to the ground surface[ and topsoil to a depth of [_____] mm inches].
1.2.4 Satisfactory Materials
NOTE: Use of CH material should be avoided if possible. As a minimum, constraints
should be set governing their use.
Satisfactory materials shall consist of materials classified in accordance with ASTM D 2487 as CL,[ CH,] CL-ML,
ML, SC, SP, SW, [_____] free from: roots and other organic matter; contamination from hazardous, toxic or radiological
substances; trash, debris; and frozen materials. Not all satisfactory materials can be used in levee. Only
the satisfactory materials stated above, meeting the additional or modified requirements of paragraph TYPES
OF FILL MATERIALS, can be used for levee construction.
1.2.5 Unsatisfactory Materials
Unsatisfactory materials shall not be used in any levee or other required fill. Unsatisfactory materials includes
all other materials that are not defined above as satisfactory materials.
1.2.6 Embankment
The terms "levee" or "embankment" as used in these specifications are defined as the earth [and rock ]fill portions
of the levee structure or other fills related to the levee structure, including [cut-off trench] and includes
all types of earth fill [and filter materials ]for the levee [and cut-off trench,] and all other fills within
the limits of the levee [, excepting those stone and filter materials used for slope protection, which are described
in paragraph [_____]].
1.2.7 Backfill
Backfill as used in this section is defined as that fill material which cannot be placed around or adjacent to
a structure until the structure is completed or until a specified time interval has elapsed after completion.
1.2.8 Excavation
Excavation shall consist of removal of material to the lines and grades shown on the drawings, or as otherwise
directed or approved by the Contracting Officer and as described in paragraph [_____] EXCAVATION in PART 3 EXECUTION.
1.2.9 Classification of Soils
Materials used to construct the embankments and for backfills shall be classified in accordance with ASTM D 2487
(Unified Soil Classification System). Cohesionless materials shall include materials classified in ASTM D 2487
as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials
classified as GM and SM will be identified as cohesionless only when the fines are nonplastic.
1.2.10 Degree of Compaction
1.2.10.1 Cohesive Material
Note: If a higher compactive effort than is attainable by ASTM D 698 is desired
ASTM D 1557 may be utilized and references to ASTM D 698, relative to compactive
effort, should be changed to ASTM D 1557.
Degree of compaction shall be expressed as a percentage of the maximum density obtained by the test procedure
presented in [ASTM D 698] [ASTM D 1557], abbreviated hereinafter as percent laboratory maximum density.
1.2.10.2 Cohesionless Material
Note: Factors such as (but not limited to) site specific materials, availability
of testing equipment and local practice may make it more practical to utilize
methods other than ASTM D 4253 and ASTM D 4254 to control the degree of compaction
of cohesionless material. If other methods are utilized the appropriate sections
of the specifications should be modified to reflect method selected. The other
methods used include comparison of in-place density to either the maximum Proctor
density or the maximum density obtained by ASTM 4253 (if vibratory table is
available).
Degree of compaction shall be expressed as a percentage of the relative density in accordance with ASTM D 4253
and ASTM D 4254.
1.3 SUBMITTALS
NOTE: Review submittal description (SD) definitions in Section 01330 SUBMITTAL
PROCEDURES and edit the following list to reflect only the submittals required
for the project. Submittals should be kept to the minimum required for adequate
quality control.
A “G” following a submittal item indicates that the submittal requires Government
approval. Some submittals are already marked with a “G”. Only delete an existing
“G” if the submittal item is not complex and can be reviewed through the Contractor’s
Quality Control system. Only add a “G” if the submittal is sufficiently important
or complex in context of the project.
For submittals requiring Government approval on Army projects, a code of up
to three characters within the submittal tags may be used following the "G"
designation to indicate the approving authority. Codes for Army projects using
the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other organization in the District
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project
Office. Codes following the "G" typically are not used for Navy, Air Force,
and NASA projects.
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose
the second bracketed item for Army projects.
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation
are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the Government.] The following shall be
submitted in accordance with Section
01330
01330
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Drainage Requirements
Written evidence consisting of an authenticated copy of the [conveyance] [easement] under
which the Contractor acquired the property rights and access thereto, prepared and executed
in accordance with applicable State and local requirements.
SD-03 Product Data
Shoring, Sheeting, and Bracing[; G][; G, [_____]]
NOTE: Add applicable minimum requirements for the shoring, sheeting and bracing
plan based upon site specific conditions.
Submit a detailed shoring, sheeting and bracing plan [_____] days prior to the beginning of
any excavation so supported. The plan for shoring, sheeting and bracing shall be prepared and
certified by licensed professional engineer. The plan shall include drawings and design computations
of the proposed shoring, sheeting, and bracing, and documentation, showing details of the coordination
and approval of shoring, sheeting, and bracing by the applicable parties. Approval of the detailed
plan shall be obtained from the Contracting Officer prior to starting the work. If necessary,
the plan shall be modified as required to meet field conditions, and the modifications shall
be approved prior to use.
Excavation[; G][; G, [_____]]
Submit a written excavation plan [_____] days prior to the beginning of any excavation. Approval
of the detailed plan shall be obtained from the Contracting Officer prior to starting the work.
If necessary, the plan shall be modified as required to meet field conditions, and the modifications
shall be approved prior to use. As a minimum, the plan shall contain, the following:
a. Proposed methods for preventing interference with, or damage to, existing underground or
overhead utility lines, trees designated to remain and other man-made facilities or natural
features designated to remain within or adjacent to the construction rights-of-way.
b. Provision for coordinating the work with other Contractors working in the construction rights-of-way
or on facilities crossing or adjacent to this work.
c. The proposed methods for controlling surface and ground water in the borrow areas and required
excavations.
d. Stockpiling plan for embankment material before it is transported to the project site showing
locations, stockpile heights, slopes, limits, and drainage around the stockpile areas.
e. A complete listing of equipment used for excavation and to transport the excavated material.
f. The Contractor's proposed sequence of work for excavating the borrow areas with plan and
cross sectional views showing starting and final work locations and clearing, grubbing and stripping
limits.
g. The Contractor's proposals for conserving arable land and for making optimum use of available
borrow, including the Contractor's proposed methods for grading the bottom of the borrow areas
after completing use of the borrow areas.
h. The Contractor's proposed road pattern, and plan for implementing dust control measures.
Borrow Areas[; G][; G, [_____]]
Submit a written statement to the Government not later than [_____] days after receipt of
Notice to Proceed indicating the Contractor's intention to use the specified Government-furnished
borrow area(s), Contractor-furnished borrow area(s), dredged borrow areas, or a combination
of these borrow areas.
Plan of Operations[; G][; G, [_____]]
NOTE: Tie this back to Section 01451A ContractorR QUALITY CONTROL requirement
for inspection and validation of CQC laboratories by the government.
Thirty (30) days prior to commencement of haul road construction or placing embankment and
backfill which ever is earlier, the Contractor shall submit for approval a Plan of Operations
for accomplishing all embankment and backfill construction and for the location and construction
of haul roads. This plan shall include but not be limited to the Contractor's proposed sequence
of construction for embankment and backfill items, and methods and types of equipment to be
utilized for all embankment and backfill operations, including transporting, placing, and compaction.
This plan shall also include the names and addresses of the [commercial testing labs] [engineering
firms] which will perform the soil testing and inspection and describe how all required soils
testing will be performed.
[Embankment and Backfill Materials[; G][; G, [_____]]
. At least [30] [_____] days prior to delivery of any Contractor-furnished material to the site
of the work, the Contractor shall submit soil classification test results, moisture-density
curves, gradation curves, and laboratory results of the required tests of the proposed material.]
[Filter Sand[; G][; G, [_____]]
At least [30] [_____] days prior to delivery of any Contractor-furnished material to the site
of the work, the Contractor shall submit soil classification test results and a gradation curve
for each of the proposed filter materials to be used.]
[Nuclear Density[; G][; G, [_____]]
Nuclear density testing equipment shall be used in accordance with ASTM D 2922 and ASTM D 3017
. In addition, the following condition shall apply:
a. Prior to using the nuclear density testing equipment on the site, the Contractor shall submit
to the Contracting Officer a certification that the operator has completed a training course
approved by the nuclear density testing equipment manufacturer[, the most recent data sheet
from the manufacturer's calibration, and a copy of the most recent statistical check of the
standard count precision].
b. The nuclear density testing equipment shall be capable of extending a probe a minimum of
150 mm 6 inches down into a hole.]
SD-06 Test Reports
Measurement of Fill Material[; G][; G, [_____]]
Submit a copy of the records of each compliance survey the next work day following the survey.
1.4 [LUMP SUM] [UNIT] PRICES
NOTE: If Section 01270A MEASUREMENT AND PAYMENT is included in the project
specifications, this paragraph title ([LUMP SUM] [UNIT] PRICE) should be deleted
from this section and the remaining appropriately edited subparagraphs below
should be inserted into Section 01270.
1.4.1 Clearing, Grubbing, and Stripping
1.4.1.1 Payment
Payment will be made for clearing, grubbing and stripping at the contract [lump sum] [unit price] for clearing,
grubbing and stripping. This price shall constitute full compensation for all equipment, labor, materials and
incidentals necessary to complete the work specified herein. Payment for refilling of holes resulting from grubbing
[and removal or plugging of existing drainage structures] will be included in the contract [lump sum] [unit price]
for clearing, grubbing and stripping. No separate or direct payment will be made for stockpiling and disposition
of stripped materials. All costs in connection therewith will be considered as a subsidiary obligation of the
Contractor. If regrowth of vegetation or trees occurs after clearing and grubbing and before placement of embankment,
and the Contractor is required to clear and grub again prior to embankment construction, no payment will be made
for this additional clearing and grubbing.
1.4.1.2 [Measurement
Note: If clearing, grubbing, and stripping is to be paid for with a unit price
bid item include the method of measurement. Delete this paragraph if payment
is by lump sum.
[Clearing, grubbing, stripping, stockpiling and the disposition of the materials from these operations[ and plugging
or removal of existing drainage structures] will not be measured for payment.] Refilling of grubbing holes will
not be measured for payment.]
1.4.1.3 Unit of Measure
Unit of measure: [lump sum] [unit price].
1.4.2 Excavation
NOTE: If excavation will not be measured or paid for separately, select the
following paragraph and delete subparagraphs PAYMENT, MEASUREMENT, and UNIT
OF MEASURE. Delete the following paragraph if excavation is to be measured
and paid for separately. If significant quantities of rock excavation is anticipated
measurement and payment for rock excavation should be addressed separately.
A definition of rock excavation should also be included.
[No separate measurement or payment will be made for Excavation. All costs in connection with excavation will
be considered a subsidiary obligation of the Contractor.]
1.4.2.1 [Payment
Payment will be made for Excavation at the contract unit price which includes full compensation for all equipment,
labor, materials, and incidentals necessary to complete the work specified. No separate payment will be made
for stockpiling.]
1.4.2.2 [Measurement
Excavation will be measured for payment by use of the average end area method. The basis of measurement will
be a survey of the area prior to the excavation[ and clearing and grubbing] and a second survey of the same area
after the completion of the excavation. For areas where lines and grades are shown on the drawings, measurement
will be limited to those lines and grades. Slides caused by fault of the Contractor, over excavation, and excavation
performed for the convenience of the Contractor shall not be measured for payment.]
1.4.2.3 [Unit of Measure
Unit of measure: cubic meters yards.]
1.4.3 Fill Material
1.4.3.1 Payment For Embankment Fill
Payment will be made for material placed as required in embankments, backfills and ramps, and including additional
material placed by reason of foundation settlement and by reason of soft material in the foundation being forced
outward from the section during construction, for [Embankment Material Type [____],] [Semicompacted Fill] [Uncompacted
Fill] [Hydraulic Fill]. Payment shall constitute full compensation for furnishing all plant, labor, equipment
and material, [except earth material, ]and performing all operations necessary for foundation preparation and
placing and compacting the material [, materials testing,] [and moisture control]. [This payment is in addition
to any payment for excavating and transporting of the material as required in paragraph [_____] EXCAVATION.]
[ When directed to perform additional rolling for compaction, it will be paid for under the unit price item for
additional rolling for compaction.]
1.4.3.2 Measurement of Fill Material
NOTE: The last sentence of the following paragraph (in brackets) should be
deleted if surveys are taken "after" clearing and grubbing operations. The
last sentence should be included if surveys are taken "prior" to clearing and
grubbing operations.
a. Fill materials specified for embankment will be measured for payment by the cubic meter yard, and
quantities will be determined by the average end area method. The basis for measurement will be cross
sections of the areas to be filled taken [prior to] [after] clearing, grubbing, and stripping operations
and the [theoretical cross sections] [actual cross sections] of the embankments constructed within the
specified tolerance[ plus additional fill placed as the result of displacement or settlement of foundation
material as calculated below].[ Cross sections shall be performed at significant breaks in grade except
that the maximum distance between cross sections shall not exceed [_____] meters feet.] Embankments
not constructed to design grade and section including allowable tolerance as indicated on the Contractor's
compliance survey will not be accepted.[ Volumes occupied by drainage structures will not be included
in measurement of embankment for payment.] [ Material removed as a result of the clearing, grubbing,
and stripping operations will not be included in measurement of embankment for payment.]
b. The basis for measurement of fill placed by reason of soft material in the foundation being forced
outward from the section will be a survey of the area taken prior to fill placement and a second survey
of the same area after completion of fill placement. The cross sections will extend [_____] meters feet
beyond the toes of the fills.[ A cross section will be taken at each settlement measurement location.]
NOTE: The engineer can select one of the two methods of settlement measurement
as described below; one based on using settlement gages, and the other based
on using core borings. Core borings should only be used when the embankment
material and the foundation material are easily distinguishable such that the
interface between the embankment and foundation can be easily located.
c. Levee Settlement. Measurement of additional fill material placed in each settlement measurement
range, shown on the drawings by reason of foundation settlement, will be based on measurements [taken
on the respective settlement gage] [obtained from the respective core borings] at the respective settlement
measurement locations as specified and will be determined as follows:
(1) The settlement measured at each settlement measurement location will be considered to apply
to the foundation area throughout the length of the settlement ranges shown on the drawings.
(2) The foundation settlement under the embankment at each transverse cross section within
a settlement range will be considered to vary uniformly between break points in the cross section.
(3) At each breakpoint, the settlement allowance will be based upon the proportion that the
specified fill height at the break point bears to the specified fill height at the settlement
measurement locations, in accordance with the following formula.
(4) Symbols used in the formula and the break points are [shown on a typical settlement cross
section on the drawing] [included in these specifications].
S = h X sm/hm, where
S = settlement to be computed at a break point;
h = specified gross fill height at S;
sm = measured or adjusted vertical change at settlement
measurement location ;
hm = specified gross fill height at settlement
measurement location.
d. Forfeiture of Payment for Settlement of Foundation. Failure to utilize settlement gages in strict
accordance with the specifications and drawings will result in total forfeiture of any payment which
will otherwise be due the Contractor for settlement of the foundation. Payment for settlement of the
foundation will be totally forfeited for the reach attributable to the each settlement measurement location
in each case for the following reasons: embankment over a settlement measurement location is constructed
to a height in excess of the specified construction lines plus the tolerance permitted; settlement plates
have been set and cannot be found after completion of the embankment; failure to take the settlement
measurement within [_____] hours after the final cross sections have been taken over the completed embankment.
1.4.3.3 Unit of Measure
Unit of measure: cubic meters yards.
1.4.4 Mortar and Concrete
1.4.4.1 Payment
Payment will be made for costs associated with mortar and concrete used in foundation and abutment preparation,
which includes full compensation for furnishing all labor, equipment, material, and incidentals, and performing
all operations necessary for placement of concrete and mortar for foundation and abutment preparation.
1.4.4.2 Measurement
Mortar and concrete used in filling spaces beneath rock overhangs and around protrusions will be measured for
payment as the actual volumes of such mortar and concrete in cubic meters yards as determined by field surveys
made before and after placement of the mortar and concrete.[ No measurement will be made for the mortar used
in filling the open joints and cracks in the rock surface.][ Measurement of mortar or concrete used in filling
the open joints and cracks in the rock surface will be made by the square meter yard based on the horizontal
projection of the area obtained from a survey performed before application.][ Measurement of mortar or concrete
used in filling the open joints and cracks in the rock surface will be the bags of cement used.]
1.4.4.3 Unit of Measure
Unit of measure: cubic meters yards.
1.4.5 [Settlement Gages
No separate payment will be made for furnishing, installing, and maintaining settlement gages during embankment
construction as specified herein, if used, including measurements required to be made by the Contractor, and
shall be at the expense of the Contractor. No separate payment will be made for compaction of fill around and
over the settlement gages or for interference with the Contractor's operations resulting from the settlement
gage installations.]
1.4.6 [Core Borings Utilized to Measure Foundation Settlement
No separate payment will be made for core borings performed for measurement of foundation settlement and shall
be at the expense of the Contractor.]
1.5 SYSTEM DESCRIPTION
The work covered by this section consists of furnishing all equipment, labor, materials, and incidentals, and
performing all operations necessary for
the clearing, grubbing, and stripping of the areas specified herein or
indicated on the drawings, and for the removal and disposal of cleared, grubbed, and stripped materials,[ removal
or plugging of existing drainage structures,] and refilling of holes resulting from grubbing; excavation of borrow
areas [and existing levees,] and for all other excavations incidental to the construction of levees[, channels]
[, ditches] [, structures] [, and ponding areas] as specified and shown; foundation preparation and the construction
of levee embankments, including new levee, enlargement of existing levee, backfill of inspection trenches, cutoff
trenches, berms, road crossings, backfill at drainage structures, and other incidental earthwork as may be necessary
to complete the levee as specified herein and as shown on the drawings. All work under this section shall comply
with the requirements of
EM 385-1-1.
1.6 GENERAL CONDITIONS
1.6.1 Lines and Grades
The embankment and backfill shall be constructed to the lines, grades, and cross sections indicated on the drawings,
unless otherwise directed by the Contracting Officer. The Government reserves the right to increase or decrease
the foundation widths and embankment slopes or to make such other changes in the embankment or backfill sections
as may be deemed necessary to produce a safe structure. Changes in quantities resulting from such revisions
will not constitute justification for change in contract unit prices, except as provided for in the Variations
in Estimated Quantities Clause. Increases in height of section, made to compensate for settlement or consolidation
of the embankment material subsequent to the completion of the embankment, will not exceed [_____] percent of
the height above the foundation at the levee centerline indicated. The end slopes and side slopes of partial
fill sections shall not be steeper than [one vertical on [____] horizontal] [, unless otherwise shown on the
drawings].
1.6.2 Conduct of the Work
The Contractor shall maintain and protect the embankment and backfill in a satisfactory condition at all times
until final completion and acceptance of all work under the Contract.[ If, in the opinion of the Contracting
Officer, the hauling equipment causes horizontal shear planes or slicken sides, rutting, quaking, heaving, cracking,
or excessive deformation of the embankment or backfill, the Contractor shall limit the type, load, or travel
speed of the hauling equipment on the embankment or backfill.] The Contractor may be required to remove, at
his own expense, any embankment material placed outside of prescribed slope lines. Any approved embankment or
backfill material which is lost in transit or rendered unsuitable after being placed in the embankment or backfill
and before final acceptance of the work shall be replaced by the Contractor in a satisfactory manner and no additional
payment will be made therefor. The Contractor shall excavate and remove from the embankment or backfill any
material which is unsatisfactory and shall also dispose of such material and refill the excavated area as directed,
all at no cost to the Government.
1.6.3 Embankment and Backfill Materials
NOTE: All available sources of materials for embankment and backfill should
be designated.
Materials for embankment and backfill construction will be obtained from [the borrow sources] [sources provided
by the Contractor] [required excavation]. Materials obtained from required excavation which meet or which can
be processed to meet the requirements for each embankment material, or any other material required for this project,
as specified herein, may be utilized [in the appropriate zone of] [in] the embankment or as backfill. All roots,
limbs, and wood fragments shall be removed from embankment materials. Materials containing sod, other organic
or perishable material, trash, debris, and frozen materials shall not be used in the embankment. The Contractor
shall submit to the Contracting Officer the source or sources from which he intends to obtain materials for embankment
construction. If a source is selected other than a commercial quarry or other commercial entity from which earth
or rock material will be directly purchased and where the Contractor or his subContractor will perform the borrow
excavation, a written statement will be provided to the Contracting Officer indicating permission to utilize
the area. It shall be the responsibility of the Contractor to obtain Federal, State, and local permits which
may be required for excavation and reclamation of the borrow area. A copy of the plan and procedures to be utilized
for reclamation shall be furnished to the Contracting Officer as required in SECTION [_____], paragraph [_____].
The Contracting Officer will require material samples from any proposed borrow source to be submitted as indicated
in paragraph Quality Control.
1.6.4 Haul Roads
NOTE: Haul roads are highly project specific. Contractor should be given as
much latitude as feasible to determine his traffic patterns. Haul roads must
be safe, not interfere with public traffic, environmentally friendly and generally
must be restored to preconstruction conditions.
Haul roads shall be located and constructed [as shown on the drawings and] [as] [approved by the Contracting
Officer] [within the project boundaries shown on the drawings].[ Prior to the commencement of construction the
Contractor shall submit for approval a site plan detailing the location of all haul roads within the project
limits.] [ Haul road[s] between the borrow site[s] and the levee embankment shall be located within the limits
[shown on the drawings] [approved by the Contracting Officer].] [ The limits of the borrow haul road shall be
clearly marked in the field using construction fencing or similar methods approved by the Contracting Officer.
Areas on each side of the borrow haul road corridor shall not be disturbed.] Haul roads shall be constructed
to maintain the intended traffic, be free draining, and be maintained in good condition throughout the contract
period.[ Any haul road which crosses any creek or drainage channel shall be constructed, and maintained by the
Contractor so as to not flood either upstream areas by restricting stream flows or flood downstream areas by
the release of any stored water in the event that the crossing fails for any cause.] Haul roads constructed
during the contract duration shall be removed after work is completed and the impacted area restored to its preconstruction
conditions.[ The Contractor shall plow and/or scarify or otherwise loosen all access and haul roads other than
existing roads to a minimum of [_____] mm inches deep and the surface shall be left in a smooth condition.]
All haul roads within the right-of-way that will remain as public thoroughfares after construction shall be cleaned
daily and maintained in the preconstruction condition. All costs associated with these haul roads shall be considered
as a subsidiary obligation of the Contractor.
1.6.5 Ramps and Crossings
Ramps and crossings shall be constructed at the locations shown on the drawings by placement of a fill as specified
in paragraph [_____]. Ramps and crossings shall be constructed only by adding material to the levee crown and
slopes. Ramps shall have a [_____] meter foot crown width, a grade not to exceed [_____] percent, and 1V on
[_____]H side slopes.
1.6.6 Runways
NOTE: Runways are temporary haul roads over a levee.
Where material is hauled over an existing levee for construction, the Contractor at his expense will be permitted
to construct temporary runways over the levee by the addition of material to the levee cross section. For the
construction of runways, if the Contractor so desires, the existing levee may be cut, [but not to exceed a depth
of [_____] meters feet below the crown] [not to exceed [_____] meters feet below the project flowline] [or 100-year
level] [not to excavate below elevation [_____] or one half the height of the levee, whichever is less], and
provided that the cut is made with side slopes not steeper than 1V on 1H, and with a minimum width of haul road
of [_____] [7.6] m [_____] [25] feet for one-way traffic, and [_____] [18.3] m [_____] [60] feet for two-way
traffic. Cutting into the existing levee at intervals of less than [_____] [152] m [_____] [500] linear feet
for the [_____] [7.6]-m [_____] [25]-foot bottom widths or less than [_____] [304] m [_____] [1,000] linear
feet for the [_____] [18.3]-m [_____] [60]-foot bottom widths will not be allowed, and no more than [_____]
runways shall be open at one time. The Contractor shall stockpile, as directed by the Contracting Officer, sufficient
suitable levee embankment material to construct emergency closure of the cuts.
1.6.7 Closure of Runways
Where runways have been cut through the levee, the Contracting Officer reserves the right to order their closure
at no additional cost to the Government at any time that such runways may endanger the security of the levee.
Just prior to restoration of the runway, the bottom of any cut made in the levee shall be broken to a depth of
[_____] [300] mm [_____] [6] inches and the side slopes thoroughly scarified. The restoration shall be made
with suitable embankment material, placed and compacted as provided in paragraph [_____]. Material used in the
construction of the approach ramps of the runways shall be removed and may be used for fill, if satisfactory.
If not used for fill, the material shall be disposed of by placing it in abandoned portions of the borrow areas
or by any other method specified in paragraph disposal of material.[ No section of the levee shall be degraded
or weakened to provide runways nor shall existing runways remain open during the nonwork season described in
[Section
[_____]
[_____]
[_____]] [GENERAL CONTRACT REQUIREMENTS], [paragraph] [Clause] EXCLUSION OF PERIODS IN COMPUTING COMPLETION
SCHEDULES, unless otherwise approved in writing by the Contracting Officer.]
1.6.8 Stockpiling
NOTE: Cost of stockpiling embankment fill material should be included in the
price for placing fill in the levee embankment.
Any on-site stockpiling of embankment materials shall be in accordance with paragraph [_____] Stockpiles.[ No
payment will be made for such stockpiling nor for the reloading and hauling of these materials to their final
position.]
1.6.9 Slides and Foundation Failures
When sliding occurs in any part of the embankment and backfills prescribed in this section after they have been
placed, but prior to final acceptance of all work under the contract, the Contractor shall repair the slide as
directed by the Contracting Officer. When the slide is caused through the fault of the Contractor, the repair
shall be made at no cost to the Government. When the slide is not the fault of the Contractor, an equitable adjustment
in the contract price shall be made pursuant to the Contract Clause CHANGES to cover the cost of the repairs.
1.6.10 Drainage Requirements
NOTE: Modify the following paragraph for specific job conditions such as fill
placed in/under water.
The Contractor shall not block or restrict the flow in a natural drain, existing culvert, ditch or channel at
any time without obtaining prior written approval from the Contracting Officer. This approval shall not relieve
the Contractor from responsibility for any damage caused by his operation. The Contractor shall monitor the
[river] [canal] [stream] flow and provide sufficient free discharge areas so that conditions are not worsened
upstream or downstream by possible floods during construction. Surface water shall be directed away from excavations
and construction sites so as to prevent erosion and undermining of foundations. Diversion ditches, dikes, and
grading shall be provided and maintained as necessary during construction. Excavated slopes and backfill surfaces
shall be protected to prevent erosion and sloughing. Excavation shall be performed so that the site and the
area immediately surrounding the site and affecting operations at the site shall be continually and effectively
drained. If private property is to be used for drainage, submit written evidence that the right has been obtained
from the property owner for drainage on his property.
1.7 REGULATORY REQUIREMENTS
NOTE: Include the applicable state highway department document title in which
an acceptable gradation for the concrete aggregate is presented.
The [state statutory and regulatory requirements] [_____] listed below form a part of this specification to the
extent referenced.
1.8 PERMITS
NOTE: Reference applicable Federal, State and Local permit requirements such
as permits for disposal and hauling of materials, erosion control, burning,
etc. The terms and conditions in any permits and environmental commitments
obtained by the Government must be made a part of the contract. The designer
must include technical requirements necessary to comply with these terms and
commitments.
In accordance with Contract Clause PERMITS AND RESPONSIBILITIES, the Contractor shall obtain all necessary permits
required for disposal, hauling, erosion control, burning, [_____], and pay all fees associated with permitting
and compliance.[ In addition, the Government has obtained permits for storm water discharge[ and [_____]],as
specified in Section
01356A
01356A
01356A STORM WATER POLLUTION PREVENTION MEASURES. The Contractor shall comply with the
terms of these permits and with the requirements of Sections
01355A
01355A
01355A ENVIRONMENTAL PROTECTION, Section
01356A
01356A
01356A
STORM WATER POLLUTION PREVENTION MEASURES, and this section.]
1.9 PROJECT SITE CONDITIONS
1.9.1 Protection of Cultural and Natural Resources
All work and Contractor operations shall comply with the requirements of Section
01355A
01355A
01355A ENVIRONMENTAL PROTECTION
and with the requirements of this section.
1.9.2 Protection of Man-Made Facilities and Natural Features
Trees within the clearing area shall be felled in such a manner as to avoid damage to trees left standing and
trees outside the clearing area, existing buildings, man-made facilities and natural features, with due regard
to the safety of employees and others, and in compliance with EM 385-1-1. Excavation shall follow the same requirements
specified above for felling trees and shall be in compliance with EM 385-1-1. Existing utility lines that are
shown on the drawings or the locations of which are made known to the Contractor prior to excavation and that
are to be retained shall be protected from damage during excavation. When utility lines that are to be removed
are encountered within the area of operations, the Contractor shall notify the applicable utility companies in
sufficient time for measures to be taken to prevent interruption of the services.
1.9.3 Historical, Archeological, and Cultural Resources
Historical, archeological, and cultural resources within the Contractor's work limits [are known to exist] [may
exist]. If, during construction activities, the Contractor observes items that may have historical or archeological
value, such observations shall be reported immediately to the Contracting Officer so that appropriate authorities
may be notified and a determination made as to their significance and what, if any, special disposition of the
finds should be made. The Contractor shall cease all activities that may result in the destruction of these
resources and shall prevent his employees from trespassing on or otherwise damaging such resources.
1.9.4 Subsurface Data
Subsurface soil boring logs are [shown on the drawings] [included in these specifications]. Subsurface investigation
reports and samples of materials obtained from subsurface investigations may be examined at the [_____] District
Office. These data represent subsurface information at the boring locations; however, variations may exist in
the subsurface between boring locations. Groundwater levels indicated on the soil boring logs were levels found
at the time of exploration. The groundwater table can vary significantly depending on time of year, variation
from normal precipitation, and river stage or tide level.
1.10 MERCHANTABLE TIMBER
Merchantable timber remaining within the areas to be cleared on or after the date of award of this contract may
be disposed of as the Contractor sees fit, as long as such merchantable timber is either removed from the rights-of-way
or is satisfactorily disposed of in accordance with the paragraph DISPOSITION OF CLEARED, GRUBBED, AND STRIPPED
MATERIAL
DISPOSITION OF EXCAVATED MATERIAL and the Contractor complies with all applicable State and local regulations
and laws.
1.11 SEQUENCE OF WORK
1.11.1 Clearing and Grubbing
All clearing and grubbing work shall be completed at least [100] [_____] meters [300][_____] feet in advance
of embankment construction.[ In locations where work on drainage structures is performed prior to embankment
construction, all clearing and grubbing shall be completed for the structure at least [_____] meters feet on
each side of the structure, measured along the levee centerline and [_____] meters feet perpendicular to the
structure.] If regrowth of vegetation or trees occurs after clearing and grubbing and before placement of embankment,
the Contractor will be required to clear and grub again prior to embankment construction.
1.11.2 Stripping
After inspection and acceptance of cleared and grubbed areas, stripping may proceed. All stripping work shall
be completed not more than [_____] meters feet in advance of embankment construction.
PART 2 PRODUCTS
NOTE:
After "PART 2 PRODUCTS" above, insert the following "(NOT APPLICABLE)",
if there are no subparagraphs in PART 2. PART 2 material requirements should
be added for contracts in which the Contractor is required to supply materials.
2.1 HAUL ROAD MATERIALS
[_____].
2.2 TYPES OF FILL MATERIALS
NOTE 1: The types of fill materials used for levee construction usually depend
on the availability of materials from required construction excavation and the
nearby borrow sources. The material types listed below as satisfactory materials
are often used in levee construction.
NOTE 2: Separate paragraphs, such as those below, should be included for each
material type that is to be placed under a contract. The plans should clearly
show, with labels, the location of the fill types. Embankment fills should
include, but not be limited to, the levee, berms, inspection trench, cutoff
trenches and any other specified fill. This allows the Designer and Specifications
Engineer to use multiple fill types within the same contract and clearly indicate
locations of each type. The types of satisfactory materials should be edited
for each type of fill. The bid schedule should include a line for each type
of fill. Where multiple fills are placed in layers, the measurement, payment
and tolerance paragraphs should be edited to specify the interfaces of the multiple
fill types.
Omit the following soil types which are not applicable to the specific project.
2.2.1 [Select Fill
Select fill embankment material shall be obtained from [the borrow site provided by the Government] [sources
provided by the Contractor] [required excavation]. The select fill material shall consist of satisfactory materials
classified in accordance with ASTM D 2487 as [_____].]
2.2.2 [Impervious Fill
NOTES: Caution should be exercised regarding the use of high plasticity clay
and silt (CH, MH) soils with Plasticity Indices greater than about 40 (30 in
dry climates and 50 in humid climates). Spreading and compacting CH or MH materials
can also present constructability problems due to difficulty maintaining proper
moisture content. These soils are susceptible to shrinkage and cracking upon
drying. Seasonal cycles of swelling and shrinkage can also result in loss of
shear strength, which may ultimately result in slope instability. Chemical
treatment, such as lime, has been used to reduce the PI and potential for cracking.
Impervious Fill material shall not be compacted using vibratory rollers.
This material shall consist of satisfactory impervious material classified as lean clay (CL),[ fat clay (CH),]
low plasticity silt (ML),[ high plasticity silt (MH),] [sand containing more than 30 percent of clay (CL),] and
borderline clay and silt (CL-ML) in accordance with ASTM D 2487.]
2.2.3 [Pervious Fill
NOTE: The designer should define the types of material which are acceptable
as Random Fill.
This material shall consist of satisfactory pervious material classified as well graded sand (SW), poorly graded
sand (SP) in accordance with ASTM D 2487.]
2.2.4 [Random Fill
Random fill shall consist of any satisfactory materials[ other than those classified in ASTM D 2487 as [_____]]
[and any silt or sand with a uniformity coefficient (Cu) less than 6].[ Random fill may consist of select fill,
impervious fill, and pervious fill, or a combination of them.]]
2.2.5 Random Rock
NOTE: Random rock is sometimes used in levee construction to build up an underwater
levee toe foundation or to buttress a slope in a constricted area. Due to its
high permeability, random rock or pervious fill should not be used alone as
levee fill material. The designer should select the types of acceptable rock
material and the maximum allowable percent fines.
Random rock shall consist primarily of [_____] (shale, siltstone, sandstone, granite or limestone) obtained from
a source provided by the Contractor. The random rock shall be free of silt, clay, or other earth material in
quantities greater than [_____] [5] percent by weight, and shall contain no debris or organic material. Random
rock shall be reasonably well-graded and the largest stones shall have a maximum dimension not exceeding [_____]
[450] mm [_____] [18] inches. Rock production at the source shall be controlled such that not more than 20 percent
of the material has a maximum dimension between adjacent earth fill shall be choked off with a layer of finer
random rock material. Random rock placed within 1 meter 3 feet of any structure shall have a maximum size of
125 mm 5 inches.
2.2.6 [Coarse Drainage Gravel
Coarse gravel material for the [rectangular and trapezoidal] toe drains shall be obtained from a source provided
by the Contractor. Coarse drainage gravel shall be non-calcareous, composed of tough durable particles, and
shall not contain any organic material or soft, friable particles in quantities. Blast furnace slag will not
be permitted. The gravel material in-place shall meet the requirements of AASHTO M 43, Size No. 57, with the
following gradation:
SIEVE SIZE PERCENTAGE BY
U.S. STANDARD WEIGHT PASSING
SQUARE MESH INDIVIDUAL SIEVE
[_____] (1-1/2 inches) [_____] (100)
[_____] (1 - inch ) [_____] (95-100)
[_____] (1/2 - inch) [_____] (25-60)
[_____] (No. 4) [_____] (0-10)
[_____] (No. 8) [_____] (0-5)]
2.2.7 [Fine Drainage Gravel
NOTE: Identify source of materials.
Fine drainage gravel shall be obtained from a source [provided by the Contractor]. Fine drainage gravel material
shall be non-calcareous, composed of tough durable particles, and shall not contain organic material. The fine
drainage gravel in-place shall meet the requirements of AASHTO M 43, Size No. 8, with the following gradation:
SIEVE SIZE PERCENTAGE BY
U.S. STANDARD WEIGHT PASSING
SQUARE MESH INDIVIDUAL SIEVE
[_____] (1/2-inch) [_____] (100)
[_____] (3/8-inch) [_____] (85-100)
[_____] (No. 4) [_____] (10-30)
[_____] (No. 8) [_____] (0-10)
[_____] (No. 16) [_____] (0-5)]
2.2.8 [Filter Sand
Fine aggregate for the filter sand in-place shall meet the quality requirements of ASTM C 33 grading for fine
aggregate with additional limits on the allowable percentage passing the No. 200 sieve as specified below.
SIEVE SIZE PERCENTAGE BY
U.S. STANDARD WEIGHT PASSING
SQUARE MESH INDIVIDUAL SIEVE
[_____] (3/8-inch) [_____] (100)
[_____] (No. 4) [_____] (95-100)
[_____] (No. 16) [_____] (50-85)
[_____] (No. 100) [_____] (2-10)
[_____] (No. 200) [_____] (0-5)
Additionally, the filter sand shall not contain any organic matter or soft friable particles.]
2.2.9 [Bedding
Bedding material, placed as a backing layer shall consist of satisfactory pervious fill material satisfying the
material requirements presented in [Section
02371
02371
02371 WIRE MESH GABIONS [AND MATTRESSES]] and [Section
02380
02380
02380 STONE,
CHANNEL, SHORELINE/COASTAL PROTECTION FOR STRUCTURES].]
2.2.10 [Topsoil
Topsoil consists of organic soil and shall be placed on the levee slopes as shown on the contract drawings and
as specified in Section [
02922
02922
02922 SODDING] [_____].]
2.2.11 [Semicompacted Fill
NOTE: The designer should list the material types that are acceptable for semicompacted
fill, which can be defined in terms of previously defined fill types or basic
material types.
Material for semicompacted fill shall consist of satisfactory materials classified in accordance with ASTM D 2487
as [_____].]
2.2.12 [Uncompacted Fill
NOTE: The designer should list the material types that are acceptable for uncompacted
fill, which can be defined in terms of previously defined fill types or basic
material types.
Material for uncompacted fill shall consist of satisfactory materials classified in accordance with ASTM D 2487
as [_____].]
2.2.13 [Hydraulic Fill for Berms and Depressed Areas
NOTE: Caution should be used when specifying hydraulic fill. Hydraulic fill
is to be used only in stability berms, pit fills, and seepage berms. Hydraulic
fill will normally not be used in construction for levee embankment. In addition
to requiring a large levee footprint, the levee embankment constructed by hydraulic
fill is susceptible to soil liquefaction, and excessive seepage. Hydraulic
fill also erodes quickly in a situation where a levee is overtopped or where
an impervious covering is penetrated. See the appropriate Engineering Manuals
for further guidance.
Fill shown on the drawings as hydraulic fill shall be placed by hydraulic methods in accordance with the plan
of operations approved by the Contracting Officer. The dredged material shall have, as placed, not less than
[_____] percent by weight passing U.S. Standard Sieve No. [_____] and not less than [_____] percent by weight
passing a U.S. Standard Sieve No. [_____].]
2.3 [MANUFACTURED PRODUCTS
NOTE: Add applicable requirements.
[_____].]
2.4 GROUTS AND DENTAL CONCRETE
Grouts and dental concrete shall be as specified in concrete Section [_____], except that the slump shall be
[_____] mm inches for dental concrete.
2.5 [STABILIZERS
NOTE: Add applicable requirements.
[_____].]
2.6 SETTLEMENT GAGES
Settlement gages shall be as shown.
PART 3 EXECUTION
3.1 CLEARING
Clearing shall be accomplished within the limits of existing ground to receive embankment [and structures], together
with strips [1.5] [_____] meters [5] [_____] feet wide, beyond and contiguous thereto, existing levees to be
degraded, ponding areas, ditches, structures, traverses, channels, riprap, revetment, borrow areas and ramps.
Trees, downed timber, snags, slash, brush, garbage, trash, debris, fencing and other items shall be cleared [[_____]
mm inches above] [flush with] the existing ground surface. Trees and vegetation designated to be left standing
or to remain shall be protected from damage from construction operations. Clearing of borrow areas shall be
limited to the minimum area required for construction operations.
3.2 GRUBBING
Grubbing shall be accomplished within the limits of existing ground to receive embankment [and structures], together
with strips [1.5] [_____] meters [5] [_____] feet wide, beyond and contiguous thereto, existing levees to be
degraded, ponding areas, ditches, structures, traverses, channels, riprap, revetment, borrow areas and ramps.
Grubbing shall be accomplished to a depth of at least [1] [_____] m [3] [_____] feet below the existing ground
surface. All holes caused by grubbing operations and removal of pipes and drains, excluding holes in borrow
areas, channels and ditches [above required grade], shall be filled with satisfactory material as specified in
paragraph [_____]. This material shall be placed in [_____] mm inch layers to the elevation of the adjacent
ground surface and each layer compacted to a density at least equal to that of the adjoining undisturbed material.
3.3 STRIPPING
The entire area within the limits of existing ground to receive embankment and structures, together with strips
[1.5] [_____] meters [5] [_____] feet wide, beyond and contiguous thereto, existing levees to be degraded, ponding
areas, and ditches [shown on the drawing shall be stripped to remove crops, weeds, grass, and other vegetative
materials to the ground surface [and topsoil to a depth of [_____] mm inches]].
3.4 DISPOSITION OF CLEARED, GRUBBED, AND STRIPPED MATERIAL
NOTE: Delete undesirable options for Disposition of Cleared, Grubbed, and Stripped
Materials.
Except as otherwise specified or indicated on the drawings, all materials resulting from clearing and grubbing
operations shall, at the Contractor's option, be disposed of either by windrowing or stockpiling within construction
limits, burying within construction limits, burning, chipping, removal from the site, or a combination thereof.
In no case shall any material resulting form clearing and grubbing operations be buried or permanently placed
within the levee foundation or any structural foundation. The Contractor shall make a reasonable effort to channel
merchantable material into the commercial market and to make beneficial use of the materials resulting from clearing
and grubbing. [The topsoil material resulting from the stripping operations shall be temporarily stockpiled
within the rights-of-way.]
3.4.1 Windrows
Cleared, grubbed and stripped material shall be placed [as shown on the drawings] in a neat windrow or in piles
with tree limbs trimmed sufficiently to make the windrow as small as practicable. No cleared, grubbed or stripped
material shall extend beyond the construction limits.
3.4.2 Burning
Subject to applicable Federal, State and local burning restrictions, the Contractor may burn material within
the contract rights-of-way. Burning operations shall be conducted so as to prevent damage to adjacent man-made
facilities and natural features. The Contractor shall be responsible for any damage to life and property resulting
from fires that are started by the Contractor's employees or as a result of the Contractor's operations. The
Contractor shall furnish, at the site of burning operations, adequate fire fighting equipment to properly equip
personnel for fighting fires. Fires shall be guarded at all times and shall be under constant surveillance until
they have been extinguished. All unburned material (material not reduced to ash) shall be removed from the site
or disposed of by [_____].
3.4.3 Burying
Subject to applicable Federal, State and local burying restrictions, the Contractor may bury the cleared and
grubbed material in the area(s) as shown on the drawings or in [_____]. No material shall be buried within [_____]
meters feet of any standing timber. All material disposed of by burying shall be covered with a minimum of
[_____] mm inches of earth.
3.4.4 Chipping
All cut timber, down timber, dead timber, branches, and brush may be chipped. The chips shall be hauled either
to stockpiles indicated on the drawings or to other locations approved by the Contracting Officer or removed
from site of work. The chips shall be deposited in these areas in either piles or windrows [above] [below] elevation
[_____] NGVD.
3.4.5 Removal from Site of Work
The Contractor may elect to remove all or part of the cleared and grubbed materials from the site of the work
in accordance with Section
01355A
01355A
01355A ENVIRONMENTAL PROTECTION. The Contractor shall, at his option, either retain
any such materials of value for his own use or dispose of them by sale or otherwise. The Government is not responsible
for the protection and safekeeping of any materials retained by the Contractor. Such materials shall be removed
from the site of the work before the date of completion of the work.
3.5 REMOVAL OR PLUGGING OF ABANDONED PIPE AND CONDUITS
NOTE: The terms and conditions in any permits and environmental commitments
obtained by the Government must be made a part of the contract. The designer
must include technical requirements necessary to comply with these terms and
commitments.
Abandoned pipes and conduits shall be removed to the limits shown on the drawings or plugged with concrete a
minimum distance of [_____] meters feet from [_____]. Prior to plugging, the Contractor shall clean the interior
of the pipe to be plugged and place the concrete in such a manner as to insure a dense, well bonded plug.
3.6 SHORING, SHEETING, AND BRACING
Shoring, sheeting, and bracing shall be installed where required for the protection of existing natural features
and man-made facilities, for the safety of workers and the public, in compliance with EM 385-1-1, and to insure
the integrity of the embankment. Shoring, sheeting and bracing shall not be used in lieu of the required excavation
slopes. Shoring, sheeting, and bracing shall be adequately designed and properly installed to withstand anticipated
loads. Shoring, sheeting and bracing shall be planned and designed by a registered professional engineer. The
Contractor shall submit a plan for shoring, sheeting, and bracing in accordance with paragraph SUBMITTALS. All
shoring, sheeting and bracing shall be removed as embankment and backfill operations progress.
3.7 DEWATERING AND DIVERSION
Surface and groundwater control shall be accomplished in coordination with the required excavation and embankment
construction. Surface and/or groundwater control may necessitate the use of temporary diversion ditches, cofferdams
and/or dewatering by the use of pumping. Methods for care of surface water and for controlling the surface and
groundwater levels shall be subject to approval of the Contracting Officer.
3.8 EXCAVATION
Excavation shall consist of removal of material in preparing the foundations to the lines and grades shown on
the drawings, removal of material from ditches and channels to the lines and grades shown on the drawings, removal
of objectionable materials and obtaining required fill materials from the borrow areas.[ Blasting will [not]
be permitted.] Over excavation shall be backfilled to grade with similar over excavated material or satisfactory
material and compacted to a density of at least that of the surrounding material.
3.8.1 Over Excavation
3.8.1.1 Outside Limits of Levee Foundations or Structures
Over excavation outside the limits of the foundations of levees or structures shall be backfilled to grade with
similar over excavated material or satisfactory material and compacted to a density of at least that of the surrounding
material.
3.8.1.2 Within Limits of Levee Foundations or Structures
Over excavation within the limits of the foundations of levees or structures shall be backfilled to grade in
accordance with paragraph PREPARATION OF FOUNDATION, PARTIAL FILL SURFACES AND ABUTMENTS.
3.8.2 Inspection Trench
An inspection trench shall be excavated and maintained free of standing water to the dimensions and locations
shown on the drawings. The trench shall be excavated at least [_____] meters feet in advance of but not more
than [_____] meters feet in advance of construction.
3.8.3 Structures
Excavations for structures shall conform to the dimensions and elevations indicated for each structure and footing,
except as specified hereinafter, and shall include trenching for utility and foundation drainage systems to a
point [_____] meters feet beyond each structure and all work incidental thereto. Excavation shall extend a sufficient
distance from walls and footings to allow for placing and removal of forms. Satisfactory material removed below
the depths indicated without specific direction of the Contracting Officer shall be replaced at no additional
cost to the Government and filled in accordance with paragraph OVER EXCAVATION above.[ Over excavation below
required invert elevations or bottoms of footings shall be backfilled with lean concrete at no additional cost
to the Government. No footings shall be constructed on unsatisfactory material as determined by the Contracting
Officer.] [ Excessively wet and/or soft material in subgrades resulting from water ponding in footing excavations
shall be removed and replaced with [lean concrete] [satisfactory material compacted to the density of the surrounding
undisturbed material]].
3.8.4 Channels
Channels shall be excavated at the locations and to the lines and grades shown on the drawings and in accordance
with paragraph TOLERANCES.
3.8.5 Ditches
Drainage ditches shall be excavated at the locations and to the lines and grades shown on the drawings and in
accordance with paragraph TOLERANCES.
3.8.6 Slopes and Surcharges
Temporary excavation slopes for any channel, structure excavation, or other required excavation shall not be
steeper than the specified finished slope or the specified construction slope, as applicable, and subject to
the approval of the Contracting Officer. This may be accomplished by benching the temporary slope so that the
average slope is not steeper than the specified slope. In addition, no temporary, permanent, or construction
slope shall be surcharged with excavated or stockpiled material or with heavy construction equipment which would
have the same effect as the surcharge material. The toe of stockpiled material shall be maintained a minimum
distance back from the top of the finished excavation equal to the depth of the excavation. The maximum height
of such stockpile without causing instability of the excavation slope shall be determined by the Contractor.
Any slide or other adverse conditions caused by failure of the Contractor to maintain these conditions shall
be considered the responsibility of the Contractor and remedial measures shall be at the Contractor's expense.
3.8.7 Borrow Areas
3.8.7.1 Government-Furnished
Borrow areas shall be excavated to the extent necessary to obtain satisfactory material within the lines and
grades as shown on the drawings. When the material necessary for the construction of the embankment and berms
cannot be obtained from adjacent borrow areas, it shall be obtained from other Government-furnished borrow areas.
[ The permissible depth(s) in the borrow areas are indicated on the drawings.] Any excavation below the depths
and slopes specified herein or shown on the drawings shall be backfilled by the Contractor, at the Contractor's
expense, to the specified permissible excavation line, with satisfactory [material(s)] [cohesive material] [or]
[other material] as specified by the Contracting Officer to a density of at least that of the surrounding material.
Borrow areas shall be drained and kept dry during excavation. Where possible, unsatisfactory materials in borrow
areas shall not be removed.
3.8.7.2 Contractor-Furnished
Borrow areas proposed by the Contractor shall be subject to approval by the Contracting Officer. Any borrow
sources proposed, accepted and approved by the Contracting Officer shall meet all applicable Federal, State and
local requirements. [ Proposed sources located within [_____] meters feet landward and [_____] meters feet riverward
of the levee between Stations [_____] and [_____] will not be permitted.] No payment will be made for Contractor-furnished
borrow areas.
3.8.7.3 Dredged
The Contractor has the option of using dredging operations to obtain material for the pervious zones or the random
zones subject to the requirements and the conditions specified herein. Dredging operations may be conducted
at approved locations in the present stream bed of [_____] or as shown on the drawings. Dredging operations
will not be permitted within [_____] meters feet of the levee centerline and no material shall be obtained within
[_____] meters feet of any revetment, stabilized channel line, bridge pier and/or abutment.
3.8.8 Cut-Off Trenches
A cutoff trench shall be excavated and maintained free of standing water to the dimensions and locations shown
on the drawings. The trench shall be excavated at least [_____] meters feet in advance of but not more than
[_____] meters feet of construction.
3.8.9 Existing Levees and Spoil Banks
Existing levees and spoil banks shall be removed as shown on the drawings. In areas where the existing levee
is located within the random or berm zone of the levee, it shall be incorporated into the embankment. Portions
of existing embankments which lie within the impervious zone of the levee shall be removed. Existing levees
located within the rights-of-way landward of the levee and berms to be constructed, may be utilized as borrow
material, but only after equal protection has been provided by construction of the new levee. When excavated
for borrow material, the existing levee shall be removed to the adjacent ground surface in a uniform manner,
and shaped to maintain drainage in accordance with the adjacent natural drainage pattern. [ When lower levels
of flood protection would be caused by levee construction the Contractor shall provide the Contracting Officer
a plan to maintain existing levels of protection during the construction period.]
3.8.10 Toe Drains
Toe drains shall be excavated to the dimensions and the locations indicated on the drawings.
3.8.11 Utilities
Excavations for pipe beds shall be shaped to fit the contour of the pipe over a width of not less than 0.6 of
the pipe diameter, or as shown on the drawings.
3.8.12 Rock
Rock and other hard foundation materials shall be cleaned of loose debris and cut to a firm surface, either level,
stepped, or serrated, as shown on the drawings. Loose disintegrated rock and thin strata shall be removed.
Rock excavation will not be measured for payment. Rock excavation will not be paid for as a separate bid item.
3.8.13 Riprap and Bedding
Excavations for riprap and bedding shall be performed at the locations and to the lines and grades shown.
3.9 TOLERANCES
A tolerance of [_____] mm inches above or below the prescribed grade will be allowed in the excavation for channels,
ditches, inspection trenches, cutoff trenches, excavations for riprap and bedding, and mandatory borrow areas.
A tolerance of [_____] mm inches below the prescribed grade will be allowed in the excavation for all other borrow
areas.
All embankments and backfills shall be constructed to the grades, lines, and cross-sections shown on the drawings.
At all points a tolerance of [100] [_____] mm [4] [_____] inches above or below the prescribed grade will be
permitted in the final dressing, provided that any excess material is so distributed that the crown of the levee
drains and that there are no abrupt humps or depressions in any surfaces. For topsoil, a tolerance of [_____]
mm inches above the thickness as shown on the drawings will be permitted.
3.10 SLIDES
In case sliding occurs in any part of the excavations prescribed in this section after they have been excavated,
but prior to final acceptance of all work under the contract, the Contractor shall repair the slide as directed
by the Contracting Officer. In case the slide is caused through the fault of the Contractor, it shall be repaired
at no cost to the Government. In case the slide is due to no fault of the Contractor, an equitable adjustment
in the contract price will be made for the repairs in accordance with the Contract Clause CHANGES.
3.11 TRAVERSES
Traverses shall be left unexcavated between borrow areas at the locations [and to the cross sections] shown on
the drawings. [ The traverses shall have minimum top widths of [_____] meters feet with side slopes no steeper
than 1 on 3 or as shown on the drawings.]
3.12 STOCKPILES
Provisions of paragraph SLOPES AND SURCHARGES are applicable to all stockpiled materials. Upon completion of
construction operations, all remaining stockpiled material shall be removed and disposed of by the disposal methods
specified in paragraph DISPOSITION OF EXCAVATED MATERIALS.
3.13 SURFACE DRAINAGE OF COMPLETED AREAS
The areas shown on the drawings designated as "GRADE FOR SURFACE DRAINAGE", the borrow areas, and the finished
embankment areas shall be graded to the lines and grades shown on the drawings. The surface shall be free from
sharp ridges, gullies, potholes, sinkholes, and any other surface irregularities. A tolerance of [_____] mm
inches above or below the prescribed grade will be allowed provided that the surface drains in the direction
as indicated on the drawings.
3.14 MAINTENANCE OF WORK
3.14.1 Debris Removal
The Contractor shall maintain all ditch and channel excavations free from leaves, brush, sticks, trash, and other
debris until final acceptance of all work under the contract at no additional cost to the Government.
3.14.2 Sediment Removal
Prior to final acceptance of all work under this contract, the removal of sediments from ditch or channel excavations
shall be required to restore design grade and section at no additional cost to the Government.
3.15 DISPOSITION OF EXCAVATED MATERIALS
3.15.1 Satisfactory Materials
Satisfactory excavated material shall be incorporated in the appropriate zones of the embankment. Satisfactory
material shall consist of material as defined in paragraph DEFINITIONS, subparagraph SATISFACTORY MATERIALS.
When direct placement is not practicable, satisfactory material from the excavation [may] [shall] be stockpiled
for subsequent use in parts of the work for which it is specified herein and/or as indicated on the drawings.
Satisfactory materials in excess of the quantity necessary to construct backfills and embankments shall be disposed
of as specified for unsatisfactory materials.
3.15.2 Unsatisfactory Materials
Unsatisfactory materials shall be as defined in paragraph DEFINITIONS, subparagraph UNSATISFACTORY MATERIALS.
Unsatisfactory materials from the excavations prescribed in this section shall be permanently disposed of by
[removal from the site to a Contractor-furnished disposal area] [placing in the disposal area shown on the drawings]
[placing in abandoned portions of the borrow areas]. [ The material shall be shaped so that its surface is free
from abrupt changes in grade and shall be sloped to drain.] [ No additional payment will be made for [Contractor-furnished
disposal areas] [placing in abandoned portions of the borrow areas].] [ The material shall be shaped so that
its surface is free from abrupt changes in grade and shall be sloped to drain.] [ No additional payment will
be made for Contractor-furnished disposal areas.]
3.16 PREPARATION OF FOUNDATION, PARTIAL FILL SURFACES AND ABUTMENTS
3.16.1 Earth
NOTE: Modify and or add to this paragraph to be compatible with the embankment
construction procedure. If uncompacted or semicompacted fill is being utilized
major modifications may be required.
After excavation (as described in paragraph EXCAVATION) or stripping (as described in paragraph CLEARING, GRUBBING
AND STRIPPING) of the embankment foundation [and excavation of the cut-off trench] to the extent indicated or
otherwise required, the sides of stump holes, test pits, and other similar cavities or depressions shall be broken
down so as to flatten out the slopes, and the sides of the cut or hole shall be scarified to provide bond between
the foundation material and the fill. [ The slopes and bottom of the cut-off trench shall be scarified, as directed.]
Unless otherwise directed, each depression shall be filled with the same material type that is to be placed immediately
above the foundation. The fill shall be placed in layers, moistened, and compacted in accordance with the applicable
provisions of paragraphs PLACEMENT, MOISTURE CONTROL, and COMPACTION for the specific material type. Materials
which cannot be compacted by roller equipment because of inadequate clearances shall be compacted with power
tampers in accordance with the paragraph COMPACTION for the specific material type. After filling of depressions
[and cut-off trench] and immediately prior to placement of compacted fill in any section of the embankment, the
foundation of such section shall be loosened thoroughly by scarifying, plowing, discing or harrowing to a minimum
depth of [_____] mm inches, and the moisture content shall be adjusted to the amount specified in paragraph MOISTURE
CONTROL for the appropriate type of material. [ After removal of roots or other debris turned up in the process
of loosening, the entire surface of the embankment foundation area shall be compacted by [_____] complete coverages
of the compaction equipment as specified for the appropriate type of fill.] Immediately prior to placement of
compacted fill on or against the surfaces of any partial fill section, all soft or loose material, all material
containing cracks or gullies, and all material that does not conform with the specified zoning of the embankment
shall be removed. The remaining surface of the partial fill shall be loosened by scarifying, plowing, discing
or harrowing to a minimum depth of [_____] [150] mm [_____] [6] inches, and the moisture content shall be adjusted
as specified in paragraph MOISTURE CONTROL for the appropriate type of material. The surface of the partial
fill section upon which fill is to be placed shall then be compacted as hereinafter specified for the appropriate
type of fill. No separate payment will be made for loosening and rolling the foundation area, the abutment area,
or the surfaces of partial fill sections, but the entire cost thereof shall be included in the applicable contract
price for fill.
3.16.2 Rock Foundation
All rock surfaces upon which or against which embankment materials are to be placed shall be excavated (as described
in paragraph EXCAVATION) or stripped (as described in paragraph CLEARING, GRUBBING AND STRIPPING). Prior to
the placement of embankment material upon or against a rock surface, all open joints and cracks in that surface
shall be filled with mortar to the depths cleaned. Those portions of such rock surfaces where, in the opinion
of the Contracting Officer, the compaction of the embankment materials cannot be accomplished satisfactorily
with power tampers or other specified compaction equipment, shall be filled with mortar or concrete as directed
to the extent necessary to permit satisfactory use of the compaction equipment. In no case shall a thin coat
of mortar be left on smooth, intact rock surfaces. Large rock overhangs and protrusions shall be removed and
rock surfaces shall be laid back to a slope no steeper than 4V on 1H by the use of pre-splitting or line drilling
techniques in such a manner as to minimize damage to the underlying rock, or the spaces beneath overhangs and
around protrusions shall be filled with tamped concrete so that satisfactory compaction of embankment materials
can be accomplished. Rock surfaces shall not be more than
0.67 m 2 feet in height, and benches of sufficient
width shall be provided as necessary so that the average slope of any rock face is not steeper than [_____]V
on [_____]H. Mortar and concrete, including forming as necessary, shall conform with the applicable provisions
of Section [
03307
03307
03307 CONCRETE FOR MINOR STRUCTURES] [_____].
3.16.3 [Benching
Benching into existing levee embankment and abutments is required in order to place and compact the material
in horizontal layers. The vertical face cut into the existing embankment or abutment resulting from the benching
operation shall be a minimum of [_____] mm inches in height but shall not exceed [_____] mm inches in height.]
3.16.4 [Preloading
NOTE: Insert applicable language for preloading as required. Identify the
extent of the area over which preloading will be required by designating the
stationing along the centerline of the levee. Indicate the length of time the
preload will be left in place or define the settlement conditions which must
occur before construction in the preloaded area can proceed. Address whether
or not the preload embankment will become part of the permanent levee.
Preloading of the levee foundation will be required between Station [_____] and Station [_____]. The preload
embankment will be constructed to the cross section shown on the drawings for the applicable location. After
completion of the construction of the preload embankment no additional construction shall take place in the preloaded
areas [for [_____] days] [until the required settlement has occurred]].
3.16.5 [Settlement of Foundation
NOTE: Modify the following to the method of determining foundation settlement,
which may be achieved by installing settlement gages or performing core borings
The Contractor [shall] [may elect to] [furnish and install settlement gages] [perform core borings], at the settlement
measurement locations shown on the plans, for determination of settlement of the foundation during construction
within the settlement measurement ranges shown on the drawings. [ Each settlement measurement location shall
be located on the prepared foundation at a point directly under the crown of the planned levee section prior
to placing of fill material. The gages shall be maintained and extended, if necessary, during the construction.
The type and arrangement of the gages shall be as shown on the drawings. The Contractor shall make such measurements
and determine such elevations on the gages prior to the placing of fill material and again within [72] [_____]
hours after final cross sections have been taken over the completed embankment at the locations of the gages.]
[ The Contractor shall perform a cross section at the settlement measurement location prior to the placing of
fill material to establish the elevation of the foundation/embankment interface. Within [72] [_____] hours after
final cross sections have been taken over the completed embankment at the settlement measurement location the
Contractor shall perform the core boring to determine foundation settlement.] Settlement measurements will be
[verified] [subject to verification] by the Contracting Officer.]
3.17 [TEST FILL STRIPS]
NOTE: Test strips are needed when the volume of the project is large, the compaction
requirement will be obtained by specifying the type of compaction equipment
and the number of passes on each lift (i.e. a method or procedure specification
is being utilized) and there is not sufficient information on the compaction
characteristics of the proposed fill materials and equipment to be used for
the project. On projects where the levees are small (greater than 5 meters
(15 feet) high) and on levee raising projects where fill placement zones are
narrow (3.3 meters (10 feet), some of the larger compaction equipment specified
herein (such as 50-ton rubber tired roller and some tamping rollers) are not
appropriate. Consistently Contractors propose using smaller equipment with
shorter tamping feet. Test fills, therefore, may also be an appropriate means
of evaluating performance and setting placement and compaction criteria to assure
satisfactory result.
3.17.1 [General
Before beginning embankment construction, the Contractor shall construct test strip(s) for [_____] fill materials
to demonstrate that the equipment and compaction procedure will achieve the moisture-dry density relationship
as specified. The test strips may be incorporated as part of the final embankment, if the fills meet the requirements
of the specifications. The test strips shall be constructed using materials from the borrow sources which have
been approved by the Contracting Officer. A test strip shall be performed for each of the following type of
fill materials [_____]. Each test strip shall be of sufficient size to allow compaction equipment to achieve
normal operating speed over a [_____] [17] meter [_____] [50] foot length. The test strip shall be a minimum
of two (2) times wider than the compaction equipment. Each test strip shall be constructed with a minimum of
4 lifts. Prior to the construction of the test strips, the foundation (subgrade) shall be proof rolled as specified
in paragraph [_____] and an 200 mm 8 inch thick subbase layer installed. The subbase layer shall consist of
the same material to be used in the test strip and shall be spread and compacted to the same requirements.
The test strips shall be constructed in accordance with the applicable provisions of paragraphs PLACEMENT, MOISTURE
CONTROL, and COMPACTION for the specific material type. The fill material shall be placed and spread in layers
in accordance with the applicable provisions of paragraphs PLACEMENT for the specific material type. Each layer
of the fill shall be compacted with a minimum of four (4) complete coverages using the specified compaction equipment,
and as many additional coverages as may be required to achieve the specified density. Even if the results from
the test strips show that the required densities can be obtained with less than four coverages by the compaction
equipment, the Contractor shall still be required to compact the impervious and random fills with a minimum of
(4) complete coverages. If the use of the proposed compaction equipment causes shearing of the fill, laminations
in the fill, or results in inadequate compaction, the Contracting Officer may direct that such roller be removed
from the fill and that another appropriate tamping roller be used.]
3.17.2 [Testing and Reporting Requirements for Test Strips
Prior to construction of the test strips, the Contractor shall perform one laboratory compaction test for each
type of material used in test strips. The compaction tests shall be performed in accordance with the requirements
specified in paragraph MATERIALS TESTING. Test results shall be submitted to the Contracting Officer before
construction of the test strips. After placement and spreading of the fill in the test strip, but prior to compaction,
five samples shall be obtained from each lift for moisture content determination in accordance with ASTM D 2216
. After compaction of the fill, a minimum of [_____] [5] in-place nuclear density and moisture content tests
(in accordance with ASTM D 2922 and ASTM D 3017, respectively) and one (1) sand cone density test (in accordance
with ASTM D 1556) shall be performed on each lift. One sample shall be obtained from each test strip for classification
testing as specified in paragraph MATERIALS TESTING. All testing and sampling locations shall be determined
by the Contracting Officer. The Contractor's QC personnel shall monitor and document construction and testing
of the test strips. Documentation shall include weather conditions, soil type, spreading and compaction equipment
type, lift thickness, number of coverages, moisture content, dry density, and a plan showing approximate location
of sampling and testing. Documentation of the test strip construction procedures and results of all testing
shall be provided to the Contracting Officer. Full scale embankment construction shall not commence until the
equipment and placement methods are approved by the Contracting Officer.]
3.18 PLACEMENT AND SPREADING
3.18.1 General
[Prior to beginning embankment placement on the levee foundation the Contractor shall notify the Government that
the foundation is ready to receive fill.] [ No fill shall be placed on any part of the embankment foundation
until such areas have been inspected and given final approval by the Contracting Officer.]
3.18.1.1 Gradation and Distribution
The gradation and distribution of materials throughout each zone of the levee shall be such that the embankment
will be free from lenses, pockets, streaks, and layers of material differing substantially in texture or gradation
from surrounding material of the same class. If lenses, pockets, or layers of materials differing substantially
in texture or gradation from surrounding material occur in the spread material, the layer shall be mixed by harrowing
or any other approved method to blend the materials. During the placing and spreading process, the Contractor
shall maintain at all times a force of workers adequate to remove all roots, debris, and oversize stone from
all embankment materials. All stones and rock fragments larger than [2/3 of the placement lift thickness measured
by the greatest dimension] [75 mm 3 inches in any dimension] shall be removed [at the source prior to hauling
to] [from] the fill. No fill shall be placed upon a frozen surface, nor shall snow, ice, or frozen earth be
incorporated in the embankment.
3.18.1.2 Foundations and Partial Embankment Fills
The foundations and all partial embankment receiving fills shall be kept thoroughly drained. Placing operations
will be such as to avoid mixing of materials from adjacent sections as much as practicable.
3.18.1.3 Equipment Traffic
Equipment traffic on any embankment zone shall be routed to distribute the compactive effort as much as practicable.
Ruts formed in the surface of any layer of spread material will be filled before that material is compacted.
If, in the opinion of the Contracting officer, the compacted surface of any layer of material is too smooth to
bond properly with the succeeding layer, the surface shall be loosened by scarifying or other approved methods
before material from the succeeding layer is placed.
3.18.2 Placement on Surfaces Containing Frozen Materials
Embankment shall not be placed on a foundation which contains frozen material, [or which has been subjected to
freeze-thaw action]. This prohibition encompasses all foundation types, including the natural ground, all prepared
subgrades (whether in an excavation or on an embankment, and all layers of previously placed and compacted earth
fill which become the foundations for successive layers of earth fill. All material that freezes or has been
subjected to freeze-thaw action during the construction work, or during periods of temporary shutdowns, such
as, but not limited to nights, holidays, weekends, or winter shutdowns of earthwork operations, shall be removed
to a depth that is acceptable to the Contracting Officer and replaced with new material. Alternatively, the
material shall be thawed, dried, reworked and recompacted to the specified criteria before additional material
is placed. The Contracting Officer will determine when placement of fill shall cease due to cold weather. The
Contracting Officer may elect to use average daily air temperatures, and/or physical observation of the soils
for the determination. Levee embankment material shall not contain frozen clumps of soil, snow or ice.
3.18.3 Placement of Embankment and Backfill Against Rock
All rock surfaces upon which or against which embankment materials are to be placed shall be cleaned in accordance
with Section
02330
02330
02330 EMBANKMENT FOR EARTH DAMS [and shall be prepared in accordance with paragraph PREPARATION
OF FOUNDATION, PARTIAL FILL SURFACES AND ABUTMENTS, subparagraph ROCK]. In restricted areas where material can
not be placed in large lifts with normal spreading and compaction equipment material shall be spread in lifts
not exceeding [_____]
mm inches and compacted with mechanical hand tampers, vibrating plates, or other approved
methods and equipment.
3.18.4 Placement of Embankment and Backfill Against Structures
No embankment or backfill shall be placed on or against concrete less than 7 days after placement or 70 percent
of the design strength, without prior approval of the Contracting Officer. Crawler-type tractors, vibratory
equipment and other similar compaction equipment shall not be used within [____] [1] meter [_____] [4] feet of
any completed or partially completed structure. Compaction within [_____] [1] meter [_____] [4] feet of completed
or partially completed structures shall be accomplished by the use of mechanical hand tampers, vibrating plates,
or other approved methods and equipment. The Contractor shall ensure that compaction operations do not damage
any existing utilities. Any damage caused by the Contractor's operation shall be repaired at the Contractor's
expense.
3.18.5 Select Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the last bracketed sentence
should be selected and the following should be substituted into the appropriate
paragraphs below. [The materials for [_____] fill shall be placed or spread
in layers, the first layer not more than [_____] [mm] [_____] inches in thickness
and the succeeding layers not more than [_____] mm [_____] inches in thickness
prior to compaction.]
Select fill material shall be placed and spread in layers not more than 200 mm 8 inches in uncompacted thickness,
except that within [_____] [1] m [_____] [4] feet of [______] structures, the uncompacted layer thickness shall
be reduced to [150] [_____] mm [6] [_____] inches. [Layers should be started full out to the slope stakes and
shall be carried substantially horizontal and parallel to the levee centerline with sufficient crown or slope
to provide satisfactory drainage during construction.] [The materials for [_____] fill shall be placed or spread
in layers, the first layer not more than [_____] mm inches in thickness and the succeeding layers not more than
[_____] mm inches in thickness prior to compaction.]
3.18.6 Coarse Drainage Gravel and Filter Sand
Coarse drainage gravel and filter sand shall be placed and spread in layers not more than [_____] [300] mm [_____]
[12] inches in uncompacted thickness, except that within [_____] [1] m [_____] [4] feet of the [_____] structures,
the uncompacted layer thickness shall be reduced to [_____] [150] mm [_____] [6] inches. The method of placement
of all gravel and sand material shall be controlled to minimize segregation of particle sizes and contamination
with other embankment materials.
3.18.7 Impervious Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the last bracketed sentence
should be selected.
The impervious fill material shall be placed and spread in layers not more than [_____] [200] mm [_____] [8]
inches in uncompacted thickness, except that within [_____] [1] m [_____] [4] feet of [______] structures, the
uncompacted layer thickness shall be reduced to [_____] [100] mm [_____] [4] inches. [Layers should be started
full out to the slope stakes and shall be carried substantially horizontal and parallel to the levee centerline
with sufficient crown or slope to provide satisfactory drainage during construction.] [The materials for [_____]
fill shall be placed or spread in layers, the first layer not more than [_____] mm inches in thickness and the
succeeding layers not more than [_____] mm inches in thickness prior to compaction.]
3.18.8 Pervious Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the last bracketed sentence
should be selected.
The pervious fill material shall be placed and spread in layers not more than [_____] [200] mm [_____] [8] inches
in uncompacted thickness, except that within [_____] [1] m [_____] [4] feet of [______] structures, the uncompacted
layer thickness shall be reduced to [_____] [150] mm [_____] [6] inches. [Layers should be started full out
to the slope stakes and shall be carried substantially horizontal and parallel to the levee centerline with sufficient
crown or slope to provide satisfactory drainage during construction.] [The materials for [_____] fill shall
be placed or spread in layers, the first layer not more than [_____] mm inches in thickness and the succeeding
layers not more than [_____] mm inches in thickness prior to compaction.]
3.18.9 Random Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the last bracketed sentence
should be selected.
Random fill material shall be placed and spread in layers not more than [_____] [200] mm [_____] [8] inches in
uncompacted thickness, except that within [_____] [1] m [_____] [4] feet of [_____]structures, the uncompacted
layer thickness shall be reduced to [_____] [150] mm [_____] [6] inches. [Layers should be started full out
to the slope stakes and shall be carried substantially horizontal and parallel to the levee centerline with sufficient
crown or slope to provide satisfactory drainage during construction.] [The materials for [_____] fill shall
be placed or spread in layers, the first layer not more than [_____] mm inches in thickness and the succeeding
layers not more than [_____] mm inches in thickness prior to compaction.]
3.18.10 [Random Rock
Random rock shall be placed within the limits indicated on the drawings in such a manner as to produce a reasonably
well graded mass of stone with a minimum percentage of voids. The random rock shall be placed in layers that
will will produce a compacted [_____] [600] mm [_____] [24] inch thick layer as shown on the drawings.[ Dewatering
of the foundation beneath the random rock zone shall be sufficient to allow the random rock material to be placed
and compacted as specified herein to produce a firm, dense surface upon which to place select earth fill.] The
outside slope of the random rock zone shall be graded to produce a reasonably even surface, within a tolerance
of plus or minus [_____] [300] mm [_____] [12] inches measured [vertical] [normal] to the slope from the lines
indicated on the he drawings, upon which slope protection layers can be placed.]
3.18.11 [Fine Drainage Gravel Placed Around Structures
Fine drainage gravel placed for drainage around [_____] structures shall be placed in horizontal layers not exceeding
[_____] mm inches in loose lift thickness, or within [_____] [1] m [_____] [4] feet when hand operated compactors
are used. After placing, each layer shall be uniformly spread, moistened or aerated as necessary to obtain the
specified moisture content, thoroughly mixed and compacted as specified. Backfilling shall not begin until construction
below finish grade has been approved, forms removed, and the excavation cleaned of trash and debris. Power driven
hand operated compactors shall be used along the closure structure for compaction within [_____] [0.7] m [_____]
[2] feet of concrete structures. Backfill shall not be placed against concrete prior to 7 days after placement.
As far as practicable, backfill shall be brought up evenly on each side of the structure and sloped to drain
away from the structure.]
3.18.12 [Semicompacted Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the last bracketed sentence
should be selected.
The location and extent of the semicompacted fill shall be as shown on the drawings. Semicompacted fill shall
not be placed in water. Semicompacted fill material shall be placed and spread in layers not more than [_____]
[300] mm [_____] [12] inches in uncompacted thickness, [except that within [_____] [1] m [_____] [4] feet of
[_____] structures, the uncompacted layer thickness shall be reduced to [_____] [150] mm [_____] [6] inches].[
Layers shall be started full out to the slope stakes and shall be carried substantially horizontal and parallel
to the levee centerline with sufficient crown or slope to provide satisfactory drainage during construction.]
[ The materials for [_____] fill shall be placed or spread in layers, the first layer not more than [_____] mm
inches in thickness and the succeeding layers not more than [_____] mm inches in thickness prior to compaction.]]
3.18.13 [Uncompacted Fill
NOTE: If it is desired that the first layer of fill over the foundation be
of a different thickness than subsequent layers, then the second bracketed sentence
should be selected.
Uncompacted fill shall be placed in approximately horizontal layers not exceeding [_____] mm inches in thickness.
The layers shall be uniformly spread, distributed, and otherwise manipulated during placement to such an extent
that individual loads of material deposited on the fill will not remain intact, and large, open voids in the
fill will be eliminated. Lifts shall not be placed in a manner which causes shrinkage cracks and open voids
from developing in previously placed lifts.[ Layers shall be started full out to the slope stakes and shall
be carried in lifts approximately horizontal and parallel to the centerline with sufficient crown or slope to
provide satisfactory drainage during construction.] [ The materials for [_____] fill shall be placed or spread
in layers, the first layer not more than [_____] mm inches in thickness and the succeeding layers not more than
[_____] mm inches in thickness prior to compaction.][ Compaction other than that obtained by the controlled
movement of the hauling and spreading equipment over the area will not be required.][ Where material must be
placed in water, it shall be dumped therein until it reaches an elevation [_____] mm foot above the water surface,
or until a stable fill surface is obtained before layer construction will be required. The material deposited
under water shall be placed in such a manner to ensure that any soft material will be forced progressively outward
from the section and not be trapped within the base of the embankment.][ Material containing more than [_____]
[15] percent fines passing the No. 200 sieve shall not be placed below the water surface.]]
3.18.14 Hydraulic Fill
3.18.14.1 Discharge Pipe
At all times when the dredge discharge pipe is being washed out or when the discharge consists of a high percentage
of water with only a minimum amount of solid material being pumped, all control plates at the bottom openings
along the spill-pipe sections of the discharge pipe lines shall be closed immediately and shall remain in a closed
position until the pumping operation produces a minimum of [10] [_____] percent solid materials in the discharge.
3.18.14.2 Discharge Pipe Outlets
During placement operations of the fill, free outlets to conduct discharge water away from the embankment shall
be provided at intervals of not more than [610] [_____] m [2,000] [_____] feet, for 300-mm 12-inch dredges or
smaller; [915] [_____] m [3,000] [_____] feet, for 325 to 400 mm 13- to 16-inch dredges; and [1219] [_____] m
[4,000] [_____] feet, for dredges over 400 mm 16 inches. The size of dredges are determined by the minimum
inside diameter of the discharge pipe. No obstruction to free flow will be permitted in these outlets or at
any point in the fill area, between the end of the discharge pipe and the outlet. A retaining dike, transverse
to the fill area center line, shall be constructed immediately beyond each outlet and shall not be breached until
the end of the discharge pipe has approached the retaining dike to within 76 m 250 feet, in the case of 300 mm
12-inch dredges or smaller; 114 m 375 feet, in case of 325 to 400 mm 13- to 16-inch dredges; or 152 m 500 feet
, in the case of dredges over 400 mm 16 inches.
3.18.14.3 Control of Materials in Hydraulic Construction
In general, the materials in the fill shall be distributed in such a way as to produce a section of relatively
uniform permeability. In order to maintain uniform permeability of the fill, the Contractor shall not place
strata and large pockets of gravel, not containing sufficient fines. Whenever they occur they shall be promptly
blended with finer materials. The Contractor shall take necessary precautions to prevent damage from discharge
water or other causes.
3.18.14.4 Rehandling Hydraulic Material
Rehandling of hydraulic material to bring the fill area to required grade and cross section shall conform to
paragraph [_____]. If, in the opinion of the Contracting Officer, the rehandled material is too dry to permit
its placement by compacted fill method, then the soil placement shall conform to paragraph [_____].
3.19 MOISTURE CONTROL
3.19.1 General
The materials in each layer of the fill shall contain the amount of moisture, within the limits specified below
or as directed by the Contracting Officer, necessary to obtain the required compaction. Material that is not
within the specified moisture content limits after compaction shall be reworked to obtain the specified moisture
content, regardless of density.
3.19.1.1 Insufficient Moisture for Suitable Bond
If the top or contact surfaces of a partial fill section become too dry to permit suitable bond between these
surfaces and the additional fill to be placed thereon, the Contractor shall loosen the dried materials by scarifying
or discing to such depths as may be directed by the Contracting Officer, shall dampen the loosened material to
an acceptable moisture content, and shall compact this layer in accordance with the applicable requirements of
paragraph COMPACTION.
3.19.1.2 Excessive Moisture for Suitable Bond
If the top or contact surfaces of a partial fill section become too wet to permit suitable bond between these
surfaces and the additional fill to be placed thereon, the wet material shall be scarified and permitted to dry,
assisted by discing or harrowing, if necessary, to such depths as may be directed by the contracting officer.
The material shall be dried to an acceptable moisture content, and shall be compacted in accordance with the
applicable requirements of paragraph COMPACTION.
3.19.1.3 Drying Wet Material
Material that is too wet shall [be spread on the embankment and permitted to dry,] [be dried in the borrow area
prior to bringing to the levee embankment] be assisted by discing or harrowing, if necessary, until the moisture
content is reduced to an amount within the specified limits.
3.19.1.4 Increasing Moisture in Dry Material
The moisture content of material that is too dry, [will be adjusted on the levee embankment] [will be adjusted
in the borrow area prior to bringing to the levee embankment]. The Contractor will add water to the fill material
and by harrowing, or other approved methods, work the moisture into the material until a uniform distribution
of moisture within the specified limits is obtained. Water applied on a layer of fill on the levee embankment
shall be accurately controlled in amount so that free water will not appear on the surface during or subsequent
to rolling. Should too much water be added to any part of the embankment, the rolling on that section of the
embankment shall be delayed until the moisture content of the materials is reduced to an amount within the specified
limits. If it is impracticable to obtain the specified moisture content by wetting or drying the material on
the fill, the Contractor may be required to pre-wet or dry back the material at the source of excavation or in
the borrow area.
3.19.2 Select Fill
The moisture content after compaction shall be within the limits of [_____] percentage points above optimum to
[_____] percentage point below optimum moisture content as determined by ASTM D 698.
3.19.3 Impervious Fill
The moisture content after compaction shall be within the limits of [2] [_____] percentage points above optimum
to [2] [_____] percentage point below optimum moisture content as determined by ASTM D 698.
3.19.4 Pervious Fill
NOTE: Saturation of the pervious fill may not be appropriate if the fill is
placed in a zone or area (trenches, etc.) which can not readily drain.
Each layer of material shall be placed, worked, and compacted in a saturated condition.
3.19.5 Random Fill
NOTE: The moisture control of random earth shall be conformed to the requirements
of the material type it most closely approximates in behavior.
[The moisture content after compaction shall be within the limits of [_____] percentage points above optimum
to [_____] percentage point below optimum moisture content as determined by ASTM D 698.] [The moisture content
shall be that which will facilitate obtaining the specified compaction.]
3.19.6 Coarse Drainage Gravel and Filter Sand
The moisture content shall be controlled such that hauling, spreading, and compacting equipment can operate with
normal procedure without excessive rutting of the fill. If the material is too wet or too dry to facilitate
proper compaction, the coarse drainage gravel or filter sand shall be wetted or dried as required by the procedures
specified in paragraph [_____].
3.19.7 Fine Drainage Gravel
Fine drainage gravel shall be placed, worked, and compacted in a saturated condition. The moisture content after
compaction shall be as uniform as practicable throughout any one layer of fine drainage gravel.
3.19.8 Semicompacted Fill
[Semicompacted fill shall be placed within plus or minus [_____] percent of optimum moisture content.] [Semicompacted
fill will be placed at their in situ moisture content.] [The moisture content of semicompacted fill shall be
controlled such that hauling, spreading, and compacting equipment can operate with normal procedure without excessive
rutting of the fill.] [The moisture content shall be that which will facilitate obtaining the specified compaction.]
3.19.9 Uncompacted Fill
Uncompacted fill will be placed at their in situ water content.[ The moisture content shall be controlled such
that hauling, spreading, and compacting equipment can operate with normal procedure without excessive rutting
of the fill.]
3.19.10 Hydraulic Fill
No moisture control is required for Hydraulic Fill.
3.20 COMPACTION
NOTE: The designer should edit the following paragraphs to account for the
use of either an end product specification (i.e., the Contractor is required
to obtain a specified degree of compaction) or a method specification (i.e.,
when the Contractor is required to compact the embankment by a specified number
of coverages of a specified/approved roller and is not responsible for the obtained
degree of compaction). If the method specification is used and the required
degree of compaction is not achieved, the Contractor should be paid for additional
rolling for compaction under a separate bid item as specified in paragraph ADDITIONAL
ROLLING FOR COMPACTION.
3.20.1 Compaction Equipment
NOTE: With reference to the use of compaction equipment in this paragraph,
the following precautions should be noted:
1. Specifications should be written to insure that the type of compaction equipment
will be used which, is best suited to obtain the desired compaction of the material
being utilized. When the size of the contract can justify the costs a requirement
should be included in the specifications for the performance evaluation of each
type of compaction equipment conforming with the specifications and intended
for use by the Contractor at an early stage of embankment construction. This
equipment evaluation should be accomplished through analysis of test fill areas
that are carefully constructed under representative working conditions with
materials and moisture contents as specified. Test fill areas may either be
separate or part of the permanent work, and for clarity to prospective bidders,
payment under a separate item is recommended to equitably cover costs of required
variations in equipment coverages, possible changes in equipment loading or
foot sizes, as well as intensified field soils testing.
2. For tamping rollers that are either towed or self-propelled, with drums
capable of being ballasted with fluid, the provision for a pressure relief valve
and safety head is optional, and should be included at the discretion of the
designer based on local experience and practice. Over-pressurization of fluid
ballasted compaction drums to the level of a safety hazard has been rare, but
has occurred on several occasions at locations of high elevation and temperature.
3. In compacting materials consisting of shales, sandstones, weathered rock
and similar random materials, consideration should be given to specifying sheepfoot-type
tamping equipment that has been modified by replacing the standard feet with
"chisel" point tamper feet generally referred to as "shale breakers". The end
areas of these modified tamper feet range from 650 to 1000 square mm (1 to 1-1/2
square inches) and tend to break up weathered rock to prevent the bridging effect
sometimes created by large rock particles.
4. For compaction of sand and gravel fills or filter and drainage layers, equipment
characteristics for both a large and small vibratory roller have been provided
for optional selection by the designer, depending upon location, selected lift
thickness, gradation, grain shape, and durability properties of the materials.
The smaller roller, which utilizes an upper limit of 40 kN/m (9000 lbs. per
foot) of drum length applied force, should be specified for materials which
exhibit degradation under compaction. Other options, based on construction
experience may also be exercised. For example, it has been found that improved
trafficability can often be achieved when compacting clean, fine grained, uniform
sands by specifying a drum driven self-propelled vibratory roller.
Compaction equipment shall conform to the following requirements and shall be used as prescribed in
subsequent paragraphs.
3.20.1.1 Tamping Rollers
Tamping rollers shall be as follows:
a. Towed -Tamping rollers shall consist of a heavy duty double drum unit, with a drum diameter not less
than 1.5 m 60 inches, and an individual drum length of not less than 1.5 m 60 inches. The drums shall
be capable of being ballasted with water or a combination of sand and water. Each drum shall have staggered
feet uniformly spaced over the cylindrical surface such as to provide approximately three tamping feet
for each 0.19 square meter 2 square feet of drum surface. The tamping feet shall be 175 to 225 mm 7
to 9 inches in clear projection from the cylindrical surface of the roller and shall have a face area
of not less than 3226 square mm 5 square inches nor more than 4516 square mm 7 square inches. The roller
shall be equipped with cleaning fingers, so designed and attached as to prevent the accumulation of material
between the tamping feet, and these cleaning fingers shall be maintained at their full length throughout
the periods of use of the roller. The weight of the roller shall not be less than 5200 kg/m 3500 psf
of linear drum length weighted, and shall not be more than 2975 kg/m 2000 psf of drum length empty.
The two drums comprising one roller unit shall be yoked such that they will oscillate when traversing
uneven surfaces. The design and operation of the tamping roller shall be subject to the approval of
the Contracting Officer who shall have the right at any time during the prosecution of the work to direct
such repairs to the tamping feet, minor alterations in the roller and variations in the weight as may
be found necessary to secure optimum compaction of the earth fill materials. The Contractor may be required
to add ballast to the roller to the maximum capacity specified by the manufacturer of the roller. The
roller shall be drawn by a crawler-type or a rubber-tired tractor at a speed not to exceed 5.6 km 3.5
miles per hour. The use of the rubber-tired tractor shall be discontinued if the tires leave ruts that
prevent uniform compaction by the tamping roller. If tamping rollers are used in tandem, not more than
two rollers in tandem will be permitted and in such case, one trip of the tandem rollers over any surface
will be considered as two passes. When tamping rollers are used in tandem, the tamper foot spacing shall
be offset so that the circumferential rows on the rear drums are in line with the mid-point of the circumferential
rows on the forward drums.
b. Self-propelled - [Conditioned upon satisfactory performance, self-propelled tamping rollers may be
used in lieu of tractor-drawn tamping rollers. Self-propelled rollers exceeding the empty weight requirement
may be used provided that by the substitution of tamping feet, having a face area not exceeding [_____]
[9030 square mm 14 square inches], the nominal foot pressure on the tamping feet of the self-propelled
roller can be adjusted to approximate the nominal foot pressure of the towed roller for the particular
working condition required for the towed rollers. The tamping feet shall be 175 to 225 mm 7 to 9 inches
in clear projection from the cylindrical surface of the roller. For self-propelled rollers, in which
steering is accomplished through use of rubber-tired wheels, the tire pressure shall not exceed [_____]
[276 kPa 40 psi]. Self-propelled rollers shall be operated at a speed not to exceed 5.6 km 3.5 miles
per hour.] [Self-propelled tamping rollers may be used in lieu of tractor drawn tamping rollers provided
the foot pressure on the tamping feet of the self-propelled roller are approximately the same as the
foot pressure on the towed roller. For self-propelled rollers steered with rubber-tired wheels, the
tire pressure shall not exceed [_____] [276 kPa 40 psi]. Self-propelled rollers shall be operated at
speeds not exceeding 5.6 km 3.5 miles per hour. The Contracting Officer has the authority to limit or
eliminate the use of self-propelled rollers if they are found to cause shearing or laminations of the
compacted fill.]
3.20.1.2 Vibratory Rollers
Vibratory rollers for compacting rock fills, pervious sand and gravel fills, or filter and transition drainage
layers shall be equipped with a smooth steel compaction drum and shall be operated at a frequency of vibration
during compaction operations between 1100 and 1500 vpm. Vibratory rollers may be either towed or self-propelled
and shall have an unsprung drum weight that is a minimum of 60 percent of the rollers' static weight. Towed
rollers shall have at least 90 percent of their weight transmitted to the ground through the compaction drum
when the roller is standing in a level position hitched to the towing vehicle. Rollers for compacting rockfill,
[sand and gravel fills, or filter and drainage layers] shall have a minimum static weight of 90 kN 20,000 pounds
, a minimum dynamic force of 180 kN 40,000 pounds when operating at 1400 vpm, and an applied force not less than
130 kN/m 9,000 pounds per foot of compaction drum length.[ Rollers for compacting sand and gravel fills or
filter and drainage layers shall have a minimum static weight of 36 kN 8,000 pounds, a minimum dynamic force
of 71 kN 16,000 pounds when operating at 1400 vpm, and an applied force not less than 22 kN 5,000 pounds nor
greater than 130 kN/m 9,000 pounds per foot of compaction drum length.] The level of amplitude and vibration
frequency during compaction will be maintained uniform throughout the embankment zone within which it is operating.
Rollers shall be operated at speeds not to exceed 2.4 km/h 1.5 mph. The equipment manufacturer shall furnish
sufficient data, drawings, and computation for verification of the above specifications, and the character and
efficiency of this equipment shall be subject to approval.
3.20.1.3 Rubber-tired Rollers
Rubber-tired rollers shall have a minimum of four wheels equipped with pneumatic tires. The tires shall be of
such size and ply as to be capable of being operated at tire pressures between 550 and 690 kPa 80 and 100 psi
at an 11,340 kg 25,000 pound wheel load. The roller wheels shall be located abreast and so designed that each
wheel will carry approximately equal load in traversing uneven ground. The spacing of the wheels shall be such
that the distance between the nearest edges of adjacent tires will not be greater than 50 percent of the rated
tire width of a single tire at the operating pressure for an 11,340 kg 25,000 pound wheel load. The roller shall
be provided with a body suitable for ballast loading such that the load per wheel may be varied, as directed
by the Contracting Officer, from 8,165 to 11,340 kg 18,000 to 25,000 pounds. The roller shall be towed at a
speed not to exceed 8 km 5 miles per hour. The character and efficiency of this equipment shall be subject to
the approval of the Contracting Officer.
3.20.1.4 Hand Operated Compactors
Compaction of material, in areas where it is impracticable to use a roller or tractor compaction shall be performed
by the use of approved hand operated power compactors.
a. Power Tampers: Power tampers shall be hand operated equipment capable of compacting material in
confined areas. The compactors shall be either an internal combustion or pneumatic activated tamper.
Tampers shall have sufficient weight and striking power to produce the specified compaction. The character
and efficiency of this equipment shall be subject to the approval of the Contracting Officer.
b. Vibratory Plate Compactor: Vibratory compactors operated by hand in confined areas shall utilize
the oscillating cam principal and shall deliver an impact of not less than 9 kN 2000 lbf at a rate of
approximately 2000 impulses per minute. The character and efficiency of this equipment shall be subject
to the approval of the Contracting Officer.
3.20.1.5 Crawler-type Tractors
Crawler-type tractors used for spreading or compaction shall weigh not less than [_____] [9,070] kg [_____] [20,000]
pounds, shall exert a unit tread pressure of not less than [_____] [41.4] kPa [_____] [6] psi, and shall be operated
at a speed not to exceed [_____] [5.6] km [_____] [3.5] miles per hour.
3.20.1.6 Sprinkling Equipment
Sprinkling equipment shall consist of tank trucks, pressure distributors or other equipment designed to apply
water uniformly and in controlled quantities to variable width of surface.
3.20.1.7 Miscellaneous Equipment
Scarifiers, disks, spring-tooth or spike-tooth harrows, spreaders, and other equipment shall be suitable for
use in embankment construction and approved by the Contracting Officer. Equipment used for blending fill material
shall be capable of penetrating the full loose lift thickness of the specific material type.
3.20.2 Compaction of Select Fill
NOTE: Experience indicates that by the time the surface lift has been laid
down, sufficient compactive effort has occurred due to hauling and spreading
equipment such that one, two, or even three passes of a heavy disk plow is not
sufficient for penetrating the full depth of lift. A harrow equipped with closely
spaced spikes (teeth) has been found to effectively penetrate the semi-compacted
surface lift in one pass, but this type of device has minimal ability to blend
and mix the fill material. It was found that a suitably designed spiked-tooth
harrow working in combination with a heavy disk plow can reliably produce the
desired result. This note applies to all types of fill placement for which
moisture and blending are required.
After a layer of material has been dumped and spread, it shall be harrowed to break up and blend the fill materials
and to obtain uniform moisture distribution. Harrowing shall be performed with a heavy disk plow, or other approved
harrow, to the full depth of the layer. If one pass of the harrow does not accomplish the breaking up and blending
of the materials, additional passes of the harrow shall be required, but in no case will more than [_____] [three]
passes of the harrow on any one layer be required for this purpose. When the moisture content and the condition
of the layer are satisfactory, the lift shall be compacted [to a minimum of [95] [_____] percent of the maximum
dry density as determined by the Contractor in accordance with ASTM D 698] [with not less than [six] [_____]
complete coverages of an approved tamping roller or [four] [_____] complete coverages of an approved 45 metric
ton 50-ton rubber-tired roller traversing in a direction parallel to the axis of the levee]. In areas which
are not accessible by roller, the fill shall be placed in layers not more than 100 mm 4 inches in uncompacted
depth and compacted with an approved hand operated compactor to a density equal to that obtained in other areas
which are accessible to rollers. Dumping, spreading, sprinkling, and compacting may be performed at the same
time at different points along a section when there is sufficient area to permit these operations to proceed
simultaneously. Compaction equipment shall be operated such that the strip being traversed by the roller shall
overlap the rolled adjacent strip by not less than [_____] [1] m [_____] [3] feet.
3.20.3 Compaction of Random Fill
NOTE: Random fill shall be compacted in accordance with the requirements of
the material type it most closely approximates in behavior.
After a layer of material has been dumped and spread, it shall be harrowed to break up and blend the fill materials
and to obtain uniform moisture distribution. Harrowing shall be performed with a heavy disk plow, or other approved
harrow, to the full depth of the layer. If one pass of the harrow does not accomplish the breaking up and blending
of the materials, additional passes of the harrow shall be required, but in no case will more than [_____] [three]
passes of the harrow on any one layer be required for this purpose. When the moisture content and the condition
of the layer are satisfactory, the lift shall be compacted [to a minimum of [95] [_____] percent of the maximum
dry density as determined by the Contractor in accordance with ASTM D 698] [with not less than [six] [_____]
complete coverages of an approved tamping roller or [four] [_____] complete coverages of an approved 45 metric
ton 50-ton rubber-tired roller traversing in a direction parallel to the axis of the levee]. In areas which
are not accessible by roller, the fill shall be placed in layers not more than 100 mm 4 inches in uncompacted
depth and compacted with an approved hand operated compactor to a density equal to that obtained in other areas
which are accessible to rollers. Dumping, spreading, sprinkling, and compacting may be performed at the same
time at different points along a section when there is sufficient area to permit these operations to proceed
simultaneously. Compaction equipment shall be operated such that the strip being traversed by the roller shall
overlap the rolled adjacent strip by not less than [_____] [1] m [_____] [3] feet.
3.20.4 Compaction of Impervious Fill
After a layer of material has been dumped and spread, it shall be harrowed to break up and blend the fill materials
and to obtain uniform moisture distribution. Harrowing shall be performed with a heavy disk plow, or other approved
harrow, to the full depth of the layer. If one pass of the harrow does not accomplish the breaking up and blending
of the materials, additional passes of the harrow shall be required, but in no case will more than [_____][three]
passes of the harrow on any one layer be required for this purpose. When the moisture content and the condition
of the layer are satisfactory, the lift shall be compacted with not less than [six][_____] complete coverages
of an approved tamping roller traversing in a direction parallel to the axis of the levee. If the desired compaction
to a minimum of [95][_____] percent of the maximum dry density as determined by the Contractor in accordance
with ASTM D 698 is not achieved, additional rolling will be required. In areas which are not accessible by roller,
the fill shall be placed in layers not more than 4 inches in uncompacted depth and compacted with an approved
hand operated compactor to a density equal to that obtained in other areas which are accessible to rollers.
Dumping, spreading, sprinkling, and compacting may be performed at the same time at different points along a
section when there is sufficient area to permit these operations to proceed simultaneously. Compaction equipment
shall be operated such that the strip being traversed by the roller shall overlap the rolled adjacent strip by
not less than [_____] [1] meter [_____] [3] feet.
3.20.5 Compaction of Pervious Fill
After a layer of material has been dumped and spread it shall be harrowed as required to break up and blend the
fill materials and to obtain uniform moisture distribution. Harrowing shall be performed with a heavy disk plow,
or other approved harrow, to the full depth of the layer. If one pass of the harrow does not accomplish the
breaking up and blending of the materials, additional passes of the harrow shall be required, but in no case
will more than [_____] [three] passes of the harrow on any one layer be required for this purpose. When the
moisture content and the condition of the layer are satisfactory, the lift shall be compacted to a [minimum [80]
[_____] percent relative density in accordance with ASTM D 4253 and ASTM D 4254] [with not less than [six] [_____]
complete coverages of an approved vibratory roller]. In areas which are not accessible by roller, the fill shall
be placed in layers not more than 100 mm 4 inches in uncompacted depth and compacted with an approved hand operated
compactor to a density equal to that obtained in other areas which are accessible to rollers. Dumping, spreading,
sprinkling, and compacting may be performed at the same time at different points along a section when there is
sufficient area to permit these operations to proceed simultaneously. Compaction equipment shall be operated
such that the strip being traversed by the roller shall overlap the rolled adjacent strip by not less than [____]
[1] m [_____] [3] feet.
3.20.6 [Compaction of Random Rock]
After the random rock has been placed and spread to the thickness specified herein, and oversized rock has been
removed or broken down, compaction shall be accomplished by not less than [_____] [3-6] complete coverages of
the specified [crawler tractor] [vibratory roller]. [ Each coverage of the tractor shall consist of sufficient
trips to provide complete coverage of the area by the treads of the tractor. The tractor coverages specified
shall be in addition to spreading operations.] [ The vibratory roller shall be operated such that the strip being
traversed by the roller shall overlap the rolled adjacent strip by not less than [_____] [1] m [_____] [3] feet
.]
3.20.7 Compaction of Semicompacted Fill
[After a layer of material has been dumped and spread it shall be harrowed as required to break up and blend
the fill materials and to obtain uniform moisture distribution. Harrowing shall be performed with a heavy disk
plow, or other approved harrow, to the full depth of the layer. If one pass of the harrow does not accomplish
the breaking up and blending of the materials, additional passes of the harrow shall be required, but in no case
will more than [_____] [three] passes of the harrow on any one layer be required for this purpose.] [ When the
moisture content and the condition of the layer are satisfactory, the lift shall be compacted by not less than
[four] [_____] complete coverages of a tamper-type roller, or by not less than [three] [_____] complete coverages
of a crawler-type tractor, or by not less than [two] [_____] complete coverages of a rubber-tired roller, all
conforming to the requirements of paragraph EQUIPMENT.] [In areas which are not accessible by roller, the fill
shall be placed in layers not more than 100 mm 4 inches in uncompacted depth and compacted with an approved hand
operated compactor to a density equal to that obtained in other areas which are accessible to rollers.] [After
preparation of the previous compacted layer to receive the new layer of fill the new layer shall be compacted
by the controlled movement of the hauling equipment over the area of the fill.] Equipment shall be routed so
as to prevent excessive rutting of the fill surface. Dumping, spreading, sprinkling, and compacting may be performed
at the same time at different points along a section when there is sufficient area to permit these operations
to proceed simultaneously.
3.20.8 Compaction of Uncompacted Fill
No compaction other than that obtained by the controlled movement of the hauling equipment over the area of the
fill is required. Equipment shall be routed so as to prevent excessive rutting of the fill surface.
3.20.9 Compaction of Hydraulic Fill
Hydraulic fill shall be compacted as uncompacted fill. If the rehandled hydraulic fill is too dry to permit
its placement by uncompacted full method, then the fill material shall be compacted using the method specified
in paragraph [_____] [COMPACTION OF SEMICOMPACTED FILL].
3.20.10 [Compaction of Random Fill Within the MSE Walls
Random earth fill within the limits of the Mechanically Stabilized Earth (MSE) walls shall be placed and compacted
in accordance with [the vendor's requirements, subject to the approval of the Contracting Officer] [requirements
specified in Section [_____]].]
3.20.11 Compaction of Coarse Drainage Gravel and Filter Sand
Coarse drainage gravel placed in the drains shall be placed in maximum [_____] [300] mm [_____] [12] inch loose
lifts and compacted by not less than four (4) complete coverages with a [static] [vibratory] roller. Each lift
of gravel within confined spaces which is not accessible to rollers shall be compacted by at least [_____] [3]
complete coverages with a vibratory plate compactor [and as many additional coverages as necessary to achieve
the same density obtained with full-size compaction equipment]. Filter sand placed along the existing rock fill
shall be compacted in accordance with the requirements for the adjacent select earth fill material.
3.20.12 Compaction of Fine Drainage Gravel
Fine drainage gravel placed in the drains shall be placed in maximum [_____] [300] mm [_____] [12] inch loose
lifts and compacted by not less than four (4) complete coverages with a [static] [vibratory] roller. Each lift
of gravel within confined spaces which is not accessible to rollers shall be compacted by at least three [_____]
[3] complete coverages with a vibratory plate compactor [and as many additional coverages as necessary to achieve
the same density obtained with full-size compaction equipment].
3.20.13 Compaction Adjacent to Structures and Utilities
Heavy equipment for spreading and compacting fill shall not be operated within [_____] [1] m [_____] [4] feet
of structures or utilities, except as otherwise specified herein. Material within [_____] [1] m [_____] [4]
feet shall be compacted using appropriate hand operated compactors specified herein.
3.20.14 [Additional Rolling for Compaction
NOTE: Use the following paragraph only when a method specification is utilized.
A bid item for "Additional Rolling for Compaction" should be included in the
bid form so that payment can be made. Measurement and payment information should
also be added to paragraph [UNIT][LUMP SUM] PRICES or Section 01270A MEASUREMENT
AND PAYMENT as applicable.
If the Contracting Officer determines that the desired compaction of any portion of the embankment is not achieved
by the number of coverages specified, additional complete coverages shall be made over the surface area as directed
by the Contracting Officer. Payment for additional rolling directed by the Contracting officer shall be made
in accordance with Bid Item No. [_____] ADDITIONAL ROLLING FOR COMPACTION; however, no payment will be made for
additional rolling not specifically directed by the Contracting Officer.]
3.20.15 [Topsoil
Topsoil shall be placed on the embankment surfaces as shown on the contract drawings and as specified in SECTION
[
02922
02922
02922 SODDING] [_____]].
3.21 FIELD QUALITY CONTROL
NOTE: FAR Part 46.312 establishes a requirement for Contractor Quality Control
(CQC) in construction contracts and ER 1180-1-6 requires that a CQC section
based on UFGS-01451A ContractorR QUALITY CONTROL be included in contracts of
$1,000,000 or more. Use of UFGS-01451A for contracts of less than $1,000,000
is discretionary. This part of the specifications must be consistent with the
CQC section.
Use caution when applying nuclear gages for in-place density measurement of
cohesive and cohesionless soils. Soils consisting of mica, halloysite, some
other chemical composition, or oversize rocks and large voids would affect the
measurement accuracy of wet density. The chemical composition and "non-free"
water of the sample may also dramatically (sometimes over 10 percent) affect
the measurement of moisture content (see the paragraph entitled "Interferences"
in ASTM D2922 and D3017. Also see paragraph 5-10.d.(2).(b). entitled "Nuclear
Method" in EM 1110-2-1911). When water content can not be accurately measured
using nuclear method, a computer controlled microwave oven system for water
content measurement combined with nuclear method for wet density has been successfully
used by some districts. Sand Cone or similar field density tests should be
performed periodically at the same location as Nuclear Tests to assure nuclear
testing is providing accurate information.
3.21.1 Clearing, Grubbing, and Stripping
The Contractor shall establish and maintain quality control for clearing, grubbing, and stripping operations
to assure compliance with contract requirements, and maintain records of the quality control for all construction
operations including but not limited to the items indicated below. These records, as well as the records of
corrective actions taken, shall be furnished to the Government in accordance with Section
01451A
01451A
01451A ContractorR
QUALITY CONTROL.
3.21.1.1 Clearing
Station to station limits, transverse clearing limits from applicable centerline; percentage of area complete;
types of materials cleared.
3.21.1.2 Grubbing
Station to station limits, transverse grubbing limits from applicable centerline; percentage of area complete;
type of material; filling of grubbed holes.
3.21.1.3 Stripping
Station to station limits, transverse stripping limits from applicable centerline; percentage of area complete;
type of material; depth of stripping.
3.21.2 Excavation
The Contractor shall establish and maintain quality control for excavation operations to assure compliance with
contract requirements, and maintain records of the Contractor's quality control for all construction operations
including but not limited to the following:
a. Lines, grades and tolerances,
b. Segregation of materials,
c. Disposal and/or stockpiling of materials,
d. Unsatisfactory materials,
e. Conditions that may induce seepage or weaken the foundation or embankment,
f. Stability of excavations.
Records of inspections and tests, as well as the records of corrective actions taken, shall be furnished to the
Government in accordance with Section
01451A
01451A
01451A ContractorR QUALITY CONTROL.
3.21.3 Embankment
3.21.3.1 General
[As a part of the Contractor Quality Control (CQC) system required by SECTION
01451A
01451A
01451A ContractorR QUALITY CONTROL,
the] [The] Contractor shall establish and maintain field quality control for foundation preparation, embankment
and backfill operations to assure compliance with contract requirements and maintain detailed records of field
quality control for all operations including but not limited to the following:
a. Earthwork Equipment
Type, size, number of units and suitability for construction of the prescribed work.
b. Foundation Preparation
Methods of preparing the foundations in advance of embankment and backfill construction and
methods for providing drainage of the foundation and partially completed fills.
3.21.3.2 Materials Testing
NOTE: Types of tests and frequency of testing should be detailed below. Types
of tests and frequency of testing will be dependent upon the types of materials
utilized, configuration of foundation and embankment, placement and compaction
procedures required, moisture control requirements etc. Testing requirements
are material type specific rather than embankment fill type specific.
The Contractor shall perform sufficient testing to insure that the fill is being constructed as specified. The
testing program specified below shall be considered the minimum acceptable frequency of testing. This does not
relieve the Contractor from the responsibility of performing additional testing, if required to ensure compliance
with these specifications.
[a. Soil Classification Tests
Soil classification tests shall be performed in accordance with ASTM D 2487. One initial classification
test shall be required for each different classification of material to be utilized as embankment
fill or backfill. As prescribed in ASTM D 2487, grain size analyses in accordance with ASTM D 422
and Atterberg limits in accordance with ASTM D 4318 shall be performed on each different classification.
The Contractor shall submit additional tests for every [_____] cubic m cubic yards of embankment
or backfill material. Soil classification tests shall be performed on foundation material as
required to determine the acceptability of the in-situ soils. Additional tests will be required
if noticeable changes in the material occur.]
b. Cohesive Material Testing
NOTE: Edit the following to comply with the method selected to determine the
optimum properties (i.e., density and moisture content).
(1) Moisture Density Relationships. The moisture-density relations for each different classification
of cohesive material utilized shall be determined in accordance with [_____] [ASTM D 698], [Method
A] [Method B] [Method C].[ Prior to placing any fill material containing cohesive material,
a minimum of [_____] (5) five-point [_____] compaction test shall be performed on representative
samples of the material to be used as fill.] During fill placement a minimum of one additional
moisture-density test shall be performed for every [_____] cubic m cubic yard placed. Additional
tests will be required each time a new material is encountered.[ The moisture-density curves
will be compiled to form a family of curves which will be utilized to estimate optimum properties
(maximum dry density and optimum moisture content) to be used with field density test.]
(2) Water (Moisture) Content Tests. Determination of water content shall be performed in accordance
with ASTM D 2216.[ ASTM D 4643 may be used when rapid moisture content results are needed.
All rapid results obtained by ASTM D 4643 shall be confirmed by a test on a duplicate sample
performed in accordance with ASTM D 2216. In the event of disagreement between the results,
ASTM D 2216 shall govern.] One water content test will be performed for each [_____] cubic
m cubic yards of material placed [or each lift of material whichever is less].[ These test
will be in addition to the water content tests performed in conjunction with in-place density
tests.] Backfill and fills not meeting the required specifications for water content shall
be retested after corrective measures have been applied.
NOTES: The designer should pick the method or methods of In-place density which
are acceptable. If uncompacted fill is specified density control may not be
required.
Use caution when applying nuclear gages for in-place density measurement of
cohesive and cohesionless soils. Soils consisting of certain chemical composition,
or oversize rocks and large voids would affect the measurement accuracy of wet
density. The chemical composition and "non-free" water of the sample may also
dramatically (sometimes over 10 percent) affect the measurement of moisture
content (see the paragraph entitled "Interferences" in ASTM D2922 and D3017.
Also see paragraph 5-10.d.(2).(b). entitled "Nuclear Method" in EM 1110-2-1911).
When water content can not be accurately measured using nuclear method, a computer
controlled microwave oven system for water content measurement combined with
nuclear method for wet density has been successfully used by some districts.
(3) In-place Density Testing for Cohesive Materials. The in-place density of the cohesive
materials shall be determined in accordance with [ASTM D 1556] [, ASTM D 2167] [, ASTM D 2922
] [, ASTM D 2937] [, or ] [ASTM D 5195]. At least one (1) in-place density test shall be performed
on [each lift of material or] every [_____] cubic m cubic yards of completed fill whichever
is more frequent with the horizontal locations randomly staggered in the fill.[ At each field
density test location, soil samples shall be obtained and one [one-point] [two-point] compaction
test, one moisture content, [one grain size analysis,] [ and one Atterberg limits test,] [if
applicable,] shall be performed on the sample.] [ The results of the [one-point] [two-point]
compaction test and the moisture content test will be utilized to obtain the optimum properties
to compare to the results of the in-place density test.] [ For use with the family of curves
to determine the optimum properties of the material a [one-point] [two-point] compaction tests
shall be performed in conjunction with each in-place density. A portion of the soil from the
in-place field density test and soil obtained immediately adjacent to the field density test
location shall be used for a [one-point] [two-point] compaction test. The minus 19 mm 3/4-inch
portion of the soil shall be subjected to [_____] compactive effort using a 150 mm 6-inch compaction
mold in accordance with the procedures presented in ASTM D [_____] [ASTM D 698] [ASTM D 1557
]]. Fill not meeting the required specifications for in-place density shall be retested after
additional compaction has been completed.[ When nuclear method is used for in-place density
testing according to ASTM D 2922 and ASTM D 3017, the first test and every tenth test thereafter
for each material type shall include a sand cone correlation test in accordance with ASTM D 1556
. The sand cone test shall be performed adjacent to the location of the nuclear test, shall
include a nominal 150 mm 6 inch diameter sand cone, and shall include a minimum wet soil weight
of 2.7 kg 6 pounds extracted from the hole. Nuclear density testing equipment shall not be
used during rain. The density correlations shall be submitted with test results. Each transmittal
including density test data shall include a summary of all density correlations for the job
neatly prepared on a summary sheet including at a minimum:
(i) Meter serial number and operators initials.
(ii) Standard count for each test.
(iii) Material type.
(iv) Probe depth.
(v) Moisture content by each test method and the deviation.
(vi) Wet density by each test method and the deviation.]
[c. Cohesionless Material Testing
(1) Compaction Tests. The Contractor shall run not less than one relative density test for
every [3,000] [_____] cubic m 3,900 [_____] cubic yards of cohesionless fill in accordance with
ASTM D 4253 and ASTM D 4254.
(2) In-Place Density Tests. The in-place density of the cohesionless materials shall be determined
in accordance with [ASTM D 1556] [, ASTM D 2167] [, ASTM D 2922] [, ASTM D 2937] [, or] [ASTM D 5195
]. The Contractor shall run not less than one (1) field in-place density test on [each lift
of material or] every [_____] cubic m cubic yards of completed embankment fill or backfill whichever
is less. Horizontal locations shall be randomly staggered in the fill.[ When nuclear method
is used for in-place density testing according to ASTM D 2922 and ASTM D 3017, the first test
and every tenth test thereafter for each material type shall include a sand cone correlation
test in accordance with ASTM D 1556. The sand cone test shall be performed adjacent to the
location of the nuclear test, and shall include a nominal 150 mm 6 inch diameter sand cone,
and shall include a minimum wet soil weight of 2.7 kg 6 pounds extracted from the hole. The
density correlations shall be submitted with test results. Each transmittal including density
test data shall include a summary of all density correlations for the job neatly prepared on
a summary sheet including at a minimum:
(i) Meter serial number and operators initials.
(ii) Standard count for each test.
(iii) Material type.
(iv) Probe depth.
(v) Moisture content by each test method and the deviation.
(vi) Wet density by each test method and the deviation.]
[(3) Water (Moisture) Content Tests. Determination of water content shall be performed in
accordance with ASTM D 2216.[ ASTM D 4643 may be used when rapid moisture content results are
needed. All rapid results obtained by ASTM D 4643 shall be confirmed by a test on a duplicate
sample performed in accordance with ASTM D 2216. In the event of disagreement between the results,
ASTM D 2216 shall govern.] One water content test will be performed for each [_____] cubic
m cubic yards of material placed [or each lift of material whichever is less].[ These test
will be in addition to the water content tests performed in conjunction with in-place density
tests.] Backfill and fills not meeting the required specifications for water content shall
be retested after corrective measures have been applied.]]
d. Additional Testing
The Contracting Officer may request additional tests if there is reason to doubt the adequacy
of the compaction, or special compaction procedures are being used, or materials change or if
the Contracting Officer determines that the Contractor's testing is inadequate or the Contractor
is concentrating backfill and fill operations in a relatively small area.
3.21.3.3 Materials
Suitability of materials for use in embankment and backfill.
3.21.3.4 Fill Placement
Layout, maintaining existing drainage, moisture control, thickness of layers, removal of oversized material,
spreading and compaction for embankment and backfill.
3.21.3.5 Grade and Cross Section
Surveys to verify that the dimensions, slopes, lines and grades conform to those shown on the drawings.[ Surveys
to monitor settlement gages to measure foundation settlement.] [ Surveys to locate core boring locations and
elevations to determine foundation settlement.]
3.21.3.6 Testing by the Government
During the life of this contract, the Government [or its Contractors] will perform quality assurance tests.
The Contractor shall make available to the government [or its Contractors] the equipment to perform these test.
3.21.3.7 Reporting
[On a daily basis, the] [The] Contractor shall furnish the inspection records and all material testing results,
[the quantity of fill placed,] as well as the records of corrective action taken, in accordance with Section
01451A
01451A
01451A ContractorR QUALITY CONTROL.
-- End of Section --