File celias_sheet2.txt -- Last modified Tue Aug 29 16:53:12 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: CELIAS Block 2 2. BLOCK IDENTIFICATION: CELIAS HV Turn-on 3. PURPOSE: Prepare CELIAS for Observations 4. SUB-BLOCKS: NR. IDENTIFICATION 2.1 STOF Initial Configuration 2.2 MTOF Initial Configuration 2.3 MTOF Initial HV Turn-on 2.4 MTOF HV Turn-on Continued 2.5 MTOF HV Commands 2.6 CTOF, MTOF, STOF HV Commands 2.7 Continue HV Turn-on 2.8 Continue MTOF HV Turn-on 2.9 Continue HV Turn-on 2.10 Continue HV Turn-on 2.11 Continue HV Turn-on 2.12 Continue HV Turn-on 2.13 Continue HV Turn-on 2.14 Continue HV Turn-on 2.15 Continue HV Turn-on 2.16 Continue HV Turn-on 2.17 Continue HV Turn-on 2.18 Continue HV Turn-on 2.19 Continue HV Turn-on 5. SUB-BLOCKS TABLE: NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 2.1 0:20 1.12 PRO, NRT-d H None 2.2 0:20 1.13 PRO, NRT-d H None 2.3 2:30 Nom PRO, NRT-d H None 2.4 2:00 Nom PRO, NRT-d H None 2.5 0:45 Nom PRO, NRT-d H None 2.6 6:20 Nom PRO, NRT-d H None 2.7 8:00 Nom PRO, NRT-d H None 2.8 8:00 Nom PRO, NRT-d H None 2.9 8:00 Nom PRO, NRT-d H None 2.10 8:00 Nom PRO, NRT-d H None 2.11 8:00 Nom PRO, NRT-d H None 2.12 4:00 Nom PRO, NRT-d H None 2.13 0:30 Nom PRO, NRT-d H None 2.14 1:30 Nom PRO, NRT-d H None 2.15 0:30 Nom PRO, NRT-d H None 2.16 0:30 Nom PRO, NRT-d H None 2.17 1:30 Nom PRO, NRT-d H None 2.18 0:30 Nom PRO, NRT-d H None 2.19 1:30 Nom PRO, NRT-d H None 6. SCHEDULING REQUIREMENTS: 2.1 Could be done right after 1.12, better wait until MCC2 and Block 1 are completed 2.2 Could be done right after 1.13, better wait until MCC2 and Block 1 are completed 2.3 Same day as 2.2 or later 2.4 day after 2.3 2.5 day after 2.4 2.6 same day as 2.5 2.7 - 2.13 each one day after predecessor 2.14 same day, wait at least 1:00 after 2.13. includes 1:00 evaluation time. 2.15 one day after 2.14 2.16 same day as 2.15, wait at least 0:30 after 2.15 2.17 same day as 2.16, wait at least 1:00 after 2.16, includes 1:00 evaluation time 2.18 one day after 2.17 2.19 same day as 2.18, wait at least 0:30 after 2.18, includes 1:00 evaluation time 7. SPECIAL REQUIREMENTS: (see Note 4) Coordination with FOT required 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: CELIAS HVs on, CELIAS ready for observations (?) 9. RELEVANT PROCEDURES: TBD by CELIAS Team 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) TBP by CELIAS Team 11. RELEVANT SECTION OF TIMELINE 16 & 20:10 # CELIAS # 2.01 STOF Initial Configuration # 0:20, could be scheduled for after end of 1.12, Procs and NRT-d ; DAY 22 ; * REQUEST FOR REVISION * MTOF requires additional HV turn on time, over at ; least nine days, as originally requested in the CELIAS 4.0 timeline. ; Request 3 hour period on day 22, does not need to be all at one time, but ; at least 30 minute command intervals. 22 & # CELIAS # 2.02 Continue MTOF Initial Configuration # 0:20, Procs and NRT-d 22 & # CELIAS # 2.03: CELIAS/MTOF INITIAL HV TURN ON # 2:30, Procs and NRT-d ; DAY 23 ; * REQUEST FOR REVISION * ADD COMMAND TIME! MTOF requires additional HV turn on time, ; over at least nine days, as originally requested in the CELIAS 4.0 timeline. ; Request minimum 2 hour period on day 23 - 4hours would be better! 23 & # CELIAS # 2.04: CELIAS/MTOF INITIAL HV TURN ON # 2:00, Procs and NRT-d ; * REQUEST FOR REVISION * MOVE CTOF BAKEOUT END TO DAY 23. 23 & # CELIAS # 1.14: End CTOF Bakeout # 0:30, Proc's and NRT-d ; DAY 24 ; * REQUEST FOR REVISION * CHANGE OF DATE! Move STOF IFC checkout to before HV ; turn ons. Requires thermal equilibrium. This change affects the time ; allotted to CELIAS HV commands on this day. 24 & 09:00 # CELIAS # 1.15: STOF IFC Checkout # 0:90 minimum, commands at start and end, includes 75 minutes of passive data taking, Procs and NRT-d 24 & 09:15 # CELIAS # 2.05: MTOF HV Commands # 0:45 minimum, Procs and NRT-d ; * REQUEST FOR REVISION * CHANGE OF DATE! Move CTOF intial configuration to before HV ; turn ons. This moves down all the HV test times also. 24 & 10:00 # CELIAS # 1.16: CTOF Initial Configuration # 0:30, at least 1 day after sub-block 1.11 in order to get thermal equilibrium, Proc's and NRT-d 24 & 10:30 # CELIAS # 1.17: End STOF IFC # 0:10, Proc's and NRT-d ; END CELIAS BLOCK 1: initial switch on and checkout 24 & 10:40 # CELIAS # 2.06: CTOF,MTOF,STOF HV commands # 6:20, Proc's and NRT-d ; DAY 25 25 & 09:00 # CELIAS # 2.07: Continue HV Turn-on # 8:00, Proc's and NRT-d ; DAY 26 ; * REQUEST FOR REVISION * ADD HV TIME! request 30 minutes to increase PM ; E/Q. This is needed in order to get the PM fully operational in time to ; be used for CTOF VVPS high voltage turn on. Can use any extra time available to ; facilitate HV turn on. 26 & 09:00 # CELIAS # 2.08: Continue MTOF HV Turn ON # 0:30, Proc's and NRT-d ; DAY 27 27 & 09:00 # CELIAS # 2.09: Continue HV Turn-on # 8:00 ; DAY 28 28 & 09:00 # CELIAS # 2.10: Continue HV Turn-on # 8:00 ; DAY 29 29 & 09:00 # CELIAS # 2.11: Continue HV Turn-on # 8:00, maybe can use just 5:30 hours here. ; DAY 30 ; * REQUEST FOR REVISION * ADD HV TIME! ; DAY 30. NO TIME ASSIGNED TO CELIAS. ; REQUEST for 4 hours of HV commanding 30 & 09:00 # CELIAS # 2.12: Continue HV turn on # 4:00 ; DAY 31 ; * REQUEST FOR REVISION * ADD HV TIME! ; DAY 31. NO TIME ASSIGNED TO CELIAS. ; REQUEST for 2 hours of HV commanding 31 & 09:00 # CELIAS # 2.13: Continue HV turn on # 0:30 31 & 10:30 # CELIAS # 2.14: Continue HV turn on # 0:30, wait at least .5 hour from 2.13, require 1:00 EVALUATION time for possible safety commands ; DAY 32 ; * REQUEST FOR REVISION * ADD HV TIME! ; DAY 32. NO TIME ASSIGNED TO CELIAS. ; REQUEST for 2.5 hours of HV commanding 32 & 09:00 # CELIAS # 2.15: Continue HV turn on # 0:30 32 & 10:30 # CELIAS # 2.16: Continue HV turn on # 0:30, wait at least 0.5 hour from 2.15 32 & 12:00 # CELIAS # 2.17: Continue HV turn on # 0:30, wait at least one hour from 2.16, require another 1:00 EVALUATION time for possible safety commands ; DAY 33 ; * REQUEST FOR REVISION * ADD HV TIME! ; DAY 33. NO TIME ASSIGNED TO CELIAS. ; REQUEST for 2 hours of HV commanding 33 & 09:00 # CELIAS # 2.18 Continue HV turn on # 0:30 33 & 10:30 # CELIAS # 2.19 Continue HV turn on # 0:30, wait at least 0.5 hour from 2.18, require another 1:00 EVALUATION time for possible safety commands