Dear Mr. Grant:

This is in response to your letter of March 14, 1988, to
Michael Petruska, concerning the recycling of nickel, copper,
and chromium-containing electroplating sludges. This is a
complex area of regulation, and you may have misunderstood some
of what Mr. Petruska explained in your March 2 meeting. My
understanding of your operation is that you plan to recycle
electroplating sludges by recovering certain metal values from
dried material produced from sludge dryers. The two key
questions in determining RCRA applicability are: (1) whether
the sludge is listed in 40 CFR Part 261, Subpart D, and (2)
whether the material is processed before use, i.e., "reclaimed".

Although the material will be fed to a metal smelting
furnace, please note that such smelters are considered
reclamation devices, and therefore the exclusions for direct use
or reuse at 40 CFR Section 261.2(e)(1)(i) and (e)(1)(ii) do not
apply. (See 50 FR 633; January 4, 198.) Listed sludges that
are reclaimed are solid waste, while sludges that are hazardous
only because they exhibit a characteristic are not solid waste
when reclaimed. Since electroplating sludges are specifically
listed wastes, these wastes when reclaimed (i.e., processed in a
metal smelting furnace) are subject to the hazardous waste
rules. In particular, the generator and transporter rules apply
when the material is shipped (40 CFR Parts 262 and 263) and the
reclamation facility is subject to 40 CFR Section 261.6(c).
Also, EPA has proposed rules for industrial furnaces in 40 CFR
Part 266, Subpart D. (See 52 FR 16982; May 6, 1987.)


- 2 -

The dried material you plan to market to smelters would be
considered a partially-reclaimed material, because further
processing is required before the metal can actually be used.
If you believe the material is commodity-like after drying, you
may petition the Agency for a variance. (See 40 CFR Sections
260.30(c), and 260.31(c).) Under these provisions, the EPA
Regional Administrator (or, in an authorized State, the Director
of the State's RCRA program) with jurisdiction over the facility
producing the material may grant a variance from classification
of the material as solid waste.1/ The factors that are
relevant in granting the variance are in Section 260.31(c), and
are discussed at 50 FR 655 (January 4, 1985).

In summary, the process you describe would be subject to the
RCRA hazardous waste regulations if listed sludges are
reclaimed. If you seek a variance for the partially-reclaimed
material, you should contact the appropriate EPA Region or State
agency. Finally, I suggest you modify your certificate because
the material would be, as EPA defines the term, "reclaimed".

If you have further questions in this area, please continue
to deal with Mr. Petruska at (202) 475-9888.

Sincerely,


Sylvia K. Lowrance, Director
Office of Solid Waste


1/ The variance is only necessary for listed sludges. As noted
above, characteristic-only sludges are not solid waste when
reclaimed.



!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!