Operating
Experience Summary 2000-03
|
||
Operating Experience Summary 2000-03
February 1 through February 14, 2000
Table of ContentsEVENTS EVENTS |
1. TRACKHOE BUCKET DAMAGED WHILE HAMMERING A CONCRETE PIER
The extrusion plant houses press pits which were used to manufacture uranium billets. Facility management wanted to create additional floor space in the plant by backfilling the press pits with concrete to level the floor. Investigators determined that the technical specification and work request written for the backfilling procedure did not include steps for hammering concrete obstructions with a trackhoe bucket. Refer to Figure 1-1 for an overall view of the trackhoe and bucket. They determined that the trackhoe manufacturer designed the bucket teeth extensions according to industrial equipment standards and did not intend the bucket to used as a substitute for a jackhammer. Refer to Figure 1-2 for details of the damage and the remaining tooth extensions. Investigators determined that the operator discovered the concrete pier obstruction after he started the job and did not follow procedure when he used the fully extended trackhoe arm and bucket to demolish the pier. Investigators also determined that site procedure dictates the use of a jackhammer or concrete saw to complete this type of job. Figure 1-1. Trackhoe used to backfill press pits Figure 1-2. Close-up of bucket with tooth extension This event underscores the importance of an integrated approach to safety that emphasizes individual and management accountability and ownership, implementation of requirements and procedures, and thorough and systematic management oversight. The responsibility to ensure adequate planning and control of work activities resides with line management. Managers should ensure that work control processes are followed and facility practices are enforced. Personnel at DOE facilities should have a continually questioning attitude toward safety issues. Each individual is ultimately responsible for complying with rules to ensure personal safety. Facility managers should communicate the idea that safety is of prime importance and all personnel must be committed to excellence and professionalism. Instructions to workers should emphasize changes in work methods or equipment, or any other deviation from an approved work plan, can introduce unforeseen hazards. Changes to approved work methods, equipment, and plans must receive the same hazard analysis, review, and approval as the original work plan. Any change should entail a work stoppage combined with a thorough review of the potential hazards associated with the change. Personnel at DOE facilities are required to follow established work
control plans without exception. Facility managers, work planners,
and subcontractor supervisors should review the following references, which
provide guidance and good practices for implementing work control plans.
KEYWORDS: trackhoe, improper procedure FUNCTIONAL AREAS: Industrial Safety, Work Planning |
2. FOLLOW UP ON WORKER WHO SUSTAINED HEAD INJURY OPENING JAMMED DUMPSTER DOORS
The report states that the driver of a belly dump truck was attempting to pry open jammed doors with an iron bar to unload stone rip-rap. The doors of the belly dump opened unexpectedly, emptying out the rock contents. The weight of the rocks pushed the iron bar upward, striking the worker and causing a severe skull fracture above his right eye. The driver was transported to a hospital in Grand Junction, Colorado, where he underwent surgery. He is expected to make a full recovery. In 1999, the construction company at the Site was awarded two contracts; one to produce and deliver sand and rock and the other to recontour areas around the Mill Site. The company hired additional trucks and drivers from a local company to haul the stone in order to maintain their production schedule for both contracts. The accident took place during delivery of stone to the stockpile area of the Mill Site. The local company hired the driver and provided him a belly dump truck that had not been used for a year. The driver noticed that the opening mechanism of the doors was not functioning, and he had to pry open the doors with an iron bar to empty the stone rip-rap. The driver was successful in unloading the stones in the first two trips on the day of the incident. The incident occurred on the third trip. The Board’s investigators determined the following causal factors.
The Type B Investigation also noted that four incidents involving scrapers took place at the site between June 1 and September 8, 1999. No personnel were injured or equipment damaged in these events. The root and contributing causes were operator error, lack of management’s awareness of road conditions and equipment failures. Lack of thorough root cause analysis and subsequent lessons learned implementation resulted in inadequate safety training of workers at the site. The complete report of the Type B Accident Investigation Board can be accessed on the web at URL http://tis.eh.doe.gov/oversight/acc_inv/acc_investigations2.html. EH has reported a number of similar incidents in ORPS data system.
The following is an example.
KEYWORDS: head injury, communication, Type B Investigation, barrier analysis, safety training FUNCTIONAL AREAS: Construction Safety, Personnel Protection |
4. FREEZE PROTECTION PROBLEMS CAUSE DAMAGE AND LOSS OF FIRE PROTECTIONInvestigators for the Oak Ridge event determined that the shift supervisor discovered that freezing temperatures had caused a process water line to break and spill process liquid into an unheated basement room. Investigators determined that the temperatures were below freezing and the heating unit in the room was malfunctioning. They also determined that the process water piping ran underground and penetrated the room in a stairwell near the entrance door. The piping did not have any heat tracing or insulation. Investigators also determined that the room had no insulation on the walls or in the roof. The rising water caused two 4,000-gallon tanks, which were not secured, to float to the ceiling and lift the ceiling approximately 18 inches. The roof is a composite of sheet metal with a tar and chip covering and needs to be partially replaced. Investigators discovered that the tanks contained a small amount of aluminum nitrate with a pH of one. Environmental management and operations sampled the spilled water and determined that the spill did not constitute a release hazard. The water was pumped from the room to a dike-protected area to provide access to the damaged area. Investigators determined that a similar incident involving this same process line freezing and rupturing occurred about three years ago with less serious consequences. The investigation also revealed that lessons learned and corrective actions from this previous event had not been effective and contributed to the seriousness of this event. Investigators for the Idaho event determined that a line valve had frozen and failed. A fire water flow alarm was received when a thaw occurred and firewater flowed out of the broken valve. The fire department determined that a drain line froze causing the valve to break and water to flow out the open break. An hourly fire watch was initiated and repairs and corrective actions are being implemented. EH has reported on several freeze-related events in previous Summaries. These events emphasize the importance of timely corrective actions. Following are examples of some freeze protection reported during the
winter months.
Facility managers should review the following guidance and ensure that freeze protection actions are effectively implemented. Facility managers should determine how long buildings could be without power. They should also develop specific contingency plans for connecting temporary power sources, including (1) what size generator is required; (2) where and how to connect power; (3) where to locate and ground a generator; and (4) how to introduce and route generator power cables into buildings. These contingency plans should be detailed and readily available to the personnel installing temporary power; otherwise, workers could introduce additional hazards into the work environment. Several steps can be taken to establish freeze protection for facility
systems equipment. These steps, together with contingency plans for
severe cold should be incorporated into written procedures and periodically
reviewed for adequacy. The following list identifies some typical
inspections that should be performed before the cold weather season begins.
Facility personnel should take the following steps to ensure freeze protection
problems are minimized.
DOE O 4330.4B, Maintenance Management Program, chapter II, section 19, "Seasonal Facility Preservation Requirements," program to prevent equipment and building damage due to cold weather. The Order states that the program should include a freeze protection plan, including details on inspections, preventive maintenance, and corrective maintenance to ensure continued safe facility operations. Section 16, requires a maintenance history and trending program. Maintenance planners, coordinators, supervisors, and craft personnel should use maintenance history on a routine basis to identify previous maintenance work and its results. DOE-STD-1064-94, Guideline to Good Practices for Facility Preservation at DOE Nuclear Facilities, provides guidance to assist facility maintenance organizations in the review of existing methods (and the development of new methods) for establishing a seasonal maintenance program. Section 3.4.1 of the guide includes cold weather preparation information; Appendix A provides an example of a cold weather checklist. This standard also contains guidance for tornadoes, cold weather, flash floods, and other natural disasters. DOE/EH-0213, Cold Weather Protection, October 1991, Safety and Health, Bulletin 91-4, provides insight, actions, and recommendations applicable to sites susceptible to cold weather. This bulletin and others can be found at URL http://www.hss.energy.gov/docs/bull/links.html. Many freeze protection failures are preceded by indicators or lessons learned from previous occurrences. Facility managers may also want to review the following guidelines on lessons learned and corrective actions. DOE-STD-1004-92, Root Cause Analysis Guidance Document, chapter 6, "Corrective Actions," states that proposed corrective actions should be (1) reviewed to ensure the appropriate criteria are met, (2) prioritized based on importance, (3) scheduled, (4) entered into a commitment tracking system, and (5) implemented in a timely manner. It states that a complete corrective action program should be based on specific causes of the occurrence, lessons learned from other facilities, appraisals, and employee suggestions. It states that corrective actions should be tracked to ensure they have been properly implemented and are functioning as intended. It also states that the recurrence of the same similar events must be identified and analyzed and, if the same or similar event recurs, the original occurrence should be investigated to determine why corrective actions were not effective. DOE-STD-1010-92,
Guide to Good Practices for Incorporating Operating Experiences, and DOE-STD-7501-99,
The DOE Corporate Lessons Learned Program, provide guidance on a systematic
approach for incorporating operating experiences. They describe an
approach for implementing the following elements into lessons-learned programs.
FUNCTIONAL AREAS: Operating Experience, Lessons Learned
|
8001 Highway 64E, Knightdale, NC 27545919 266-3671 • FAX 919 217-6625 October 28, 1999
To: Square D Customers and Users of Class 9001 Type SKRU_ Multi-Speed Push Button Operators From: Neil W. Tollas - Director, Logic Control Products SUBJECT: SKRU Multi-Speed Push Button Operators
Square D has become aware from a field report that the Class 9001 Type SKRU2, 3, 4, or 5 multi-speed operators may randomly maintain their actuated state when pressure to the button is released. A small percentage of the units produced between January 1999 and September 1999, may exhibit this condition. Depending on the application, an operator remaining in its actuated state can result in unintended machine operation, leading to a potential for serious personal injury or property damage. The potential problem has been corrected in production beginning the
1st of October.
Recommended Action - Uninstalled Product(s):
Installed Product(s):
Determine the date of manufacturing for your Class 9001 Type SKRU2, 3, 4, or 5 product by checking the date code located on the product. (See attachment A, PRODUCT IDENTIFICATION INSTRUCTIONS) If you identify products with date codes of 9901, 9902, 9903, through 9940, make arrangements for immediate replacement of the operators. Please complete the attached CUSTOMER INFORMATION FORM (Attachment B). List the Type Number and Quantity of products identified. Fax the completed form to (828) 255-1576 or mail it direct to: Square D Company
You will receive replacement operators from Square D at no charge. You must return you old operators to Square D Asheville (at the above address) within 90 days to avoid being invoiced for the replacement operators. Questions regarding return and replacement of subject products should be directed to Bill Crum (828) 255-1383 Direct Line, (828) 255-1576 Fax. This notice is applicable to Class 9001 Type SKRU2, 3, 4, or 5 multi-speed push button operators with date code between 9901 and 9940 as described in the Attachment A – PRODUCT IDENTIFICATION INSTRUCTIONS. Products which are not of the Class, Type, and date codes as described in attachment A are not subject to this notice. We regret any inconvenience this may cause. Sincerely,
Neil W. Tollas
Enclosures:
|
| What's New | Search | Comments | HSS TIS | |
|
|
|
|