Federal Emergency Management Agency Washington, 20472 MEMORANDUM FOR: Regional Directors FROM: SUBJECT: Procedure Memorandum No. 36-Profile Baselines on Digital Flood Insurance Rate Maps with Orthophoto Bases Background: Since Guidelines and Specifications for Flood Hazard Mapping Partners was last updated, several studies performed by Indefinite Delivery Indefinite Quantity Contractors and Cooperating Technical Partners were brought to the attention of the Engineering and Mapping Integrated Program Team (IPT) as being processed without a streamline or profile baseline when orthophotos were used as the base. During the independent quality assurance reviews for these studies, it became apparent that it is necessary to at least show a profile baseline (that matches the streamlines shown on the effective FIRM) on all DFIRMs. The April 2003 version of the Guidelines does not specify that streamlines or profile baselines are required on that are developed using orthophoto bases; rather, the Guidelines states that the streamlines or profile baselines are optional, as indicated below. Appendix C, Subsection C.6.1.5 (Page C-37) of the Guidelines, entitled "Effective Floodplain to New Streamlines,"states the following: The process of fitting unrevised floodplain boundaries to new streamlines likely will result in changes in stream channel distances from the unrevised hydraulic model to the new FIRM. Theses changes shall be addressed by placing a note in the FIRM legend on a case-by-case basis.. (See Appendix of these Guidelines for examples of this note.) Appendix K, Subsection K.4.1.1 (Page K-43) of the Guidelines, entitled "Base Map Types,"states the following: "The assigned Mapping Partner may show vectors that depict studied flooding sources on top of the orthophotos to clarify their locations." For Table Appendix L of the Guidelines, entitled "Guidance for Preparing Draft Digital Data and Database,"states the following on Page L-113: Page 2 of 3 -Procedure Memorandum 36 This table is required for a detailed study when hydrologic and hydraulic models have been developed for reaches of streams. The results of the models are shown on the FIRM. The profile baseline and/or stream centerline may or may not be shown on the FIRM. For Table Appendix L of the Guidelines, entitled "Guidance for Preparing Draft Digital Data and DFIRM Database,"states the following on Page L-347: "Vector streams must always be shown with a vector base map. They may also be shown on raster base maps." Issue: Streamlines and profile baselines are linked to the hydraulic models developed for detailed-study reaches. Without these links, the relationship between the DFJRM, the Flood Profiles, and the Data Table will no longer exist. This will impact the affected communities' ability to use the DFIRM, Flood Profiles, and Data Table for accurate floodplain management and provide property owners accurate information. Therefore, developing a Base Flood Elevation that is accurate and usable for processing Conditional Letters of Map Amendment; Conditional Letters of Map Revision Based on Fill, Letters of Map Amendment; and Letters of Map Revision Based on Fill will be very difficult, if not impossible. Likewise, it will be very difficult, if not impossible, to determine whether revised BFEs for Conditional Letters of Map Revision and Letters of Map Revision tie into effective BFEs at the upstream and downstream ends of the revised reach within the maximum allowable tolerance of 0.5 foot, and to determine whether increases over 1.0 foot between BFEs and the regulatory elevations occur. Action Procedure: This memorandum revises several sections of the April 2003 version of the Guidelines and sets forth a requirement that a profile baseline that matches the baseline used in the effective or new study must be shown on all DFIRMs. The profile baseline can be included in the table as a line with a WATER-TYP of PROFILE BASELINE, or can be added to the table. All mapping partners, including and CTPs, that are tasked with issuing the Preliminary are to produce Preliminary DFIRMs that meet FEMA specifications, including the changes described in this memorandum. If the CTPs cannot meet these specifications, FEMA Regional Office staff should establish a clear plan for how the affected will be brought into compliance with FEMA specifications before the DFIRMs become effective and how that work will be funded. The FEMA Regional Office staff should coordinate the plan with the respective Project Engineer from the Hazard Section at FEMA Headquarters as soon as any temporary deviations from the specifications are identified. cc: See Distribution List or Page 3 of 3 -Procedure Memorandum 36 Distribution List (electronic distribution only) Office of the Mitigation Division Director Risk Assessment Branch Risk Identification Branch Flood Insurance and Mitigation Divisions in FEMA Regional Offices Office of Legislative Affairs Office of General Counsel National Service Provider Systems Engineering and Technical Assistance Contractor Map Service Center