File golf_sheet2.txt -- Last modified Mon Aug 14 14:56:29 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: GOLF, Block 2 2. BLOCK IDENTIFICATION: Channel A functional test and tuning 3. PURPOSE: Verify and tune channel A 4. SUB-BLOCKS: (see Note 1) NR. IDENTIFICATION 5. SUB-BLOCKS TABLE: (see Note 2) NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 2.1 03:30 Nom PRO, NRT-d M None 2.2 00:30 Nom NRT-d M Nom 2.3 00:30 Nom NRT-d M Nom 2.4 00:15 Nom NRT-d M Nom 2.5 00:15 Nom NRT-d M Nom 2.6 00:15 Nom NRT-d M Nom 2.7 00:15 Nom NRT-d M Nom 2.8 00:15 Nom NRT-d M Nom 6. SCHEDULING REQUIREMENTS: (see Note 3) Can wait until early SVM checkout has been concluded. Earliest, day 4. Latest, day 17. If impossible, after MCC2 (do not interrupt for MCC2). Each following subblock on subsequent day, except block 2.3 on same day as block 2.2 with 2:00 hours in between. Block 2.1 can be interrupted after each procedure of approximately 00:30 hours. If it is interrupted, first day must end by running "recovery" sequence which is less than 15 minutes. Any left STOL can be run on another day. 7. SPECIAL REQUIREMENTS: (see Note 4) Coordination with FOT. This operation requires reconfiguration of SVM. 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: Channel A functionally commissioned 9. RELEVANT PROCEDURES Procedures to be run by FOT : 1 - run "x_exp_prep_on" sequence (30 minutes TBC by FOT), 2 - Switch GOLF non-op heaters OFF, 3 - run "g_pwron_m" STOL 4 - run manually from IWS. Equivalent to: "g_comm_a_m" STOL, 5 - run manually from IWS. Equivalent to: "g_comm_bc_m" STOL, 6 - run manually from IWS. Equivalent to: "g_comd_abc_m" STOL, 7 - run manually from IWS. Equivalent to: "g_comd_d_m" STOL, 8 - run manually from IWS. Equivalent to: "g_comd_ef_m" STOL, 9 - run manually from IWS. Equivalent to: "g_comd_g_m" STOL, 10 - run manually from IWS. Equivalent to: "g_comm_ef_m" STOL, only if day 10 is over, 11 - run manually from IWS. Equivalent to: "g_recovery_m" STOL, 12 - run manually from IWS. Equivalent to: "g_observe_m" STOL, This shall be followed by NRT commanding. Described sequence supposes that Channel A is tested first 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) Ask Jacques 11. RELEVANT SECTION OF TIMELINE (backpage) N/A