Wedge/Arch Test with new electronics at B0 - Part II ----------------------------------------------------- * note: ADMEM Crate1 = for wedges 21,22,23W (will be 18,19,20W in end of Apr) ADMEM Crate2 = for wedges 6,7,8W tasks responsible party ----- ----------------- Feb 8-12 Install CMUASD, HADASD in the crate Nathan, Hahn Install SMXR, SMC, SMD crate, SMD with digital SQUID & associated cables JinYuan, Drennen, Drake Install Clock fanout at B0 Chappa Readout TDC crate via VRB Lusin, Patrick, Chlebana Feb 15-19 Sign-off ADMEM Transition card Hahn Install more ADMEM (total 100 channels) Scott & Transition card with PMT cables Hahn, Lindgren, Fred Noise test of ADMEM with SMXR, CMUASD, Hahn, HaoWei, Chlebana HadASD, MVME2301 running together Kuhlmann, Proudfoot Readout ADMEM crate via VRB Hahn, Chlebana Install CMUASD with TDC Eddy, Holloway Install DIRAC Peter/Culbertson EVB/VRB crate readout test Chris, Tether, Chlebana Feb 22-26 Install TS prototype system at B0 Martin, Schmidt Start electronics test with 2.5 wedges - solve grounding problems Hahn, HaoWei, Igor, - take pedestal data Gallinaro, Chlebana - source, Flasher calibration runs Test ADMEM/DIRAC integration Peter/Culbertson Readout CMUASD with TDC Eddy, Holloway Mar 1- 5 Sign-off ADMEM production Hahn TS system installation start at B0 Andrew, Vejcik Run SMX readout system with digital SQUID Proudfoot, Kuhlmann Readout HadASD with TDC Igor. Cordelli Continue ADMEM/DIRAC integration Peter/Culbertson Mar 8-12 Continue HadASD readout with TDC Igor, Cordelli Install 24 ch SQUID for CES readout Drake, JinYuan Connect CMU HV cables (to chamber & CAEN) Roser, Eddy Readout CMUASD with TDC Eddy, Holloway VRB -> CS/DL test Chris, Tether, Maco (* Digital power supply prototype delivered and checked out) Mar 15-19 Get CHA laser working with TSI & DAQ Cordelli & Co Readout CES with 24 ch SQUID Drake, JinYuan Run CMU with a bottled Ar/Et Roser, Eddy Readout CMU chamber with ASD & TDC Eddy, Holloway Integrated Software Prototype ready & test Patrick & Co (Run Control, TS, VRB, EVB, Clock, ADMEM, TDC, SMXR, etc) Mar 22-26 Install Cal Card, transition board Gallinaro & cables to CEM for 3 wedge operation Continue Integrated Software Prototype test Patrick & Co Test Online Monitoring Software prototype Jack, Frank, Simone, (Calorimeter, TDC) Aurore Mar 29-Apr 2 Install 100 ch SQUID for CES readout Drake, JinYuan Install Crate, ethernet connection, F Lewis, Roser & Co & electrical power in the rack for ADMEM crate2 (wedges 6,7,&8W) Install Transition card with PMT cables Hahn, Lindgren, Dervin (* crate, cable should be FINAL installation not temporary) (* Analog power supply prototype delivered and checked out) Apr 5- 9 PISABOX program for HV control ready & test Cordelli & Co Install top & bottom Scin trg counters Willis, Hahn, Igor under wedge 6,7,8W and 18,19,20W Setup NIM logic crate for cosmic trigger Willis, Hahn, Igor Readout 100 CES with SMQIE (21W) Drake,JinYuan,Proudfoot Install SVX DAQ integration test system Slawk, Mary, Jean, Colin Apr 12-16 Install power supply, TRACER, CPU (6,7,8W) F Lewis, S Orr, DeMaat Install ADMEM (old prototype 100 ch) Scott Install CCAL card for wedge 6,7,8W Gallinaro & co Start electronics test with wedge 6,7,8W - solve grounding problems Hahn, HaoWei, Igor, - take pedestal data Gallinaro, Chlebana - source, Flasher calibration runs Continue Readout CES with SMQIE Drake,JinYuan,Proudfoot Start SVX DAQ integration test @B0 Slawk, Mary, Jean, Colin Apr 19-23 Install Transition card with PMT cables Hahn, Lindgren, Dervin for wedge 18,19,20W (FINAL installation) Move ADMEM from 21,22,23W to 18,19,20W Hahn, HaoWei, Igor Clock & TS connected to ADMEM crates 1&2 Chappa, Martin, Wilson Readout ADMEM crates 1&2 via VRB/EVB Chlebana, Patrick Run QIE calibration simultaneously in 2 ADMEM crates Chlebana, HaoWei Continue test CES readout with SMQIE Drake,JinYuan,Proudfoot Apr 26-30 Continue readout ADMEM crates 1&2 - take pedestal data Hahn, HaoWei, Igor, - source, Flasher calibration runs Gallinaro, Chlebana Start to trigger and readout cosmic events Hahn, HaoWei, Igor from ADMEM crates 1&2 Continue test CES readout with SMQIE Drake,JinYuan,Proudfoot Prototype calibration database running Cranshaw, Vidal, Umesh Prototype YMON (calorimeter) running Nodulman & Co May 3- 7 Trigger and readout cosmic events Hahn, HaoWei, Igor from ADMEM crates 1&2 Continue test CES readout with SMQIE Drake,JinYuan,Proudfoot Install CMUASD in ADMEM crates 1&2 Nathan, Holloway Install CMUTDC crate on 1st floor Wilson Cable up CMUASD to TDC crate (Final) Dervin Start of CMU trigger integration test Eric, Ron, Nathan May 10-14 Calibration & pedestal data taking of CMUASD/TDC Nathan, Holloway Run 6 wedges with ADMEM, SMXR, Hahn, Patrick, Chlebana HadASD & TDC, CMUASD & TDC (pedestal, noise, gain drift, error rate studies) May 17-21 Cosmic data taking with 6 wedges Hahn, Patrick, Chlebana ADMEM, SMXR, HadASD & TDC, CMUASD & TDC (CMU in operation?) May 24-28 Install production ADMEM in crates 1 & 2 Scott, Shaw, Nelson Resume cosmic data taking Hahn, Patrick, Chlebana May 31-Jun 4 Schedule contingency Jun 7-11 Schedule contingency Jun 14-18 Schedule contingency Jun 21-25 Schedule contingency