KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Friday, Jan. 25, 2002 (3 p.m. EST) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-109 - HST Servicing Mission 3B VEHICLE: Columbia/OV-102 TARGET KSC LAUNCH DATE: Feb. 28, 2002 TARGET KSC LANDING DATE: March 11, 2002 MISSION DURATION: 11 days CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees Shuttle Processing Note: The rollout of Shuttle Columbia from the Vehicle Assembly Building (VAB) high bay to Pad A has been rescheduled for Monday, Jan. 28, with first motion at 7 a.m.. Verification testing of the operation of the steering linkage in all four of the crawler-transporter truck drives is in progress. No impact is expected on the STS-109 launch date or the milestone processing events leading up to it. MISSION: STS-110 - 13th ISS Flight (8A) - ITS SO TRUSS AND MOBILE TRANSPORTER VEHICLE: Atlantis/OV-104 TARGET KSC LAUNCH DATE: April 4, 2002 TARGET KSC LANDING DATE: April 15, 2002 MISSION DURATION: 11 days CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Shuttle Atlantis is undergoing prelaunch preparations in the Orbiter Processing Facility (OPF). The payload premate test is complete and main propulsion leak checks are in work. Inspection of the condition of attach point No.5 continues after the left-hand Orbiter Maneuvering System (OMS) pod was removed last Wednesday. MISSION: STS-111 - 14th ISS flight (UF2) - MPLM VEHICLE: Endeavour/OV-105 TARGET LAUNCH DATE: May 2, 2002 TARGET KSC LANDING DATE: May 13, 2002 CREW: Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS up) Korzun, Whitson, Treschev; (ISS down) Onufrienko, Bursch, Walz ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Auxiliary Propulsion System (APS) leak and functional checks are being conducted on Shuttle Endeavour in the OPF. The pitch actuator for Main Engine No. 1 is being removed to repair a faulty connector. STRUCTURAL INSPECTION & MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Discovery is scheduled to be moved back to the OPF from temporary storage in the VAB high bay on Monday. No decision has been made by Shuttle managers on the content, schedule and location for the structural inspection and modification down period. -- end --