The PDF version


U.S. Department of Energy                                   ORDER
     Washington, D.C.                                    DOE 5480.19
                                                            7-9-90
                                                 Change 1:  5-18-92
						 Change 2: 10-23-01
						
						
SUBJECT:  CONDUCT OF OPERATIONS REQUIREMENTS FOR DOE FACILITIES
                                                                                       

1.	PURPOSE.  To provide requirements and guidelines for Departmental Elements, including the National Nuclear Security Administration (NNSA), to use in developing directives, plans, and/or procedures relating to the conduct of operations at DOE facilities.  The implementation of these requirements and guidelines should result in improved quality and uniformity of operations.
	
2.	SCOPE.  The provisions of this Order apply to all Departmental Elements, including the NNSA, and contractors performing work for the Department as provided by law and/or contract and as implemented by the appropriate contracting officer.

3.	DEFINITIONS.

	a.	DOE Facility Representative.  For each major facility or group of lesser facilities, an individual assigned responsibility by the Head of the Field Element for monitoring the performance of the facility and its operations.  This individual shall be the primary point of contact with the contractor and will be responsible to the appropriate DOE Program Office and field elements for implementing the requirements of this Order.

	b.	Program Manager.  The DOE Headquarters (HQ) individual, designated by and under the direction of a Program Secretarial Officer, or NNSA Deputy/Associate Administrator who is directly involved in the operation of facilities under his or her cognizance and with signature authority to provide technical direction through DOE field elements to contractors for these facilities.

4.	POLICY.  It is the policy of the Department that the conduct of operations at DOE facilities be managed consistent with the requirements of this Order:

	a.	Operations at DOE facilities be conducted in a manner to assure an acceptable level of safety;

	b.	Operators at facilities have procedures in place to control the conduct of their operations;
	
	c.	Line organizations review existing and planned programs important to safe and reliable facility operations; and


	d.	Line organizations assess the effectiveness of corporate directives, plans, or procedures at facilities under their cognizance.

	5.	REQUIREMENTS.

	a.	Each PSO, field element and contractor shall use this Order and Attachment 1 in the review and development of existing and proposed directives, plans, or procedures relating to the conduct of operations at DOE facilities.

	b.	A graded approach shall be used in the application of the guidelines provided in Attachment I to assure that the depth of detail required and the magnitude of resources expended for operations are commensurate with each facility's programmatic importance and potential environmental, safety, and/or health impact.

	c.	Conformance with the requirements of this Order shall be documented.  However, it is not necessary to develop a separate manual or plan.  As a minimum, a document (e.g., a matrix) shall be prepared in coordination with the Head of the Field Element and the cognizant Program Secretarial Officer(s) that:

		(1)	Indicates whether a specific guideline applies to a facility;

		(2)	Indicates where and how each of the guidelines (Attachment 1) of this Order are applied within the field element’s and contractor's existing policies and procedures; and

		(3)	Identifies any deviations or exemptions from the guidelines.

	This document shall, as a minimum, be approved by the Head of the Field Element.

	6.	RESPONSIBILITIES AND AUTHORITIES.

	a.	Program Secretarial Officers (PSOs) shall:

	(1)	Provide direction to field elements for the conduct of operations for facilities under their cognizance.

	(2)	Ensure the preparation, review, and approval of field element and contractor documentation implementing the requirements of this Order for programs under their cognizance; and

	(3)	Ensure that Program Managers oversee the conduct of operations at those facilities under their cognizance in accordance with the requirements of this Order.

	b.	Environment, Safety and Health (EH-1) acting as the independent element responsible for assuring the protection of the public, workers, and the environment from DOE operations, shall:

	(2)	Develop, and maintain policies necessary to implement and sustain effective DOE-wide conduct of operations of facilities and associated equipment/systems;

	(3)	Develop, promulgate, and maintain guidance materials and conduct training and workshops, as necessary, for line management to implement the above policies and procedures;

	(3)	Monitor appraisal reports relative to conduct of operations at DOE facilities to review implementation of this Order to identify needed requirements, and

	(4)	Provide interpretation to the requirements of this Order upon request.

	c.	Heads of Field Elements shall:

	(1)	Ensure that adequate field element and contractor plans, procedures, and programs are in place and assess the effectiveness of their implementation at sites under their jurisdiction, consistent with the provisions of this Order;

	(2)	Ensure that a DOE Facility Representative is assigned responsibility for a major facility or group of lesser facilities, and oversee the day-to-day conduct of operations at these facilities in accordance with the requirements of this Order and the direction received from the Program Manager; and

	(3)	Approve documentation prepared by the field element and contractor to demonstrate conformance to the guidelines in Attachment 1.
	
	d.	Director, Naval Nuclear Propulsion Program, Executive Order 12344, statutorily prescribed by Public Law (P.L.) 98-525 (42 United States Code 7158, Note) establishes the responsibilities and authority of the Director, Naval Nuclear Propulsion Program (who is also the Deputy Administrator for Naval Reactors, NNSA) for all facilities and P.L.106-65    (Oct. 5, 1999) activities which comprise the Program, a joint Navy-DOE organization.  These executive and legislative actions establish the responsibilities of the Director as including the safety of reactors and associated naval nuclear propulsion plants, the control of radiation and radioactivity associated with naval nuclear propulsion plants, and the o crating practices and procedures applicable to naval nuclear propulsion plants.  Accordingly, the provisions of this Order do not apply to the Naval Nuclear Propulsion Program.  The Director shall establish the conduct of operations requirements implemented within the program.
	
	e.	Heads of Power Administration, In accordance with Section 302 of the Department of Energy Organization Act (Public Law 95-91), the Secretary operates and maintains the Power Marketing Administration (PMA) electric power transmission systems by and through the PMA Administrators.  The PMAs have in place operations management programs. which are geared to the special needs of utility operations, are responsive to coordinated multi-utility system requirements, and are in conformance with prudent utility practice.  In view of the unique nature of the Administrators' obligations to meet their statutory and public utility responsibilities for the safety, security, and reliability of electric power transmission and of their legal and contractual obligation, the Administrators shall determine the appropriate operations management program for their facilities, which will include consideration of appropriate parts of the criteria set forth by this Order.

	
BY ORDER OF THE SECRETARY OF ENERGY:



   FRANCIS S. BLAKE
   Deputy Secretary 



                         GUIDELINES FOR THE CONDUCT OF
                         OPERATIONS AT DOE FACILITIES

                              TABLE OF CONTENTS

                                                                       Page

GENERAL INTRODUCTION...................................................I-12

CHAPTER I.  OPERATIONS ORGANIZATION AND ADMINISTRATION.................I-15
     A.   Introduction.................................................I-15
     B.   Discussion...................................................I-15
     C.   Guidelines...................................................I-16
          1.   Operations Policies.....................................I-16
          2.   Resources...............................................I-16
          3.   Monitoring of Operating Performance.....................I-16
          4.   Accountability..........................................I-18
          5.   Management Training.....................................I-18
          6.   Planning for Safety.....................................I-18

CHAPTER II.  SHIFT ROUTINES AND OPERATING PRACTICES....................I-19
     A.   Introduction.................................................I-19
     B.   Discussion...................................................I-19
     C.   Guidelines...................................................I-20
          1.   Status Practices........................................I-20
          2.   Safety Practices........................................I-20
          3.   Operator Inspection Tours...............................I-20
          4.   Round/Tour Inspection Sheets............................I-21
          5.   Personnel Protection....................................I-22
          6.   Response to Indications.................................I-23
          7.   Resetting Protection Devices............................I-23
          8.   Load Changes............................................I-24
          9.   Authority to Operate Equipment..........................I-24
          10.  Shift Operating Bases...................................I-24
          11.  Potentially Distractive Written Materials and Devices...I-25

CHAPTER III.  CONTROL AREA ACTIVITIES..................................I-27
     A.   Introduction.................................................I-27
     B.   Discussion...................................................I-27
     C.   Guidelines...................................................I-27
          1.   Control Area Access.....................................I-27
          2.   Professional Behavior...................................I-27
          3.   Monitoring the Main Control Boards......................I-28
          4.   Control Operator Ancillary Duties.......................I-28
          5.   Operation of Control Area Equipment.....................I-28

CHAPTER IV.  COMMUNICATIONS............................................I-29
     A.   Introduction.................................................I-29
     B.   Discussion...................................................I-29
     C.   Guidelines...................................................I-29
          1.   Emergency Communications Systems........................I-29
          2.   Public Address System...................................I-30
          3.   Contracting Operators...................................I-30
          4.   Radios..................................................I-30
          5.   Abbreviations and Acronyms..............................I-31
          6.   Oral Instructions and Informational Communications......I-31

CHAPTER V.  CONTROL OF ON-SHIFT TRAINING...............................I-33
     A.   Introduction................................................ I-33
     B.   Discussion...................................................I-33
     C.   Guidelines...................................................I-34
          1.   Adherence to Training Programs..........................I-34
          2.   On-shift Instructor Qualification.......................I-34
          3.   Qualified Operator Supervision and Control of Trainees..I-34
          4.   Operator Qualification Program Approval.................I-35
          5.   Training Documentation..................................I-35
          6.   Suspension of Training..................................I-35
          7.   Maximum Number of Trainees..............................I-35

CHAPTER VI.  INVESTIGATION OF ABNORMAL EVENTS..........................I-37
     A.   Introduction.................................................I-37
     B.   Discussion...................................................I-37
     C.   Guidelines...................................................I-38
          1.   Events Requiring Investigation..........................I-38
          2.   Investigation Responsibility............................I-39
          3.   Investigator Qualification..............................I-40
          4.   Information to be Gathered..............................I-40
          5.   Event Investigation.....................................I-41
          6.   Investigative Report....................................I-42
          7.   Event Training..........................................I-42
          8.   Event Trending..........................................I-43
          9.   Sabotage................................................I-43

CHAPTER VII.  NOTIFICATIONS............................................I-45
     A.   Introduction.................................................I-45
     B.   Discussion...................................................I-45
     C.   Guidelines...................................................I-45
          1.   Notification Procedures.................................I-45
          2.   Notification Responsibility.............................I-46
          3.   Names and Phone Numbers.................................I-46
          4.   Documentation...........................................I-46
          5.   Communication Equipment.................................I-46

CHAPTER VIII.  CONTROL OF EQUIPMENT AND SYSTEM STATUS..................I-47
     A.   Introduction.................................................I-47
     B.   Discussion...................................................I-47
     C.   Guidelines...................................................I-47
          1.   Status Change Authorization and Reporting...............I-47
          2.   Equipment and System Alignments.........................I-48
          3.   Equipment Locking and Tagging...........................I-49
          4.   Operational Limits Compliance...........................I-49
          5.   Equipment Deficiency Identification and Documentation...I-49
          6.   Work Authorization and Documentation....................I-50
          7.   Equipment Post-Maintenance Testing and Return to
                 Service...............................................I-50
          8.   Alarm Status............................................I-50
          9.   Temporary Modification Control..........................I-51
          10.  Distribution and Control of Equipment and System
                 Documents.............................................I-51

CHAPTER IX.  LOCKOUTS AND TAGOUTS......................................I-53
     A.   Introduction.................................................I-53
     B.   Discussion...................................................I-53
     C.   Guidelines...................................................I-53
          1.   Lockout/Tagout Use......................................I-53
          2.   Lockout and Tagout Implementation.......................I-54
          3.   Protective Materials and Hardware.......................I-55
          4.   Lockout/Tagout Program..................................I-56
          5.   Procedures for Lockout/Tagout...........................I-56
          6.   Application of Lockout/Tagout...........................I-58
          7.   Testing or positioning of equipment or components.......I-60
          8.   Periodic Inspections....................................I-60
          9.   Caution Tags............................................I-60
          10.  Training and Communication..............................I-61
          11.  Lockout or Tagout Implementation........................I-63
          12.  Notification of Personnel...............................I-63
          13.  Outside Contractors.....................................I-63
          14.  Group Lockouts or Tagouts...............................I-63
          15.  Shift or Personnel Change...............................I-63

CHAPTER X.  INDEPENDENT VERIFICATION...................................I-65
     A.   Introduction.................................................I-65
     B.   Discussion...................................................I-65
     C.   Guidelines...................................................I-66
          1.   Components Requiring Independent Verification...........I-66
          2.   Occasions Requiring Independent Verification............I-67
          3.   Verification Techniques.................................I-69

CHAPTER XI.  LOGKEEPING................................................I-72
     A.   Introduction.................................................I-72
     B.   Discussion...................................................I-72
     C.   Guidelines...................................................I-72
          1.   Establishment of Operating Logs.........................I-72
          2.   Timeliness of Recordings................................I-73
          3.   Information to be Recorded..............................I-73
          4.   Legibility..............................................I-73
          5.   Corrections.............................................I-74
          6.   Log Review..............................................I-74
          7.   Care and Keeping of Logs................................I-74

CHAPTER XII.  OPERATIONS TURNOVER......................................I-75
     A.   Introduction.................................................I-75
     B.   Discussion...................................................I-75
     C.   Guidelines...................................................I-75
          1.   Turnover Checklists.....................................I-75
          2.   Document Review.........................................I-77
          3.   Control Panel Walkdown..................................I-77
          4.   Discussion and Exchange of Responsibility...............I-78
          5.   Shift Crew Briefing.....................................I-78
          6.   Reliefs Occurring During the Shift......................I-78

CHAPTER XIII.  OPERATIONS ASPECTS OF FACILITY CHEMISTRY AND UNIQUE
          PROCESSES....................................................I-79
     A.   Introduction.................................................I-79
     B.   Discussion...................................................I-79
     C.   Guidelines...................................................I-79
          1.   Operator Responsibilities...............................I-79
          2.   Operator Knowledge......................................I-80
          3.   Operator Response to Process Problems...................I-81
          4.   Communicating Between Operations and Process Personnel..I-81

CHAPTER XIV.  REQUIRED READING.........................................I-83
     A.   Introduction.................................................I-83
     B.   Discussion...................................................I-83
     C.   Guidelines...................................................I-83
          1.   File Index..............................................I-83
          2.   Reading Assignments.....................................I-83
          3.   Required Dates for Completion of Reading................I-84
          4.   Documentation...........................................I-84
          5.   Review..................................................I-84

CHAPTER XV.  TIMELY ORDERS TO OPERATORS................................I-85
     A.   Introduction.................................................I-85
     B.   Discussion...................................................I-85
     C.   Guidelines...................................................I-85
          1.   Content and Format......................................I-85
          2.   Issuing, Segregating, and Reviewing Orders..............I-86
          3.   Removal of Orders.......................................I-86

CHAPTER XVI.  OPERATIONS PROCEDURES....................................I-87
     A.   Introduction.................................................I-87
     B.   Discussion...................................................I-87
     C.   Guidelines...................................................I-88
          1.   Procedure Development...................................I-88
          2.   Procedure Content.......................................I-88
          3.   Procedure Changes and Revisions.........................I-90
          4.   Procedure Approval......................................I-91
          5.   Procedure Review........................................I-92
          6.   Procedure Availability..................................I-92
          7.   Procedure Use...........................................I-92

CHAPTER XVII.  OPERATOR AID POSTINGS...................................I-95
     A.   Introduction.................................................I-95
     B.   Discussion...................................................I-95
     C.   Guidelines...................................................I-95
          1.   Operator Aid Development................................I-95
          2.   Approval................................................I-95
          3.   Posting.................................................I-95
          4.   Use of Operator Aids....................................I-96
          5.   Documentation...........................................I-96
          6.   Review..................................................I-96

CHAPTER XVIII.  EQUIPMENT AND PIPING LABELING..........................I-97
     A.   Introduction.................................................I-97
     B.   Discussion...................................................I-97
     C.   Guidelines...................................................I-97
          1.   Components Requiring Labeling...........................I-97
          2.   Label Information.......................................I-98
          3.   Label Placement.........................................I-98
          4.   Replacing Labels........................................I-99


                            Attachment I	DOE 5480.19 Chg 2
			    Page I-12	10-23-01
			    
			    
GENERAL INTRODUCTION
   
The guidance contained in this attachment for the Conduct of Operations at DOE facilities is based on well-developed industrial operations practices.  The guidelines are written to be flexible, so that they encompass the range from large, permanent DOE test or production facilities to small research or
testing facilities.  These guidelines form a compendium of good practices and describe key elements of programs that support operations at DOE facilities.  Their implementation should result in a high level of performance and therefore contribute to safe and reliable operation.
			    
Experience has shown that the better operating facilities have well-defined, effectively administered policies and programs to govern the activities of the operating organization, including the areas described by these guidelines. These guidelines have, therefore, been prepared to assist facilities in the review and development of programs important to operations.  Not all activities in the operations area are addressed.  Some areas, such as the technical aspects of specific equipment operation, are not included because they involve facility-specific situations requiring unique direction.  However, use of these guidelines should support or complement performance in the areas not addressed.
			    
These guidelines have been written to assist facilities in meeting operations performance and safety objectives.  It is intended that they be used to review existing or planned programs or facilities and in developing programs where none presently exist.  It is expected that facilities may use different approaches or methods than those defined in the guidelines, but facilities are expected to meet the intent of these guidelines.  Some expansion of the intent of the guidelines is provided in the introduction and discussions section for each chapter, and the specific guidelines that follow reflect generally accepted methods for conducting operational activities. Deviation from any particular guideline would not in itself
indicate a problem in operation.  However, differences between the guidelines and actual practices should be reviewed to determine if a facility practice should be changed.  A change in facility practice would be appropriate if a performance weakness is determined to exist.  It is recognized that these guidelines cross into areas covered by multiple DOE Orders (e.g., DOE 5480.4 or DOE 5500), which need to be used on an equal basis.  During the development of this guideline, no specific guidance was found which conflicts with other DOE Orders.  If a user finds any conflicts, the matter should be resolved by the Program Manager, or field office and identified to EH.

    These guidelines are also intended to be useful to Program Managers and
field offices responsible for oversight of facility operations.  In
particular, these guidelines could be used to assess the effectiveness and
adequacy of policies and actions in the areas addressed.  Groups reviewing
facility performance could use this document as a reference to support some
aspects of their activities.  It is therefore incumbent upon Program
Managers, field offices, and facility management to review their operations,
and determine and document specific facility conformance with the
guidelines.

    Each chapter of these guidelines is organized into three sections.  The
Introduction briefly describes the objective to be achieved and describes,
where needed, the relationship of the chapter to other chapters.  This is
followed by a Discussion section that concisely describes the actions needed
to accomplish the objectives and includes a brief explanation of why these
actions are necessary or important.  The final section, the guidelines
themselves, provides specific guidance for meeting the chapter objectives.
In some cases, example situations accompany the guidelines.  Such examples
should not be construed as the only method for meeting the intent of the
guidelines.

                               CHAPTER I

               OPERATIONS ORGANIZATION AND ADMINISTRATION


A.  INTRODUCTION

    The organization and administration of operations should ensure that a
    high level of performance in DOE facility operations is achieved through
    effective implementation and control of operations activities.
    Operations activities should recognize that environment, safety, and
    productivity are compatible goals.  DOE facility policies should
    describe the philosophy of standards of excellence under which the
    facility is operated and clear lines of responsibility for normal and
    emergency conditions are established.  Effective implementation and
    control of operating activities are primarily achieved by establishing
    written standards in operations, periodically monitoring and assessing
    performance, and holding personnel accountable for their performance.
    This chapter discusses the policies, resources, monitoring, and
    accountability needed in operations.

B.  DISCUSSION

    A high level of performance in DOE operations is accomplished by
    establishment of high operating standards by management, by
    communicating operating standards to the working level, by providing
    sufficient resources to the operations department, by ensuring personnel
    are well trained, by closely monitoring performance in operations, and
    by holding workers and their supervisors accountable for their
    performance in conducting activities.

    Senior management establishes operating standards, considering input
    from the working level when appropriate.  The working level will more
    eagerly support the standards when they have had input into the
    development of those standards.  The standards should define operating
    objectives, establish expected performance levels, and clearly define
    responsibility in plant operations.  Standards for operating activities
    should also be integrated into operations department procedures and
    programs.  Operating standards should also be communicated to the
    working level by training workers in operating practices and by
    supervisory monitoring and guidance of work involving plant operations.
    Sufficient staff, equipment, and funding should be allocated to permit
    the operations department can effectively perform its functions.
    Performance in operations should be closely monitored by facility
    management, and operating reports and goals should be used so that the
    performance of the operations department can be effectively measured.
    Operations personnel should be held accountable for their performance
    through supervisory counseling, performance appraisals and, when
    necessary, disciplinary measures.  Remedial training should be provided
    when appropriate.

C.  GUIDELINES

    1.  Operations Policies

        Procedures or other definitive documentation should specify policies
        that are to be applied for operations.  These policies should
        specify goals and the means to achieve those goals.  These documents
        should also provide for the types of controls necessary to implement
        policies as discussed in this and other chapters of the guidelines.
        Operations procedures should support facility and DOE guidance for
        operations.  Responsibilities for implementing these policies,
        including the responsibility of shift personnel, if applicable,
        should be clearly defined.  Operations personnel should clearly
        understand their authority, responsibility, accountability, and
        interfaces with other groups.  Physical security should be in
        accordance with DOE 5630.11.

    2.  Resources

        The operations supervisor for DOE facilities should be provided with
        sufficient resources in materials and personnel to accomplish
        assigned tasks without requiring excessive overtime by the
        operations staff.  These resources should include technical
        personnel needed to support the operations.  A long-range staffing
        plan that anticipates personnel losses should be developed and
        implemented.

    3.  Monitoring of Operating Performance

        As described in Chapter VI, operating problems should be documented
        and evaluated.  Based on assessments of these problems, corrective
        actions should be taken to improve the performance of the operations
        department performance.  Additionally, frequent direct observation
        of operations activities by supervisors and managers is essential to
        performance of monitoring operations.

        Safety, Environment, and Operating goals should be used as a
        management tool for involving cognizant groups or individuals in
        improving operating performance and for measuring operating
        effectiveness.  Operations goals in areas such as the following
        should be established:

        -  minimizing the unavailability of safety systems;
        -  minimizing personnel errors;
        -  As-Low-As Reasonably-Achievable (ALARA);
        -  minimizing lost facility capability;
        -  minimizing the number of unscheduled facility shutdowns per year;
        -  timely completion of scheduled surveillance;
        -  minimizing the amount of overtime;
        -  achieving and maintaining complete staffing and training of shift
           positions;
        -  minimizing waste; and
        -  minimizing the number of lighted annunciators.

        Goals should be auditable, measurable, realistic, and challenging.
        Meeting goals should require a definite set of actions or an action
        plan.  The action plan should be developed with input from personnel
        involved in conducting operations, reviewed by the operations
        supervisor at DOE facilities, and approved by management.  The
        progress toward completing the action plan and achieving goals
        should be monitored periodically.  If results show a significant
        variance from the desired progress in achieving goals, management
        should review the action plan to ensure that it is adequate and is
        being executed.  An audit of performance relative to operating goals
        should be provided to facility management and DOE.  This summary
        should include an explanation of performance and actions planned to
        improve future performance.

        Operating and safety goals should be set and used as motivators for
        improvement, not as ends in themselves.  The purpose is not simply
        to meet a numerical goal; rather, the purpose is to improve and
        monitor operating performance.  Meaningless goals (i.e., goals that
        are easy to meet with little action) should not be used.

        Inspections, audits, reviews, investigations, and self-assessments
        are a part of the checks and balances needed in an operating
        program.  Line managers and supervisors should perform routine
        observations of personnel performing operating activities.
        Deficiencies identified should be documented, trended, and
        corrected.  Also, other groups, such as quality assurance personnel,
        should periodically review and assess operation performance.  These
        reviews can assist line managers and supervisors in identifying and
        correcting problems.

    4.  Accountability

        Workers and their supervisors should be held accountable for
        operating performance.  Personnel involved in significant or
        frequent violations of operating practices should be counseled,
        retrained, and disciplined, as appropriate.  Supervisor performance
        appraisals and promotions should include an assessment of operating
        performance.

    5.  Management Training

        Formalized supervisory and management training should be
        incorporated into training programs.  This is especially important
        to the first-line supervisors on shift and should aid them in
        managing shift activities.

    6.  Planning for Safety

        Facility guidance should exist which describes safety preplanning
        requirements for all operational activities.  The guidance should
        explain the role of safety analysis reviews, job safety analyses,
        and the handling of safety matters.  All operations personnel should
        understand the safety planning requirements.


                           CHAPTER II

              SHIFT ROUTINES AND OPERATING PRACTICES


A.  INTRODUCTION

    Standards for the professional conduct of operations personnel should be
    established and followed so that operator performance meets the
    expectations of DOE and facility management.  The guidelines of this
    chapter describe watchstanding practices that apply to all operating
    personnel.  Additional guidelines are delineated in Chapter III, Control
    Area Activities.  Chapter IV, Communications, describes some
    communication practices applicable to all operations personnel.  This
    chapter describes some important aspects of routine shift activities and
    watchstanding practices.

B.  DISCUSSION

    Professional conduct and good watchstanding practices result in
    appropriate attention to facility conditions.

    Effective equipment monitoring is necessary to detect abnormal
    conditions or adverse trends so that appropriate action can be taken
    before equipment malfunction occurs.  Notifying supervisors promptly of
    unusual or unexpected situations helps to ensure that proper attention
    is given to changing and/or off-normal conditions. Equipment status and
    the authority to operate equipment should be understood by all
    operations personnel so that activities can be controlled and
    coordinated.  Operations personnel should follow proper industrial
    safety, radiological protection (if applicable) and quality assurance
    practices.  These items are key elements that should be included in an
    effective operator watchstanding program.  A desire to conduct assigned
    tasks expeditiously should not interfere with good watchstanding
    practices.

    It is the responsibility of the on-shift operating crew to safely
    operate the DOE facility through adherence to operating procedures and
    technical specification or operational safety requirements and sound
    operating practices.  The authority for operations should be vested in
    the on-duty shift supervisor and transferred only through formal
    turnover to a qualified relief.

    The on-duty shift supervisor should maintain authority and
    responsibility for all facility operations.  If a special test,
    evolution, or abnormal condition arises, facility personnel should be
    aware that the responsibility and authority to determine corresponding
    operating conditions, system alignments, or equipment manipulations
    rests fully with the on-duty shift supervisor (or cognizant manager).
    The shift supervisor (or cognizant manager) should not permit any
    individual to bypass or overrule his/her operational judgment without
    bringing the matter to the attention of higher line operational
    authority.

C.  GUIDELINES

    1.  Status Practices

        The operator responsible for the facility should be promptly
        notified of all changes in facility status, abnormalities, or
        difficulties encountered in performing assigned tasks.  Similarly,
        the operator should notify the shift supervisor (or cognizant
        manager for research and test facilities) of any unexpected
        situations.

    2.  Safety Practices

        Operations personnel should adhere to the requirements of the
        facility industrial safety program.  Proper hearing, eye, head,
        foot, and respiratory protection should be worn in designated areas
        to reduce the potential for injury.  Similarly, ladders or other
        approved means should be used to access equipment located in the
        overhead when permanent steps or catwalks are not available, thus
        minimizing the potential for accidents.  Operators should not
        routinely climb or walk on facility components and insulation,
        because this could result in personnel injury or damage to
        equipment.  Operators should exercise appropriate precautions when
        entering or working in or around energized panels or equipment.  For
        example, operators should ensure that electrical panel closures are
        securely fastened prior to making the breakers operable to energize
        equipment.  This reduces the potential for personnel injury if a
        fault causes breaker arcing during operation.

    3.  Operator Inspection Tours

        Operator tours should be of sufficient detail to ensure that the
        status of equipment is known.  Each operator should conduct a
        thorough tour of all areas within his/her responsibility, making
        appropriate equipment inspections at designated times at least once
        per shift.  However, the operations supervisor may designate
        specific rooms to be inspected less frequently because of adverse
        radiological or equivalent personnel safety conditions, or more
        frequently if problems have been encountered.  In these cases, the
        operations supervisor (or cognizant manager for research test
        facilities) should specify an alternate inspection schedule.  Plant
        security concerns should not override operator safety assessment
        duties.  A tour normally should be made early in the shift, before
        the operator attends to other duties, so that he/she can become
        familiar with the condition and status of equipment for which he/she
        is responsible.  During the tour, equipment should be inspected to
        ensure that it is operating properly or, in the case of standby
        equipment, that it is fully operable.  In addition, the following
        activities should be conducted in conjunction with the tour:

        a.  The status of equipment (i.e., operating, standby, work in
            progress, or out-of-service) should be determined so that the
            operator will be best able to respond to problems he/she may
            face during his/her shift.

        b.  Components, such as electrical panels, alarm panels, auto-start
            standby equipment, and breakers should be inspected for abnormal
            or unusual conditions.  Unexpected conditions such as equipment
            vibrations, unusual noises or smells, or excessive temperatures
            should be reported to the control room so that supervisors will
            be aware of the conditions and be able to direct repairs,
            troubleshooting, or additional operator action, as necessary.

        c.  Equipment panel alarm light bulbs and annunciators should be
            periodically checked to ensure satisfactory operation of visual
            and audible abnormal condition indicators.

        d.  Each operator should inspect all areas for which he/she is
            responsible and note any deficiencies that may be present.
            These deficiencies may include steam, oil, or water leaks; fire
            and safety hazards or radiological problems; seismic concerns
            such as open electrical panels and mobile objects; clogged floor
            drains; housekeeping or cleanliness problems; and building
            deficiencies such as inoperative lighting, roof leaks, or doors
            that do not close properly.

        Operators should take appropriate action to correct or report
        deficiencies noted during tours.  Equipment deficiencies should also
        be documented in accordance with the facility maintenance work
        request system.

    4.  Round/Tour Inspection Sheets

        Round inspection sheets are an effective method for providing
        operators with guidance on the extent to which equipment and areas
        should be inspected during routine tours.  The recording of key
        equipment parameters during tours provides a record of equipment
        performance and can be used to reconstruct events leading up to
        unusual occurrences or system malfunctions.  This record permits
        short-term trending by operators so that undesirable trends and
        equipment problems can be identified and corrected.  Round
        inspection sheets also facilitate operator turnover of equipment
        status and are an effective aid in the training and qualification of
        new operators.

        Round inspection sheets should be developed and approved by the
        operations supervisor (or cognizant managers for test and research
        facilities).  They should include areas located within the
        particular shift position and important parameters for equipment.
        Where appropriate, equipment parameters should include maximum/
        minimum values or expected operating ranges to enable operators to
        recognize abnormal readings quickly.  Safety limits derived from
        Technical Specifications or Operational Safety Requirements should
        be highlighted.  Equipment should be listed on round sheets in the
        same order that it would be encountered during a normal tour of the
        operating station, and the round sheets should include a narrative
        section.

        Operators should use the narrative section to document major
        evolutions, causes of abnormal conditions, and actions taken to
        correct abnormal conditions.  A narrative log book may be
        substituted for the narrative section on the round sheet.  Data
        should be recorded on round sheets at the times specified by the
        operations supervisor.  When round sheet data is not obtained within
        one hour of the specified time, the actual time the data was
        obtained should be noted on the round sheet.

        Parameters exceeding the specified maximum/minimum values should be
        circled or otherwise highlighted on the round sheet and promptly
        reported to the control room and/or the cognizant operations
        manager.  The causes of abnormal indications should be promptly
        investigated with supervisors becoming involved as appropriate.  The
        round sheet data should be reviewed by a supervisor each shift to
        identify trends or abnormal readings and to verify that data has
        been properly recorded.

        Operator rounds should be periodically monitored by supervisory
        personnel to ensure that comprehensive tours continue to be
        conducted, including, as necessary, periodic inspections of
        equipment and areas not listed on the round sheets.

    5.  Personnel Protection

        Operations personnel should be appropriately qualified to follow
        good personnel protection practices to maintain personnel exposure
        as low as reasonably achievable (ALARA) to radiation (DOE 5480.11),
        chemicals, electromagnetic fields, toxic materials, or other
        personnel hazards.  In particular, operations personnel should
        observe the following requirements:

        a.  Operators should adhere to all posted personnel protection
            requirements and observe proper practices and precautions while
            in controlled areas.

        b.  Operators should correctly utilize appropriate monitoring
            instruments when required.

        c.  Operators should be cognizant of their own exposure levels and
            take appropriate action to minimize exposures.

        d.  Operators should be knowledgeable of the proper use of radiation
            work permits, safe work permits, or inhalation limits, where
            applicable.

        e.  Operators should promptly report protection deficiencies and
            hazards to the control personnel and/or appropriate protection
            personnel.  In addition, operators should take appropriate
            immediate actions to reduce or correct the hazards.

        f.  Appropriate protection personnel should be informed prior to
            evolutions or activities that have a potential to significantly
            change conditions in the facility.

        Operations supervisory personnel should periodically review exposure
        trends of operating personnel under their supervision.  Emphasis
        should be placed on determining the adverse factors that contribute
        to personnel exposures and minimizing those factors to keep
        exposures as low as reasonably achievable.

    6.  Response to Indications

        Operators should believe instrument readings and treat them as
        accurate unless proven otherwise.  Ignoring an unusual reading
        because the operator believes an instrument is faulty can cause
        abnormal conditions to be undetected.  In general, operators should
        check other indications, if possible, when unexpected readings are
        observed.  Prompt action should be taken to investigate the cause of
        abnormal or unexpected indications so that prompt corrective action
        can occur.  When malfunctioning or inaccurate instruments are
        discovered, they should be appropriately identified to prevent
        subsequent confusion and instrument and control personnel should be
        notified to effect repairs.  In situations of operator doubt,
        operators should be instructed to achieve facility, personnel, and
        environmental safety above facility production.

    7.  Resetting Protective Devices

        When protective devices trip (e.g., circuit breakers, fuses, reactor
        protection channels where multichannel logic exists), an attempt
        should be made to understand the cause of the trip before the device
        is reset.  Normally, before action is taken, an operator should
        ensure no abnormal condition exists that would preclude reset.
        However, because the consequences of inappropriately resetting
        protective devices vary considerably, good judgment and specific
        guidance are necessary in this area.  The operations management
        should provide the appropriate guidance so that tripped protective
        devices will be properly addressed.

        Facility trips and unplanned forced shutdown require a thorough
        investigation in accordance with the guidance of Chapter VI.

    8.  Load Changes

        The shift supervisor, the control room lead operator, or the
        cognizant manager for a test and research facility should approve
        all power or process rate changes because these persons are held
        accountable for safe operation.  Additionally, they will probably be
        the persons most knowledgeable of problems that occur as a result of
        load changes.  However, the operator could decrease load or rate
        without approval, if necessary, to respond to a facility emergency
        situation in accordance with the facility's emergency procedures.

    9.  Authority to Operate Equipment

        The overall operation of the facility should be directed by the
        operations supervisor for a large DOE facility and by the cognizant
        manager for a test and research facility.  Operations management
        should ensure that only trained and qualified personnel operate
        plant equipment.  In general, the operator and the operations
        supervisor should be aware of all activities affecting equipment.
        The operations supervisor should specify those general activities
        that may normally be performed without informing the supervisor and
        should amplify these specifications as appropriate.  Examples of
        such activities are pumping certain sumps (plant equipment
        operators) and the routine minor adjusting of controls necessary for
        maintaining stable process conditions.  However, nonroutine
        operation of controls should not be made without specific approval
        of the shift supervisor.  In addition, during emergencies, operators
        may take necessary immediate actions required to ensure personnel,
        plant, and environmental safety without obtaining prior approval;
        however, appropriate supervisors should be promptly informed of
        these actions.  Operators should be instructed that plant safety
        should be achieved over facility production for off normal and
        emergency facility conditions.

    10. Shift Operating Bases

        The operating base is the facility area where an operator returns
        when he is not performing in-plant duties.  An operating base should
        be established for each shift position.  Each operating base should
        be equipped with appropriate office equipment for the operator to
        maintain necessary procedures and references and to conduct
        administrative duties, and necessary communication equipment should
        be available at the operating base.  Shift turnovers should be
        conducted within those facility areas assigned to the operations
        department and typically at the operating base.  The operating bases
        should be located at a convenient place within the area of
        responsibility for that shift position.

    11. Potentially Distractive Written Material and Devices

        Written material that does not relate to operation and entertainment
        devices (such as radios, televisions, tape players, and computer
        games) should be prohibited from use by on-duty operations personnel
        in order to minimize distractions from their responsibilities.
        Written material and entertainment devices should not be brought to
        work stations.  However, operators may read training bulletins,
        technical manuals, or operating experience information or review
        other written, audible, or visual materials that relate to operator
        duties.  Judgment should be used to ensure the operators' primary
        duties are not compromised.  The operations supervisor (or
        equivalent) should provide guidance to the shift crews for the use
        of potentially distractive materials and devices.


                            CHAPTER III

             CONTROL AREA ACTIVITIES FOR DOE FACILITIES


A.  INTRODUCTION

    Control area activities should be conducted in a manner that achieves
    safe and reliable facility operations.  Other shift activities are
    discussed in Chapter II, Shift Routines and Operating Practices.  This
    chapter addresses the important elements of control area activities that
    are necessary to support safe and efficient facility operation.

B.  DISCUSSION

    The control area or control room is the most critical facility operating
    base and the coordination point for all important facility activities.
    Therefore, activities in the control area or control room must be
    businesslike, and a professional atmosphere conducive to safe and
    efficient operation must be maintained.  In addition, control area
    operators should not be overburdened with administrative
    responsibilities, and control area access should be limited so that
    operators will not be distracted from properly monitoring facility
    parameters.

C.  GUIDELINES

    1.  Control Area Access

        Control area access should be limited to those persons on official
        business only.  The "at-the-controls" area of the control room
        should be clearly identified, and its boundary should be understood
        by all persons who are granted access to the control room.  Access
        to the "at-the-controls" area should be restricted to persons who
        need to be in the area.  Entry into this area should be granted by
        designated individuals, and persons who might need to enter this
        area should know who can grant access.

    2.  Professional Behavior

        Professional behavior should be displayed in the control area at all
        times.  Only activities essential to supporting operation and
        activities authorized by management should be conducted in the
        control area.  Potentially distracting activities (such as radio
        listening, game playing, and horseplay) should be prohibited.
        Non-job-related discussions should be minimized so as not to
        interfere with conduct of the shift or monitoring of key parameters.

    3.  Monitoring the Main Control Panels

        Operators should be alert and attentive to control panel indications
        and alarms.  Control panel indications should be monitored
        frequently, and prompt action should be taken to determine the cause
        of and correct abnormalities.  Emphasis should be placed on closely
        monitoring and trending to detect problem situations early.
        Operator response to alarms should be timely, and actions should be
        taken to address and correct the alarm causes.  All reasonable
        action should be taken to clear alarming conditions.  The number of
        evolutions affecting control panel indications that are performed
        concurrently should be limited so that the operators' ability to
        detect and respond to abnormal conditions will not be compromised.
        If computer or automated systems are in place, there should be an
        appropriate backup to those systems.

    4.  Control Operator Ancillary Duties

        Duties assigned to operators should not interfere with their ability
        to monitor facility parameters.  Activities such as preparation of
        tagging orders, reviews of operating procedures, required reading,
        and review of maintenance work activities should not comprise a
        major portion of these operators' shift responsibilities.  The
        administrative workload of operators responsible for monitoring and
        operating the control board should be minimized.  If one operator is
        involved in administrative tasks, other operators should assume
        responsibility to monitor the unit.  Some administrative activities
        are better performed away from the "at-the-controls" area by an
        operator who is not responsible for operating the main control
        panel.

    5.  Operation of Control Area Equipment

        Only persons specifically authorized by the administrative
        procedures of the operations department should operate control area
        equipment.  When trainees operate this equipment, they should be
        supervised and controlled by the operator who normally would perform
        the operations.


                          CHAPTER IV

                        COMMUNICATIONS


A.  INTRODUCTION

    Communications should be highly reliable in providing accurate
    transmission of information within the facility.  This chapter describes
    the important aspects of a plant program for audible communications.

B.  DISCUSSION

    Audible communications are used to transmit operating and emergency
    information within the facility.  Oral (face-to-face), telephone, radio,
    public address (page) announcements, sound-powered phones, and special
    sounds (horns and bells) are examples of audible communications.

    Since accurate communications are essential for the safe and efficient
    operation of facilities, guidance in the use of the various forms of
    audible communication is necessary.  This includes repeating back
    instructions to ensure the accurate transmission and receipt of verbal
    instructions.  Standardized terminology and the use of a phonetic
    alphabet are other means of ensuring that verbal communications are
    understood.

    Many facilities use horns, sirens, bells, and the public address system
    to alert personnel to abnormal or emergency conditions.  These
    communications must be controlled to ensure that they do not detract
    from normal operations and are available in an emergency.

C.  GUIDELINES

    1.  Emergency Communications Systems

        Methods should be implemented to ensure all facility personnel are
        promptly alerted to facility emergencies.  When personnel are
        working in areas where the public address system or emergency
        signals cannot be heard, alternate methods for alerting these
        persons should be utilized.  Flashing lights, personal pagers that
        vibrate and can be felt, and persons dedicated to notifications are
        examples of alternate methods that might be effective.

        Emergency communications systems should be periodically tested to
        ensure that they are functional.  Control areas should have the
        capability of overriding other users of the public address system
        for emergency announcements.

    2.  Public Address System

        Use of the facility public address system (page) should be
        administratively controlled to ensure it retains its effectiveness
        in contacting plant personnel.  Excessive use of the public address
        system for paging of personnel and unnecessary announcements should
        be avoided because excessive use can reduce the impact of important
        announcements and can be distracting.  Facility telephones and other
        point-to-point communications channels should be used in lieu of the
        public address system whenever practical.  Consideration should be
        given to dedicating certain paging system channels to specific
        groups or functions, (e.g., a dedicated channel for routine
        operations or a dedicated channel used only for emergencies).

    3.  Contacting Operators

        Methods should be implemented to ensure that control areas can
        quickly contact on-shift operators or supervisors.  Examples cited
        above in item 1, Emergency Communications Systems, for communication
        in high-noise areas may be effective in accomplishing this function.
        However, to avoid operator confusion, distinction should be made
        between a routine and emergency notifications.

    4.  Radios

        Portable radios can be an effective means of providing mobile
        point-to-point communications and may be used for this purpose.
        However, radio usage should not be allowed in areas where electronic
        interference with plant equipment may result.  Areas where radio use
        is prohibited should be delineated.  Instructions regarding
        frequencies (channels) and postings should be provided.
        Consideration should be given to dedicating certain radio channels
        to specific groups or functions (e.g., a dedicated channel for
        security or a dedicated channel employed integrated surveillance
        tests).

    5.  Abbreviations and Acronyms

        Only abbreviations and acronyms obtained from an approved list
        should be used in facility communications.  Both written and spoken
        terms should be prescribed in the list.  For example, residual heat
        removal service water might be written "RHRSW" and spoken "RHR
        service water."

    6.  Oral Instructions and Informational Communications

        Oral instructions should be clear and concise.  In all
        communications, the sender and intended receiver should be readily
        identifiable.  Instructions involving the operation of equipment
        should be repeated by the receiver to the extent necessary for the
        sender to ensure the instructions are correctly understood.


                           CHAPTER V

                 CONTROL OF ON-SHIFT TRAINING


A.  INTRODUCTION

    Facility operation by personnel under instruction should be carefully
    supervised and controlled to avoid mistakes in operations by unqualified
    personnel and to use trainees' time effectively.  On-shift training
    should be conducted so that the trainee satisfactorily completes all of
    the required training objectives and receives maximum learning benefit
    from this experience.  The guidelines of this chapter relate to control
    of training activities by operations personnel.  Other aspects of
    training are covered by other DOE Orders.

B.  DISCUSSION

    On-shift training is that portion of an operator qualification program
    where the trainee receives training within the job environment and with
    as much hands-on experience as possible.  This period of instruction is
    normally controlled by the operations organization personnel because the
    operation of equipment is usually involved.  Operations-administered
    controls are appropriate for the following aspects of the training
    activities:

    o   On-shift training should adhere to established training programs so
        that instructional uniformity will be maintained.

    o   On-shift instructors/evaluators should be qualified for the
        activities they perform to ensure both correct operation and quality
        training.

    o   Trainees should be supervised by qualified operators so that
        unqualified personnel do not make mistakes that could affect safety.

    o   Policies that direct how trainees may be used to support operations
        work activities should be developed.  These policies should ensure
        that trainee personnel are effectively and appropriately used and
        that they are aware of all operating limits and hazards.

    o   The operations supervisor (or equivalent) should approve the
        training program so that it will best meet operations needs.

    o   On-shift training should be appropriately documented.

C.  GUIDELINES

    1.  Adherence to Training Programs

        On-shift training should be conducted in accordance with training
        programs that specifically identify items the trainee must
        accomplish on shift.  The knowledge requirements for each item
        should be defined as well as what the trainee must do (perform,
        simulate, observe, or discuss).  Both the instructor and the trainee
        should understand what is required for each training item.

    2.  On-shift Instructor Qualification

        On-shift training should be conducted by qualified operators.  This
        may require the successful completion of appropriate instructor
        training requirements for on-shift training.  However,
        operator-qualified training department personnel may also be used.
        The on-shift instructors should be specifically selected, taking
        into account communication skills, technical knowledge, and ability
        to provide trainees with hands-on experience.  In many cases, the
        trainees will actually be operating equipment; this requires special
        instructor techniques in order to prevent misoperation or damage of
        equipment.

    3.  Qualified Operator Supervision and Control of Trainees

        Whenever trainees operate equipment, a qualified operator serving as
        an on-shift instructor should observe the trainee in order to ensure
        the trainee does not make an error that could adversely impact the
        facility.  Until the trainee has demonstrated reasonable proficiency
        in an operation, he/she should discuss the procedure steps,
        cautions, and notes with the instructor.  Trainees should also
        demonstrate actions to be performed by pointing to the control
        switch, valve, breaker, etc., that will be manipulated.

        On-shift instructors should not become complacent with trainees.
        Just because a trainee has performed a task once does not mean he is
        aware of all problems that could occur.  The instructor should
        always monitor the trainee closely and remain in a position to
        intervene or assume control, if necessary.

        When trainees record equipment parameters on official round sheets
        (as opposed to practice round sheets) or logs, the on-shift
        instructor should verify that the recorded information is correct.
        In addition, the trainee and on-shift instructor should discuss any
        out-of-specification readings and the consequences of allowing such
        trend to continue.

    4.  Operator Qualification Program Approval

        The operator qualification program should be approved by the
        operations supervisor, and changes to the program should be
        coordinated with the training department.  For operating positions
        requiring certification, qualifications should be based on
        one-to-one instruction at that station.

    5.  Training Documentation

        Completion of the operator qualification program should be formally
        documented.  Classroom requirements and written exam results should
        be documented by training department instructors.  On-shift training
        and system checkouts should be documented by on-shift instructors.

    6.  Suspension of Training

        Trainee operation of equipment should be immediately suspended
        during unanticipated or abnormal events, accident conditions, or
        whenever the operations personnel or on-shift instructor believes
        suspension is necessary to ensure safe and reliable facility
        operation.  During abnormal or accident conditions, trainees should
        provide assistance at the discretion of the qualified operator.

    7.  Maximum Number of Trainees

        The maximum number of trainees allowed to simultaneously participate
        in any particular training evolution needs to be considered.
        Consideration should be given to training effectiveness and to the
        potential for adverse effects on the facility.  A maximum limit for
        the trainee-to-instructor ratio will ensure that the trainee is
        provided with the most effective instruction and will ensure that
        the instructor is not distracted by having too many trainees at
        once.  Shift supervisors should ensure that established limits are
        observed.


                          CHAPTER VI

               INVESTIGATION OF ABNORMAL EVENTS


A.  INTRODUCTION

    A program for the investigation of abnormal events should ensure that
    facility events are thoroughly investigated to assess the impact of the
    event, to determine the root cause of the event, to ascertain whether
    the event is reportable to DOE in accordance with DOE 5000.3A,
    OCCURRENCE REPORTING AND PROCESSING OF OPERATIONS INFORMATION OF 5/30/90
    and to identify corrective actions to prevent recurrence of the event.
    The program should include the investigation of "near miss" situations,
    thus reducing the probability of a similar situation recurring as an
    actual facility event.  Abnormal events are not unique to the operating
    organization.  Therefore, the guidelines of this chapter may have
    applicability in other areas besides operations.  Required notifications
    associated with abnormal events are addressed in Chapter VII and In DOE
    5000.3A.  This chapter covers important aspects of the abnormal event
    investigation program.

B.  DISCUSSION

    An established and thorough review process should ensure that all
    significant aspects of an abnormal event are identified, investigated,
    and resolved.  In addition, the investigation of "near miss" situations
    can identify detrimental conditions that, if left uncorrected, can
    impact safety and operations.

    A comprehensive review program should identify those types of events
    that require investigation, assign responsibility for conducting the
    investigation, list necessary qualifications for those conducting
    investigations, list the necessary information that must be examined,
    outline the steps for performing an investigation, and establish
    guidelines for assigning and completing corrective action.

    It is helpful to define which circumstances should result in an abnormal
    event investigation.  The criteria should be available to first-line
    supervisors so that, following an event, the investigation process can
    begin in a timely manner.  The list of events or criteria requiring an
    event investigation should be based on DOE requirements.  The
    requirements include such considerations as personnel safety, facility
    safety and reliability, and DOE requirements.

    A manager should have overall responsibility for the event investigation
    process.  However, the manager may delegate specific investigative tasks
    to other personnel as appropriate.

    Investigator qualifications should be established to ensure competency
    in technical aspects of operation and investigative techniques.  The
    credibility of the investigation process will depend heavily on the
    credibility of the event investigators.

    The process of performing an abnormal event investigative should be
    established to ensure the thoroughness of each investigation and to
    ensure consistency between investigations.  The program should describe
    the information collected, investigative techniques utilized, and the
    final reporting format.  Two important products of the event
    investigation are the identification of the root cause and assignment of
    corrective action to prevent recurrence.

    The abnormal event investigation program is needed to thoroughly
    investigate abnormal events, verify the proper operation of equipment,
    identify the root cause of events, ensure all necessary notifications
    are completed, comply with DOE requirements, and ensure appropriate
    corrective action steps are established to minimize the chance of the
    event recurring.  Operations personnel should recognize this need as
    well as their obligation to assist in performing thorough
    investigations.

C.  GUIDELINES

    1.  Events Requiring Investigation

        Events that occur in the facility and adversely affect operations,
        personnel safety, or DOE requirements (DOE 5000.3A) should receive a
        thorough investigation.  The criteria for when to perform an event
        investigation should be clearly established.  Specific events
        requiring investigation should be listed for supervisory use, along
        with criteria for use in deciding what "near miss" situations should
        receive review.  The following conditions and situations should
        require an investigation:

        a.  Design limits are violated (Tech Specs, OSR, SAR, or other
            limits).

        b.  Facility system performance is unusual, abnormal or unexplained.

        c.  Facility safety conditions are abnormal or unexplained.

        d.  Safety or system features are improperly positioned.

        e.  Reportability to DOE or other agencies (e.g., EPA) is
            appropriate.

        f.  An unplanned shutdown or significant loss of operation occurs:

        g.  A procedural violation or personnel error occurs that caused or
            could have caused serious personnel injury or equipment damage
            or could have affected facility safety.

        h.  Equipment failure occurs that could affect facility capability
            or safety.

        i.  Radiological or toxic material limits are exceeded or
            radioactive or toxic material is lost/released.

        j.  Actual or attempted sabotage is suspected.

        k.  Chemistry or process parameters are out of specification or
            indicate unexplained trends.

        l.  A department head or the facility safety review committee deems
            an investigation is appropriate.

        m.  Loss of Special Nuclear Material.

        n.  Repetitive problems occur.

        The above list is not intended to be all-inclusive.  At the
        discretion of the operations supervisor (or other appropriate
        department head), other specific events should receive a formal
        investigation.

        "Near miss" situations should also receive a formal review at the
        discretion of the responsible supervisor.  It is important to review
        "near miss" situations to uncover aspects of the situation that, if
        not identified and corrected, can cause recurrence of the event,
        possibly with more serious consequences.  A "near miss" situation is
        one in which an inappropriate action occurs (or a necessary action
        is omitted) but is detected and corrected before an adverse effect
        on personnel or equipment results.

    2.  Investigation Responsibility

        The operations supervisor or another manager should be responsible
        for event investigations.  He/she may delegate specific
        investigations or portions of investigations to other personnel.
        For example, the initial review following a reactor trip might be
        conducted by the shift supervisor.  Based on the results of the
        shift supervisor investigation, the need for further review will be
        established.  Examples of specific tasks of an investigation that
        may be delegated include gathering necessary records, conducting
        interviews, recommending restart following a reactor trip, and
        determining the long-term corrective action to prevent recurrence.
        However, the overall responsibility for the consistency and
        thoroughness of event investigations should be the responsibility of
        the appropriate manager.

    3.  Investigator Qualification

        The credibility of the investigative process is highly dependent
        upon the knowledge and experience of the individuals performing the
        investigation.  It is important that individuals performing an
        investigation be technically knowledgeable and well respected by the
        facility staff.  Additionally, investigators should not have a bias
        or a vested interest in the results of the investigation.
        Investigators should be trained in facility systems and operations
        and other major disciplines appropriate for the event under
        investigation.  Additionally, investigators should be trained in
        techniques for conducting an investigation.  This can include
        training in areas such a root-cause determination, diagnostics for
        plant events, interviewing techniques, and factors affecting human
        performance.

    4.  Information to be Gathered

        Sufficient data must be collected to allow the event investigators
        to perform a reconstruction and analysis of the event.  An
        individual should be assigned responsibility for collecting the
        required information and assembling the information for review.  It
        is important to collect the necessary information as soon as
        possible after the event.  This will minimize the possibility of
        losing information or that observers of the event will be
        unavailable.  Information should be gathered in the following areas:

        a.  Initial facility conditions.

        b.  Statements of operators and personnel involved in the event
            (this should be permanently recorded).

        c.  Pertinent computed printouts (post-trip log sequence of events)
            and strip charts.

        d.  Pertinent documentation (such as operator logs, radiation work
            permits, chemistry logs, and radiological surveys) as required
            to establish conditions prior to and during the event.

        As listed above, statements of operators and facility personnel
        involved in the event should be obtained.  This item is particularly
        useful because personnel observing or participating in an event can
        provide insights into the facility response during the event and
        into actions leading up to the event that would be not available
        from strip charts or other hard-copy data.  Methods for collecting
        this information can vary; however, the event investigation
        containing relevant information should be permanently recorded for
        future reference.

        When collecting hard copy (such as strip charts), it is important to
        annotate the data with its source, chart speed (if applicable), and
        a time mark to aid in coordinating the data during the
        reconstruction of the event.  The collection of data should not
        interfere with the continued operation of the facility.  Temporary
        interference should occur only if necessary to understand the event.

    5.  Event Investigation

        Upon completion of the data collection, a structured review of the
        abnormal event should occur.  The format of the investigation will
        depend upon the significance of the event.  Each event investigation
        should include the following steps, with emphasis placed on each
        individual step depending upon the severity or potential
        consequences of the event.

        a.  Event Reconstruction

            The abnormal event should be reconstructed using the collected
            information.  When applicable, this is best accomplished using
            the sequence of events recorder printout as a basis.

            If the sequence of events printout is not available (or not
            applicable) or if the abnormal event was not of sufficient
            magnitude or nature to impact the sequence of events recorder,
            then a chronological listing of events should be developed.  It
            is desirable to include the personnel involved in the event in
            the reconstruction process.

        b.  Event Analysis and Evaluation

            Once the facts of the event have been established, the event
            should be analyzed to determine the response of equipment and
            involved personnel.  During the analysis, emphasis should be
            placed on determining the proper response of systems, comparison
            of actual and expected response, adequacy of procedures, and
            factors affecting human performance.  When available, the event
            should be compared with previous event investigations of similar
            events or transients.  During the analysis, a safety evaluation
            should be performed to ascertain the proper response of
            equipment and to identify detrimental effects on facility
            equipment.  If the event was a process shutdown, the
            acceptability of restart may be determined at this time.  In
            some instances, however, steps 5c and 5d below may also be
            required prior to restart.  Supervisors need to be sure no
            further corrective action is required prior to restart.

        c.  Root-Cause Determination

            The root cause of the event should be determined.  The root
            cause can be defined as those causal factors that, if corrected,
            would preclude a recurrence of the event.

        d.  Corrective Action Determination

            Appropriate corrective action should be established for each
            event investigation, and specific personnel should be assigned
            responsibilities for the corrective action.  Corrective action
            can take the form of procedure changes, training, design
            modifications, and changes to administrative controls.  The
            final approval for corrective action should be made by the
            facility manager.

    6.  Investigative Report

        An investigative report should be prepared in a timeframe determined
        by the responsible authority.  The report should include a
        description of the event (including pertinent conditions), a
        discussion of the impact of the event, root cause, the lessons
        learned, and the proposed corrective action(s).  The report should
        include positive aspects of the event (such as particularly
        effective personnel responses).  The investigative report should be
        approved by the facility manager and reviewed by appropriate
        supervisors, managers, and the safety review committee.

        It is important that the lessons learned from an event investigation
        be shared with all appropriate personnel who could benefit from the
        lessons learned.  For example, a problem with an operations
        procedure might also exist in another department's procedures.

    7.  Event Training

        In-house events should be evaluated by the operations supervisor to
        determine if the event should be included in the training program
        for operations personnel.  In some cases, due to the severity or
        possible safety consequences of some events, it is appropriate to
        train shift operations personnel on the event immediately.  A
        mechanism should exist so that appropriate shift personnel could be
        immediately trained on an event when they next report for work.

    8.  Event Trending

        Patterns of deficiencies such as operator errors or inadequate
        procedures should be trended.  A periodic summary report of events,
        causes, and trends should be submitted to department heads, the
        facility manager, and appropriate managers.  Department heads should
        ensure training programs include appropriate material from the
        summary report.

    9.  Sabotage

        Acts of known or suspected sabotage are a special case of event
        investigations.  If an act of sabotage is discovered or suspected,
        it is important to begin an investigation immediately and to
        accomplish the following:

        a.  Determine the condition of the affected system(s) and ensure the
            operability of all safety-related systems;

        b.  Decide if continued operation is justified or if systems are
            available to support safe facility shutdown; and

        c.  Minimize the impact of discovered acts of sabotage and deter
            future acts of sabotage.


                           CHAPTER VII

                          NOTIFICATIONS


A.  INTRODUCTION

    Timely notification of appropriate DOE personnel and other agencies,
    when required, should be employed to ensure that the facility is
    responsive to public health and safety concerns.  This chapter provides
    guidelines to ensure uniformity, efficiency, and thoroughness of these
    notifications to support fulfillment of DOE requirements that are
    consistent with DOE 5000.3A.

B.  DISCUSSION

    For events that require notification of DOE personnel (and when
    appropriate, state and local officials), it is essential that
    information be gathered and transferred in a systematic, controlled
    method.  Procedures that define responsibilities and provide for
    adequate documentation should be used to control the process and ensure
    that the notification procedure is effective.

C.  GUIDELINES

    1.  Notification Procedures

        Procedures should be developed to address appropriate notifications
        and should include the following elements:

        a.  Specific responsibilities for notifications;

        b.  Identification of events and conditions requiring notifications;

        c.  Identification of primary and alternate personnel to be notified
            for various situations;

        d.  Establishment of time requirements for notifications that are
            consistent with the facility emergency plan; and

        e.  Definition of recordkeeping requirements that documents the
            reason for notifications, the time of notifications, and the
            person notified.

    2.  Notification Responsibility

        The operations supervisor should ensure that all appropriate
        personnel receive notification when required.  The actual
        notification of specific individuals or agencies may be accomplished
        by other individuals.

    3.  Names and Phone Numbers

        Names of primary and alternate contacts and current phone numbers
        and page codes should be readily available to the person assigned
        to make the notifications.

    4.  Documentation

        All notifications should be documented.  Fill-in-the-blank forms for
        different types of situations might be useful as a checklist and for
        providing necessary documentation.  In any case, a formal record of
        notifications should be maintained.

    5.  Communication Equipment

        Adequate communication equipment should be maintained in the main
        control area to meet the objectives of this chapter.


                          CHAPTER VIII

             CONTROL OF EQUIPMENT AND SYSTEM STATUS


A.  INTRODUCTION

    Good operating discipline should ensure that facility configuration is
    maintained in accordance with design requirements and that the operating
    shift knows the status of equipment and systems.  Specific applications
    of equipment control are addressed in Chapter IX, Lockout/Tagout;
    Chapter X, Independent Verification; Chapter XI, Logkeeping; and Chapter
    XII, Operations Turnover.  This chapter provides an overall perspective
    on control of equipment and system status.

B.  DISCUSSION

    It is imperative that equipment and systems in a DOE facility be
    properly controlled.  Not only must the operating shift be aware of how
    equipment and systems will function for operational purposes, but in
    order to satisfy the design bases and the operational limits, the proper
    component, equipment, and system configurations must be established and
    maintained.

    DOE facilities are required to establish administrative control programs
    to handle configuration changes resulting from maintenance,
    modifications, and testing activities.  Typically, changes in equipment
    and system configuration are to be communicated from shift to shift
    through the shift turnover process or through an equivalent method of
    controlling status.  Turnover checklists and equipment status boards are
    often used as aids for compiling and transmitting status information
    efficiently and accurately.

    Control over equipment and system status should be established in
    accordance with a formal guidance to ensure that proper configuration is
    maintained.  This guidance should include instructions for system
    alignments, locking of components, verification of technical
    specification compliance prior to plant operating-mode changes,
    authorization prior to removing or restoring equipment to service, and
    identification and documentation of equipment deficiencies.

C.  GUIDELINES

    1.  Status Change Authorization and Reporting

        The operations supervisor is responsible for maintaining proper
        configuration and should authorize status changes to major equipment
        and systems.  Since the supervisor is typically the senior operating
        person on shift, he/she is tasked with maintaining a broad overview
        of facility operations.  His/her perspective of status must
        necessarily be the focal point of shift operations.

        Authorization of status changes to equipment and systems of lesser
        importance may be delegated by the operations supervisor to other
        cognizant shift positions.  For example, radwaste operations may be
        assigned to a radwaste operator or to a foreman who authorizes
        changes in operating alignments or equipment configurations.  The
        shift supervisor should be advised periodically of changes in status
        of equipment and systems so assigned.

        Since the operators must be aware of equipment and system status,
        the supervisor should ensure that all changes in status are
        communicated to these persons.  Typically, the control area operator
        is in the line-of-information flow to and from the supervisor.

        Changes in the status of facility equipment and systems should be
        reported to the governing stations (e.g., control area) or to the
        individual (or his relief) who authorized the change.  Typically,
        changes in status of safety-related equipment and systems should be
        authorized by the supervisor and reported to the control area.

    2.  Equipment and System Alignment

        Prior to first placing the equipment or system into operation,
        individual components for facility equipment and systems should be
        properly aligned or checked for proper alignment.  An initial
        alignment of valves, switches, and breakers establishes a baseline
        configuration against which further operations may be measured.
        Once the equipment or system is properly aligned and is operating in
        accordance with operating procedures, frequent complete alignments
        of all individual components may not be necessary.  Alignment
        checklists should be used to guide the operator in establishing the
        correct component positions.  The alignment checklists should
        include provisions for equipment nomenclature that matches the
        nomenclature placed on the component, a location for individual
        documentation of the check of each component, the required alignment
        position for each component, and a location for annotating
        deviations from the required alignment.  The supervisor should
        review and approve completed alignment checklists.

        The need for a complete alignment of equipment and systems should be
        based on the level of control that has been maintained over the
        status of the components.  Typical situations that may require
        equipment and systems to be aligned include startup from cold
        shutdown, major outages, and mode changes.  In addition,
        safety-related equipment and systems should be functionally tested
        in accordance with surveillance requirements in the technical
        specifications/operational safety requirements following maintenance
        and before the equipment or system is considered capable of
        performing its design function.

        Records of equipment and system alignments should be retained for
        reference by the operating shift.  Administrative controls that
        analyze and document deviations from the reference alignment should
        be established.  Administrative control programs (e.g., tagout/
        lockout, temporary modification, etc.) are addressed in other
        chapters of these guidelines.

    3.  Equipment Locking and Tagging

        Locks and Tags should be used on those components that require
        special administrative control for safety or other reasons.  Locks
        and Tags provide some security that a component will be operated
        only by authorized facility personnel performing required evolutions
        in a controlled fashion.  Additionally, Locks and Tags should alert
        the operator of the importance of the component and remind him/her
        that special controls over repositioning are to be maintained.  In
        this respect, all personnel should receive training regarding their
        responsibilities concerning the manipulation of locked or tagged
        controls.  More details about requirements for Lockout and Tagout
        are found in Chapter IX.

    4.  Operational Limits Compliance

        Administrative controls should be established to document compliance
        with requirements of operational limits (limiting conditions for
        operation).  The operations supervisor should be cognizant of action
        taken to comply with operational limit requirements and should
        ensure that the actions taken are appropriate and correct or that
        they mitigate any adverse consequences to the facility.  Logs,
        status sheets, turnover checklists, or other appropriate
        documentation should reflect the entry conditions and actions that
        are taken in response to operational limits requirements.
        Appropriate operating personnel should be apprised of limiting
        conditions for operations and actions for which they may be
        responsible.  Responsible personnel should periodically review the
        limiting conditions for operation and action statements in effect to
        ensure that the required actions are met.

    5.  Equipment Deficiency Identification and Documentation

        Equipment deficiencies should be noted by facility operating
        personnel and identified in the work control system for correction.
        Methods that identify deficient equipment to operating personnel
        should be established.  Some facilities can use unique deficiency
        tags to identify equipment problems.  Others may use logs, status
        sheets, shift turnover sheets, or caution tags to ensure
        deficiencies are communicated to personnel responsible for
        monitoring and operating the equipment.

    6.  Work Authorization and Documentation

        The operations supervisor or his/her designee should authorize all
        shift activities (including Maintenance) on equipment that is
        important to safety, that affects operations, or that changes
        control indications or alarms.  This authorization should be in
        writing on the document controlling the work.  Documentation of the
        status of work in progress should be available in the control area
        for review by operating personnel.  These activities could include
        such things as maintenance, test, fuel movement, radiography, and
        others.

    7.  Equipment Post-Maintenance Testing and Return to Service

        Equipment should be tested following maintenance to demonstrate that
        it is capable of performing its intended function.  The testing
        should include performance of all functions that may have been
        affected by the maintenance.  The testing should also verify that
        the maintenance performed served to correct the original problem and
        that no new problems were introduced.  Any testing following
        maintenance should be specified on the maintenance work order or
        accompanying documentation (e.g., maintenance procedure).  The
        operations supervisor should ensure that testing appropriately
        proves equipment operability.

    8.  Alarm Status

        The status of control panel and/or local panel alarms should be
        readily available to appropriate operating personnel.  Information
        that should be available includes alarms that are totally disabled,
        alarms with individual inputs disabled, alarms with temporarily
        changed setpoints, alarms that are normally lighted during power
        operation, and multiple input alarms that do not reflash when more
        than one input is activated.

        Appropriate actions should be taken to monitor equipment parameters
        for abnormal conditions that would be masked by deficient or
        non-reflashing alarms.  Color coding of alarm windows or the use of
        deficiency stickers may be useful in enhancing operator awareness of
        these status considerations.

    9.  Temporary Modification Control

        Administrative control systems should be established for
        installation of temporary modifications such as electrical jumpers,
        lifted leads, pulled circuit boards, disabled annunciators/alarms,
        mechanical jumpers/bypasses, temporary setpoint changes, installed
        or removed block flanges, disabled relief or safety valves,
        installed or removed filters or strainers, plugged floor drains, and
        temporary pipe supports.  Prior to modification, these controls
        should provide for communicating the installation of temporary
        modifications to the design authority to allow for technical
        oversight and an evaluation of the impact on current design
        activities, and approval of the design modification.  These control
        systems should make provisions for safety reviews, installation
        approval, independent verification of correct installation and
        removal, documentation of the modification, update of operating
        procedures and documents, training, marking of installed
        modifications, and periodic audits of outstanding modifications.

    10. Distribution and Control of Equipment and System Documents.

        A system should be established to ensure that the operations
        personnel receive and utilize the latest revisions of engineering
        drawings and specifications.  Operations personnel should be made
        aware of all changes to these documents.  The document distribution
        should include all operations related activities such as procedures
        review groups, maintenance groups, facility safety analysis groups,
        and testing groups.


                           CHAPTER IX

                      LOCKOUTS AND TAGOUTS


A.  INTRODUCTION

    The purpose of this chapter is to provide a method for equipment status
    control through component Tagging or Locking which should protect
    personnel from injury, protect equipment from damage, maintain
    operability of plant systems, and maintain the integrity of the physical
    boundaries of plant systems.  If there is a potential for equipment
    damage or injury during equipment operation, servicing, maintenance, or
    modification activities due to inadvertent activation of equipment, a
    facility Lockout/Tagout program should be established and used.  The
    Lockout/Tagout program should provide for independent verification of
    the removal from service and the restoration to service of
    safety-related and other facility equipment.  This chapter describes the
    important elements of a Lockout/Tagout Program and is intended to meet
    the requirements of 29 CFR 1910.

B.  DISCUSSION

    A Tagout program includes the placement of a Tagout device on an
    energy-isolating device, in accordance with an established procedure, to
    indicate that the energy-operating device and the equipment being
    controlled many not be operated until the Tagout device is removed.
    Similarly, a Lockout program includes the placement of a Lockout device
    (e.g., a lock, or hasp with a lock in place) on an energy-isolating
    device in accordance with an established procedure ensuring that the
    energy-isolating device and the equipment being controlled cannot be
    operated until the Lockout device is removed.  An effective Lockout/
    Tagout program should be developed by each facility and should include
    detailed administrative procedures, training of personnel, and uniquely
    identifiable tags.  The program should also exercise appropriate control
    over Lockout/Tagout preparation, approval, placement, and removal;
    provide for adequate documentation; and be consistent with the
    requirements of 29 CFR 1910.

C.  GUIDELINES

    1.  Lockout/Tagout Use

        Locks and Tags should be placed on controls when for safety or other
        special administrative reasons controls must be established.
        Lockout is the application of a lock on a control to render the
        control inoperative.  Locks may be built into the switch or be
        external locks (e.g. padlocks) that may be affixed and or removed
        when necessary.  Keys and/or combinations for Locks are controlled.
        Other devices (such as wiring a control inoperable, placing control
        defeating devices, etc.) may also constitute a lesser degree of
        Lockout.  Tagout is the application of a danger or warning device on
        the control, which indicates that the control is not to be used
        except under conditions indicated by the tag.  Tags should be placed
        on the control that is tagged out, or as close as possible to
        indicate clearly the condition.

    2.  Lockout and Tagout Implementation

        a.  If a device (e.g., for energy or toxic material isolation) has
            the capability of being locked out, it should be locked out.

        b.  If the isolating device cannot be locked out, it should be
            tagged out.

        c.  New equipment design and major modifications to existing
            equipment should be designed to provide the capability of being
            locked out.

        d.  The following administrative guidance is an example that could
            be established to outline acceptable controls over locked
            components:

            (1)  A list of components that are required to be locked should
                 be established and approved by the operations supervisor or
                 appropriate manager.  The list should be separate from the
                 standard alignment checklists.

            (2)  Criteria for locking of additional components and necessary
                 authorizations should be provided.

            (3)  When key operated locks are used, access to the keys should
                 be restricted to authorized personnel.  Keys should be
                 readily available to appropriate personnel.

            (4)  Specific techniques for verifying the position of locked
                 components should be established.  A hands-on physical
                 check of critical equipment or the observation of a
                 reliable position indicator should be used whenever
                 possible.

            (5)  When locked components must be unlocked or placed in a
                 position other than the normal locked position, the
                 deviation should be authorized and documented.

            (6)  Periodic checks of locked components should be performed to
                 ensure that locking devices are properly attached and that
                 the component is in the required position.

    3.  Protective Materials and Hardware

        a.  Locks, tags, chains, wedges, key blocks, adapter pins,
            self-locking fasteners, or other hardware should be provided for
            isolating, securing, or blocking machines or equipment from
            energy sources.

        b.  Lockout and Tagout devices should be singularly identified
            (i.e., should be the only devices used for controlling energy
            and should not used for other purposes) and should meet the
            following requirements:

            (1)  Durable

                 o   Should be capable of withstanding the environment to
                     which they are exposed for the maximum period of time
                     for exposure is expected,

                 o   Should be constructed to minimize deterioration of the
                     tag or the message when exposed to weather conditions,

                 o   Should not deteriorate when used in corrosive
                     environments where acid and/or alkali chemicals are
                     handled and/or stored.

            (2)  Standardized

                 Lockout and Tagout devices should be standardized within
                 the facility in at least one of the following criteria:
                 color, shape, or size.  In addition, Tagout devices should
                 utilize standardize print and format.

            (3)  Substantial

                 Lockout devices should be substantial enough to prevent
                 removal, without the use of excessive force or unusual
                 techniques, such as the use of bolt cutters or other metal
                 cutting tools.

                 When used as the sole means of preventing operation of an
                 energy isolating device, Tagout devices, including their
                 means of attachment shall, in addition to other
                 requirements for their use, be of a non-reusable type,
                 attachable by hand, self-locking, and non-releasable with a
                 minimum unlocking strength of no less than 50 pounds and
                 having the general design and basic characteristics of
                 being at least equivalent to a one-piece,
                 all-environment-tolerant nylon cable tie.

                 Tagout device attachment means should be of a non-reusable
                 type, attachable by hand, self locking, and non-releasable.

            (4)  Identifiable

                 Tagout/Lockout devices should indicate the identity of the
                 personnel and the organization applying the device.

            (5)  Warning

                 Tagout devices should warn against hazardous conditions if
                 the machine or equipment is energized and should include a
                 legend such as the following:  Do Not Start, Do Not Open;
                 Do Not Close; Do Not Energize; Do Not Operate.

    4.  Lockout/Tagout Program

        A Lockout/Tagout program should be established consisting of
        procedures to control potentially hazardous energy and materials and
        personnel training.  This program should ensure that potentially
        hazardous energy or toxic material sources are isolated and rendered
        inoperative during servicing or maintenance or in any case where
        unexpected energizing, startup, or release of stored energy or toxic
        material can cause injury.

    5.  Procedures for Lockout/Tagout

        Procedures should be developed, documented, validated, and utilized
        for control of potentially hazardous energy or material.  Procedures
        should clearly and specifically state the scope, purpose,
        authorization, rules, and techniques of the Lockout/Tagout program.

        a.  Procedures should include, but not be limited to, the following:

            (1)  Specific statement of intent of use;

            (2)  Specific procedural steps for isolating, blocking and
                 securing machines or equipment for hazardous energy or
                 material;

            (3)  Specific procedural steps for the placement, removal, and
                 transfer of the Lockout/Tagout device(s); and

            (4)  Specific requirements to test machines and to determine and
                 verify the effectiveness of Lockout, Tagout or other
                 control measures.

        b.  It is not necessary to document the required procedure for a
            particular machine or equipment, when all of the following
            elements exist.

            (1)  The machine or equipment has no potential for stored or
                 residual energy or reaccumulation of stored energy after
                 shutdown which could endanger personnel.

            (2)  The machine or equipment has a single energy source which
                 can be readily identified and isolated.

            (3)  The isolation and locking out of that energy source will
                 completely de-energize and de-activate the machine or
                 equipment.

            (4)  The machine or equipment is isolated from that energy
                 source and locked out during servicing or maintenance.

            (5)  A single lockout device will achieve a locked out
                 condition.

            (6)  The lockout device is under the exclusive control of the
                 authorized personnel performing servicing of maintenance.

            (7)  The servicing or maintenance does not create hazards to
                 other personnel.

            (8)  The employer, in utilizing the exception, has had no
                 accidents involving the unexpected activation or
                 reenergization of the machine or equipment during servicing
                 or maintenance.

        c.  Documentation of Lockout/Tagout

            Lockout/Tagout placement, activation and removal should be
            recorded including any information relevant to their occurrence.
            This record should be maintained by the shift supervisor or
            appropriate manager to ensure accuracy and completeness.  The
            Lockout/Tagout record should be reviewed periodically by
            operations and maintenance personnel as guidance.

    6.  Application of Lockout/Tagout

        The established procedure for the application of energy control
        (implementing Lockout/Tagout) should cover the elements and actions
        in the following sequence:

        a.  Preparation for Shutdown

            Before a machine is turned off, personnel should be informed of
            the type and magnitude of the energy, the hazards and the
            methods of control.

        b.  Machine or Equipment Shutdown

            The equipment should be shutdown using the procedures required
            by this chapter.  An orderly shutdown should be utilized to
            avoid any added hazard.

        c.  Equipment Isolation

            All Lockout/Tagout devices needed for control are physically
            located and operated in such a manner as to isolate the
            equipment from the energy source.

        d.  Affixing Locks/Tags

            Lockout or Tagout devices should be affixed to each isolation
            device by qualified personnel in a manner that will hold the
            devices in a "safe" or "off" position or clearly indicate that
            operation of the device is prohibited.

        e.  Stored Energy

            Upon application of Lockout or Tagout devices, all potentially
            hazardous stored or residual energy should be relieved,
            disconnected, restrained, or otherwise rendered safe.  If stored
            energy might re-accumulate to a hazardous level, verification of
            isolation should be continued until the servicing or maintenance
            is completed.

        f.  Verification of Installation

            Prior to starting work on equipment that has been locked or
            tagged out, personnel should verify that isolation and
            deenergization have been accomplished.

        g.  Release from Lockout/Tagout

            Before Lockout or Tagout devices are removed and energy restored
            to the equipment, procedures should be followed and actions
            taken by personnel to ensure the following:

            (1)  Equipment/workspace.  The machine or equipment is
                 operationally intact.  The area has been inspected to
                 ensure that nonessential items have been removed.  The
                 individual authorizing tag removal should specify the final
                 component position and, when appropriate, the sequence in
                 which components should be positioned.  In addition, the
                 need to check the positioning of other components that were
                 not locked, or tagged, but are related to the operation of
                 the Lockout/Tagout component, should be determined at this
                 time and appropriate instructions should be developed.
                 These checks should be done when necessary, to ensure that
                 components within the Locked/Tagout boundaries are
                 correctly aligned to support operation.

            (2)  Personnel.  The workspace should be checked to ensure that
                 all personnel have been positioned safely or removed from
                 the area.  Before Lockout/Tagout devices are removed and
                 equipment energized, affected personnel should be notified
                 that equipment will be energized.

            (3)  Lockout/Tagout Device Removal.  Each Lockout/Tagout device
                 should be removed from each energy-isolating device by the
                 person who applied the device.  He/she should reposition
                 the components in the sequence specified and check the
                 positioning as deemed necessary.  The removal of Locks or
                 Tags should be documented.  Tags should be returned to the
                 operations supervisor or authorizing manager.  The
                 supervisor/manager should be satisfied that all tags and
                 safety devices associated with this Lockout/Tagout are
                 removed and are accountable.

                 When the person who applied the Lockout/Tagout device is
                 not available to remove it, that device may be removed
                 under the direction of the appropriate supervisor/manager,
                 provided that specific procedures and training for such
                 removal have been developed and incorporated into the
                 facility program.  The supervisor should demonstrate that
                 the specific procedure provides equivalent safety to the
                 removal of the device by the authorized personnel who
                 applied it.  The specific procedure should include the
                 following elements:

                 o   Verification by the supervisor/manager that the person
                     who applied the device is not available.

                 o   Assurance that all reasonable efforts are made to
                     inform him/her that the device has been removed.

                 o   Ensuring that all relevant personnel have this
                     knowledge before he/she resumes work at the facility.

    7.  Testing or Positioning of Equipment or Components

        Temporary removal of Lockout/Tagout devices should be discouraged.
        However, situations in which Lockout/Tagout devices must be
        temporarily removed and the equipment energized, the following
        sequence of operations should be followed:

        1.  Clear the equipment of tools and materials.

        2.  Remove personnel from the equipment area.

        3.  Remove the Lockout/Tagout device as procedures indicate.

        4.  Energize and proceed with testing or positioning.

        5.  De-energize all systems and reapply the lockout/tagout.

    8.  Periodic Inspections

        Periodic inspections should be conducted by authorized personnel,
        supervisor, or appropriate manager, to determine whether procedures
        are being followed and to correct any deviations or inadequacies
        observed.  Inspections should include a review of the
        responsibilities of personnel and supervisors.  The supervisor or
        appropriate manager should certify that the periodic inspections
        have been performed, documenting the equipment and procedures
        involved, dates of inspection, personnel participating in the
        inspections, and personnel performing the inspections.

    9.  Caution Tags

        Caution tags should not be used for personnel protection (i.e.,
        caution tags should not be used where it is appropriate to use a
        Lockout or Tagout devise).  Administration of caution tags could,
        however, be accomplished as part of the Lockout/Tagout program or it
        could be covered separately.  The use of caution tags should be
        restricted to those situations in which a component or system is
        functional, but when some precaution or item(s) of information is
        necessary prior to operation.  In addition, the program should
        include the following elements:

        a.  Caution tags should be uniquely identifiable and different in
            appearance from other station tags.  The following information
            should be included on the tags as an aid in administering the
            program:

            (1)  caution tag number;

            (2)  component name and number;

            (3)  effective date;

            (4)  precaution or information applicable to the particular
                 situation and/or component or system; and

            (5)  signature of authorizing individual and organization.

        b.  Situations that require special operator or maintenance
            precautions or amplifying information should be brought to the
            attention of the shift supervisor or appropriate manager.  The
            supervisor or manager should ensure that issuing a caution tag
            is necessary and that the tag is not being used in place of more
            appropriate administrative action (such as a temporary procedure
            change, placing an operator aide, use of the work control
            system, or issuance of a safety Lockout or Tagout).  The
            supervisor review should also ensure that any instruction
            contained in the caution tag does not deviate from established
            facility procedures, technical specifications, or OSR's.

        c.  A record of all active caution tags and associated amplifying
            information should be available to the appropriate personnel.
            This record and associated tags should be reviewed periodically
            by qualified personnel.  This review should verify the continued
            need and applicability for each caution tag and ensure that the
            caution tag index accurately reflects all active caution tags.
            This review should be documented.  Any caution tags remaining in
            an active status for extended periods (e.g., longer than three
            months, as appropriate) should be brought to the attention of
            the operations supervisor or manager.  The operations supervisor
            or manager should determine what action is needed to resolve the
            continued use of the caution tag.

        d.  Caution Tag Placement

            Caution tags should be placed in such a way that they do not
            interfere with or obscure indications, switches, or other
            control devices but are readily apparent to an individual prior
            to the operation of the tagged device.  Placement of caution
            tags should be documented.

    10. Training and Communication

        a.  Training should be provided and documented to ensure that the
            purpose and function of the Lockout/Tagout program is understood
            by all personnel and that they have the knowledge and skills
            required for safe application, use, and removal of Lockouts and
            Tagouts. Training should include the following:

            (1)  Recognition of applicable hazardous energy sources, type
                 and magnitude of energy or materials involved and methods
                 to isolate and control.

            (2)  Personnel involved should be instructed in the purpose and
                 use of the Lockout/Tagout procedures.

            (3)  All personnel who may enter the area should be trained to
                 recognize the Lockout/Tagout and to understand the
                 procedure and prohibition relating to attempts to restart
                 or re-energize machines or equipment.

        b.  When Tagout systems are used, personnel should be trained in the
            limitations of tags:

            (1)  Tags are essentially warning devices and do not provide
                 physical restraint on those devices as are provided by a
                 lock.

            (2)  When a Tag is attached, it is not to be removed without
                 authorization of the person responsible for it, it should
                 not be bypassed, ignored, or otherwise defeated.

            (3)  Tags must be legible and understandable by all personnel.

            (4)  Tags and their means of attachment should be able to
                 withstand the environmental conditions encountered in the
                 workplace.

            (5)  Tags may evoke a false sense of security and their meaning
                 needs to be understood.

            (6)  Tags must be securely attached so they cannot be
                 inadvertently or accidentally detached during use.

        c.  When Lockout systems are used, personnel should be trained in
            the limitations of Locks, especially concerning the following:

            (1)  Operation of the facility may be hindered (this is
                 significant when local component operations are necessary,
                 such as remote shutdown or remote control).

            (2)  Locks and chains installed on small instrument line
                 isolation valves can contribute to seismic loading and may
                 not have been considered during safety analysis.

        d.  Retraining

            Retraining should be provided for all authorized or affected
            personnel whenever there is a change in job, procedures,
            machines, equipment or processes that present new hazards or
            periodic inspection determines it is needed.

    11. Lockout or Tagout Implementation

        Lockout or Tagout should only be accomplished by authorized,
        qualified personnel.

    12. Notification of Personnel

        A supervisor or appropriate manager should notify affected personnel
        of the application and removal of Lockout/Tagout devices.
        Notification should be given before the devices are applied and
        after they are removed.

    13. Outside Contractors

        Whenever outside servicing personnel are to be engaged in activities
        covered by the scope of the Lockout/Tagout program, the facility and
        the outside contractor should inform each other of their respective
        Lockout/Tagout procedures and should ensure that their personnel are
        aware of the changes.

    14. Group Lockouts or Tagouts

        When servicing or maintenance is performed by a crew, craft,
        department, or other group, they should utilize a procedure that
        will provide for equivalent safety provided by the personal Lockout
        or Tagout device.

    15. Shift or Personnel Changes

        Specific procedures should be utilized during shift of personnel
        changes to ensure the continuity of Lockout or Tagout protection,
        including provision for the orderly transfer of Lockout or Tagout
        devices between personnel or shifts.


                           CHAPTER X

                    INDEPENDENT VERIFICATION


A.  INTRODUCTION

    An independent verification program should provide a high degree of
    reliability in ensuring the correct facility operation and the correct
    position of components such as valves, switches, and circuit breakers.
    This chapter describes the important aspects of an independent
    verification program.  Other equipment status control programs are
    addressed in Chapter VIII, Control of Equipment and System Status, and
    some applications of independent verification are addressed in Chapter
    IX, Tagouts.  Additionally, appropriate investigations for component
    mispositioning events are discussed in Chapter VI, investigation of
    Abnormal Events.

B.  DISCUSSION

    Independent verification is the act of checking that a given operation
    conforms to established operational criteria, as well as checking a
    component position independently of activities related to establishing
    the component's position.  A comprehensive independent verification
    program will identify components to be included in the program, define
    when independent verification is required, and prescribe the methods of
    performing independent verification.  Similarly, independent auditing of
    operations should confirm that established operational requirements are
    met.

    Because the possibility of mispositioning may be quite remote, or
    because the effect of a mispositioning may not be significant to safe
    and reliable operation, not all components require independent
    verification.  Therefore, it is important to identify those components
    that must be independently verified.  Designating systems or components
    that require independent verification ensures the program will be
    consistently applied.

    Definition of when independent verification is required will also help
    ensure consistent application of the program.  The criteria should
    ensure that independent verification is performed in all cases where a
    reasonable potential exists for component mispositioning.

    Independent verification recognizes the human element of component
    operation; that is, any operator, no matter how proficient, can make a
    mistake.  This concept should be stressed in an independent verification
    program so that the operators' confidence in the ability of their peers
    will not cause a relaxation of attentiveness with respect to
    verification tasks.  Operators should understand the importance of the
    independent verification program and address this task with a high level
    of personal integrity and discipline.

C.  GUIDELINES

    1.  Components Requiring Independent Verification

        Components that are critical to ensure safe and reliable operation
        should receive an independent verification of their position when
        circumstances warrant.  These components should be identified
        explicitly in facility procedures or other official documents so
        that unnecessary interpretation of requirements will be minimized.
        In addition, this will result in uniform practices by operations
        personnel.  Because mispositioning of certain components that are
        not safety related can lead to facility shutdowns, challenges to
        safety-related equipment, or other undesirable effects on facility
        safety and reliability, independent verification should not be
        limited to safety-related system components.  Each facility should
        use an accepted safety analysis method (e.g., fault-tree analysis,
        Probability Risk Analysis) and/or expert opinion to determine its
        own facility specific list of systems and components, which should
        receive independent verification in accordance with the following
        guidelines:

        a.  Safety-Related Systems

            All components in systems that have safety-related functions
            should be considered for independent verification.  However, if
            the following criteria have been met, some components might not
            need independent verification:

            (1)  Mispositioning would not affect system performance.

                 For example, if an engineering analysis has shown that
                 mispositioned vent or drain valves do not affect system
                 performance, they might not require independent
                 verification.

            (2)  The mispositioning would be known immediately to an
                 operator.

                 For example, resetting a steam-supply trip valve might not
                 require independent verification if an annunciator alarm in
                 the control room were available to alert operators to an
                 improperly reset valve.  However, such annunciator alarms
                 should be independent from the valve position lights
                 associated with main control board valve operation
                 switches.  Valve position lights alone should not warrant
                 exemption from independent verification requirements,
                 because these lights might not alert operators to a
                 mispositioned valve.  Mispositionings have occurred when
                 main control board indication was available.

            (3)  Significant radiation exposure would be received by the
                 person(s) performing the independent verification.

                 In this case, alternate means for independent verification
                 that do not involve radiation exposure, such as observing
                 process parameters (Section C.3), should be considered.

            Variances from independent verification requirements in
            accordance with the above criteria should be approved by the
            operations supervisor.

        b.  Systems Not Related to Safety

            Independent verifications should be performed for certain
            components that are not related to safety which, if,
            mispositioned, could lead to unplanned shutdowns, challenges to
            safety systems, or (through interfaces with safety-related
            systems) cause radioactive or toxic material release.  For
            example, component positions necessary to support the operation
            of important facility equipment, such as redundant generator
            stator cooling water pumps or turbine control oil (EHC) pumps,
            should be independently verified in order to prevent unnecessary
            process shutdowns.  Also, certain valve positions in liquid or
            gaseous radioactive waste systems should be independently
            verified if a mispositioning could lead to an unintended
            radioactive or toxic material release.

    2.  Occasions Requiring Independent Verification

        Components should receive independent verification when the
        equipment they serve must be available and when a reasonable
        possibility exists that the components might have been
        mispositioned.  The following guidelines describe situations where
        independent verification would be appropriate:

        a.  Returning Equipment to Service Following Maintenance or Testing.

            Independent verifications should be performed to ensure that
            systems are properly aligned when equipment is returned to
            service.  After maintenance activities, it is appropriate to
            verify independently the positions of components that have been
            tagged to establish an isolation boundary for the work.  Also,
            additional components that could have been mispositioned during
            maintenance should be selected for verification on a
            case-by-case basis by the individual authorizing equipment for
            return to service.

            Such additional items requiring verification would include any
            component(s) that had been worked on and might also include
            instrument stop valves, bypass valves, switches, and isolation
            valves located within the work boundary.

            Failure to properly restore systems following surveillance
            testing has resulted in mispositionings.  Selected components
            should therefore be independently verified during, or after
            surveillance tests.  Surveillance tests are normally performed
            in strict adherence to detailed procedures that specifically
            address each operating component.  Components not addressed by
            the test procedure would not be likely to be mispositioned as a
            result of tests, and independent verification would be necessary
            only for components that had been positioned during tests.

        b.  Removing Equipment From Service

            To ensure that only the specific items of equipment intended to
            be removed from service are affected by Tagouts, independent
            verifications should be performed when equipment is removed from
            service.  For example, when tagging out a pump, a verification
            that the redundant pump was not inadvertently affected should be
            performed.  This might be done by checking for correct alignment
            of components on the redundant equipment, or this might be done
            by verifying that all Tags were placed on the correct
            components.

        c.  System Lineups

            During extended shutdowns, it is often impractical to completely
            restore systems to their normal operating alignment immediately
            after maintenance is completed.  Therefore, most facilities
            delay restoration of systems not needed for shutdown activities
            until shortly before startup.  At that time, all systems whose
            status is questionable are checked.  When system lineups are
            performed, the considerations of Section C1, Components
            Requiring Independent Verifications, should be applied to
            determine the need for independent verification.

        d.  Periodic Checks During Facility Operation

            In order to verify that all associated equipment is fully
            functional, DOE facilities should perform routine, periodic
            verifications of certain critical components during normal
            operations.  Since this check is independent from any activity
            that might have caused a component to be mispositioned, it can
            be considered an independent verification; a second check
            normally would not be necessary.  However, if a mispositioning
            were discovered while the periodic check was being performed,
            the component position would then be corrected after review
            and/or approval by a qualified supervisor; an independent
            verification of this action would be appropriate.

    3.  Verification Techniques

        Operators should be trained in the appropriate techniques for
        verifying the positions of all facility components.  In addition, a
        reference document should be provided explaining what an operator
        should do when verifying a component position. Because of the large
        variety of components in use in DOE facilities, it is not feasible
        to provide specific instructions for verification of individual
        component positions without facility-specific knowledge.  Each
        facility should use its most experienced personnel to develop these
        instructions, using applicable manufacturer's recommendations where
        available.  The instructions should describe the techniques for
        verifying manual valves, motor- and air-operated valves,
        solenoid-operated valves, circuit breakers, blank flanges, removable
        links and fuses, and the availability of control power.  These
        instructions will help to ensure that operators use approved methods
        when verifying component positions and will help provide uniformity
        in operator performance.  The following general guidelines apply to
        component verification techniques:

        a.  Independence

            Independent verifications should be conducted in a manner such
            that each check constitutes an actual identification of the
            component and a determination of both its required and actual
            positions.  To be independent, the integrity of the checks must
            be maintained by minimizing interaction between the personnel
            operating components and those performing the independent
            verifications.  It is not always possible to determine if an
            operator has completely shut or opened a valve by merely
            observing the action; mistakes in component identification or
            requirement determination might not be caught without both
            individuals' reading the labels and procedures.

        b.  Remote Position Indicators

            Some equipment failures have caused valve position indicating
            lights on the main control board to be incorrect, and some of
            these failures were undetected for a significant length of time.
            Since the failure may be in the sensor or transmission,
            independent verification should be performed locally unless
            ALARA or other overriding factors preclude.  In this case,
            independent verification may be done at a remote position
            indicator.

        c.  Process Parameters

            In some situations, a component's position can be determined by
            observing such process parameters as pressure, flow, or voltage.
            The observation of process parameters, combined with a physical
            check of a component's position, can constitute an independent
            verification.  However, care must be exercised when using
            process parameters because alternate flow paths or other factors
            could cause them to be misleading indicators of component
            position.  For example, voltage on a bus would prove that a
            particular supply breaker was shut only when there was no
            alternate power supply.  Additionally, flow and pressure do not
            necessarily indicate that a valve is fully open.  For the above
            reasons, process parameters normally should not be used as the
            only indication of a component's position.  Facility procedures
            should specify where and when process parameters are acceptable
            indicators of component position.

        d.  Throttled Valves

            Verifying throttled valves by shutting and reopening the valve
            by a prescribed number of turns should be avoided because this
            practice has the potential to create valve mispositionings.
            Instead, position indicators, scribe marks, or other officially
            recognized and designated indicators should be used to determine
            throttled valve positions.  When shutting and reopening a
            throttled valve are necessary to determine its position, having
            a verifier observe a valve operator's actions would be
            preferable to having both persons independently shut and reopen
            the valve.  This would cause the verification to be partially
            nonindependent, a situation preferred in this case because, when
            a valve is operated to check its position, the action
            effectively nullifies any previous check.

        e.  Surveillance Testing

            In some cases, surveillance testings may be substituted for
            normal verification techniques.  A notable example would be a
            full-flow test to prove the correct positioning of flow
            controlling P-valves.  However, surveillance tests frequently
            will not serve to verify the position of all components that are
            important to subsequent system's operation.  For example,
            running a pump in recirculation would not prove that all main
            flow-path valves were properly positioned or that support
            functions such as external cooling or backup lube oil pumps are
            aligned properly.

            Surveillance testing therefore should not be used as independent
            verification, unless it can be shown that the test conclusively
            proves the position of the components in question.  The
            applicability of surveillance testing to satisfy independent
            verification requirements should be approved beforehand by the
            operations supervisor.

        f.  Operations Self-Appraisal and Verification

            Programmatic operations appraisals should be independently
            conducted and/or verified to ensure that environment, safety,
            and health considerations, and operations functions (such as
            training) are being conducted in accordance with established
            operational criteria.


                           CHAPTER XI

                           LOGKEEPING


A.  INTRODUCTION

    The operations records should contain a narrative log of the facility's
    status and of all events as required to provide an accurate history of
    facility operations.  As used in this context, logs are defined as a
    narrative sequence of events or functions performed at a specific shift
    position, as opposed to the operator round sheets that are discussed in
    Chapter II, Shift Routines and Operating Practices.  This chapter
    describes the features needed in the operation logs to ensure they are
    properly maintained.

B.  DISCUSSION

    Operation logs should be established for all key shift positions in
    order to record fully the data necessary to provide an accurate history
    of facility operation.  Events should be recorded in a timely fashion in
    order to ensure the accuracy of the entry.  The scope, type, and data
    required by management is properly entered into the logs.  This includes
    documentation of actions taken, activities completed, transfer of
    information among operators, and data necessary for event
    reconstruction.

    A review schedule for the operating logs should be established to ensure
    they are adequately maintained and that operations personnel are aware
    of the information contained in the logs.  Administrative controls
    should be established to ensure that all operating logs are readily
    available for a sufficient period of time to allow for the transfer of
    information among the operators.

C.  GUIDELINES

    1.  Establishment of Operating Logs

        Narrative logs should be established at all key shift positions.  As
        a minimum, a narrative log should be maintained by the operations
        supervisor or the control area operator.  For those shift positions
        that are manned on a part-time basis (e.g., radwaste operator,
        makeup plant, etc.) a log should be established to ensure that
        pertinent information is passed from operator to operator.  A
        narrative section should be provided on round sheets when a
        narrative log is not used for a particular shift position.

    2.  Timeliness of Recordings

        Information should be promptly recorded in the logs.  Delaying the
        recording of activities or events often leads to incomplete or
        inaccurate entries.

    3.  Information to be Recorded

        The operations supervisor should provide written guidance to define
        thoroughly the type and scope of entries for each log and the format
        for making entries.  The following information should be recorded in
        at least one station log, although any one log might not contain all
        these items:

        a.  Facility mode or condition changes (e.g., shutdown, operations,
            run, startup, refueling, etc.);

        b.  Criticalities and appropriate critical data (for DOE reactors);

        c.  Abnormal facility configurations;

        d.  Status changes to safety-related and other major facility
            equipment;

        e.  Occurrence of any reportable events;

        f.  Initiation and completion of surveillance tests;

        g.  Entering and exiting operational limit actions;

        h.  Security incidents;

        i.  Out-of-specification chemistry or process results; and

        j.  Shift reliefs.

        To aid in event reconstruction, as much significant information as
        possible should be logged during emergencies and abnormal or
        unexpected events.  However, logkeeping should not take precedence
        over controlling and monitoring the facility.

    4.  Legibility

        Log entries should be made in a manner such that they can be easily
        read and understood.  Additionally, the log entries should be
        readily reproducible with standard photocopy machines. For these
        reasons, black, waterproof ink is recommended.

    5.  Corrections

        A standardized method for correcting any erroneous entries should be
        established.  The method chosen should not obscure the incorrect
        entry.  Log entries should not be erased or covered up.  Corrections
        can be made by placing a single line through the incorrect entry and
        writing the correct entry in a nearby space.  All corrections should
        be initialed and dated.

    6.  Log Review

        Control area logs should be reviewed periodically by the operations
        supervisor and logs kept by operators outside the control area
        should be reviewed by the control area operator or an appropriate
        supervisor.  These reviews should ensure that entries are accurate
        and adequate.

    7.  Care and Keeping of Logs

        Management should provide written guidance on the disposition of
        completed logs.  This guidance should address the following:

        a.  Making the logs available for operators who return after periods
            of absence from their regular duties;

        b.  Storing the completed logs to ensure preservation for the
            expected life of the facility; and

        c.  Retrieving stored logs should this become necessary.


                          CHAPTER XII

                      OPERATIONS TURNOVER


A.  INTRODUCTION

    Operations shift turnovers should provide oncoming operators with an
    accurate picture of the overall facility status.  This chapter
    complements the guidelines of Chapter II, Shift Routines and Operating
    Practices, and Chapter III, Control Area Activities, and describes the
    important aspects of a good shift turnover.

B.  DISCUSSION

    Shift turnover is a critical part of DOE facility operation.  Personnel
    should not assume operational duties unless they are physically and
    mentally fit to do so and until they and the offgoing personnel have a
    high degree of confidence that an appropriate information transfer has
    taken place.

    Oncoming personnel should conduct a comprehensive review of appropriate
    written (logs, records) and visual (equipment, control boards)
    information before responsibility for the shift position is transferred.
    Oncoming personnel could arrive early or offgoing personnel could stay
    late so that adequate review time is available.

    Shift turnovers should be guided by a checklist and should include a
    thorough review of appropriate documents describing important aspects of
    facility status and should include an inspection of appropriate facility
    instrumentation.  These reviews should then be complemented by a
    discussion between the offgoing and oncoming operators.

C.  GUIDELINES

    1.  Turnover Checklists

        As a minimum, supervisory positions should have a turnover checklist
        to be used in the turnover process.

        a.  Equipment Operator Checklists Equipment operator checklists, or
            other formal documents, should provide for noting major
            components status (e.g., operating pumps, trains in service,
            etc.), abnormal lineups, valid alarms on all pertinent local
            control panels, and surveillances or evolutions planned or in
            progress.  Provisions should also be made for documenting that a
            review of round sheets and narrative logs has been performed by
            the oncoming operator.

        b.  Operator Checklists

            Operator checklists or other documents reviewed at shift change
            should provide for recording vital information about the
            following facility status.  Examples may include:

            (1)  Facility power level, test status, or equivalent;

            (2)  Key temperatures limit status;

            (3)  Key pressures limit status;

            (4)  Important tank levels;

            (5)  Safety equipment status;

            (6)  Operational limits in effect;

            (7)  Other important parameters;

            (8)  Required chemistry or process sample times;

            (9)  Maintenance, surveillances, tests, or evolutions (in
                 progress or planned);

            (10) Problems experienced with equipment and major equipment out
                 of service;

            (11) When specific planned actions are required;

            (12) Changes in radiological or hazardous materials conditions;
                 and

            (13) Temporary procedure changes in effect.

            Operator checklists may require documenting reviews of certain
            facility status documents.  These may include the operator's own
            operating (narrative) log, the Tagout (clearance) log, the
            temporary modification and jumper logs, the out-of-service
            annunciator log, the operational limit action log, the shift
            order books, and required reading since the last shift.  Each
            operator turnover checklist should be provided with enough space
            for the offgoing operator to list other important information
            his relief should have.

        c.  Operations Supervisory Checklists

            Operations supervisory checklists or other documents reviewed at
            shift change should provide vital information about facility
            status.  Examples may include:

            (1)  Facility status;

            (2)  Evolutions (completed, in progress, or planned);

            (3)  Controlled key status;

            (4)  Abnormal lineups or conditions;

            (5)  Changes in radiological or hazardous substance conditions;

            (6)  Surveillance tests planned or in progress;

            (7)  Maintenance planned or in progress; and

            (8)  Waste management status.

            Operations supervisory checklists should require documenting
            review of certain status documents.  These can include the
            supervisor's own narrative log, the status log, the equipment
            status checklist, the emergency safeguards equipment list, shift
            order books, and required reading since the last shift.

    2.  Document Review

        Oncoming operators and supervisors should review documents specified
        on their checklists prior to assuming responsibility for their shift
        position.  Document review should be as intensive as necessary for
        the oncoming personnel to understand important history, present
        status, and planned events.  Normally, narrative log entries for the
        previous 24-hour period or since his/her last shift should be
        reviewed. Status logs should be reviewed so that the operator and
        supervisors are familiar with all currently active entries, with an
        emphasis on what has changed since he/she last had the shift.

    3.  Control Panel Walkdown

        Walkdowns of appropriate control panels should be conducted by each
        shift watchstander.  The purpose of a panel walkdown is to determine
        plant status through observation of system lineups, switch
        positions, lighted annunciators, chart recorders, and status lights.

        Oncoming operations supervisors should walk down the main control
        panels before, during, or shortly after shift turnover.  Oncoming
        and offgoing control area operators should walk down their unit's
        main control panel together.  Equipment operators should review all
        pertinent local control panels, (e.g., fuel supplies, lubrication
        levels, makeup water treatment, and ventilation) during their tour
        early in the shift.

    4.  Discussion and Exchange of Responsibility

        At a time when facility conditions are stable, the offgoing
        supervisor or operator should explain all items noted on the
        turnover checklist, and the oncoming operator or supervisor should
        ask any pertinent questions.

        When all operations personnel are satisfied that the oncoming crew
        is fully cognizant of the plant conditions, the oncoming operators
        and supervisors should state that he/she is assuming responsibility
        for the shift position with an entry into the log.

    5.  Shift Crew Briefing

        Crew briefing should be conducted by the operations supervisor as
        required and may be conducted after he has accepted responsibility
        for the shift.  The briefing should include a review of the status,
        problems with equipment, and evolutions in progress or planned
        during the shift.  In addition to shift operators, personnel from
        support groups (e.g., contractors, vendors, and test groups) should
        also attend briefings when their activities can directly affect
        operations.  This practice results in better understanding of shift
        priorities and objectives among operations and support personnel.

    6.  Reliefs Occurring During the Shift

        Reliefs occurring during the shift (e.g., exchange of control
        supervisory function) should have a turnover to ensure that the
        oncoming person is at least as knowledgeable of the conditions as he
        would have been had a complete shift turnover process been
        conducted.  For example, control panel walkdowns and log reviews may
        or may not be necessary, depending on the oncoming person's
        familiarity with the current conditions.


                             CHAPTER XIII

      OPERATIONS ASPECTS OF FACILITY CHEMISTRY AND UNIQUE PROCESSES


A.  INTRODUCTION

    Operational monitoring of facility chemistry or unique process, data and
    parameters should ensure that parameters are properly maintained.
    Maintenance of proper processes will promote maximum component life.
    Monitoring will identify problems such as air inleakage, failed fuel, or
    resin depletion before components or safety are adversely affected.  A
    close coordination between the operations and chemistry or process
    departments is necessary for this to be effective.  This chapter
    describes the important aspects of operations involvement in chemistry
    and unique processes.

B.  DISCUSSION

    In order to enhance proper process control of systems, operations
    personnel must have an understanding of all facility processes and must
    effectively coordinate operations activities with the respective
    technical process support departments.

    Operators should understand the responsibilities associated with their
    positions (both in process monitoring and control and in interface with
    the technical process department).  So that they can identify early
    signs of process-related problems.  Operators should also understand how
    equipment and operational problems affect process conditions.  A good
    working relationship between the operations and technical process
    departments should be established so the facility staff can effectively
    control facility processes.

C.  GUIDELINES

    1.  Operator Responsibilities

        The operations supervisor should define each operator's specific
        responsibilities with respect to process control.  In general,
        operators should monitor chemistry or process parameters using
        control room instruments and other instruments related to equipment
        under operations control.  Operators should be able to recognize
        out-of-specification conditions or adverse trends and be familiar
        with corrective actions associated with chemistry or process
        problems.  Operators should consult and be advised by chemistry or
        technical process department personnel.  By monitoring key
        parameters and taking appropriate action promptly, long-term adverse
        effects of chemistry or process problems can be avoided or
        minimized.

    2.  Operator Knowledge

        Operators should be knowledgeable about aspects of facility
        processes and safety that affect operation and should be able to
        analyze off-normal situations and take appropriate action to correct
        the causes(s) of problems.  Examples of the types of concepts and
        processes with which operations personnel should be familiar include
        the following:

        a.  Concepts of pH, conductivity, cation conductivity, and dissolved
            oxygen and the effect these parameters have on the facility.

        b.  The radiochemical indications of failed fuel (for DOE reactors).

        c.  How demineralizers work and how to determine if they are
            performing inefficiently.

        d.  The purpose and hazards associated with facility storage and use
            of such chemicals as boron, acids, caustics, chromates,
            hydrazine, ammonia, solvents containing chlorinated
            hydrocarbons, and chemicals containing organics.

        e.  Chemical and radiochemical parameters, including calculations
            associated with technical specifications/operational safety
            requirements.

        f.  Chemistry parameters monitored in the control room or on local
            panels under the responsibility of facility equipment operators.

        g.  Properties and hazards of such gases as hydrogen, nitrogen,
            carbon dioxide, chlorine, and halon.

        h.  Corrosion problems, including stress corrosion, intergranular
            cracking, and ammonia attack of copper alloys.

        i.  The chemical constraints, process equipment, and controls
            associated with the radioactive or toxic waste systems.

        j.  Operation of such water pretreatment equipment as clarifiers or
            charcoal filters (if such equipment is operated or monitored by
            operations personnel).

        k.  Knowledge of operating limits and characteristics of off-normal
            and unique processes.

        l.  Knowledge of appropriate response and recovery from off-normal
            or hazardous conditions.

        The operations supervisor should ensure that these and other topics
        are appropriately addressed in training programs.

    3.  Operator Response to Process Problems

        Each operator should be capable of correctly interpreting the
        chemistry or process parameters that he is responsible for and be
        able to provide appropriate, timely, corrective action when
        required.  High air inleakage and poor quality makeup water are
        examples of conditions that could require operator identification
        and response.

    4.  Communication Between Operations and Process Personnel

        If possible, operators should inform appropriate process personnel
        prior to commencing evolutions that could potentially affect
        facility processes or require action from support technicians.
        Operators should receive reports from the process department on key
        day-to-day process results and problems.  When process-related
        problems occur, operations and process-personnel should work closely
        to provide prompt corrective action.


                          CHAPTER XIV

                       REQUIRED READING


A.  INTRODUCTION

    Proper use of a required reading file by operations personnel should
    ensure that appropriate individuals are made aware of important
    information that is related to job assignments.  This chapter describes
    an effective required-reading program.

B.  DISCUSSION

    It is usually not necessary for a document to be read by all personnel;
    however, it is essential that a method be provided to ensure that each
    individual receives the information important to his/her position.  The
    method should designate which documents should be read by whom and by
    when.  Personnel should be required to understand assigned material.
    When reading material is not understood, appropriate questions should be
    directed to supervisors.

C.  GUIDELINES

    1.  File Index

        A list of the types of documents to be included in the required
        reading file should be maintained.  The list should include the
        following documents:

        a.  Procedure changes;

        b.  Equipment design changes;

        c.  Related industry and in-house operating experience information;
            and

        d.  Other information necessary to keep operations department
            personnel aware of current facility activities.

        Reading material should be screened to ensure that only appropriate
        material is placed in the file.

    2.  Reading Assignments

        A method should be in place to designate which documents need to be
        read by the individuals filling each position, and the reading file
        should be readily available to those individuals.

    3.  Required Dates for Completion of Reading

        A required completion date should be designated for reading each
        document.  This date would be determined based on the nature of the
        material.  Personnel should complete their reading assignments by
        the required date.  Certain documents may be designated for
        "immediate reading."  These should be read before assuming
        responsibility for a shift position.

    4.  Documentation

        Completion of reading should be documented, and the documentation
        should be retained.

    5.  Review

        The reading file should be periodically reviewed to ensure that all
        department personnel complete readings by the required dates.
        Material that has been read by all appropriate personnel should be
        removed from the active file.  A "dead" file may be maintained as a
        reference.


                           CHAPTER XV

                   TIMELY ORDERS TO OPERATORS


A.  INTRODUCTION

    A means for operations management to communicate short-term information
    and administrative instructions to operations personnel should exist.
    Other means of disseminating guidance to operators are addressed in
    Chapter XVI, Operations Procedures, and Chapter XVII, Operator Aid
    Postings.  This chapter describes the key features of an effective
    operator orders program.

B.  DISCUSSION

    The changing needs and requirements of DOE facility operations
    necessitate that a program be implemented to disseminate information to
    operations personnel in a timely manner.  To ensure that this
    information remains current, periodic reviews to remove outdated
    information should be included in the program.

C.  GUIDELINES

    1.  Content and Format

        Information such as special operations, administrative directions,
        special data-collection requirements, plotting process parameters,
        and other similar short-term matters can be included in operator
        orders.  Examples of orders could include instructions on the need
        for and performance of specific evolutions or tests; it could also
        include work priorities, announcements of policy information, and
        administrative information.  Orders should be clearly written,
        dated, and maintained in the control room.  Information and policies
        intended as permanent should be incorporated into appropriate
        administrative procedures.  The operator orders program should not
        be used to change operating procedures, because the changes noted in
        the operator orders might be missed by a procedure user.
        Additionally, operator orders may not receive the approval
        appropriate for a procedural change. Therefore, information intended
        to supplement operating procedures should be promptly incorporated
        into the appropriate procedure by a procedure change or revision
        (see Chapter XVI).

    2.  Issuing, Segregating, and Reviewing Orders

        Operator orders should be issued by the operations supervisor or
        his/her designee whenever necessary to communicate instructions to
        the shift personnel.  Operator orders should be segregated into
        daily and long-term orders in order to facilitate review by shift
        personnel.  Daily orders that are postponed or prolonged should have
        daily review or updates.  Reviews of long-term orders may not be
        required on a daily basis but should be made periodically and when
        changes occur.  Appropriate operations personnel should review the
        orders early in the shift and document their review by initialing
        the log or notebook.

    3.  Removal of Orders

        Orders that are no longer applicable or are outdated should be
        promptly removed or cancelled.  The operations supervisor should
        periodically review the operator orders to ensure that only
        applicable and current orders remain effective.


                           CHAPTER XVI

                      OPERATIONS PROCEDURES


A.  INTRODUCTION

    Operations procedures are written to provide specific direction for
    operating systems and equipment during normal and postulated abnormal
    and emergency conditions.

    Operations procedures should provide appropriate direction to ensure
    that the facility is operated within its design bases and should be
    effectively used to support safe operation of the facility.  Other
    methods of disseminating operational information are addressed in
    Chapter XI, Operator Orders, and Chapter XVII, Operator Aid Postings.
    This chapter describes the important aspects of operations procedure
    development and use.

B.  DISCUSSION

    Procedures are a key factor affecting operator performance. Appropriate
    attention should be given to writing, reviewing, and monitoring
    operations procedures to ensure the content is technically correct and
    the wording and format are clear and concise in accordance with
    NUREG-0899.  Although a complete description of a system or process is
    not needed, operations procedures should be sufficiently detailed to
    perform the required functions without direct supervision.  Consistency
    in procedure format, content, and wording is essential to achieve a
    uniformly high standard of operator performance.  Operators should not
    be expected to compensate for shortcomings in such procedures as poor
    format or confusing, inaccurate, or incomplete information.  Instead,
    procedures should be written in such a way that they can be easily used
    without making mistakes.

    During the course of operations, technical and operational requirements
    change and better ways of doing things develop.  To ensure that
    procedures in use provide the best possible instructions for the
    activity involved, periodic review and feedback of information are
    essential.

    The facility policy on use of procedures should be clearly understood by
    all operators.  Properly controlled and readily available procedures
    promote use and ensure that operational activities will be conducted in
    the manner intended.

C.  GUIDELINES

    1.  Procedure Development

        To ensure consistency among operations procedures, the methods for
        developing new procedures, including procedure formats, should be
        clearly defined.  Administrative procedures and/or writers' guides
        should direct the development and review process for procedures.

        Procedures should be developed for all anticipated operations,
        evolutions, tests, and abnormal or emergency situations.
        Annunciator/alarm response procedures that guide the operator in
        verifying abnormal conditions or changes in plant status and provide
        the appropriate corrective action should be developed for all alarm
        panels.  All procedures should provide administrative and technical
        direction to conduct the intent of the procedure effectively.  The
        extent of detail in a procedure should depend on the complexity of
        the task, the experience and training of the user(s), the frequency
        of performance, and the significance of the consequences of error.

        Procedure preparation, verification, and validation should receive
        high-level attention.  Qualifications for procedure writers should
        be considered, including operating organization and experience.
        Review, verification, and validation should be formalized for
        written and software procedures.

    2.  Procedure Content

        To provide uniformity in operations procedures, the content of
        procedures should conform to prescribed guidelines.  The procedure
        aspects described below should be followed when developing
        operations procedures:

        a.  The scope and applicability of individual procedures should be
            readily apparent.  Procedures with single-unit applicability
            should be distinctively identified to avoid confusion with
            sister-unit procedures.  In addition, to enhance rapid
            retrieval, emergency procedures should be distinguishable from
            other procedures.  Color coding could be used for these
            purposes.

        b.  Procedures should incorporate appropriate information from
            applicable source documents, such as the facility design
            documents, safety analysis documents, and vendor technical
            manuals.

        c.  Prerequisites and initial conditions should be detailed.
            Careful consideration should be given to the location of this
            information within the procedure in order to help ensure that
            the intent of the procedure is understood.  In addition, any
            hoses, tools, or other temporary testing equipment should be
            verified operable, calibrated, or inspected and in good
            condition where possible, before implementing any test
            procedure, to ensure that they function as expected during the
            test.  These verifications should be identified in the
            prerequisite section, with completion sign-offs required.
            "Hold" points (requiring independent verification and/or
            approval) should be clearly delineated.

        d.  Definitions used in the procedure should be explained.

        e.  Procedures should be easily understood, and actions should be
            clearly stated.

        f.  Procedures should contain only one action per step.

        g.  Procedures should contain sufficient but not excessive detail.
            The skill level, experience, and training of the users should be
            considered.

        h.  Warnings, notes, and cautions should be easily identifiable and
            should not contain action statements.  The probability of
            missing an action step increases when it is included in a
            warning, note, or caution.

        i.  Warnings and cautions should precede the step to which they
            apply.  Warnings, notes, and cautions should appear on the same
            page as the step to which they apply.  This ensures that
            operators are alerted to necessary information before performing
            a procedural step.

        j.  Procedures should be technically and administratively accurate
            (i.e., the instructions and information should be correct;
            referenced documents should be correctly identified; and
            necessary instructions should be present to guide the user when
            transferring between procedures).

        k.  Individual sign-offs should be provided for selected critical
            steps.  One sign-off should not be applied to more than one
            action.

        l.  Limits and/or tolerances for operating parameters should be
            specified and should be consistent with the readable accuracy of
            instrumentation.  Operators should not be required to perform
            mental arithmetic to determine if a specified parameter is
            acceptable.

        m.  Acceptance criteria for surveillance or test procedures should
            be easily discerned, including tolerances and units.  If
            calculations are needed to compare data to acceptance criteria,
            the calculations should be clearly explained.
        n.  Sequence of procedural steps should conform to the normal or
            expected operational sequence.  Training on this sequence,
            reinforced with procedures that show the same sequence, will
            serve to improve operator performance by development of patterns
            of action that are more easily remembered.

        o.  Procedures should be developed with consideration for the
            human-factor aspects of their intended use.  For example,
            references to components should exactly match drawing and
            label-plate identifiers, units should be the same as those
            marked on applicable instrumentation, and charts and graphs
            should be easily read and interpreted.  Important factors (such
            as operating limits, warnings, cautions, etc.) should be
            highlighted.

        p.  Emergency operating procedures should provide guidance in
            responding to single and multiple casualties.

        q.  Portions or steps of other procedures that are used or referred
            to when performing a procedure should be specifically identified
            within the procedure so that operators will not be confused when
            transferring between procedures.

        r.  Component or system shutdown and restoration requirements
            following shutdown or a surveillance or test activity should be
            specific and controlled by the procedure.

    3.  Procedure Changes and Revisions

        Procedure changes and revisions are necessary to ensure that
        procedures reflect current operating practices and requirements.
        The review and approval process for each procedure change or
        revision should be documented.  For the purpose of these guidelines,
        a "procedure change" refers to an on-the-spot change (whether for
        permanent or for one-time-only use).  Procedure changes do not
        involve retyping or reissuing a procedure.  "Procedure revisions"
        constitute a new, retyped edition of the procedure.  Procedure
        changes and revisions should conform to the following practices:

        a.  Procedure changes intended for use more than one time should be
            documented in a location readily available for operator
            reference.  To avoid the possibility of error, these changes
            should also be referenced in procedure copies used by operators.

        b.  Appropriate procedure changes and revisions should be initiated
            when procedure inadequacies or errors are noted.

        c.  Procedure revisions should be initiated when a change has been
            outstanding for an extended period (e.g., greater than 6 months)
            or when a procedure has been affected by several changes (e.g.,
            more than five).  All currently effective procedure changes
            should normally be incorporated when the procedure is revised.

        d.  Procedure revisions should be implemented concurrently with
            modifications.  Procedure updates required by temporary
            modifications should be handled as procedure "change" and
            implemented concurrently with the temporary modification
            installation.

        e.  Important information regarding changed or revised procedures
            should be communicated to appropriate operations personnel via
            the required reading system (Chapter XIV), a pre-shift briefing,
            or a similar method.

        f.  Documentation of the reason for key procedure steps should be
            maintained and reviewed when implementing changes or revisions
            that alter these steps.  This practice is important to ensure
            that the reason for any step is not overlooked.

        g.  The review process should involve verification and validation of
            the procedure using walkthroughs or similar methods.

    4.  Procedure Approval

        Operating procedures should be approved by the operations
        supervisor.  In addition, procedures that affect safety-related
        equipment and emergency procedures should be reviewed by the
        facility safety review committee or by another appropriate review
        mechanism.  Procedure revisions should receive the same depth of
        review and level of approval as the initial versions.  New and
        revised procedures should be approved prior to use.

        Changes in Operations procedure that do not affect the intent of
        operations procedure should be approved by two individuals; one
        should be a qualified operator, and the other should be a member of
        facility management.  For this purpose, management could be
        interpreted to mean the operations supervisor or a more senior
        individual within the operating organization.  Within 2 weeks, these
        procedure changes should be concurred with by the individuals who
        would normally approve a revision or the Initial version of the
        procedure.  Changes that alter the intent of a procedure should
        receive the same approval as a new or revised procedure.

    5.  Procedure Review

        New and revised operations procedures should be reviewed prior to
        issuance and at periodic intervals to ensure that the information
        and instructions are technically accurate and that appropriate
        human-factor considerations have been included.  The frequency of
        subsequent reviews should be specified; it may vary with the type
        and complexity of the activity involved and with time as a given
        plant reaches operational maturity.  Applicable procedures should be
        reviewed after an unusual incident (such as an accident, an
        unexpected transient, significant operator error, or equipment
        malfunction).  During reviews, procedures should be compared to
        source documents to verify their accuracy.  In addition, new
        procedures should be validated by walk-throughs in the facility or
        by operation on a facility-specific simulator to ensure workability.

    6.  Procedure Availability

        A controlled copy of all operations procedures should be maintained
        in the control area for operator reference, and selected controlled
        procedures should be maintained at other appropriate locations.  For
        example, controlled procedures for facility shutdown from outside
        the control area should be maintained at the remote shutdown
        location(s).  It may be desirable to have procedures for routine
        evolutions available at local work stations.

        Working copies of controlled procedures should be available for use
        during evolutions.  However, since these documents have only a
        limited lifespan, working copies should be controlled and a system
        should be in place to ensure that outdated procedures are not used
        by mistake and that working copies are replaced according to
        approved procedures.  For example, uncontrolled working copies could
        be verified by comparison to a controlled copy prior to use.

        Controlled annunciator response procedure information should be
        easily accessible to the operators responsible for responding to
        alarms.  Some facilities can provide annunciator response procedures
        at local control panels.  If this is not done, annunciator response
        procedures should be provided at an alternate location convenient to
        the equipment operator.

    7.  Procedure Use

        Facility operation should be conducted in accordance with applicable
        procedures that reflect the facility design basis.  The requirements
        for use of procedures should be clearly defined and understood by
        all operators.  If procedures are deficient, a procedure change
        should be initiated.  In exception to this policy, operators may
        take whatever action is necessary during emergency conditions to
        place the facility in a safe condition, and to protect equipment,
        personnel, and public safety without first initiating a procedure
        change.

        Operators should have procedures with them and follow them in a
        step-by-step manner when the procedures contain sign-offs for the
        various activities.  In addition, procedures should be referenced
        during infrequent or unusual evolutions when the operator is not
        intimately familiar with the procedure requirements or when errors
        could cause significant adverse impact to the facility.  Operators
        need not reference emergency procedures during the performance of
        immediate actions since these actions, are committed to memory;
        however, the emergency procedure immediate action instructions
        should be reviewed after the actions are performed, thus, verifying,
        that all required actions have been taken.


                          CHAPTER XVII

                      OPERATOR AID POSTINGS


A.  INTRODUCTION

    Facility operator aids (information posted for personnel use) should
    provide information useful to operators in performing their duties.  An
    operator aid program should be established to ensure that operator aids
    that are posted are current, correct, and useful.  This chapter
    describes the important aspects of an operator aid program.

B.  DISCUSSION

    Operator aids provide an important function in the safe operation of the
    facility.  Operator aids may come in many forms:  copies of procedures
    (portion or pages thereof), system drawings, handwritten notes,
    information tags, curves, and graphs.  It is important to make sure that
    these types of postings reflect the most current information available
    and that they do not supersede or conflict with any other controlled
    procedure or information.

C.  GUIDELINES

    1.  Operator Aid Development

        Any facility employee could develop an operator aid; however, it
        should be approved prior to posting.  Operator aids (system
        drawings, maintenance procedures, etc.) may often be posted by
        individuals other than operations personnel; therefore, all facility
        personnel should be informed of the importance of controlling posted
        information and the procedure to be followed when posting
        information.

    2.  Approval

        The operations supervisor, or a higher authority, should approve all
        operator aids.  The person approving an operator aid should ensure
        that the aid is necessary and correct.  Operator aids that alter
        procedures should not be approved.  Instead, appropriate procedures
        should be changed to incorporate the necessary information.

    3.  Posting

        Operator aids should not be posted in such a way as to obscure
        instruments or controls.  The aids should be located in close
        proximity to the area of their expected use.  The operator aids
        should, when possible, be protected (laminated) and should be
        securely fastened to the equipment to which they refer.

    4.  Use of Operator Aids

        Operator aids should be viewed as a convenience to the individual
        using them, not a requirement.  In most cases, operator aids remind
        users of information that might otherwise be overlooked and provide
        guidance that is not procedural in nature.  Operator aids may
        supplement approved procedures, but they should not be used in lieu
        of approved procedures.

    5.  Documentation

        A listing of all approved operator aids should be maintained along
        with a copy of each aid posted in the facility.  This list should be
        used during periodic reviews of operator aids in order to help
        ensure that the posted aids remain current, and to provide a
        reference copy should an operator aid be missing during the review.
        The list should be kept in the control area, the operations
        supervisor's office, or other appropriate location.  References from
        which operator aids were derived, control numbers (including
        revision), and dates of approval should be provided.

    6.  Review

        The posted operator aids should be reviewed periodically to ensure
        they are still correct and necessary.  In addition, an operator
        should audit the control area listing to ensure that only currently
        posted aids are recorded on the listing.  Operator aids no longer
        posted should be removed from the listing, and missing aids should
        be replaced.

        Some operator aids are graphs, curves, or other portions of approved
        procedures.  To help ensure that these types of operator aids are
        the most current versions, they should be updated when the "parent"
        procedure is revised.  One way to accomplish this is to notify
        appropriate document control personnel of those operator aids that
        are derived from procedures.  When a revision is made to one of
        these procedures, document control would notify the control room to
        check the affected operator aid and see if changes are necessary.

        During routine facility inspections, operations personnel should
        review operator aids to ensure that they are approved.  Unapproved
        postings should be submitted for approval or removed.  It is
        important for all personnel to understand that the use of an
        out-of-date operator aid could be just as detrimental as the use of
        an out-of-date procedure.


                          CHAPTER XVIII

                  EQUIPMENT AND PIPING LABELING


A.  INTRODUCTION

    A well-established and maintained equipment labeling program should help
    ensure that facility personnel are able to positively identify equipment
    they operate.  In addition, equipment labeling is required by
    Operational Safety and Health Administration (OSHA) regulations.  This
    chapter describes the important aspects of a labeling program.

B.  DISCUSSION

    A good labeling program, understood and maintained by operating and
    maintenance personnel, will enhance training effectiveness and will help
    reduce operator and maintenance errors resulting from incorrect
    identification of equipment.  Personnel radiation exposure or exposure
    to hazardous materials will also be reduced if operators spend less time
    identifying components.

    The labeling program should continue throughout the life of the
    facility.  Because equipment labels will be continually misplaced or
    damaged, an ongoing labeling program should exist to allow personnel to
    identify components needing labels, to identify a person or persons
    responsible for making new labels, and to ensure that new labels are
    correct and placed on the proper equipment.  In addition to equipment,
    doors to rooms should be labeled so that personnel can identify the room
    and, if applicable, the equipment inside.

C.  GUIDELINES

    1.  Components Requiring Labeling

        The following components should be labeled:

        a.  Valves;

        b.  Major equipment (e.g., tanks, pumps, and compressors);

        c.  Switches;

        d.  Circuit breakers (4.16KV, 480V, 120VAC/DC, etc.);

        e.  Fuse blocks or fuse locations;

        f.  Instruments and gauges;

        g.  Busses and motor control centers;

        h.  Cabinets (including internal components such as relays,
            terminals, etc.);

        i.  Room doors;

        j.  Emergency equipment (such as fire alarm stations, sound powered
            phone headsets, etc.); and

        k.  Fire protection systems.

    2.  Label Information

        Information on labels should be consistent with the information
        found in facility procedures, valve lineup sheets, and piping and
        instrument diagrams.  Abbreviations and nomenclature used should be
        standardized and should be understood by facility personnel.  Labels
        should be permanent, securely attached, and have distinguishable,
        easy-to-read information.  Each component label should list a unique
        component number.  The accompanying component noun name or
        description and power supply, if applicable, should also be
        provided.  Labels may be color coded for unit, system, and/or train
        designation.  If color coding is used, the colors should be applied
        consistently and have only one meaning per color or combination.

        Piping should be labeled to indicate the fluid contained and the
        normal flow direction.  OSHA color coding for pipes could be used,
        and pipes containing potentially radioactive fluids, toxic fluids,
        or explosive gases should be uniquely marked.

        Labels should be made from materials that are compatible with their
        particular application.  For example, chloride-free labels should be
        used on stainless steel piping, and temperature-tolerant labels
        should be used on hot components.  Adhesives used for label
        attachment should also be verified for compatibility.

    3.  Label Placement

        Labels should be placed on or as near as practicable to the
        equipment to be labeled.  The label should be oriented in a manner
        that is easy to read and so that the correct component is easy to
        identify.

        For example, labels for switches, indications, and breakers on
        control or power panels should be placed closer to the identified
        component than any other component so that the label clearly
        identifies the correct component.  Label placement should not
        interfere with equipment operation or obscure indicators.

    4.  Replacing Labels

        a.  Identifying Lost or Damaged Labels

            Procedures should be established to ensure that misplaced or
            damaged labels are replaced.  Since labels are often missing
            after maintenance, the post-maintenance test could require a
            check to ensure that the appropriate labels are attached.
            Another method that could be used to check for labels is to add
            another column to valve lineup sheets that would require the
            operator to verify that labels are present, readable, and
            undamaged. Operators should also look for missing or damaged
            labels during their normal tours and during other routine
            activities.  They should become especially observant for
            situations where a black marking pen has been used for labeling
            (and then sometimes crossed out and re-labeled) and should
            replace these informal labels with the proper labels.

        b.  Providing New Labels

            A method should exist to help ensure the prompt identification
            and correction of labeling deficiencies.  A number of ways can
            be suggested to accomplish this:  operators could make labels on
            their own, or operators could fill out forms and forward them to
            a central facility to have labels made.  In either case, a
            temporary label should be attached to the component until the
            replacement label can be made.  The replacement label should be
            approved by the operations supervisor (or higher authority).  In
            most cases the presence of labeling machines on-site promotes
            relabeling.

            The attachment of temporary and/or replacement labels to correct
            components should be verified.  The new label should meet the
            guidelines for label information as addressed in paragraph C2 of
            this chapter.
            
DOE 5480.19 Chg 2			Attachment II
10-23-01				Page II-1 (and II-2)



	CONTRACTOR REQUIREMENTS DOCUMENT

	DOE 5480.19, CONDUCT OF OPERATIONS REQUIREMENTS
	FOR DOE FACILITIES


Pending revision of this Order to the new Directives System format, this whole Order applies to contractors and should be attached to the contract.

U.S. Department of Energy			PAGE CHANGE
Washington, D.C.				DOE 5480.19 Chg 2

						10-23-01      

SUBJECT:  CONDUCT OF OPERATIONS REQUIREMENTS FOR DOE FACILITIES


1.	PURPOSE. To transmit revised pages to DOE 5480.19, CONDUCT OF OPERATIONS REQUIREMENTS FOR DOE FACILITIES, dated 7-9-90.
	 
	
2.	EXPLANATION OF CHANGE. To update EH responsibilities in DOE 5480.19, and facilitate the Department’s organizational transition necessitated by establishment of the NNSA.

	
3.	FILING INSTRUCTIONS.   

Remove			Dated	   Insert			Dated
Pages 1 thru 4		5-18-92	   Pages 1 thru 4		10-23-01
Attach I, Page I-12	7-9-90	   Attach I, Page I-12		10-23-01
Attach II, Pages II-1 (and II-2)				10-23-01
	
After filing the attached pages, this transmittal may be discarded.

BY ORDER OF THE SECRETARY OF ENERGY:



   FRANCIS S. BLAKE
   Deputy Secretary