Click Here to Display Options
Click Here to Close Options
USACE / NAVFAC / AFCESA / NASA UFGS-33 05 23.19 (April 2006)
------------------------------
Preparing Activity:
NAVFAC Replacing without change
UFGS-02441 (August 2004)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated 1 April 2006
Section Table of Contents
SECTION 33 05 23.19
TRENCHLESS EXCAVATION USING MICROTUNNELING
04/06
PART 1 GENERAL
1.1 REFERENCES
1.2 RELATED REQUIREMENTS
1.3 DESIGN REQUIREMENTS
1.3.1 Pipe Casing
1.4 SUBMITTALS
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Handling
1.6 QUALITY ASSURANCE
1.6.1 Design Calculations of Pipe Casing
PART 2 PRODUCTS
2.1 PIPING CASING MATERIALS
2.1.1 Piping Casing
2.1.1.1 Ductile-Iron Piping
2.1.1.2 Polyvinyl Chloride Pipe (PVC)
2.1.1.3 Reinforced Concrete Pipe
2.1.1.4 Steel Pipe
2.1.1.5 Fiberglass Pipe
2.1.1.6 Vitrified Clay Pipe
2.2 CONCRETE
2.3 BENTONITE
2.4 BACKFILL
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Access Shafts
3.2 INSTALLATION
3.2.1 Installation of Tracer Wire
3.2.2 Connections to Existing Lines
3.2.3 Settlement, Alignment and Tolerances
3.2.4 Microtunneling
3.2.5 Ventilation
3.2.6 Lighting
3.2.7 Spoil Transportation
3.2.8 Pipe Jacking Equipment
3.2.9 Jacking Pipe
3.3 FIELD QUALITY CONTROL
3.3.1 Field Tests and Inspections
3.3.2 Testing Requirements
SECTION 33 05 23.19
TRENCHLESS EXCAVATION USING MICROTUNNELING
NOTE: This guide specification covers the requirements for
work related to
the installation of utility systems (i.e., electrical power, communications,
water, gas, oil, petroleum products, steam, sewage, drainage, irrigation, and
similar facilities) utilizing the microtunneling trenchless excavation methods.
Comments and suggestions on this guide specification are welcome and should
be directed to the technical proponent of the specification. A listing of
technical
proponents, including their organization designation and telephone number, is
on the Internet.
Recommended changes to a UFGS should be submitted as a
Criteria Change Request
(CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer choices or locations where
text must be supplied by the designer.
NOTE: Microtunneling Horizontal Earth Boring is a process characterized as
highly sophisticated, laser guided, remote controlled system providing the capability
of continuous accurate monitoring and control of alignment and grade.
1. Microtunneling is ideally suited for placing a 450 to 1800 mm 18 to 72 inch
casing pipe for containing utility lines. Distances between manholes can exceed
300 m 1000 linear feet. It is ideally suited for utility lines that must be
buried in rock, sand, clay and contaminated soils in depths ranging from 1.8
to 30 m 6 to 100 feet below grade. Varied soil conditions can be dealt with
a single cutting head and dewatering is greatly reduced. There are many manufacturers
of equipment that can perform the work described in this specification.
2. Permanent pipe casing can be used as the carrier pipe or a separate pipe
may be placed inside the casing. The designer has the option of selecting the
casing pipe however it may limit the number of possible bidders.
3. Cathodic protection for steel pipes should be considered where the anticipated
degree of corrosion is so great that coating systems, including polyethylene
encasement, are not adequate to protect the piping for the desired life of the
system.
NOTE: Project Drawings:
1. The following information should be shown on the project drawings:
a. Plan and location of all new pipelines, including size of pipe casing and
carrier pipe.
b. Location and profiles of soil sampling and bore holes.
c. Location, size, and type of service of existing connecting, intersecting,
and adjacent pipelines and other utilities.
d. Paved areas and railroads which pass over new pipelines.
e. Profile, where necessary to show unusual conditions.
f. Manhole and lateral piping bedding conditions.
g. Details for the connection of the pipe casing to manholes and infiltration
control.
h. Location of surrounding structures and sensitivity to settlement, pile foundations,
and subsurface structures that could be affected by the project.
i. Show traffic plans for work near roadways and possible equipment and spoils
storage areas. Spoil storage and removal requires a large area for dewatering
and must be strictly controlled in Section 01 57 19.00 20, TEMPORARY ENVIRONMENTAL
CONTROLS. Refer the other sections for specific removal and disposal of hazardous
materials. Spoil storage locations and construction need to consider possible
runoff into wetlands, streams, or storm drains.
j. Maximum working pressure of the system.
k. Class or thickness of pipe, including material identification, and limits
for same where class or thickness will differ along length of pipeline.
PART 1 GENERAL
1.1 REFERENCES
NOTE: This paragraph is used to list the publications cited in the text of
the guide specification. The publications are referred to in the text by basic
designation only and listed in this paragraph by organization, designation,
date, and title.
Use the Reference Wizard's Check Reference feature when you add a RID outside
of the Section's Reference Article to automatically place the reference in the
Reference Article. Also use the Reference Wizard's Check Reference feature
to update the issue dates.
References not used in the text will automatically be deleted from this section
of the project specification when you choose to reconcile references in the
publish print process.
The publications listed below form a part of this specification to the extent referenced. The publications are
referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API) |
|
API Spec 13A | | (1993; A 1999) Drilling-Fluid Materials |
|
API Spec 5L | | (2004) Line Pipe |
AMERICAN WATER WORKS ASSOCIATION(AWWA) |
|
AWWA C104 | | (1995) Cement-Mortar Lining for Ductile-Iron
Pipe and Fittings for Water |
|
AWWA C111 | | (2000) Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings |
|
AWWA C150 | | (2002) Thickness Design of Ductile-Iron Pipe |
|
AWWA C151 | | (2002) Ductile-Iron Pipe, Centrifugally Cast,
for Water |
|
AWWA C200 | | (1997) Steel Water Pipe - 6 In. (150 mm) and
Larger |
|
AWWA C203 | | (2002; A C203a-99) Coal-Tar Protective Coatings
and Linings for Steel Water Pipelines - Enamel
and Tape - Hot-Applied |
AMERICAN WELDING SOCIETY (AWS) |
|
AWS D1.1/D1.1M | | (2006) Structural Welding Code - Steel |
|
AWS D1.5 | | (2002) Bridge Welding Code |
ASTM INTERNATIONAL (ASTM) |
|
ASTM A 139 | | (2000) Electric-Fusion (Arc)-Welded Steel Pipe
(NPS 4 and Over) |
|
ASTM A 53 | | (2004) Pipe, Steel, Black and Hot-Dipped, Zinc-Coated,
Welded and Seamless |
|
ASTM A 716 | | (2003) Ductile Iron Culvert Pipe |
|
ASTM A 746 | | (2003) Ductile Iron Gravity Sewer Pipe |
|
ASTM C 1208/C 1208M | | (2004) Vitrified Clay Pipe and Joints for Use
in Microtunneling, Sliplining, Pipe Bursting
and Tunnels |
|
ASTM C 1208M | | (1995) Vitrified Clay Pipe and Joints for Use
in Jacking, Sliplining, and Tunnels (Metric) |
|
ASTM C 301 | | (2004) Vitrified Clay Pipe |
|
ASTM C 443 | | (2005) Joints for Concrete Pipe and Manholes,
Using Rubber Gaskets |
|
ASTM C 443M | | (2005) Joints for Concrete Pipe and Manholes,
Using Rubber Gaskets (Metric) |
|
ASTM C 497 | | (2004) Concrete Pipe, Manhole Sections, or Tile |
|
ASTM C 497M | | (2004) Concrete Pipe, Manhole Sections, or Tile
(Metric) |
|
ASTM C 700 | | (2002) Vitrified Clay Pipe, Extra Strength,
Standard Strength, and Perforated |
|
ASTM C 76 | | (2005a) Reinforced Concrete Culvert, Storm Drain,
and Sewer Pipe |
|
ASTM C 76M | | (2005a) Reinforced Concrete Culvert, Storm Drain,
and Sewer Pipe (Metric) |
|
ASTM D 1248 | | (2005) Polyethylene Plastics Extrusion Materials
for Wire and Cable |
|
ASTM D 3212 | | (1996a; R 2003) Joints for Drain and Sewer Plastic
Pipes Using Flexible Elastomeric Seals |
|
ASTM D 3262 | | (2004) "Fiberglass" (Glass-Fiber-Reinforced
Thermosetting-Resin) Sewer Pipe |
|
ASTM D 4161 | | (2001) "Fiberglass" (Glass-Fiber-Reinforced
Thermosetting-Resin) Pipe Joints Using Flexible
Elastomeric Seals |
|
ASTM F 477 | | (2002e1) Elastomeric Seals (Gaskets) for Joining
Plastic Pipe |
|
ASTM F 794 | | (2003) Poly(Vinyl Chloride) (PVC) Profile Gravity
Sewer Pipe and Fittings Based on Controlled
Inside Diameter |
[1.2 RELATED REQUIREMENTS
]1.3 DESIGN REQUIREMENTS
1.3.1 Pipe Casing
NOTE: Design Requirements:
1. External loads shall include earth loads, truck loads, seismic loads, construction
loads (i.e., sheetpile insertion/extraction at manholes and pipe ramming/jacking
forces) and impact in the design stage of the project; also hydrostatic and
buoyancy forces.
2. It is recommended that the following site information should be provided
(at a minimum):
a. Grain size analysis of soil particles
b. Unconfined compressive strength of soils
c. Dry density
d. Cohesion
e. Shear strength
f. Plasticity of fill material
g. Classification of fill material
h. Rock type and color
i. Permeability
j. Moisture content
k. Water table depth
l. Nature of pollutants
m. Grain size
n. Core recovery TCR SCR
o. Fracture index
p. Standard penetration N value
q. Friction angle
r. Where possible, soil boring information should be provided at not more than
60 m 200 ft intervals outside the bore of the tunnel and at manhole locations.
3. Use equivalent pipe design for the project conditions (using the applicable
criteria for each pipe material) for each different pipe material.
NOTE: Provide only those pipe sizes and materials applicable to the project
requirements.
NOTE: Choose one of the following options.
[Provide pipe casing indicated as [_____] mm inch of [polyvinyl chloride (PVC) plastic] [clay tile] [concrete]
[steel] or [_____] pipe. Provide utility line accessories, [valves], [connections], and [manholes] as specified
and where indicated. Submit design calculations of pipe casing.]
NOTE: Where the casing will not serve as the actual carrier or utility line,
specify the appropriate carrier pipe, joints and connections in other specification
Sections 33 11 00 WATER DISTRIBUTION, and 02630, "Storm Drainage."
1.4 SUBMITTALS
NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL
PROCEDURES and edit the following list to reflect only the submittals required
for the project. Submittals should be kept to the minimum required for adequate
quality control.
A “G” following a submittal item indicates that the submittal requires Government
approval. Some submittals are already marked with a “G”. Only delete an existing
“G” if the submittal item is not complex and can be reviewed through the Contractor’s
Quality Control system. Only add a “G” if the submittal is sufficiently important
or complex in context of the project.
For submittals requiring Government approval on Army projects, a code of up
to three characters within the submittal tags may be used following the "G"
designation to indicate the approving authority. Codes for Army projects using
the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other organization in the District
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project
Office. Codes following the "G" typically are not used for Navy, Air Force,
and NASA projects.
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose
the second bracketed item for Army projects.
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation
are [for Contractor Quality Control approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for the Government.] The following shall
be submitted in accordance with Section
01 33 00
01 33 00
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Microtunneling Boring Machine equipment to be used
SD-03 Product Data
NOTE: Use other specifications to require submittals for the actual carrier
pipe unless the pipe casing is going to act as the carrier pipe.
Piping casing, joints, fittings, valves, and couplings
Bentonite
Submit manufacturer's standard drawings or catalog cuts, except submit both drawings and cuts
for push-on [and rubber-gasketed bell-and-spigot] joints. Include information concerning gaskets
with submittal for joints and couplings.
SD-05 Design Data
NOTE: Suggested Submittals:
1. The following material should be submitted for review by the designer:
a. Manufacturer's literature describing in detail the microtunneling system
to be used. Detailed descriptions of projects on which this system has been
successfully used, giving total pipe length, project duration, and number of
restarts.
b. Method of spoil removal.
c. Anticipated jacking loads.
d. Method(s) of controlling groundwater at shafts and by the microtunneling
boring machine.
e. Shaft dimensions, locations, surfaced construction, profile, depth, method
of excavation, shoring bracing, and thrust block design.
f. Verification that the pipe complies with the specification.
Design calculations of pipe casing
SD-07 Certificates
Piping casing piping, fittings, joints, valves, and coupling
Shop-applied linings
Certificates shall attest that tests set forth in each applicable referenced publication have
been performed, whether specified in that publication to be mandatory or otherwise and that
production control tests have been performed at the intervals or frequency specified in the
publication. Other tests shall have been performed within 3 years of the date of submittal
or certificates on the same type, class, grade, and size of material as is being provided for
the project.
SD-08 Manufacturer's Instructions
Installation procedures for pipe casing
1.5 DELIVERY, STORAGE, AND HANDLING
Inspect materials delivered to site for damage. Unload and store with minimum handling. Store materials on
site in enclosures or under protective covering. Store [plastic piping, jointing materials and] rubber gaskets
under cover out of direct sunlight. Do not store materials directly on the ground. Keep inside of pipes, fittings,
[and] [valves] free of dirt and debris.
1.5.1 Handling
NOTE: Delete coatings not allowed for the project. AWWA M11 in the chapter
on protective coatings contains information on the relative merits of cement
mortar and coal-tar enamel coatings. See Forward to AWWA C210 for information
on coal-tar epoxy coating.
Handle pipe, fittings, valves, hydrants, and other accessories in a manner to ensure delivery to the excavation
in sound undamaged condition. Take special care to avoid injury to coatings and linings on pipe and fittings;
make satisfactory repairs if coatings or linings are damaged. Carry, do not drag pipe to the excavation. [Store
plastic piping, jointing materials and] [rubber gaskets that are not to be installed immediately, under cover
out of direct sunlight.] [Handle steel pipe with [coal-tar enamel] [coal-tar epoxy] coating in accordance with
the provisions for handling coal-tar enamel coated pipe in AWWA C203.]
1.6 QUALITY ASSURANCE
1.6.1 Design Calculations of Pipe Casing
Submit design calculations of pipe casing demonstrating that the pipe casing selected has been designed to support
the maximum anticipated earth loads and superimposed live loads, both static and dynamic, which may be imposed
on the pipe casing.
PART 2 PRODUCTS
2.1 PIPING CASING MATERIALS
NOTE: Allowable Materials:
1. The project specification should allow all carrier piping materials for
the utility lines which are suitable for the project, each to be permitted as
a Contractor's option. The structural support contribution of the casing piping
and annulus grout may be considered when specifying the thickness of the utility
piping. The casing may also greatly reduce infiltration of ground water.
2. Pipe materials which are known to be unsuitable for particular local conditions,
(i.e., corrosion, deterioration, etc.) should not be permitted for the project
for either the casing or the utility piping. However, consider use of more
effective protective coatings, etc., where economically feasible. Consider
the protective nature of the pipe casing and annulus grout with regards to exterior
attack. [Cathodic protection of the casing may also be desirable.]
3. Utility piping material and size should be specified in their own appropriate
sections of the specification.
4. Several methods of installing pipe casings are available to the Contractor.
Different tunneling machines have different means of installing the casing.
Many of the machines allow the pipe casing to be used as the jacking shield
and are left in place after the tunneling head has reached the receiving pit.
Other machines use a temporary jacking shield that is replaced with a lighter
casing. The final casing material doesn't need to be as strong because it doesn't
need to jack the cutting head. Fiberglass casing can be an appropriate alternative
for these methods. The Contractor should have the option of selecting an appropriate
alternative for the casing based on his tunneling method and the design requirements
of the utility lines.
5. The annulus grout (e.g., the grout the fills the void between the casing
and the utility line(s) is traditionally a lightweight grout that is designed
to merely stabilize the utility line(s). The utility lines are usually temporarily
supported on wooden shims to position them inside the casing prior to grouting.
2.1.1 Piping Casing
2.1.1.1 Ductile-Iron Piping
NOTE: Insert the necessary Pressure/Thickness Class to meet project conditions,
as determined from AWWA C151.
a. Pipe and Fittings: Pipe, [except flanged pipe,] AWWA C151 [Pressure Class [_____]] [Thickness
Class [_____]]. The outside diameter of ductile iron microtunneling pipe shall be in accordance
with AWWA C150.
(1) Deflection: The maximum allowable deflection shall not exceed three percent of the outside
diameter of the pipe barrel for pipe manufactured with a rigid lining and/or rigid coating nor
five percent for pipe manufactured with a flexible lining and/or flexible coating.
(2) Linings: [Cement mortar shall be in accordance with latest version of AWWA C104] [Polyethylene
lining shall be virgin polyethylene complying with ASTM D 1248 compounded with an inert filler
and with sufficient carbon black to resist ultraviolet rays.]
(3) End Squareness: The ends of the pipe shall be perpendicular to the longitudinal axis of
the pipe with a maximum deviation of not more than 6 mm 0.25 inches.
(4) Hydrostatic Test: Each pipe section shall be subject to a hydrostatic test of not less
then 3447 kPa 500 psi as per the requirements of AWWA C151. Non-standard joint lengths shall
be cut only from full length pipe having satisfactorily passed the required 3447 kPa 500 psi
hydrostatic test.
(5) Material Properties: The following are representative minimum values for the physical
properties of ductile iron for use as microtunneling pipe for pressure or gravity service.
(a) Tensile strength: Minimum 420 MPa 60,000 psi
(b) Tensile yield strength: Minimum 300 MPa 42,000 psi
(c) Compressive strength: The compressive yield strength of ductile iron is 10 to 20 percent
higher than the tensile yield strength. The ultimate strength in compression is not normally
determined for ductile metals, though apparent strength in tests may be several times the tensile
strength value.
(d) Elongation: Minimum 10 percent.
(e) Modulus of Elasticity: 165,500 MPa 24,000,000 psi (tension or compression).
(f) Poisson's ratio: 0.28
(6) Spigot End Outside Diameter: The Spigot end outside diameter must be within the following
ranges: [75 to 300 mm, + 1.5 mm] [350 to 600 mm, + 1.3 mm] [750 to 1200, + 2.0 mm] [1350 to
1600 mm, + 1.0 mm] [3 to 12 inches, + 0.06 inches] [14 to 24 inches, + 0.05 inches] [30 to 48
inches, + 0.08 inches] [54 to 64 inches, + 0.04 inches].
b. Joints and Jointing Material:
NOTE: Do not locate flanged, grooved, and shouldered joints on buried pipelines
unless they are in valve pits or chambers.
(1) Joints: Pressure and gravity microtunneling pipe shall have either an integral-bell push-on
or rubber gasket coupled joint meeting the following criteria:
(a) Integral-bell push-on joint microtunneling pile shall consist of a rubber-gasket joint
manufactured to conform with AWWA C111 and the dimensions shown in AWWA C151. The exterior
of the pipe shall be coated with a durable cement-mortar or concrete coating applied in such
a manner as to provide a uniform outside diameter.
(b) Cement-mortar or concrete strength, reinforcement and method of placement shall be in accordance
with manufacturer's recommendations. [Durable Coatings of other types may be substituted provided
they maintain a uniform outside diameter and they are approved by the designer.] Rubber gasket
coupled microtunneling joint shall be manufactured so as to provide a joint which has the same
nominal outside diameter as the pipe barrel.
2.1.1.2 Polyvinyl Chloride Pipe (PVC)
ASTM F 794. ASTM D 3212 for gasketed joint systems. ASTM F 477 for gasket materials.
NOTE: Polyvinyl Chloride Pipe (PVC): PVC pipe may be an ideal conveyance system
for sewage and storm water, and for the construction of culverts installed and
constructed by microtunneling methods. These pipes require microtunneling systems
that generate low compressive loads on the pipe.
2.1.1.3 Reinforced Concrete Pipe
NOTE: This section covers reinforced concrete pipe intended for use as conveyance
systems of sewage and storm water, and for the construction of culverts and
industrial casings installed and constructed by jacking methods.
a. Pipe: Pipe, [[_____] mm inch inside diameter,] class [_____], wall [_____], nominal length
[_____] and concrete strength [_____] MPa psi in accordance withASTM C 76MASTM C 76.
NOTE: Reinforced Concrete Pipe:
1. Nominal dimensions: Typical nominal dimensions for reinforced concrete
pipe are detailed in ASTM standards [ASTM C 76MASTM C 76, ASTM C 361M ASTM C
361, ASTM C 655M ASTM C 655, ASTM C 822]. Pipe meeting these requirements is
generally acceptable for jacking. The permissible variation allowed with respect
to these and other dimensions should be in accordance with the variations listed
in the section.
2. Pipe lengths: Concrete pipe manufactured for jacking operations should
be typically manufactured in lengths of 2.25 to 2.4 m 7.5 to 8 feet. This is
primarily a function of the size of the jacking equipment and the excavation.
Lengths vary in any given geographical area.
3. Joint: Historical field data has shown that concrete pipe joint for jacking
applications is commonly of two types, all concrete or concrete and steel.
Factors influencing the selection of one of these joint types, or other alternative
joints, include:
a. Magnitude of the anticipated jacking forces
b. Joint deflection characteristics
c. Joint shear strength required during the jacking operation
d. Specific site design parameters.
4. Joint description: Two primary types of joints are used:
a. Joint formed entirely of concrete that may utilize a rubber gasket or mastic
to provide the seal. Rubber gaskets should be used where water tightness is
needed. A compressive bearing strip is required between the faces of the adjoining
pipes.
b. Joint includes an assembly of steel bands or steel bell ends with spigot
rings and rubber gaskets. This type of joint also requires a compressive bearing
strip.
5. Joint selection: Historical performance has shown that in instances of
straight alignment under relatively low jacking forces, both types of joints
can be used. Curved alignments and high jacking pressures may require the use
of the second type of joint.
6. Axial load capacity: A factor of safety of at least 2.22 should be used
for pipes installed by jacking methods. The axial load capacity should be based
on the ultimate strength of the concrete and it assumes that the load is uniformly
distributed over the bearing surface. Eccentric or concentrated load combinations
on the pipe surface should be evaluated for effective surface contact area and
reduction in the factor of safety.
(1) Internal Diameter: The internal diameter of [300 to 60012 to 24 inches pipe shall not
vary by more than+6 mm+1/4 inch from the design diameter]. [686 mm27 inch and larger pipe
shall not vary from the design diameter by more than +one percent or+10 mm+3/8 inch, whichever
is less].
(2) Wall Thickness: At any location along the length of the pipe, or at any point around its
circumference, the wall thickness shall not vary by more than +five percent.
(3) End Squareness: Each pipe end shall lie within two planes perpendicular to the longitudinal
center line of the pipe, spaced at 10 mm 3/8 inches apart. The tongue or spigot end shall be
square within 5 mm 3/16 inches and the groove or bell end of the pipe shall be square within
5 mm 3/16 inches.
(4) Hydrostatic Test: Each pipe section shall be subject to a hydrostatic test of not less
than [69 kPa10 psi for straight] [90 kPa 13 psi for deflected] alignment as per the requirements
of section 10 ofASTM C 443MASTM C 443 and section 8 ofASTM C 497MASTM C 497. Non-standard
joint lengths shall be cut only from full length pipe having satisfactory passed the required
[_____] kPa psi hydrostatic test.
(5) Roundness: The outside diameter of the pipe shall not vary from a true circle by more
than 1.0 percent. The out-of-round dimensions shall be one half the difference between the
maximum and minimum outer diameter of the pipe at any one location along the barrel.
(6) Length of Pipe: Finished pipe length shall not deviate from design length by more than+3 mm per 300 mm+1/8 inch per foot with a maximum variation of+13 mm 1/2 inchin any length
of pipe.
(7) Length of two opposite sides: Variations in laying length of two opposite sides of the
pipe shall not be more than [6 mm1/4 inch for all sizes through 600 mm 24 inches internal diameter]
[3 mm per 300 mm1/8 inch per foot for all sizes larger than 600 mm 24 inchesin internal diameter],
with a maximum of 10 mm 3/8 inches in any length of pipe.
b. Joints and Jointing Material:
(1) Joints: Joint shall [be formed entirely of concrete and as detailed in the contract drawings,
[may] [shall] utilize a rubber gasket or mastic to provide the seal]. [Incorporate an assembly
of [steel bands] [or] [steel bell ends] and spigot rings and rubber gaskets in accordance with
contract drawings].
2.1.1.4 Steel Pipe
NOTE: This section covers steel pipe used as an encasement for other carrier
pipes or it may also serve as the carrier pipe for water, gas, sanitary sewer
or other utility products.
a. Pipe: Steel pipe shall be in conformance with [ASTM A 139, Grade B with a minimum yield
strength of 242 MPa 35,000 psi] [AWWA C200] [API Spec 5L Grade B] [ASTM A 53] [ASTM A 716] [
ASTM A 746]. Steel pipe shall be welded, seamless, square cut with even lengths [and shall
comply of Articles 4.2, 4.3, and 4.4 of the API Spec 5L].
(1) Roundness: The difference between the major and minor outside diameters shall not exceed
[one percent] of the specified nominal outside diameter of 6 mm 0.25 inch whichever is less.
[For pipe exceeding 1200 mm 48 inches in diameter, a maximum deviation of 13 mm 1/2 inch shall
be permitted provided the circumference tolerance is maintained within 6 mm 1/4 inch.]
(2) Circumference: The outside circumference shall be within +1 percent of the nominal circumference
or within+13 mm+0.50 inches, whichever is less.
(3) Straightness: The maximum allowable straightness deviation in any 3 m 10 foot length shall
be 3 mm 1/8 inch. [For lengths over 3 m 10 feet, the maximum deviation of the entire length
may be computed by the following formula, but not to exceed 10 mm 3/8 inch in any 12 m 40 foot
length:
(1/8) x (total length in meters/0.125 = Max. Deviation in mm)(1/8) x (total length in feet)/10
= Maximum Deviation in inches)]
(4) Pipe ends: The end of the pipe shall be perpendicular to the longitudinal axis of the
pipe and within 2 mm per meter 1/16 inches per foot of diameter, with a maximum allowable deviation
of 6 mm 1/4 inch measured with a square and straightedge across the end of the pipe.
b. Joints: The connection of adjacent pieces of microtunneling steel pipe may be accomplished
by [field buttwelding,] [internal weld sleeves,] [integral press fit connectors,] as long as
loading and installation design criteria are met.
2.1.1.5 Fiberglass Pipe
NOTE: This section covers centrifugally cast fiberglass pipe for installation
be pipe jacking and microtunneling for use in sanitary sewer, storm drain, wastewater
collection and industrial effluent applications.
a. Pipe: Fiberglass pipe shall meet the requirements of ASTM D 3262, Type 1, Liner 2, Grade
3. The method of the manufacture shall be centrifugal casting resulting in a controlled outside
diameter. Minimum wall thickness shall be+38 mm+1.5 inches.
(1) Roundness: The pipes shall be round within 0.1 percent of the outside diameter.
(2) Pipe lengths: Lengths tolerance shall be+6 mm+1/4 inches per length of pipe.
(3) End squareness: Pipe ends shall be perpendicular to the pipe axis within a tolerance of+2 mm+1/16 inch.
(4) Straightness: Pipes shall be straight to within+2 mm+1/16 inch over 3 m 10 feet.
(5) Jacking strength The average ultimate axial compressive strength shall be 83 MPa 12,000
psi minimum. The jacking capacity shall be based on the structural wall (end area) under the
gasket groove (reduced cross-section). The allowable jacking capacity shall be determined by
applying a 2.5 safety factor.
b. Joints: The pipes shall be connected by gasket-sealed bell-spigot joints. The gasket material
shall meet requirements of ASTM F 477. The joint shall meet the requirements of ASTM D 4161
and shall be leak-free under the following conditions:
(1) External pressures up to 2 bars 200 kPa 29 psi from bentonite injection, slurry system
operation or groundwater head.
(2) Internal air testing up to 35 kPa 5 psi.
(3) Gaps between the pipe ends up to two percent of the diameter (maximum of 25 mm one inch
).
[c. The liner shall consist of a minimum thickness of 1.2 mm 0.04 inch of reinforced polyester
resin. The outside pipe coating shall have a minimum thickness of one mm 0.03 inches and shall
consist of thermosetting polyester resin and sand.]
2.1.1.6 Vitrified Clay Pipe
ASTM C 700.
NOTE: This section covers the criteria for the manufacture, quality assurance
testing, inspection, installation, and field acceptance testing of vitrified
clay pipe to be used in jacking, sliplining, and in tunnels for the conveyance
of sewage, industrial wastes, and storm water.
a. Pipe: Vitrified clay pipe shall be manufactured from fire clay, shale, surface clay, or
a combination that can meet three edge bearing strength for nominal diameters of: [100 mm 2980]
[150 mm 2980] [200 mm 3278] [250 mm 3576] [300 mm 3874] [375 mm 4321] [450 mm 4917] [525 mm
5736] [600 mm 6556] [675 mm 7003] [750 mm 7450] [900 mm 8940] [1050 mm 10430] kg/m [4 inches
2000] [6 inches 2000] [8 inches 2200] [10 inches 2400] [12 inches 2600] [15 inches 2900] [18
inches 3300] [21 inches 3850] [24 inches 440] [27 inches 4700] [30 inches 5000] [36 inches 6000]
[42 inches 7000] lb/linear foot.
(1) Acid Resistance: The pipe shall be resistant to acid in accordance with test methods specified
in ASTM C 301.
(2) Compressive Strength: Pipe materials shall have a minimum compressive strength of 48 MPa
7,000 psi.
(3) Dimensional tolerances: The outside diameter shall not vary from a true circle by more
than 2 percent of its nominal diameter. The out-of-round dimension is the difference between
the maximum and minimum diameters measured at any one location along the barrel and must be
limited to less than. Pipe shall not deviate from straight by more than 1.3 mm per 300 mm 0.05
inches per linear foot when maximum offset is measured from the concave side of the pipe.
(4) End squareness: The space formed by a pipe end shall not deviate by more than 0.13 mm
per 25 mm 0.005 inches per inch of outside diameter.
b. Joints: Joints shall be capable of supporting a shear load of 8755 N/m 50 pounds per inch
of nominal diameter uniformly applied over an arc of not less than 2.09 rad 120 degreesand
along a distance of 300 mm 12 inches adjacent to the joint. Apply an internal 3 m 10 foot head
30 kPa 4.3 psi of water pressure for a period of one our. Joints shall fully comply withASTM C 1208MASTM C 1208/C 1208M.
2.2 CONCRETE
2.3 BENTONITE
Bentonite shall conform with API Spec 13A and have the capacity of mixing with water to form a stable and homogeneous
suspension.
2.4 BACKFILL
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Access Shafts
a. Construction methods required to provide access shafts for microtunneling shall be subject
to approval of the Contracting Officer. Acceptable construction methods may include the use
of interlocked steel sheetpiling or precast circular concrete segments lowered in place during
excavation.
b. Final dimensions of access shafts selected by the Contractor shall be modified as required
following installation of pipe casings to the size and shape of acceptable manhole designs shown
on the Contract Drawings [to permit installation of conveyance piping.]
c. Shafts shall be of a size commensurate with safe working practices and located as shown
on plans. With the approval of the Contracting officer, the Contractor may relocate shafts
to better suit the capabilities of the microtunneling method proposed. Where no locations are
given, the Contractor shall determine such locations with the approval of the Contracting Officer.
d. Shaft locations shall, where possible, be kept clear of road intersections and within a
single traffic lane, in order to minimize disruption to the flow of traffic. Support equipment,
spoil piles, and materials shall also be located such as to minimize disruption to traffic and
are subject to the approval of the Contracting Officer.
e. The Contractor shall properly support all excavations and prevent movement of the soil,
pavement, utilities or structures outside of the excavation. The Contractor shall furnish,
place and maintain sheeting, bracing, and lining required to support the sides and floor of
all pits and to provide adequate protection of the work, personnel, and the general public.
Design loads on the sides of the jacking and receiving pit walls are dependent on the construction
method and flexibility of the wall systems.
f. Construct a starter shaft to accommodate the installation of pipe casings, slurry shield
and piping jacking device. Install thrust block as required and consolidate the ground (grout)
where the casings exit the shaft.
g. Construct a receiver shaft to accommodate the installation of pipe casings and the slurry
shield. Consolidate the ground (grout) where the casings enter the shaft.
h. The Contractor shall furnish, install, and maintain equipment to keep the jacking shaft
free of excess water. The Contractor shall also provide surface protection during the period
of construction to ensure that surface runoff does not enter driving shaft(s). Groundwater
dewatering shall comply with the approved dewatering plan and shall not affect surrounding soils
or structures beyond the tolerances stated in paragraph entitled "Settlement, Alignment and
Tolerances."
i. Provide security fence around all access shaft areas and provide shaft cover(s) when the
shaft area is not in use.
j. Design of the jacking and receiving pit supports should also take into account the loading
from shield or pipe jacking where appropriate, as well as special provisions and reinforcement
around the breakout location. The base of the pits shall be designed to withstand uplift forces
from the full design head of water, unless approved dewatering or other ground modification
methods are employed.
k. Where a thrust block is required to transfer jacking loads into the soil, it shall be properly
designed and constructed by the Contractor. The backstop shall be normal (square) with the
proposed pipe alignment and shall be designed to withstand the maximum jacking pressure to be
used with a factor of safety of at least 2.0. It shall also be designed to minimize excessive
deflections in such a manner as to avoid disturbance of adjacent structures or utilities or
excessive ground movement. If a concrete thrust block or treated soil zone is utilized to transfer
jacking loads into the soil, the tunnel boring is not to be jacked until the concrete or other
materials have attained the required strength.
l. Pit Backfill and Compaction: Upon completion of the pipe drive and approval of the installed
pipeline by the Contracting Officer, remove all equipment, debris, and unacceptable materials
from the pits and commence backfilling operation. Backfilling, compaction and pavement repairs
shall be completed in accordance with Section
31 00 00
31 00 00
31 00 00 EXCAVATION.
[m. If tremie concrete sealing slabs are placed within the earth support system to prevent
groundwater inflow when access shafts are dewatered, the sealing slabs shall be of sufficient
thickness to provide a factor of safety equal to 1.2 against hydrostatic uplift in order to
prevent bottom blowout when the excavation is completely dewatered.]
3.2 INSTALLATION
3.2.1 Installation of Tracer Wire
Install a continuous length of tracer wire for the full length of each run of nonmetallic pipe. Attach wire
to top of pipe in such a manner that will not be displaced during construction operations.
3.2.2 Connections to Existing Lines
Make connections to existing lines after Government approval is obtained and with a minimum interruption of service
on the existing line. Make connections to existing lines under pressure [in accordance with the recommended
procedures of the manufacturer of the pipe being tapped] [as indicated].
NOTE: Microtunneling Information
The minimum depth of cover over the pipe being installed using the microtunneling
process is normally 1.8 m 6 feet or 1.5 times the outer diameter of the pipe
being installed, whichever is the greater. Microtunneling work is executed
so as to minimize settlement or heave. The overcut of the tunneling machine
or method shall be determined by the need to satisfy settlement or heave tolerances.
Overcut should not exceed 25 mm one inch on the radius of the pipe. The annular
space created by the overcut usually can be filled with the lubricating material
that is used to reduce the friction drag of the soil on the pipe (i.e., bentonite
slurry).
3.2.3 Settlement, Alignment and Tolerances
a. Settlement or heave of ground surface along centerline of microtunneling alignments during
and after installation of pipe casings shall not exceed [_____] mm inches.
b. No more than [_____] mm inch lateral and [_____] mm inch vertical deviation shall be permitted
in the position of the completed jacked pipe casings. [Water shall be free draining between
any two points at the pipe invert. No reverse grades will be allowed.]
[c. Overcut shall not exceed 25 mm one inch on the radius of the pipe being installed. The
annular space created by the overcut [may] [must] be filled with the lubrication material that
is used to reduce soil friction drag on the pipe.]
3.2.4 Microtunneling
NOTE: Select one of the following options. The first option restricts the
Contractor to using an unmanned tunneling machine while the second option also
permits the Contractor to use tunneling shields.
[a. The microtunneling boring machine shall be an unmanned mechanical type earth pressure counter-balanced
bentonite slurry shield system. The machine shall be laser guided and monitored continuously,
with a closed circuit television system. The machine shall be capable of fully supporting the
face both during excavation and during shutdown and shall have the capability, of positively
measuring the earth pressure at the face. Excavation face pressure shall be maintained at all
times between the measured active earth pressure and 50 percent of the computed passive earth
pressure. Fluid pressure applied at the face to stabilize the excavation shall be maintained
at a level slightly in excess of normal hydrostatic pressure and shall be monitored continuously.
The machine shall be operated so as to prevent either surface heave or loss of ground during
tunneling and shall be steerable and capable of controlling the advance of the heading to maintain
line and grade within the tolerances specified in paragraph entitled "Settlement, Alignment
and Tolerances." The machine shall be capable of handling and removing materials of high water
content from the machine head.
b. Each pipe casing section shall be jacked forward as the excavation progresses in such a
way to provide complete and adequate, ground support at all times. A bentonite slurry (driller's
mud) shall be applied to the external surface of the pipe to reduce skin friction. A jacking
frame shall be provided for developing a uniform distribution of jacking forces around the periphery
of the pipe. A plywood spacer shall be placed on the outer shoulder of the pipe casing joint.
The thrust reaction backstop shall be properly designed and constructed.
c. The backstop shall be normal (square) with the proposed pipe casing alignment and shall
be designed to support the maximum obtainable jacking pressure with a safety factor at least
2.0.
d. The jacking system shall be capable of continuously monitoring the jacking pressure and
rate of advancement. Special care shall be taken when setting the pipe guard rails in the starter
shaft to ensure correctness of the alignment, grade and stability.]
[a. Only tunneling equipment capable of fully supporting the face of the tunnel shall be used
for pipe jacking work described.
b. Tunneling equipment selected for the project shall be compatible with the geotechnical information
contained in this contract. The tunneling equipment shall be capable of tunneling through mixed
face conditions without exceeding the settlement tolerances specified in paragraph "Settlement,
Alignment and Tolerances."
c. Face pressure exerted at the heading by the tunneling machine shall be maintained as required
to prevent loss of ground, groundwater inflows, and settlement or heave of the ground surface
by balancing soils and groundwater pressures present.
d. Dewatering for groundwater control shall be allowed at the jacking and receiving pits only.]
e. Do not jack pipe casing until the concrete thrust block and termie seal (if selected), and
grouted soil zone in starter and receiving shafts have attained the required strength.
f. The pipe casing shall be jacked in place without damaging the pipe casing joints or completed
pipe casing section.
g. After completion of the jacking operation between starter and receiver shafts, the lubricate
material shall be displaced from between the pipe casing exterior and the surrounding ground
by a cement grout. Pressure and the amount of grout shall be controlled to avoid pipe damage
and displacement of the pipe and soil beyond the tolerances specified in paragraph "Settlement,
Alignment and Tolerances." Grouting shall be accomplished promptly after pipe installation
has been completed to prevent any surface settlement due to movement of soil material into the
void space or loosened zone around the pipe casing.
h. Any pipe casing which has been damaged during installation shall be replaced by the Contractor
at no additional cost. If a new replacement pipe casing is required extending from the starter
to the receiver shaft, it shall be installed in conformance with the contract drawings and this
section.
[i. Steel pipe casing joints shall be continuously welded with butt joint per AWS D1.1/D1.1M
. The welds shall attain the full strength of the pipe and shall result in a full watertight
section. The inner face of internal weld seam shall be flush with the pipe to facilitate the
installation of the conveyance pipe in the pipe casing.
j. Perform all welding in accordance with requirements for shielded metal arc welding of AWS D1.5
for bridges and AWS D1.1/D1.1M for buildings and other structures.]
[i. Fiberglass pipe casing joints shall be fully watertight and shall attain the full strength
of the pipe. Casing joints shall be field connected with sleeve couplings or bell and spigot
type joints that utilize elastomeric sealing gaskets as the sole means to maintain joint water
tightness.
j. The joint shall have the same outside diameter as the pipe so when the pipelines are assembled
such that the joints are flush with the pipe inside and outside surface [to facilitate installation
of he conveyance pipe in the pipe casing].]
k. [All excavated material from tunnel and shaft construction shall be disposed of away from
the construction site.] [On-site storage of material must comply with Section
01 57 19.00 20
01 57 19.00 20
01 57 19.00 20 TEMPORARY CONTROLS and must be stored in areas shown on site drawings.] [Stockpiling
shall be permitted on the construction site and material shall be removed at regular intervals
not exceeding [_____] hours.]
l. Monitor ground movements associated with the project and make suitable changes in the construction
methods that control ground movements and prevent damage or detrimental movement to the work
and adjacent structures and pavements.
m. Install instrumentation, take readings and provide the Contracting Officer with weekly reports
containing measurements data with weekly reports to inspector. These actions are meant to supplement
the Contractor's monitoring system and do not relieve the Contractor of his responsibility,
nor place on the Contracting Officer, responsibility for control of ground movement and protection
of the project and adjacent structures. Instrumentation readings shall be continued for a period
of [_____] weeks after pipe casings have been installed to establish that detrimental settlement
has not occurred.
n. Unprotected mining of the tunnel bore is not permitted. The tunnel face and bore shall
be fully supported at all times.
[o. A topographic survey will be performed by the Contractor before and after microtunneling
and at [_____] week intervals for a period of [_____] weeks. Survey markers will be installed
by the contractor at grid points located at [_____] m foot spacing over an area [_____] square
meter square foot centered on the proposed tunnel alignments. Perform all remedial work including
repaired if heave or settlement greater than [_____] mm inches is recorded.
p. Approval by the Contracting Officer of the topographic survey and final set of readings
provided by the Contractor will constitute [partial] approval of the microtunneling phase of
work.]
3.2.5 Ventilation
a. Adequate ventilation shall be provided for all cased tunnels and shafts. Follow confined
space entry procedures. [Local burn permit regulations must be obeyed and complied with.]
The design of ventilating system shall include such factors as the volume required to furnish
fresh air in the shafts, and the volume to remove dust that may be caused by the cutting of
the face and other operations which may impact the laser guidance system. The minimum amount
of fresh air to be supplied shall be [_____] cubic m/s CFM. [Air testing shall be required
for the specific conditions to ensure that the following gas concentration requirements are
met:
Carbon Monoxide <0.005 percent
Methane <0.25 percent
Hydrogen Sulfide <0.001 percent
Oxygen >20.0 percent]
3.2.6 Lighting
Adequate lighting shall be provided for the nature of the activity being conducted by workers for the microtunneling.
Both power and lighting circuits shall be separated and thoroughly insulated with ground fault interrupters are
required. Lights shall comply with requirements with regards to shatter resistance and illumination requirements.
3.2.7 Spoil Transportation
The soil transportation system shall match the excavation rate with rate of spoil removal. The system must also
be capable of balancing groundwater pressures and adjustment to maintain face stability for he particular soil
conditions of this project.
3.2.8 Pipe Jacking Equipment
The main jacking equipment installed must have a capacity greater than the anticipated jacking load. Intermediate
jacking stations shall be provided by the Contractor when the total anticipated jacking force needed to complete
the installation may exceed the capacity of the main jacks or the designed maximum jacking force for the pipe.
The jacking system shall develop a uniform distribution of jacking forces on the end of the pipe by use of thruster
rings and cushioning material.
3.2.9 Jacking Pipe
NOTE: Some microtunneling methods utilize a temporary jacking pipe or shield
that is replaced by a permanent casing or carrier pipe. This section applies
to all jacking pipes, but it intended to ensure that temporary jacking pipes
are covered by this section.
NOTE: Jacking and Installation Information
1. The length of drive that is possible to achieve with particular equipment
is dependent upon the jacking force required to push the pipe, the soil conditions
and the depth of the pipe. The jacking force require is a function of many
variables including the soil conditions, depth of the pipeline, annular space
between the pipe and soil, lubrication of the pipe, material, diameter and strength.
2. When a slurry system is used by the Contractor, the composition of the slurry
must be closely monitored for specific gravity and viscosity in certain soil
conditions. With an auger soil removal system, the speed of rotation of the
auger flight and the addition of water and/or compressed air must be closely
monitored.
In general, pipe used for jacking shall be smooth, round, have an even outer surface, and joints that allow for
easy connections between pipes. Pipe ends shall be square and smooth so that jacking loads are minimized when
the pipe is jacking. Pipe used for pipe jacking shall be capable of withstanding the jacking forces that will
be imposed by the process or installation, as well as the final place loading conditions. The driving ends of
the pipe and intermediate joints shall be protected from damage.
a. Any pipe showing signs of failure may be jacked through to the receiving shaft and removed.
Other methods of repairing the damaged pipe may be used, as recommended by the manufacturer
and subject to approval by the Contracting Officer.
b. The pipe manufacturer's design jacking loads shall not be exceeded during the installation
process. The pipe shall be designed to take full account of all temporary installation loads.
3.3 FIELD QUALITY CONTROL
3.3.1 Field Tests and Inspections
NOTE: Indicate appropriate Section number and title in blank below using proper
format per UFC 1-300-02.
The Contractor shall perform field tests, and provide labor, equipment, and incidentals required for testing
[, except that water and electric power needed for field tests will be furnished as set forth in _____]. The
Contractor will product evidence, when required, that any item of work has been constructed in accordance with
drawings and specifications.
3.3.2 Testing Requirements
For pressure test, use a hydrostatic pressure [_____] kPa psi greater than the maximum working pressure of the
system. Hold this pressure for not less than [_____] hours. For leakage test, use a hydrostatic pressure not
less than the maximum working pressure of the system. Leakage test may be performed at the same time and at
the same test pressure as the pressure test.
-- End of Section --