Wedge/Arch Test with new electronics at B0 ------------------------------------------ tasks responsible party ----- ----------------- '98 Oct 5- 9 ** START 1 WEDGE CONFIGURATION - WEDGE 21W Install Crate, ethernet connection, F Lewis, Roser & Co & electrical power in rack for wedge 21W Exercise PMT HV (manual operation) Pauletta Oct 12-16 Install power supply F Lewis, S Orr Install temporary rack monitoring Schmitt, Elias Install Crate CPU (MVME162) DeMaat Install 2 ADMEM, TRACER, TestClk L Scott Install Transition card with PMT cables Hahn, Lindgren, Dervin Install Cal Card, transition board Gallinaro & cables to CEM Software for ADMEM, TRACER, TestClk Chlebana (moving from ICB) Oct 19-23 Start electronics test with 1 wedge (Stand alone system with TestClk) - solve grounding problems Hahn, Sakumoto, Budd, - take pedestal data HaoWei, Chlebana, Orr, - source, flasher calibration runs Gallinaro, Nodulman Oct 26-29 Noise studies (Standalone readout) - Noise into ADMEM from power supply, crate CPU, Clock Hahn, HaoWei, Sakumoto - Noise into CES (using Rabbit readout) Drake, Drennen Nov 2- 6 Continue Noise studies (Standalone readout) Nov 9-13 Continue Noise studies (Standalone readout) Install & run portable chilled water Roser & Co Install SMXR, SMC, SMD crate, SMD with digital SQUID & associated cables JinYuan, Drennen, Drake Install CMUASD, HADASD in the crate Nathan, Hahn (transition modules needed) Install TDC's in 1st floor Kelly, Fritz (paddle card needed) Install temporary ASD->TDC cables Dervin (1 ansley, 1 HADASD cable) Install temporary 10 Lv1 Trigger cables Dervin Connect CMU HV cables (to chamber & CAEN) Roser, Eddy Nov 16-20 Continue noise/performance studies (Standalone readout) - Pedestal data Hahn, HaoWei, Sakumoto, - Source calibration Budd, Gallinaro, - Flasher calibration Lindgren, Nodulman - Laser calibration Exercise SMX system data path JinYuan, Drennen, Drake (SMX system running with digital SQUID) Readout TDC crate with TestClk Fritz (TDC crate cabled to CMUASD & HADASD) Test online Calibration DB Prototype Umesh, Jack, J Patrick Nov 23-25 Continue activities listed in Nov 16-20 Nov 30-Dec 4 Continue activities listed in Nov 16-20 Install Crate Fanout crates Roser & Co Install Clock fanout at B0 Chappa Install TS prototype system at B0 Martin, Schmidt Run CMU with a bottled Ar/Et Roser, Eddy Dec 7 -11 ** ADD 3 MORE WEDGES - WEDGE 18W, 19W, 20W Install Crate, ethernet connection, F Lewis, Roser & Co & electrical power in the rack for wedges 18W, 19W, & 20W Install power supply, TRACER, TestClk F Lewis, S Orr Install Crate CPU (MVME2301) DeMaat Install ADMEM (120 channels) Scott Install Transition card with PMT cables Hahn, Lindgren, Dervin Install Cal Card, transition board Gallinaro & cables to CEM for 3 wedge operation Run "Standard Software" for ADMEM, TRACER Chlebana, Vejcik Dec 14-18 Continue activities listed in Dec 7 -11 Get CHA laser working with TSI & DAQ Cordelli & Co PISABOX program for HV control ready & test Cordelli & Co Readout 24 CES channels with SMQIE Drake, JinYuan, Drennen Test ADMEM/DIRAC/DCAS integration Peter/Culbertson/Monica ******* Dec 21 - Jan 3 Lab Holidays ******** '99 Jan 4- 8 Start electronics test with 4 wedges - solve grounding problems Hahn, Sakumoto, Budd, - take pedestal data HaoWei, Chlebana, Orr, - source, Flasher calibration runs Gallinaro, Nodulman Continue Readout CES channels Drake, JinYuan, Drennen Continue ADMEM/DIRAC/DCAS integration Peter/Culbertson/Monica Jan 11-15 Continue electronics test with 4 wedges Continue ADMEM/DIRAC/DCAS integration Peter/Culbertson/Monica Install TAXI transition module Walter Connect ADMEM & TDC crates to VRB JJ, Dervin, Vejcik Prototype EVB running with VRB which are connected to ADMEM TDC crates Tether, Patrick, Vejcik Jan 18-22 Continue noise/performance studies - Pedestal data Hahn, HaoWei, Sakumoto, - Source calibration Budd, Gallinaro, - Flasher calibration Lindgren, Nodulman - Laser calibration Jan 25-29 Integrated Software Prototype ready & test Patrick & Co (Run Control, TS, VRB, EVB, Clock, ADMEM, TDC, SMXR, etc) Feb 1- 5 Continue Integrated Software Prototype test Patrick & Co Test Online Monitoring Software prototype Jack, Fritz, Frank (Calorimeter, TDC) Feb 8-12 Schedule Contingency Feb 15-19 Schedule Contingency Feb 22-26 Schedule Contingency