August 2004

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1
Projected Work:
• Continue 3 Planes per day Calorimeter Installation, starting at 7am daily.
• Continue Detector Commissioning, starting at 8am daily.
• Continue installing Absorber.
2
3 Planes installed, cabled and light-leak checked: 22, 21, 20.

Absorber - lowered & staged 3 roof steel blks, and 3 B Blks. B Blks are for the back wall and provide a work platform for welding the core pipes.  Set 5 roof steel blks & 0 Blu Blk; 29/78 roof steel & 85/88 Blu Blks in place.
3
3 Planes installed, cabled and light-leak checked: 19, 18, 17.

Absorber - lowered & staged 2 roof steel blks, and 2 back wall B Blks. Set B Blks, 2 roof steel blks & 0 Blu Blk; 31/78 roof steel & 85/88 Blu Blks in place.
4
3 Planes installed, cabled and light-leak checked: 16, 15, 14.

Absorber - lowered & staged 8 roof steel blks, and 2 back wall B Blks. Preping for core pipe welding. Set B Blks, 3 roof steel blks & 0 Blu Blk; 34/78 roof steel & 85/88 Blu Blks in place. Start bricking up the gap between upstream shield blocks and the wall around the DK pipe.
5
3 Planes installed, cabled and light-leak checked: 13, 12, 11.

Absorber - lowered & staged 6 roof steel blks. Welded 90-degree bends on 16/32 core cooling pipes. Set 5 roof steel blks & 1 Blu Blk; 39/78 roof steel & 86/88 Blu Blks in place. Continue upstream end brick-work.

Muon Monitor detector tubes arrive.
6
3 Planes installed, cabled and light-leak checked: 10, 9, 8.

Absorber - Welded 90-degree bends on 8 more (24/32) core cooling pipes. Set 14 roof steel blks & 2 Blu Blk; 53/78 roof steel & 88/88 Blu Blks in place. Continue upstream end brick work.

Muon tubes lowered and stashed in Alcove 3.
7

 
 
 
 
8
Projected Work:
• Complete Near Detector Plane Inststallation, 8/11.
• 3 Planes per day Calorimeter Installation, starting at 7am daily.
• Continue Detector Commissioning, starting at 8am daily.
• Continue installing Absorber.
9
3 Planes installed, cabled and light-leak checked: 7, 6, 5.

Absorber - completed welding 90-degree bends on core cooling pipes. Set 7 roof steel blks, 60/78 now in place. Remaining roof blocks constitute the "back porch". The back porch rests upon the back wall of B Blks - there are 12 such B Blks and 8 are now in place. Continue upstream brick-work.
10
3 Planes installed, cabled and light-leak checked: 4, 3, 2.

Absorber - 2 B Blks lowered & staged. Leak testing of core cooling pipe welds made to date, while all such welds are easily reached - once the "back porch" goes in these welds can still be reached but its a lot harder.  Continue upstream brick-work.
11
2 Planes installed, Plane 1, which is cabled and light-leak checked, and then Plane 0, which is bare steel.

Near Detector Plane Installation is complete.

Absorber - 6 roof steel blks lowered & staged. 12/12 B Blks set in place. Continue upstream brick-work.
12
Near Detector Coil Lifting Fixture fails it's load test - not due to inability to carry the weight, but because the load twists as it is lifted. A design revision is planned and work begins on it.

Absorber - 3 roof steel blks lowered & staged. Set 5 roof blks, 65/78 now in place. Continue upstream brick-work. B Blks for Labyrinth are staged outside MSB.
13
Absorber - 9 roof steel blks lowered & staged. Set 2 roof blks, 67/78 now in place. Continue upstream brick-work.

Riggers also removed all the steel plating which covered the Sump Covers - remaining loads - Absorber blocks and the Detector Coil, do not require the additional plate.
14

 
 
 
 
15
Projected Work:
• Continue Detector Commissioning, starting at 10am daily.
• Continue installing Absorber.
16
Absorber - Set 5 roof blks, 72/78 now in place. Complete upstream brick-work.

17
Absorber - Set 6 roof blks, 78/78 now in place. All Absorber block stacking is complete. Riggers begin to remove their hydraulic gantry and lift beam.
18
Absorber - Riggers continue to remove their heavy lift equipment.
19
Absorber - Riggers continue to remove their heavy lift equipment. Lower and stage the 1st Labyrinth B Blk. Electricians remove a light fixture which will interfere with the Labyrinth blocks.

Holding tank for cooling water 2ndry containment delivered and set.
20
Absorber - lowered 1 B and 2 C Blks for Labyrinth. Set 1 B and 2 Cs. Lowered and set the Bead Box, a wood box which fits around the Absorber cooling pipes, and which will be filled with Poly Beads. The box serves to absorb slow neutrons which would otherwise leak out along the piping path.
21

 
 
 
 
22
Projected Work:
• Continue Detector Commissioning, starting at 10am daily.
• Continue installing Absorber.
23
Absorber - lowered 1 A and 2 E Blks for Labyrinth. Set Blocks: total so far 1/2 C, 2/9 B, 1/2 A, 2/9 E, 0 F, and no handstack.

Rad Safety begins install or Rad Gate at the entrance into the DK Tunnel, just upstream of the Absorber Enclosure.
24
Absorber - lowered various Blks for Labyrinth, including pallets of handstanck bricks. Set Blocks: total so far 1/2 C, 3/9 B, 1/2 A, 3/9 E, 1/2 F. Handstack to roof, above all blocks installed so far.
25
Absorber - no work today.

FYI - Absorber cooling pipe connections are not yet complete due to a redesign of the connecting manifold. Fabrication of this manifold currently held up waiting for parts.
26
Absorber - lowered various Blks for Labyrinth, including pallets of handstanck bricks. Set Blocks: total so far 2/2 C, 5/9 B, 1/2 A, 4/9 E, 1/2 F, plus Handstack.
27
Absorber - lowered various Blks for Labyrinth, including pallets of handstanck bricks. Set Blocks: total so far 2/2 C, 7/9 B, 1/2 A, 4/9 E, 1/2 F, plus Handstack.

Drain pipe installed between the 2ndry containment pan and the holding tank.
28

 
 
 
 
29
Projected Work:
• Continue Detector Commissioning, starting at 10am daily.
• Continue installing Absorber.
30
Near Coil lifting fixture passes it's tests. Coil installation scheduled for next week. Support tripod used to install coil underground is delivered to the Hall.

Absorber - lowered various Blks for Labyrinth. Set Blocks: total so far 2/2 C, 8/9 B, 1/2 A, 8/9 E, 1/2 F, plus Handstack.

Rad Safety returns to work on the DK tunnel rad gate.
31
Absorber - lowered various Blks for Labyrinth. Set Blocks: total so far 2/2 C, 8/9 B, 2/2 A, 8/9 E, 1/2 F, plus Handstack. Mostly handstack today.