View PDF Version
No. 03-358
In the Supreme Court of the United States
UNITED STATES DEPARTMENT OF TRANSPORTATION,
ET AL., PETITIONERS
v.
PUBLIC CITIZEN, ET AL.
ON WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
JOINT APPENDIX
VOLUME I
THEODORE B. OLSON
Solicitor General
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
Counsel of Record
for Petitioners
STEPHEN P. BERZON
Counsel of Record
JONATHAN WEISSGLASS
ADAM B. WOLF
ALTSHULER, BERZON,
NUSSBAUM, RUBIN & DEMAIN
177 Post Street, Suite 300
San Francisco, CA 94108
(415) 421-7151
Attorneys for Respondents
Public Citizen, Inter-
national Brotherhood of
Teamsters, California
Labor Federation,
and Environmental Law
Foundation
(Additional Counsel Listed on Inside Cover)
GAIL RUDERMAN FEUER
ADRIANNA QUINTERO SOMAINI
NATURAL RESOURCES
DEFENSE COUNCIL
71 Stevenson Street, Suite 1825
San Francisco, CA 94105
(415) 777-0200
Attorneys for Respondents
Natural Resources Defense
Council and Planning and
Conservation League
DAVID C. VLADECK
PUBLIC CITIZEN
1600 20th Street, N.W.
Washington, D.C. 20009
(202) 588-1000
Attorneys for Respondent
Public Citizen
DAVID ROSENFELD
WEINBERG, ROGER &
ROSENFELD
1800 Grand Avenue, Suite 1400
Oakland, CA 94612
(510) 839-6600
Attorneys for Respondent
Brotherhood of Teamsters,
Auto and Truck Drivers,
Local 70
PATRICK J. SZYMANSKI
General Counsel
INTERNATIONAL
BROTHERHOOD
OF TEAMSTERS
25 Louisiana Ave., N.W.
Washington, D.C. 20001
(202) 624-6945
Attorney for Respondent
International Brotherhood
of Teamsters
PATRICK J. COUGHLIN
ALBERT H. MEYERHOFF
STANLEY S. MALLISON
MILBERG WEISS BERSHAD
HYNES & LERACH LLP
100 Pine Street, Suite 2600
San Francisco, CA 94111
(415) 288-4545
WILLIAM S. LERACH
MILBERG WEISS BERSHAD
HYNES & LERACH LLP
401 B Street, Suite 1700
San Diego, CA 92101
(619) 231-1058
Attorneys for Respondents
International Brotherhood
of Teamsters, Brotherhood
of Teamsters, Auto and
Truck Drivers, Local 70,
California Labor Federa-
tion, California Trucking
Association, and Environ-
mental Law Foundation
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
No. 02-70986
PUBLIC CITIZEN; BROTHERHOOD OF TEAMSTERS; AUTO AND TRUCK DRIVERS, LOCAL
70; CALIFORNIA LABOR FEDERATION; CALIFORNIA TRUCKING ASSOCIATION; ENVIRONMENTAL
LAW FOUNDATION; INTERNATIONAL BROTHERHOOD OF TEAMSTERS', PETITIONERS
NATURAL RESOURCES DEFENSE COUNCIL (NRDC) AND THE PLANNING AND CONSERVATION
LEAGUE (PCL), PETITIONER-INTERVENORS
v.
DEPARTMENT OF TRANSPORTATION; FEDERAL MOTOR CARRIER SAFETY ADMINISTRATION;
NICHOLAS R. WALSH, RESPONDENTS
DOCKET ENTRIES
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/2/02 FILED PETITION FOR REVIEW DOCKETED CAUSE AND ENTERED APPEARANCES
OF COUNSEL, NOTIFIED RESPONDENTS OF FILING, SENT PETITIONER CIVIL APPEALS
DOCKETING STATEMENT setting schedule as follows: petitioners' opening brief
is due 7/22/02; respondents' brief is due 8/20/02; petitioner's optional
reply brief is due 9/3/02. [02-70986] (vt) [02-70986]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/2/02 Filed Petitioner Public Citizen, et al., emergency motion to stay
and request for judicial notice in support w/declaration of Charles s. Crandall.
served on 5/2/02 MOATT (vt) [02-70986]
5/2/02 Filed Jonathan Weissglass Civil Appeals
Docketing Statement served on 5/2/02 (to CONFATT) [02-70986] [02-70986]
(vt)
[02-70986]
5/2/02 Received (oversized) ***FAXED*** Respondent Dept. of Transporta,
Federal Motor, Nicholas R. Walsh's response in opposition to petr's emergency
mtn under Cir. Rule 27-3; served on 5/2/02. (MOATT) [02-70986] (af) [02-70986]
5/2/02 Filed Original and 15 copies People of the State of CA ex rel. Atty
General Bill Lockyer's amicus brief in support of petrs' petition for review
and emergency mtn in 23 pages; served on 5/2/02. (MOATT)
[02-70986] (af) [02-70986]
5/2/02 Filed Order (Harry PREGERSON, Ferdinand F. FERNANDEZ,) Petrs' emergency
mtn under Cir. Rule 27-3 is DENIED. The briefing schedule established previously
shall remain in effect. [02-70986] (af)
[02-70986]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/3/02 Received Petitioners' reply in support of emergency mtn; served on
5/2/02. (FYI/ MOATT) (faxed copy rec'd 5/2/02) [02-70986] (af) [02-70986]
5/6/02 Filed Petitioner International Brotherhood of Teamsters, CA Labor
Federation, and Environmental Law Foundation EMERGENCY mtn under Cir. Rule
27-3 to expedite proceedings; declaration of Jonathan Weissglass; served
on 5/6/02. (hand delivered to PROMO) [02-70986] (af)
[02-70986]
5/8/02 Notice of appearance of John L.Smeltzer on behalf of Federal Motor
Carrier Safety.
[02-70986] (af) [02-70986]
5/9/02 Filed Respondent Federal Motor's response in opposition to petr's
emergency mtn under Cir. Rule 27-3 to expedite proceedings; served on 5/8/02.
(PROMO) (faxed copy rec'd 5/8/02) [02-70986] (af) [02-70986]
5/9/02 Filed Petitioner International B rotherhood of Teamsters, CA Labor
Federation, and Environmental Law Foundation's reply in support of emergency
mtn under Cir. Rule 27-3 to expedite proceedings; served on 5/9/02. (FYI/PROMO)
[02-70986] (af)
[02-70986]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/9/02 Filed Order (Dep Clk: PROMO/tah) The ct is in receipt of the petrs'
mtn to expedite the above captioned petition for review and the resps' response
thereto. The mtn to expedite is GRANTED IN PART. The resp shall file the
certified administrative record on or before 5/28/02. The opening brf is
due 6/5/02. The ans brf is due 7/5/02. The optional reply brf is due 14
day from svc of the ans brf. No telephonic exts of time to file brfs prusuant
to 9th Cir. Rule 31-2.2(a) shall be granted. Written mtns for ext. filed
pursuant to 9th Cir. Rule 31-2.2(b) will not be granted absent a showing
of extraordinary and compelling circumstatnces. This cs shall be placed
on the next available calendar after the filing of the resps' ans brf. (c.c.
Calendar Unit) [02-70986] (af)
[02-70986]
5/22/02 Filed Order (Dep Clk: PROMO/cb) Petrs' opposed mtn to consolidated
Nos. 02-70986 and 02-71249 is GRANTED. Petrs' opposed mtn to expedite is
GRANTED IN PART. The following schedule shall govern both petitions. The
records remain due 5/28/02; the opening brf(s) shall be due 6/19/02; the
Govt's brf is due 7/19/02; the optional reply brf(s) shall be due 14 days
from svc of the ans brf. The provisions of 9th Cir. Rule 31-2.2(a) shall
not be applicable to these cases;
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
any Rule 31-2.2(b) mtn is strongly disfavored. The provisions of 9th Cir.
Rule 28-4 as they apply to continances are also inapplicable to these cases.
Petrs are reminded of the ct's preference for joint brfs. (cite) The cases
shall be placed on the next available calendar after the filing of the ans
brf. Petrs are informed that the provisions of 9th Cir. Rule 27-3 are not
intended for application to requests for procedural relief. (c.c. Calendar
Unit) [02-70986, 02-71249] (af) [02-70986 02-71249]
5/28/02 Filed certified list in lieu of record on appeal; served on 05/24/02.
(RECORDS)
[02-71249, 02-70986] [02-71249, 02-70986] (dv) [02-70986 02-71249]
5/31/02 Filed Petitioner-Intervenor Natural Resources' motion for intervene
on behalf of petrs; served on 5/31/02. (WIP/PROMO/tah) [02-70986, 02-71249]
(af) [02-70986 02-71249]
6/7/02 Filed Federal Respondent's response to mtn to intervene as petrs'
and mtn to recon ct's order dated 5/9/ and 5/22/02; served on 6/6/02. (WIP/PROMO-tah)
[02-70986,
02-71249] (af) [02-70986 02-71249]
6/10/02 Filed Petitioners' response to resps' request to reconsider expedited
proceedings; served on 6/10/02. (WIP/PROMO-tah)
[02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
6/14/02 Filed Order (Appellate Commissioner) The mtn of the Natural Resources
Defense Council and the Planning and Conservation League for leave to intervene
on behalf of petrs is GRANTED. The response to the mtn to intervene includes
a request for an order requiring petrs and intvns to file a joint brf. Resps'
request is DENIED. However, the parties are reminded of the ct's strong
preference for a joint brf. (cite) Resps are reminded that under 9th Cir.
Rule 28-4, they may request an enlargement of brf size. Resps' request for
recon of the provisions of 5/9/ and 5/22/02 orders regarding ext. of time
is DENIED. (PROMO) [02-70986, 02-71249] (af) [02-70986 02-71249]
6/19/02 Filed original and 15 copies of Petitioners CONSOLIDATED opening
brief (Informal: no) 52 pages and five excerpts of record in 2 volumes;
served on 6/19/02. [02-70986,
02-71249] (af) [02-70986 02-71249]
6/25/02 Filed Original and 15 copies People of the State in 02-70986's brief
of 31 pages; served on 6/24/02. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
7/15/02 Filed Mtn of Resps' and Order (Dep Clk: PROMO/tah) The federal resps'
mtn for an enlargement of brf size for the ans brf is GRANTED. The movants
may file an ans brf not to exceed 15,400 words. The briefing schedule is
unchanged. This order was issued prior to the expiration of time within
which a response may be filed. (cite) (Motion recvd 7/12/02)(phoned Atty
Smeltzer for movant) [02-70986, 02-71249] (af)
[02-70986 02-71249]
* * * * *
7/22/02 Filed Original and 15 copies respondent Dept. of Transportation
Federal Motor Carrier Safety Admin.'s 70 pages brief, 5 Sup Excerpts of
Record in 1 vol; served on 7/19/02. [02-70986, 02-71249] (af) [02-70986
02-71249]
7/25/02 Received Amicus ATA Litigation in
02-70986, in 02-71249's brief in 15 copies of 30 pages; served on 7/24/02.
(REFERRED TO MERITS PNL per 7/31/02 order) [02-70986, 02-71249] (af) [02-70986
02-71249]
7/25/02 Filed Amicus ATA Litigation's mtn for leave to file amicus curiae
in support of resps; served on 7/24/02. (RECORDS FOR MERITS PNL per 7/31/02
order) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
7/31/02 Filed Order (Dep Clk: PROMO/cag) Ata Litigation Center, Inc.'s mtn
for leave to file amicus curiae in spport of resps, the proposed brf and
any related filing shall be REFERRED FOR DISPOSITION TO THE PNL that considers
the merits of the cs. ANY FUTURE MTNS TO FILE A FRIEND OF THE CT BRF SHALL
BE TREATED IN THE SAME FASHION. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
8/2/02 Filed Original and 15 copies of Petitioners' CONSOLIDATED reply brief
(Informal: no) 34 pages; served on 8/2/02. (Calendar Unit) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/2/02 Filed Petitioners' mtn for leave to file evidence in support of standing;
served on 8/2/02. (Calendar Unit) [02-70986, 02-71249] (af) [02-70986 02-71249]
8/2/02 Received Petitioners' evidence in support of standing; served on
8/2/02. (mtn for leave to file pending) (Calendar Unit) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/2/02 Filed Petitioner-Intervenor Natural Resources' mtn for leave to file
evidence in support of standing; served on 8/2/02. (Calendar Unit) [02-70986,
02-71249] (af)
[02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
8/6/02 Filed Petitioner-Intervenor Natural Resources' mtn to correct "Intervenor-Petrs'
mtn for leave to file evidence in support of standing"; served on 8/6/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
8/7/02 CALENDARED: San Francisco October 8, 2002 9:00 a.m. Courtroom 2 [02-70986,
02-71249] (mw) [02-70986 02-71249]
8/19/02 Filed Petrs' International Brotherhood of Teamsters, CA Labor Federation,
and Environmental Law Foundation's mtn for additional time for oral argument;
served on 8/19/02. (faxed to PANEL) [02-70986, 02-71249] (af) [02-70986
02-71249]
8/29/02 Filed Order (Dep Clk: DOCKETING/hh) Petrs' and Intervenors' Mtns
for Leave to File Evidence in Support of Standing are hereby GRANTED. (served
PANEL; phoned csls at 2:30 p.m.; c.c. Front Counters) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/29/02 Filed Petrs' evidence in support of standing; served on 8/2/02.
(per 8/29/02 order) [02-70986, 02-71249] (af) [02-70986 02-71249]
9/4/02 Filed Amicus People of the State's mtn to present oral argument in
supprt of petrs' petition for review and emergency mtn; served on 9/3/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
9/12/02 Received Adrianna Quintero Somaini for Petitioner-Intervenor Natural
Resources' ltr dated 9/12/02 re: respectfully write to call to the attention
of the pnl a rpt from the U.S. Environmental Protection Agency, entitled
"FINAL HEALTH ASSESSMENT DOCUMENT FOR DIESEL ENGINE EXHAUST."
. . . (faxed to PANEL) [02-70986, 02-71249] (dv) [02-70986 02-71249]
9/23/02 Filed order (Dep Clk/hh) The mtn for leave to file an amicus curiae
brf by ATA Litigation Center, Inc. is GRANTED. Petrs' mtn for add'l time
for oral argument is DENIED without prejudice. The mtn by the People of
State of CA as amicus curiae for add'l time to present oral argument is
DENIED; however, petrs may choose to allocate a portion of their time to
the Atty General. (PHONED @1:20 pm) [4493704-1] [4509949-1] [4522553-1]
[02-70986, 02-71249] (ea) [02-70986 02-71249]
9/23/02 Filed orig & 15 copies ATA Litigation's amicus curiae brf of
30 pgs; served on 7/24/02. (PREVIOUSLY REC'D) [02-70986, 02-71249] (ea)
[02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
9/30/02 Received Petrs' additional citations in 02-70986, 02-71249; served
on 9/30/02 (faxed to PANEL; hand delivered to S.F Chambers; c.c. ctrroom
dep/tu) (Rec'd in docketing on 10/2/02) [02-70986, 02-71249] (af) [02-70986
02-71249]
10/8/02 ARGUED AND SUBMITTED TO Dorothy W. NELSON, Michael D. HAWKINS, Kim
M. WARDLAW [02-70986, 02-71249] (tu) [02-70986 02-71249]
10/22/02 Received Petrs' additional citations, served on 10/22/02 (faxed
to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/2/02 Received Petrs' additional citations, served on 12/1/02 (faxed to
PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/2/02 Filed Petitioners' EMERGENCY mtn for stay under Cir. R. 27-3 declaration
of Jonathan Weissglass; served on 12/2/02. (faxed and Fedex to PANEL) [02-70986,
02-71249] (af) [02-70986 02-71249]
12/2/02 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW)
Resps shall file their opp, if any, to Petrs' emergency stay mtn by Wed,
12/4/02. Each side file a supp brf addressing the effect of the President's
Memo of 11/27/02 modifying
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
the Mexican-domiciled motor carrier moratorium, (cite), on the issues presented
in this cs. Brfs must be filed on or before Fri, 12/13/02, and shall be
no longer than 15 pgs in length. It is so ORDERED. (served PANEL; phoned
and faxed to parties at 4:15 p.m.; c.c. Front Counter) [02-70986,
02-71249] (af) [02-70986 02-71249]
12/3/02 Received notice of Intervenors' from Petitioner-Intervenor Natural
Resources Defense Council and the Planning and Convervation League in 02-70986,
in 02-71249 notice of joinder in petrs' emergency mtn for stay under Cir.
R. 27.3; served on 12/3/02. (faxed to PANEL) (af) [02-70986
02-71249]
12/4/02 Filed Amicus People of the State in 02-70986, in 02-71249's brf
in support of petrs' emergency mtn for stay; served on 12/4/02. (faxed to
PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/4/02 Filed ****FAXED**** Respondents' response in opposition to petrs'
mtn for an emergency stay under Cir. R. 27-3; served on 12/4/02. (faxed
to PANEL) (hard copies rec'd 12/5/02) [02-70986, 02-71249] (af)
[02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
12/5/02 Filed Petrs' reply in support of mtn for stay; served on 12/5/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/6/02 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW)
Petrs' Emergency Mtn for Stay under Cir. R. 27-3 is taken under submission.
Resps shall provide this Ct with immediate notice upon the occurrence of
any of the following events: (1) the completion of the negotiations between
Resps and the Mexican gov't on a Memo of Understanding to establi sh protocols
for U.S. inspectors' operations in Mexico; (2) the scheduling of FMCSA's
first safety audit of a Mexico-domiciled motor carrier; or (3) the publication
of notice that any such carrier has successfully passed such as audit. To
reiterate our order of 12/2/02, simultaneous sup briefing addressing the
effect of the President's Memo of 11/27/02 modifying the Mexican-domiciled
motor carrier moratorium, (cite), on the issues presented in this cs shall
be filed on or before Friday, 12/13/02. It is so ORDERED. (served PANEL;
phoned and faxed to csls at 4:00 p.m.; c.c. Front Counter and C. Catterson
by hh) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
12/13/02 Filed ***FAXED*** Original and 0 copies Respondents' supplemental
brief of 16 pages, served on 12/13/02. (total of 3543 words) (faxed to PANEL)
(ORIGINAL and 15 Copies rec'd 12/16/02; PANEL) [02-70986, 02-71249] (af)
[02-70986 02-71249]
12/13/02 Filed Original and 15 copies Petitioners and Intervenors' JOINT
Supplemental brf of 14 pgs pursuant to order of the ct; served 12/13/02.
(faxed and served PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
1/13/03 Received Petrs' in 02-70986, in 02-71249 additional citations, served
on 1/13/03. (faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
1/16/03 FILED OPINION: GRANTED AND REMANDED. (Terminated on the Merits after
Oral Hearing; Granted and Remanded; Written, Signed, Published. Dorothy
W. NELSON; Michael D. HAWKINS; Kim M. WARDLAW, author.) FILED AND ENTERED
JUDGMENT. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
2/26/03 Filed Federal Motor in 02-70986, in 02-71249 motion for an ext.
of time in which to seek rehearing or rehearing en banc; served on 2/24/03.
(faxed to KMW) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
2/28/03 Filed Order (Kim M. WARDLAW,) Pursuant to Resps' mtn, the Ct grants
Resp an additional seven days in which to file a petition for rehearing
or rehearing en banc. Resps may file any such petitions on or before 3/10/03.
NO FURTHER EXTS WILL BE GRANTED. It is so ordered. (served PANEL; phoned
csls at 11:30a.m.; c.c. Front Counter) [02-70986, 02-71249] (af) [02-70986
02-71249]
3/10/03 Filed Original and 50 copies of Federal Resps' petition for panel
rehearing and petition for rehearing en banc in 18 pgs; served on 3/10/03.
(total of 4198 words) (PANEL and all active judges) [02-70986, 02-71249]
(af) [02-70986 02-71249]
4/10/03 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW)
The pnl has voted unanimously to deny the petition for pnl rehearing. Judges
Hawkins and Wardlaw have voted to deny the petition for en banc rehearing,
and Judge Nelson has so recommended. The full ct has been advised of the
petition for rehearing en banc and no active judge has requested a vote
on whether to rehear the matter en banc. (cite) The petition for rehearing
and for rehearing en banc are DENIED.
[02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
4/18/03 MANDATE ISSUED. Costs taxed against respondents in the amount of
$3370.80. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
No. 02-71249
INTERNATIONAL BROTHERHOOD OF TEAMSTERS; BROTHERHOOD OF TEAMSTERS, AUTO AND
TRUCK DRIVERS, LOCAL 70; CALIFORNIA LABOR FEDERATION; CALIFORNIA TRUCKING
ASSOCIATION; ENVIRONMENTAL LAW FOUNDATION; PUBLIC CITIZEN, PETITIONERS
NATURAL RESOURCES DEFENSE COUNCIL (NRDC) AND THE PLANNING AND CONSERVATION
LEAGUE (PCL), PETITIONER-INTERVENORS
v.
U. S. DEPARTMENT OF TRANSPORTATION; FEDERAL MOTOR CARRIER SAFETY ADMINISTRATION;
JOSEPH M. CLAPP; NICHOLAS R. WALSH, RESPONDENTS
DOCKET ENTRIES
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/16/02 FILED PETITION FOR REV DOCKETED CAUSE AND ENTERED APPEARANCES OF
COUNSEL, NOTIFIED RESPONDENTS OF FILING, SENT PETITIONER CIVIL APPEALS DOCKETING
STATEMENT setting schedule as follows: petitioners'
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
opening brief is due 8/5/02; respondents' brief is due 9/3/02; petitioners'
optional reply brief is due 9/17/02. [02-71249] (tm) [02-71249]
5/16/02 Filed attorney for Petitioner Civil Appeals Docketing Statement
served on 5/14/02 (to CONFATT) [02-71249] [02-71249] (tm) [02-71249]
5/16/02 Filed Petitioner Public Citizen's emergency motion to consolidate
petitions for review; served on 05/16/02. (MOATT) [02-71249] [4433427] (govt
telephonically informed court that opp will be filed) (dv) [02-71249]
5/20/02 Filed notice of appearance of Andrew C. Mergen and John L. Smeltzer
(Withdrew as counsel: attorney Robert Plocki for DOT) [02-71249] (dv) [02-71249]
5/20/02 Filed Respondent DOT response opposing emergency motion to consolidate
cases; served on 05/17/02. (MOATT) [4433427-1] [02-71249] (dv) [02-71249]
5/20/02 Filed Petitioner's reply to response in support of emergency motion
to consolidate petitions for review and expedite proceedings; served on
05/20/02. (MOATT) [02-71249] (dv) [02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/22/02 Filed Order (Dep Clk: PROMO/cb) Petrs' opposed mtn to consolidated
Nos. 02-70986 and 02-71249 is GRANTED. Petrs' opposed mtn to expedite is
GRANTED IN PART. The following schedule shall govern both petitions. The
records remain due 5/28/02; the opening brf(s) shall be due 6/19/02; the
Govt's brf is due 7/19/02; the optional reply brf(s) shall be due 14 days
from svc of the ans brf. The provisions of 9th Cir. Rule 31-2.2(a) shall
not be applicable to these cases; any Rule 31-2.2(b) mtn is strongly disfavored.
The provisions of 9th Cir. Rule 28 -4 as they apply to continances are also
inapplicable to these cases. Petrs are reminded of the ct's preference for
joint brfs. (cite) The cases shall be placed on the next available calendar
after the filing of the ans brf. Petrs are informed that the provisions
of 9th Cir. Rule 27-3 are not intended for application to requests for proceduaral
relief. (c.c. Calendar Unit) [02-70986, 02-71249] (af) [02-70986 02-71249]
5/28/02 Filed certified list in lieu of record on appeal; served on 05/24/02.
(RECORDS) [02-71249, 02-70986] [02-71249, 02-70986] (dv) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
5/31/02 Filed Petitioner-Intervenor Natural Resources' motion for intervene
on behalf of petrs; served on 5/31/02. (WIP/PROMO/tah) [02-70986, 02-71249]
(af) [02-70986 02-71249]
6/7/02 Filed Federal Respondent's response to mtn to intervene as petrs'
and mtn to recon ct's order dated 5/9/ and 5/22/02; served on 6/6/02. (WIP/PROMO-tah)
[02-70986, 02-712 49] (af) [02-70986 02-71249]
6/10/02 Filed Petitioners' response to resps' request to reconsider expedited
proceedings; served on 6/10/02. (WIP/PROMO-tah) [02-70986, 02-71249] (af)
[02-70986 02-71249]
6/14/02 Filed Order (Appellate Commissioner) The mtn of the Natural Resources
Defense Council and the Planning and Conservation League for leave to intervene
on behalf of petrs is GRANTED. The response to the mtn to intervene includes
a request for an order requiring petrs and intvns to file a joint brf. Resps'
request is DENIED. However, the parties are reminded of the ct's strong
preference for a joint brf. (cite) Resps are reminded that under 9th Cir.
Rule 28-4, they may request an enlargement of brf size. Resps' request for
recon of the provisions of 5/9/ and 5/22/02 orders regarding ext. of time
is DENIED. (PROMO) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
6/19/02 Filed original and 15 copies of Petitioners' CONSOLIDATED opening
brief (Informal: no) 52 pages and five excerpts of record in 2 volumes;
served on 6/19/02. [02-70986, 02-71249] (af) [02-70986 02-71249]
6/25/02 Filed Original and 15 copies People of the State in 02-70986's brief
of 31 pages; served on 6/24/02. [02-70986, 02-71249] (af) [02-70986 02-71249]
7/8/02 Received Respondent Dept. of Transporta-tion 02-70986 letter dated
7/1/02 re: . . . This requests that you amend your svc lists. 1st, on Nos.
02-70986 and 02-71249 delete the Secretary and the Administrtor, Nat'l Highway
Traffic Safety Admin. . . 2nd, on No. 02-70303 add, Ass. Chief Csl for litigation,
Nat'l Highway Traffice Safety Admin, Rm 5219, Mail Code NCC-10, 400 7th
St, SW, WA, DC 20590. [02-70986, 02-71249] (af) [02-70986 02-71249]
7/15/02 Filed Mtn of Resps' and Order (Dep Clk: PROMO/tah) The federal resps'
mtn for an enlargement of brf size for the ans brf is GRANTED. The movants
may file an ans brf not to exceed 15,400 words. The briefing schedule is
unchanged. This order was issued prior to the expiration of time
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
within which a response may be filed. (cite) (Motion recvd 7/12/02) (phoned
Atty Smeltzer for movant) [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
7/22/02 Filed Original and 15 copies respondent Dept. of Transportation
Federal Motor Carrier Safety Admin.'s 70 pages brief, 5 Sup Excerpts of
Record in 1 vol; served on 7/19/02. [02-70986, 02-71249] (af) [02-70986
02-71249]
7/25/02 Received Amicus ATA Litigation in 02-70986, in 02-71249's brief
in 15 copies of 30 pages; served on 7/24/02. (REFERRED TO MERITS PNL per
7/31/02 order) [02-70986, 02-71249] (af) [02-70986 02-71249]
7/25/02 Filed Amicus ATA Litigation's mtn for leave to file amicus curiae
in support of resps; served on 7/24/02. (RECORDS FOR MERITS PNL per 7/31/02
order) [02-70986, 02-71249] (af) [02-70986 02-71249]
7/31/02 Filed Order (Dep Clk: PROMO/cag) Ata Litigation Center, Inc.'s mtn
for leave to file amicus curiae in spport of resps, the proposed brf and
any related filing shall be REFERRED FOR DISPOSITION TO THE PNL that considers
the merits of the cs.
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
ANY FUTURE MTNS TO FILE A FRIEND OF THE CT BRF SHALL BE TREATED IN THE SAME
FASHION. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
8/2/02 Filed Original and 15 copies of Petitioners' CONSOLIDATED reply brief
(Informal: no) 34 pages; served on 8/2/02. (Calendar Unit) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/2/02 Filed Petitioners' mtn for leave to file evidence in support of standing;
served on 8/2/02. (Calendar Unit) [02-70986, 02-71249] (af) [02-70986 02-71249]
8/2/02 Received Petitioners' evidence in support of standing; served on
8/2/02. (mtn for leave to file pending) (Calendar Unit) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/2/02 Filed Petitioner-Intervenor Natural Resources' mtn for leave to file
evidence in support of standing; served on 8/2/02. (Calendar Unit) [02-70986,
02-71249] (af) [02-70986 02-71249]
8/6/02 Filed Petitioner-Intervenor Natural Resources' mtn to correct "Intervenor-Petrs'
mtn for leave to file evidence in support of standing"; served on 8/6/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
8/7/02 CALENDARED: San Francisco October 8, 2002 9:00 a.m. Courtroom 2 [02-70986,
02-71249] (mw) [02-70986 02-71249]
8/19/02 Filed Petrs' International Brotherhood of Teamsters, CA Labor Federation,
and Environmental Law Foundation's mtn for additional time for oral argument;
served on 8/19/02. (faxed to PANEL) [02-70986, 02-71249] (af) [02-70986
02-71249]
8/29/02 Filed Order (Dep Clk: DOCKETING/hh) Petrs' and Intervenors' Mtns
for Leave to File Evidence in Support of Standing are hereby GRANTED. (served
PANEL; phoned csls at 2:30 p.m.; c.c. Front Counters) [02-70986, 02-71249]
(af) [02-70986 02-71249]
8/29/02 Filed Petrs' evidence in support of standing; served on 8/2/02.
(per 8/29/02 order) [02-70986, 02-71249] (af) [02-70986 02-71249]
9/4/02 Filed Amicus People of the State's mtn to present oral argument in
supprt of petrs' petition for review and emergency mtn; served on 9/3/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
9/12/02 Received Adrianna Quintero Somaini for Petitioner-Intervenor Natural
Resources' ltr dated 9/12/02 re: respectfully write to call to the attention
of the pnl a rpt from the
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
U.S. Environmental Protection Agency, entitled "FINAL HEALTH ASSESSMENT
DOCUMENT FOR DIESEL ENGINE EXHAUST." . . . (faxed to PANEL)
[02-70986, 02-71249] (dv) [02-70986 02-71249]
9/23/02 Filed order (Dep Clk/hh) The mtn for leave to file an amicus curiae
brf by ATA Litigation Center, Inc. is GRANTED. Petrs' mtn for add'l time
for oral argument is DENIED without prejudice. The mtn by the People of
State of CA as amicus curiae for add'l time to present oral argument is
DENIED; however, petrs may choose to allocate a portion of their time to
the Atty General. (PHONED @1:20 pm) [4493704-1] [4509949-1] [4522553-1]
[02-70986, 02-71249] (ea) [02-70986 02-71249]
9/23/02 Filed orig & 15 copies ATA Litigation's amicus curiae brf of
30 pgs; served on 7/24/02. (PREVIOUSLY REC'D) [02-70986, 02-71249] (ea)
[02-70986 02-71249]
9/30/02 Received Petrs' additional citations in
02-70986, 02-71249; served on 9/30/02 (faxed to PANEL; hand delivered to
S.F Chambers; c.c. ctrroom dep/tu) (Rec'd in docketing on 10/2/02) [02-70986,
02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
10/8/02 ARGUED AND SUBMITTED TO Dorothy W. NELSON, Michael D. HAWKINS, Kim
M. WARDLAW [02-70986, 02-71249] (tu) [02-70986 02-71249]
10/22/02 Received Petrs' additional citations, served on 10/22/02 (faxed
to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/2/02 Received Petrs' additional citations, served on 12/1/02 (faxed to
PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/2/02 Filed Petitioners' EMERGENCY mtn for stay under Cir. R. 27-3 declaration
of Jonathan Weissglass; served on 12/2/02 (faxed and Fedex to PANEL) [02-70986,
02-71249] (af) [02-70986 02-71249]
12/2/02 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW)
Resps shall file their opp, if any, to Petrs' emergency stay mtn by Wed,
12/4/02. Each side file a supp brf addressing the effect of the President's
Memo of 11/27/02 modifying the Mexican-domiciled motor carrier moratorium,
(cite), on the issues presented in this cs. Brfs must be filed on or before
Fri, 12/13/02, and shall be no longer than 15 pgs in length. It is so ORDERED.
(served PANEL; phoned and faxed to parties at 4:15p.m.; c.c. Front Counter)
[02-70986, 02-71249] (af) [02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
12/3/02 Received notice of Intervenors' from Petitioner-Intervenor Natural
Resources Defense Council and the Planning and Convervation League in 02-70986,
in 02-71249 notice of joinder in petrs' emergency mtn for stay under Cir.
R. 27.3; served on 12/3/02. (faxed to PANEL) (af) [02-70986
02-71249]
12/4/02 Filed Amicus People of the State in 02-70986, in 02-71249's brf
in support of petrs' emergency mtn for stay; served on 12/4/02. (faxed to
PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/4/02 Filed ****FAXED**** Respondents' response in opposition to petrs'
mtn for an emergency stay under Cir. R. 27-3; served on 12/4/02. (faxed
to PANEL) (hard copies rec'd 12/5/02) [02-70986, 02-71249] (af)
[02-70986 02-71249]
12/5/02 Filed Petrs' reply in support of mtn for stay; served on 12/5/02.
(faxed to PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/6/02 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW)
Petrs' Emergency Mtn for Stay under Cir. R. 27-3 is taken under submission.
Resps shall provide this Ct with immediate notice upon
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
the occurrence of any of the following events: (1) the completion of the
negotiations between Resps and the Mexican gov't on a Memo of Understanding
to establish protocols for U.S. inspectors' operations in Mexico; (2) the
scheduling of FMCSA's first safety audit of a Mexico-domiciled motor carrier;
or (3) the publication of notice that any such carrier has successfully
passed such as audit. To reiterate our order of 12/2/02, simultaneous sup
briefing addressing the effect of the President's Memo of 11/27/02 modifying
the Mexican-domiciled motor carrier moratorium, (cite), on the issues presented
in this cs shall be filed on or before Friday, 12/13/02. It is so ORDERED.
(served PANEL; phoned and faxed to csls at 4:00p.m.; c.c. Front Counter
and C. Catterson by hh) [02-70986, 02-71249] (af) [02-70986 02-71249]
12/13/02 Filed ***FAXED*** Original and 0 copies Respondents' supplemental
brief of 16 pages, served on 12/13/02. (total of 3543 words) (faxed to PANEL)
(ORIGINAL and 15 Copies rec'd 12/16/02; PANEL) [02-70986, 02-71249] (af)
[02-70986 02-71249]
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
12/13/02 Filed Original and 15 copies Petitioners and Intervenors' JOINT
Supplemental brf of 14 pgs pursuant to order of the ct; served 12/13/02.
(faxed and served PANEL) [02-70986, 02-71249] (af) [02-70986 02-71249]
1/13/03 Received Petrs' in 02-70986, in 02-71249 additional citations, served
on 1/13/03. (faxed to PANEL) [02-70986, 02-71249] (af)
[02-70986 02-71249]
1/16/03 FILED OPINION: GRANTED AND REMANDED. (Terminated on the Merits after
Oral Hearing; Granted and Remanded; Written, Signed, Published. Dorothy
W. NELSON; Michael D. HAWKINS; Kim M. WARDLAW, author.) FILED AND ENTERED
JUDGMENT. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
2/26/03 Filed Federal Motor in 02-70986, in 02-71249 motion for an ext.
of time in which to seek rehearing or rehearing en banc; served on 2/24/03.
(faxed to KMW) [02-70986, 02-71249] (af) [02-70986 02-71249]
2/28/03 Filed Order (Kim M. WARDLAW,) Pursuant to Resps' mtn, the Ct grants
Resp an additional seven days in which to file a petition for rehearing
or rehearing en banc.
_________________________________________________
DATE PROCEEDINGS
_________________________________________________
Resps may file any such petitions on or before 3/10/03. NO FURTHER EXTS
WILL BE GRANTED. It is so ordered. (served PANEL; phoned csls at 11:30a.m.;
c.c. Front Counter) [02-70986, 02-71249] (af) [02-70986 02-71249]
3/10/03 Filed Original and 50 copies of Federal Resps' petition for panel
rehearing and petition for rehearing en banc in 18 pgs; served on 3/10/03.
(total of 4198 words) (PANEL and all active judges) [02-70986, 02-71249]
(af) [02-70986 02-71249]
4/10/03 Filed Order (Dorothy W. NELSON, Michael D. HAWKINS, Kim M. WARDLAW,)
The pnl has voted unanimously to deny the petition for pnl rehearing. Judges
Hawkins and Wardlaw have voted to deny the petition for en banc rehearing,
and Judge Nelson has so recommended. The full ct has been advised of the
petition for rehearing en banc and no active judge has requested a vote
on whether to rehear the matter en banc. (cite) The petition for rehearing
and for rehearing en banc are DENIED. [02-70986, 02-71249] (af) [02-70986
02-71249]
4/18/03 MANDATE ISSUED. Costs taxed against respondents in the amount of
$3370.80. [02-70986, 02-71249] (af) [02-70986 02-71249]
* * * * *
Regulatory Analysis and
Regulatory Flexibility Analysis
FMCSA-98-3297-[287]
FMCSA-98-3298-[260]
FMCSA-98-3299-[263]
FMCSA-01-10886-[2]
FMCSA-01-11060-[2]
Part 365, Part 368, and Part 385 Rules
Mexican Carrier Provisions
Federal Motor Carrier Safety Administration
December 2001
* * * * *
[4] Approximately 190 Mexican motor carriers currently have OP-1(MX) forms
pending with the DOT.
Mexican carriers that operate within the U.S. municipalities and commercial
zones along with the U.S.-Mexico border must file form OP-2. The current
version of the OP-2 form asks detailed questions about the carrier's operations,
location, and equipment, and the FMCSA estimates that it takes approximately
two hours for a carrier to complete (OMB Approval No. 2126-0010). Approximately
10,100 active Mexican carriers currently have OP-2 authority. This does
not mean that all these carriers are currently operating in the United States,
just that they are legally able to do so.
The ICC also developed an OP-1(MX) form, for Mexican carriers to apply for
authority to operate beyond the four border States. This form is similar
to the OP-1 form long used by the former ICC for domestic for-hire carriers.
While a number of Mexican carriers submitted these forms, they were not
processed by the DOT, pending the outcome of the delay in implementing NATA.
The OP-1(MX) is similar to the OP-2 form, and also takes two hours to complete
(OMB Approval No. 2126-0016).
Even without the broader border opening envisioned by NAFTA, trade between
the United States and Mexico has skyrocketed the last few years. Along with
the growth in trade has come an increase in truck traffic crossing the broder.
According to the Federal Reserve Board of Dallas, trade with Mexico reached
$196.6 billion in 1999, up more than 141 percent from 1993 (Vargas). The
growth in trade appears to have accelerated in 2000, according to data from
the Bureau of Economic Analysis reported by Economic Data Resources. Northbound
truck crossings have grown almost 90 percent from fiscal year (FY) 1993
to FY 2000, rising from 2.4 million to 4.55 million crossings per year (Economic
Data Resources, 2000).
The growth in trade and traffic has been accompanied by increasing concern
about the safety of Mexican motor carriers operating in the United States.
Several government reports indicate that many Mexican motor carriers are
unlawfully operating outside the commercial zone, and that they have a higher
out-of-service (OOS) rate than domestic carriers. The DOT's Office of the
Inspector General (IG) issued a report in November 1999 detailing safety
and operational problems with Mexican motors carriers and the Department's
oversight of there carriers. The IG found that 41 percent of 23,300 Mexican
vehicles inspected at the border or in the commercial zones in FY 1998 were
placed OOS. The IG also estimated that approximately 130 Mexican motor carriers
may be operating illegally outside the border States, and 505 in the border
States but outside the commercial zones (Office of the Inspector General).
The General Accounting Office (GAO) noted in 1997 that Mexican trucks inspected
at the border had an average monthly OOS rate of 45 percent between January
and December of 1996, compared to a 28 percent rate for domestic carriers
during fiscal year 1995 (General Accounting Office).
* * * * *
FMCSA
FINDING OF NO SIGNIFICANT IMPACT
FOR
FMCSA-98-3297
FMCSA-98-3298
FMCSA-98-3299
FMCSA-01-10886
FMCSA-01-11060
Revision of Regulations and Application Form for Mexico-Domiciled Motor
Carriers To Operate in United States Municipalities and Commercial Zones
on the United States-Mexico Border
Application by Certain Mexico-Domiciled Motor Carriers To Operate Beyond
United States Municipalities and Commercial Zones on the United States-Mexico
Border
Safety Monitoring System and Compliance Initiative for Mexico-Domiciled
Motor Carriers Operating in the United States
Parts and Accessories Necessary for Safe Operation; Certification of Compliance
with Federal Motor Vehicle Safety Standards (FMVSSs)
These proposed actions have been thoroughly reviewed by the Federal Motor
Carrier Safety Administration (FMCSA) and it has been determined, by the
undersigned, that these proposed actions would have no significant effect
on the human environment.
This finding of no significant impact (FONSI) is based on the attached FMCSA
prepared Environmental Assessment (EA) which has been determined to adequately
and accurately discuss the environmental issues, impacts, and alternatives
of the proposed actions, and provides sufficient evidence and analysis for
determining that an environmental impact statement is not required. The
EA is attached to this document and is hereby incorporated by reference
in this FONSI.
[1-16-02] /s/ DALE M. JENNIFER, for
Date DALE M. JENNIFER
Charles Rombro, Environmental
Project Manager, FMCSA
I have considered the information contained in the EA (and any other appropriate
environmental documentation), which is the basis for this FONSI. Based on
the information in the EA and this FONSI document, I agree that the proposed
actions as described above, and in the EA, will have no significant impact
on the environment.
[1-16-02] /s/ [ILLEGIBLE]
Date Joseph M. Clapp, Administrator
FMCSA ENVIRONMENTAL ASSESSMENT
FOR
Revision of Regulations and Application Form for Mexico-Domiciled Motor
Carriers To Operate in United States Municipalities and Commercial Zones
on the United States-Mexico Border
Application by Certain Mexico-Domiciled Motor Carriers To Operate Beyond
United States Municipalities and Commercial Zones on the United States-Mexico
Border
Safety Monitoring System and Compliance Initiative for Mexico-Domiciled
Motor Carriers Operating in the United States
Parts and Accessories Necessary for Safe Operation; Certification of Compliance
with Federal Motor Vehicle Safety Standards (FMVSSs)
This Federal Motor Carrier Safety Administration's (FMCSA) environmental
assessment (EA) was prepared in compliance with the National Environmental
Policy Act of 1969, as amended (42 U.S.C. 4321-4347, hereinafter "NEPA")
and the regulations for implementing NEPA issued by the Council of Environmental
Quality Regulations, November 29, 1978 (49 C.F.R. parts 150-1508), and in
accordance with the Department of Transportation's (DOT) Order 5610.lC,
Procedures for Considering Environmental Impacts, September 18, 1979, as
amended July 3, 1982, and July 30, 1985.
This environmental assessment serves as a concise public document to briefly
provide sufficient evidence and analysis for determining the need to prepare
a finding of no significant impact or to assist the FMCSA in determining
whether there is a need to prepare an environmental impact statement.
This environmental assessment concisely describes the proposed actions,
the need for the proposal, identifies the alternatives, and determines which
aspects of the proposed actions and alternatives have potential for social,
economic, or environmental impact. This EA also contains a comparative analysis
of the actions and alternatives, a statement of the environmental significance
of the preferred alternative, and a list of the agencies and persons consulted
during EA preparation.
1-16-02 [Illegible Signature]
Date Charles Rombro, Environmental Project
Manager, FMCSA
1-16-02 [Illegible Signature]
Date Julie Anna Cirillo, Chief Safety Officer,
FMCSA
In reaching my decision/recommendation on the FMCSA's proposed action, I
have considered the information contained in this EA on the potential for
environmental impacts.
1-16-02 [Illegible Signature]
Date Joseph M. Clapp, Administrator, FMCSA
[Seal Omitted]
US. Department of Transportation
Federal Motor Carrier Safety Administration
Safety Oversight for Mexico-Domiciled Commercial Motor Carriers
Final Programmatic Environmental
Assessment
January 2002
Prepared by
John A. Volpe National Transportation Systems
Center
Table Of Contents
List of Figures
[ ]
List of Acronyms
[ ]
1. PURPOSE AND NEED FOR ACTION
[ ]
1.1. Introduction
[ ]
1.2. Background
[ ]
1.3. Need for Action
[ ]
1.4. Scope of Analysis
[ ]
1.5. Government-Wide Coordination
[ ]
2. PROPOSED ACTION AND ALTERNATIVES
[ ]
2.1. Overview of Alternatives
[ ]
2.2. Applications for Operating Authority
[ ]
2.2.1 Baseline Scenario - Moratorium Re-
tained with Current Application Forms
[ ]
2.2.2 No Action - Moratorium Modified
with Current Application Forms
[ ]
2.2.3 Proposed Action - Moratorium
Modified with Revised Application Forms
[ ]
2.3 Safety Monitoring for Mexico-Domiciled
Motor Carriers
[ ]
2.3.1 Baseline Scenario - Moratorium
Retained with Current Safety Monitoring
Monitoring Program
[ ]
2.3.2 No Action - Moratorium Modified
with Current Safety Monitoring Program
[ ]
2.3.3 Proposed Action - Moratorium
Modified with Revised Safety Monitoring
System for Mexico-Domiciled CMC
[ ]
3. AFFECTED ENVIRONMENT
[ ]
3.1 Description of United States Highway
Transportation System
[ ]
3.2 Description of United States and Border
Zone Resources
[ ]
3.2.1 Transportation
[ ]
3.2.2 Public Health and Safety
[ ]
3.2.3 Air Quality
[ ]
3.2.4 Noise
[ ]
3.2.5 Socioeconomics
[ ]
3.2.6 Other Resources
[ ]
4. ENVIRONMENTAL CONSEQUENCES
[ ]
4.1 Transportation
[ ]
4.1.1 Applications for Operating
Authority
[ ]
4.1.2 Safety Monitoring for Mexico-
Domiciled Motor Carriers
[ ]
4.1.3 Summary of Impacts of the Proposed
Action on Transportation
[ ]
4.2 PUBLIC SAFETY AND HEALTH
[ ]
4.2.1 Applications for Operating
Authority
[ ]
4.2.2 Safety Monitoring for Mexico-
Domiciled Motor Carriers
[ ]
4.2.3 Summary of Impacts of the Proposed
Action on Public Safety and Health
[ ]
4.3. AIR QUALITY
[ ]
4.3.1 Applications for Operating
Authority
[ ]
4.3.2 Safety Monitoring for Mexico-
Domiciled Motor Carriers
[ ]
4.3.3. Summary of Impacts of the Proposed
Action and Air Quality
[ ]
4.4. NOISE
[ ]
4.4.1 Applications for Operating
Authority
[ ]
4.42 Safety Monitoring Program for New
Applicants
[ ]
4.43 Summary of Impacts of the Proposed
Action on Noise
[ ]
4.5. SOCIOECONOMICS
[ ]
4.5.1 Applications for Operating
Authority
[ ]
4.5.2 Safety Monitoring for Mexico-Dom-
iciled Motor Carriers
[ ]
4.5.3 Summary of Impact of the Proposed
Action on Socioeconomics
[ ]
5. MITIGATION AND BEST MANAGEMENT
PRACTICES
[ ]
6. LIST OF PREPARERS AND REVIEWERS
[ ]
7. REFERENCES
[ ]
LIST OF APPENDICES
[ ]
Appendix A - Definition of commercial motor
vehicles and Description of Roadside
Inspections
[ ]
Appendix B - Roles of Selected Agencies With
Environmental and Public Health Over-
sight Authority Over the Operation of
CMC in the United States
[ ]
Appendix C - Air Quality
[ ]
Appendix D - Environmental Screening Pro-
cess
[ ]
Appendix E - Noise Emissions Analysis
[ ]
Appendix F - Selected NAFTA Environmental
References
[ ]
Appendix G - Socioeconomic Demographic
Numbers
[ ]
Appendix H - Proposed Forms OP-2 and
OP-1 (MX)
[ ]
List of Tables
Table 2-1: Requisite Conditions for each Alter-
native
[ ]
Table 2-2: Proposed Action Alternative Contents
[ ]
Table 2-3: New OP-2 Applications for Border Zone
Operating Authority from Mexico-Domiciled
CMC
[ ]
Table 3-1: NAAQS Attainment Status for United
States - Mexico Border Counties
[ ]
Table C-1 NAAQS as of December 2000
[ ]
Table C-2 Criteria pollutant description and poten-
tial health effects
[ ]
Table C-3 Source contribution to emissions for
the United States during 1999
[ ]
Table C-4 Total emissions from on-road mobile
sources in 1999
[ ]
Table C-5 Percent change in emissions and concen-
trations in the U.S. (1980-1999)
[ ]
Table C-6 Estimated total 1997 vehicle emissions
by fuel type
[ ]
Table C-7 Total annual emissions from operation
of Mexican CMV under the baseline scenario
[ ]
Table C-8 Total annual emissions from operation
of Mexican CMV under the No Action Alter-
native
[ ]
Table C-9 Total annual emissions from operation
of Mexican CMV under the proposed action
alternative
[ ]
Table C-10 Total annual emissions from inspections
of Mexican CMV under the baseline scenario
[ ]
Table C-11 Total annual emissions from inspections
of Mexican CMV under the No Action Alter-
native
[ ]
Table C-12 Total annual emissions from inspections
of Mexican CMV under the proposed action
alternative
[ ]
Table D-1 Resource Consumption from Paper
Production
[ ]
Table G-2 Population Breakdown For Border
Cities
[ ]
Table G-3 Northbound Crossings From Mexico
1984 to 2000
[ ]
List of Figures
Figure 3-1: Mexico Imports into the United States
between 1997 and 2000, as Measured by Weight
(United States Short Tons)
[ ]
Figure 3-2: Trend in the Total Number of North-
bound Truck Crossings into the United States
from Mexico between FY 1992 and 2000
[ ]
Figure 3-3: Change in Northbound Truck Cross-
ings at the Seven Busiest Ports of Entry for FY
[ ]
1992, 1996 and 2000
[ ]
Figure 3-4: General Population versus Hispanic
Population in border crossing cities
[ ]
Figure 3-5: Percent Hispanic Population compared
to average income for border crossing cities and
the United States total
[ ]
Figure 4-1: Distribution of NOx and PM Emissions
from On-Road Sources and Mexican, United
States and Canadian CMV, FY 2002 as Percent
of Weight
[ ]
Figure E-1 National noise emission levels in tnm
[ ]
Figure E-2 Heavy trucks, acoustically hard sur-
face
[ ]
Figure E-3 Heavy trucks, acoustically hard surface,
close-in
[ ]
Figure E-4 Buses, acoustically hard service
[ ]
Figure E-5 Buses, acoustically hard service
[ ]
LIST OF ACRONYMS
CAA - Clean Air Act
CEQ - Council on Environmental Quality
CFR - Code of Federal Regulations
CMC - commercial motor carrier
CMV - commercial motor vehicle
CO - carbon monoxide
CVSA - Commercial Vehicle Safety Alliance
dB - decibels
DOT - Department of Transportation
EO - Executive order
EPA - Environmental Protection Agency
ESA - Endangered Species Act
FHWA - Federal Highway Administration
FMCSA - Federal Motor Carrier Safety Administration
FMVSS - Federal Motor Vehicle Safety Standards
GAO - General Accounting Office
GHG - greenhouse gases
ICC - Interstate Commerce Commission
NAAQS - National Ambient Air Quality Standards
NAFTA - North American Free Trade Agreement
NEPA - National Environmental Policy Act
NHPA - National Historic Preservation Act
NHTSA - National Highway Safety Administration
NO2 - nitrogen dioxide
NOx - nitrogen oxides
OIG - Office of Inspector General
OMCS - Office of Motor Carrier Safety
Pb - lead
PEA - Programmatic Environmental Assessment
PM - particulate matter
TNRCC - Texas Natural Resource Conservation
Commission
USAF - United States Air Force
USC - United States Code
USFWS- Unites State Fish and Wildlife Service
VOC - volatile organic compounds
VMT - vehicle-miles of travel
1. PURPOSE AND NEED FOR ACTION
1.1. INTRODUCTION
The National Environmental Policy Act of 1969 (NEPA)1 and the Council on
Environmental Quality's (CEQ) implementing regulations2 establish policies
and procedures that ensure environmental information is available to decision
makers, regulatory agencies, and the public before Federal actions are implemented.
The Federal Motor Carrier Safety Administration (FMCSA) with the cooperation
of the John A. Volpe National Transportation Systems Center prepared this
Programmatic Environmental Assessment (PEA) for the purpose of analyzing
the potential environmental impacts associated with four proposed rulemakings.
This PEA follows the procedures established by the United States Department
of Transportation (DOT)3 to implement NEPA, pursuant to the CEQ regulations.
The focus of this PEA concerns four proposed rulemakings that relate to
the safety of Mexico-domiciled commercial motor carrier (CMC) operations
in the United States. CMC include operators of trucks and buses. The first
two of these rules would revise the application process for Mexico-domiciled
CMC to improve FMCSA's ability to identify high-risk CMC and track CMC performance.
The third rule would establish a safety monitoring system for Mexico-domiciled
CMC that includes mandatory safety audits of CMC records and targeted roadside
inspections of CMC commercial motor vehicles (CMV). (Refer to Appendix A
for the definition of CMV.) The fourth rule would empower FMCSA to enforce
the current National Highway Traffic Safety Administration (NHTSA) requirement
that every CMV operated within the United States display a label certifying
that it complies with all applicable Federal Motor Vehicle Safety Standards
(FMVSS) in effect on the date of manufacture of the vehicle. These rules
together form the Proposed Action of this PEA.
This PEA will focus only on the potential environmental impact and safety
of operation implications of the proposed actions and alternatives based
on: (1) the change in the number of Mexico-domiciled CMC receiving certificates
of operating authority pursuant to the revised application forms (i.e.,
OP-2 and OP-1 (MX) Forms), and the associated change in the number of Mexican
CMV operating in the United States; and (2) the change in the number, method,
and frequency of inspections conducted on Mexican CMV operating in the United
States. The purpose of this PEA is to assist FMCSA and the public in understanding
the potential environmental consequences, if any, of the Proposed Action
and alternatives. The PEA will be used by FMCSA to determine whether the
proposed changes to the application process for Mexico-domiciled CMC and
inspections system for Mexican CMV will result in significant environmental
impacts. The PEA addresses the purpose and need for the Proposed Action,
describes the Proposed Action and alternaives to the action, analyzes the
potential environmental consequences of the proposed action and alternatives,
and describes mitigation strategies and best management practices. This
PEA is not intended to be a scientific document. Where appropriate, more
detailed information and analysis is provided in one of the appendices to
the PEA.
1.2. BACKGROUND
Prior to 1982, Mexico-domiciled CMC could apply for authority to operate
within the United States by making an application for such authority to
the former Interstate Commerce Commission (ICC). Under the Bus Regulatory
Reform Act of 1982,4 Congress imposed a two-year moratorium on the issuance
of new certificates of United States operating authority to CMC domiciled
in a contiguous foreign country, or owned or controlled by persons of a
contiguous foreign country. The Act authorized the President to remove or
modify the moratorium if the President determined that such action was in
the national interest. The Act was developed in response to complaints that
neither Mexico nor Canada were permitting United States CMC the same access
to their markets as Mexican and Canadian CMC had to United States markets.
Through the ICC Termination Act of 1995 (ICCTA), Congress, among other things,
amended the President's authority under the 1982 Act by authorizing the
President to remove or modify the moratorium upon the President's determination
that such action is consistent with United States obligations under a trade
agreement or with United States transportation policy.
While the trade issues with Canada were resolved quickly, resulting in the
moratorium being modified for Canada-domiciled CMC, the trade issues with
Mexico were not addressed until the North American Free Trade Agreement
(NAFTA) was negotiated in the early 1990s. Legislative and executive extensions
have maintained the moratorium for most Mexico-domiciled CMC since 1982.
However, the President has twice exercised his statutory authority and has
modified the moratorium pursuant to the NAFTA. First, in 1994, the President
modified the moratorium to allow certificates of authority for the operation
in foreign commerce of Mexico-domiciled charter and tour buses throughout
the United States. Second, in 2001, the President modified the moratorium
to allow new certificates of authority for the operation of Mexican-owned
or controlled, United States-domiciled CMC engaged in the transportation
of passengers and of international cargo.
A number of Mexico-domiciled CMC have been permitted to operate in the United
States because they are not covered by the moratorium. The moratorium only
applies to certificates of new operating authority for operations beyond
municipalities and commercial zones adjacent to Mexico in Texas, New Mexico,
Arizona, and California (herein called the "border zone"). Thus,
Mexico-domiciled carriers that intend to operate only within the border
zone are not barred from receiving operating authority for operations in
those areas, and Mexico-domiciled CMC that had obtained unrestricted operating
authority before the moratorium was enacted may continue to operate throughout
the United States. Additionally, the moratorium does not affect United States-owned,
Mexico-domiciled private carriers, whose services are not for-hire, Mexico-domiciled
CMC of certain commodities and Mexico-domiciled carriers that only traverse
the United States to deliver or pick up cargo or passengers in Canada. Such
carriers have never been restricted to the border zone.
The ICCTA also dissolved the ICC and transferred the authority to issue
new certificates of United States operating authority for CMC and some other
regulatory functions to the Office of Motor Carriers (OMC) of the Federal
Highway Administration (FHWA). The Secretary of Transportation (the "Secretary")
subsequently re-delegated the authority to carry out the duties and powers
related to CMC safety outside of the FHWA to the Director, Office of Motor
Carrier Safety (OMCS).5 On December 9, 1999, the President signed the Motor
Carrier Safety Improvement Act of 1999.6 The new statute established the
FMCSA within the Department of Transportation. Effective January 1, 2000,
the Secretary rescinded the authority previously delegated to the former
OMCS, and delegated this authority to FMCSA.7
The primary mission of the FMCSA is to reduce fatalities and injuries caused
by CMV and to enforce hazardous materials regulations as they relate to
CMC. The FMCSA works to ensure safety in CMC operations by developing and
enforcing safety regulations, targeting high-risk carriers and CMV drivers,
improving safety information systems and CMV technologies, strengthening
CMV equipment and operating standards, and increasing safety awareness.
To accomplish these activities, the FMCSA works with Federal, State, and
local enforcement agencies, the CMC industry, organized labor, safety interest
groups, and others.
The criteria that the FMCSA must apply when evaluating an application for
operating authority in the United States is statutory, and the FMCSA has
no authority to deviate from, or add to, this criteria. Specifically, the
statute requires the FMCSA to issue a certificate of operating authority
to any person whom is deemed willing and able to comply with designated
economic, safety, and financial responsibility requirements.8 These specific
requirements are either set forth in the statute or in regulations specifically
authorized by the statute. Currently, the FMCSA must issue a certificate
of operating authority to any United States or Canadian carrier submitting
an application that indicates the carrier's willingness and ability to meet
the above stated criteria. But for the moratorium, this would also be true
as to Mexican applicants. The Secretary may not even consider complaints
challenging a registration application unless the complaint concerns the
applicant's willingness and ability to comply with the above three DOT regulatory
requirements.9 In the absence of such complaints, or other evidence regarding
noncompliance with these requirements, the Secretary must grant the application.
Consequently, the FMCSA is statutorily precluded from considering environmental
issues in deciding whether to grant applications to provide CMC transportation
in interstate or foreign commerce. Please refer to Appendix B for a list
of selected government agencies with environmental and public health oversight
and regulatory authority.
1.3. NEED FOR ACTION
Under the terms of the NAFTA, the United States, Mexico, and Canada agreed
to remove certain existing barriers to the cross border operations of CMC
(for more information on the environmental review of NAFTA, see references
in Appendix F). The President and Congress committed the United States in
the NAFTA to a timetable for modifying the moratorium that was to allow
Mexico-domiciled CMC engaged in the transportation of international cargo
to operate within the four Border States beginning in December 1995 and
throughout the United States on January 1, 2000. Due to safety concerns,
in December 1995, President Clinton indefinitely delayed the modification
of the moratorium for Mexico-domiciled CMC. In February 2001, a NAFTA arbitral
panel ruled that this action was contrary to the NAFTA. Under the NAFTA,
this ruling meant that Mexico could impose trade sanctions against the United
States unless the United States fulfilled its NAFTA obligations. Shortly
after the panel issued its ruling, President Bush announced his intent to
comply with the terms of the NAFTA in a manner consistent with safety by
modifying the moratorium, pursuant to his statutory authority, once FMCSA
was ready to issue its new regulations governing Mexico-domiciled CMC seeking
United States operating authority. Once the moratorium is modified, the
FMCSA must process Mexico-domiciled CMC applications for authority to operate
throughout the United States.
If the moratorium is modified and the Proposed Action of issuing the four
rules is not taken, the FMCSA would process applications currently on file
from Mexican carriers seeking authority to operate beyond the border zone
applying the same criteria stated in the previous section above. These applications
were submitted on an application form created by the ICC in a 1995 rulemaking.
Until that form is substituted with a different form upon completion of
these rulemakings, it remains the form that Mexico-domiciled CMC must use
to request operating authority beyond the border zone.
In anticipation of the modification of the moratorium, the FMCSA is concerned
that Mexico-domiciled CMC may have difficulty transitioning their operations
to meet United States safety standards. To address this concern, FMCSA proposed
to revise the application process and safety monitoring program currently
in place for Mexico-domiciled CMC. These revisions would help FMCSA ensure
that Mexico-domiciled CMC are willing and able to comply with all United
States safety laws and regulations, prior to receiving a certificate of
operating authority. In addition, the revisions will improve FMCSA' s ability
to monitor Mexico-domiciled CMC operations in the United States. Specifically,
the FMCSA proposes to modify the existing regulatory framework in two general
areas:
( Applications by Mexico-domiciled CMC for authority to operate within the
United States (both within and beyond the border zone), the first two rules;
and
( FMCSA safety monitoring of Mexico-domiciled CMC (including new applicants)
to ensure compliance with safety regulations, the third and fourth rules.
Both of these areas are currently governed by a regulatory scheme that is
administered by the FMCSA. Under this current regulatory scheme, Mexico-domiciled
CMC seeking authority to operate within the border zone may apply for such
authority using existing Form OP-2. Similarly, Mexico-domiciled CMC seeking
authority to operate beyond the border zone may apply for such authority
using the existing Form OP-1(MX) that was created by the ICC in 1995. Finally,
all Mexico-domiciled CMC operating in any part of the United States are
subject to the same inspection and review regime currently in place for
United States and Canadian CMC (FMCSA 2001b).
1.4. SCOPE OF ANALYSIS
This PEA will analyze the potential environmental impacts associated with
the current regulatory framework, and the four proposed rules that would
modify this framework. Initially, this PEA will focus on the effect these
alternatives will have on the number of Mexican CMV operating in the United
States and the number of inspections that will be performed on these vehicles.
Next, the PEA will describe the environment that may be impacted by changes
in the total number of vehicles and inspections. Finally, the PEA will describe
the potential environmental impacts associated with these changes on the
following primary areas of potential concern: Transportation, Public Safety,
Air Quality, Noise, and Socioeconomics.
1.5. GOVERNMENT-WIDE COORDINATION
Regulatory agency involvement is critical in the analysis of the proposed
rulemakings, particularly with regard to NEPA. The FMCSA has coordinated
the development and completion of this PEA to ensure participation and feedback
from the Environmental Protection Agency and the Council on Environmental
Quality.
2. PROPOSED ACTION AND ALTERNATIVES
2.1. OVERVIEW OF ALTERNATIVES
The purpose of this PEA is to assist FMCSA in understanding the potential
environmental consequences of the Proposed Action and alternatives in order
to determine whether they will result in significant environmental impacts.
The analysis involves comparing each alternative to current environmental
conditions to identify the resulting change. In most environmental reviews,
the No Action Alternative provides a good description of the baseline, since
it describes the current environmental conditions and the environmental
consequences of maintaining the status quo. However, in the current situation,
the anticipated Presidential order to modify the moratorium constitutes
an intervening event that will modify the baseline conditions. Recognizing
the influence of this intervening event, FMCSA has identified three probable
scenarios that this PEA must consider. The Baseline Scenario consists of
the continued use of existing FMCSA regulations with the Moratorium remaining
unmodified. The second scenario is the No Action Alternative, whereby the
use of the existing FMCSA regulations continues and the Presidential order
to modify the Moratorium is implemented. The third scenario consists of
the Proposed Action Alternative, whereby the four rules proposed by FMCSA
are promulgated and the Presidential order to modify the Moratorium is implemented.
Table 2-1 shows the requisite conditions that apply for the three scenarios
considered in this PEA.
Table 2-1: Requisite Conditions for each Alternative
Moratorium Unmodified
Moratorium Modified by Presidential order
No Change to Current FMCSA Regulations
Baseline
No Action
FMCSA Regulations Revised by
Proposed Rules
N/A
Proposed Action
FMCSA also recognizes that there is a fourth scenario whereby the proposed
rules are promulgated with the moratorium remaining in effect; however,
this scenario has been dismissed from further analysis for several reasons.
First, as stated in Section 1.3 describing the Need for Action, the President
has announced his intent to comply with the terms of NAFTA. Second, although
the President could modify the moratorium after the FMCSA completes this
rulemaking, the period of time between the issuance of the final rules and
the moratorium modification would be very short, and the rules relating
to Mexican carrier operations beyond the border zone would, in any event,
have no practical impact until the moratorium is modified. Third, the analysis
of the other three scenarios will capture the moratorium's effect on the
proposed rules, and any additional analysis of this scenario would thus
be redundant.
Immediately prior to the completion of this PEA, the Congress passed the
DOT Appropriations Act for FY 2002. The Act sets forth several conditions
that must by met by the DOT before FMCSA may expend any FY 2002 appropriated
funds to process Form OP-1 (MX) applications. Among the conditions set forth
in the Act are the requirements that FMCSA promulgate rules that implement
the regulatory safety requirements contained in rules 2, 3 and 4 of the
Proposed Action. This section of the Appropriations Act withholds funds
for the processing of Form OP-1 (MX) until the satisfaction by DOT of the
conditions set forth in the Act or upon the expiration of the appropriations
period on September 30, 2002, whichever event occurs first. While the appropriations
hold is in effect, any Presidential order to modify the statutory moratorium
will have no practical effect, since FMCSA would still be prohibited from
processing OP-1 (MX) applications.
As a result, while the appropriations hold is in effect, the No Action Alternative
against which the environmental impacts from the Proposed Action should
be measured is identical to the Baseline scenario described in this document.
Accordingly, to account for this additional scenario, our analysis of environmental
impacts in Chapter 4 will compare the environmental impacts of the Proposed
Action to the impacts associated with both the Baseline and No Action alternative.
This dual analysis will allow the FMCSA to determine whether the Proposed
Action will result in a significant impact to the environment as compared
to a No Action Alternative with or without the appropriations hold in place.
To facilitate the environmental impact discussion in Chapter 4, this chapter
describes each alternative and focuses on the operating conditions that
will result from each alternative. The Proposed Action Alternative consists
of four rules and is divided into two corresponding subsections to facilitate
a separate review of each regulatory area addressed under the Proposed Action
and described in Section 1.3 (see Table 2-2).
The first subsection addresses the application process for operating authority
(rules 1 and 2, including a new pre-authority safety audit for those CMC
operating pursuant to OP-1 (MX) authority). The second subsection addresses
the safety monitoring program for Mexico-domiciled CMC operations (rules
3 and 4, including maintaining a current Commercial Vehicle Safety Alliance
(CVSA) decal). Within each of these subsections, the PEA begins by describing
the Baseline Scenario, followed by the No Action Alternative, and then the
Proposed Action Alternative. Finally, since the Proposed Action is comprised
of the implementation of the four rules, each resource analyzed in Chapter
4 concludes with a discussion of the total potential impact of the two regulatory
sections together in a summary section.
Table 2-2: Proposed Action Alternative Contents
PROPOSED ACTION ALTERNATIVE
Applications for Operating Authority
Rule 1 - Form OP-2 Revised
Rule 2 - Form OP- 1 (MX) Revised, including a new pre-authority safety audit
Safety Monitoring Program for Mexico-
Domiciled CMC *
Rule 3 - Proposed Safety Monitoring System Requirements
Rule 4 - Proposed Certification Label Requirements (FMVSS)
* Also includes maintaining current CVSA decal
For the purposes of this analysis it was assumed that the implementation
of the Proposed Action would not affect the trade volume between the United
States, Mexico, and Canada, nor would it alter existing regulations relating
to the cargo or payloads carried by Mexico-domiciled CMC. Even though actual
resulting trade conditions are at best difficult to quantify, it is expected
that the Presidential order to modify the moratorium could result in changes
in trade volume and operations between the United States and Mexico. As
a result, there could be an increase in the number of Mexican CMV trips
in the United States. The resulting increase would be determined by the
difference between the new Mexican CMV trips and the offset resulting from
the reduction in the number of United States CMV trips that would be replaced
by their Mexican counterparts. However, this and any other associated effects
in trade characteristics would be the result of the modification of the
moratorium and not the implementation of the Proposed Action.
As a result, this PEA will focus only on the potential environmental impact
and safety implications of the proposed actions and alternatives based on:
(1) the change in the number of Mexico-domiciled CMC receiving certificates
of operating authority pursuant to the revised application forms (i.e.,
OP-2 and OP-1 (MX) Forms), and the associated change in the number of Mexican
CMV operating in the United States; and (2) the change in the number, method,
and frequency of inspections conducted on Mexican CMV operating in the United
States.
2.2. APPLICATIONS FOR OPERATING AUTHORITY
This section describes the operating conditions of Mexico-domiciled CMC
within the United States, as the application process affects those conditions.
This section begins by describing current operating conditions under the
Baseline scenario, followed by a description of how those conditions would
change under the No Action and Proposed Action Alternatives.
2.2.1 Baseline Scenario - Moratorium Retained with Current Application Forms
Under current Baseline operating conditions, Mexico-domiciled CMC may apply
for two different types of operating authority. The first is authority to
operate within the commercial zone along the United States-Mexico border,
known as the "border zone." Economic Commercial Zones are established
geographical areas, as outlined or set forth in FMCSA regulations where
interstate commerce is partially exempt from economic regulation.10 The
commercial zones exist throughout the United States and vary in size according
to the population of the base municipality. Although commercial zone CMC
are partially exempt from economic regulation they are still required to
meet the same State safety standards that apply to other motor carriers.
Most of the commercial zones are 20 miles wide or less, but the Rio Grande
Valley zone, including four Texas counties, and the San Diego zones extend
70 miles wide. Mexican CMV operating within the United States commercial
zone must obtain a certificate of registration from the FMCSA. In addition,
approved Mexico-domiciled charter and tour bus companies can operate throughout
the United States, but regular route operations are not allowed. Mexico-domiciled
CMC may request border zone operating authority by submitting the application
Form OP-2.
The second type of authority is required to operate throughout the United
States, beyond the border zone. Mexico-domiciled CMC request this broader
operating authority by submitting the application Form OP-1 (MX). Under
current Baseline conditions, with the moratorium in place, FMCSA is prevented
from processing applications submitted on Form OP-1 (MX), in effect preventing
Mexico-domiciled CMC from receiving authority to operate beyond the border
zone.
Mexico-domiciled CMC may request an application form for operating authority
from either an FMCSA division office or a border inspection station (Muñoz
2001). When a Form OP-2 application is submitted to FMCSA, the agency reviews
the completed form and conducts a background check to determine whether
the applicant carrier is willing and able to comply with all applicable
DOT regulatory requirements. If the FMCSA finds that a carrier is willing
and able to comply with the applicable laws and regulations, the carrier
will receive a Certificate of Registration authorizing it to operate within
the border zone. When a Form OP-1 (MX) application is received by FMCSA,
the form is placed in a file to be processed when the moratorium is modified.
There are approximately 200 Form OP-1 (MX) applications currently on file.
The FMCSA estimates that in 2001, there were 9,500 Mexico-domiciled CMC
and 593,000 United States- and Canada-domiciled CMC with United States operating
authority. These CMC operated approximately 4.5 million CMV in the United
States, including approximately 63,000 Mexican CMV (FMCSA 2001d). The number
of Mexico-domiciled CMC seeking operating authority in the United States
border zone continues to increase every year, as shown in Table 2-3 (FMCSA
2001a). FMCSA has received approximately 1,300 new OP-2 applications per
year over the past four years.
Table 2-3: New OP-2 Applications for Border Zone Operating Authority from
Mexico-Domiciled CMC
Year
Number of Applications Received
1996
611
1997
1,223
1998
1,447
1999
1,377
2000
1,182
Source: FMCSA 2001a
Under a continuation of Baseline Scenario operating conditions, FMCSA expects
to continue receiving and approving approximately 1,300 applications per
year from Mexico-domiciled CMC seeking operating authority in the United
States, resulting in 10,800 Mexico-domiciled CMC with operating authority
in FY 2002. These carriers could operate approximately 71,500 CMV inside
the United States, but would be largely confined to the border zone.
2.2.2 No Action - Moratorium Modified with Current Application Forms
Under the No Action Alternative, FMCSA would retain its current regulations
after the Presidential order to modify the moratorium is issued. Under this
alternative, Mexico-domiciled CMC would continue to apply for operating
authority using either Form OP-2 or OP-l (MX), and FMCSA would be under
the obligation to process both application forms. The FMCSA would grant
operating authority to a Mexico-domiciled CMC-to operate within or beyond
the border zone -based upon a finding that the applicant carrier is willing
and able to comply with applicable CMC safety regulations. Carriers operating
under current certificates of authority would not be required to submit
a new application. In addition, once the Presidential order to modify the
moratorium is implemented, NAFTA bus provisions would be in place, and Mexican
bus companies would be able to apply for authority to carry passengers between
Mexico and the United States over regular routes in scheduled operations.
Also, Mexican bus companies may apply for authority to establish an enterprise
in the United States to provide point-to-point passenger services (FMCSA
2001c). FMCSA expects that the economic opportunities created by the modification
of the moratorium would result in a 9% annual increase in the number of
new applications it would receive from Mexico-domiciled CMC, relative to
the Baseline scenario.
Under the No Action Altemative, FMCSA expects half of the 9,500 Mexico-domiciled
CMC currently operating within the border zone could apply for OP-1(MX)
authority. In addition, FMCSA expects 1,500 new applications for operating
authority could be received and approved by FMCSA in 2002, with approximately
75% of these carriers applying for OP-2 authority and the remaining 25%
applying for OP-1 (MX) authority. Thus, the total number of Mexico-domiciled
CMC operating pursuant to either type of authority in 2002 could be 11,000.
These carriers could operate approximately 73,000 CMV, with 39,000 CMV operated
pursuant to OP-2 authority and 34,000 CMV operated pursuant to OP-1 (MX)
authority.
2.2.3 Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action, the FMCSA would promulgate two new rules. The
first rule would amend 49 CFR parts 368 and 387 and revise Form OP-2, while
the second rule would amend 49 CFR part 365 and revise Form OP-l (MX) (see
Appendix H for a copy of the revised OP-2 and OP-1 (MX) application forms).
Under the amended regulations, all Mexico-domiciled CMC seeking authority
to operate within the border zone would be required to submit the revised
Form OP-2. CMC who already have a certificate of registration would have
18 months to submit a new OP-2 application form. Likewise, Mexico-domiciled
CMC seeking authority to operate beyond the border zone, including carriers
that previously filed pending Form OP-1 (MX) applications as well as carriers
falling under one of the exceptions described in Chapter 1, would be required
to submit the revised Form OP-1 (MX). All certificates of authority issued
under either application form would be provisional for at least 18 months
and until the Mexico-domiciled CMC completed a successful safety audit or
compliance review, as outlined in Rule 3 (see the next Section, below).
In addition, Mexico-domiciled CMC would be required to file a Motor Carrier
Identification Report on a biannual basis, allowing the FMCSA to maintain
current records concerning Mexico-domiciled CMC operations.
Under the second rule, all Mexico-domiciled CMC applying for authority to
operate beyond the border zone using Form OP-l (MX) would be subject to
a safety audit prior to receiving authority to operate in the United States.
The safety audits required by this action would involve a review of the
carrier's initial application for operating authority and a review of the
carrier's records. An FMCSA safety auditor would evaluate the carrier's
prior history of compliance with applicable CMC safety laws, as well as
its ability to comply with these laws in the future. The safety audit would
be conducted either at the carrier's place of business or at an alternative
location in the United States designated by the FMCSA. A satisfactory audit
would be required before the carrier could receive authority to operate
beyond the border zone.
Under both revised Forms OP-2 and OP-1 (MX), the FMCSA would collect more
detailed information on an applicant CMC's size, operations, and history
than can be collected using the current forms. The revised forms would require
an applicant to affirm its basic knowledge of FMCSA regulations and indicate
how it would comply with those regulations. The applicant would be required
to certify that it has a system in place to ensure compliance with FMCSA
safety requirements, identify contact names and provide additional information
concerning driver qualifications, hours of service, drug and alcohol testing,
vehicle conditions, accident monitoring, and hazardous material transportation.
In addition, both forms would request information about the CMC' s insurance
coverage. The carrier would be required to notify the FMCSA in writing of
certain key changes in the information on either form within 45 days of
the change. A failure to update the form could result in a suspension or
revocation of the CMC's operating authority. The additional information
required by both forms would allow the FMCSA to better determine the willingness
and ability of Mexico-domiciled CMC to comply with Federal motor carrier
safety regulations.
FMCSA expects that the economic opportunities created by the modification
of the Moratorium would result in a 5% annual increase in the number of
new applications it would receive from Mexico-domiciled CMC, relative to
the Baseline scenario. Under the Proposed Action Alternative, the increase
in new applications would be less than under the No Action Alternative because
the revised application form would deter applicants that would be unable
to adequately demonstrate their willingness and ability to comply with the
safety regulations.
Under the Proposed Action Alternative, half of the 9,500 Mexico-domiciled
CMC currently operating within the Border Zone would apply for OP-1 (MX)
authority. In addition, approximately 1,400 new applications for operating
authority would be received and approved in 2002, with approximately 75%
of these carriers applying for OP-2 authority and the remaining 25% applying
for OP-1 (MX) authority. Thus, the total number of Mexico-domiciled CMC
authorized to operate under either type of authority in 2002 would be approximately
10,900. These carriers would be authorized to operate approximately 72,000
CMV, with 38,000 CMV authorized pursuant to Form OP-2 and 34,000 CMV authorized
pursuant to Form OP-l (MX).
FMCSA also expects that the pre-authority safety audits under Rule 2 would
not affect the total number of Mexican CMV operating in the United States
or the total amount of goods transported between Mexico and the United States.
The FMCSA anticipates that some carriers would fail to pass the pre-authority
safety audit and therefore be prevented from operating in the United States.
However, since the Proposed Action would not affect total trade between
the United States and Mexico, FMCSA expects that other carriers that succeed
in passing the audit would replace any carriers that fail to pass the pre-authority
safety audit.
2.3. SAFETY MONITORING FOR MEXICO-DOMICILED MOTOR CARRIERS
This section describes the operating conditions of Mexico-domiciled CMC
within the United States, as those conditions are affected by the safety
monitoring of Mexican CMC, CMV, and drivers. This section begins by describing
the operating conditions as they are affected by the current baseline scenario,
followed by a description of how those conditions would change under the
No Action and Proposed Action Alternatives.
2.3.1 Baseline Scenario - Moratorium Retained with Current Safety Monitoring
Program
Under current baseline operating conditions, the existing safety monitoring
system for Mexican CMV is largely limited to monitoring border zone operations
because, with the few exceptions listed in Chapter 1, Mexico-domiciled CMC
are limited to conducting operations within the border zone. Currently,
FMCSA conducts inspections on Mexico-domiciled CMC and CMV following the
same guidelines applied for inspections of United States and Canadian CMV.
In the United States inspections can take place at the border at designated
roadside inspection stations, at a carrier's place of business, or at any
point along the roadway. These inspections may occur at any time. (For more
information on the inspection process, refer to Appendix A). All CMV operating
in the United States are subject to inspections by Federal, State, or local
authorities.
All CMV crossing the border from Mexico into the United States are required
to pass through a United States Customs Service checkpoint, where some are
selected for customs inspection. In Arizona, New Mexico, and Texas, CMV
may then be selected for a safety inspection by a Federal CMC safety inspector,
who also works in the customs compound. Arizona, New Mexico, and Texas State
inspectors may additionally inspect these trucks after they leave the compound.
In California, the CMV leave the United States Customs compound and drive
on a private road directly to the office of the California Highway Patrol
where they are weighed by Weigh in Motion (WIM) scales. Certain vehicles
passing over the WIM scales are then selected for a safety inspection, based
in part on the inspecting official's determination that something on the
vehicle raises a safety concern (Cisneros 2001a).
Currently, manufacturers of motor vehicles built for sale or use in the
United States, as well as manufacturers of vehicles imported for use in
the United States, must comply with the Federal Motor Vehicle Safety Standards
(FMVSS) established by the National Highway Traffic Safety Administration
(NHTSA) that were in effect at the time of their manufacture, and apply
a FMVSS label to their vehicles attesting to their compliance.11 In 1975,
NHTSA issued an interpretive letter prohibiting the importation of vehicles
without a certification label, including CMV used to transport passengers
or cargo.12 NHTSA subsequently included the FMVSS label requirements in
its regulations, and all Mexico-domiciled CMC are required to comply with
the NHTSA regulation by ensuring that their CMV bear the label while conducting
operations in the United States.13 Currently, FMCSA's own safety regulations
do not include the FMVSS label requirement and accordingly, FMCSA inspectors
do not have authority to take enforcement action against Mexico-domiciled
CMC found to be in violation of NHTSA's FMVSS label requirement (FMCSA 2001h).
In calendar year 2000, Federal and State authorities conducted 2.45 million
CMV inspections, including 47,000 Mexican CMV inspections. This figure includes
inspections that were conducted both within and outside the border zone.
Previously, Federal and State authorities had conducted 2.36 million inspections
in calendar year 1999 and 2.23 million inspections in calendar year 1998,
reflecting an average annual increase of 110,000 inspections. During this
same period, there were 27,000 inspections of Mexican CMV in 1998 and 42,000
inspections in 1999. This reflects an average annual increase of 10,000
Mexican CMV inspections.
FMCSA has received funding to hire and train more than 200 additional inspectors
to work along the United States-Mexico border. These inspectors will be
deployed regardless of whether the moratorium is modified or the proposed
rules are implemented. These additional inspectors will perform approximately
100,000 inspections of Mexican CMV. Thus, under the Baseline scenario, FMCSA
would expect approximately 2.77 million total CMV inspections in 2002 and
2.88 million inspections in 2003. Within this total, approximately 170,000
of the 2002 inspections and 180,000 of the 2003 inspections would be conducted
on Mexican CMV.
2.3.2 No Action - Moratorium Modified with Current Safety Monitoring Program
Under the No Action Alternative, the FMCSA would retain its current inspection
and review authority after the Presidential order to modify the moratorium
is implemented. FMCSA expects that once the moratorium is modified, some
Mexico-domiciled CMC would apply for and receive authority to operate beyond
the border zone. As a result, some Mexican CMV would begin to transport
goods to intermediate or final destinations throughout the United States,
replacing the drayage operators and the United States CMV that previously
transported these goods.
FMCSA would continue to conduct inspections on Mexico-domiciled CMC and
CMV following the same guidelines applied for inspections of United States
and Canadian CMV, whereby all CMV operating in the United States are subject
to inspections by Federal, State, or local authorities at the border, at
designated roadside inspection stations, at a carrier's place of business,
and at any point along the roadway. These inspections may occur at any time.
Since the modification of the moratorium could affect the total amount of
freight transported between Mexico and the United States, the total number
of CMV transporting those goods and the proportion of Mexican CMV operating
in the United States may both increase slightly. As the total number of
Mexican CMV subject to inspection increases, the number of those vehicles
inspected may rise as well. In addition, FMCSA will continue to deploy additional
inspectors at the border, as described under the Baseline scenario.
Under the No Action Alternative, FMCSA would expect the number of Mexican
CMV inspections to increase above normal trends by approximately l0%, resulting
in approximately 180,000 Mexican inspections in 2002 and 190,000 inspections
in 2003. It was conservatively assumed that there would be no replacement
of inspections on United States and Canadian CMV as a result of the additional
inspections of Mexican CMV. Thus, the total number of CMV inspections identified
under the Baseline scenario would increase to approximately 2.78 million
inspections in 2002 and 2.89 million inspections in 2003.
2.3.3 Proposed Action - Moratorium Modified with Revised Safety Monitoring
System for Mexico-Domiciled CMC
Under the Proposed Action, FMCSA would promulgate two new rules. The first
rule would amend 49 CFR, part 385 to establish a new Safety Monitoring Program
for all Mexico-domiciled CMC operating within and beyond the border zone.
The program would combine targeted roadside inspections with a system of
safety audits to help ensure that Mexico-domiciled CMC are operated in compliance
with all applicable safety regulations and conduct safe operations within
the United States (FMCSA 2001e). The second rule would allow FMCSA to enforce
the NHTSA requirement that all CMV operated in the United States display
a certification label that acknowledges that the CMV complies with all FMVSS
in effect on the date of manufacture.
Under the new Safety Monitoring Program, a Mexico-domiciled CMC that adequately
demonstrates its willingness and ability to comply with applicable CMC safety
regulations would be granted provisional operating authority for a minimum
of 18-months, rather than the permanent authority granted under the Baseline
and No Action Alternatives. The Mexico-domiciled CMC would operate under
provisional authority during this 18-month period while in the new safety
monitoring system. While in the program, the carrier would remain subject
to selective compliance reviews, as are United States-domiciled CMC. In
addition, FMCSA will continue to deploy additional inspectors at the border,
as described under the Baseline scenario.
The safety audits and compliance reviews conducted under the new Safety
Monitoring Program would be similar to the pre-authority safety audits under
Rule 2 described above, the revision of OP-1 (MX). However, the safety audits
and compliance reviews conducted under Rule 3 would occur after the FMCSA
grants operating status pursuant to either OP-2 or OP-1 (MX) authority and
after Mexico-domiciled CMC commence operations in the United States. These
audits would involve a review of the carrier's initial application and a
review of the carrier's records. The safety auditor would evaluate the carrier's
prior history of compliance with all applicable CMC safety provisions. The
safety audit would be conducted either at the carrier's place of business
or at an existing office building in the United States designated by the
FMCSA. A satisfactory safety audit or compliance review would be required
before a carrier could be released from the safety monitoring system at
the end of the 18-month oversight period.
While operating under the safety monitoring system, a Mexico-domiciled CMC
would also be subject to expedited action by the FMCSA if found to pose
a potentially serious threat to the safety of the general public. If such
a finding were made, FMCSA could either schedule an expedited safety audit
or compliance review of the CMC or take other appropriate action. Failure
to respond appropriately or undergo the audit or review could result in
the suspension of the carrier's registration. Examples of CMC activities
that would lead to expedited action include, but are not limited to, the
following activities:
( Using drivers that do not have or are operating without a valid Government
of Mexico Commercial Driver's License (Licencia Federal de Conductor).
( Operating out-of-service vehicles without first making the required repairs.
( Being involved in, due to CMC act or omission, hazardous materials incidents
within the United States.
( Using a driver who tests positive for drugs or alcohol or who refuses
to submit to required drug or alcohol tests.
( Operating within the United States a vehicle that is not insured.
( Having a driver or vehicle out-of-service rate of 50 percent or more based
upon at least three inspections occurring within a consecutive 90-day period
(FMCSA 2001f).
Under the Proposed Action Alternative, FMCSA would begin enforcing the NHTSA
requirement that all CMV operating in the United States, including Mexican
vehicles, bear a label certifying their compliance with the FMVSS on their
date of manufacture. Mexican vehicle manufacturers have stated that Mexican
CMV have been built to meet FMVSS standards since 1994 (FMCSA 2001k); however,
applying a label to signify this is not required for sale in Mexico and
has been voluntary thus far. It is estimated that about 130,000 of the 400,000
trucks and buses that are operating on Mexican Federal roads were built
after 1994 (FMCSA 2001h). FMCSA inspectors would check for the FMVSS label
during their normal inspection process and would enforce violations of the
requirement through a notice of violation and a fine. FMCSA expects that
the enforcement of this existing NHTSA requirement would not affect total
inspection numbers or substantially change inspection procedures. The only
measurable change would be to increase the duration of inspections by approximately
5 seconds while inspectors verified the authenticity of a FMVSS label (FMCSA
e-mail 2001).
FMCSA anticipates that manufacturers will retrofit labels for existing vehicles
that are in compliance with the FMVSS regulations that existed at the time
of manufacture. FMCSA expects many Mexican vehicles to already be in compliance
with the FMVSS; however, a small portion of carriers may not be able to
bring their vehicles into compliance. As a result, FMCSA expects that only
a small number of Mexico-domiciled CMC will be compelled to reduce operations
due to the implementation of this alternative. It is assumed that there
will be no measurable effect from FMVSS labeling on the total number of
Mexican CMV operating in the United States since those vehicles not bearing
an FMVSS label will be replaced by vehicles that do bear an FMVSS label
(FMCSA 2001h).
Under the Proposed Action Alternative, the trends in the total number of
inspections that were identified under the No Action Alternative would continue.
As a result, FMCSA expects there would be 180,000 Mexican inspections in
2002 and 190,000 inspections in 2003. The increase in Mexican vehicle inspections
compared to the Baseline Scenario would increase the total number of CMV
inspections to approximately 2.78 million inspections in 2002 and 2.89 million
inspections in 2003.
Commercial Vehicle Safety Alliance Decal - Proposed Requirement:
Under this requirement, all Mexico-domiciled CMC granted provisional operating
authority pursuant to a Form OP-1 (MX) application would be required to
maintain a current Commercial Vehicle Safety Alliance (CVSA) decal on any
of its CMV operated within the United States. In addition, CMC granted permanent
OP-1 (MX) authority would be required to have a current CVSA decal on their
CMV for three years after receiving permanent OP-1 (MX) authority. This
requirement would supplement the new safety monitoring program requirements
discussed in the Proposed Action above. Under this alternative, a CVSA decal
would be affixed to each CMV that passed a Level I inspection. (Refer to
Appendix A for more information on the criteria used to determine whether
a vehicle has passed an inspection). Consistent with CVSA guidelines, a
CVSA certified government employee who had successfully completed a CVSA
approved training program would be authorized to conduct the inspection
and affix the CVSA decal. The CVSA decal is valid for three consecutive
months.
The FMCSA has determined that this alternative would require each Mexico-domiciled
CMC conducting United States operations beyond the border zone to submit
each of its CMV to a Level I inspection four times per year. In contrast,
Mexican CMV would be inspected approximately 2 to 3 times per year under
the Baseline, No Action and Proposed Action Alternatives. These additional
inspections would occur at existing inspection stations or other facilities
where inspections currently take place. For the purposes of this PEA, we
will assume that all of the inspections, and thus all of the impacts, will
occur within the United States.
FMCSA estimates that the total number of Mexican CMV inspections would be
230,000 in 2002. The additional 50,000 inspections on Mexican CMV are necessary
to meet the CVSA requirement of four yearly inspections for Mexican CMV
operating pursuant to OP-l(MX) authority. (For more information, refer to
Appendix A.) The calculation of the number of Mexican CMV inspections under
the CVSA requirement was performed under the assumption that the average
number of inspections per Mexican CMV operating pursuant to OP-2 authority
would remain the same as those under the Baseline, No Action and Proposed
Action Alternatives. Thus, the total number of CMV inspections would be
approximately 2.83 million in 2002 and 2.99 million in 2003.
FMCSA expects that this requirement would not affect the total number of
Mexican CMV operating in the United States or the total amount of goods
transported between Mexico and the United States. The FMCSA anticipates
that some Mexican vehicles would fail to meet the requirements for receiving
a CVSA decal, requiring those vehicles to be placed out of service or denied
entry into the United States. Vehicles places out of service in the United
States must be repaired before continuing or returning to Mexico. However,
since this alternative would not affect total trade between the United States
and Mexico, FMCSA expects that other vehicles that successfully obtain a
CVSA decal would replace the Mexican CMV that fail to receive one.
3. AFFECTED ENVIRONMENT
The Alternatives considered in this document relate to the operation of
Mexican CMV throughout the United States, including specific operations
occurring within the United States-Mexico border zone. To assist the FMCSA
in understanding the potential environmental impacts of these alternatives,
this chapter describes the environmental resources of the United States
particular to the Proposed Action, as well as the environmental resources
that are specific to the border zone. The resources that may be affected
by the alternatives are described as they exist today with the moratorium
in place. A description of the regulatory framework is provided where relevant.
In general, the transportation sector affects a range of environmental resources
through the initial construction of roads, the improvement of these roads,
and the operation of vehicles upon the roadways. No new roadways or facilities
are being constructed for the Proposed Action so there will be no construction
impacts from this action. Specifically, CMV can have impacts on these resources
as the result of normal operations, inspections and crashes. In order to
understand the scope of relevant resources that may be affected by the specific
alternatives described in this PEA, descriptions of the United States highway
transportation system and the resources of the United States and border
zone are detailed.
3.1. DESCRIPTION OF UNITED STATES HIGHWAY TRANSPORTATION SYSTEM
This section describes the current state of the United States Highway Transportation
System, including its layout, some programs that are in place to protect
United States resources, and traffic volumes of CMV. In this section only,
CMV are defined as a single-unit, 2-axle, 6-tire or more truck, or a combination
truck with either a single trailer or multiple trailers. CMV use the highways
in the United States as a means to transport products throughout the country.
The general highway corridors travel predominantly east-west or north-south
and are broken down by rural and urban areas and then by the number of lanes
for each roadway. In both rural and urban areas across the United States,
more than half of all miles driven are on 2-lane roadways with the next
largest number of miles traveled on four-lane highways. Most of these lanes
are 12 feet wide.
On rural interstates, principal arterials, and minor arterials, CMV traffic
comprises from 0.4 to 42 percent of all traffic volume, with an average
volume of 14.9 percent. The majority of miles traveled in these rural areas
are on roads with an average traffic volume of under 5,000 vehicles per
day. Within three of the four border States, CMV traffic comprises more
than the national average. Specifically, CMV traffic accounts for approximately
17 percent of all rural traffic in Arizona, New Mexico, and Texas, and approximately
14 percent of all rural traffic in California (OHPI 1996). On urban interstates,
freeways and expressways, principal arterials, and minor arterials, CMV
traffic comprises from 0.2 to 20.6 percent of all traffic volume with an
average volume of 7.8 percent. The majority of miles traveled in these urban
areas are on roads with an average traffic volume between 10,000 and 20,000
vehicles per day. Only one of the four border States experiences CMV traffic
volume above the national average for urban areas. Specifically, CMV traffic
accounts for approximately 12 percent of all urban traffic in Arizona, 7
percent in California and Texas, and 6 percent in New Mexico (OHPI 1996).
Highway corridors traverse through some protected resources areas such as
national and state parks, wetlands and waterways, and nature preserves.
Guadalupe Mountains National Park in Texas has route 62/180 running through
it, while routes 118 and 385 travel through Big Bend National Park in Texas.
White Sands National Monument in New Mexico has route 70 running through
it, while route 85 travels through Organ Pipe Cactus National Monument in
Arizona. Amistad National Recreation Area on the Texas/ Mexico border has
route 90 passing directly through it. Wetlands such as those in South Carolina,
and agricultural resources such as those in Nebraska also have highways
passing through them. The FHWA runs the Federal Lands Highway Program roads
that serves both tourism and recreational travel, protects and enhances
the natural resources in these lands, provides sustained economic development
in rural areas, and provides Native Americans with needed transportation
access (FHWA 2001).
The FHWA administers a coordinated Federal lands program consisting of forest
highways, public land highways, park roads and parkways, refuge roads, and
Indian reservation roads. This program funds more than 90,000 miles of federally-owned
and public authority-owned roads, which serve Federal lands. They work with
many different agencies such as the Bureau of Indian Affairs, Bureau of
Land Management, Bureau of Reclamation, Department of Defense, Federal Aviation
Administration, Federal Railroad Administration, Federal Transit Administration,
Military Traffic Management Command, National Park Service, State and Local
Governments, United States Amy Corps of Engineers, United States Fish and
Wildlife Service, and United States Forest Service, to help with the preservation
of the land and its resources while at the same time, providing roadways
for both personal travel and the transportation of goods across the United
States (FHWA 2001).
3.2. DESCRIPTION OF UNITED STATES AND BORDER ZONE RESOURCES
While the proposed actions have national scope, many of the potential impacts
could be focused in the border zone. Thus, it is important to look at both
the resources of the entire United States as well as the border zone resources
in this Chapter. The Southwest region encompassing the border zone is the
primary area potentially impacted by the Proposed Action. The border region,
defined as a 100-kilometer band on both sides of the border, encompasses
four United States States and six Mexico States, with approximately 6.2
million people in the United States and 4.3 million people in Mexico. Both
general and border zone resources that could be affected by the proposed
actions are described below. Primary resources that have the potential to
be directly impacted are transportation, public health and safety, air quality,
noise, and socioeconomics. The alternatives examined in this environmental
assessment relate directly to the aforementioned resources and will be assessed
in detail in Chapter 4. It is recognized that impacts to these primary resources
may result in secondary impacts to other resources, such as, hazardous materials,
solid waste, topography and geology, biological resources, invasive species,
endangered species, water resources, cultural, 4(f) and farmland resources,
and visual resources. Therefore, these resources are discussed in this Chapter.
3.2.1 Transportation
United States Resources
The United States transportation system carries over 4 trillion passenger
miles and 3.7 trillion ton-miles of freight every year, generated by more
than 260 million people and 6 million businesses. Medium- and heavy-duty
vehicles play a large role in moving consumer and commercial goods throughout
the United States, using the highway infrastructure. Details of the highway
system have been discussed Section 3.1.
The United States economy encompasses several regional economies with major
links to international markets. CMC transport freight both within the United
States and throughout North America. Between 1997 and 2000, annual imports
from Mexico, by weight, increased from 23.99 million to 30.40 million United
States Short Tons. This represents an average annual growth rate of approximately
9 percent. Over the past 4 years, CMV have carried approximately 75 percent
of all imports from Mexico, as measured by weight (see Figure 3-1). The
efficient transport of freight is essential to the economic prosperity of
the nation, since the national economy is highly evolved and no one region
is independent of the goods and services provided by other regions and external
trade. The transportation of these goods is highly dependent on CMC and
other freight transporters. As a result, between 1975 and 1998, annual vehicle
miles traveled (VMT) by CMV in the United States more than doubled-from
81 billion VMT to 196 billion VMT (DOT 2001).
Figure 3-1: Mexico Imports into the United States between 1997 and 2000,
as Measured by Weight (United States Short Tons)
Source: United States Customs Service
Border Zone Resources
Increases in trade between the United States and Mexico have generated a
significant increase in cross border traffic in recent years (see Figure
3-2). This additional traffic has placed a strain on the local and regional
transportation infrastructure and created congestion at border crossings.
The dramatic growth in population along the border spurred by a significant
increase in industrialization in the region has also contributed to the
increased traffic. Another reason for delays and congestion is the inadequacy
and poor condition of roads connecting the ports of entry (DOT 2001). This
congestion can create a public safety hazard for local traffic and pedestrians,
as well as increase pollution in border towns and cities. Additionally,
delays due to congestion to and from ports of entry can have a potential
impact on firms that rely on supplies and finished goods being shipped and
processed quickly across the border.
Figure 3-2: Trend in the Total Number of Northbound Truck Crossings into
the United States from Mexico between FY 1992 and 2000.
Source: United States Customs Service
The growth in cross border trade between the United States and Mexico has
been led by the maquiladora, or export assembly industry. Products from
maquiladoras as well as fresh produce arrive at the border through five
major Mexico highways. While some ports of entry process a high volume of
commercial traffic, others are underutilized. According to United States
Customs, approximately 91 percent of the all CMV crossing into the United
States from Mexico between fiscal years 1992 and 2000 took place at seven
of the 23 ports of entry that handle commercial traffic. During this period,
the average annual growth rate in the number of northbound crossings was
approximately 9 percent. The top seven ports of entry based on traffic volume
are Laredo, Otay Mesa, El Paso, Brownsville, Hidalgo, Nogales, and Calexico
(several of these ports have more than one bridge or crossing) (see Figure
3-3). At some ports of entry, such as the Juarez-Lincoln Bridge in Laredo,
Texas and Otay Mesa, Califomia, there were as many as 2,500 commercial vehicle
crossings during one day in 1998 (GAO 2000). Two-thirds of the total northbound
CMV traffic crosses through three communities: Laredo and El Paso, Texas,
and San Diego, California (See Table G-2) (GAO 2000).
Figure 3-3: Change in Northbound Truck Crossings at the Seven Busiest Ports
of Entry for FY 1992, 1996 and 2000.
Source: United States Customs Service
There are several issues affecting United States-Mexico border crossing
inspections that result in increased congestion (GAO 2000). Increased CMV
traffic and associated congestion at some border crossings that were built
in downtown areas, such as, Laredo and El Paso, Texas, have taxed border
community infrastructure. Lines of trucks, many of which are empty, waiting
to enter the United States from Mexico can run up to several miles during
peak time-periods in the early to late afternoon. These idling trucks contribute
to air pollution and safety concerns in some major border zone cities. At
the same time, crossings in remote and less accessible areas along the border
zone, such as, Sasabe, Arizona or Roma, Texas, are underutilized and less
congested. According to United States Customs records, nearly 47 percent
of the 3.6 million trailers that crossed the border in fiscal year 1998
from Mexico were empty. United States Customs officials at the ports of
entry must still process all trucks, empty or not, to ensure compliance
with United States laws and regulations (GAO 2000).
Commercial traffic congestion at the United States-Mexico border is primarily
caused by the high volume of vehicles at ports of entry that must be processed
through facilities that have physical and technological limitations and
comprehensive Federal and State processes. The specific factors that contribute
to border congestion include: difficulties resulting from multiple checks
at the border by various Federal and State agencies; inspection agency staffing
shortages at some border crossings; limited use of automated management
information systems for processing commercial traffic; poor port of entry
planning among United States inspection agencies and limited coordination
between United States and Mexico governments; and the number of inspections
that a single CMV can be subject to (e.g., some CMV undergo up to six separate
secondary inspections after inspection by United States Customs) (GAO 2000).
There are approximately two hundred sites where certified inspection stations
exist throughout the Border States.
3.2.2 Public Health and Safety
United States Resources
The primary mission of the FMCSA is to save lives and reduce injuries by
preventing truck and bus crashes. The FMCSA establishes standards for CMC
operations, vehicles, and drivers to ensure the safety of the public on
the United States roadways. The agency enforces both safety and hazardous
material standards and monitors CMC operations that may affect the safety
of workers. FMCSA programs ensure safety in CMC operations by targeting
high-risk carriers and CMV drivers, improving safety information systems
and CMV technologies, strengthening CMV equipment and operating standards,
and increasing safety awareness.
The FMCSA works closely with Federal, State, and local enforcement agencies,
the CMC industry, labor safety interest groups, and others to accomplish
their safety goals. Crashes involving CMV are the largest safety concern
in the CMC industry. In the United States in 1999, there were approximately
100,000 fatal and injury crashes involving heavy trucks-including 4,560
fatal crashes and 95,000 injury crashes. Approximately 800, or 18 percent
of these fatal crashes occurred in Arizona, California, New Mexico, and
Texas (US DOT 2001).
Between 1975 and 1998, annual VMT for large trucks in the United States
more than doubled-from 81 billion VMT to 196 billion VMT. Despite this increase
in large truck VMT, both the fatality rate and total crash incident rate
per 100 million VMT have decreased. In 1998, there were 2.3 large truck
crash fatalities for every 100 million VMT, down from 3.5 fatalities in
1988. The total number of fatalities, however, increased over the same period.
In 1999, there were 5,380 fatalities in crashes involving large trucks,
compared to 4,483 in 1975. On average, more than 80 percent of those killed
in large truck crashes were non-motorists or occupants of other vehicles
involved in the crash (US DOT 2001).
Enhanced alertness and work readiness are important requirements for CMV
drivers. FMCSA's Motor Carrier Research and Technology Program aims to improve
CMC safety and economic performance through research in the following areas:
Driver Safety Performance, Commercial Safety Performance, Carrier Compliance
and Safety, Safety Systems and Technologies, and Cross-Cutting Safety Initiatives.
Specific project levels include such areas as crash causation and profiling,
regulatory evaluation and reform, compliance and enforcement, hazardous
materials safety and cargo tank integrity, commercial driver training and
performance management, driver alertness and fatigue, driver physical qualification,
and car-truck proximity (United States DOT 2001).
The Intelligent Vehicle Initiative portion of the Intelligent Transportation
Systems Program aims to accelerate the development and commercialization
of in-vehicle safety systems, such as, collision avoidance and driver condition
monitoring. These complement other elements of the ITS Program, such as
electronic clearance, onboard safety monitoring systems, automated administrative
processes, and hazardous materials incident response. While the ITS Program
addresses all highway vehicles, the safety implications for CMV are important
since significant losses can result from crashes involving these vehicles
(United States DOT 2001).
Although highway crash fatality rates have declined, new strategies are
continually being developed to provide further reductions. The centerpiece
of the FMCSA's Commercial Motor Vehicle Safety Action Plan is to reduce
fatalities involving trucks and buses by half by 2010. While crashes involving
CMV are frequently found not to be the fault of the operator of the truck,
advanced technological systems installed in CMV, together with carefully
targeted investments, will continue to reduce CMV-related fatalities. One
of the major challenges likely to be faced in the near term will not be
technology advances-such as crash avoidance systems, early hazard detection,
countermeasures for driver fatigue, and roadside brake examination on moving
CMV-but adoption and implementation of these new technologies in the CMV
industry to improve safety. Among the longer range solutions are crashworthiness
requirements to reduce fatalities in truck/ car collisions (United States
DOT 2001).
United States DOT's technical goal for CMV is to reduce both the likelihood
and severity of crashes involving CMV. Particular goals related to CMV crash
avoidance include safer retreaded tires, better traction control and stopping
capabilities, capabilities such as detecting and responding to driver fatigue,
avoiding collisions involving "blind spots" and other situations
involving car/CMV proximity and possibly supplementing brakes during emergency
deceleration events. Goals related to severity of crashes involving CMV
include better tank integrity, particularly for hazardous materials, as
well as greater crash compatibility with light vehicles. United States DOT
plans to refine technical goals for CMV on an on-going basis through the
investigation of crashes nationwide, particularly those that may be related
to emerging trends or technologies (United States DOT 2001).
One method of measuring the safety of trucking operations in the United
States is by analyzing the frequency with which carriers' vehicles are placed
out-of-service by safety inspectors due to the discovery of a serious safety
defect. Reports by the United States Department of Transportation's Office
of the Inspector General (OIG 1999) have indicated that the rate at which
Mexican CMV have been placed out of service has fallen over the past few
years from 44 percent in FY 1997 to 37 percent in FY 2000. The OIG also
noted that the out-of-service rate for United States CMV inspected nationwide
in FY 2000 was 24 percent. This data indicates that while the overall level
of safety of all Mexican CMV may be improving, the safety of United States
CMV may still be better when compared an average of both drayage and long-haul
Mexican CMV. However, as will be discussed in the Border Zone Resources
section below, the out-of-service rate for the Mexican long-haul fleet is
19 percent, making it comparable to that of the United States long-haul
fleet.
Border Zone Resources
Public safety issues are also a concern in the border zone since all Mexican
CMV either operate in, or pass through, the border zone while operating
in the United States. Increased traffic concerns in the border zone relate
to the need for appropriate measures to safeguard public health and safety.
Two of the Border States-Arizona and New Mexico-report a larger percentage
of CMV crashes involving fatalities than the United States as a whole, whereas
California and Texas remained below the United States national average.
Ports of entry are expected to be the places most affected by an increase
in trade. Some resulting traffic safety concerns include the high congestion
in the area and the lack of emergency lanes. According to a 1993 report
by the University of Texas at El Paso, crash rates and fatality rates in
the Texas border counties were noticeably higher than those rates compiled
for the entire State of Texas. This implies traffic and safety problems
are more abundant at the border than throughout the rest of the State (Pezo,
R. and Cook, G. 1993).
In May 2001, the OIG published a Interim Report on the Status of Implementing
the North America Free Trade Agreement's Cross Border Trucking Provisions
detailing its recent audit of DOT's oversight of Mexico-domiciled CMC. As
a part of this audit, the OIG analyzed Federal and State inspection data
maintained by the DOT for FY 1998. This data revealed that some Mexico-domiciled
CMC had been subjected to a safety inspection beyond the border zone, in
many cases while operating beyond the scope of their Form OP-2 authority.
The OIG looked specifically at the number of Mexican CMV inspected in each
of three areas: within the border zone, within the Border States but beyond
the border zone, and beyond the Border States. In addition, the OIG reported
the number of times that vehicles were placed out-of-service after an inspector
identified a serious safety violation. This OIG report indicated that, the
out-of-service rate for Mexican CMV inspected within the border zone was
41%, within the border states but beyond the border zone was 32% and beyond
the border states was 19%.
3.2.3 Air Quality
United States Resources
Air quality is technically defined as the concentration of air pollutants
present within the air mass of a region and is measured in parts per million
(ppm) or micrograms per cubic meter (mg/m3). Air pollutants are a significant
cause for concern for both public health and welfare. Public health refers
to the physiological effect on a human being while public welfare refers
to such concerns as property damage and aesthetic effects. In response to
both of these concerns, Federal regulations have been developed for six
criteria pollutants identified by EPA. These pollutants are considered harmful
to public health and the environment. The six criteria pollutants that EPA
established under the National Ambient Air Quality Standards (NAAQS) are
carbon monoxide (CO), lead (Pb), nitrogen dioxide (NO2), ozone (O3), sulfur
dioxide (SO2), and particulate matter (PM). Nitrogen dioxide reacts in the
atmosphere over the course of several hours and is often referred to simply
as nitrogen oxides or NOx.
In measuring air quality, the ambient concentration of pollutants is compared
with the EPA's NAAQS. Table C-1 in Appendix C shows the primary and secondary
standards used to regulate air pollution in the United States. If the concentration
of any of these pollutants is less than or equal to their NAAQS standard,
the air quality is considered in attainment of the standards. However, if
the concentrations are greater than the NAAQS standard, the air quality
for a region is considered to be in non-attainment of the NAAQS. Non-attainment
areas are regions where the air pollution levels persistently exceed national
air quality standards established by the Clean Air Act of 1967.14 The EPA
is continuously monitoring ambient air quality within counties and air basins
in the United States. A detailed description of the criteria pollutants
and their sources, current status and potential health effects is presented
in Appendix C and Table C-2.
As shown in Table C-3 in Appendix C, mobile sources in the United States
produce the highest or the second highest levels of emissions for several
pollutants. The transportation sector continues to be a significant source
of air pollutants at the national level. The table shows that motorized
vehicles are responsible for most of the total CO (77.1 percent) and NOx
(55.5 percent) emissions in the United States. Close to half (47.0 percent)
of the total VOCs (volatile organic compounds) and a quarter of total PM
emissions are also due to motor vehicles. The contributions of Pb and SOx
from vehicles are relatively less, partly due to their reduced presence
in transportation fuels (Pb has essentially been eliminated from gasoline).
This table clearly indicates that the transportation sector is a significant
source of pollutant emissions in the United States. Table C-4 shows the
actual emissions from on-road vehicles separated into categories. The values
reveal that although light-duty gasoline vehicles are generally the most
significant source of pollution, heavy-duty gasoline and diesel vehicles
are also significant. Indeed, for NOX emissions, diesel vehicles are the
most significant category. Heavy-duty diesel vehicles as a whole produce
far more NOX and PM emissions than light-duty vehicles. This is due to greater
mass emissions from heavy-duty diesel vehicles that have only been regulated
in the last decade (EPA 2001).
Total United States Emissions and Concentration Trends
Since 1970, the transportation sector as a whole has made tremendous progress
in reducing emissions of criteria and hazardous air pollutants. Transportation
related emissions of some pollutants, such as carbon monoxide (CO) and unburned
hydrocarbons (HC), have been reduced by more than half since the 1970s (DOT
2001). However, heavy-duty surface vehicles, including CMV, have not made
as rapid overall progress as cars and light trucks. PM emissions from diesel
engines are still great despite recent attempts to regulate the engines.
Greenhouse gas (GHG) emissions from the transportation sector have continued
to grow rapidly, with the transportation sector currently accounting for
about a quarter of United States GHG emissions (DOT 2001). Consistent with
recent economic growth, GHG emissions from CMC have been growing very quickly.
Medium-and heavy-duty trucks contribute significantly to urban air pollution.
For the 1989-1998 period, most of the criteria pollutants experienced significant
decreases in both emissions and atmospheric concentrations in the United
States. Table C-5 shows that with the exception of NOx, emissions and atmospheric
concentrations for all of the criteria pollutants decreased during the study
period. It should be noted that CO emissions decreased even though total
VMT increased by 57 percent during this period. The decrease in Pb levels
is the result of the effects of legislation that eliminated Pb from gasoline
and limited its usage in industrial applications. Almost no change occurred
for NO2 emissions while concentration levels decreased. VOC emissions decreased
while O3 concentrations decreased slightly. 03 levels (concentrations) for
urban and suburban areas decreased more than those in rural areas. Likewise,
decreases in PM10 concentrations are also supplemented with the findings
that urban and suburban areas experienced higher concentration levels. With
most of the emissions occurring near power plants, including coal-burning
plants, the emissions and concentration levels for SO2 both decreased during
the study period. These decreases are generally attributed to SO2 controls
that EPA implemented as part of their Acid Rain Program in 1995 (EPA 2001).
Mobile Sources
Mobile sources are generally classified under two broad categories: on-road
and off-road. As their names imply, on-road vehicles are primarily used
on paved roads while off-road vehicles include those used for construction,
farming, lawn and garden, and airport services. The on-road engines can
be further categorized into light-duty vehicles and heavy-duty vehicles
with the weight difference changing at approximately 8,500 lbs gross vehicle
weight (GVW) (National Research Council 2000). The light-duty category includes
both passenger vehicles and light-duty trucks. Heavy-duty vehicles include
both trucks and buses and are further categorized into gasoline and diesel-powered
vehicles (light-duty vehicles are primarily fueled by gasoline). Table C-6
shows estimated pollutant emissions due to these different fuel types. The
emission estimates were calculated using EPA's MOBILE5 and PART5 models.
In general, using gasoline appears to produce more emissions of CO, NOx,
and VOCs while burning diesel appears to produce more NOx and PM emissions.
The contributions from diesel emissions of NOx and SO2 are significant compared
to those for light-duty gasoline vehicles. Unlike light-duty vehicles, heavy-duty
vehicles cover a much broader GVW range. Heavy-duty vehicle engines are
certified on a special dynamometer since truck and bus engines can be placed
in many different types of chassis and weight classes. Urban buses have
their own emission certification standards. Until recently emissions standards
for heavy-duty vehicles were less stringent than those for light-duty vehicles.
CMV are not presently required to participate in an Emissions Inspection
and Maintenance Program, similar to that which is required for cars under
8,500 lbs. GVW. This is because there has been little research into Emissions
Testing of CMV due to the high cost of chassis dynamometers. The University
of West Virginia has conducted some chassis emissions testing of urban buses
in New York City powered by diesel, natural gas, and hybrid electric, but
more research is required. Some states have random roadside inspections
to check for the opacity or smoke levels of CMV. Opacity/smoke testing is
also in its initial stages and requires more work.
The factors that affect emissions from vehicles include: engine design and
operating features; driver operating and maintenance practices; fuel composition;
add-on pollution control technology; and environmental conditions (Cooper
1994). Engine design and operating features include air-to-fuel ratio or
stoichiometry, compression ratio, and timing of the spark relative to the
stroke of the piston. Driver operations are also important factors since
no matter how well an engine is designed, it must be operated properly:
the vehicle should not be overloaded, proper fuels should be used, and the
vehicle must be maintained. Fuel composition is important because impurities
in the fuel will be emitted into the environment. Sulfur is commonly used
as an example of an impurity that directly forms S02. Add-on pollution control
technology affects emissions after the pollutants have been formed. The
technology emission controls such as the catalytic converter, refueling
vapor canisters, positive crankcase ventilation and exhaust gas recirculation
among others.
In many areas, transportation planning is subjected to the conformity process.
States that fail to meet EPA standards for criteria pollutants must develop
State Implementation Plans (SIPs) detailing how they will reach these standards.
Transportation emissions must remain within levels projected by State Implementation
Plans that, when implemented will lead to attainment of air quality standards.
Transportation plans and programs, therefore, must conform to air quality
goals. Neither the transportation conformity nor general conformity rules
apply to the Proposed Action. Transportation plans, programs and projects
in non-attainment and maintenance areas that are funded or approved by the
FHWA and the Federal Transit Administration must meet the requirements of
EPA's transportation conformity provisions.15 Since these FMCSA actions
do not involve such approvals or funds, they are not subject to the provisions
of the transportation conformity rule.16
Border Zone Resources
In considering air pollution from CMV, NOx and PM- 10 are the pollutants
of main concern, because of the significant contribution of CMV to national
emissions for these two pollutants, compared to the contribution of CMV
to national emissions for the other criteria pollutants described above
and in Appendix C. NOx is predominantly created by high-compression internal
combustion engines, and is a precursor to ozone (the main component of smog).
On the other hand, PM-10 is produced in the fine soot particles that are
emitted by diesel engines (ICF, 2001). Therefore, these are the primary
pollutants of concern that are dispelled from heavy-duty trucks and buses.
Among the seven counties containing the busiest border crossings with Mexico,
Santa Cruz County in Arizona, and Cameron, Hidalgo, and Webb Counties in
Texas, are considered "in attainment" for both PM-10 and ozone
(see Table 3-1). EPA classified El Paso, Texas as a Moderate PM-10 non-attainment
area and a serious ozone non-attainment area. San Diego, California is in
attainment of the NAAQS for PM-10 but is classified by EPA as serious non-attainment
for ground level ozone. Imperial County, California is a Moderate PM-10
non-attainment area and is no longer classified as a non-attainment area
for ozone, but it is in a Maintenance status for the ozone standard.
Table 3-1: NAAQS Attainment Status for United States - Mexico Border Counties
COUNTY
PM-10
OZONE
San Diego, CA
In Attainment
Serious Non-
Attainment
Imperial, CA
Moderate Non- Attainment
In Attainment*
Santa, Cruz, AZ
In Attainment
In Attainment
Cameron, TX
In Attainment
In Attainment
Hidalgo, TX
In Attainment
In Attainment
Webb, TX
Moderate Non-Attainment
Serious Non-
Attainment
El Paso, TX
Moderate Non-Attainment
Serious Non-
Attainment
* Currently in a Maintenance status under Section 185A of the Clear Air
Act
Source: EPA 2001
In the highway corridor from San Antonio, Texas to Monterrey, Mexico, 84%
of NOx and 90% of the other pollutants are caused by trucking freight. This
corridor contains the Laredo border crossing, and is in Webb County, Texas.
Also in this same region, it was discovered that 6.3% of trade-related CO
emissions is due to truck idling. Another corridor where comparable air
quality measurements were conducted is the highway that spans Tucson, AZ
to Hermosillo, Mexico (ICF 2001). This corridor passes through the border
city of Nogales, AZ in Santa Cruz County. While Santa Cruz County, AZ is
in attainment for PM-10 and ozone, at the city level, Nogales, is in non-attainment
status for PM-10 under the United States EPA standards (ICF, 2001).
3.2.4 Noise
Sound, an element of all human and natural environments, becomes noise when
it is unwanted, unnecessary, or does not convey useful information. Noise
is further defined as sound that disrupts normal activities or that diminishes
the quality of the surrounding environment.
Generally, sound is measured in decibels (dB), which is a logarithmic scale
that condenses the large range of sounds that make up the range of human
hearing. Using this scale, an increase of 3 dB represents a doubling of
sound energy, but this difference is barely detectable by the human ear.
An increase in sound energy by 10 dB is approximately equivalent to a doubling
in perceived loudness (USAF 1978). An "A-weighted" scale, termed
dBA, places more emphasis on some frequencies while de-emphasizing others
because the human hearing range is more sensitive to certain frequencies.
Acceptable noise levels for residential areas, as stated by the United States
Department of Housing and Urban Development guidelines, are 65 dBA during
the day and 55 dBA at night. For perspective, 55 dBA is the approximate
sound level of a quiet conversation at a distance of about 10 feet. Sixty-five
dBA is typical of what might be heard in a large, fairly busy store, from
a vacuum cleaner at 10 feet, or from heavy truck-dominated highway traffic
at about 250 feet. Ambient noise levels in specific communities or locations
will vary depending on certain variables, including the amount of development
in an area and the population density of an area. For example, rural settings
are typically about 40-48 dBA, while downtown urban settings are typically
about 72-80 dBA. Sensitive receptors, such as residential areas, schools,
hospitals, churches or any facility requiring mostly quiet conditions, can
be affected by noise. Similarly, noise levels also affect workers in workplaces
where noise can affect performance or cause hearing damage, and noise-sensitive
wildlife species.
An important characteristic of sound is that its energy levels decrease
as distance from the sound source increase. Typically, doubling the distance
between a sound source and sound receiver results in four times less sound
energy at the receiver than at the source. The noise attenuation of a line-source
of noise, such as a highway, is less than that of a point source, such as
a piece of machinery. This attenuation occurs because (1) a sound wave spreads
out as it leaves its origin, which results in a more diffuse wave at the
receiver and (2) the atmosphere absorbs some of the sound energy as the
wave passes through it. Other factors can also influence this attenuation,
including wind, temperature, humidity, terrain, and infrastructure (USAF
1978).
The transportation sector continues to generate considerable noise pollution.
Achieving DOT's environmental goals will entail reducing the number of people
exposed to significant transportation-related noise, including that from
CMV. Although changes in design and operation of transportation facilities
is a primary strategy, reduced noise emissions from vehicles such as trucks
and buses will contribute significantly toward this objective (United States
DOT 2001).
3.2.5 Socioeconomics
United States Resources
Socioeconomics includes the social and economic portion of the human environment
and includes information on the demographics (population and employment),
income and housing of the major geographic regions throughout the United
States. External events, such as changes in public policy, have the potential
to directly or indirectly affect these different areas of the human environment.
Social consequences, such as adverse health effects from poor air quality
conditions, have an effect on the quality of life enjoyed by residents in
a community. Economic consequences, such as increases in health care costs,
have an effect on business activities, market structure, and circulation
of goods within and between communities. Size, distribution, and composition
of a community's population will be affected by demographic consequences,
such as out-migration of firms and labor due to increased business costs.
A community is defined partly by behavior patterns, which individuals or
groups of individuals have in common. Daily social interactions, use of
local facilities, participation in local organizations, and involvement
in activities that satisfy the population's economic and social needs are
ways of expressing these "community" behavior patterns (FHWA 1996).
In order to measure how well a community supports its demands, the response
to changing environmental, social, economic, and demographic conditions
must be examined. The Bureau of the Census provides information on demographics,
income, public finances and local housing availability.
Border Zone Resources
On February 11, 1994, the President issued Executive Order (EO) 12898, entitled
"Federal Actions to Address Environmental Justice in Minority Populations
and Low-Income Populations." The Presidential Transmittal Memorandum
that accompanies EO 12898 states that, "Each Federal agency shall analyze
the environmental effects, including human health, economic and social effects,
of Federal actions, including effects on minority communities and low-income
communities, when such analysis is required by NEPA."17 In order to
identify any potential impacts on environmental justice and thereby comply
with this Presidential order, this PEA identifies socioeconomic characteristics
within the border zone.
According to 2000 census data, 4.8 million people live in the seven counties
adjacent to the busiest border crossings, with over half of those people
living in San Diego County adjacent to the Otay Mesa crossing. Of the people
living adjacent to these seven crossings, 50% identified themselves as being
of Hispanic or Latino origin (83% if San Diego County is excluded) (see
Figure 3-4). San Diego County had a median household income of $39,427 and
the remaining counties had median household incomes that ranged from $20,034
to $26,515 (see Figure 3-5). During the same period, the total United States
population was 281.4 million with 12.5% identifying themselves as being
of Hispanic or Latino origin. The median household income throughout the
United States was $37,005. Six of the border counties have a median household
income under 72% of the national average. In addition, one county has a
Hispanic/Latino population that is twice the proportion of the national
average, while the remaining six counties have Hispanic/Latino populations
that are 5.5 to 7.5 times the national average (United States Census Bureau
2001).
Figure 3-4. General population versus Hispanic Population in border crossing
cities.
Source: United States Census 2001
Figure 3-5. Percent Hispanic Population compared to average income for border
crossing cities and the United States total.
Source: United States Census 2001
In addition to Hispanic and Latino communities within the border region,
there are also many Native American groups that live within the Border States.
Among these are Piman, Yuman, Dene, Shoshonean, and Pueblo peoples.
3.2.6 Other resources
The remaining potential areas of concern: Topography and Geology, Biological
Resources, Hazardous Materials, Solid Wastes, Water Resources, Cultural,
4(f), and Farmland Resources, Visual Resources, Endangered Species, and
Invasive Species are dismissed from further analysis. These areas of potential
concern were dismissed after considering any potential impacts and- depending
on the specific resource-based on a resource consumption analysis developed
that provided basis for findings of minimal potential impacts. These calculations
are found in Appendix D. In addition to the minimal resource consumption,
the determination to drop these resources was based on the fact that the
administrative, audit, and roadside inspections will occur at existing facilities
thus causing no new construction, and FMCSA does not expect an increase
in the total number of CMV operating in the United States. Based on these
assumptions, FMCSA has concluded that there will be no more than insignificant
impacts and minimum increases in resource consumption and waste disposal.
All of the areas of potential concern were analyzed individually and the
reasons for dropping these resources from further environmental analysis
are explained briefly below and in Appendix D.
Hazardous Materials
Hazardous substances and wastes are solid, liquid or gaseous materials that
because of their quantity, concentration or physical, chemical or infectious
characteristics may:
( Cause or significantly contribute to an increase in mortality or an increase
in irreversible illness, and
( Pose a substantial present or potential hazard to human health, or the
environment when improperly treated, stored, transported, or disposed of,
or otherwise managed.18
Hazardous materials are designated by the Secretary of the Department of
Transportation as posing an unreasonable risk to health, safety, property
and environment. Hazardous materials include hazardous substances, hazardous
wastes, marine pollutants, elevated temperature materials, and materials
identified by the DOT in the Code of Federal Regulations.19 Those hazardous
materials that are specifically regulated by the DOT are Class 1 Explosives,
Class 2 Gases, Class 3 Flammable Liquids, Class 4 Flammable Solids, Class
5 Oxidizing Substances; Organic Peroxides, Class 6 Poisonous (Toxic) and
Infectious Substances, Class 7 Radioactive Material, Class 8 Corrosives,
and Class 9 Miscellaneous Dangerous Goods.
Carriers must register with the DOT to transport hazardous materials. Under
existing regulations, hazardous materials must be properly classed, described,
packaged, marked, labeled, placarded and in condition for shipment as required
or authorized. Transporters of hazardous waste must meet strict guidelines,
must obtain an EPA identification number, and are not allowed to accept
shipments without complete manifests. Waste cannot be stored for more than
10 days without becoming subject to storage facility regulations and only
facilities with RCRA permits must be used. Transporters of hazardous waste
must follow the EPA and DOT regulations concerning spilling and reporting
of spills, and must retain records for a minimum of two years (FMCSA 2001d).
The gas, oil, and other fluids in the engine that are required for vehicles
to operate properly are not regulated by the FMCSA. If and when crashes
occur that cause the release of these substances, the proper authorities
are notified and these authorities will perform any necessary clean-up activities.
The Proposed Action will not alter the existing regulatory framework governing
the transportation or storage of hazardous materials. The main impacts on
hazardous materials would be related to public health and safety, since
crashes may involve CMV transporting hazardous materials. As will be discussed
in Chapter 4, the Proposed Action may result in a beneficial impact to public
safety. As a result, there should be negligible impacts with regard to hazardous
materials. For more information on hazardous materials, see Appendix D.
Solid Waste
The generation of solid waste is not exclusive to any industry. However,
the transportation sector will not be generating any significant additional
solid waste as a result of FMCSA's implementation of the rules set forth
in this document.
The transportation sector generates a good deal of solid waste that is either
recycled or ends up in landfills. Discarded vehicles and vehicle parts and
abandoned infrastructure, such as pavement from highways or rail line materials,
are the major elements of transportation solid wastes. Much of the material
generated by scrapping automobiles and trucks is currently recycled. Further
changes in CMV, such as even greater use of recycled and recyclable materials
would complement these efforts.
The Proposed Action does not entail new construction or an increase in the
overall total number of CMC operating in the United States. In addition,
FMCSA has concluded that there will be no more than a minimal increase in
resource consumption and waste disposal. Since the Proposed Action does
not significantly affect the generation of solid wastes, this resource will
not be further analyzed in Chapter 4.
Topography and Geology
Topographic and geologic structures have the potential to be impacted with
the construction of highways, roads, and associated facilities, including
inspections stations. Construction has the potential to change the face
of the land as blasting occurs with the creation of buildings and roads.
However, all CMV operations conducted pursuant to the Proposed Action will
occur using existing highways and roadway systems. In addition, all currently
planned roadside inspections would be carried out at existing facilities.
Therefore, no construction activities directly related to the proposed rulemakings
are expected.
Since the proposed actions do not involve activities with the potential
to significantly affect topographical or geological resources, these resources
will not be further analyzed in Chapter 4.
Biological Resources
The biological resources of the United States consist of all terrestrial
and aquatic flora and fauna and the habitats in which they occur. They may
be divided into the following seven major terrestrial climatic regions:
tundra, taiga, temperate deciduous forest, grassland, desert, scrub forest,
and tropical forest. The United States Fish and Wildlife Service (United
States FWS) has jurisdiction over terrestrial and freshwater ecosystems
and the National Marine Fisheries Service (NMFS) has jurisdiction over marine
ecosystems. Protected biological resources include sensitive habitats and
species under consideration for listing (candidates species) or listed as
threatened or endangered by the United States FWS or by individual States.
Sensitive habitats include areas protected by legislation or are habitats
of concern to regulating agencies. Endangered species are presented in a
separate subsection.
Some of the habitats that characterize the border zone are desert, aquatic,
riparian, and mountainous regions. As previously mentioned, the border zone
contains sections of both the Chihuahuan and Sonoran Deserts. Rainfall in
the desert is less than 10 inches per year and grasses cannot survive. This
arid region is subject to the most extreme weather fluctuations in the country.
During the day, intense sunlight raises air and soil temperatures very high
and at night the heat is lost rapidly. Most desert animals are active primarily
at night or during the brief periods in early morning and late afternoon
when the heat is not so intense. The major scrub forests of the United States
are the chaparral and coastal sage scrub communities in western California.
The region is dominated by shrubs and multi-stemmed trees that are typically
less than 16 feet in height. Both types of communities are subject to periodic
fires.
Aquatic ecosystems in the border zone consist of freshwater and coastal
ecosystems, and wetlands ecosystems. These resources support a variety of
wildlife. The Rio Grande (spanning Texas, New Mexico, and Colorado) and
the Colorado River (running through California and Arizona) are the major
rivers within the border zone. Additionally, to the east, the Texas border
zone touches the Gulf of Mexico. Wetlands areas are located in transitional
areas of freshwater and saltwater. Riparian ecosystems encompass all terrestrial
areas of relatively high soil moisture that occur adjacent to rivers and
streams. These areas would exist adjacent to the Rio Grande, Colorado River,
and the many tributaries to those rivers. Riparian zones provide habitat
for a wide variety of species. In arid to semi-arid regions, riparian zones
often support the only significant forest habitats and harbor a large number
of wildlife species in comparison to surrounding uplands. The biological
resources of riparian areas are extremely sensitive to changes in water
level, neighboring vegetation, and sedimentation.
Construction activities have the potential to result in habitat destruction.
However, all CMV operations conducted pursuant to the Proposed Action will
occur using existing highway and roadway systems. In addition, all currently
planned roadside inspections would be carried out at existing facilities.
Therefore, no construction activities directly related to the proposed rulemakings
are expected.
Air quality and noise impacts may also effect biological resources, some
of which are very sensitive to the quality of air and the amount of noise
in their habitats. However, as will be discussed in Chapter 4, air quality
and noise impacts associated with the proposed actions are minor.
Since the Proposed Action does not involve activities with the potential
to significantly effect biological resources, these resources will be further
analyzed in Chapter 4.
Invasive Species
In 1999 Former President Clinton issued Executive Order 13112 on invasive
species. This EO directs Federal agencies to identify agency actions that
affect the status of invasive species. An invasive species is an alien species
whose introduction does or is likely to cause economic or environmental
harm or harm to human health. This introduction does not have to be intentional
and most introductions are unintentional. The transportation sector has
contributed to such unintentional introductions. For example, the Asian
Longhorn Beetle was first discovered in the United States in 1996. This
species is believed to have arrived in the United States via cargo ships
from Asia. The Asian Longhorn Beetle is a threat because it eats the insides
of a living tree until it weakens and dies. Since its 1996 discovery in
the Northeastern United States, thousands of trees have been infested. There
are many other examples, including the introduction of the brown tree snake
in Guam by military aircraft during World War II. This species of snake,
originally from New Guinea, has eliminated 9 of 11 species of native birds
and has caused major power outages by climbing on power lines and into electronic
equipment. Introduced plants are not any less of a problem. The introduction
of kudzu in the southeastern states and purple loosestrife in the north,
have choked out native plant species impacting the wildlife and fish of
those regions. Executive Order 13112 has reinforced and expanded DOT agency
efforts to address this issue.
DOT agencies are working with other Federal and State agencies, as well
as the international community in developing strategies to reduce the risk
of invasive species introduction. The importation of goods from Mexico by
CMV can potentially introduce species into the United States within the
transported cargo or on the CMV themselves. However, as noted in Chapters
1 and 2, the promulgation of the four proposed rules will not affect the
cargo imported from Mexico or the use of trailers from Mexico to haul this
cargo.
Since the proposed actions do not include activities with the potential
to affect the status of invasive species, this issue will not be further
analyzed in Chapter 4.
Endangered Species
The Endangered Species Act of 1973 (ESA)20 declares the intention of Congress
to protect all federally listed threatened and endangered species. This
includes both flora and fauna, and their designated critical habitat. Section
7 of the ESA outlines requirements for Federal agencies' actions, whether
authorized, funded or carried out. Federal agencies may not jeopardize endangered
or threatened species or adversely affect critical habitat. Critical habitat,
as defined in the ESA is the specific location within the geographic area
occupied by the species essential to the conservation of the species, which
may require special management consideration or protection.21 Critical habitat
does not include the entire geographic area that can be occupied by the
threatened or endangered species.22
The United States Fish and Wildlife Service (USFWS) is the primary regulatory
agency responsible for compliance of the ESA. The USFWS maintains additional
flora and fauna categories that are not legally protected, but should be
considered during the planning process for any Federal project. These additional
categories are Proposed Threatened, Proposed Endangered, and Candidate Species.
Listed and candidate species-at the Federal and State levels-occur throughout
the United States, although within a relatively small proportion of the
total surface area of the nation.
Since there would be no construction activities associated with the Proposed
Action, any impact to endangered species would only occur as a secondary
impact due to decreased traffic safety, decreased quality of air, or increased
noise disturbance. Some of the resources that could be secondarily impacted
are the several areas of protected habitat in the border zone region. Most
notable is Big Bend National Park as well as Guadalupe Mountains National
Park. Additionally, there are several State parks and wildlife refuges within
the United States-Mexican border zone. The USFWS lists one hundred and fifty
four endangered and threatened species as ranging in the four States (Arizona,
California, New Mexico, Texas) along the United States-Mexican border zone.
Many of these are specific to those States (USFWS 2001).
As will be discussed in Chapter 4, public safety, air quality and noise
impacts associated with the proposed actions would be beneficial and/or
minor, resulting in no significant impacts to endangered species. Therefore
there will be no further analysis of endangered species in Chapter 4.
Water Resources
The water resources of the United States include groundwater and surface
water. Groundwater is found beneath the surface of the earth. Sources of
groundwater include rainfall and surface waters, such as lakes, rivers and
wetlands. These waters penetrate and move through the soil to the water
table.
Much of the nation's drinking water is supplied from groundwater aquifers.
Groundwater is an important source of water supply for municipalities, agriculture,
and industry. Western and Midwestern areas of the United States are generally
much more dependent on groundwater than other areas of the country. Many
of these States depend on groundwater for over 50 percent of their drinking
water needs. Surface waters include rivers, streams, wetlands, and lakes.
Surface and groundwater resources are both used in the border region to
maintain economic development. The availability of water is a critical issue
in the region. Annual rainfall in the region varies from approximately 7
to 25 inches.
Surface water resources include several rivers, streams, and tributaries
as well as two international reservoirs. The chief surface water resource
in the border zone is the Rio Grande River. The Rio Conchos, Rio San Juan,
and Rio Salado are all main tributaries to the Rio Grande, the main international
river in the border region. The Rio Grande not only traverses two countries,
but also three United States states, 19 tribal and pueblo lands and five
Mexican states. The Rio Conchos also feeds the region's two international
reservoirs. Combined, the reservoirs' storage capacity totals 6.05 million
acre-feet of water. These international water resources are governed by
two treaties between the United States and Mexico, established in 1906 and
1944 through the International Boundary and Water Commission. In addition
to the two international reservoirs (Amistad and Falcon) in the border region,
the region contains the United States' Elephant Butte Reservoir, a water
resource for New Mexico and parts of Texas.
Groundwater, also used widely in the border region, is provided through
use of aquifers. One notable aquifer is the Edwards Aquifer in south-central
Texas. It is the chief water supply to more than 2 million people. Much
of the border zone's groundwater sources come from shared Mexican/United
States aquifers. There is no international agreement detailing sharing or
protection of these aquifers (TNRCC 2001).
One method by which the transportation sector may adversely impact water
sources is through the generation of air pollution. The generation of NOx
emissions that mix in the atmosphere with SOX is the biggest potential impact
CMV have on water quality. An increase in emissions of these pollutants
would decrease air quality and in turn, adversely impact water resources
through the creation of acid rain. Acid rain is not a significant problem
in the border crossing region or the Southwest. There are no sensitive bodies
of water in the Southwest due to natural filtration of NOx and SOX emissions
by the land. Acid rain is a problem in the Northeast because the soils are
naturally more acidic and not buffered by lime or other natural elements.
New CMV emission standards in the United States are expected to be implemented
between 2004 and 2007, lowering NOx and PM emissions by almost 90 percent.
Low-sulfur diesel fuel will allow after-treatment with three-way catalytic
converters that will reduce NOx, VOC, CO, PM, and SOX.
Another method by which the transportation sector adversely impacts water
quality is through incidents such as oil and fuel leaks and spills, particularly
from tankers, motor vehicles, and fuel storage tanks. Runoff from roads,
infrastructure construction, and deterioration of discarded vehicles have
an impact on wetlands, surface and groundwater quality as well (United States
DOT/RSPA 2001).
As will be discussed in Chapter 4, air quality impacts associated with the
Proposed Action would be minor, and public safety impacts would be beneficial.
Therefore, water resource impacts would be minimal. As a result, there will
be no further analysis of water resources in Chapter 4.
Cultural, 4(f) and Farmland Resources
Cultural resources consist of prehistoric and historic sites that are important
to a culture. There are four different categories of cultural resources-
prehistoric archaeological resources, paleontological resources, historic/architectural
resources, and Native American resources.
Federal agencies are legally required to consider the effects of a proposed
project on cultural resources. The primary law protecting cultural resources
is the National Historic Preservation Act of 1966 (NHPA).23 It addresses
the identification and preservation of historic properties, as well as coordination
among Federal agencies. The region of influence for cultural resources encompasses
any area potentially affected by the implementation of the Proposed Action
as defined under Section 106 of the NHPA.
Some forms of recreational opportunities and parklands are protected from
impacts due to federal projects. Impacts to coastal, water-dependent recreation
are considered under the Coastal Zone Management Act, whereby potential
impacts may be reviewed and regulated by the administering state. Impacts
to significant publicly owned parks and recreation areas, wildlife/ waterfowl
refuges, as well as certain historic sites, are regulated under Section
4(f) of the Department of Transportation Act.24 These resources are found
throughout the United States and adjacent to roadways and inspection areas.
Farmland is a valuable resource that is often lost to development projects.
The purpose of the Farmland Protection Act is to minimize the extent to
which federal programs convert farmland to non-agricultural uses.25 Soils
classified by the United States Department of Agriculture, Natural Resource
Conservation Service as prime or unique are collectively protected by this
Act. In addition to this federal regulation, several states have enacted
their own regulations to aid in protection of farmland.
Cultural, 4(f) and farmland resources could be indirectly affected through
decreased air quality and increased acid rain as a result of increased emissions
from CMV or through changes to topographical or geological resources. Considering
the history and culture of the region, it is reasonable to foresee that
substantial resources from several cultures, including Native American,
Tejano, Mexican, and Latino, are located in this border region. Realizing
the distinct history and heritage that the southwest holds, it follows that
there are many sites of cultural, 4(f) and farmland resources protected
in the Border States.
As will be discussed in Chapter 4, air quality impacts associated with the
proposed actions would be minor. As a result, impacts on cultural, 4(f)
and farmland resources would be minimal. Therefore there will be no further
analysis of cultural, 4(f) and farmland resources in Chapter 4.
Visual Resources
Visual resources can be defined as the physical features of a landscape
that affect the viewer's perception of the vista. Mountains, rivers, plains,
buildings, power lines and roads are natural and human- made landscape features
that contribute to the impression the landscape makes on its viewers. Within
the United States, there are four general landscape types, natural, rural,
urban, and transitional settings.
Each type is identified by the relative dominance of natural and artificial
features present. All of these types of visual resources are subject to
be affected by the proposed actions. These effects would most likely occur
through secondary impacts of increased CMV emissions that may deteriorate
air quality. Deterioration in air quality can lead to significant obstructions
of views and vistas through the formation of haze and smog. These issues
are covered in the air quality section.
Natural landscapes are classified as those areas dominated by physiographic
landforms and pristine natural scenes and where there is an absence of all
human influence. Rural landscapes are classified as areas that include small
towns and villages, sparsely distributed homes, agricultural fields, silos,
barns, and ranging livestock. Urban landscapes are classified as areas dominated
by human activity and infrastructure. Transitional landscapes occur within
the classifications of any of the above three types.
Within the border zone, all four types of landscapes can be seen. These
visual resources can be classified as natural, rural, urban, and transition
landscapes. Most notable natural landscapes would be those within Guadalupe
Mountains and Big Bend National Parks. Specifically, parts of Rio Grande
as it flows through Big Bend National Park have been designated as "wild
and scenic" under the Wild and Scenic Rivers Act, and thus protected.
However, there are many more areas that could be considered as visual resources
than just those spaces within the National Parks. Rural landscapes occur
in the more pastoral areas across the border zone. Most of the actual border
crossings are more typical of urban landscapes and transitional landscapes
bridge the many visual resources mentioned.
As will be discussed in Chapter 4, air quality impacts associated with the
proposed actions are minor, so there will be no further analysis of visual
resources in Chapter 4.
4. ENVIRONMENTAL CONSEQUENCES
This Chapter of the PEA addresses the potential environmental consequences
associated with the Baseline, No Action, and Proposed Action Alternatives.
The analysis focuses primarily on the environmental impacts associated with
changes in the number of Mexican CMV operated and inspected under the three
alternatives. As in Chapter 2, the analysis for each potential environmental
impact area is divided into two subsections, the first addressing the impacts
of the Mexico-domiciled CMC application process, and the second addressing
the impacts from FMCSA's safety monitoring of Mexican CMV. A summary is
provided that considers the total potential impact. The potential impacts
are quantified, and direct comparisons between the alternatives are made,
where possible.
Five of the areas of potential concern identified in Chapter 3 are discussed
in detail in this Chapter. These five areas were selected because they may
be directly impacted by the operation or inspection of CMV, or because direct
impacts in these environmental areas could result in secondary impacts in
other environmental areas. For example, direct impacts on air quality may
cause secondary impacts on biological resources, water resources, visual
resources, or endangered species. The Transportation and the Public Safety
areas were analyzed to determine the probable affect that the alternatives
would have on traffic congestion and safety involving CMV. The Air Quality
and Noise areas were analyzed to determine how emission levels of air pollutants
and noise would potentially be affected by the alternatives. Finally, the
Socioeconomics area was analyzed to determine whether the distribution of
impacts would disproportionately affect minority or low-income communities.
4.1. TRANSPORTATION
This section addresses the potential effects on traffic and congestion from
the current baseline conditions, the No-Action alternative, and the Proposed
Action.
4.1.1 Applications for Operating Authority
Baseline - Moratorium Retained with Current Application Forms
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and FMCSA would take no action to modify its current
application forms OP-2 and OP-1 (MX) for Mexico-domiciled CMC. Mexico-domiciled
CMC would use the existing Form OP-2 to apply for operating authority within
the border zone, or the existing Form OP-1 (MX) to apply for operating authority
beyond the border zone. With the moratorium in place conditions, FMCSA would
continue to be prevented from processing OP-1 (MX) applications, and thus
Mexico-domiciled CMC would not receive authority to operate beyond the border
zone. FMCSA would continue to receive approximately 1,300 new applications
annually from Mexico-domiciled CMC seeking authority to operate in the United
States. Under baseline operating conditions, the amount of goods imported
from Mexico may continue to increase at approximately 9% per year. This
increase in the amount of goods imported from Mexico may cause an increase
in the number of northbound truck crossings from Mexico into the United
States. With the moratorium in place, most goods would continue to be delivered
to transfer stations on the U.S side of the border, where the trailer and/or
the goods would be transferred to a United States CMV. These goods would
then be delivered by a United States CMV to their intermediate or final
destinations throughout the United States. Many of these goods would continue
to be carried across the border by drayage carriers whose sole fiction is
to ferry goods from transfer stations along the border in Mexico to transfer
stations within the United States border zone.
Therefore, under baseline operating conditions, the total volume of goods
imported from Mexico in 2002 could be approximately 36 million United States
short tons, of which approximately 75%, or 27 million United States short
tons, may be transported by truck. This amount of trade could generate approximately
5 million northbound truck crossings from Mexico into the United States
in FY 2002. These truck crossings could continue to be made by both United
States-domiciled CMC and Mexico-domiciled CMC with authority to operate
in the United States. FMCSA estimates that 10,800 Mexico-domiciled CMC would
operate approximately 71,500 CMV within the border zone in FY2002, all pursuant
to OP-2 authority. This volume of traffic could continue to cause congestion
problems at the border and along the major transportation corridors leading
into the United States from Mexico.
No-Action - Moratorium Modified with Current Application Forms
Under the No-Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its current application forms for
Mexico-domiciled CMC - OP-2 and OP-1 (MX). Under this alternative, Mexico-domiciled
CMC would be eligible to receive authority to operate their CMV both within
the border zone pursuant to OP-2 authority and throughout the United States
pursuant to OP-1 (MX) authority, and would thus be permitted to transport
their freight to intermediate or final destinations throughout the United
States.
As discussed in Chapter 2, the FMCSA expects that the No Action Alternative
may cause a slight increase in the total amount of goods imported into the
United States from Mexico. In addition, economic opportunities created by
the No Action Alternative could result in an approximate 10% increase in
the annual number of Mexico-domiciled CMC applying for new authority to
operate in the United States. As a result, FMCSA estimates that 11,000 Mexico-domiciled
CMC would be authorized to operate approximately 73,000 CMV within and beyond
the border zone in FY 2002. However, a portion of the increase in the number
of Mexican CMV actually traveling within or beyond the border zone should
be offset by a decrease in the number of United States CMV traveling these
same routes. In addition, the increase in the number of Mexican CMV represents
a very small fraction of the approximately 4.5 million CMV currently operating
in the United States .
This modest increase in trade and in the total number of Mexico-domiciled
CMC with authority to operate CMV in the United States, compared to Baseline
conditions, should not exacerbate the current traffic and congestion problems
at the border.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Alternative, a Presidential order would modify
the moratorium and FMCSA would revise its current application forms OP-2
and OP-1 (MX) for Mexico-domiciled CMC, in order to improve FMCSA's capability
to determine the willingness and ability of Mexico-domiciled CMC to comply
with United States CMC safety regulations. Thus, under this alternative,
Mexico-domiciled CMC could be eligible to receive authority to operate their
CMV both within the border zone pursuant to the revised OP-2 authority,
and throughout the United States pursuant to the revised OP-1 (MX) authority.
Under the second rule, CMC intending to operate beyond the border zone pursuant
to OP-1(MX) authority would be subject to a safety audit prior to receiving
authority to operate in the United States. FMCSA expects that this requirement
should not affect the total number of Mexican CMV operating in the United
States nor the total number of Mexican CMV inspections, because the operations
of carriers that fail the safety audit should be replaced by the operations
of carriers that pass the audit. By requiring a pre- authority safety audit,
FMCSA should be able to better ensure that only safe CMC would operate in
the United States. Ensuring the safe operation of CMV would improve overall
highway safety and result in a decrease in the total number of CMV crashes.
A decrease in CMV crashes should cause a decrease in crash-related congestion.
This could result in a beneficial impact on transportation and congestion
both within the border zone and throughout the United States. This effect
is difficult to quantify but is expected to be minor, however, given the
proportion of Mexican to total CMV operating throughout the United States.
As discussed in Chapter 2, the FMCSA expects that the Proposed Action Alternative
should have no effect on the total amount of goods imported into the United
States from Mexico relative to the No Action Alternative. However, economic
opportunities created by the Proposed Action would result in an increase
of approximately 5% in the annual number of Mexico-domiciled CMC applying
for new authority to operate in the United States. FMCSA expects that the
increase in the number of new applications from Mexico-domiciled CMC could
be less under the Proposed Action Alternative than under the No Action Alternative
because the revised application forms would deter some applicants that would
not be able to demonstrate their willingness and ability to comply with
United States safety regulations. Thus, the FMCSA estimates that 10,900
Mexico-domiciled CMC could be authorized to operate approximately 72,000
CMV within and beyond the border zone.
Therefore, while the total number of Mexico-domiciled CMC with authority
to operate their CMV in the United States may increase under the Proposed
Action Alternative compared to the Baseline conditions, it would decrease
relative to the No Action Alternative. However, since the changes in the
number of Mexican CMV are a very small fraction of total United States CMV
operations, they would have a very minor impact on the current traffic and
congestion problems at the border. In addition, as discussed in Chapter
2, the Proposed Action Alternative should not affect the total amount of
goods transported between the United States and Mexico, which would continue
its approximate 9% rate of increase experienced under Baseline conditions.
Since the total amount of trade would be unchanged from the No Action Alternative,
the total number of northbound truck crossings also would not change from
the 9% rate of increase expected under the No Action Alternative operating
conditions. Therefore, increases in the number of Mexican CMV actually operating
within or beyond the border zone compared to the Baseline alternative would
be largely offset by a decrease in United States CMV operating along those
same routes. Likewise, a decrease in the number of Mexican CMV in operation
compared to the No Action Alternative would be largely offset by an increase
in the number of United States CMV in operation along those same routes.
Thus, this part of the Proposed Action Alternative would not further impact
transportation systems at the border or in the United States when compared
to the conditions under either the Baseline or No Action Alternatives.
4.1.2 Safety Monitoring for Mexico-Domiciled Motor Carriers
Baseline - Moratorium Retained with Current Safety Monitoring Program
Under a continuation of current baseline operating conditions, with the
moratorium unmodified, Federal, State and local authorities would conduct
safety inspections of United States, Canadian, and Mexican CMV at the border,
at designated roadside inspection stations throughout the United States,
at individual carriers' places of business, or at any point along the roadway
system. The safety monitoring for Mexican CMV would be largely limited to
monitoring border zone operations since most Mexico-domiciled CMC operations
would be confined to the border zone. These inspections would not include
verification of compliance with the FMVSS labeling requirement.
Based on current and projected numbers of inspections, including FMCSA'
s anticipated addition of 85 new Federal inspectors, FMCSA estimates that
2.77 million total CMV inspections could occur in the United States in 2002,
with approximately 170,000 of these inspections involving Mexican CMV. These
safety inspections take between 40 to 50 minutes to complete. The inspection
process involves selecting one CMV for inspection per inspection area at
a time, with fixed inspection stations often accommodating several inspection
areas. Since the inspection process at fixed locations involves choosing
CMV out of the lines for the weigh stations, at a rate of one CMV per inspection
area at a time, the potential effect of inspections on congestion at and
around the inspection stations is minimized.
No-Action - Moratorium Modified with Current Safety Monitoring Program
Under the No Action Alternative, the FMCSA would take no action to modify
its current inspection and review authority after the Presidential order
to modify the moratorium is implemented. FMCSA expects that once the moratorium
is modified, some Mexico-domiciled CMC could apply for and receive authority
to operate beyond the border zone. FMCSA would continue conducting inspections
on Mexican CMV following the same guidelines used for United States and
Canadian CMV. These inspections would occur both within and beyond the border
zone, and would continue to occur at the border, at designated roadside
inspection stations, at individual carriers' places of business, or at any
point along the roadway. These inspections would not include verification
of compliance with the FMVSS labeling requirement.
As the number of Mexican CMV operating the Unites States increases, and
the length of the trips these CMV make increases, the number of inspections
performed on Mexican CMV will likely increase as well. In addition, FMCSA
will continue to deploy additional inspectors at the border, as described
under the Baseline Scenario. FMCSA estimates that 2.78 million total CMV
inspections would occur in the United States in 2002, with approximately
180,000 of these inspections involving Mexican CMV. All inspections would
continue occurring at existing facilities. The safety inspections performed
on Mexican CMV should occur throughout the United States, and would not
be limited to the border zone. In addition, since the total number of inspections
in the United States should increase only marginally, there should be only
a minor effect on transportation from the No Action Alternative.
Proposed Action - Moratorium Modified with Revised Safety Monitoring Program
for Mexico-Domiciled Motor Carriers
Under the Proposed Action, a Presidential order to modify the moratorium
would be implemented and FMCSA would promulgate two new safety monitoring
rules. The first rule would establish a safety monitoring system for all
new applicant Mexico-domiciled CMC operating within and beyond the border
zone. This system would include safety audits and compliance reviews to
ensure that Mexico-domiciled CMC comply with applicable safety regulations
and conduct safe operations within the United States. The second rule would
allow FMCSA to enforce CMC compliance with the FMVSS labeling requirement.
FMCSA expects that once the moratorium is modified, some Mexico-domiciled
CMC would apply for and receive authority to operate beyond the border zone.
Under the Proposed Action Alternative, the revised Safety Monitoring System
would monitor the operation of Mexican CMV within and beyond the border
zone. FMCSA would continue conducting inspections on Mexican CMV following
the same guidelines used for United States and Canadian CMV. These inspections
would take place at the border, at designated roadside inspection stations,
at individual carriers' places of business, or at any point along the roadway.
These inspections would include verification of compliance with the FMVSS
labeling requirement.
As discussed in Chapter 2, FMCSA expects the trends in the total number
of inspections identified under the No Action Alternative to continue. As
a result, FMCSA estimates that there could be the same schedule of inspections
as under the No Action Alternative, with approximately 180,000 inspections
of Mexican CMV in 2002, and a total number of CMV inspections in the United
States of 2.78 million. All inspections would occur at existing facilities
throughout the United States, using the same resources as those that would
be used under the No-Action scenario. Thus, there would be no change on
transportation from the inspections schedule under this part of the Proposed
Action.
Therefore, the implementation of these rules should not result in any additional
congestion at and around the inspections stations. In addition, as will
be discussed further in the next section on Public Safety, the Mexican CMV
that do not comply with safety regulations and standards would be put out-of-service,
thus removing them from the roadways. By removing unsafe CMV from the transportation
system, overall highway safety should improve and result in fewer CMV crashes.
A decrease in CMV crashes would result in a decrease in safety-related congestion.
This would result in a beneficial impact on transportation and congestion
within and beyond the border zone. This effect is difficult to quantify
but would likely be minor, given the proportion of Mexican to total CMV
operating throughout the United States under this part of the Proposed Action.
Commercial Vehicle Safety Alliance Decal - Proposed Requirement:
Under the Proposed Action, Mexico-domiciled CMC granted provisional operating
authority pursuant to Form OP-1 (MX) would be required to maintain a current
CVSA decal on all their CMV operating within the United States. In addition,
CMC would be required to maintain current CVSA decals on their CMV for three
years after receiving permanent OP-1 (MX) authority. FMCSA estimates that
this requirement could result in 230,000 Mexican CMV inspections in 2002.
The additional inspections are necessary to meet the CVSA requirement of
four yearly inspections for Mexican CMV operating pursuant to OP-1 (MX)
authority. It was assumed that the average number of inspections per Mexican
CMV operating pursuant to OP-2 authority should be the same as that under
the Proposed Action and No Action scenarios. Thus, the total number of CMV
inspections in the United States should be 2.83 million. However, these
inspections would be carried out at the same locations as inspections under
the previous scenarios, or at other existing facilities where CVSA decal
inspections currently take place. Since the increase in inspections represents
a very small fraction of total nationwide inspections, there should be negligible
effects on transportation and congestion from the intensified schedule of
inspections for Mexican CMV.
As will be discussed further in the next section on Public Safety impacts,
the increased number of inspections required by this alternative would help
to ensure the safe operation of Mexican CMV in the United States, because
CMV that do not pass inspections will be placed out-of-service and removed
from the roadways. By removing unsafe CMV from the transportation system,
overall highway safety could improve and result in fewer CMV crashes. A
decrease in CMV crashes would cause a decrease in crash-related congestion.
This could result in a beneficial impact on transportation and congestion
both within the border zone and throughout the United States. This effect
is difficult to quantify but is expected to be minor, given the proportion
of Mexican to total CMV operating throughout the United States.
4.1.3 Summary of Impacts of the Proposed Action on Transportation
No Action - Moratorium Modified with Current Application Forms and Current
Safety Monitoring Program
The potential transportation impacts of the No Action Alternative were determined
by combining the analysis performed for the two categories of regulatory
actions used in this study: applications for operating authority, and safety
monitoring system. The No Action Alternative could result in an increase
in the number of Mexican CMV operating and being inspected in the United
States relative to the Baseline Scenario. The contribution of these increases
compared to nationwide operations and inspections on CMV is very minor.
In addition, these minor increases in the number of Mexican CMV operating
within the United States could be further reduced by an offset from the
reduction in the operations associated with those United States CMV trips
replaced by trips carried out by some of the new entrant Mexican CMV operating
within the United States. Furthermore, inspections on Mexican CMV would
no longer be restricted to the border zone but could occur anywhere in the
United States. Thus, the No Action Alternative could result in very minor
adverse impacts to transportation and congestion in the United States.
Proposed Action - Moratorium Modified with Revised Application Forms and
Revised Safety Monitoring System
The potential transportation impacts of the Proposed Action Alternative
were determined by combining the analysis performed for the two categories
of regulatory actions used in this study: applications for operating authority,
and safety monitoring program (including implementation of the CVSA requirement).
The resulting numbers of Mexican CMV operating and being inspected were
compared to those calculated under the Baseline Scenario and the No Action
Alternative. When compared to the Baseline Scenario, the Proposed Action
could result in a marginal increase in the number of Mexican CMV operating
in the United States. In addition, there could be an increase in the number
of inspections on Mexican CMV. When compared to the No Action Alternative,
the Proposed Action could result in a marginal decrease in the number of
Mexican CMV operating within the United States. In addition, there could
be an increase in the number of inspections on Mexican CMV.
Although there is a slight increase in the number of Mexican CMV operating
within the United States when considering the combined effect of the No
Action Alternative and the implementation of the Proposed Action, this increase
is a result of the No Action Alternative and not the Proposed Action itself.
In fact, the Proposed Action results in a slight reduction in the number
of Mexican CMV operating in the United States. However, the changes in resulting
numbers of Mexican CMV are negligible when compared to national operations
of CMV. Further, any increase in the number of Mexican CMV operating in
the United States would be largely offset by a decrease in United States
CMV operating along these same routes.
The increases in the number of inspections on Mexican CMV would not have
an effect on transportation since these inspections would be dispersed throughout
the United States. In addition, there could be safety benefits from the
increased inspections that could result in transportation benefits from
the reduction of crashes and other safety related incidents, which lead
to congestion. Therefore, the implementation of the Proposed Action could
result in a beneficial impact to transportation and congestion in the United
States. This effect would be minor given the proportion of Mexican to total
CMV operating throughout the United States.
4.2. PUBLIC SAFETY AND HEALTH
This section addresses the potential effects on public safety and health
from the Baseline, No Action, and Proposed Action. A more detailed analysis
of the safety benefits associated with the proposed rules can be found in
the "Regulatory Analysis and Regulatory Flexibility Analysis"
documents developed by the FMCSA to evaluate the costs and benefits of the
Proposed Action.
4.2.1 Applications for Operating Authority
Baseline - Moratorium Retained with Current Application Forms
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current application forms would not be revised.
Mexico- domiciled CMC would remain largely limited to operating in the border
zone. Most goods imported from Mexico by CMV would continue to be carried
across the border by drayage carriers and delivered to transfer stations
in the border zone. United States- domiciled CMC would continue to transport
these goods from the transfer stations to their intermediate or final destinations
throughout the United States.
No-Action - Moratorium Modified with Current Application Forms
Under the No Action Alternative, the moratorium would be modified by Presidential
order and FMCSA would take no action to revise its current application forms
OP-1(MX) and OP-2 for Mexico-domiciled CMC. Mexico-domiciled CMC would become
eligible to operate beyond the border zone. As a result, FMCSA assumes some
goods previously imported across the border by Mexican drayage carriers
may be imported by Mexican long-haul carriers. Likewise, Mexico-domiciled
CMC may transport some goods previously transported to transfer stations
in the border zone directly to final destinations in the United States.
The potential shifting of trips from Mexico-domiciled drayage carriers to
long-haul carriers may occur as some goods are delivered directly from Mexico
to final destinations in the United States. The long-haul fleet may make
these trips across the border in lieu of the drayage fleet, which is typically
not maintained in a condition that allows for long distance cross-country
trips. As discussed in Chapter 3, the out-of-service rate for the Mexican
long-haul fleet is substantially better than the rate for the Mexican drayage
fleet. This indicates that the Mexican long-haul fleet is better maintained
and safer than the drayage fleet. Thus, a shift from drayage carriers to
long-haul carriers may result in a beneficial impact to public safety.
The shifting of trips from Mexico-domiciled long-haul carriers to United
States-domiciled long-haul carriers may occur as some goods are delivered
directly from Mexico to final destinations in the United States. The Mexican
long-haul fleet may replace a small segment of the United States long-haul
fleet for those trips where it may be economically efficient for a Mexican
CMV to make the trip. As discussed in Chapter 3, the Mexican long-haul fleet
has an out-of-service rate comparable to the rate for the United States
long-haul fleet. Thus, the shift from United States to Mexican long-haul
CMV would not result in an impact to public safety.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Altemative, the moratorium would be modified by
a Presidential order and the FMCSA would revise its current application
forms OP-2 and OP-1 (MX) for Mexico-domiciled CMC. The revision of the application
forms should improve FMCSA's capability to determine the willingness and
ability of Mexico-domiciled CMC to comply with United States safety standards.
This should improve FMCSA's ability to identify unsafe CMC and deny them
operating authority. As under the No Action Alternative, Mexico-domiciled
CMC would become eligible to operate beyond the border zone. As a result,
some goods previously imported across the border by Mexican drayage carriers
may be imported by Mexican long-haul carriers. Some goods previously transported
from transfer stations in the border zone to final destinations in the United
States by United States-domiciled CMC could instead be transported by Mexico-domiciled
CMC. The number of trips made by Mexican carriers as opposed to United States
carriers could be lower under the Proposed Action Altemative than under
the No Action Alternative.
Under the second rule, Mexican CMC seeking to operate beyond the border
zones under Form OP-1(MX) authority would be subject to a safety audit,
prior to receiving authority to operate within the United States. This requirement
should create a more stringent screening process for applicants that should
improve the ability of the FMCSA to deny entry to the highest risk Mexico-domiciled
CMC. The decrease in the number of unsafe Mexican trucks and buses on the
roadways should promote public safety and health by reducing the number
of incidents associated with the operation of unsafe Mexican CMV in the
United States. The total number of accidents,-and related injuries and fatalities,-potentially
avoided by this requirement is difficult to quantify. This requirement should
result in an overall benefit to public health and safety, by reducing the
number and proportion of high-risk CMC and CMV operating in the United States.
The revision of the application forms under this alternative may improve
FMCSA's ability to screen applicants for either OP-1(MX) or OP-2 authority.
The revised application forms would require applicants to provide more detailed
information regarding the nature of their operations. Mexican carriers would
plan for ensuring compliance with United States safety laws and regulations.
The carriers would provide contact points for taking enforcement action
against the carriers for violations, and other information that could be
used by FMCSA's safety monitoring resources. These revisions would result
in a beneficial impact on public safety. The proportion of Mexico-domiciled
CMC to all CMC conducting operations in the United States is small, so this
benefit will be minor.
The revision of the applications forms under the Proposed Action Alternative
may provide the greatest benefit to public safety. The shift from drayage
to long-haul fleets for transporting goods across the border could result
in a benefit when compared to a continuation of the Baseline conditions.
There may be no impact to public safety from the shift between Mexican and
United States long-haul carriers. The implementation of the Proposed Action
could result in a beneficial impact to public safety relative to both a
continuation of Baseline conditions or implementation of the No Action Alternative.
The benefit may be greater in the border zone where a higher proportion
of trips involve Mexico imported goods.
4.2.2 Safety Monitoring for Mexico-Domiciled Motor Carriers
Baseline - Moratorium in place with Current Safety Monitoring Program
Under a continuation of the current Baseline operating conditions, the moratorium
would remain unmodified and the current safety monitoring program would
not be revised. Eligible Mexico-domiciled CMC applying for operating authority
would continue to receive permanent certificates of authority. Mexico-domiciled
CMC would remain largely limited to operating in the border zone, so safety
inspections of Mexican CMV would continue to occur predominantly at the
United States-Mexico border. Safety inspections would remain the primary
tool used by Federal, State and local authorities to help ensure the safe
operation of all CMV. These inspections would not include verification of
CMC compliance with the FMVSS labeling requirement. Mexican CMV operating
in the United States would be inspected approximately two to three times
per year on average.
No-Action - Moratorium Modified with Current Safety Monitoring Program
Under the No Action Alternative, the moratorium would be modified by Presidential
order and FMCSA would take no action to revise its safety monitoring program.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent certificates of authority. Mexico-domiciled CMC could
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV could occur both at the United States-Mexico border and at other
inspection locations throughout the United States. Safety inspections would
remain the primary tool used by Federal, State and local authorities to
help ensure the safe operation of all CMV. These inspections would not include
verification of CMC compliance with the FMVSS label requirement. Mexican
CMV operating in the United States would continue to be inspected approximately
two to three times per year on average.
Under the No Action Alternative, there would be no impact on public safety.
As the range of Mexico- domiciled CMC operations expand beyond the border
zone, a larger number of Mexican CMV inspections would occur at inspection
stations beyond the border zone. The inspection procedures used at these
inspection stations are the same as the inspection procedures used at the
United States-Mexico border. Thus, the likelihood that an unsafe condition
on a CMV could be discovered may be the same at both inspection locations.
As a result, there may be no public safety impact as a result of inspecting
Mexican CMV at both the border and throughout the United States.
Proposed Action - Moratorium Modified with Revised Safety Monitoring System
for Mexico-Domiciled Motor Carriers
Under the Proposed Action Alternative, the moratorium would be modified
by Presidential order. The FMCSA would promulgate two rules to revise its
safety monitoring program. Eligible Mexico-domiciled CMC applying for operating
authority would receive provisional certificates of authority for 18 months.
As under the No Action Alternative, Mexico-domiciled CMC could be eligible
to operate beyond the border zone, so safety inspections of Mexican CMV
should occur both at the United States-Mexico border and at other inspection
locations throughout the United States. All Mexico-domiciled CMC, including
carriers with current certificates of authority, would be required to re-apply
using the revised applications forms set forth in the first two rules. In
addition to the safety inspections used by Federal, State and local authorities,
FMCSA would also conduct at least one safety audit or compliance review
while a carrier was operating under a provisional authority. Both the safety
inspections and the safety audits could be used as tools to help ensure
the safe operation of Mexican CMV. Safety inspections would include verification
and enforcement of CMC compliance with the FMVSS labeling requirement. Mexican
CMV operating in the United States should continue to be inspected approximately
two to three times per year on average.
By granting provisional operating authority to Mexico-domiciled CMC and
conducting a safety audit or compliance review prior to granting permanent
authority at the completion of the 18-month period, FMCSA may improve its
oversight of CMC operations. By focusing its improved oversight on the initial
18-month period of CMC operations in the United States FMCSA should be more
likely to identify and reform unsafe CMC practices that relate to the CMC's
inexperience with United States safety regulations. FMCSA should take expedited
action against carriers found to have committed certain identified violations
of the regulations. These actions may result in a benefit to public safety.
By requiring Mexico-domiciled CMC with existing certificates of authority
to re-apply using the revised forms OP-1 (MX) and OP-2, FMCSA should enhance
its oversight of these CMC's operations. These requirements may result in
a benefit to public safety.
Through verification and enforcement of the FMVSS labeling requirement,
FMCSA would ensure that all CMV operating in the United States were manufactured
in compliance with the FMVSS requirements in place on the date of their
manufacture. These FMVSS requirements help ensure that CMV are free from
defects or other conditions that could make their operation on the roadways
unsafe. The verification and enforcement of the labeling requirement may
result in a benefit to public safety.
Commercial Vehicle Safety Alliance Decal - Proposed Requirement:
Under this proposed requirement, all Mexico-domiciled CMC granted provisional
operating authority under Form OP-1 (MX) would be required to maintain a
current CVSA decal on all their CMV operating within the United States.
In addition, CMC would be required to maintain current CVSA decals on their
CMV for three years after receiving permanent OP-1 (MX) authority. FMCSA
estimates that this requirement could increase the average number of inspections
for CMV operating pursuant to OP-1 (MX) authority to approximately four
inspections per year. The increase in the average annual number of inspections
performed on CMV may provide a benefit to public health and safety. The
benefit could be realized in three ways.
Firstly, the increase in the average annual number of inspections per vehicle
increases the probability that an individual unsafe vehicle could actually
be inspected in a given year. This increases the likelihood that the safety
hazard on the unsafe vehicle may be discovered, that the unsafe vehicle
could be removed from the roadway. As the likelihood of discovering unsafe
vehicles increases, the actual number of unsafe CMV discovered and placed
out of service should increase, thereby decreasing the number of unsafe
vehicles on the roadway.
Secondly, as the number of unsafe vehicles discovered and placed out-of-service
increases, the economic losses for CMC that operate these unsafe vehicles
should increase. An increase in economic losses could create an economic
disincentive for those carriers to continue operating unsafe vehicles. This
may provide an economic incentive to properly maintain the vehicles. An
economic incentive to properly maintain vehicles may result in a greater
number of safe vehicles on the roadway.
Thirdly, increasing the average annual number of inspections per vehicle
should result in an average increase in the frequency of inspections per
vehicle. As the average frequency of inspections increases, the average
length of time between inspections becomes shorter. As the average length
of time between inspections becomes shorter, the potential period of time
during which a safety hazard on an individual vehicle may go undetected
should decrease. As the period of time that a safety hazard may go undetected
decreases, the amount of time that the public could be exposed to that hazard
should decrease, resulting in a decrease in overall risk to public safety.
4.2.3 Summary of Impacts of the Proposed Action on Public Safety and Health
No Action - Moratorium Modified with Current Application Forms and Current
Safety Monitoring Program
The potential public safety and health impacts of the No Action Alternative
were determined by combining the analysis performed for the two categories
of regulatory actions used in this study: applications for operating authority,
and safety monitoring program. The No Action Alternative could result in
an increase in the number of Mexican CMV operating and being inspected in
the United States relative to the Baseline Scenario. The contribution of
these increases compared to nationwide operations and inspections on CMV
is very minor. In addition, a shift from drayage carriers to long-haul carriers
may result in a beneficial impact to public safety due to the better operating
condition of long-haul CMV. This benefit would be minor, however, given
the low proportion of CMV trips transporting goods imported from Mexico.
Under the No Action Alternative inspections on Mexican CMV would no longer
be restricted to the border zone but could occur anywhere in the United
States. Mexican CMV operating in the United States would continue to be
inspected approximately two to three times per year on average. As the range
of Mexico-domiciled CMC operations expand beyond the border zone, a larger
number of Mexican CMV inspections would occur at inspection stations beyond
the border zone. However, there may be no public safety impact as a result
of inspecting Mexican CMV at both the border and throughout the United States.
Proposed Action - Moratorium Modified with Revised Application Forms and
Revised Safety Monitoring Program
The potential public safety impacts of the Proposed Action Alternative were
determined by combining the analysis performed for the two categories of
regulatory actions used in this study: applications for operating authority,
and safety monitoring program (including implementation of the CVSA requirement).
The revision of the application forms should improve FMCSA's capability
to determine the willingness and ability of Mexico-domiciled CMC to comply
with United States safety standards. This should improve FMCSA's ability
to identify and deny operating authority to unsafe CMC. The number of trips
made by Mexican carriers as opposed to United States carriers could be lower
under the Proposed Action Alternative than under the No Action Alternative.
The revisions to the application forms could result in a beneficial impact
on public safety. However, this benefit would be minor given the low proportion
of Mexico-domiciled CMC to all CMC conducting operations in the United States.
In addition, the shift from drayage carriers to long-haul carriers compared
to the Baseline could result in a beneficial impact to public safety.
As under the No Action Alternative, Mexico-domiciled CMC could be eligible
to operate beyond the border zone, so safety inspections of Mexican CMV
should occur both at the United States-Mexico border and at other inspection
locations throughout the United States. The requirements set forth under
the Safety Monitoring System portion of the Proposed Action would help FMCSA
ensure that all Mexican CMV operating in the United States meet United States
safety standards and regulations, thus promoting their safety of operation
within the United States. Thus, the implementation of the Proposed Action
could result in a beneficial impact to public safety relative to either
a continuation of Baseline conditions or implementation of the No Action
Alternative. The benefit may be greater in the border zone where a higher
proportion of trips involve Mexico imported goods.
4.3. AIR QUALITY
This section addresses the potential effects on air quality from the current
Baseline Scenario, the No-Action alternative, and the Proposed Action Alternative.
The EPA emissions models-MOBILE5a and PART5- were used to quantify direct
pollutant emissions resulting from the operation of and inspections on Mexican
CMV. The emissions effects and inventories were calculated based on conservative
average engine emission factors for Mexican CMV and did not take into account
the exclusion of very high emitters. The data and assumptions in this list
are generally very conservative so actual emissions from the operation and
inspection of Mexican CMV are expected to be significantly lower than those
calculated here. The data and assumptions are presented in Appendix C, which
presents detailed information on the modeling methodology, criteria pollutants,
air quality health effects, legislation, current state of the environment,
and source characteristics.
The determination of the contribution of emissions from the operation and
inspection of CMV was carried out by comparing the calculated emissions
with national levels of emissions from all on-road vehicle sources (e.g.,
light-duty and heavy-duty vehicles, commercial and private) and from all
sources combined (e.g., transportation, industrial processes, fuel combustion,
and miscellaneous). Emission values for on-road and "all sources"
were obtained from the National Air Quality and Emissions Trends Report,
1999. Since the transportation sector continues to be a significant source
of air pollutants at the national level, and total emissions continue to
increase, current levels of emissions from the transportation sector are
expected to be higher than those used in this analysis. Thus, the actual
contribution of emissions from CMV operations and inspections should be
lower than those presented here.
4.3.1 Applications for Operating Authority
As discussed in Chapter 2, the increase in the number of Mexican CMV that
would operate within and beyond the border zone once the Presidential order
to modify the moratorium is implemented would be partly offset by a decrease
in the number of United States CMV operating along the same routes. The
rate of replacement is at best difficult to quantify since the fashion in
which Mexican CMC will respond to and operate under the new conditions resulting
from the Presidential order cannot be determined with any degree of certainty
at this time. In addition, the total amount of cargo transported from Mexico
into the United States could increase slightly with the Presidential order
modifying the moratorium.
Therefore, the actual change in emissions under the different scenarios
analyzed would be determined by the difference between the emissions from
the additional trips carried out by Mexican CMV that would start operating
in the United States once the Presidential order to modify the moratorium
is implemented, and the emissions from the trips previously carried out
by United States CMV that would be replaced by those Mexican CMV. Hence,
the emissions profiles of the engines used by United States and Mexican
CMV would determine the difference in emissions for every individual trip
replacement. Since the ratio of replacement and Mexican engine emission
profiles are difficult to predict, a conservative approach was used in this
analysis in order to estimate the significance of any potential air quality
impacts. The level of significance of air quality impacts was determined
based upon the increase in emissions from the operation of the additional
Mexican CMV, with no consideration of the reduction in the number of United
States CMV that would be operating under the No Action Alternative conditions.
Hence, the emissions reduction associated with the decrease in operations
of United States CMV is not considered. Thus, the effect of the Presidential
order to modify the moratorium is overestimated, since the actual increase
in emissions would be lower than that calculated here.
Baseline - Moratorium Retained with Current Application Forms
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current application forms would not be revised.
Mexico-domiciled CMC would use the existing Form OP-2 to apply for operating
authority within the border zone, or the existing Form OP-1 (MX) to apply
for operating authority beyond the border zone. With the moratorium in place,
FMCSA would continue to be prevented from processing OP-1 (MX) applications,
and thus Mexico-domiciled CMC would not receive authority to operate beyond
the border zone.
The FMCSA estimates that there are approximately 4.5 million CMV currently
operating throughout the United States, including United States, Canadian,
and Mexican CMV. The total amount of emissions-for criteria pollutants-generated
by the total number of CMV operating in the United States can be calculated
from the values included in Table C-4. These values were obtained from the
National Air Quality and Emissions Trends Report, 1999. No independent values
are provided for CMV emissions in the report, so a conservative approach
was used, and all emissions from heavy-duty gasoline vehicles and from diesel
vehicles were attributed to CMV. Since not all diesel vehicles are CMV,
the emissions numbers reported here overestimate actual CMV emissions. As
discussed in Chapter 3, the two pollutants of concern for analyzing the
environmental impact of the operation of CMV are NOx and PM. Using the conservative
assumptions stated above, the maximum amount of NOx that would be emitted
under Baseline conditions is 4,094,000 short tons, representing about 48
percent of all NOx on-road vehicle sources. The maximum amount of PM emissions
that would be emitted is 201,000 short tons, representing about 68 percent
of all on-road vehicle sources.
The FMCSA estimates that there are currently a maximum of 63,000 Mexican
CMV operating in the United States under Baseline conditions within the
border zone. FMCSA expects that approximately 10,800 Mexico-domiciled CMC
would operate approximately 71,500 CMV within the border zone in FY2002,
all pursuant to OP-2 authority. The total amount of emissions -for criteria
pollutants-generated by the total number of Mexican CMV projected to operate
within the border zone in FY2002 under Baseline conditions is shown in Table
C-7 in Appendix C. The amount of NOx emitted under the Baseline conditions
would be approximately 1 16,000 short tons or 1.4 percent of all on-road
sources, and approximately half a percent of all national NOx sources. The
amount of PM emissions under Baseline conditions would be approximately
9,400 short tons or 3.2 percent of all on-road/highway sources, and less
than a tenth of a percent of all national PM sources. Figure 4-1 shows the
relative distribution of NOx and PM emissions for Mexican CMV, compared
to those for all CMV-including United States and Canadian, and all other
on-road sources. As shown in the figure, the contribution of emissions from
Mexican CMV to the total for all CMV operating in the United States, and
to all other on-road sources is relatively very small.
No-Action - Moratorium Modified with Current Application Forms
Under the No-Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its current application forms OP-2
and OP-1 (MX) for Mexico-domiciled CMC. Under this alternative, Mexican
CMV would operate within the border zone pursuant to OP-2 authority and
throughout the United States pursuant to OP-1 (MX) authority.
Figure 4-1: Distribution of NOx and PM Emissions from On-Road Sources and
Mexican, United States and Canadian CMV, FY 2002 as a Percent of Weight
The FMCSA estimates that 11,000 Mexico-domiciled CMC would operate approximately
73,000 CMV within and beyond the border zone. FMCSA estimates that approximately
5,900 Mexico-domiciled CMC could operate under the current OP-2 authority
and would operate approximately 39,000 CMV within the border zone. In addition,
FMCSA estimates that approximately 5,100 Mexico-domiciled CMC would receive
OP-1 (MX) authority and operate approximately 34,000 CMV beyond the border
zone. These CMV would necessarily pass through the border zone to reach
their destinations. Therefore, a portion of the emissions associated with
the operation of those CMV operating pursuant to OP-1 (MX) authority would
occur within the border zone. Thus, they are accounted for in the analysis
of the air quality impacts of the No Action Alternative.
The analysis of potential air quality impacts was performed following the
conservative rationale and assumptions explained at the beginning of this
section. In order to evaluate the significance of the emissions from the
operation of Mexican CMV, two different calculations were performed: one
for the emissions within the border zone, also representative of all emissions
in the United States from all Mexican CMV; and the other for those occurring
beyond the border zone, representative of the emissions from those Mexican
CMV operating pursuant to OP-1 (MX) authority. The emissions within the
border zone were calculated under the assumption that the emissions of all
73,000 Mexican CMV would occur within the border zone, which is a conservative
assumption since a portion of the emissions from the CMV operating pursuant
to OP-1 (MX) authority would occur outside the border zone. The total amount
of emissions-for criteria pollutants-generated by the total number of Mexican
CMV that would operate within the border zone under the No Action Alternative-
including those CMV passing through-is shown in Table C-8 in Appendix C.
As discussed in Chapter 3, the two pollutants of concern are NOx and PM.
The maximum amount of NOx potentially emitted by Mexican CMV operating within
the border zone under the No-Action Alternative would be approximately 117,000
short tons or 1.4 percent of all on-road sources and approximately half
a percent of all national NOx sources. This represents an increase of 3,000
short tons of NOx compared to the Baseline scenario. The maximum amount
of PM emissions within the border zone under the No-Action Alternative would
be approximately 9,600 short tons or 3.3 percent of all on-road/highway
sources, and less than a tenth of a percent of all national PM sources.
This represents an increase of approximately 200 short tons of PM compared
to the Baseline scenario. This increase of about 2 percent represents the
emissions change from the No Action Altemative as a result of the reduced
number of OP-2 applicants, but including the CMC that would be applying
for OP-l (MX) authority and operate beyond the border zone. Thus, the No
Action Altemative could result in increased traffic of Mexican CMV in the
border zone, with an associated increase in emissions from the operation
of those Mexican CMV. This increase in emissions results in an insignificant
impact to air quality, given its negligible contribution to all on-road
and national emissions. In addition, as explained before, the increase in
the number of Mexican CMV could be offset by a decrease in the number of
United States CMV, so the increase in emissions should be significantly
lower than that calculated above. Therefore, the No Action Alternative results
in a very small contribution to air emissions within the border zone.
The amount of NOx emitted beyond the border zone under the No Action Alternative
would be approximately 55,000 short tons or 0.6 percent of all on-road sources
and 0.2 percent of all national NOx emissions. The amount of PM emissions
beyond the border zone would be 4,500 short tons or 1.5 percent of all on-road
sources and less than a tenth of a percent of all national PM emissions.
These emissions would be offset by the reduction in emissions from those
United States CMV that would be replaced by the Mexican CMV. Thus, the No
Action Alternative would result in a very small contribution to air emissions
beyond the border zone.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Alternative, the Presidential order would modify
the moratorium and FMCSA would revise its current applications OP-2 and
OP-1 (MX) for Mexico-domiciled CMC. The revision of the application forms
should improve FMCSA' s capability to determine the willingness and ability
of Mexico-domiciled CMC to comply with United States safety standards and
regulations. Under this alternative, Mexican CMV would operate within the
border zone under the revised OP-2 authority and throughout the United States
under the revised OP-1(MX) authority. The FMCSA estimates that approximately
10,900 Mexico-domiciled CMC would operate approximately 72,000 CMV within
and beyond the border zone. FMCSA estimates that 5,800 Mexico-domiciled
CMC would receive OP-2 authority and would operate approximately 38,000
CMV within the border zone. In addition, FMCSA estimates that 5,100 Mexico-domiciled
CMC would receive OP-1 (MX) authority and operate approximately 34,000 CMV
beyond the border zone.
Under the second rule, CMC intending to operate beyond the border zones
under Form OP-1(MX) authority would be subject to a pre-authority safety
audit, prior to receiving authority to operate within the United States
FMCSA expects that this requirement should not affect the total number of
Mexican CMV operating in the United States, or the number of inspections
on those Mexican CMV.
The analysis of the significance of potential air quality impacts associated
with the implementation of the applications part of the Proposed Action
was performed following the conservative rationale and assumptions presented
in the beginning of this section. Thus, the reduction in the number of United
States CMV resulting from their replacement by Mexican CMV is not considered,
so the resulting calculations overestimate the actual change in emissions.
In order to evaluate the significance of the emissions from the operation
of Mexican CMV, two different calculations were performed: one for the emissions
within the border zone, also representative of all emissions in the United
States from all Mexican CMV; and the other for those occurring beyond the
border zone, representative of the emissions from those Mexican CMV operating
pursuant to OP-1 (MX) authority. The emissions within the border zone were
calculated under the assumption that the emissions of all 72,000 Mexican
CMV would occur within the border zone, which is a conservative assumption
since a portion of the emissions from the CMV operating pursuant to OP-1
(MX) authority would occur outside the border zone. The total amount of
emissions generated by the total number of Mexican CMV that would operate
within the border zone under the proposed Action Alternative-including those
CMV passing through-is shown in Table C-9 in Appendix C.
As discussed in Chapter 3, the two pollutants of concern are NOx and PM.
The maximum amount of NOx potentially emitted by Mexican CMV within the
border zone under the Proposed Action Alternative would be 117,000 short
tons or 1.4 percent of all on-road sources and approximately half a percent
of all national NOx sources. This represents a decrease of 2,000 short tons
of NOx compared to the No Action Alternative and an increase of 1,000 short
tons compared to the Baseline Scenario. The maximum amount of PM emissions
within the border zone under the Proposed Action Alternative would be approximately
9,500 short tons or 3.2 percent of all on-road sources and less than a tenth
of a percent of all national PM sources. This represents a decrease of 100
short tons of PM compared to the No Action Alternative and an increase of
100 short tons compared to the Baseline Scenario. The increase in emissions
relative to the Baseline Scenario is a result of increased trade under the
No Action Alternative and not the implementation of the rules. The decrease
in emissions of approximately 1 percent relative to the No Action Alternative
represents the emissions change from the reduced number of Mexican CMV operating
within the border zone that results from the implementation of the two rules
revising Forms OP-2 and OP-1 (MX). However, as noted above, the Mexican
CMV that would not operate in the United States would be replaced by United
States CMV, thereby further reducing any potential air quality benefits
associated with the implementation of the proposed rules. Therefore, the
implementation of this part of the Proposed Action results in a very small
reduction in air emissions within the border zone, relative to the No Action
Alternative.
The amount of NOx and PM emissions beyond the border zone under the Proposed
Action Alternative would be approximately the same as that calculated under
the No Action Alternative since the difference in the number of Mexican
CMV operating beyond the border zone under both scenarios is indiscernible
under the approximation conditions used in this analysis. Thus, the implementation
of this part of the Proposed Action would result in no air quality impacts
beyond the border zone relative to the No Action Alternative. The difference
in emissions compared to the Baseline Scenario would be very small relative
to national levels of emissions, and would be a consequence of the increased
trade under the No Action Alternative and not a result of the implementation
of the revised Forms.
4.3.2 Safety Monitoring for Mexico-Domiciled Motor Carriers
To quantify the magnitude of direct pollutant emissions resulting from the
inspections of Mexican CMV, the EPA emissions models, MOBILE5a and PART5,
were used. MOBILE5a was used to determine emission factors for CO, VOC,
and NOx. PART5 was used to determine emission factors for Pb, S02, PMl0,
and PM2.5. For more detail on the methodology and data used for modeling
please see Appendix C.
Baseline - Moratorium in place with Current Safety Monitoring Program
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current safety monitoring would not be revised.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent certificates of authority. Mexico-domiciled CMC would
remain largely limited to operating within the border zone, so safety inspections
of Mexican CMV should continue to occur predominantly within the border
zone. Safety inspections would remain the primary tool used by Federal,
State and local authorities to help ensure the safe operation of all CMV.
Inspections on Mexican CMV would follow the same guidelines used for United
States and Canadian CMV, and would not include verification of compliance
with the FMVSS labeling requirement. Mexican CMV operating in the United
States would be inspected approximately two to three times per year on average.
FMCSA estimates that 2.77 million total CMV inspections would occur in the
United States in 2002, with approximately 170,000 of these inspections involving
Mexican CMV. All inspections would occur at existing facilities, and all
inspections on Mexican CMV would occur in the border zone since they are
only allowed to operate in that area. Roadside inspections take between
40 to 50 minutes with an engine-on-time (idle) of up to 15 minutes. Table
C-10 in Appendix C shows the emissions calculations for the analysis of
the current baseline conditions. The emissions resulting from the inspections
represent a very small fraction of total emissions in the United States.
Even when considering just the on-road vehicle emissions (not off-road or
from other industries), the contribution from the inspections is still a
very small fraction of these emissions. The main pollutants from cars, trucks,
and buses that EPA targets for regulation are VOC, NOx, CO, and PM. There
have been great reductions of all these pollutants in the last 30 years.
As discussed in Chapter 3, NOx and PM are the main pollutants of concern
that EPA targets when analyzing emissions from heavy-duty vehicles. Current
NOx emissions were calculated to be approximately 2.74 short tons for 170,000
annual inspections of Mexican CMV, or 3.2x10-5 percent of all on-road emissions;
and 44.6 short tons for all 2.77 million inspections on all CMV in the United
States, or 5.2x10-4 percent of all on-road emissions. PM emissions were
calculated at 0.17 short tons or 5.9x10-5 percent of all on-road emissions
in the U.S from 170,000 inspections on Mexican CMV; and 2.84 short tons
for all 2.77 million inspections on all CMV in the United States, or 9.6x10-4
percent of all on-road emissions. The contribution of emissions from inspections
on CMV-Mexican, Canadian, and United States-to total on-road emissions is
negligible. Considering these results and the conservatism of the data and
assumptions used in the analysis, the effects on air quality in the United
States under the current inspection schedule should be negligible.
No-Action - Moratorium Modified with Current Safety Monitoring Program
Under the No Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its safety monitoring program.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent certificates of authority. Mexico-domiciled CMC would
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV would occur within and beyond the United States-Mexico border
zone. Safety inspections would remain the primary tool used by Federal,
State and local authorities to help ensure the safe operation of all CMV.
Inspections on Mexican CMV would follow the same guidelines used for United
States and Canadian CMV, and would not include verification of compliance
with the FMVSS labeling requirement. Mexican CMV operating in the United
States would be inspected approximately two to three times per year on average.
FMCSA estimates that 2.78 million total CMV inspections would occur in the
United States in 2002, with approximately 180,000 of these inspections involving
Mexican CMV. All inspections would continue occurring at existing facilities.
The number of inspections on Mexican CMV should be slightly larger than
under the Baseline scenario, but would occur throughout the United States
and would not be limited to the border zone as is currently the case. However,
all CMV operating beyond the border zone will necessarily pass through the
border zone to reach their destinations and points of origin. Thus, a conservative
approach was used, and it was assumed that all emissions from inspections
of Mexican CMV would occur within the border zone, thereby calculating the
maximum potential air quality impact of the No Action Alternative. Roadside
inspections take between 40 to 50 minutes with an engine-on-time (idle)
of up to 15 minutes. Table C-11 in Appendix C shows the emissions calculations
for the analysis of the No Action Alternative. The calculations were performed
using the same methodology and assumptions used in the Baseline Scenario.
The emissions resulting from the inspections represent a very small percentage
of total on-road emissions in the United States.
As discussed in Chapter 3, NOx and PM are the main pollutants of concern
that EPA targets when analyzing emissions from heavy-duty vehicles. Current
NOx emissions were calculated to be 2.89 short tons for 180,000 annual inspections
of Mexican CMV, or 3.4x10-5 percent of all on-road emissions; and 44.8 short
tons for all 2.78 million inspections on all CMV in the United States, or
5.2x10-4 percent of all on-road emissions. PM emissions were calculated
at 0.19 short tons or 6.3x10-5 percent of all on-road emissions in the U.S
from 180,000 inspections on Mexican CMV; and 2.85 short tons for all 2.78
million inspections on all CMV in the United States, or 1.0x10-3 percent
of all on-road emissions. The contribution of emissions from inspections
on CMV- Mexican, Canadian, and United States-to total on-road emissions
is negligible. Considering these results and the conservatism of the data/assumptions
used in the analysis, the effects on air quality in the United States under
the current inspection schedule are negligible.
Under the No Action Alternative there would be an increase of 0.16 short
tons of NOx emitted when compared to the emissions from Mexican CMV under
the Baseline scenario. The amount of PM emitted from Mexican CMV inspections
would be 0.01 short tons more under the proposed action compared to the
Baseline scenario. This represents an emissions increase of less than half
a percent in NOx and PM emissions from all CMV inspections as a result of
the Presidential order to modify the moratorium. The emissions increase
is a result of the increase in the number of Mexican CMV that could be inspected
under the No Action Alternative as a response to the increase in traffic
of Mexican CMV within the United States. This increase in emissions represents
a negligible fraction of total on-road emissions. Considering these results
and the conservatism of the data and assumptions used in the analysis, the
increase in air emissions under the No Action Alternative represents a very
small contribution to air emissions within the border zone and throughout
the United States.
Proposed Action - Moratorium Modified with Revised Safety Monitoring Program
for Mexico-Domiciled Motor Carriers
Under the Proposed Action Alternative, a Presidential order would modify
the moratorium and FMCSA would promulgate two rules to revise its safety
monitoring program. Eligible Mexico-domiciled CMC applying for operating
authority would receive provisional authority for a period of no less than
18 months. As under the No Action Alternative, Mexico-domiciled CMC would
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV would occur both at the U.S-Mexico border and at other inspection
locations throughout the United States. All Mexico-domiciled CMC, including
carriers with current certificates of authority, would be required to re-apply
using the revised application forms set forth in the first two rules. In
addition to the safety inspections used by Federal, State and local authorities,
FMCSA would also conduct at least one safety audit or compliance review
while a carrier was operating under a provisional authority. Both the safety
inspections and the safety audit would be used as tools to help ensure the
safe operation of Mexican CMV. Inspections on Mexican CMV would follow the
same guidelines used for United States and Canadian CMV, and would include
verification of compliance with the FMVSS labeling requirement. Mexican
CMV operating in the United States. would continue to be inspected approximately
two to three times per year on average.
The inspection schedule would be the same than that under the No Action
Alternative. Since there would be the same number of inspections on Mexican
CMV, the total number of inspections on all CMV also remains the same. As
in the No Action Alternative, these inspections could occur anywhere in
the United States. and would not be limited to the border zone. Since these
inspections include verification of FMVSS compliance, they will be approximately
5 seconds longer, or about a fifth of a percent longer than those inspections
considered under the No Action Alternative and Baseline scenario. The increase
in emissions from this added time was calculated and considered negligible
due to its insignificant contribution to emissions from all inspections
and to emissions from all on-road sources at the national level (see Table
C-11 in Appendix C). Thus, the implementation of the revised Safety monitoring
program should have no impacts to air quality, relative to the No Action
Alternative.
Commercial Vehicle Safety Alliance Decal - Proposed Requirement:
Under the Proposed Action, FMCSA could implement a CVSA requirement, under
which Mexico-domiciled CMC granted provisional operating authority under
Form OP-1 (MX) would be required to maintain a current CVSA decal on all
their CMV operating within the United States. In addition, CMC would be
required to maintain current CVSA decal on their CMV for three years after
receiving permanent OP-1 (MX) authority. FMCSA estimates that this requirement
could result in 230,000 Mexican CMV inspections in 2002. The additional
inspections are necessary to meet the CVSA requirement of four yearly inspections
for Mexican CMV operating pursuant to OP-1 (MX) authority. It was assumed
that the average number of inspections per Mexican CMV operating pursuant
to OP-2 authority would be the same as that under the Proposed Action and
No Action scenarios. This should result in an increase in the number of
Mexican CMV inspections compared to the No Action Alternative and the Baseline
scenario. Thus, the total number of CMV inspections in the United States
should be 2.83 million. These inspections would occur at existing roadside
inspection stations or other existing facilities where CVSA decal inspections
currently take place.
Table C-12 in Appendix C shows the impact on emissions from the 230,000
inspections on Mexican CMV. The calculations were performed using the same
methodology and assumptions used in the Proposed Action Alternative, including
consideration of the slight increment in time for inspection due to the
FMVSS requirement. The emissions resulting from the inspections represent
a very small percentage of total on-road emissions in the United States.
As discussed in Chapter 3, NOx and PM are the main pollutants of concern
that EPA targets when analyzing emissions from heavy-duty vehicles. Projected
NOx emissions were calculated to be approximately 3.7 short tons for 230,000
annual inspections of Mexican CMV, or 4.3x10-5 percent of all on-road emissions;
and 45.6 short tons for all 2.83 million inspections on all CMV in the United
States, or 5.3x10-4 percent of all on-road emissions. PM emissions were
calculated at 0.24 short tons or 8.0x10-5 percent of all on-road emissions
in the U.S from 230,000 inspections on Mexican CMV; and 2.91 short tons
for all 2.83 million inspections on all CMV in the United States, or 1.0x10-3
percent of all on-road emissions.
Under this requirement, there would be an increase of approximately 30 percent
on emissions from inspections on Mexican CMV and an increase of approximately
2 percent on emissions from all CMV, relative to the Proposed Action and
No Action Alternatives. However, the contribution of emissions from inspections
on all CMV nationwide to total on-road emissions is negligible. Considering
these results and the conservatism of the data/assumptions used in the analysis,
the effects on air quality in the United States under the proposed inspection
schedule should be negligible.
4.3.3 Summary of Impacts of the Proposed Action on Air Quality
No-Action - Moratorium Modified with Current Application Forms and Current
Safety Monitoring Program
The potential air quality impacts of the No Action Alternative were determined
by combining the analysis performed for the two categories of regulatory
actions used in this study: applications for operating authority, and safety
monitoring program. The No Action Alternative could result in a maximum
increase in NOx and PM emissions from the operation and inspection of Mexican
CMV of approximately 2 to 3 percent when compared to the emissions calculated
under the Baseline Scenario. The contribution of these emissions compared
to nationwide emissions from all on-road sources is negligible. In addition,
these minor emissions increases could be further reduced by the offset from
the reduction in the emissions associated with those United States CMV trips
replaced by trips carried out by some of the new entrant Mexican CMV operating
within the United States. Thus, the No Action Alternative could result in
very minor contributions to air emissions in the United States.
Proposed Action - Moratorium Modified with Revised Application Forms and
Revised Safety Monitoring Program
The potential air quality impacts of the Proposed Action Alternative were
determined by combining the analysis performed for the two categories of
regulatory actions used in this study: applications for operating authority,
and safety monitoring program (including implementation of the CVSA requirement).
The calculated emission levels were compared to those calculated under the
Baseline Scenario and No Action Alternative. When compared to the Baseline
Scenario, the Proposed Action could result in a maximum increase in NOx
and PM emissions from the operation and inspection of Mexican CMV of approximately
1 percent. When compared to the No Action Alternative, the Proposed Action
could result in a decrease in NOx and PM emissions of approximately 1 to
2 percent. Thus, although there is a slight increase in the emissions of
NOx and PM when considering the combined effect of the No Action Alternative
and the implementation of the Proposed Action, this increase is a result
of the No Action Alternative and not the Proposed Action itself. In fact,
the Proposed Action results in a slight reduction in emissions. Therefore,
the implementation of the Proposed Action could result in a very minor reduction
in air emissions in the United States. The changes in resulting emissions
are negligible when compared to national levels of emissions for the operations
of CMV, all on-road sources, and total emissions from all sources.
4.4. NOISE
Given detailed operational and site information regarding individual inspection
stations throughout the United States, a site-specific analysis of noise
impacts would be possible using the methodology outlined in Appendix E.
With less detailed information the analysis of inspection noise impacts
is limited to generalizations and order-of-magnitude approximations. It
is important to note, however, that in all noise analyses presented herein,
assumptions are made such that any potential error is on the conservative
(i.e., predicting greater noise levels) than would actually occur.
An example of site-specific analysis follows. For a given inspection station,
suppose that the nearest residential dwelling is located 100 ft from the
inspection site. Given this proximity, as well as other assumptions outlined
in Appendix E, FHWA regulations allow for up to 171 hourly heavy truck inspections
at this site prior to consideration of noise mitigation measures. If the
closest dwelling were located 200 ft from the site, up to 319 hourly operations
would be permissible. In addition to the details presented in this section,
FHWA regulations necessitate the analysis of project sound levels with respect
to existing ambient sound levels; see Appendix E. Given that inspection
stations are already situated alongside roads and highways, it is likely
that project sound levels will not require noise mitigation based on these
criteria.
Conversely, if one knew the actual total operations at a given inspection
station, it would then be possible to determine the minimum distance between
the station and a residential dwelling that did not result in impact per
FHWA regulations. A worst-case scenario follows. This analysis utilizes
as a given the FMCSA-estimated yearly total inspections under each of the
three scenarios (baseline, no action, and proposed action), the potential
for inspections 235 days per year (weekdays only with 25 extra days off
for bad weather and holidays), 7 hours of inspections per day (8-hour work
day with 1 hour off for lunch) and a potential 200 inspection stations in
states bordering Mexico. The analysis is conservative in that: (1) inspections
may occur more than 235 days of the year (thus distributing the resultant
noise over a longer time period), (2) inspections may occur any time during
a 24-hour day (resulting in lower hourly-average sound levels), (3) inspections
may potentially occur anywhere within the United States, as opposed to only
within border states and at fixed inspection stations. Given the above-outlined
scenario, on average one would expect approximately 7 hourly inspections,
which indicates mitigation measures need only be considered for residential
dwellings within 30 feet of the inspection station, per FHWA impact criteria.
It should be noted that the numbers of Mexican CMV identified for analysis
herein (between approximately 71,500 and 73,000 vehicles for the various
scenarios outlined below) represent less than 2% of the total number of
such vehicles currently estimated to operate within the United States. While
it is difficult to quantify potential noise impacts of such vehicles over
an expanse of area such as the United States, intuitively the contribution
of noise is relatively small when compared to the overall population of
CMV. Further, given the conservative nature of the assumptions made in deriving
the following scenarios, actual sound levels would be typically very low.
4.4.1 Applications for Operating Authority
Potential noise impact assessments utilize heavy trucks operating at a representative
average speed of 40 mph. The FHWA's Traffic Noise Model (TNM) was utilized
to model hourly equivalent sound levels for sound propagation over an acoustically
hard surface. Further, worst-case scenarios were developed using the following
assumptions: (1) that all United States-Mexico border crossings occur at
the seven ports of entry identified in Chapter 3 (Laredo, Otay Mesa, El
Paso, Brownsville, Hidalgo, Nogales, and Calexico); and (2) that each CMC
utilizes approximately 6.63 CMV. Accordingly, total FMCSA CMC estimates
were scaled by this factor of 1/7 for noise analyses at a single, "worst-case"
site.
Baseline - Moratorium Retained with Current Application Forms
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current application forms would not be revised.
Mexico-domiciled CMC would use the existing Form OP-2 to apply for operating
authority within the border zone, or the existing Form OP-1 (MX) to apply
for operating authority beyond the border zone. With the moratorium in place,
FMCSA would continue to be prevented from processing OP-1 (MX) applications,
and thus Mexico-domiciled CMC would not receive authority to operate beyond
the border zone.
The FMCSA estimates that there are approximately 4.5 million CMV currently
operating throughout the United States, including United States, Canadian,
and Mexican CMV. The FMCSA estimates that there are approximately of 63,000
Mexican CMV operating in the United States under Baseline conditions within
the border zone. FMCSA expects that 10,800 Mexico-domiciled CMC could operate
a maximum of 71,500 CMV within the border zone in FY2002, all pursuant to
OP-2 authority. Using the scaling factor highlighted above, an estimated
10,300 (conservatively rounding up the calculated 10,214) Mexican CMV may
potentially cross the border at one crossing. In order to be very conservative,
it was further assumed that all 10,300 vehicles hypothetically crossing
each location would do so within the same hour. Using these assumptions,
the TNM predicts hourly equivalent sound levels of 76.6 dBA at a distance
of 900 feet. Given the extremely conservative nature of the assumptions
and the calculated noise levels, the baseline scenario would result in indistinguishable
contributions to noise levels.
No Action - Moratorium Modified with Current Application Forms
Under the No-Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its current application forms OP-2
and OP-1 (MX) for Mexico-domiciled CMC. Under this alternative, Mexican
CMV would operate within the border zone pursuant to OP-2 authority and
throughout the United States pursuant to OP-1 (MX) authority.
The FMCSA estimates that 11,000 Mexico-domiciled CMC could operate approximately
73,000 CMV within and beyond the border zone. FMCSA estimates that 5,900
Mexico-domiciled CMC could operate under the current OP-2 authority and
could operate a maximum of 39,000 CMV within the border zone. In addition,
FMCSA estimates that 5,100 Mexico-domiciled CMC would receive OP-1 (MX)
authority and operate 34,000 CMV beyond the border zone. These CMV would
necessarily pass through the border zone to reach their destinations. Therefore,
it is assumed that a seventh of all 73,000 Mexican CMV-or 10,500 (conservatively
rounding up the calculated 10,428) Mexican CMV- could pass through a location
within the same hour. The TNM predicts hourly equivalent sound levels of
76.6 dBA at a distance of 900 feet. Thus, the No Action Alternative results
in no change in noise levels relative to the Baseline scenario. Thus, the
No Action Alternative would result in no noise impacts.
Beyond the border zone, assume that a seventh of all 34,000 Mexican CMV-or
4,900 (conservatively rounding up the calculated 4,857) Mexican CMV-operating
pursuant to OP-1 (MX) authority could pass through a location within the
same hour. The TNM predicts hourly equivalent sound levels of 73.3 dBA at
a distance of 900 feet. In addition, the increase in the number of Mexican
CMV would be offset by a decrease in the number of United States CMV traveling
the same routes. Thus, the No Action Alternative would result in a very
minor increase in noise levels beyond the border zone relative to the Baseline
scenario. Given the extremely conservative nature of the assumptions and
the calculated noise levels, the No Action Alternative would result in negligible
contributions to noise levels.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Alternative, the Presidential order would modify
the moratorium and FMCSA would revise its current applications OP-2 and
OP-1(MX) for Mexico-domiciled CMC. The revision of the application forms
will improve FMCSA' s capability to determine the willingness and ability
of Mexico-domiciled CMC to comply with United States safety standards and
regulations. Under this alternative, Mexican CMV would operate within the
border zone under the revised OP-2 authority and throughout the United States
under the revised OP-1 (MX) authority.
Under the second rule, Mexican CMC seeking to operate beyond the border
zones pursuant to Form OP-1 (MX) authority would be subject to a pre-authority
safety audit, prior to receiving authority to operate within the United
States FMCSA expects that this requirement should not affect the total number
of Mexican CMV operating in the United States, nor the number of inspections
on those Mexican CMV. This alternative should create a more stringent screening
process for applicants that should improve the ability of the FMCSA to deny
entry to the highest risk Mexico-domiciled CMC, thereby reducing the number
of CMV in operation. This should result in a reduction of noise emissions
by eliminating the impacts associated with operating and inspecting those
vehicles. Quantitative estimates of the noise reductions resulting from
this supplemental alternative are at best difficult to calculate due to
the lack of data on the actual number of Mexican CMV that would be denied
authority to operate in the United States. However, with a reduced number
of inspections of Mexican vehicles, the total number of inspections should
remain within the operating limits initially established for the inspection
stations. Implementation of this requirement should result in a minor reduction
compared to the No Action Alternative.
The FMCSA estimates that 10,900 Mexico-domiciled CMC could operate a maximum
of 72,000 CMV within and beyond the border zone. FMCSA estimates that 5,800
Mexico-domiciled CMC could operate under the current OP-2 authority and
could operate 38,000 CMV within the border zone. In addition, FMCSA estimates
that 5,100 Mexico-domiciled CMC could receive OP-1(MX) authority and operate
a maximum of 34,000 CMV beyond the border zone. These CMV may necessarily
pass through the border zone to reach their destinations. Therefore, it
is assumed that a seventh of all 72,000 Mexican CMV-or 10,300 (conservatively
rounding up from the calculated 10,286) Mexican CMV - could pass through
a location within the same hour. The TNM predicts hourly equivalent sound
levels of 76.6 dBA at a distance of 900 feet. In addition, the increase
in the number of Mexican CMV would be offset by a decrease in the number
of United States CMV traveling the same routes. Thus, the Proposed Action
Alternative results in minor reduction in noise levels relative to the No
Action Alternative and no change from the Baseline scenario.
Beyond the border zone, there should be no changes relative to the No Action
Alternative in the approximate number of CMV operating pursuant to OP-1
(MX) authority and potentially passing through a location within the same
hour. Accordingly, the TNM predicts hourly equivalent sound levels of 73.3
dBA at a distance of 900 feet. Thus, the implementation of the two revised
forms results in no change in sound levels beyond the border zone relative
to the No Action Alternative, and thereby in no noise impacts.
4.4.2 Safety Monitoring Program for New Applicants
Baseline - Moratorium in place with Current Safety Monitoring Program
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current safety monitoring would not be revised.
Eligible Mexico-domiciled CMC applying for OP-2 authority would continue
to receive permanent certificates of authority. Mexico-domiciled CMC would
remain largely limited to operating within the border zone, so safety inspections
of Mexican CMV would continue to occur predominantly within the border zone.
Safety inspections would remain the primary tool used by Federal, State
and local authorities to help ensure the safe operation of all CMV. Inspections
on Mexican CMV would follow the same guidelines used for United States and
Canadian CMV, and would not include verification of compliance with the
FMVSS labeling requirement. Mexican CMV operating in the United States would
be inspected approximately two to three times per year on average.
Based on current and projected number of inspections on Mexican CMV and
the expected increase from the addition of inspectors to work along the
United States-Mexico border, FMCSA estimates that 2.77 million total CMV
inspections would occur in the United States in 2002, with approximately
170,000 of these inspections involving Mexican CMV. All inspections would
occur at existing facilities, and all inspections on Mexican CMV would occur
in the border zone since they are only allowed to operate in that area.
Roadside inspections take between 40 to 50 minutes with an engine-on-time
(idle) of up to 15 minutes. During this time, noise emissions could potentially
affect that area. However, the number of inspections will remain within
the operating limits initially established for the inspection stations.
Thus, the Baseline scenario will result in no noise impacts.
No-Action - Moratorium Modified with Revised Safety Monitoring Program
Under the No Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its safety monitoring program.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent certificates of authority. Mexico-domiciled CMC would
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV would occur within and beyond the United States-Mexico border
zone. Safety inspections would remain the primary tool used by Federal,
State and local authorities to help ensure the safe operation of all CMV.
Inspections on Mexican CMV would follow the same guidelines used for United
States and Canadian CMV, and would not include verification of compliance
with the FMVSS labeling requirement. Mexican CMV operating in the United
States would be inspected approximately two to three times per year on average.
The FMCSA estimates that 2.78 million CMV inspections would occur in the
United States, with 180,000 of these inspections involving Mexican vehicles.
All inspections would occur at existing facilities, and the inspections
on Mexican CMV would occur within and beyond the border zone. Since all
Mexican CMV would necessarily pass through the border zone to reach their
destinations, they could be inspected within the border zone. Thus, since
the actual geographic distribution of inspections is unknown, this analysis
assumes that all 180,000 inspections on Mexican CMV could occur within the
border zone. However, both within and beyond the border, the number of inspections
would remain within the operating limits initially established for the inspection
stations. Therefore, the No Action Alternative would result in no noise
impacts from the inspection of Mexican CMV within and beyond the border
zone.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Altemative, a Presidential order would modify
the moratorium and FMCSA would promulgate two rules to revise its safety
monitoring program. Eligible Mexico-domiciled CMC applying for operating
authority would receive provisional authority for a period of no less than
18 months. As under the No Action Alternative, Mexico-domiciled CMC would
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV would occur both at the U.S-Mexico border and at other inspection
locations throughout the United States. All Mexico-domiciled CMC, including
carriers with current certificates of authority, would be required to re-apply
using the revised application forms set forth in the first two rules. In
addition to the safety inspections used by Federal, State and local authorities,
FMCSA would also conduct at least one safety audit or compliance review
while a carrier was operating under provisional authority. Both the safety
inspections and the safety audit would be used as tools to help ensure the
safe operation of Mexican CMV. Inspections on Mexican CMV would follow the
same guidelines used for United States and Canadian CMV, and would include
verification of compliance with the FMVSS labeling requirement. Mexican
CMV operating in the United States would continue to be inspected approximately
two to three times per year on average.
The inspection schedule would be the same as under the No Action Alternative.
Since there would be the same number of inspections on Mexican CMV, the
total number of inspections on all CMV would remain the same. As in the
No Action Altemative, these inspections would occur at existing facilities
and would not be limited to the border zone. Since these inspections would
include verification of FMVSS compliance, they will be approximately 5 seconds
longer, or about a fifth of a percent longer than those inspections considered
under the No Action Alternative and Baseline scenario. This would essentially
have negligible effects on noise levels.
Commercial Vehicle Safety Alliance Decal - Proposed Requirement:
Under this requirement, all Mexico-domiciled CMC granted provisional operating
authority under Form OP-1 (MX) would be required to maintain a current CVSA
decal on all their CMV operating within the United States. In addition,
CMC would be required to maintain current CVSA decals on their CMV for three
years after receiving permanent OP-1 (MX) authority. FMCSA estimates that
this requirement could result in 230,000 Mexican CMV inspections in 2002.
The additional 50,000 inspections are necessary to meet the CVSA requirement
of four yearly inspections for Mexican CMV operating pursuant to OP-1 (MX)
authority. It was assumed that the average number of inspections per Mexican
CMV operating pursuant to OP-2 authority would be the same than that under
the Proposed and No Action scenarios. Thus, the total number of CMV inspections
in the United States should be 2.83 million. These inspections would occur
at existing roadside inspection stations or other existing facilities where
CVSA decal inspections currently take place. These inspections would include
verification of the FMVSS label so would be just as long as those under
the Proposed Action.
Since all Mexican CMV would necessarily pass through the border zone to
reach their destinations, they could be inspected within the border zone.
Thus, since the actual geographic distribution of inspections is unknown,
this analysis assumes that all 230,000 inspections on Mexican CMV could
occur within the border zone. However, both within and beyond the border,
the number of inspections would remain within the operating limits initially
established for the inspection stations. Therefore, the implementation of
the CVSA requirement would result in indistinguishable noise impacts from
the inspection of Mexican CMV within and beyond the border zone.
4.4.3 Summary of Impacts of the Proposed Action on Noise
No Action - Moratorium Modified with Current Application Forms and Current
Safety Monitoring Program
The potential noise impacts of the No Action Alternative were determined
by combining the analysis performed for the two categories of regulatory
actions used in this study: applications for operating authority, and safety
monitoring program. The No Action Alternative could result in an increase
in the number of Mexican CMV operating and being inspected in the United
States relative to the Baseline Scenario, with an associated potential increase
in noise. However, the contribution of these noise increases compared to
noise emissions from operations and inspections on all CMV, and in particular
to total on-road emissions, is negligible. In addition, these minor increases
in the number of Mexican CMV operating within the United States could be
further reduced by a reduction in the operations associated with those United
States CMV trips replaced by trips carried out by some of the new entrant
Mexican CMV operating within the United States. Furthermore, inspections
on Mexican CMV would no longer be restricted to the border zone but could
occur anywhere in the United States. Thus, the No Action Alternative could
result in negligible contributions to noise emissions in the United States.
Proposed Action - Moratorium Modified with Revised Application Forms and
Revised Safety Monitoring Program
The potential noise impacts of the Proposed Action Alternative were determined
by combining the analysis performed for the two categories of regulatory
actions used in this study: applications for operating authority, and safety
monitoring program (including implementation of the CVSA requirement). The
resulting numbers of Mexican CMV operating and being inspected were compared
to those calculated under the Baseline Scenario and the No Action Alternative.
When compared to the Baseline Scenario, the Proposed Action could result
in a marginal increase in the number of Mexican CMV operating in the United
States. In addition, there could be a significant increase in the number
of inspections on Mexican CMV. When compared to the No Action Alternative,
the Proposed Action could result in a marginal decrease in the number of
Mexican CMV operating within the United States. In addition, there could
be a significant increase in the number of inspections on Mexican CMV.
Although there is a slight increase in the number of Mexican CMV operating
within the United States compared to the Baseline, this change is negligible
when compared to national operations of CMV. In addition, the increased
number of inspections and longer inspections would not result in identifiable
changes in sound levels. Thus, given the estimated number of Mexican CMV
operating and being inspected, the implementation of the Proposed Action
would result in no noise impacts.
4.5. SOCIOECONOMICS
This section addresses the potential effects on socioeconomics from the
current Baseline Scenario, the No Action Alternative and the Proposed Action.
Impacts from the rules on socioeconomics and environmental justice are identified
where appropriate.
4.5.1 Applications for Operating Authority
Baseline - Moratorium Retained with Current Application Forms
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current application forms would not be revised.
Mexico-domiciled CMC would use the existing Form OP-2 to apply for operating
authority within the border zone, or the existing Form OP-1 (MX) to apply
for operating authority beyond the border zone. With the moratorium in place,
FMCSA would continue to be prevented from processing OP-1 (MX) applications,
and thus Mexico-domiciled CMC would not receive authority to operate beyond
the border zone.
The FMCSA estimates that there are approximately 4.5 million CMV currently
operating throughout the United States, with a maximum of 63,000 Mexican
CMV operating within the border zone. FMCSA estimates that under the baseline
scenario, there could be a maximum of 71,500 Mexican CMV operating pursuant
to OP-2 authority in FY2002. Any potential impacts associated with these
operations should be concentrated in the border zone as Form OP-2 restricts
operations to a 20-mile radius from the border (FMSCA 2001c). According
to 2000 census data, 4.8 million people live in the seven counties adjacent
to the busiest border crossings, with over half of those people living in
San Diego County adjacent to the Otay Mesa crossing. Of the people living
adjacent to these seven crossings, 50% identified themselves as being of
Hispanic or Latino origin (83% if San Diego County is excluded). San Diego
County had a median household income of $39,427 (See Appendix G for more
demographic and socioeconomic data) and the remaining counties had median
household incomes that ranged from $20,034 to $26,515. During the same period,
the total United States population was 281.4 million with 12.5% identifying
themselves as being of Hispanic or Latino origin. The median household income
throughout the United States was $37,005 (United States Census Bureau 2001).
Given this information, the current border zone activities-and their effects-could
be disproportionately impacting Hispanic and Latino communities as well
as low-income communities in the border counties.
No Action - Moratorium Modified with Current Application Forms
Under the No-Action Alternative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its current application forms OP-2
and OP-1(MX) for Mexico-domiciled CMC. Under this alternative, Mexican CMV
would operate within the border zone pursuant to OP-2 authority and throughout
the United States pursuant to OP-1 (MX) authority. The FMCSA estimates that
11,000 Mexico-domiciled CMC could operate approximately 73,000 CMV within
and beyond the border zone. FMCSA estimates that approximately 5,900 Mexico-domiciled
CMC could operate 39,000 CMV under the current OP-2 authority. In addition,
FMCSA estimates that approximately 5,100 Mexico-domiciled CMC could receive
OP-1 (MX) authority and operate approximately 34,000 CMV beyond the border
zone. These CMV should necessarily pass through the border zone to reach
their destinations. Therefore, all 73,000 Mexican CMV could travel within
and/or through the border zone.
Thus, under the No Action altemative, there could be an increase of approximately
1,500 Mexican CMV with authority to operate in the border zone, compared
to the Baseline. In addition, as discussed in Chapter 2, the modification
of the moratorium may cause a slight increase in the total amount of goods
imported into the United States from Mexico. This modest increase in trade
and in the total number of Mexican CMV with authority to operate in the
United States should result in an economic benefit to the communities in
the border zone. This economic benefit would be offset by a decrease in
the use of transfer stations within the border zone, as Mexico-domiciled
CMC begin transporting goods directly from Mexico to their final destinations
beyond the border zone. It is difficult to quantify effects from each of
these factors; however, the overall economic impact within the border zone,
whether beneficial or adverse, is expected to be small.
Beyond the border zone, the FMCSA anticipates that Mexican CMV would travel
throughout the United States, and that their travel would not be limited
to specifically identifiable areas. Thus, since the impacts associated with
Mexico-domiciled CMC operations would be spread throughout the United States,
no single area or community would be disproportionately impacted, and negative
socioeconomic impacts beyond the border zone would be minor.
Proposed Action - Moratorium Modified with Revised Application Forms
Under the Proposed Action Alternative, the Presidential order would modify
the moratorium and FMCSA would revise its current applications OP-2 and
OP-1 (MX) for Mexico-domiciled CMC. The revision of the application forms
will improve FMCSA' s capability to determine the willingness and ability
of Mexico-domiciled CMC to comply with United States safety standards and
regulations. Under this altemative, Mexican CMV would operate within the
border zone under the revised OP-2 authority and throughout the United States
under the revised OP-1 (MX) authority. Under the second rule, Mexican CMC
seeking to operate beyond the border zones pursuant to Form OP- 1(MX) authority
would be subject to a pre-authority safety audit, prior to receiving authority
to operate within the United States.
The FMCSA estimates that approximately 10,900 Mexico-domiciled CMC could
operate approximately 72,000 CMV within and beyond the border zone. FMCSA
estimates that 5,800 Mexico-domiciled CMC could operate under the current
OP-2 authority and could operate approximately 38,000 CMV within the border
zone. In addition, FMCSA estimates that 5,100 Mexico-domiciled CMC could
receive OP-1 (MX) authority and operate approximately 34,000 CMV beyond
the border zone. These CMV could necessarily pass through the border zone
to reach their destinations and to retum to Mexico. Therefore, all 72,000
Mexican CMV could travel within and/or through the border zone.
Thus, under the Proposed Action Alternative, there could be decrease of
approximately 1,000 Mexican CMV with authority to operate in the border
zone, compared to the No Action Alternative, and an increase of 500 Mexican
CMV compared to the Baseline. As discussed in Chapter 2, the proposed rules
are not expected to increase the total amount of goods imported into the
United States from Mexico. The decrease in the total number of Mexican CMV
with authority to operate in the United States compared to the No Action
Alternative, should be offset by an increase in the number of trips made
by existing Mexican CMV since the overall volume of trade should not be
affected by the Proposed Action. In addition, fewer Mexico-domiciled CMC
would transport goods directly from Mexico to final destinations within
the United States, mitigating this adverse economic impact to the border
zone from the No Action Alternative. It is difficult to quantify the effects
from each of these factors; however, the overall economic impact within
the border zone, whether beneficial or adverse, is expected to be small.
This conclusion applies to a comparison of economic impacts between the
Proposed Action alternative and either the No Action or Baseline
Beyond the border zone the implementation of the Proposed Action results
in a reduction of 110 Mexican CMV operating pursuant to OP-1 (MX) authority,
when compared to the number operating under the No Action Alternative. The
level of safety would be improved, as the reduction in vehicles should be
the result of the FMCSA denying authority to high-risk CMC. Thus, the revision
of Forms OP-2 and OP-1(MX) could reduce the impacts associated with increased
border traffic resulting from the No Action Alternative. Therefore, low
income and Hispanic/Latino communities living beyond the border zones could
benefit from this part of the Proposed Action, and would not be disproportionately
affected by its implementation.
4.5.2 Safety Monitoring for Mexico-Domiciled Motor Carriers
Baseline - Moratorium Retained with Current Safety Monitoring Program
Under a continuation of the current baseline operating conditions, the moratorium
would remain unmodified and the current safety monitoring would not be revised.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent authority. Mexico-domiciled CMC would remain largely
limited to operating within the border zone, so safety inspections of Mexican
CMV would continue to occur predominantly within the border zone. Mexican
CMV operating in the United States would be inspected approximately two
to three times per year on average.
Based on current and projected number of inspections on Mexican CMV and
the expected increase from the addition of inspectors to work along the
United States-Mexico border, FMCSA estimates that 2.77 million total CMV
inspections could occur in the United States in 2002, with approximately
170,000 of these inspections involving Mexican CMV. These roadside inspections
take between 40 to 50 minutes. Since the inspection process at fixed locations
involves choosing CMV out of the lines for the weigh stations, at a rate
of one CMV per inspection area at a time, the potential effects at and around
the inspection stations are minimized. In addition, FMCSA anticipates that
all non-Mexican CMV inspections will continue to occur at any of the State
and Federal inspection stations located throughout the United States and
will not be concentrated in any particular area. Inspections on Mexican
CMV would largely occur within the border zone.
No-Action - Moratorium Modified with Current Safety Monitoring Program
Under the No Action Altemative, a Presidential order would modify the moratorium
and FMCSA would take no action to revise its safety monitoring program.
Eligible Mexico-domiciled CMC applying for operating authority would continue
to receive permanent authority. Mexico-domiciled CMC would be eligible to
operate beyond the border zone, so safety inspections of Mexican CMV would
occur within and beyond the United States Mexico border zone. Mexican CMV
operating in the United States would be inspected approximately two to three
times per year on average.
FMCSA expects that the proportion of Mexican CMV inspected would increase
as the number of Mexican CMV operating in the United States increases. In
addition, FMCSA will continue to deploy additional inspectors at the border,
as described under the Baseline Scenario. FMCSA estimates that 2.78 million
total CMV inspections would occur in the United States in 2002, with approximately
180,000 of these inspections involving Mexican CMV. All inspections would
continue occurring at existing facilities. The number of inspections on
Mexican CMV could be slightly larger than under the current baseline conditions,
but could occur anywhere in the United States and would not be limited to
the border zone as is currently the case. Thus, no single area or community
would be disproportionately impacted, since these inspections will occur
at any of the State and Federal inspection stations located throughout the
United States and will not be concentrated in any particular area. Therefore,
the No Action Alternative could have a minor beneficial impact to socioeconomics
in the border zone. However, the significance of this benefit is expected
to be minor and is at best difficult to quantify since there is no data
on the expected geographic distribution of inspections on Mexican CMV. In
addition, the total number of inspections in the United States would increase
only marginally, so there would be no impacts on socioeconomics from the
No Action Alternative.
Proposed Action - Moratorium Modified with Revised Safety Monitoring Program
for Mexico-Domiciled Motor Carriers
Under the Proposed Action Alternative, a Presidential order would modify
the moratorium and FMCSA would promulgate two rules to revise its safety
monitoring program. Eligible Mexico-domiciled CMC applying for operating
authority would receive provisional authority for a period of no less than
18 months. As under the No Action Alternative, Mexico-domiciled CMC would
be eligible to operate beyond the border zone, so safety inspections of
Mexican CMV would occur both at the U.S-Mexico border and at other inspection
locations throughout the United States. All Mexico-domiciled CMC, including
carriers with current certificates of authority, would be required to re-apply
using the revised application forms set forth in the first two rules. In
addition to the safety inspections used by Federal, State and local authorities,
FMCSA would also conduct at least one safety audit or compliance review
while a carrier was operating under a provisional certificate of authority.
Mexican CMV operating in the United States would continue to be inspected
approximately two to three times per year on average. These inspections
would include verification of compliance with the FMVSS labeling requirement.
The inspection schedule would be the same as under the No Action Alternative
and the total number of inspections on all CMV also should remain the same.
As in the No Action Alternative, these inspections could occur anywhere
in the United States and would not be limited to the border zone. Since
these inspections include verification of FMVSS compliance, they will be
approximately 5 seconds longer, or about a fifth of a percent longer than
those inspections considered under the No Action Alternative and Baseline
scenario. Since the total number of inspections will not change, and any
potential beneficial or adverse impacts associated with CMV inspections
would be spread throughout the United States, no single area or community
would be disproportionately affected (FMCSA 2001b). Furthermore, safety
benefits from the implementation of the revised Safety Monitoring System
would have a minor beneficial impact on socioeconomics within and beyond
the border zone.
Commercial Vehicle Safety Alliance Decal-Proposed Requirement:
Under this requirement, all Mexico-domiciled CMC granted provisional operating
authority under Form OP-1 (MX) would be required to maintain a current CVSA
decal on all their CMV operating within the United States. In addition,
CMC would be required to maintain current CVSA decals on their CMV for three
years after receiving permanent OP-1 (MX) authority. FMCSA estimates that
this requirement could result in 230,000 Mexican CMV inspections in 2002.
The additional 50,000 inspections are necessary to meet the CVSA requirement
of four yearly inspections for Mexican CMV operating pursuant to OP-1 (MX)
authority. It was assumed that the average number of inspections per Mexican
CMV operating pursuant to OP-2 authority should be the same than that under
the Proposed and No Action scenarios. The total number of CMV inspections
in the United States should be 2.83 million. These inspections would occur
at existing roadside inspection stations or other existing facilities where
CVSA decal inspections currently take place.
The total number of inspections should only increase by approximately 2
percent when compared to the Proposed Action, No Action, and Baseline scenarios.
In addition, these inspections would occur at any of the State and Federal
inspection stations located throughout the United States and should not
be concentrated in any particular area. Since the total number of inspections
should change only marginally, and the impacts associated with CMV inspections
should be spread throughout the United States, no single area or community
would be disproportionately affected (FMCSA 2001b). Furthermore, safety
benefits from the implementation of the CVSA requirement should have a minor
beneficial impact on socioeconomics within and beyond the border zone.
4.5.3 Summary of Impacts of the Proposed Action on Socioeconomics
No Action - Moratorium Modified with Current Application Forms and Current
Safety Monitoring Program
The potential socioeconomics impacts of the No Action Alternative were determined
by combining the analysis performed for the two categories of regulatory
actions used in this study: applications for operating authority, and safety
monitoring program. The No Action Alternative could result in an increase
in the number of Mexican CMV operating and being inspected in the United
States relative to the Baseline Scenario. The contribution of these increases
compared to nationwide operations and inspections on CMV is very minor.
In addition, these minor increases in the number of Mexican CMV operating
within the United States could be further reduced by the offset from the
reduction in the operations associated with those United States CMV trips
replaced by trips carried out by some of the Mexican CMV operating within
the United States.
Furthermore, inspections on Mexican CMV would no longer be restricted to
the border zone but could occur anywhere in the United States. Therefore,
there would be very minor changes in operations and inspections when compared
to national CMV operations and inspections.
Operation and inspection emissions of NOx and PM would be higher than under
Baseline conditions, with possible disproportionate impacts on those minority
and low-income communities in the border counties. However, as previously
mentioned, increases in operations are minor when compared to national CMV
operations and would be offset by reductions in United States operations
along the same routes. In addition, inspections could occur anywhere in
the United States and would not be limited to the border zone. Thus, any
impacts associated with the inspection of Mexican CMV would be spread out
throughout the United States instead of being confined to the border zone.
In addition, since the total number of inspections in the United States
would increase only marginally, there would be very minor contributions
to emissions and no effects on socioeconomics from the No Action Alternative.
Proposed Action - Moratorium Modified with Revised Application Forms and
Revised Safety Monitoring Program
The potential socioeconomics impacts of the Proposed Action Alternative
were determined by combining the analysis performed for the two categories
of regulatory actions used in this study: applications for operating authority,
and safety monitoring program (including implementation of the CVSA requirement).
The resulting numbers of Mexican CMV operating and being inspected were
compared to those calculated under the Baseline Scenario and the No Action
Alternative. When compared to the Baseline Scenario, the Proposed Action
could result in a marginal increase in the number of Mexican CMV operating
in the United States. In addition, there could be an increase in the number
of inspections on Mexican CMV. When compared to the No Action Alternative,
the Proposed Action could result in a marginal decrease in the number of
Mexican CMV operating within the United States. In addition, there could
be a significant increase in the number of inspections on Mexican CMV. Thus,
although there is a slight increase in the number of Mexican CMV operating
within the United States when considering the combined effect of the No
Action Alternative and the implementation of the Proposed Action, this increase
is a result of the No Action Alternative and not the Proposed Action itself.
In fact, the Proposed Action results in a slight reduction in the number
of Mexican CMV operating in the United States. However, the changes in resulting
numbers of Mexican CMV are negligible when compared to national operations
of CMV.
Operation and inspection emissions of NOx and PM should be lower than those
under the No Action Alternative. Furthermore, the FMCSA estimates that the
implementation of the Proposed Action would improve its ability to promote
the safe operation of Mexican CMV within the United States, thereby reducing
the number of high-risk CMV in operation and thereby the number of safety
related incidents. The effect on socioeconomics would be beneficial because
the roadways will be safer. This effect would be minor however, given the
proportion of Mexican to United States and Canadian CMV operating throughout
the United States.
5. MITIGATION AND BEST MANAGEMENT PRACTICES
As explained in Chapter 4, because the Proposed Action by FMCSA is mostly
administrative, impacts associated with this Action are expected to be minor.
The only area of potential concern is the proposed focus on increasing the
number of roadside inspections of Mexican CMV. This focus, however, will
only marginally increase the total number of inspections in the United States.
Moreover, the FMCSA anticipates that the increase in roadside inspections
of Mexican CMV may cause the number of Mexico-domiciled CMC and CMV operating
in the United States to be reduced (FMCSA 2001b). Therefore, the Proposed
Action should not have any significant adverse effects requiring mitigation.
Nonetheless, in an effort to be conservative and mitigate potential adverse
impacts, areas of general and specific mitigation are discussed below.
Through the Proposed Action, the FMCSA expects to target the highest risk
CMC and bring them into compliance with United States safety and environmental
laws, standards, policies, rules, and regulations. The Proposed Action does
not limit the operations of Mexico-domiciled CMV throughout the border zone
and nation. Therefore, the only mitigation practice available is ensuring
that high risk Mexico-domiciled CMC are screened out and denied operating
authority in the United States through the development of the safety data-tracking
database established by FMCSA based on the revised application forms and
the enhanced safety monitoring program.
FMCSA has instituted proactive outreach and education efforts to minimize
any potential impacts. The agency has made additional funding available
to the Border States for increased enforcement and compliance activities.
FMCSA has also hired additional inspectors and used funds to purchase equipment,
provide training, and conduct outreach efforts. Additionally, FMCSA trained
Mexican inspectors in order to perform inspections on Mexican CMV. The DOT
has developed a requirements handbook and will hold a three-day information
conference to assist CMC in understanding the requirements for legal operations
outside of their own countries. FMCSA itself is holding regular seminars
in the border regions to educate CMC about FMCSA regulations (Lameiro 2001).
These efforts could also include information regarding new requirements
set forth by the Proposed Action.
More specifically, FMCSA could use Best Management Practices (BMP) to further
mitigate any possible impacts. In general, BMP deployed by FMCSA to their
field inspectors will limit and minimize impacts on the environment and
human resources. BMP devised by agencies are used to train their staff in
siting new facilities and in daily operations. The FMCSA BMP includes random
roadside inspections that will not potentially have an adverse affect on
the environment or human resources.
Inspectors should take great care in initiating and conducting random roadside
inspections on Mexico-based CMV. Specifically, the FMCSA could implement
inspector education and training on BMP policies for conducting safe inspections.
For example, FMCSA could instruct its roadside inspectors not to perform
random inspections in or near any of the following sensitive receptor areas:
railway crossings, highway ramps and interchanges; human structures (especially
schools, hospitals, and residences); wetlands, floodplains during a storm;
wilderness areas, ecological/wildlife refuges, preserves, conservation areas
and sanctuaries; threatened and endangered species and their habitat; coastal
zones; steeply sloping terrain; hazardous waste sites; capped land fills;
wild and scenic rivers; scenic highways, national natural landmarks, prime
and unique farmlands; historical, archeological, and cultural sites; and
national and state parks and recreation areas.
Furthermore, the inspectors should not conduct a random roadside inspection
under dangerous conditions, including severe weather warnings. The random
roadside inspections could be planned to the maximum extent possible so
as to not impact one highway corridor during the day or during peak commuting
hours (7:00 to 10:00 a.m. and 4:00 to 7:00 p.m.) near metropolitan centers,
thus reducing the potential of congestion. Additionally, FMCSA random roadside
inspections could have a buffer zone between planned inspections along a
given highway corridor. To the extent practicable, a majority of the random
roadside inspections on Mexico-based CMV could take place outside of the
commercial border zone so as to minimize adverse impacts on the existing
infrastructure, congestion, and emissions in the border region. Any indication
of leaking fluids from the fuel tank, engine, or cargo department of the
Mexico-domiciled CMV should result in the inspector immediately contacting
local police and fire departments, and where necessary, the state Hazardous
Materials Rapid Response Team.
The actual types and extent of minor impacts indirectly related to the Proposed
Action would depend upon site-specific conditions. These actions could include
new state inspection stations that would be subject to its own site-specific
NEPA analysis prepared by the state. In the FMCSA Proposed Action, no new
construction of any facility or roadway is planned. The adherence of the
FMCSA inspectors to BMPs for inspections at existing stations, random inspections,
the siting of new inspection stations, and any other BMPs developed in the
future will mitigate and assuage any deleterious environmental and human
resources impacts from the planned roadside inspections for Mexico-based
CMV, and thus the Proposed Actions.
The Proposed Action by FMCSA has no significant environmental impacts and
thus requires no mitigation. If in the future it is determined that adverse
impacts are occurring, FMCSA may consider developing strategies to address
those impacts.
6. LIST OF PREPARERS AND REVIEWERS
The following is a list of contributors to this Programmatic Environmental
Assessment.
* * * * *
LIST OF APPENDICES
Appendix A - Definition of Commercial Motor
Page
Vehicles and Description of Roadside Inspec-
tions
[ ]
Appendix B - Roles of Selected Agencies with En-
vironmental and Public Health Oversight
Authority Over the Operation of CMC in the
United States
[ ]
Appendix C - Air Quality
[ ]
Appendix D - Environmental Screening Process
[ ]
Appendix E - Noise Emissions Analysis
[ ]
Appendix F - Selected NAFTA Environmental
References
[ ]
Appendix G - Socioeconomic Demographic
Numbers
[ ]
Appendix H - Proposed Forms OP-2 and
OP-1 (MX)
[ ]
APPENDIX A - DEFINITION OF COMMERCIAL MOTOR VEHICLES AND DESCRIPTION OF
ROADSIDE INSPECTIONS
Commercial motor vehicle (CMV) are defined as self-propelled or towed motor
vehicle used on a highway in interstate commerce to transport passengers
or property when the vehicle-
(1) Has a gross vehicle weight rating or gross combination weight rating,
or gross vehicle weight or gross combination weight, of 4,537 kg (10,001
lb) or more; whichever is greater; or
(2) Is designed or used to transport more than 8 passengers (including the
driver) for compensation; or
(3) Is designed or used to transport more than 15 passengers, including
the driver, and is not used to transport passengers for compensation; or
(4) Is used in transporting material found by the Secretary of Transportation
to be hazardous under 49 U.S.C. 5103 and transported in a quantity requiring
placarding under regulations prescribed by the Secretary under 49 CFR, subtitle
B, chapter I, subchapter C. (49 CFR 390.5)
Roadside inspections of CMC are carried out by FMCSA to ensure the safety
of operation of drivers and commercial vehicles in the United States. There
are six different levels of inspections:
( Level I- North American Standard Inspection
( Level II- Walk-Around Driver/Vehicle Inspection
( Level III- Driver-Only Inspection
( Level IV- Special Inspections
( Level V- Vehicle-Only Inspection
( Level VI- Enhance NAS Inspection for Radioactive Shipments
The North American Truck Inspection Procedure (Level I) consists of first
interviewing the driver and collecting all of his/her documents and paperwork.
Then, the inspector checks for the presence of hazardous materials. After
checking thoroughly for hazardous materials, the inspector reviews all of
the documents and the paperwork received from the CMC. Next, the inspector
starts the vehicle inspection, starting with the left front of the truck
and examining all parts, including the trailer and wheels, and moving then
to the left rear of the truck. The right rear comes next, followed by the
right saddle tank area and the right fuel tanks. The inspector then moves
up to the right front of the truck and continues by checking the steering
wheel lash, the air loss rate, the axles, and the brake adjustment. The
inspection is completed by inspecting the tractor protection system that
includes both the tractor protection valve and the emergency brakes, and
the fifth wheel movement (CVSA 2001). The engine will be off for most of
the inspection. There are, however, some parts of the inspection, such as
verification of the air pressure, where the truck must be running to build
up the air (Cisneros 2001). The Level I inspection is the most intensive
and takes about 20 minutes. These inspections are held primarily at the
border inspection stations in Arizona, California, New Mexico and Texas.
The other inspection levels take less time to complete, and are done less
frequently than the Level I inspections (Cisneros 2001).
The Level II inspection includes only the items from the Level I inspection
that can be inspected without physically getting under the vehicle. The
Level III inspection includes an examination of the driver and his/her documents
and paperwork. The Level IV inspection includes a one-time inspection of
a particular item. The Level V inspection includes all parts of a vehicle
in a Level I, without a driver being present. These inspections can be conducted
at any location. The Level VI inspections consist of an inspection for select
radiological shipments, which include inspection procedures, enhancements
to the Level I inspection, radiological requirements, and the enhanced out-of-service
criteria. Select radiological shipments include only highway route controlled
quantities as defined by title 49, Section 173.403 and all transuranics
(CVSA 2001). Buses are subject to the same requirements but escape doors
and windows are also inspected.
If a truck fails the inspection, it is placed out-of-service. The ensuing
action varies by State and is determined by the inspection station polices,
as well as by practical conditions at the time the vehicle is rendered under
out-of-service status. For example, in most cases in California the out-of-service
truck would remain parked at the inspection site until the repairs are made.
In the rare case that the repairs cannot be made on site, the company can
have the vehicle towed to a repair facility. In Arizona, if the vehicle
can be fixed within 2 hours, it is allowed to remain onsite until the repairs
are made. If the repairs will take longer than 2 hours, either the company
or United States Customs will tow the vehicle to a repair facility. At various
border locations in Texas, the policies change based on the available space
at that specific site. In some cases, the vehicle may be allowed to return
to Mexico for repairs; on other occasions, the repairs are made on site
(Cisneros 2001).
Aside from direct and indirect safety benefits, the inspections could have
an environmental benefit, as they have the potential to alert officials
of other problems, such as leaking CMV. There is always the possibility
that leaking CMV could cause environmental harm, but if officials become
aware of the problem they could notify the proper environmental authorities
to address the issue and minimize any potential environmental effect from
the release of hazardous and other materials from the CMV.
APPENDIX B - ROLES OF SELECTED AGENCIES WITH ENVIRONMENTAL AND PUBLIC HEALTH
OVERSIGHT AUTHORITY OVER THE OPERATION OF CMC IN THE UNITED STATES
Below is a summary of the regulatory functions that Federal agencies other
than FMCSA play in the oversight of the operation of CMC in the United States.
The Environmental Protection Agency (EPA) regulates air emissions from braking
action and fuel. Within the EPA, the Office of International Affairs, Region
6, and Region 9 have personnel who, on a regular basis, work with State
and local government officials to monitor air quality in the cities along
the southern borders of Texas and New Mexico. In areas where air quality
does not meet federal standards, appropriate local and State agencies work
with EPA to design air quality improvement plans to reduce emissions, to
improve air quality to national standards. The EPA also sponsors a program,
known as The Border XXI Program, which protects and improves the environment
and environmental health while fostering sustainable development in the
United States-Mexico border region, is an alliance of organizations dedicated
to environmental progress on the United States-Mexico Border area.
* * * * *
APPENDIX C - AIR QUALITY
This section presents detailed information on modeling methodology, criteria
pollutants, air quality health effects, legislation, current state of the
environment, and source characteristics. This section serves as a complement
to the general air quality information provided in the Air Quality Section
in Chapter 3 (Section 3.4).
To quantify the magnitude of direct pollutant emissions resulting from the
inspections of Mexican CMC, the EPA emissions models, MOBILE5a and PART5,
were used. MOBILE5a was used to determine emission factors for CO, VOC,
and NOx. PART5 was used to determine emission factors for Pb, SO2, PM10,
and PM2.5. Due to the lack of actual modeling data and the resulting assumptions
that needed to be made, the predictions from these models should only be
considered provisional, first-order approximations. The following list indicates
the data and assumptions that were used in modeling the emissions during
the inspections (FMCSA 2001b):
Total inspection time of 50 minutes.
( Engine on time (idle) of 15 minutes during inspection.
( Approximately 130,000 out of 400,000 Mexican heavy-duty vehicles were
considered to be manufactured after 1994. Modeling was conducted for years
1986 and 1994.
( 2.3 million inspections occur on heavy-duty trucks and buses in the United
States each. The amount of total inspections performed will not change but
under the proposed actions a shift will occur to inspect more Mexican heavy-duty
trucks and buses. Under the No-Action Alternative the number inspections
of Mexican trucks and buses will be 170,000 in 2002. Under Rule 3: Safety
Fitness Oversight Program for New Applicants 180,000 inspections of Mexican
trucks and buses would occur in 2002. Under the Commercial Vehicle Safety
Alliance requirement, 230,000 inspections would occur on Mexican CMV in
2002.
( The average VMT for CMV was assumed to be 80,000 per year (VIUS 1999).
( The daily maximum and minimum temperatures (i.e., part of the local area
parameters for MOBILE5a) were estimated for the border areas (i.e., San
Diego, CA and El Paso, TX) to be 51 and 76 degrees Fahrenheit.
( The modeling temperatures (i.e., part of the scenario data for MOBILE5a)
were also estimated for the border areas as 51 and 76 degrees Fahrenheit.
Both of these temperatures were used to create different scenario runs.
( The Reid Vapor Pressure of 14.9 psi was obtained from published literature
for gasoline samples with a "high volatility" rating (Bardon and
Rao 1984).
( The weights of heavy-duty vehicles were modeled by using both the low
end at 8,500 lbs and the high end at 80,000 lbs (limit for a United States
truck). Although Mexican vehicles can weigh more than 80,000 lbs, it was
not considered likely that there would be many above this value.
( Only heavy-duty gasoline and diesel vehicles and buses were modeled. The
default fleet mix for vehicle-miles-traveled as provided by the models was
used. Since MOBILE5a does not explicitly provide emission factors for buses,
they were assumed to be similar to those for heavy-duty diesel vehicles.
The data and assumptions in this list are generally very conservative. For
those cases when more than one scenario was modeled (e.g., for different
temperatures), the higher emission factors were used. A significant confounding
variable in this analysis is that both MOBILE5a and PART5 were based on
United States vehicles. Therefore, the methods and/or data that form the
backbone of these models may not be applicable to Mexican vehicles. However,
it is believed that the conservative nature of this analysis overrides the
magnitude of this affect. The analysis also took into account evaporative
hydrocarbon losses for heavy-duty gasoline vehicles. Diesel fuel does not
evaporate. For simplicity and conservatism, the total VOC emissions were
used for the idling condition. The evaporative emissions (i.e., diurnal,
hot soak, and resting) during the engine-off period were also taken into
account by using the appropriate evaporative components provided by MOBILE5a.
Table C-1 shows the primary and secondary standards used to regulate air
pollution in the United States. The standards for short term averages (i.e.,
less than 24 hours) are devised to protect the public from short-term exposures
resulting in adverse health effects, and the standards for long term averages
(i.e., annual) are devised to protect the public from both short-term and
prolonged exposures.
Table C-1. NAAQS as of December 2000
Sources for the criteria pollutants and their status are presented in the
following discussions:
Carbon Monoxide
Carbon monoxide (CO) is a colorless, odorless gas that is caused by incomplete
carbon combustions. Vehicle exhaust accounts for about 60 percent of all
CO emissions in the United States. Therefore, the highest concentrations
of CO are found in areas of heavy traffic congestion; in urban areas vehicle
exhaust accounts for 95 percent of CO emissions. Other causes of CO are
industrial sources, non-transportation fuel combustion, and wildfires (EPA
2001). A majority of the non-attainment areas are in the western half of
the United States with California having the highest CO levels. Also having
non-attainment levels were parts of counties in Washington, Idaho, Oregon,
Montana, Utah, Colorado, Nevada, Arizona, and Texas in the west and Pennsylvania
and Massachusetts in the East (EPA 2001).
Lead
Prior to the enactment of EPA regulations that reduced the content of lead
in gasoline during the late seventies and early eighties, the primary source
of lead (Pb) emissions in the United States was the automobile. Now, the
major sources of lead emissions are industrial processes, primarily metals
processing. The highest concentrations of lead in the air are near smelters
and battery processors. Lead emissions and concentrations decreased sharply
during the 1980s and early 1990s. The emissions decreased 95 percent in
20 years and the concentrations decreased by 94 percent in the same period
(EPA 2001). Parts of counties in Montana, Nebraska, Missouri, and Tennessee
have non-attainment levels of lead in the atmosphere (EPA 2001).
Nitrogen Dioxide
High temperature combustion processes are the major sources of nitrogen
dioxide (NO2) nationwide. These processes are found in both automobiles
and power plants. Indoor heaters and gas stoves also can create harmful
indoor quantities of the gas. Out of the areas that at one time violated
the national air quality standard for NO2, all areas now meet the standard
(EPA 2001). There are no officially designated non-attainment areas for
NO2 (EPA 2001).
Ozone
Ozone (O3) is a gas that is formed from a reaction between VOCs and NOx
in the presence of heat and sunlight. Some examples of VOC emission sources
are, motor vehicles, chemical plants, refineries, factories, consumer and
commercial products and other industrial sources. The NOx sources are listed
above. Ideal conditions for ozone formation are high temperatures, clear
skies, light winds and limited vertical mixing. The ozone levels at urban
and suburban locations have decreased almost 25 percent over the past 20
years while the rural locations have only decreased by 14 percent (EPA 2001).
There are many non-attainment designations in the United States with almost
the entire states of Massachusetts, New Jersey, Connecticut and Rhode Island
covered by this status. Also in a non-attainment designation are most of
Pennsylvania, California, Maryland, and Delaware; and also select counties
in New York, Arizona, New Mexico, Texas, Colorado, Oregon, Louisiana, Missouri,
Illinois, Virginia, Kentucky, Indiana, Wisconsin, Georgia, and Alabama (EPA
2001).
Sulfur Dioxide
Sulfur dioxide (S02) is formed when fuels containing sulfur (mostly coal
and oil) are burned and also during metal smelting and other industrial
processes. Fuel combustion accounts for a majority of the SO2 emissions
thereby causing most of the nation's SO2 to be found in the vicinity of
large industrial facilities such as coal-fired power plants. SO2 concentrations
have decreased almost 50 percent from 1980 to 1999 and emissions have decreased
28 percent. These decreases are due mostly to SO2 controls that EPA implemented
as part of their Acid Rain Program in 1995 (EPA 2001). The non-attainment
designations are in Montana, Nevada, Utah, Arizona, New Mexico, Minnesota,
Wisconsin, Indiana, Ohio, West Virginia, Pennsylvania, and New Jersey (EPA
2001).
Particulate Matter
Particulate matter (PM10) are particles that are less than 10 micrometers
in diameter and are a mixture of solid particles and liquid droplets found
in the air such as dust, dirt, soot and smoke. These particles are generated
from a number of different sources: combustion from motor vehicles, power
generation, industrial facilities, fires, driving on unpaved roads and wind
blowing on dust are just a few. From 1990 to 1999, the concentration of
these particles decreased by 18 percent and the emissions decreased by 16
percent. In 1999, EPA started monitoring PM2.5 particles that are less than
2.5 micrometers in diameter. In addition to the monitoring of the PM2.5
particles, in 2000 EPA started a Phase II Acid Rain Program to regulate
coal-fired power plants. The non-attainment designations for PMl0 were mostly
in the west (EPA 2001). There were parts of counties in Connecticut, Pennsylvania,
Indiana, Illinois, Texas, New Mexico, Colorado, Nevada, Utah, Wyoming, Montana,
Idaho, Washington, and Oregon with the largest numbers of counties in California
and Arizona (EPA 2001).
The formation of these criteria pollutants and their health effects are
presented in Table C-2. The health effects can be categorized into two general
categories: acute and chronic. Acute or short-term effects usually include
irritations, headaches, and nausea. Chronic or long-term effects may include
decreased lung capacity and cancer.
Table C-2. Criteria Pollutant
Description and Potential Health Effects
Table C-3 presents the contribution of different sectors of the United States
economy to total emissions of criteria pollutants. Transportation emissions
include all ground, air, and water transportation systems.
Table C-3. Source Contribution to Emissions for the United States during
1999
Percent Source Contribution
Pollutant
Transportationa
Industrial Processes
Fuel Combustion
Miscel-laneous
CO
77.1
7.8
5.5
9.6
Pb
12.8
75.3
11.9
0.0
NO2
55.5
3.7
39.5
1.3
VOC
47.0
44.1
5.0
3.9
PM10
24.7
41.5
33.8
0.0
PM2.5
27.6
39.4
33.0
0.0
SO2
6.9
7.8
85.3
0.1
aIncluding on-road and off-road sources.
Source: EPA 2001.
Table C-4 presents a summary of the contribution of the different types
of on-road vehicles to total vehicle emissions in the United States. Vehicles
are classified according to size and fuel type.
Table C-4. Total Emissions from On-Road Mobile Sources in 1999
Total Emissions by Vehicle Category
(thousand short tons)
Pollutant
LDGVa
LDGTb
HDGVc
Dieselsd
Total On-Road Vehiclese
Total from all Sourcesf
CO
27,382
16,115
4,262
2,230
49,989
88,063
Pb
14
7
1
0
22
4,199
NO2
2,859
1,638
459
3,635
8,590
25,393
VOC
2,911
1,722
375
289
5,297
18,145
PM10
59
36
12
189
295
23,679
PM2.5
34
22
8
166
229
6,773g
SO2
137
91
17
118
363
18,867
aLDGV = Light Duty Gas Vehicle (Includes motorcycles).
bLDGT = Light Duty Gas Truck.
cHDGV = Heavy Duty Gas Vehicle.
dDiesels = Encompasses all diesel vehicles.
eValues may not equal total due to rounding.
fIncludes all sources (i.e., transportation, industrial processes, fuel
combustion, and miscellaneous).
gFrom 1998.
Source: EPA 2001.
Table C-5 shows the changes in emissions and concentrations of criteria
pollutants in the United States for the last 20 years.
Table C-5. Percent Changes in Emissions and Concentrations in the US (1980-1999)
Pollutant
Percent Change in Emissions
Percent Change in Atmospheric Concentrations
CO
-21
-57
Pb
-94
-94
NO2
+4
-25
VOC/O3
-31a
-12b
PM10
-15c
-18c
PM2.5
N/Ad
-17c
SO2
-27
-50
aEmissions of VOCs.
bConcentration of O3 for 8-hr.
cFor 1990-1999.
dNot Available.
Source: EPA 2001.
Table C-6 shows estimated pollutant emissions due to these different fuel
types. The emission estimates were calculated using EPA's MOBILE5 and PART5
models.
Table C-6. Estimated Total 1997 Vehicle Emissions by Fuel Type
Pollutant
Emissions due to Gasoline (x 1000 Tons)
Emissions due to Diesel (x 1000 Tons)
CO
48,749
1,509
NOX
5,103
1,933
VOC
4,989
238
SO2
235
84
PM10
105
165
PM2.5
63
144
Source: EPA 2001.
Emissions from Operation and Inspection of Mexican CMV
Table C-7 shows the total amount of emissions-for criteria pollutants-generated
by the approximately 7 1,500 Mexican CMV projected to operate in FY2002
under Baseline conditions.
Table C-7. Total Annual Emissions from Operations of Mexican CMV under the
Baseline Scenario
Pollutant
Operationsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
307826
49989000
0.6158%
88063000
0.3496%
NO2
116489
8590000
1.3561%
25393000
0.4587%
VOC
45182
5297000
0.8530%
18145000
0.2490%
Pb
60
22000
0.2734%
4199000
0.0014%
SO2
7835
363000
2.1585%
18867000
0.0415%
PM10
9397
295000
3.1855%
23679000
0.0397%
PM2.5
8528
229000
3.7239%
6773000
0.1259%
a= Total emissions from the operation of Mexican CMVs in the Border Zone
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e= % of all Sources = (Inspections/Total from all Sources) X 100%
Table C-8 shows the total amount of emissions-for criteria pollutants-generated
by the approximately 73,000 Mexican CMV projected to operate in FY2002 under
the No Action Alternative.
Table C-8. Total Annual Emissions from Operations of Mexican CMV under the
No Action Alternative
Pollutant
Operationsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
314284
49989000
0.6287%
88063000
0.3569%
NO2
118933
8590000
1.3846%
25393000
0.4684%
VOC
46130
5297000
0.8709%
18145000
0.2542%
Pb
61
22000
0.2791%
4199000
0.0015%
SO2
8000
363000
2.2038%
18867000
0.0424%
PM10
9594
295000
3.2523%
23679000
0.0405%
PM2.5
8707
229000
3.8021%
6773000
0.1286%
a= Total emissions from the operation of Mexican CMVs in the Border Zone
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e = % of all Sources = (Inspections/Total from all Sources) X 100%
Table C-9 shows the total amount of emissions-for criteria pollutants-generated
by the approximately 72,000 Mexican CMV projected to operate in FY2002 under
the Proposed Action Alternative.
Table C-9. Total Annual Emissions from Operations of Mexican CMV under the
Proposed Action Alternative
Pollutant
Operationsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
309978
4998900
0.6201%
8806300
0.3520%
NO2
117304
8590000
1.3656%
25393000
0.4620%
VOC
45498
5297000
0.8589%
18145000
0.2507%
Pb
61
22000
0.2753%
4199000
0.0014%
SO2
7890
363000
2.1736%
18867000
0.0418%
PM10
9463
295000
3.2077%
23679000
0.0400%
PM2.5
8587
229000
3.7500%
6773000
0.1286%
a= Total emissions from the operation of Mexican CMVs in the Border Zone
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e= % of all Sources = (Inspections/Total from all Sources) X 100%
Table C-10 shows the total amount of emissions-for criteria pollutants-generated
from the inspection of 170,000 Mexican CMV under the Baseline Scenario.
Table C-10. Total Annual Emissions from Inspections of Mexican CMV under
the Baseline Scenario
Pollutant
Inspectionsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
35.5797
49,989,9000
0.00007118%
88,0630,000
0.00004040%
NO2
2.7370
8,590,000
0.00003186%
25,393,000
0.00001078%
VOC
7.7720
5,297,000
0.00014672%
18,145,000
0.00004283%
Pb
0.0013
22,000
0.00000580%
4,199,000
0.00000003%
SO2
0.1330
363,000
0.00003665%
18,867,000
0.00000071%
PM10
0.1747
295,000
0.00005921%
23,679,000
0.00000074%
PM2.5
0.1585
229,000
0.00006922%
6,773,000
0.00000234%
a= Total emissions from the inspections of Mexican CMVs
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e= % of all Sources = (Inspections/Total from all Sources) X 100%
Table C-11 shows the total amount of emissions-for criteria pollutants-generated
from the inspection of 180,000 Mexican CMV under the No Action and Proposed
Action Altematives.
Table C-11. Total Annual Emissions from Inspections of Mexican CMV under
the No Action Alternative
Pollutant
Inspectionsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
37.6727
49,989,000
0.00007536%
88,063,000
0.00004278%
NO2
2.8980
8,590,000
0.00003374%
25,393,000
0.00001141%
VOC
8.2292
5,297,000
0.00015535%
18,145,000
0.00004535%
Pb
0.0014
22,000
0.00000614%
4,199,000
0.00000003%
SO2
0.1409
363,000
0.00003880%
18,867,000
0.00000075%
PM10
0.1850
295,000
0.00006269%
23,679,000
0.00000078%
PM2.5
0.1679
229,000
0.00007330%
6,773,000
0.00000248%
a= Total emissions from the inspections of Mexican CMVs
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e= % of all Sources = (Inspections/Total from all Sources) X 100%
Table C-12 shows the total amount of emissions-for criteria pollutants-generated
from the inspection of 230,000 Mexican CMV under the CVSA Supplemental Alternative.
Table C-12. Total Annual Emissions from Inspections of Mexican CMV under
the Proposed Action Alternative
Pollutant
Inspectionsa
(short tons)
Total from On-Road Vehiclesb
(short tons)
% of On-Roadc
Total all Sourcesd
(short tons)
% of all Sourcese
CO
48.2175
49,989,000
0.00009646%
88,063,000
0.00005475%
NO2
3.7092
8,590,000
0.00004318%
25,393,000
0.00001461%
VOC
10.5326
5,297,000
0.00019884%
18,145,000
0.00005805%
Pb
0.0017
22,000
0.00000785%
4,199,000
0.00000004%
SO2
0.1803
363,000
0.00004966%
18,867,000
0.00000096%
PM10
0.2367
295,000
0.00008024%
23,679,000
0.00000100%
PM2.5
0.2148
229,000
0.00009381%
6,773,000
0.00000317%
a= Total emissions from the inspections of Mexican CMVs
b= Total emissions from the operation of on-road vehicles in the United
States
c= % of On-Road = (Inspections/Total from On Road Vehicles) X 100%
d= Total emissions from all sources in the United States
e= % of all Sources = (Inspections/Total from all Sources) X 100%
APPENDIX D - ENVIRONMENTAL
SCREENING PROCESS
Introduction
The following resources were eliminated from the environmental consequences
analysis because of the insignificance of the impacts on these resources
from the implementation of the four proposed rules and supplemental alternatives:
topography, biological resources, cultural resources, visual resources,
endangered species, water resources, land use, hazardous waste and solid
waste. These resources were dropped from detailed environmental analysis
because: 1) the alternatives do not require any construction activities,
and 2) the resource consumption levels and associated waste generation required
for longer application forms are insignificant. This appendix includes the
calculations of the impacts on resource consumption, which aided in the
determination of the insignificant impacts on the above-mentioned resources
and the specifics behind why these resources were eliminated.
* * * * *
APPENDIX E - NOISE EMISSIONS ANALYSIS
* * * * *
APPENDIX F - SELECTED NAFTA ENVIRONMENTAL REFERENCES
CEC, 2001. "Closing the Pathways of Aquatic Invasive Species Across
North America." Commission for Environmental Cooperation, Conservation
of Biodiversity. April 11, 2001.
http://www.cec.org/programs_projects/conserv_biodiv/217/index.cfm?varlan=english
This document presents the work of a project designed to develop alternatives
to protect marine and aquatic ecosystems from the effects of aquatic invasive
species. The initiative will develop a coordinated, multinational prevention
and control campaign aimed at eliminating pathways for the introduction
of invasive species among the coastal and fresh waters of Canada, Mexico,
and the United States.
CEC, 2001. "Assessing Environment and Trade Relationships." Commission
for Environmental Cooperation, Environment, Economy and Trade. April 11,
2001.
http://www.cec.org/programs_projects/trade_environ_econ/112/index.cfm?varlan=english
This project is designed to deepen understanding of the linkages between
the environment and trade liberalization, in accordance with the provision
in Article 10(6)(d) of NACEC to undertake an "ongoing assessment"
of the environmental effects of NAFTA. Among the strengths of NACEC's work
in this area is the commitment to undertake trade-related environmental
assessments in an open and participatory way.
CEC, 2001. "Tri-national Air Quality Improvement Initiative: North
American Trade and Transportation Corridors." Commission for Environmental
Cooperation, Pollutants and Health. April 11, 2001.
http://www.cec.org/programs_projects/pollutants_health/313/index.cfm?varlan=english
This project seeks to address significant air quality and other environmental
issues associated with transport along North American trade corridors. Such
issues affect all three countries of North America.
CEC, 2001. "Comparative Report on Environmental Standards." Commission
for Environmental Cooperation, Law and Policy. April 11, 2001.
http://www.cec.org/programs_projects/law_policy/411/index.cfm?varlan=english
NACEC is preparing a report on existing environmental standards in an area
of concern for Canada, Mexico and the U. S. Areas under current consideration
include, for example, trends in trade in wastes and the regulatory regimes
controlling transboundary movement of wastes, intensive agriculture practices,
control regimes for invasive species, and controls on air emissions from
electricity generating facilities. This report will form the basis for identifying
a process to develop greater compatibility of environmental technical regulations
and standards in the area studied.
CEC, 1999. "Assessing Environmental Effects of the North American Free
trade Agreement: An Analytic Framework (Phase II) and Issue Studies (3)."
Communications and Public Outreach Department of the CEC Secretariat, Commission
for Environmental Cooperation. March 1999.
http://www.cec.org/pubs_info_resources/publications/pdfs/english/engframe.pdf
This document is the second draft of a methodology for examining the environmental
effects of NAFTA. This methodology represents the ongoing work of a team
of more than two-dozen experts, with advice from dozens of other experts
and stakeholders from the United States, Canada, and Mexico. In addition
to the methodology, this report contains three issue studies taken from
the agriculture and energy sectors that were chosen to test and enrich the
framework.
CEC, 1997. "NAFTA's Institutions: The Environmental Potential and Performance
of the NAFTA Free trade Commission and Related Bodies." Communications
and Public Outreach Department of the CEC Secretariat, Commission for Environmental
Cooperation. November 1997.
http://www.cec.org/pubs_info_resources/publications/pdfs/english/NAFTen.pdf
This project presents a framework to be used for the ongoing monitoring
of the environmental changes occurring throughout North America in the wake
of NAFTA and the side agreements negotiated in conjunction with it. This
study analyzes the way NAFTA's economic institutions have moved to fulfill
their responsibilities and potential for environmental enhancement specific
in the NAFTA text, and have acted synergistically with NAFTA's environmental
institutions. Specifically, the document identifies and assesses NAFTA's
achievements during the first three years and evaluates how they might be
built upon in the future.
CEC, 1996. "NAFTA Effects-Potential NAFTA Effects: Claims and Arguments
1991-1994." Commission for Environmental Cooperation. August 1996.
http://www.cec.org/pubs_info_resources/publications/enviro_trade_econ/claindex.cfm?varlan=
english
This document identifies the major claims and arguments made by governments,
academics, non-governmental organizations (NGOs), and others in Canada,
the United States, and Mexico, suggesting that there are potential direct
and indirect environmental effects of the NAFTA.
CEC, 1996. "NAFTA Effects-A Survey of Recent Attempts to Model the
Environmental Effects of Trade." Commission for Environmental Cooperation.
August 1996.
http://www.cec.org/pubs_info_resources/publications/pdfs/english/nsae.pdf
This document reviews current theoretical understandings about the impact
of trade, trade liberalization, and trade agreements on the environment.
It also discusses the state of knowledge about modeling and analyzing the
environmental effects of trade.
CEC, 1996. "Dispute Avoidance: Weighing the Values of Trade and the
Environment under the NAFTA and the NAAEC." Commission for Environmental
Cooperation. October 1996.
http://www.cec.org/pubs_info_resources/publications/pdfs/english/disputee.pdf
This document examines past, present, and potential environmental trade
disputes in North America, in order to identify ways to avoid and/or resolve
such disputes. The report also discusses trade policies and dispute resolution
systems already in place under NAFTA and GATT, and cites possible improvements.
CEC, 1996. "Building a Framework for Assessing NAFTA Environmental
Effects Report of a Workshop held in La Jolla, CA, on April 29 and 30, 1996."
Commission for Environmental Cooperation. November 1996.
http://www.cec.org/pubs_info_resources/publications/pdfs/english/builde.pdf
This document makes available the presentations and supporting documents
from the CEC's first public meeting of its NAFTA Effects Project. In addition
to presenting original research from top experts in Mexico, the United States,
and Canada, this report includes both a summary of the workshop, and contact
information.
CPA, 2001. Rylander , Carole Keeton. "Economic Factors Affecting Cross-border
Transportation." State Functions at the Texas-Mexico Border and Cross-Border
Transportation. Texas Comptroller of Public Accounts. January 2001.
http://www.cpa.state.tx.us/specialrpt/border/sfatb1.html
This document contains the border logistics at the United States-Mexico
border in Texas. It explains the maquilladoras role in the population and
traffic increase at the border and also discusses other general border information.
CPA, 2001. Rylander , Carole Keeton. "The Cross-Border Process."
State Functions at the Texas-Mexico Border and Cross-Border Transportation.
Texas Comptroller of Public Accounts. January 2001.
http://www.cpa.state.tx.us/specialrpt/border/sfatb4.html
This document discusses the border crossing process between the United States
and Mexico at the Texas border. It includes the pre-border crossing activities
in Mexico, bridge crossing processes and both Mexican and United States
Inspections processes.
EPA, 2000. Protecting the Environment of the United States-Mexico Border
Area. United States Environmental Protection Agency Border Program. Washington:
December 2000.
http://www.scerp.org/transition.pdf
This paper discusses the many tools that the United States and Mexico have
developed to carry out improvement at the United States-Mexico border, an
area under particularly strong environmental stress. It also discusses the
opportunities for the new United States and Mexican Administrations and
the opportunities that they have to advance institutional and environmental
improvements.
GTW, 2001. Hunter, J. Martin, et al. "In the Matter of Cross-Border
Trucking Issues." NAFTA Panel Established Pursuant to Chapter Twenty.
Public Citizen Global Trade Watch. February 2001.
http://www.citizen.org/pctrade/nafta/naftapg.html
This discussion states that the panel must decide whether the United States
is in breach of Articles 1202 and/or 1203 of NAFTA by failing to modify
its moratorium on the processing of applications by Mexican-owned trucking
firms for authority to operate in the United States border states.
USITC, 2000 "International Trade Developments." International
Economic Review. United States. Office of Economics. Washington: August/September
2000.
http://www.usitc.gov/ier.htm
This document measures the impact of free trade on the environment. The
document finds evidence that freer trade may induce cleaner production in
poorer countries while resulting in small increases in pollution. This minor
effect may also be offset by improved environmental regulations, as freer
trade causes income to rise.
USMCC, 1998 "Environmental Issues in Mexico under NAFTA." United
States-Mexico Chamber of Commerce, NAFTA Forum Series. Washington. May 1998.
http://www.usmcoc.org/environment.html
This paper describes NAFTA's impact on the environmental situation in Mexico.
It also highlights bi-national and multinational Mexican institutions that
are working to improve Mexico's environment. This paper also explains the
opportunity that United States environmental technology firms have to export
solutions to Mexico.
APPENDIX G - SOCIOECONOMIC DEMOGRAPHIC
NUMBERS
* * * * *
APPENDIX H - PROPOSED FORMS OP-2 AND
OP-1 (MX)
* * * * *
1 42 U.S.C. § 4321 et seq.
2 40 C.F.R. § 1500 et seq.
3 DOT Order 5610.1C, Procedures for Considering Environmental Impacts, 9/18/79,
as amended 7/13/82, 7/30/85.
4 Section 6 of Public Law No. 97-261, 96 Stat. 1102 (September 20, 1982),
formerly codified at 49 U.S.C. § 10922(1), is now codified at 49 U.S.C.
§ 13902.
5 64 Fed. Reg. 58356, October 29, 1999.
6 Public Law No. 106-159, 113 Stat. 1748 (December 9, 1999).
7 65 Fed. Reg. 220, January 4, 2000 (effective, January 1 , 2000).
8 49 U.S.C. § 13902(a)(1).
9 49 U.S.C. § 13902(a)(4).
10 49 C.F.R., Part 372, Subpart B.
11 49 U.S.C., Section 30112.
12 NHTSA interpretive letter to the Canadian Trucking Association, dated
May 9, 1975.
13 49 C.F.R., Part 567.
14 42 U.S.C. § 112.
15 Titles 23 and 49, U.S.C.
16 40 C.F.R., parts 51 and 93.
17 42 U.S.C. Section 43321, et seq.
18 Resource Conservation and Recovery Act of 1976 (RCRA) codified at 42
U.S.C. §§ 6901 et seq.
19 49 CFR § 172.101, and 49 CFR, Part 173.
20 16 U.S.C. §§1531-1543).
21 16 U.S.C §1532(5)(A).
22 16 U.S.C. § 1532(5)(C).
23 16 U.S.C. Sec 470 et seq.
24 49 U.S.C. Sec 303 (c)
25 Pub. Law. 97-98, Sec 1530-1549, codified at 7 USC 4201, et seq
2
No. 03-358
PETITION FOR WRIT OF CERTIORARI FILED: SEPT. 8, 2003
CERTIORARI GRANTED: DEC. 15, 2003