Jump to main content.


Detroit River-Western Lake Erie Basin Indicator Project

INDICATOR: Combined Sewer Overflow Controls in Southeast Michigan

Other Indicators:

On this page:

Also:

Background

Most large, older cities in the Great Lakes basin were located on the banks of rivers or lakes to meet the needs for transportation and commerce. Detroit was no exception. During the 1700s and 1800s, the streets were primarily dirt or gravel and they frequently remained muddy after rainfall. Citizens of Detroit and similar cities grew tired of muddy streets and urged the government to do something about this inconvenience.

The immediate solution was to build sewers to drain storm water off the streets during wet weather so that they would not remain muddy for long periods of time. These sewers were either open ditches or pipes buried underground. As communities grew, these sewers needed to be quite substantial in size to carry away the storm water. Remember, of course, that the vehicles on these roads were horses and carriages, and that the horses left behind more than footprints. At that time, domestic water use was relatively low, but the domestic wastewater was simply dumped in the gutter where it would be flushed away during the next rain. During these rains, both domestic wastewater and manure from the streets were flushed into the sewers, where they were transported directly to the nearest waterway. This created both odor problems and pollution of waterways.

A new kind of sewer, called an interceptor sewer, was built to address these problems. They were primarily built parallel to waterways to carry wastewater further downstream. It was common and acceptable up to the late 1800s and early 1900s to move this wastewater further downstream where there were fewer or no people to complain. In the early 1900s, domestic use of water increased rapidly with human population growth and resulted in increased domestic wastewater discharges. Since the sewers at that time were originally designed to carry away storm water, the increased domestic wastewater from the growing population could exceed sewer capacity during heavy rains and snow melt. However, because of budget constraints, the sewers at that time were sized to intercept only the domestic waste during dry weather conditions. Therefore, one of two things had to happen during a rainstorm. Either the sewers would exceed their capacity and flood the streets or there needed to be a relief discharge directly into a waterway near these populated areas. Structures, called regulators, were constructed to provide this relief. They operate when the flow rises above the height of the overflow weir, allowing the combined storm and sanitary sewer flow to overflow into the receiving waterway – thus causing what has come to be called a combined sewer overflow (CSO).

As time went by, the idea of building sewers that handled both the sanitary wastewater and the storm water gave way to the concept of building a separate system just for sanitary wastes. These separate sewers came to be called sanitary sewers and the original type of sewer came to be called combined sewers. Today, these combined sewers are found only in older, larger cities where combined storm water and wastewater are treated during dry weather, but it overflows directly into rivers during and after wet weather events. When many of these combined sewers were constructed, they were simply called "sewers." Later on, in the 1930s and 1940s, the distinction between storm sewers, sanitary sewers, and combined sewers became well accepted.

Top of page

Status and Trends

Figure 1. Areas of Wayne, Oakland, and Macomb counties that have combined and separate sewer systems.


Figure 2. Historical and projected effects of Detroit Water and Sewerage Department's and customers' efforts to reduce and treat CSOs.

In 1972, the U.S. Congress passed the Clean Water Act which launched a major effort to control pollution from industrial and municipal sources. The law required each state to issue discharge permits to regulate the quantity and concentration of pollutants from municipal and industrial treatment facilities to meet state water quality standards.

By the mid-1980s virtually all of the over 400 municipal wastewater treatment plants in Michigan had achieved compliance with the Clean Water Act requirement to provide secondary treatment of all flows. Michigan's treatment plants were also required to disinfect the wastewater prior to discharge and reduce phosphorus loadings to control nutrient impacts in the Great Lakes basin.

As the discharges from wastewater treatment plants came under control, attention began to focus on water quality problems attributable to intermittent wet weather discharges from combined sewer systems. CSO discharges can be a significant source of pollution to receiving waters since they consist of a diluted mixture of untreated sanitary wastewater and storm water runoff. Water quality problems attributable to uncontrolled CSOs include public health threats from bacteria contamination and pathogenic organisms, dissolved oxygen depletion, aesthetic problems, and residues from sanitary trash and floatable materials.

CSOs are a particularly significant problem in southeast Michigan because of the high population and the fact that CSO discharges were impacting small urban waterways such as the Rouge River and its tributaries. Within the service area of the Detroit wastewater treatment plant, more than 25% of the service area utilizes combined sewer systems. Within the city of Detroit there are 35,924 hectares (88,770 acres) served by combined sewers and an additional 24,186 hectares (59,764 acres) in suburban communities in Wayne, Oakland and Macomb counties (Figure 1). Uncontrolled CSO discharges were identified as a major source of pollution throughout much of the Rouge River basin, the Clinton River basin, and portions of the Lake St. Clair and Detroit River shoreline.

In 1985, work began on the development of Remedial Action Plans for these watersheds to define alternatives for improving water quality and protecting public health. The Rouge River Remedial Action Plan was adopted in 1988 and called for substantial investment in facilities to control CSOs in Detroit, Wayne County and Oakland County. Similar control efforts were initiated along the Clinton River and Red Run Drain basin, and the shoreline areas of Lake St. Clair and the Detroit River.

The recommendations of the Remedial Action Plans were the basis for new permit requirements to eliminate or adequately treat CSO discharges throughout southeast Michigan. The southeast Michigan CSO control program received support from the federal government when Congress approved the Rouge River National Wet Weather Demonstration Project in 1992. Under this program, municipalities in the Rouge River watershed served as a pilot program to demonstrate the effectiveness of various CSO control measures. The program also instituted a variety of other pollution control activities related to storm water discharges, streambank erosion control, wetland preservation, public education, and other measures.

Prior to 1990, there were more than 170 uncontrolled CSOs in existence in 35 municipalities in southeast Michigan. The quantity of untreated combined sewage discharged annually at that time is estimated at more than 119 billion liters per year (over 31 billion gallons per year), although the actual quantity of the discharge varies in response to climatic conditions and rainfall patterns. CSO discharges typically occurred about 50 times per year throughout the region and the pollutant load from these discharges was significant. Numerous water quality studies in the area documented serious impairments and water quality standards violations during and after wet weather events when CSO discharges occurred. Dissolved oxygen levels in some areas were depleted, making it difficult for the watersheds to support aquatic life and fish.

In response to the regulatory initiative to control CSOs, southeast Michigan communities in the Detroit Water and Sewerage Department service area have committed to the construction of projects totaling nearly $2.2 billion to eliminate, capture, or treat combined sewage. A list of the CSO control projects is included in Table 1. The debt obligation to pay for these capital improvements has had a significant impact on local sewer rates, even though many facilities were financed with low interest loan assistance from the State Revolving Loan Fund, and the initial projects received grant support through the National Wet Weather Demonstration Project.

The benefits of this massive CSO expenditure have become apparent as water quality throughout southeast Michigan continues to improve. The volume of uncontrolled CSOs has decreased substantially, and further improvements will be achieved as projects currently in design and construction are completed and placed into service. As shown in Figure 2, the quantity of uncontrolled CSO discharges will be reduced by 85% when all of the facilities are completed and placed in service.

Dissolved oxygen levels in receiving waters throughout southeast Michigan have shown steady improvement, and fish and aquatic life surveys document that area waterways are markedly improved. Because the CSO control projects typically include disinfection to control bacteria, recreational users benefit from improved public health protection practices, and beach closures in response to wet weather events have become increasingly infrequent.

While the effort to control wet weather pollution from CSOs is not yet complete, the progress achieved to date demonstrates that significant water quality improvements are achievable in urban areas when CSO controls are constructed. The overall health of the watersheds in southeast Michigan is continuing to improve, and in large measure this is a result of the work by local government to control pollution from combined sewer systems throughout the area.

Table 1. CSO investment of southeast Michigan as of May 2007a. DWSD = Detroit Water and Sewerage Department.

a Listing does not include facilities to control sanitary sewer overflows (SSOs) from separated sewer systems except for equalization basins which were built to retain excess wet weather flows in newly separated combined sewer systems.
b Construction cost reflects the cost to build the facility (as-bid contractor's cost plus or minus change orders) and has not been adjusted to account for inflation since the project was built. Costs do not include engineering, administrative, land acquisition or legal expenses.

Name of the Facility Ownership Status Storage Volume: million liters (million gallons) Construction Cost b
Detention Basins
Belle Isle DWSD In Construction
1.14 (0.30)
Est. $13,866,000
Conner Creek DWSD Operational
119.24 (31.50)
$186,512,000
Hubbell-Southfield DWSD Operational
83.28 (22.00)
$54,884,000
Oakwood Pump Station DWSD In Construction
34.07 (9.00)
Est. $131,437,000
Puritan – Fenkell DWSD Operational
15.52 (4.10)
$18,194,000
Seven Mile DWSD Operational
11.73 (3.10)
$29,948,000
Acacia Park Oakland County Operational
15.14 (4.00)
$10,681,000
Bloomfield Village Oakland County Operational
37.85 (10.00)
$21,994,000
Birmingham Oakland County Operational
20.82 (5.50)
$26,252,000
GWK Oakland County Operational
350.91 (92.70)
$165,068,000
Chapaton Macomb County Operational
105.99 (28.00)
$25,817,000
Martin Macomb County Operational
32.55 (8.60)
$7,471,000
Milk River Wayne County Operational
71.92 (19.00)
$31,200,000
Dearborn Heights Dearborn Heights Operational
10.22 (2.70)
$18,678,000
Inkster Inkster Operational
11.73 (3.10)
$18,592,000
Redford Township Redford Operational
7.19 (1.90)
$14,300,000
SUBTOTAL
   
929.32 (245.50)
$774,894,000
Treatment/Capture Shafts
Capture Shaft 013 Dearborn In Construction
27.25 (7.20)
$28,895,000
Capture Shaft 014 Dearborn In Construction
38.23 (10.10)
$33,097,000
Disinfection Facility for Capture Shaft 013 and 014 Dearborn In Construction
Included Above
$4,397,000
Capture Shaft 015 Dearborn In Construction
9.08 (2.40)
$10,528,000
Original CSO Shafts Dearborn Constructed
Included Above
$26,000,000
Treatment Shafts 1 – 5 Dearborn In Design
98.80 (26.1)
$170,000,000
Treatment Shaft 016 Dearborn In Construction
12.49 (3.30)
$25,997,000
Treatment Shaft 017 Dearborn In Construction
24.61 (6.50)
$36,791,000
SUBTOTAL
   
210.47 (55.60)
$335,705,000
Screening & Disinfection Facilities
Baby Creek (Including VR-7) DWSD Operational
115.08 (30.4)
$73,107,000
Leib DWSD Operational
31.42 (8.3)
$31,438,000
St. Aubin DWSD Operational
9.20 (2.43)
$19,821,000
SUBTOTAL
   
155.69 (41.13)
$124,366,000
Tunnels
Upper Rouge Tunnels DWSD In Design
760.87 (201.00)
$640,000,000
SUBTOTAL
   
760.87 (201.00)
$640,000,000
In-System Storage Facilities (Dams and Gates)
Conner Creek Influent Storage Gates DWSD Operational
152.93 (40.40)
$4,392,000
Wyoming Relief (ISD001) DWSD Operational
23.24 (6.14)
$26,469,000
Weatherby (ISD002) DWSD Operational
11.92 (3.15)
Upper Livernois Relief (ISD003) DWSD Operational
9.24 (2.44)
Joy (ISD004) DWSD Operational
13.55 (3.58)
Clark Summit (ISD005) DWSD Operational
15.06 (3.98)
First Hamilton (ISD006) DWSD Operational
34.14 (9.02)
First Hamilton (ISD007) DWSD Operational
16.77 (4.43)
First Hamilton (ISD008) DWSD Operational
14.99 (3.96)
First Hamilton (ISD009) DWSD Operational
16.20 (4.28)
First Hamilton (ISD010) DWSD Operational
5.38 (1.42)
Conant Mt. Elliott (ISD011) DWSD Operational
34.18 (9.03)
Six Mile Rd. (ISD012) DWSD Operational
8.86 (2.34)
Seven Mile Rd. (ISD013) DWSD Operational
13.51 (3.57)
6 Mile & 6 Mile Relief Outfall Gates DWSD Operational
26.12 (6.90)
$7,708,000
Puritan Outfall Gates DWSD Operational
1.14 (0.30)
Lyndon Outfall Gates DWSD Operational
6.44 (1.7)
Lahser Outfall Gates DWSD Operational
5.30 (1.4)
W. Chicago Outfall Gates DWSD Operational
19.68 (5.2)
Tireman Outfall Gates DWSD Operational
21.58 (5.7)
Bloomfield Hills, Birmingham, Acacia Park Oakland County Operational
18.17 (4.8)
$1,552,000
GWK Influent Weir Storage Oakland County Operational
124.92 (33.00)
Included w/GWK Basin
Frisbee Sewer City of Detroit Operational
7.19 (1.9)
$2,043,000
SUBTOTAL
   
600.52 (158.64)
$42,164,000
Equalization Basins (as part of CSO Elimination Program)
Farmington Farmington Operational
12.11 (3.20)
$5,000,000
City of Wayne Wayne County Operational
8.71 (2.30)
$3,827,000
Livonia Livonia Operational
8.33 (2.20)
$1,029,000
SUBTOTAL
   
29.15 (7.70)
$9,856,000
Sewer Separations/Relief Sewers and Collection System Upgrades
Area 25 City of Wayne Operational  
$221,000
Areas 19, 20, 23 City of Wayne Operational  
$2,454,000
Area 18 City of Wayne Operational  
$82,000
Farmington Farmington Operational  
$9,000,000
Midtown West Garden City Operational  
$9,727,000
Midtown East Garden City Operational  
$6,435,000
South Venoy Garden City Operational  
$1,228,000
Merriman Garden City Operational  
$459,000
Perrin & Middlebelt Garden City Operational  
$10,848,000
Robinson Subdivision Plymouth Township Operational  
$557,000
Districts 30, 31, & 32 Plymouth Township Operational  
$341,000
Area 42 Westland Operational  
$346,000
Area 38 Westland Operational  
$1,364,000
Area 10 (Contract 1 & 2) Westland Operational  
$4,010,000
Area 10 (Contract 3) Westland Operational  
$1,874,000
Area 10 (Contract 4) Westland Operational  
$768,000
Grosse Pointe Farms Grosse Pointe Farms Operational  
$10,000,000
Grosse Pointe Park Grosse Pointe Park Operational  
$18,600,000
Eastpointe Roseville Separation Macomb County Operational  
$4,184,000
So. Macomb Relief Sewers Macomb County Operational  
$15,269,000
So. Macomb Pump Station/Bypass Structure Macomb County Operational  
$22,827,000
Area Tributary to CSO 016 Dearborn In Construction  
$6,380,000
Miller Rd. Pump Station Renovation Dearborn Operational  
$8,000,000
SUBTOTAL
     
$134,974,000
Operational Elements
Fairview Pump Station DWSD Operational  
$6,072,000
VR-15 (Conant Mt. Elliott) DWSD Operational  
$6,902,000
VR-17 (Shiawassee Gate) DWSD Operational  
$198,000
VR-8 (Hubbell-Southfield) DWSD Operational  
$202,000
SUBTOTAL
     
$13,374,000
Detroit WWTP
Primary Clarifiers No. 17, 18 DWSD Operational  
$89,018,000
PS-2A (Additional Pump) DWSD Operational  
$2,048,000
SUBTOTAL
     
$91,066,000
TOTAL EXPENDITURE
$2,166,399,000

Top of page

Management Next Steps

Key management actions for southeastern Michigan watersheds include:

Research/Monitoring Needs

Monitoring is essential for proper watershed management. Priority must be given to ensuring sufficient monitoring to be able to adequately evaluate effectiveness of programs and to make midcourse corrections. Further, research is needed on innovative funding mechanisms for storm water, CSOs, and watershed management in order to maintain the momentum for restoration and protection efforts.

Links for more information

Detroit Water and Sewerage Department www.dwsd.org exit EPA

Rouge River National Wet Weather Demonstration Project www.rougeriver.com exit EPA

Contact Information regarding Combined Sewer Overflow Controls in Southeast Michigann

Gary Fujita
Deputy Director of Detroit Water and Sewerage Department
E-mail Address: fujita@dwsd.org

James Sherrill
Wade Trim
E-mail Address: jsherrill@wadetrim.com

Dick Hinshon
Hinshon Environmental Consulting
E-mail Address: hinshonr@aol.com

Top of page


LLRS Navigation


Jump to main content.