Bridge Technology | |||
FHWA > Infrastructure > Bridge > Post-Tensioning Manual | |||
PDF Version (2.6 mb)
List of Figures and Tables1.1 ObjectiveChapter 2 Post-Tensioning System Materials and Components1.1.1 Benefits of Post-Tensioning1.2 Permanent Post-Tensioned Applications
1.1.2 Principle of Prestressing
1.1.3 Post-Tensioning Operations
1.1.4 Post-Tensioning Systems
1.2.1 Cast-in-Place Bridges on Falsework1.3 Temporary Longitudinal Post-Tensioning (Bars) - Typical Applications
1.2.2 Post-Tensioned AASHTO, Bulb-T, and Spliced Girders
1.2.3 Cast-in-Place Segmental Cantilever Bridges
1.2.4 Precast Segmental Balanced Cantilever Bridges1.2.4.1 Typical Features of Precast Cantilever Segments1.2.5 Precast Segmental Span-by-Span Bridges
1.2.4.2 Cantilever Tendons
1.2.4.3 Continuity Tendons
1.2.6 Transverse Post-Tensioning of Superstructures
1.2.7 Post-Tensioning of Substructures
1.2.7.1 Hammerhead Piers
1.2.7.2 Straddle Bents
1.2.7.3 Cantilever Piers
1.2.7.4 Precast Piers
1.2.7.5 Precast Segmental Box Section Arches
1.2.7.6 Transverse, Confinement Tendons at Tops of Piers1.3.1 Erection of Precast Cantilever Segments
1.3.2 Closure of Epoxy Joints in Span-by-Span Erection
2.1 Prestressing SteelChapter 3 Post-Tensioning Duct and Tendon Installation2.1.1 Strands and Bars2.2 Grout2.1.1.1 Strands2.1.2 Shipping, Handling and Storage
2.1.1.2 Bars
2.1.3 Acceptance2.2.1 Purpose2.3 Ducts
2.2.2 Cement and other Pozzolans for Grout
2.2.3 Pre-bagged Grouts
2.2.4 Thixotropic vs. Non-Thixotropic Grouts
2.2.5 Admixtures
2.2.6 Laboratory Tests2.2.6.1 Setting Time2.2.7 Shipping, Handling, Storage and Shelf life
2.2.6.2 Grout Strength
2.2.6.3 Permeability
2.2.6.4 Volume Change
2.2.6.5 Pumpability and Fluidity (Flow Cone)
2.2.6.6 Simulated Field High Temperature Fluidity Test
2.2.6.7 Bleed
2.2.6.8 Corrosion
2.2.6.9 Wet Density
2.2.8 Acceptance
2.2.9 Field Mock-Up Tests2.3.1 Duct Size2.4 Other Post-Tensioning System Hardware2.3.1.1 Strand Tendons2.3.2 Ducts for Tendons
2.3.1.2 Bar Tendons
2.3.2.1 Corrugated Steel2.3.3 Shipping, Handling and Storage of Ducts
2.3.2.2 Smooth, Rigid Steel Pipe
2.3.2.3 Corrugated Plastic
2.3.2.4 Smooth, High Density Polyethylene Pipe (HDPE) for External Tendons
2.3.2.5 Plastic Fittings and Connections for Internal Tendons
2.3.2.6 External Tendon Duct Connections
2.3.2.7 Shrink Sleeves
2.3.4 Acceptance of Duct Materials2.4.1 Anchorages2.5 Other PT System Qualification Tests2.4.1.1 Basic Bearing Plates2.4.2 PT Bars, Anchor Nuts and Couplers
2.4.1.2 Special Bearing Plates or Anchorage Devices
2.4.1.3 Wedge Plates
2.4.1.4 Wedges and Strand-Wedge Connection
2.4.3 Grout Inlets, Outlets, Valves and Plugs
2.4.4 Permanent Grout Caps
3.1 Shop DrawingsChapter 4 Grouting of Post-Tensioning Tendons3.1.1 Drawings and Details3.2 Tendon Testing On Site3.1.1.1 Purpose3.1.2 Stressing Calculations
3.1.1.2 Typical Contents
3.1.1.3 Typical Approval Process3.1.2.1 Example 1: Four Span Spliced I - Girder
3.1.2.2 Example 2: External Tendon in End Span3.2.1 Friction3.3 Anchorages and Anchor Components
3.2.2 Modulus of Elasticity
3.3.1 Standard or Basic Anchor Bearing Plate3.4 Duct Installation
3.3.2 Multi-Plane Anchor
3.3.3 Special (Composite) Anchor Plates
3.3.4 Anchor Plates for Bar Tendons
3.3.5 Local Zone Reinforcement3.4.1 Alignment3.5 Tendon Installation3.4.1.1 Ducts for Internal Tendons: I-girders and Cast-in-Place Construction3.4.2 Duct Supports
3.4.1.2 Ducts for Internal Tendons in Precast Segments
3.4.1.3 Ducts for External Tendons in Cast-in-Place and Precast Segments
3.4.1.4 Alignment at Anchors
3.4.1.5 Cover
3.4.3 Splices and Connections
3.4.4 Grout Inlets and Outlets
3.4.5 Size of Pipes for Grout Inlets, Outlets and Drains
3.4.6 Positive Shut-Offs
3.4.7 Protection of Ducts during Concrete Placement3.4.7.1 Concrete Pressure
3.4.7.2 Movement of Concrete
3.4.7.3 Vibration of Concrete3.5.1 Tendon Types3.6 Jacks and Other Stressing Equipment
3.5.2 Proving of Internal Post-Tensioning Ducts
3.5.3 Installation Methods
3.5.4 Aggressive Environments
3.5.5 Time to Grouting and Temporary Tendon Protection3.6.1 Types3.7 Jacking Methods3.6.1.1 Mono-Strand Jacks3.6.2 Calibration
3.6.1.2 Multi-Strand Jacks
3.6.1.3 Bar Jacks3.6.2.1 Jack and Gauge
3.6.2.2 Master Gauge
3.6.2.3 Calibration Curve
3.6.2.4 Jack Repair3.7.1 Single (Mono) Strand Stressing3.8 Stressing Operations3.7.1.1 Single Strand, Single End and Alternate End Stressing3.7.2 Multi-Strand
3.7.1.2 Single Strand, Two-End Stressing3.7.2.1 Multi-Strand, Single End Stressing and Alternate End Stressing3.7.3 Bar Tendons
3.7.2.2 Multi-Strand, Two-End Stressing3.8.1 Personnel and Safety3.9 Stressing Records
3.8.2 Jacking Force
3.8.3 Measuring Elongations on Strand Tendons
3.8.4 Measuring Elongations on PT Bars
3.8.5 Field Variables3.8.5.1 Friction3.8.6 Final Force
3.8.5.2 Anchor Set or Wedge Set
3.8.5.3 Strand Slip
3.8.5.4 Re-Gripping of Strand by Wedges
3.8.7 Strand End Cut-Off
3.8.8 Lift-Off
3.10 Stressing Problems and Solutions3.10.1 Strand Slip
3.10.2 Wire Breaks
3.10.3 Elongation Problems3.10.3.1 Too Small Elongation at Jacking End under Full Load3.10.4 Breaking Wedges
3.10.3.2 Low Elongation for Whole Tendon
3.10.3.3 Elongation Greater than Tolerance
3.10.3.4 Low Stressing Force
3.10.3.5 Overall Tolerance on a Group of Tendons
4.1 Grouting PlanAppendix A Terminology
4.2 Grout Testing
4.3 Grouting Operations4.3.1 Verification of Post-Tensioning Duct System Prior to Grouting4.4 Grouting Problems and Solutions4.3.1.1 Check for Water and Debris4.3.2 Grouting Equipment
4.3.1.2 Proving Ducts with Torpedo
4.3.1.3 Inlets, Outlets and Connections
4.3.1.4 Pressure Check of Duct System4.3.2.1 Mixer, Storage Hopper, Screen, Pump, Pressure Gauges, Hoses4.3.3 Batching and Mixing
4.3.2.2 On-Site Test Equipment for Production Grouting
4.3.2.3 Vacuum Grouting Equipment
4.3.2.4 Stand-by Grouting Equipment
4.3.2.5 Clean Grouting Equipment
4.3.4 On-site Tests for Production Grouting4.3.4.1 Production Bleed Test-Prior to Injection4.3.5 Injection of Grout
4.3.4.2 Normal, Non-Thixotropic, Grout-Prior to Injection at Inlet
4.3.4.3 Thixotropic Grout-Prior to Injection at Inlet
4.3.4.4 Normal, Non-Thixotropic Grout-Discharge at Final Outlet
4.3.4.5 Thixotropic Grout-Discharge at Final Outlet4.3.5.1 Pumping4.3.6 Grout Injection of Superstructure Tendons
4.3.5.2 Limiting Grout Injection Pressures
4.3.5.3 Grout Flow Rate4.3.6.1 Locations of Inlets and Outlets4.3.7 Grout Injection of Vertical Tendons
4.3.6.2 Sequence of Using and Closing Outlets
4.3.6.3 Grout Pressure Test for Leaks
4.3.6.4 Release Entrapped Air and Lock-Off
4.3.6.5 Incomplete Grouting
4.3.7.1 Grout Material4.3.8 Post-Grouting Inspection
4.3.7.2 Standpipes
4.3.7.3 Grout Injection
4.3.7.4 Incomplete Grouting4.3.8.1 Opening Inlets and Outlets for Inspection4.3.9 Filling Voids by Vacuum Grouting
4.3.8.2 Drill Grout to Verify Absence of Voids
4.3.8.3 Frequency of Inspection
4.3.8.4 Filling Drilled Inspection Holes
4.3.8.5 Incomplete Grouting
4.3.9.1 Time for Completion of Vacuum Grouting4.3.10 Sealing of Grout Inlets and Outlets
4.3.9.2 Grout Material
4.3.9.3 Equipment
4.3.9.4 Vacuum Grouting Operation
4.3.11 Protection of Post-Tensioning Anchorages
4.3.12 Grouting Report4.4.1 Interruption of Grout Flow4.5 Examples of Grouting Procedures
4.4.2 Too High Grouting Pressure
4.4.3 Flushing of Incomplete Grout
4.4.4 Unanticipated Cross-Grouting
4.4.5 Production Grout Fluidity Unacceptable4.5.1 Example 1: Two-Span Spliced I-Girder
4.5.2 Example 2: Four-Span Spliced I-Girder
4.5.3 Example 3: Cantilever and Drop-In Spliced 3-Span I-Girder
4.5.4 Example 4: Cast-in-Place on Falsework
4.5.5 Example 5: Cantilever or Top Continuity Post-Tensioning
4.5.6 Example 6: Bottom Continuity Tendon in Variable Depth Cantilever
4.5.7 Example 7: End Span External Tendon in Span-by-Span Structure
4.5.8 Example 8: Inlet and Outlet Connections to Bottom External Tension
4.5.9 Example 9: Lateral Tendons in Hammerhead Pier Cap
4.5.10 Example 10: Vertical Post-Tensioning in Pier
4.5.11 Example 11: Cantilever C-Pier
A.1 Post-Tensioning SystemsAppendix B Personnel Qualifications
A.2 Post-Tensioning Grout Related Definitions
A.3 Contract Administration Definitions
A.4 Abbreviations and Acronyms
B.1 Contractor's PersonnelAppendix C Further Examples of Post-Tensioning Tendon ApplicationsB.1.1 Project EngineerB.2 Construction Engineering and Inspection (CEI)
B.1.2 Project Superintendent / Manager
B.1.3 Foreman
B.1.4 Crews for Tendon Installation and Stressing
B.1.5 Crews for Tendon GroutingB.2.1 Resident Engineer or Senior Project Engineer
B.2.2 Project Engineer
B.2.3 Lead Inspector
B.2.4 Inspector
C.1 Cantilever TendonsAppendix D Corrosion Protection of Post-Tensioning Tendons
C.2 Continuity Tendons
C.3 Continuity Tendons in Expansion Joint Spans
C.4 In-Span Hinges in Balanced Cantilever Construction
C.5 Precast Segmental Span-by-Span Bridges
C.6 Precast Segmental Progressive Cantilever Bridges
C.7 Transverse Post-TensioningC.7.1 Transverse Top Slab Post-Tensioning
C.7.2 Transverse Post-Tensioning of Multiple Precast Element Superstructures
C.7.3 Transverse Post-Tensioning in Diaphragms
C.7.4 Vertical Post-Tensioning in Diaphragms
C.7.5 Transverse Post-Tensioning in Deviator Ribs of Precast Segments
C.7.6 Vertical Post-Tensioning Bars in Webs
D.1 Corrosion ProtectionAppendix E BibliographyD.1.1 BackgroundD.2 Corrosion Protection Materials
D.1.2 Levels of ProtectionD.2.1 Concrete CoverD.3 Corrosion Protection along a Tendon
D.2.2 Ducts
D.2.3 Grout
D.2.4 Other ConsiderationsD.3.1 Internal TendonsD.4 Sealing Intermediate Inlets and Outlets
D.3.2 External Tendons
D.4.1 Internal TendonsD.5 Corrosion Protection at Anchorages
D.4.2 External TendonsD.5.1 Possible Levels of Anchorage ProtectionD.6 Temporary Protection during Construction
D.5.2 Permanent Grout Caps
D.5.3 Anchor Protection Details
D.5.4 Post-Tensioning Anchorage Protection InstallationD.5.4.1 Surface Preparation
D.5.4.2 Forms for Anchorage Pour-Backs
D.5.4.3 Seal Coatings - On Non-Visible Surfaces
D.5.4.4 Concrete Test Block for Seal Coating on Visible Vertical Surfaces
D.7 Watertight Segmental Box Girder Bridges