Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
09/24/08 |
09/30/08 |
FRN Published- Receipt & Availability |
11/17/08 |
11/17/08 |
FRN Published – Acceptability and Opportunity for Hearing |
12/30/08 |
12/30/08 |
FRN Published-Notice of Intent to Conduct Environmental Scoping |
1/27/09 |
1/26/09 |
Public Meeting – LR Overview & Environmental Scoping |
2/25/09 |
2/25/09 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
2/23/09 |
2/23/09 |
Environmental Scoping Period Ends |
3/27/09 |
|
Audit – Environmental |
3/30/09-4/3/09 |
|
Audit - Scoping & Screening Methodology |
4/20/09-4/24/09 |
|
Environmental Requests for Additional Information (RAIs) Issued |
4/30/09 |
|
Audit - Aging Management Programs (AMPs/TLAAs/AMR) |
TBD |
|
Environmental RAIs - Response Received |
6/1/09 |
|
Safety RAIs – Issued |
6/30/09 |
|
Inspection – Regional |
7/13/09-7/17/09 |
|
Safety RAI - Responses Received |
7/30/09 |
|
Public Exit Meeting - Regional Inspections |
TBD |
|
Inspection – Final |
7/27/09-7/31/09 |
|
Draft Supplemental Environmental Impact Statement (SEIS) – Issued |
12/15/09 |
|
EPA FRN Published - Availability / Comment on draft SEIS |
12/22/09 |
|
Public Meeting - draft SEIS |
1/21/10 |
|
Safety Evaluation Report (SER) with Open Items – Issued* |
3/2/10 |
|
End of draft SEIS Comment Period |
4/06/10 |
|
ACRS Subcommittee Meeting on SER with Open Items |
5/5/10 |
|
Final SEIS – Issued |
6/29/10 |
|
EPA FRN Published - Availability of Final SEIS |
7/06/10 |
|
SER – Issued |
7/29/10 |
|
ACRS Full Committee Meeting on SER |
10/7/10 |
|
Staff Recommendation to Director, NRR |
10/22/10 |
|
Decision Director NRR - Approval (26 months if no hearing) |
11/29/10 |
|
Commission decision (if hearing is granted) |
7/15/11 |
|
The public is encouraged to participate in the reactor license renewal
process through public meetings, and public comment periods on rules,
renewal guidance, and other documents. The Reactor
License Renewal Public Involvement page provides general information
to help the public participate.