Plant Applications for License Renewal
Arkansas Nuclear One,
Unit 1
Arkansas Nuclear One,
Unit 2
Beaver Valley
Browns Ferry
Brunswick
Calvert Cliffs
Cooper
Crystal River
D.C. Cook
Dresden and Quad Cities
Duane Arnold Energy Center
Edwin I. Hatch
Farley
FitzPatrick
Fort Calhoun
Ginna
Harris
Indian Point
Kewaunee
McGuire and Catawba
Millstone
Monticello
Nine Mile Point,
Units 1 and 2
North Anna and Surry
Oconee
Oyster Creek
Palisades
Palo Verde
Peach Bottom
Pilgrim
Point Beach
Prairie Island, Units 1 and 2
Robinson
St. Lucie
Summer
Susquehanna
Three Mile Island, Unit 1
Turkey Point
Vermont Yankee
Vogtle
Wolf Creek

Cooper Nuclear Station - License Renewal Application

Cooper Nuclear Station

On this page:

Application Information:

The following links on this page are to documents in Adobe Portable Document Format (PDF). See our Plugins, Viewers, and Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.

(To top of page)

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive License Renewal (LR) Application 09/24/08 09/30/08
FRN Published- Receipt & Availability 11/17/08 11/17/08
FRN Published – Acceptability and Opportunity for Hearing 12/30/08 12/30/08
FRN Published-Notice of Intent to Conduct Environmental Scoping 1/27/09 1/26/09
Public Meeting – LR Overview & Environmental Scoping 2/25/09 2/25/09
Deadline for Filing Hearing Requests and Petitions for Intervention 2/23/09 2/23/09
Environmental Scoping Period Ends 3/27/09  
Audit – Environmental 3/30/09-4/3/09  
Audit - Scoping & Screening Methodology 4/20/09-4/24/09  
Environmental Requests for Additional Information (RAIs) Issued 4/30/09  
Audit - Aging Management Programs (AMPs/TLAAs/AMR) TBD  
Environmental RAIs - Response Received 6/1/09  
Safety RAIs – Issued 6/30/09  
Inspection – Regional 7/13/09-7/17/09  
Safety RAI - Responses Received 7/30/09  
Public Exit Meeting - Regional Inspections TBD  
Inspection – Final 7/27/09-7/31/09  
Draft Supplemental Environmental Impact Statement (SEIS) – Issued 12/15/09  
EPA FRN Published - Availability / Comment on draft SEIS 12/22/09  
Public Meeting - draft SEIS 1/21/10  
Safety Evaluation Report (SER) with Open Items – Issued* 3/2/10  
End of draft SEIS Comment Period 4/06/10  
ACRS Subcommittee Meeting on SER with Open Items 5/5/10  
Final SEIS – Issued 6/29/10  
EPA FRN Published - Availability of Final SEIS 7/06/10  
SER – Issued 7/29/10  
ACRS Full Committee Meeting on SER 10/7/10  
Staff Recommendation to Director, NRR 10/22/10  
Decision Director NRR - Approval (26 months if no hearing) 11/29/10  
Commission decision (if hearing is granted) 7/15/11  

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

(To top of page)

Project Managers for Cooper Nuclear Station

Cooper Nuclear Station PMs
License Renewal Tam Tran
License Renewal Emmanuel Sayoc
Lead Power Plant Fred Lyon