Viet Nam,Soc Rep of
|
AOTA: (N) VIE 39595-01
|
Project Name
Mong Duong Thermal Power Generation Project
Executing Agency
Electricity Viet Nam
TA Amount (US$ '000)
150.00
Sector/Subsector
Energy /Conventional Energy Generation (other than hydropower)
Date of First Listing
29 September 2005
|
- Objectives and Scope
-
The TA's objective is to confirm the technical and economic viability for developing the Stage 1 (1,000 MW) of Mong Duong coal fired power plant in terms of EVN's power development plan. The scope of the SSTA include: (i) confirming the project's justification, in terms of EVN's power development plan, and its viability; (ii) confirming with EVN the general approach to be adopted in developing the overall project including its initial public sector component and its subsequent private sector component; (iii) agreeing with EVN on th most appropriate coal-burning technology for environmental impacts and complying with national environmental emission standards, as well as others as necessary; (iv) preparing detailed scope, terms of reference, and cost estimates, for phase 2 (i.e. Technical Assistance Engineering Loan) for detailed designs, preparation of tender documents and procurement, environment and social safeguard activities, for Stage 1 of Mong Duong power project; and (v) providing assistance to the Mnistry of Industry and EVN in developing the Stage 2 as a private sector project.
- Consulting Services
-
The TA will require assistances of about six person-months of international and about five person-months of domestic consulting services. The consultants will be recruited as individual consultants in accordance with the ADB's Guidelines on the Use of Consultants.
- Project Processing Stage
-
Fact-Finding Mission Completed
|
:
|
8 September 2005
|
- Recruitment of Consultants
-
The TA will be implemented within a four-month period commencing in November 2005 and ending in February 2006.
- Project Officer
-
Anthony J. Jude (632-6317)
- Infrastructure Division, MKRD
- ajude@adb.org
|
|