skip navigation links 
 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page

Generic Environmental Impact Statement for License Renewal of Nuclear Plants (NUREG-1437, Supplement 2)


On this page:

Table of Contents


Publication Information

[ Next | Top of file ]

Supplement 2
Regarding the Oconee Nuclear Station
Final Report
Manuscript Completed: December 1999
Date Published: December 1999

Division of Regulatory Improvement Programs
U.S. Nuclear Regulatory Commission
Office of Nuclear Reactor Regulation
Washington, DC 20555-0001


Abstract

[ Prev | Next | Top of file ]

The U.S. Nuclear Regulatory Commission (NRC) considered the environmental effects of renewing nuclear power plant operating licenses for a 20-year period in the Generic Environmental Impact Statement for Renewal of Nuclear Plants (GEIS), NUREG-1437, and codified the results in 10 CFR Part 51. The GEIS (and its Addendum 1) identifies 92 environmental issues and reaches generic conclusions related to environmental impacts for 69 of these issues that apply to all plants or to plants with specific design or site characteristics. Additional plant-specific review is required for the remaining issues. These plant-specific reviews are to be included in a supplement to the GEIS.

This supplemental environmental impact statement (SEIS) has been prepared in response to an application submitted to the NRC by Duke Energy Corporation (Duke) to renew the operating licenses (OLs) for Oconee Nuclear Station (ONS) Units 1, 2, and 3 for an additional 20 years under 10 CFR Part 54. This SEIS includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse effects. It also includes the staff's recommendation regarding the proposed action.

Neither Duke nor the staff has identified significant new information for any of the 69 issues for which the GEIS reached generic conclusions and which apply to ONS. Therefore, the staff concludes for these issues that the impacts of renewing the ONS OLs will not be greater than impacts identified in the GEIS for these issues. For each of these issues, the GEIS conclusion is that the impact is of SMALL significance (except for collective offsite radiological impacts from the fuel cycle and from high-level waste and from spent fuel, which were not assigned a single significance level) and that additional mitigation measures are likely not to be sufficiently beneficial to be warranted.

Each of the remaining 23 issues that applies to ONS is addressed in this SEIS. For each applicable issue, the staff concludes that the significance of the potential environmental effects of renewal of the OL is small. The staff also concludes that additional mitigation measures are likely not to be sufficiently beneficial as to be warranted.

The NRC staff recommends that the Commission determine that the adverse environmental impacts of license renewal for ONS Units 1, 2, and 3 are not so great that preserving the option of license renewal for energy-planning decisionmakers would be unreasonable. This recommendation is based on (1) the analysis and findings in the GEIS; (2) the Environmental Report submitted by Duke; (3) consultation with Federal, State, and local agencies; (4) the staff's own independent review, and (5) the staff's consideration of public comments.


Figures


[ Prev | Next | Top of file ]

2-1 Location of Oconee Nuclear Station

2-2 Oconee Nuclear Station - One-Mile Exclusion Area

2-3 Location of Oconee Nuclear Station Relative to Other Parts of Keowee-Toxaway Project

2-4 Oconee Nuclear Station Layout

2-5 Oconee Nuclear Station (aerial photo)

2-6 Transmission Lines Attributable to the Oconee Nuclear Station in the Final Environmental Statement

2-7 Oconee Nuclear Station - Water Flow Diagram

2-8 Oconee Nuclear Station - 16-km (10-mi) Radius

2-9 Oconee Nuclear Station - 80-km (50-mi) Radius

4-1 Geographic Distribution of Minority Populations Within 80 km (50 mi) of ONS

4-2 Geographic Distribution of Low-Income Populations Within 80 km (50 mi) of ONS


Executive Summary


[ Prev | Next | Top of file ]

By letter dated July 7, 1998, Duke Energy Corporation (Duke) submitted an application to the U.S. Nuclear Regulatory Commission (NRC) to renew the operating licenses for Units 1, 2, and 3 of the Oconee Nuclear Station (ONS) for an additional 20-year period. If the operating licenses are renewed, Federal (other than NRC) agencies, State regulatory agencies, and the owners of the plant will ultimately decide whether the plant will continue to operate. This decision will be based on factors such as the need for power or other matters within the State's jurisdiction or the purview of the owners. If the operating licenses are not renewed, Units 1, 2, and 3 will be shut down on or before the expiration of the current operating licenses, which are February 6, 2013, October 6, 2013, and July 19, 2014, respectively.

Under the National Environmental Policy Act of 1969 (NEPA), an environmental impact statement (EIS) is required for major Federal actions significantly affecting the quality of the human environment. The NRC has implemented Section 102 of NEPA in 10 CFR Part 51. In 10 CFR 51.20(b)(2), the Commission requires preparation of an EIS or a supplement to an EIS for renewal of a reactor operating license; 10 CFR 51.95(c) states that the EIS prepared at the operating license renewal stage will be a supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437.(1)

Upon acceptance of the Duke application, the NRC staff began the environmental review process described in 10 CFR Part 51 by publishing a notice of intent to prepare an EIS and to conduct scoping. The staff visited the ONS site in October 1998 and held public scoping meetings on October 19, 1998, in Clemson, South Carolina. The staff reviewed the Duke environmental report (ER) and compared it to the GEIS, consulted with Federal, State, and local agencies, conducted an independent review of the issues following the guidance set forth in the draft Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal, NUREG-1555, Supplement 1, and considered the public comments from the scoping process and the comment period for the draft Supplemental Environmental Impact Statement (SEIS) for ONS (that was issued on May 20, 1999). Two public meetings were held in Clemson, South Carolina, on July 8, 1999, during which the staff described the preliminary results of the NRC environmental review and answered questions related to it in order to provide members of the public with information to assist them in formulating their comments. This SEIS includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse effects. It also includes the staff's recommendation regarding the proposed action.

The Commission has adopted the following definition of purpose and need for license renewal from the GEIS:

The purpose and need for the proposed action (renewal of an operating license) is to provide an option that allows for power generation capability beyond the term of a current nuclear power plant operating license to meet future system generating needs, as such needs may be determined by State, utility, and, where authorized, Federal (other than NRC) decisionmakers.

The goal of the staff's environmental review, as defined in 10 CFR 51.95(c)(4) and the GEIS, is to determine:

... whether or not the adverse environmental impacts of license renewal are so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable.

Both the statement of purpose and need and the evaluation criterion implicitly acknowledge that there are factors, in addition to license renewal, that will ultimately determine whether ONS continues to operate beyond the period of the current operating licenses.

The GEIS contains the results of a systematic evaluation of the consequences of renewing an operating license and operating a nuclear power plant for an additional 20 years. It evaluates 92 environmental issues using a three-level standard of significance--SMALL, MODERATE, or LARGE--based on Council on Environmental Quality guidelines. These significance levels are as follows:

SMALL: Environmental effects are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.

MODERATE: Environmental effects are sufficient to alter noticeably, but not to destabilize, important attributes of the resource.

LARGE: Environmental effects are clearly noticeable and are sufficient to destabilize important attributes of the resource.

For 69 of the 92 issues considered in the GEIS, the analysis in the GEIS shows that

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other plant or site characteristics

(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from high-level waste and spent fuel disposal)

(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

These 69 issues are identified in the GEIS as Category 1 issues. In the absence of significant new information, the staff relied on conclusions as amplified by supporting information in the GEIS for issues designated Category 1 in 10 CFR Part 51, Subpart A, Appendix B, Table B-1.

Of the 23 issues not meeting the criteria set forth above, 21 are classified as Category 2 issues requiring analysis in a plant-specific supplement to the GEIS. The remaining two issues, environmental justice and chronic effects of electromagnetic fields, are not categorized. Environmental justice was not evaluated on a generic basis and must also be addressed in a plant-specific supplement to the GEIS. Information on the chronic effects of electromagnetic fields was not conclusive at the time the GEIS was prepared.

This SEIS documents the staff's evaluation of all 92 environmental issues considered in the GEIS. The staff considered the environmental impacts associated with alternatives to license renewal and compared the environmental impacts of license renewal and the alternatives. The alternatives to license renewal that are considered include the no-action alternative (not renewing the ONS operating licenses) and alternative methods of power generation. Among the alternative methods of power generation, coal-fired and gas-fired generation appear the most likely if the power from ONS is replaced. These alternatives are evaluated assuming that the replacement power generation plant is located at either the ONS site or an unspecified "greenfield" site.

Duke and the staff have established independent processes for identifying and evaluating the significance of any new information on the environmental impacts of license renewal. Neither Duke nor the staff has identified any significant new information related to Category 1 issues that would call into question the conclusions in the GEIS. Similarly, neither Duke nor the staff has identified any new issue applicable to the ONS that has a significant environmental impact. Therefore, the staff relies upon the conclusions of the GEIS for all 69 Category 1 issues.

The staff has reviewed the Duke analysis for each Category 2 issue and has conducted an independent review of each issue. Five Category 2 issues are not applicable because they are related to plant design features or site characteristics not found at ONS. Four Category 2 issues are not discussed in this SEIS because they are specifically related to refurbishment. Four additional Category 2 issues that apply to both refurbishment and to operation during the renewal term are only discussed in relation to operation during the renewal term. Duke has stated that their evaluation of structures and components, as required by 10 CFR 54.21, did not identify any major plant refurbishment activities or modifications necessary to support the continued operation of ONS beyond the end of the existing operating licenses. In addition, routine replacement of components or additional inspection activities are within the bounds of normal plant component replacement and therefore are not expected to affect the environment outside of the bounds of the plant operations evaluated in the Final Environmental Statement (FES) for ONS.

Twelve Category 2 issues, as well as environmental justice and chronic effects of electromagnetic fields, are discussed in detail in this SEIS. For all 12 Category 2 issues and environmental justice, the staff concludes that the potential environmental effects are of SMALL significance in the context of the standards set forth in the GEIS. In addition, the staff determined that a consensus has not been reached by appropriate Federal health agencies that there are adverse effects from electromagnetic fields. Therefore, no further evaluation of this issue is required. For severe accident mitigation alternatives (SAMAs), the staff concludes that a reasonable, comprehensive effort was made to identify and evaluate SAMAs. Based on its review of the SAMAs for ONS, the staff concludes that none of the candidate SAMAs are cost beneficial.

Mitigation measures were considered for each Category 2 issue. Current measures to mitigate environmental impacts of plant operation were found to be adequate, and no additional mitigation measures were deemed sufficiently beneficial to be warranted.

In the event that the ONS operating licenses are not renewed and the units cease operation on or before the expiration of their current operating licenses, the adverse impacts of likely alternatives will not be smaller than those associated with continued operation of ONS. The impacts may, in fact, be greater in some areas.

The NRC staff recommends that the Commission determine that the adverse environmental impacts of license renewal for Oconee Nuclear Station Units 1, 2, and 3 are not so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable. This recommendation is based on (1) the analysis and findings in the GEIS; (2) the ER submitted by Duke; (3) consultation with other Federal, State, and local agencies; (4) the staff's own independent review, and (5) the staff's consideration of public comments.


Abbreviations/Acronyms


[ Prev | Next | Top of file ]

AEA Atomic Energy Act
AEC U.S. Atomic Energy Commission
ALARA as low as reasonably achievable
ALI annual limits on intake
AOC averted offsite property damage costs
AOE averted occupational exposure
AOSC averted onsite costs
APE averted public exposure
 
Btu British thermal units
BWST borated water storage tank
 
CCW condenser circulating water
CDF core damage frequency
CEQ Council on Environmental Quality
CFR Code of Federal Regulations
COE cost of enhancement
CRAC Calculations of Reactor Accident Consequences
CWA Clean Water Act
 
DBA design basis accidents
DO dissolved oxygen
DOC Department of the Census
DOE U.S. Department of Energy
DOT U.S. Department of Transportation
Duke Duke Energy Corporation
 
EC effluent concentration
EIS Environmental Impact Statement
EMF electromagnetic field
EPA U.S. Environmental Protection Agency
ER environmental report
ESRP Environmental Standard Review Plan for License Renewal
EWST elevated water storage tank
 
FERC Federal Energy Regulatory Commission
FES final environmental statement
FR Federal Register
FSAR Final Safety Analysis Report
ft feet
FWPCA Federal Water Pollution Control Act (also known as the Clean Water Act)
FWS U.S. Fish and Wildlife Service
 
GEIS Generic Environmental Impact Statement for License Renewal of Nuclear Plants, NUREG-1437
gpd gallons per day
gpm gallons per minute
 
ha hectare
HE high energy
HLW high-level waste
HPI high pressure injection
HPSW high pressure service water
HVAC heating, ventilation, and air conditioning
 
IPE Individual Plant Examination
IPEEE Individual Plant Examination for External Events
IRP Integrated Resource Plan
ISFSI Independent Spent Fuel Storage Installation
 
km kilometer
kV kilovolt
 
LOCA loss-of-coolant accident
LWR light-water reactors
 
m meter
MACCS Melcor Accident Consequence Code System
mi mile
MTHM metric tonnes of heavy metal
MTU metric ton of uranium
MW megawatt
MW(e) megawatt electric
MW(t) megawatt thermal
MWd/MTU megawatt-days per metric ton of uranium
 
NAS National Academy of Sciences
NEPA National Environmental Policy Act
NESC National Electric Safety Code
NIEHS National Institute of Environmental Health Sciences
NPDES National Pollutant Discharge Elimination System
NRC U.S. Nuclear Regulatory Commission
NRCS Natural Resources Conservation Service
NRR Office of Nuclear Reactor Regulation
ODCM Offsite Dose Calculation Manual
OL operating license
ONS Oconee Nuclear Station
 
PDS plant damage states
PRA Probabilistic Risk Assessment
PSI pollutant standards index
 
RAI request for additional information
RCM reactor coolant makeup
RCRA Resource Conservation and Recovery Act
REMP radiological environmental monitoring program
 
SAMA Severe Accident Mitigation Alternative
SCDHEC South Carolina State Department of Health and Environmental Control
SCDNR South Carolina Department of Natural Resources
SCR selective catalytic reduction
SCSHPO South Carolina State Historic Preservation Office
SEIS supplemental environmental impact statement
SGTR steam generator tube rupture
SRM staff requirements memorandum
SSF standby shutdown facility
 
UFSAR Updated Final Safety Analysis Report


1.0 Introduction


[ Prev | Next | Top of file ]

Duke Energy Corporation (Duke)(2) operates Oconee Nuclear Station (ONS) Units 1, 2, and 3 in northwestern South Carolina under operating licenses (OLs) DPR-38, DPR-47, and DPR-55 issued by the U.S. Nuclear Regulatory Commission (NRC). These OLs will expire in 2013 for Units 1 and 2 and in 2014 for Unit 3. By letter dated July 7, 1998, Duke submitted an application to the NRC to renew the ONS OLs for an additional 20 years under Title 10 of the Code of Federal Regulations (CFR) Part 54. Duke is a licensee for the purposes of its current OLs and an applicant for the renewal of the OLs.

The National Environmental Policy Act of 1969 (NEPA) requires an environmental impact statement (EIS) for major Federal actions significantly affecting the quality of the human environment. As provided in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437 (NRC 1996; 1999a),(3) under NRC's environmental protection regulations in 10 CFR Part 51 implementing NEPA, renewal of a nuclear power plant operating license is identified as a major Federal action significantly affecting the quality of the human environment. Therefore, an EIS is required for a plant license renewal review. The EIS requirements for a plant-specific license renewal review are specified in 10 CFR Part 51. Pursuant to 10 CFR 54.23 and 51.53(c), Duke submitted an environmental report (ER) (Duke 1998) in which Duke analyzed the environmental impacts associated with the proposed action, considered alternatives to the proposed action, and evaluated any alternatives for reducing adverse environmental effects.

As part of NRC's evaluation of the application for license renewal, the NRC staff is required under 10 CFR Part 51 to prepare an EIS for the proposed action, issue the statement in draft form for public comment, and issue a final statement after considering public comments on the draft. This report is the final plant-specific supplement to the GEIS (supplemental environmental impact statement [SEIS]) for the Duke license renewal application. The staff will also prepare a separate safety evaluation report in accordance with 10 CFR Part 54.

The following sections in this introduction describe the background and the process used by the staff to assess the environmental impacts associated with license renewal, describe the proposed Federal action, discuss the purpose and need for the proposed action, and present the status of compliance with environmental quality standards and requirements that have been imposed by Federal, State, regional, and local agencies having responsibility for environmental protection. Chapter 2 describes the site, power plant, and interactions of the plant with the environment. Chapters 3 and 4 discuss the potential environmental impacts of plant refurbishment and plant operation during the renewal term, respectively. Chapter 5 contains an evaluation of potential environmental impacts of plant accidents and includes consideration of severe accident mitigation alternatives (SAMAs). Chapter 6 discusses the uranium fuel cycle and solid waste management, and Chapter 7 discusses decommissioning. The alternatives to license renewal are considered in Chapter 8. Finally, Chapter 9 summarizes the findings of the prior chapters, draws conclusions related to the adverse impacts that cannot be avoided (the relationship between short-term uses of man's environment and the maintenance and enhancement of long-term productivity, and the irreversible or irretrievable commitments of resources), and presents the recommendation of the staff with respect to the proposed action. Additional information is included in Appendices. Appendix A contains a discussion of comments on the draft SEIS issued on May 20, 1999. Appendix B lists preparers of this supplement, and Appendix C lists the chronology of correspondence between NRC and Duke with regard to this supplement. The remaining appendices are identified in subsequent sections.


Generic Environmental Impact Statement


[ Prev | Next | Top of file ]

The NRC initiated a generic assessment of the environmental impacts associated with the license renewal term to improve the efficiency of the license renewal process by documenting the assessment results and codifying the results in the Commission's regulations. This assessment is provided in the GEIS. The GEIS serves as the principal reference for all nuclear power plant license renewal EISs.

The GEIS documents the results of the systematic approach that was taken to evaluate the environ-mental consequences of renewing the licenses of individual nuclear power plants and operating them for an additional 20 years. For each potential environmental issue, the GEIS (1) described the activity that affects the environment, (2) identified the population or resource that is affected, (3) assessed the nature and magnitude of the impact on the affected population or resource, (4) characterized the significance of the effect for both beneficial and adverse effects, (5) determined whether the results of the analysis applied to all plants, and (6) considered whether additional mitigation measures would be warranted for impacts that would have the same significance level for all plants.

The standard of significance was established using the Council on Environmental Quality (CEQ) terminology for "significantly" (40 CFR 1508.27) for assessing environmental issues as SMALL, MODERATE, or LARGE. Using the CEQ terminology, the NRC established three significance levels as follows:

    SMALL: Environmental effects are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.
MODERATE: Environmental effects are sufficient to alter noticeably, but not to destabilize, important attributes of the resource.
LARGE: Environmental effects are clearly noticeable and are sufficient to destabilize important attributes of the resource.

The GEIS assigned a significance level to each environmental issue. In assigning these levels, it was assumed that ongoing mitigation measures would continue.

The GEIS included a determination of whether the analysis of the environmental issue could be applied to all plants, and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) The environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristic
(2) A single-significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from high-level waste (HLW) and spent fuel disposal)
(3) Mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are not likely to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that do not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required.

In the GEIS, the staff assessed 92 environmental issues and determined that 69 qualified as Category 1 issues, 21 qualified as Category 2 issues, and two issues were not categorized. The latter two issues, environmental justice and chronic effects of electromagnetic fields, are to be addressed in a plant-specific analysis. Of the 92 issues, 10 are related to refurbishment, 74 are related to operations during the renewal term, and 8 apply to both refurbishment and operation during the renewal term. A summary of the findings for all 92 issues of the GEIS is codified in 10 CFR Part 51, Subpart A, Appendix B, Table B-1.


License Renewal Evaluation Process


[ Prev | Next | Top of file ]

An applicant seeking to renew its operating license is required to submit an ER as part of its application. This ER must provide an analysis of the issues listed as Category 2 in 10 CFR Part 51, Subpart A, Appendix B, Table B-1 in accordance with 10 CFR 51.53(c)(3)(ii). The ER must include a discussion of actions to mitigate adverse impacts associated with the proposed action and environmental impacts of alternatives to the proposed action. In accordance with 10 CFR 51.53(c)(2), the ER need not consider the economic benefits and costs of the proposed action and alternatives to the proposed action except insofar as such benefits and costs are either essential for determination regarding the inclusion of an alternative in the range of alternatives considered or relevant to mitigation. Section 51.53(c)(2) also provides that certain other issues, including the need for power and other issues not related to the environmental effects of the proposed action need not be considered in the ER. In addition, the ER need not discuss any aspect of the storage of spent fuel within the scope of the generic determination in 10 CFR 51.23(a) in accordance with 10 CFR 51.23(b). Pursuant to 10 CFR 51.53(c)(3)(I)(iii) and (iv), the ER is not required to contain an analysis of any Category 1 issues unless there is significant new information on a specific issue. New and significant information is (1) information that identifies a significant environmental issue not covered in the GEIS and codified in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, or (2) information that was not considered in the analyses summarized in the GEIS and which leads to an impact finding different from that codified in 10 CFR Part 51.

In preparing to submit its application to renew the ONS operating licenses, Duke developed a process to ensure that new and significant information regarding the environmental impacts of license renewal for ONS would be properly reviewed before submitting the ER and to ensure that new and significant information related to renewal of the ONS licenses would be identified, reviewed, and addressed during the period of NRC review. Duke reviewed the Category 1 issues appearing in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, to verify that the conclusions of the GEIS remained valid with respect to ONS. This review was performed by personnel from Duke's Group Environmental Health and Safety and the Oconee station personnel. Duke has committed to repeating this review process at 1-year intervals until a determination on the Oconee license renewal application is made. Duke also committed to include the South Carolina Department of Health and Environmental Control (SCDHEC), the South Carolina Department of Natural Resources (SCDNR), and the U.S. Fish and Wildlife Service (FWS) as part of the review process and making revisions to the ER if new issues were identified that had not been included in the GEIS or if changes to conclusions made in the ER were required.

The NRC staff also has a process for identifying new and significant information. That process is described in detail in a draft of the Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal (ESRP), NUREG-1555, Supplement 1 (February 1999 pre-publication copy) (NRC 1999b). The search for new information includes a review of an applicant's ER and the process for discovering and evaluating the significance of new information; review of records of public meetings and correspondence; review of environmental quality standards and regulation coordination with Federal, State, and local environmental protection and resource agencies; and review of the technical literature. Any new information discovered by the staff is evaluated for significance using the criteria set forth in the GEIS. For Category 1 issues where new and significant information is identified, reconsideration of the conclusions for those issues is limited in scope to the assessment of the relevant new and significant information; the scope of the assessment does not include other facets of the issue that are not affected by the new information. Neither Duke nor the staff has identified any new issue applicable to ONS that has a significant environmental impact.

The discussion of the environmental issues considered in the GEIS that are applicable to ONS is found in Chapters 3 through 7. At the beginning of the discussion of each set of issues, there is a table that identifies the issues to be addressed and lists the sections in the GEIS where the issue is discussed. Category 1 and Category 2 issues are listed in separate tables. For Category 1 issues for which there is no new and significant information, the table is followed by a set of short paragraphs that state the GEIS conclusion codified in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, followed by the staff's analysis and conclusion. For Category 2 issues, in addition to the list of GEIS sections where the issue is discussed, the tables list the subparagraph of 10 CFR 51.53(c)(3)(ii) that describes the analysis required and the SEIS sections where the analysis is presented. The SEIS sections discussing the Category 2 issues are listed immediately following the table.

The NRC prepares an independent analysis of the environmental impacts of license renewal as well as a comparison of these impacts to the environmental impacts of alternatives. The evaluation of Duke's license renewal application began with publication of a notice of acceptance for docketing (63 FR 42885, August 11, 1998). The staff published a notice of intent to prepare an EIS and conduct scoping (63 FR 50257, September 21, 1998). Two public scoping meetings were held on October 19, 1998, in Clemson, South Carolina. Comments received during the scoping meeting were summarized in the Environmental Impact Statement Scoping Process, Oconee Nuclear Station, Summary Report, January 1999 (NRC 1999c).

The staff visited the ONS Site on October 19 through 22, 1998, reviewed the comments received during scoping, and consulted with Federal, State, regional, and local agencies. A list of the organizations consulted is provided in Appendix D of this document. Other documents related to ONS were also reviewed and are referenced.

The staff followed the review guidance contained in the February 1999 prepublication version of the ESRP (which was under development at the time of the Duke application). It issued requests for additional information (RAIs) to Duke by letters dated December 29, 1998 (NRC 1998a and 1998b). Duke provided its responses in a letter dated March 4, 1999 (Duke 1999). The staff reviewed this information, incorporated it into its analysis, and, on May 20, 1999, issued a draft of the SEIS, which contained the preliminary results of its evaluation and recommendation.

With the publication of the EPA Notice of Filing of the draft SEIS (64 FR 28843, May 28, 1999), a 75-day comment period began to allow members of the public to comment on the preliminary results of the NRC staff's review. During this comment period, two public meetings were held in Clemson, South Carolina, on July 8, 1999, during which the staff described the preliminary results of the NRC environmental review and answered questions related to it in order to provide members of the public with information to assist them in formulating their comments. The comment period for the ONS draft SEIS ended on August 16, 1999.

This report presents the staff's final analysis that considers and weighs the environmental effects of the proposed renewal of the ONS licenses, the environmental impacts of alternatives to license renewal, and alternatives available for avoiding adverse environmental effects. The staff considered the comments that were received during the comment period. The disposition of these comments is addressed in Appendix A of this SEIS. The staff modified the analysis set forth in the draft SEIS to address certain comments, where appropriate. A vertical bar in the margin indicates where the staff made changes to the draft SEIS. In addition, Chapter 9, "Summary and Conclusions," provides the NRC staff's final recommendation to the Commission on whether the adverse environmental impacts of license renewal are so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable.


1.1 The Proposed Federal Action


[ Prev | Next | Top of file ]

The proposed Federal action is renewal of the operating licenses for ONS Units 1, 2, and 3. ONS is located in Oconee County, South Carolina, approximately 13 km (8 mi) northeast of Seneca, South Carolina. The plant has three pressurized light-water reactors, each with a design rating for net electrical power output of 887 megawatts (MW(e)). Plant cooling is provided by a once-through heat dissipation system into Lake Keowee. Keowee Hydroelectric Station, was constructed at approximately the same time as ONS. ONS produces electricity to supply the needs of more than 730,000 homes. The current operating license for Unit 1 expires on February 6, 2013, for Unit 2 on October 6, 2013, and for Unit 3 on July 19, 2014. By letter dated July 7, 1998, Duke submitted an application to renew these operating licenses for an additional 20 years of operation (i.e., until February 6, 2033, for Unit 1, October 6, 2033, for Unit 2, and July 19, 2034, for Unit 3).


1.2 Purpose and Need for the Action


[ Prev | Next | Top of file ]

Although a licensee must have a renewed license to operate a plant beyond the term of the existing operating license, the possession of that license is just one of a number of conditions that must be met for the licensee to continue plant operation during the term of the renewed license. Once an OL is renewed, State regulatory agencies and the owners of the plant will ultimately decide whether the plant will continue to operate based on factors such as the need for power or other matters within the State's jurisdiction or the purview of the owners.

Thus, for license renewal reviews, the Commission has adopted the following definition of purpose and need (GEIS, Section 1.3):

The purpose and need for the proposed action (renewal of an operating license) is to provide an option that allows for power generation capability beyond the term of a current nuclear power plant operating license to meet future system generating needs, as such needs may be determined by State, utility, and where authorized, Federal (other than NRC) decision makers.

This definition of purpose and need reflects the Commission's recognition that, unless there are findings in the safety review required by the Atomic Energy Act (AEA) of 1954, as amended, or findings in the NEPA environmental analysis that would lead the NRC to reject a license renewal application, the NRC does not have a role in the energy planning decisions of State regulators and utility officials as to whether a particular nuclear power plant should continue to operate. From the perspective of the licensee and the State regulatory authority, the purpose of renewing an operating license is to maintain the availability of the nuclear plant to meet system energy requirements beyond the current term of the plant's license.


1.3 Compliance and Consultations


[ Prev | Next | Top of file ]

Duke is required to hold certain Federal, State, and local environmental permits, as well as meet relevant Federal and State statutory requirements. Duke provided a list in its ER of the status of authorizations from Federal, State, and local authorities for current operations as well as environmental approvals and consultations associated with ONS license renewal. Authorizations most relevant to the proposed license renewal action are summarized in Table 1-1. The full list of authorizations provided by Duke is included as Appendix E.

The staff reviewed the list and has consulted with the appropriate Federal, State, and local agencies to identify any compliance or permit issues or significant environmental issues of concern to the reviewing agencies. Agency interactions identified no new and significant environmental issues. The staff has also not identified any new and significant environmental issues.

Table 1-1. Federal, State, and Local Authorizations

Agency Authority Requirement License Permit Number Permit Expiration or Consultation Date Activity Covered
NRC Atomic Energy Act, 10 CFR Part 50 Operating license DPR-38, DPR-47, DPR-55 Expires February 6, 2013, October 6, 2013, and

July 19, 2014

Operation of ONS Units 1, 2,

and 3

FERC Federal Power Act, Section 4(e) Associated hydro project FERC Project No. 2503 Expires 2016 License for Keowee Dam and Hydro Station
FWS Endangered Species Act, Section 7 Consultation

Informal Consultation

NA Consultation initiated

June 23, 1998

June 30, 1999

Operation during the renewal term
SCDHEC Clean Air Act, Section 112 Air quality permit 1820-0041 April 22, 2002 Air quality permit
SCDHEC Safe Drinking Water Act, 42 U.S.C. 1412 Water quality 202098AI In compliance ONS has a permit for a drinking water well in protected area
SCDHEC RCRA-subtitle 1 Permit 06673,11174, 11843 Issued January 1, 1982, November 3, 1988, and November 3, 1989 Underground storage tanks
SCDHEC FWPCA Section 402 State discharge permit SCR000000 Issued October 1, 1992, in compliance General storm water permit
SCDHEC FWPCA Section 402 Water quality SCR0000515 Issued September 29, 1999

Expires September 30, 2003

Discharges of process waste water (NPDES permit)
SCDHEC RCRA Section 3005 Permit SCD043979822 Issued March 9, 1998 Part A Hazardous Waste Permit, Interim Storage Facility for Mixed Wastes
SCSHPO National Historic Preservation Act, Section 106 Consultation NA Letter from Duke requesting consultation dated September 30, 1997 Operation during the renewal term
EPA - U.S. Environmental Protection Agency
FERC - Federal Energy Regulatory Commission
FWPCA - Federal Water Pollution Control Act (also known as the Clean Water Act)
FWS - U.S. Fish and Wildlife Service
NPDES - National Pollutant Discharge Elimination System
RCRA - Resource Conservation and Recovery Act
SCDHEC - South Carolina Department of Health and Environmental Control
SCSHPO - South Carolina State Historic Preservation Office
NA - Not applicable


References


[ Prev | Next | Top of file ]

10 CFR Part 51, "Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions."

10 CFR 51.53, "Postconstruction environmental reports."

10 CFR 51.95, "Postconstruction environmental impact statements."

10 CFR Part 51, Subpart A, Appendix B, Table B-1, "Environmental effect of renewing the operating license of a nuclear power plant."

10 CFR Part 54, "Requirements for renewal of operating licenses for nuclear power plants."

10 CFR 54.23, "Contents of application - environmental information."

40 CFR 1508.27, "Terminology and Index - Significantly."

63 FR 42885, "Notice of Acceptance for Docketing of the Application and Notice of Opportunity for a Hearing Regarding Renewal of Licenses Nos. DPR-38, DPR-47 and DRP-55." August 11, 1998.

63 FR 50257, "Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process." September 21, 1998

64 FR 28843, "Duke Energy Corporation, Oconee Nuclear Station, Units 1, 2, and 3; Notice of Availability of the Draft Supplement to the Generic Environmental Impact Statement and Public Meeting for the License Renewal of Oconee Nuclear Station, Units 1, 2, and 3." May 27, 1999.

Atomic Energy Act of 1954, as amended, 42 USC 2011, et seq.

Duke Energy Corporation. 1998. Application for Renewed Operating Licenses - Oconee Nuclear Station, Units 1, 2, and 3. Volume IV, Environmental Report.

Duke Energy Corporation. 1999. Letter from M.S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Subject: License Renewal-Response to Requests for Additional Information, Oconee Nuclear Station. Dated March 4, 1999.

Endangered Species Act, as amended, 16 USC 1531, et seq.

Federal Water Pollution Control Act (FWPCA), as amended, 33 USC 1251, et seq. (also known as the Clean Water Act).

National Environmental Policy Act of 1969, as amended, 42 USC 4321, et seq.

National Historic Preservation Act, as amended, 16 USC 470, et seq.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1998a. Letter from U.S. NRC to William R. McCollum, Duke Energy Corporation. Subject: Request for Additional Information for the Review of the Oconee Nuclear Station Units 1, 2, and 3. Environmental Report Associated with License Renewal-Environmental. Dated December 29, 1998.

U.S. Nuclear Regulatory Commission (NRC). 1998b. Letter from U.S. NRC to William R. McCollum, Duke Energy Corporation. Subject: Request for Additional Information for the Review of the Oconee Nuclear Station Unit Nos. 1, 2 & 3 Environmental Report Associated with License Renewal - SAMA. Dated December 29, 1998.

U.S. Nuclear Regulatory Commission (NRC). 1999a. Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Main Report, Section 6.3 - Transportation, Table 9.1, Summary of findings on NEPA issues for license renewal of nuclear power plants, NUREG-1437 Vol. 1, Addendum 1. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999b. Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal, NUREG-1555, Supplement 1. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999c. Environmental Impact Statement Scoping Process: Summary Report - Oconee Nuclear Station Units 1, 2 and 3, Oconee County, South Carolina. Washington, D.C.


2.0 Description of Nuclear Power Plant and Site and Plant Interaction with the Environment


[ Prev | Next | Top of file ]

The Oconee Nuclear Station (ONS) is located near State Highways 130 and 183 on Lake Keowee in eastern Oconee County, South Carolina, approximately 13 km (8 mi) northeast of Seneca, South Carolina. The site is within 40 km (25 mi) of the boundaries of the States of North Carolina and Georgia, as shown in Figure 2-1. ONS is a three-unit plant. Each unit is equipped with a nuclear steam supply system manufactured by Babcock & Wilcox that uses a pressurized light-water reactor (LWR) and once-through cooling with water from Lake Keowee. The electricity generated is transferred to the switchyards located at the ONS site. Each unit has a design rating for net electrical power output of 887 megawatts electric [MW(e)]. Each unit is rated at 846 MW(e) net power. This provides a combined station total of 2538 MW(e) net power. The amount of electricity produced by ONS can supply the needs of more than 730,000 homes. Descriptions of the plant and its environs follow in Section 2.1, and the plant's interaction with the environment is presented in Section 2.2.

Figure 2-1. Location of Oconee Nuclear Station


2.1 Plant and Site Description and Proposed Plant Operation During the Renewal Term


[ Prev | Next | Top of file ]

ONS is located on 210 ha (510 acres) in a rural part of northwestern South Carolina. Figure 2-1 shows the location of ONS in relationship to the tri-state area (northwest South Carolina, northeast Georgia, and southwest North Carolina). The site is surrounded by an exclusion area of 1.6-km (1-mi) radius as shown in Figure 2-2. All land is owned by Duke in full except for a small rural church lot, a highway right-of-way, and approximately 4 ha (9.9 acres) included in the Hartwell Reservoir project.

The region surrounding ONS was identified by the Generic Environmental Impact Statement (GEIS) as having a medium population density. Approximately 1700 persons comprise the non-outage work force at ONS. There are 1350 Duke employees normally onsite. The remainder of the 1700 persons are contract or vendor workers. The plant is located near the cities of Seneca, Walhalla, and Clemson, South Carolina. The nearest town is Six Mile, located 6 km (4 mi) east northeast. The majority of the land area is forest, with pasture, cropland, and residential development each contributing significant proportions of land use. The land within 8 km (5 mi) of the plant is primarily forest.

The property consists of rolling hills, with surface elevations ranging from about 210 m to 273 m (700 ft to 900 ft) within the region. The area is well drained by several intermittent streams flowing away from the center of the site in a radial pattern. The site lies within the drainage area of the Little and Keowee Rivers, which flow southerly into the Seneca River and subsequently discharge into the main drainage course of the Savannah River. The average annual rainfall at the site area is approximately 135 cm (53 in).

ONS is part of Duke's integrated energy producing area called the Keowee-Toxaway complex. ONS was constructed as a part of the Keowee-Toxaway Project (FERC Project #2503). This project also included the construction of Lake Keowee, Lake Jocassee, and the associated hydroelectric stations. Construction of the project occurred between 1968 and 1974. The Keowee-Toxaway Complex is located in the upper Savannah River drainage basin. It consists of the three-unit ONS, the Keowee Hydroelectric Station (a two-unit conventional hydroelectric facility), the Jocassee Hydroelectric Station (a four-unit pumped storage hydroelectric facility) and the Bad Creek Pumped Storage Project (a four-unit pumped storage hydroelectric facility). A pumped storage hydroelectric facility can operate in a generating mode or in a pumping mode to store water for later generation of electric power. In the generating mode, electricity is generated by allowing water to flow from Lake Jocassee (upper pond) into Lake Keowee (lower pond). In the pumping mode, water is pumped into Lake Jocassee from Lake Keowee for generation of electricity at a later time. The Bad Creek Pumped Storage Facility uses Lake Jocassee as the lower pond, and the Bad Creek Reservoir serves as the upper pond. Figure 2-3 illustrates the location of ONS in relationship to the rest of the Keowee Toxaway project and the Bad Creek project.

Figure 2-2. Oconee Nuclear Station - One-Mile Exclusion Area

Figure 2-3. Location of Oconee Nuclear Station Relative to Other Parts of Keowee-Toxaway Project

ONS is on the shores of Lake Keowee. The main bodies of the lake lie to the north and southwest of the site. Lake Keowee was formed by damming the water of the Little River and the Keowee River above the Hartwell Reservoir. Hartwell Reservoir, an Army Corps of Engineers' reservoir, is located south and downstream of the site. Lake Jocassee is approximately 17.5 km (11 mi) to the north. Keowee Lake covers about 7490 ha (18,500 acres) and has 480 km (300 mi) of shoreline, which is developed with both permanent and vacation residences, along with campgrounds, boat launch areas, marinas, golf courses, and some small retail establishments. The volume of Lake Keowee is 1.18x109 m3 (952,300 acre ft). The mean depth is 16 m (52 ft) with a maximum depth of 43 m (141 ft). In addition to uses for the needs of the nuclear and hydroelectric power plants, Lake Keowee is used as a source of municipal drinking water by Greenville and Seneca and is extensively used for recreation by fishermen, swimmers, skiers, and boaters.

2.1.1 External Appearance and Setting

The station is sited within a forested valley and is only visible from the neighboring highways in a few locations. The most obvious view is that of the water tower. ONS consists of three cylindrical concrete reactor building structures, approximately 38 m (125 ft) in diameter and about 61 m (200 ft) high. A turbine building and an auxiliary building are shared among the three units. Switchyards are located near the turbine building. Various other office buildings and facilities are located at ONS to support the station. Figure 2-4 shows the general features of the ONS site. Figure 2-5 presents an aerial view of the facility showing the three cylindrical reactor buildings.

Duke has an independent spent fuel storage installation (ISFSI) located on the site that has a license separate from the operating license. Duke was issued a Materials License (No. SNM-2503) for the ISFSI on January 29, 1990, with an expiration date of January 31, 2010. The ISFSI is outside the scope of this review.

The Old Pickens Presbyterian Church and Cemetery are located to the southeast of ONS on a small parcel of land that is not owned by Duke. The church is the only building remaining from the original Pickens town site. A Visitor's Center on a hill just above the site displays "The Story of Energy," which describes how sources of energy are found in nature and converted into electricity by Duke's generating facilities. There is also a lakeside picnic area, a nature trail, and landscaped grounds.

The site's geological setting is in the southeastern Piedmont physiographic province, and the site is underlain by crystalline rocks (AEC 1972). This northeastward-trending belt of ancient metamorphic rocks extends northward from Alabama east of the Appalachians, and in South Carolina, it crosses the state from the fall line on the east to the Blue Ridge and Appalachian Mountains on the west. These rocks are generally recognized as being divided into four parallel northeast-southwest-trending belts in the Carolinas. From southeast to northwest, these are the Carolina Slate Belt, the Charlotte Belt, the Kings Mountain Belt, and the Inner Piedmont Belt. The site is in the northwestern Inner Piedmont Belt.

Figure 2-4. Oconee Nuclear Station Layout

Figure 2-5. Oconee Nuclear Station (aerial photo)

The rocks are geologically ancient and complex. These rocks were folded and metamorphosed when the Appalachian Mountains were formed during the Appalachian Revolution, some 270 million years ago. Faults and other lines of weakness dating from this Revolution may serve to locate present-day minor crustal movements that produce small earthquakes, and their location is of some importance. The most important is the Brevard fault zone that passes 17.5 km (11 mi) northwest of the site. The design criteria for the Station took this fault zone into account. Small earthquakes have been detected along this zone with intensities of IV to VI. Using this scale of intensities, V and VI represent disturbances that can dislodge plaster, etc.; X, XI, and XII represent disturbances that are severely damaging (AEC 1972).

In addition to the Brevard fault, there are fault zones 48 km (30 mi) to 320 km (200 mi) southeast where quake intensities of VII or VIII have been recorded. But because of their distance from the site, these zones are of slight importance for ONS (AEC 1972).

ONS is in the drainage basins of the Little and Keowee Rivers, which receive the runoff of surface water and groundwater from the site. The residual soil in the area is comparatively impermeable, particularly in late winter and early spring when the soil is saturated, and much of the precipitation goes into direct surface runoff. The residual soils do accept some water, and the area is underlain by a water table that is a subdued replica of the topography. Groundwater is not an important source of water supply in the area; all neighboring towns obtain their municipal supplies from above-ground sources.

The rate of movement of the groundwater was calculated to be 45 m to 76 m (150 ft to 250 ft) per year (AEC 1972). The residual soil has excellent ion exchange properties.

2.1.2 Reactor Systems

ONS is a three-unit plant. Each unit is a pressurized LWR, with a nuclear steam supply system manufactured by Babcock & Wilcox. Each unit has a design rating for net electrical power output of 887 MW(e) and is operated at a maximum core thermal power output level of 2568 MW(t). The turbines are manufactured by General Electric Company. Each turbine is a tandem, compound, six-flow exhaust, indoor unit.

ONS fuel is low-enriched (up to 5 percent by weight)(4) uranium dioxide in the form of pellets contained in zirconium alloy fuel rods (tubes fitted with welded end caps).

Duke can operate ONS in accordance with the methodology presented in B&W topical report BAW-10186P-A, which was approved by the staff in its letter dated April 29, 1997 (NRC 1997). Based on this methodology, cycle length, and fuel enrichment, the ONS fuel burnup(5) rate does not exceed 62,000 megawatt-days per metric ton uranium (MWd/MTU).

Reactor containment structures are designed with engineered safety features to protect the public and plant personnel from an accidental release of radioactive fission products, particularly in the unlikely event of a loss-of-coolant accident (LOCA). These safety features function to localize, control, mitigate, and terminate such events to limit exposure levels below applicable dose guidelines. The reactor is controlled using a combination of chemical controls (boric acid dissolved in coolant water) and solid absorber material.

2.1.3 Cooling and Auxiliary Water Systems

ONS is equipped with a once-through heat dissipation system that withdraws cooling water from the Little River arm of Lake Keowee, from underneath a skimmer wall. The discharge for the cooling water is located on the Keowee River arm of the lake just above the Lake Keowee dam. The Keowee River and the Little River basins are connected by a canal, approximately 31 m (100 ft) wide and 12 m (40 ft) deep (illustrated in Figure 2.2). It is nearly 3.2 km (2 mi) by lake from the point of discharge to the mouth of the intake canal. A natural cove was deepened and extended to within a few hundred feet of the power plant as part of the project when initially licensed. Across the mouth of the cove, a skimmer wall was constructed extending from above the surface of the lake (normally 244 m [800 ft] above mean sea level) down to an elevation of 223 m (735 ft). This wall ensures that cooler water from near the bottom of the lake enters the intake canal. Further into the intake cove is a submerged dam, or weir, with its crest at 233 m (770 ft) above mean sea level. The distance from the weir to the intake structures is nearly 1.2 km (0.75 mi). Figure 2-4 shows the water flow for the plant and illustrates the location of the skimmer wall, intake structure, and the outfall for the once-through cooling system.

Each generating unit has three separate water loops. The primary coolant loop is a closed piping system: pressurized water in the system is circulated through the reactor and transfers heat from the reactor to the steam generator. The secondary loop is also a closed system: water from this system is converted into steam (in the steam generators) that is used to drive the turbine. The third loop is an open system: water from the Little River arm of Lake Keowee is used to cool the spent steam in the secondary loop, and then it is returned to the Keowee River arm of Lake Keowee. The principal components of the third cooling loop are the skimmer wall, intake structure, circulating water pumps, condensers, and discharge conduits.

2.1.4 Radioactive Waste Management Systems and Effluent Control Systems

ONS uses liquid, gaseous, and solid radioactive waste management systems to collect and process the liquid, gaseous, and solid wastes that are the by-products of the ONS operation. These systems reduce radioactive liquid, gaseous, and solid effluents before they are released to the environment. The ONS waste processing systems meet the design objectives of 10 CFR Part 50, Appendix I, and control the processing, disposal, and release of radioactive liquid, gaseous, and solid wastes. Radioactive material in the reactor coolant is the source of gaseous, liquid, and solid radioactive wastes in LWRs. Radioactive fission products build up within the fuel as a consequence of the fission process. These fission products are contained in the sealed fuel rods, but small quantities escape the fuel rods and contaminate the reactor coolant. Neutron activation of the primary coolant system also is responsible for coolant contamination.

Non-fuel solid wastes result from treating and separating radionuclides from gases and liquids and from removing contaminated material from various reactor areas. Solid wastes also consist of reactor components, equipment, and tools removed from service as well as contaminated protective clothing, paper, rags, and other trash generated from plant design and operations modifications and routine maintenance activities. Solid wastes may be shipped to a waste processor for volume reduction before disposal or may be sent directly to the licensed burial site. Spent resins and filters are dewatered and stored or packaged for shipment to an offsite processing or disposal facility.

Fuel rods that have exhausted a certain percentage of their fuel and that are removed from the reactor core for disposal are called spent fuel. ONS currently operates on an 58-month refueling cycle for all three units. Spent fuel is stored onsite either in a spent fuel pool in the Auxiliary Building or in dry storage at the ONS ISFSI. ONS also temporarily stores mixed waste onsite (mixed wastes are composed of radioactive material and hazardous waste). This storage is governed by the Atomic Energy Act (AEA) for radioactive material and the Resource Conservation and Recovery Act (RCRA) for hazardous waste, consistent with NRC and EPA requirements (42 USC 2011-2259 [AEA]; 42 USC 6901 [RCRA]).

The systems used for processing--liquid waste processing, gaseous waste processing, solid waste processing, and nonradioactive waste systems--are discussed in the subsequent sections.

The Offsite Dose Calculation Manual (ODCM) specifies the following methodology and parameters used to calculate potential offsite doses due to radioactive liquid and gaseous effluents and to ensure compliance with the dose limitations of the Selected Licensee Commitments (Section 16.11, "Radiological Effluents Control," of the Updated Final Safety Analysis Report [UFSAR]):

2.1.4.1 Liquid Waste Processing Systems and Effluent Controls

Based on the water source and process train, radioactive liquid wastes from the operation of ONS are accumulated in storage tanks. These wastes are collected in the Auxiliary Building and transferred to the Radwaste Facility for processing by filtration or demineralization or both. The Radwaste Facility processes high-activity wastes, low-activity wastes, and miscellaneous wastes from the Auxiliary Building. There is also an Interim Radwaste Building that can process liquid wastes, but it is not currently in use.

ONS liquid wastes are disposed of by one of the following three methods based on the concentration of radioactive material in the waste:

The potential waste generation rate for the three units is 28,343 m3 (944,773 ft3) per year. The liquid waste holdup capacity is approximately 303,200 liters (80,000 gal). The actual liquid waste generated is reported in the Oconee Annual Effluent Report.

The ODCM prescribes the effluent release rate that will ensure that the concentration of radioactive liquid effluents released from the site to the unrestricted area is less than ten times the effluent concentrations of 10 CFR Part 20, Appendix B, Table 2. In addition, the ODCM provides calculations for the radiation monitor alarm/trip set points that define the relationship between the measured effluent activity, the maximum allowable effluent activity, and the effluent flowrate needed to ensure that the instantaneous release rate is not exceeded and thereby that the Selected Licensee Commitments are met.

2.1.4.2 Gaseous Waste Processing Systems and Effluent Controls

Radioactive gaseous wastes at ONS are created by the evolution of gases in liquid contained in tanks and piping. The wastes are monitored and released at a permissible rate prescribed by the ODCM. Units 1 and 2 share a Gaseous Waste Disposal System, and Unit 3 has a separate system that can be interconnected to the Unit 1 and 2 system. The purposes of the Gaseous Waste Disposal Systems are to (1) maintain a non-oxidizing cover gas of nitrogen in tanks and equipment that may contain radioactive gas, (2) holdup gas for decay, and (3) release the gases under controlled conditions.

The gaseous wastes are to be released in the following ways depending on the source, quantities, and concentration of radioactive material: (1) release of Auxiliary Building ventilation air and Reactor Building purges into the unit vents, (2) release of Reactor Building purges through high-efficiency particulate and charcoal iodine filters to the unit vents, (3) release of waste gas directly or through high efficiency particulate and charcoal iodine filters to the unit vents, (4) diversion of gaseous radioactive waste to waste gas tanks followed by a controlled release to the unit vents via high-efficiency particulate and charcoal iodine filters after sampling and analysis, and (5) release of Radwaste Facility heating, ventilation, and air conditioning (HVAC) and process exhaust.

The ODCM prescribes the effluent release rate to ensure that releases are less than the Selected Licensee Commitments. In addition, the ODCM provides the calculational methodology for the radiation monitor alarm/trip set points, which defines the relationship between the measured effluent activity, the maximum allowable effluent activity, and the effluent flowrate needed to ensure that the instantaneous release rate limit is not exceeded and thereby that the Selected Licensee Commitments are met.

2.1.4.1 Solid Waste Processing and Handling

Solid waste is packaged in containers to meet the applicable requirements of 49 CFR Parts 171 through 177. Disposal and transportation are performed in accordance with the applicable requirements of 10 CFR Part 61 and Part 71, respectively. There are no releases to the environmentfrom radioactive solid wastes created at ONS. NRC and the state of South Carolina have approved the disposal of slightly contaminated materials within the Owner Controlled Area. For each onsite disposal, the waste is analyzed and confirmed to have acceptably low radionuclide concentrations, following the approval process described in 10 CFR 20.2002.

Approximately 150 shipments are made from ONS each year. About 120 are radioactive material shipments (contaminated parts, tools, equipment, sources, etc.) and 30 radwaste shipments (dry active waste, dewatered resins, irradiated hardware, etc.). The radwaste shipments may be shipped to a waste processor to reduce the volume before disposal or may be sent directly to a licensed burial site.

From year to year, the volume of radioactive contaminated waste generated will vary, but averages are about 750 m3 (25,000 ft3) per year. ONS has been aggressively reducing volume and minimizing waste for several years and plans to continue to do so in the future.

2.1.5 Nonradioactive Waste Systems

The primary nonradioactive chemical wastes produced by ONS are from reactor coolant system make-up water, steam generator make-up water, water treatment demineralizers, and deborating demineralizers. Non-sanitary, nonradioactive wastes are neutralized and sent to the holding ponds, eventually being discharged to the Keowee River, downstream from the Keowee Hydroelectric Station. Sanitary wastes are routed to an aerated sewage lagoon. The effluents are treated by chlorination. The treated effluents from the sanitary waste treatment system are dechlorinated before being discharged.

2.1.6 Plant Operation and Maintenance

Routine maintenance performed on plant systems and components is necessary for safe and reliable operation of a nuclear power plant. Some of the maintenance activities conducted at ONS include inspection, testing, and surveillance to maintain the current licensing basis of the plant and to ensure compliance with environmental and public safety requirements. Certain activities can be performed while the reactor is operating. Others require that the plant be shut down. Long-term outages are scheduled for refueling and for certain types of repairs or maintenance, such as replacement of a major component. Scheduled refueling outages commonly have a duration of 35 to 55 days for a single unit. An additional 800 to 900 workers are onsite during a typical outage. Scheduled refueling outages for ONS occur on 18-month intervals for all three units.

Duke performed an aging management review and developed an integrated plant assessment for managing the effects of aging on systems, structures, and components in accordance with 10 CFR Part 54. The integrated plant assessment identified several activities that must necessarily be conducted during the period of extended operation. These activities include inspections and replacement of certain components. The applicant indicated that replacing these components and conducting additional inspections are within the bounds of normal plant operations. Therefore, Duke expects to conduct these activities during plant operation or normal refueling and other outages, but plans no outages specifically for the purpose of refurbishment. Duke has no plans to add additional full-time persons (non-outage workers) at the plant during the period of the extended license.

2.1.7 Power Transmission System

The ONS FES (AEC 1972) lists the transmission lines shown in Table 2-1 as being "attributable to the (Oconee) nuclear station." These lines account for 528 km (330 mi) of lines and about 3120 ha (7800 acres) of land in the rights-of-way. Figure 2-6 illustrates the location of these transmission lines.

Table 2-1. Transmission Lines from Oconee Nuclear Station

Destination Double or Single kV Distance (mi)(a) Width of Right-of-way (ft)(a) Date Line was Energized
Tiger d 230 53 150 November 1, 1973
Central (2) d 230 9 270 October 31, 1970
Site H (McGuire) s 525 130 200 July 2, 1974
Newport s 525 110 200 April 1, 1973
N. Greenville d 230 28 200 January 1, 1970
(a) Information taken from AEC (1972). Distances are left in English units as they were in the original.

These transmission lines were constructed concurrently with the construction of Oconee and the Keowee-Toxaway project and at a time that the Duke transmission system was being expanded in the Piedmont area. These lines are owned and operated by Duke Electric Transmission, a division of Duke Energy separate from Duke Power (Duke 1998a). The applicant indicated that the transmission lines will remain in service following the termination of operation and the decommissioning of Oconee, unless business needs require otherwise. The applicant stated that the 525 kV and the 230 kV lines from the Oconee substation provide an outlet for the 1675 MW of electrical power at the Jocassee and Bad Creek Pumped Storage Hydro plants. They are a source of power when these units are in pump mode.

Figure 2-6. Transmission Lines Attributable to the Oconee Nuclear Station in the Final Environmental Statement (AEC 1972)

In addition, Duke stated that three of the lines were energized before initial ONS startup. These lines are also used for tie-ins to the Virginia-Carolinas subregion of the Southeastern Electric Reliability Council as well as for connections to Georgia and Florida. In its license renewal application, uke (1998a) proposed that the transmission lines that should be considered to connect the plant to the transmission system are only those lines from the Oconee Turbine Building to the 230 kV and the 525 kV switchyards. However, as provided in 10 CFR 51.53(c)(3)(ii)(H), the scope of the review of transmission lines for the Category 2 issue concerning electric shock is the set of transmission lines that were constructed for the specific urpose of connecting the plant to the transmission system. The NRC staff has determined that the scope of the review of transmission lines for the Category 2 issue concerning threatened or endangered species should be identical to the scope of review for electric shock (NRC 1999b). As stated above, the ONS FES indicates that all the transmission lines listed in Table 2-1 were "attributable to [ONS]." Accordingly, the staff has determined that all these lines were

constructed for the specific purpose of connecting ONS to the transmission system and determined that all of the transmission lines discussed in the FES should be evaluated.


2.2 Plant Interaction with the Environment


[ Prev | Next | Top of file ]

Subsections 2.2.1 through 2.2.8 provide general descriptions of the environment as background information. They also provide detailed descriptions where needed to support the analysis of potential environmental impacts of refurbishment and operation during the renewal term as discussed in Chapters 3 and 4. Subsection 2.2.9 describes the historical and archaeological resources in the area, and 2.2.10 describes possible impacts on other Federal project activities.

2.2.1 Land Use

ONS is located in the northwest corner of South Carolina. The station is in the eastern portion of Oconee County. It is approximately 13 km (8 mi) northeast of the city of Seneca, the largest city in Oconee County. Lake Keowee occupies the area immediately north and west of the station. Lake Keowee covers approximately 7500 ha (18,500 acres) and was created by dams on the Lower Keowee and Little River.

The total area occupied by the station is 210 ha (510 acres). Forests cover the majority of the land area in the region surrounding ONS. The topography of the immediate area is undulating to rolling. Surface elevations range from approximately 210 m (700 ft) to 275 m (900 ft).

Oconee County is predominantly rural. The county's major population centers and developed areas are concentrated in the east central portion of the county around the municipalities of Walhalla, Westminster, and Seneca. Walhalla is the county seat for Oconee County. Table 2-2 shows a breakdown of land use in Oconee County in 1994. The amount of developed land is increasing with time.

Table 2-2. Land Use in Oconee County in 1994 (Talbert & Bright 1996)

Land Use Hectares (Acres) % of Total
Farming 97,700 (241,300) 56.3
Residential 5,700 (14,100) 3.3
Government Owned 41,000 (101,200) 23.6
Other (commercial and industrial) 9,500 (23,500) 5.5
Water Bodies 19,700 (48,600) 11.3
Total 173,600 (428,700) 100

The land occupied by the station is in an unincorporated portion of Oconee County. Oconee County has not imposed any zoning or land-use restrictions in the unincorporated portions of the county.

2.2.2 Water Use

Water from Lake Keowee (8.3 x 106 m3/d [2200 million gpd]) provides once-through condenser circulating water (CCW) for ONS (see Section 2.1.3). Lake Keowee serves as the lower pond for the Jocassee Pumped Storage Station and furnishes energy to drive the Keowee Hydroelectric Station. Water from the Seneca water treatment plant (120 m3/d [0.03 million gpd]) is used for potable water. Treated waste water (51 m3/d [0.01 million gpd]) from the plant's liquid rad-waste system is diluted and returned to the Keowee dam tailrace. Treated water (5300 m3/d [1.4 million gpd]) from the sewage treatment system, the chemical treatment system, the landfill leachate collection system, chemical treatment ponds, storm water runoff, and the turbine building sump are returned to the Keowee River at a location below the tailrace. Figure 2.7 illustrates the water flow for the plant.

In addition to serving the needs of the nuclear and hydroelectric power plants, Lake Keowee is used as a source of municipal drinking water for the cities of Greenville and Seneca. Lake Keowee experiences extensive recreational use by fishermen, boaters, skiers, and swimmers.

Seven groundwater wells are located at the Oconee site. One of these wells is used to supply the site baseball field with drinking water and with water for a restroom facility. This well is also used for seasonal irrigation at the site baseball field and has a pumping capacity of 0.0019 m3/s (30 gpm). The well at the baseball field is the only onsite groundwater well permitted to supply drinking water. There are two groundwater wells used to supply seasonal irrigation for landscaping at a training building and office complex. The other four wells are used infrequently as low volume, non-potable water sources.

The estimated combined pumping rate for all groundwater wells at the Oconee site is less than 0.068 m3/s (100 gpm).

2.2.3 Water Quality

The concentrations of all minerals in Lake Keowee are very low, with total dissolved solids of less than 25 mg/L (0.00021 lb/gal). Water clarity is generally very high. Dissolved oxygen concentrations in the surface waters are adequate, and algae are never present in nuisance concentrations. Due to low nutrient content of its waters, Lake Keowee has a relatively low standing crop (pounds per acre) of fish.

Figure 2-7. Oconee Nuclear Station - Water Flow Diagram

SCDHEC, as part of the Clean Lakes program, monitors the water quality and use of lakes in the State. These results are published in Watershed Water Quality Assessment, Savannah and Salkehatchie Basins, Technical Report No. 003-97 (SCDHEC 1997). In this document, SCDHEC reported that

Eutrophication assessments indicate that Lake Keowee is the least eutrophic large lake in South Carolina, characterized by very low nutrient concentrations. Preservation of this lake's desirable trophic condition is recommended. Aquatic life uses are not supported in Lake Keowee due to occurrences of copper in excess of the aquatic life acute standards, including a high concentration of copper measured in 1995, compounded by a significant increasing trend in pH. A significant increasing trend in dissolved oxygen concentration and a significant decreasing trend in five-day biochemical oxygen demand suggest improving conditions for these parameters. Recreational uses are fully supported at this site.

Pursuant to the Federal Water Pollution Control Act (FWPCA) (33 USC 1251), also known as the Clean Water Act (CWA), the water quality of plant effluent discharges is regulated through the National Pollutant Discharge Elimination System (NPDES). The SCDHEC is the state agency delegated by the EPA to issue the NPDES permit. The current permit (SC0000515) was issued on September 29, 1999, and expires on September 30, 2003. Any new regulations promulgated by EPA or the SCDHEC would be included in future permits.

2.2.4 Air Quality

ONS is located on the eastern slope of the Appalachian Mountains at an elevation of about 240 m (800 ft) mean sea level. The climate of the region is generally mild. Climatological records for Greenville-Spartanburg, South Carolina (NOAA 1998), which should be representative of the site, show normal daily maximum temperatures ranging from about 10C (50F) in January to about 31C (88F) in July; normal daily minimum temperatures range from about -1C (30F) in January to about 20C (68F) in July. Precipitation, which averages about 130 cm (51 inches) per year, is spread rather uniformly through the year. Monthly average wind speeds range from 2.7 m/s (6.1 mph) to 3.75 m/s (8.4 mph), with the highest speeds during the winter and lowest speeds during the summer. The influence of the Appalachian Mountains is seen in the prevailing wind directions, which are west-southwest and northeast. Section 2.3 of the ONS updated final safety analysis report (UFSAR) (Duke 1998b) contains a more detailed description of the climate of the region and site.

Climatological records also show that the area is subject to occasional storms, including destructive winds. In most years, one or more tropical storms affect the site; however, ONS is sufficiently far inland that the winds associated with these storms are below hurricane force. Tornadoes are infrequent in this region and are generally small when they occur.

For about two-thirds of the year, the region is under the influence of the Bermuda high pressure system. High pressure systems are typically associated with low winds and increased potential for air pollution problems. As indicated in 40 CFR 81.334, 40 CFR 81.341, and the 1997 South Carolina Air Quality Annual Report (SCDHEC 1998), South Carolina and North Carolina are in attainment of the National Air Quality Standards. The only non-attainment area in Georgia is an ozone non-attainment area in the Atlanta region (40 CFR 81.311). The Pollutant Standards Index (PSI) is an air quality index developed by the EPA in cooperation with the Council on Environmental Quality. For 1997, the average PSI for the Spartanburg, Greenville, Anderson metropolitan area was 48, which is associated with Good air quality (SCDHEC 1998). The daily PSIs for 211 days were in the Good range, and the remaining daily PSIs were in the Moderate range. The days with Moderate PSIs resulted from ozone formation.

The Oconee site is within 100 km (62 mi) of the Great Smoky Mountains National Park and Shining Rock Wilderness Area. These areas are designated in 40 CFR, Part 81, Subpart D, as mandatory Class I Federal areas in which visibility is an important value. As a result of the proximity of the Oconee Site to these Class I areas, future industrial development at the site will be subject to strict Federal standards for pollution control (SCDHEC 1998).

2.2.5 Aquatic Resources

Lake Keowee serves the needs of the local nuclear and hydroelectric power plants and is also used as a source of municipal drinking water by the cities of Greenville and Seneca, South Carolina. It is used extensively by fishermen, boaters, skiers, and swimmers, and its banks are developed with vacation and permanent residences, campgrounds, boat launch areas, marinas, golf courses, and small retail establishments.

Algae have never been present in nuisance concentrations, and, because of the low nutrient content of the water, Lake Keowee has a relatively low standing crop of fish. A creel census conducted in 1973 indicated that largemouth bass (Micropterus salmoides), bluegill (Lepomis macrochirus), and crappie (Pomoxis, spp.) were the most important recreational species in Lake Keowee (Edwards et al. 1976). Data on angler effort and harvest rates collected over a period from 1974 to 1993 (Barwick et al. 1995) confirmed that largemouth bass remained the most important sportfish in the reservoir and that sunfish (Lepomis spp., including bluegill) and crappie were the only other species that contributed in a significant way to the reservoir's sport fishery.

The U.S. Fish and Wildlife Service (FWS), in a letter dated April 17, 1998, provided a list of the Federally endangered and threatened species that potentially occur in Oconee County, South Carolina. No Federally listed aquatic species were identified for Oconee County. However, the bog turtle (Clemmys muhlenbergii) occurs in neighboring Pickens County and was listed as a threatened species due to similarity of appearance to the northern population of the same species. A survey conducted during June 1998 by Dr. L.L. Gaddy (Duke 1998a) found no Federal- or State-listed threatened or endangered species present within a 1.6-km (1-mi) radius Unit 2's reactor building at ONS. This includes the owner-controlled areas as well as additional lands along the Keowee River and along Lake Keowee. No State-ranked aquatic species listed as occurring in Oconee or Pickens Counties have been identified as occurring on or in the immediate vicinity of ONS.

The importance of fishery resources to the local community has promoted a partnership between Duke and SCDNR. Recently, SCDNR and Duke Power Company signed a Memorandum of Understanding (Keowee-Toxaway Fisheries Resources 1996) and developed a 10-year work plan to enhance communication between the two groups and provide for continued research, management, and enhancement of the fisheries resources in the watershed.

2.2.6 Terrestrial Resources

The vegetation in the vicinity of ONS has been variously described as part of the oak-pine-hickory biome of the eastern deciduous forest (Greller 1988) or as part of the southern mixed forest province (Bailey 1976, 1980). Much of the Piedmont region near ONS was cleared and converted to cotton production during the late 1800s and then abandoned in the 1930s. Most of the existing forested areas in the vicinity of ONS consequently represent second growth forests. The various pine species, such as loblolly (Pinus taeda), shortleaf (P. echinata), and Virginia (P. virginiana) pines, are the dominant conifers. Common hardwoods include red and white oaks (Quercus rubra, Q. alba), hickory (Carya sp.), and tulip poplar (Liriodendron tulipifera), among others. The understory is dominated by shrubs such as dogwood (Cornus florida), mountain laurel (Kalmia latifolia), and redbud (Cercis canadensis), as well as many species of herbs and grasses.

White-tailed deer (Odocoileus virginianus), black bear (Ursus americanus), raccoon (Procyon lotor), rabbits (Sylvilagus floridanus), squirrels (Sciurus carolinensis and Tamiasciurus hudsonicus), beavers (Castor canadensis), muskrats (Ondatra zibethica), foxes (Urocyon cinereoargenteus and Vulpes vulpes), opossums (Didelphis marsupialis), skunks (Mephitus mephitus and Spilogale putorius), river otters (Lutra canadensis), mink (Mustela vison), and various mice, voles, and shrews are wildlife species found in the project area. The white-tailed deer is the most popular game species, and black bear are hunted in the areas to the west of ONS.

The turkey (Meleagris gallopavo), bobwhite quail (Colinus virginianus), and mourning dove (Zenaida macroura), are the most common game birds. Many species of songbirds inhabit the area, including the eastern bluebird (Sialia sialis), red-eyed vireo (Vireo olivaceus), cardinal (Cardinalis cardinalis), tufted titmouse (Parus bicolor), woodthrush (Hylocichla mustelina), summer tanager (Piranga rubra), blue-gray gnatcatcher (Polioptila caerulea), hooded warbler (Wilsonia citrina), and Carolina wren (Thryothorus ludovicianus). The box turtle (Terrapene carolina), common garter snake (Thamnophis sirtalis), timber rattlesnake (Crotalus horridus), and assorted frogs, toads, and salamanders comprise the herpetofauna.

Extensive areas of ONS are protected or managed as upland natural areas, wetlands, or wildlife areas. In support of the environmental report, Duke funded a survey of all lands within a 1.6-km (1-mi) radius of the plant site. This survey, which was conducted in May and June 1998, identified several areas that retain characteristics of mature upland forests that the applicant has designated as protected natural areas. Wetlands were also identified during this survey, and these are managed as sensitive environmental areas. The applicant has a program of wildlife enhancement in unused portions of the plant site. The program was designed in partnership with the South Carolina Wildlife Federation, the SCDNR, and the National Wild Turkey Federation. This program has established semi-natural meadows, enhanced wetland native plants, placed wood duck and bluebird nesting boxes, and developed a butterfly garden.

The field survey also included an inventory of endangered, threatened, and otherwise noteworthy plant and animal species within a 1.6 km (1 mi) radius of ONS. No Federally listed, proposed, or candidate threatened or endangered species were identified during the onsite survey. However, three State-listed plant species and one plant species not previously known in South Carolina (Table 2-3) were identified. The populations of these four species were all confined to "natural areas" located toward the periphery of the survey area, well away from areas used for normal plant operations. Three additional state-listed plant and one animal species have been reported from the general area in the past, but were not located within the 1.6-km (1-mi) radius of ONS during this survey (Table 2-3).

Table 2-3. Endangered, Threatened, and South Carolina State Listed Plant and Animal Species Found on or Historically Occurring in the Vicinity of the Oconee Nuclear Station

Scientific Name> Common Name State Status(a) Occurrence(b)
ANIMALS
Sigmora robusta a centipede SC Historical
PLANTS
Carex laxiflora Loose-flowered sedge SR Present
Carex prasina Drooping sedge SC Present
Echinacea laevigata Smooth coneflower FE, SC Historical
Nestronia umbellula Indian olive SC Present
Orobanche uniflora One-flowered broomrape SC Historical
Pachysandra procumbens Allegheny spurge SC Historical
Viola tripartita Three-parted violet SC Present
(a) FE = Federally endangered, SC = Species of Concern in South Carolina, SR = new state record for species.

(b) Historical = species have been reported from the general area in the past, but were not located within the 1-mile radius of ONS during the applicant's survey; Present = species was found within a 1-mile radius of ONS.

During the spring of 1998, Duke contacted the FWS and the SCDNR to request information about threatened or endangered species that potentially could occur in the vicinity of the ONS. The staff contacted the FWS during the spring of 1999 to request similar information concerning the ONS related transmission lines. The FWS identified (FWS 1998) nine species that have been reported to occur within either Pickens or Oconee counties, South Carolina, and eight additional species reported from the other counties crossed by the transmission lines (Table 2-4). None of the species listed in Table 2-4 are known to inhabit the immediate vicinity of the ONS.

Federally listed species that have been occasionally sighted near ONS include the threatened bald eagle (Haliaeetus leucocephalus) and the endangered peregrine falcon (Falco peregrinus). Bald eagles are occasional visitors near the ONS site, but are not known to nest or to reside near the site for significant time periods. Bald eagles are known to be more numerous and spend more time in the vicinity of the Jocassee and Bad Creek Reservoirs. Peregrine falcons are occasional transients near ONS. Attempts have been made to introduce individuals near the Jocassee dam, but they are not known to reside near ONS.

Transmission lines associated with the ONS extend through a number of additional counties in both South Carolina and North Carolina. The FWS provided the staff information about threatened and endangered species that may occur in these counties. This list is summarized in Table 2-4.

Table 2-4. Federally Listed Threatened or Endangered Species Known or Potentially Occurring Near the ONS or in Counties Crossed by Transmission Lines Associated with the ONS

  COUNTY
Species Common Name Status(a) Greenville, SC Spartanburg, SC Anderson, SC Laurens, SC Union, SC York, SC Rutherford, SC Cleveland, SC Gaston, SC Lincoln, SC Oconee, SC Pickens, SC
ANIMALS
Halieeatus leucocephalus Bald eagle T     X     X         X X
Falco pereginus anatum Peregrine falcon E X           X       X X
Picoides borealis Red-cockaded woodpecker E       X                
Myotis sodalis Indiana bat E             X       X  
Clemmys muhlenbergii Bog turtle T* X               X     X
PLANTS
Sisyrinchium dichotomum White irisette E X           X          
Hexastylus naniflora Dwarf-flowered heartlleaf T X X       X X X   X   X
Helianthus schweinitzii Schweinitz's sunflower E           X     X      
Rhus michauxii Michaux's sumac E                   X    
Echinacea laevigata Smooth coneflower E     X               X X
Helonius bullata Swamp pink T X                      
Isotria medeoloides Small whorled pogonia T X                   X  
Sagittaria fasciculata Bunched arrowhead E X                      
Sarracenia rubra ssp. jonesii Mountain sweet pitcher plant E X                     X
Amphianthus pusillus Little amphianthus T           X            
Gymnoderma lineare Rock gnome lichen E X           X          
Trillium persistens Persistent trillium E                     X  
Isoetes malanospora Black-spored quillwort E                       X
(a) E = Endangered, T = Threatened, T* = threatened due to similarity of appearance.

Examination of the National Heritage Databases from South Carolina and North Carolina indicates that three plant species listed in Table 2-4 may occur within or near the transmission line rights-of-way. The bunched arrowhead occurs in the corridors located northwest of Greenville, South Carolina, and in the corridors located northeast of Traveler's Rest, South Carolina. The dwarf-flowered heartleaf occurs near corridors northeast of Traveler's Rest and also between Landrum, South Carolina, and the McGuire substation. Schweinitz's sunflower is known to occur near the Newport and McGuire substation at the far eastern end of the ONS related transmission system.

2.2.7 Radiological Impacts

Duke has conducted a radiological environmental monitoring program (REMP) around ONS since 1969. The radiological impacts to workers, the public, and the environment have been carefully monitored, documented, and compared to the appropriate standards. The purposes of the REMP are to

Radiological releases are summarized in the annual reports titled "Oconee Nuclear Station Units 1, 2, and 3 Annual Radiological Environmental Operating Report" and the annual effluent release reports and includes the results of the monitoring for the ISFSI. The limits for all radiological releases are specified in the Selected Licensee Commitments, and these limits are designed to meet Federal standards and requirements. The REMP includes monitoring of the aquatic environment (aquatic organisms and shoreline sediment in Lake Keowee and Hartwell Reservoir), atmospheric environment (air particulates and iodine), and terrestrial environment (vegetation and direct radiation).

Review of historical data on releases and the resultant dose calculations revealed that the doses to maximally exposed individuals in the vicinity of ONS were fractions of the limits specified in the Environmental Protection Agency's environmental radiation standards 40 CFR Part 190 as required by 10 CFR 20.1301(d). For 1997 (the most recent year that data were available), dose estimates were calculated based on actual 1997 liquid and gaseous effluent release data (Duke Power 1997). Calculations were performed using the plant effluent release data, onsite meteorological data, and appropriate pathways identified in the ODCM.

A review of whole body and organ doses (Duke Power 1997) revealed the following results: the total body dose estimate to an adult from environmental measurements was 0.0014 mSv/yr (0.14 mrem/yr) and the total body dose estimate from all effluent release pathways was 0.00615 mSv/yr (0.615 mrem/yr). The critical pathway for both of these estimates was from fish consumption. Cesium-137 was the major contributing radionuclide. These doses, which are representative of the doses from the past 5 years, are provided to demonstrate that the impact to the environment from releases from ONS is small.

The applicant does not anticipate any significant changes to the radioactive effluent releases or exposures from ONS operations during the renewal period and, therefore, the impacts to the environment are not expected to change.

2.2.8 Socioeconomic Factors

The staff reviewed the applicant's environmental report and information obtained from several county staff members, local real estate agents/appraisers, and social services providers during the October 1998 site visit. The following information describes the economy, population, and communities near ONS.

2.2.8.1 Housing

Between 1970 and 1990, total housing units in Oconee County increased from 14,032 to 25,983 (DOC 1991; U.S. Bureau of the Census 1988). Approximately 146 new households, or one percent of the growth in households, may be attributed to ONS employment (NRC 1996). A total of 891 ONS employees currently live in Oconee County (as of January 1999). As of January 1999, 515 ONS employees live in Pickens County and 161 live in Anderson (see Table 2-5). County growth has continued since 1990. Based on the estimates in the GEIS (NRC 1996) of 2,300 direct employment in 1990, immigrant ratio of 16.4 percent, and indirect employment multiplier of 0.41, ONS may have accounted for 3,243 direct and indirect jobs in Oconee, Pickens, and Anderson Counties. This accounted for 378 households and less than 2 percent of the housing growth from 1970 to 1990. Between 1980 and 1990, the number of housing units in the Tri-County (Oconee, Pickens, and Anderson) area increased approximately 22.5 percent to a total of 122,602 units (Knight 1998a). Table 2-6 provides the number of housing units and housing unit vacancies by county in the Tri-County area for the years 1970 to 1996.

Since 1990, Oconee County population has continued to increase from 57,494 at the 1990 Census to 64,059 in 1998 (Table 2-7). Pickens County increased in population from about 93,894 in 1990 to 104,618 in 1998 (Table 2-7). About 4,000 units were added to the Oconee County housing stock between 1990 and 1996, as the county became a more popular bedroom community, recreation area, and second home and retirement community and as manufacturing jobs were added (Table 2-6). The east end of Pickens County increasingly became a bedroom community for Greenville. At the time of the 1990 Census, about 10,700 Pickens County residents per day commuted to Greenville County (Knight 1997) and this number likely has increased. Clemson University is a major employer in Pickens County, with 7,156 jobs in 1997 (Knight 1997). Anderson County increased in population from 145,177 at the 1990 Census to 160,791 in 1998 (South Carolina Statistical Abstract [South Carolina Office of

Table 2-5. Employee Residence Information, Oconee Nuclear Station, January 1999

County and Selected Cities Duke and Contractor Employees
Oconee County 891
Salem 50
Seneca 454
Tamassee 19
Walhalla 138
West Union 75
Westminister 125
Other Cities and Towns 30
Pickens County 515
Central 102
Clemson 45
Easley 127
Liberty 68
Pickens 83
Six Mile 79
Other Towns and Cities 11
Anderson County 161
Anderson 88
Belton 13
Pendleton 20
Other Towns and Cities 40
Greenville County 35
Other Counties 29
North Carolina 49
Georgia 65
Other States 40
Total 1785
Source: Duke (1999a).

Table 2-6. Housing Units and Housing Units Vacant (Available) by County 1970-1996

  1970 1980 1990 1996

Oconee County

Housing Units 14,032 20,226 25,983 30,000
Occupied Units 12,764 17,373 22,358 25,200
Vacant Units 1,268 2,853 3,625 4,800

Pickens County

Housing Units 18,673 28,469 35,865 40,700
Occupied Units 17,274 25,986 33,422 38,200
Vacant Units 1,399 2,483 2,443 2,500

Anderson County

Housing Units 35,981 51,369 60,753 67,700
Occupied Units 33,277 46,944 55,481 60,700
Vacant Units 2,704 4,375 5,264 7,000
Source: 1990 Census of Housing, file STF1A, Table H2; Reference 1 (DOC. 1991); 1988 City and County Data Book; South Carolina Statistical Abstract (South Carolina Office of Research and Statistical Services 1998).

Table 2-7. Population Growth in Oconee, Pickens, and Anderson Counties, South Carolina (1970-1998)

  Oconee County Pickens County Anderson County
  Population Annual Growth % Population Annual Growth % Population Annual Growth %
1970 40,728 -- 59,956 -- 105,474 --
1980 48,611 1.8 79,292 2.8 133,235 2.4
1990 57,494 1.7 93,896 1.7 145,177 0.9
1998 64,059 1.4 107,087 1.7 160,791 1.3
Sources: U.S. Bureau of the Census, County Population Estimates for July 1, 1998 and Population Change for July 1, 1997 to July 1, 1998, Population Estimates Program Population Division, March 12, 1999; Knight 1998a.

Research and Statistical Services 1998]), due largely to growth in branch plant manufacturing. In 1997, Anderson County employed 15,800 in major manufacturing facilities, compared with 8,400 in Oconee County and 6,800 in Pickens County (Knight 1997). Oconee County added 4,017 housing units between 1990 and 1996; Pickens County added 4,835 housing units over the same period; while Anderson County added 6,947 units (Table 2-6). Housing availability in the Tri-County area is not limited by growth-control measures. With a 1996 vacancy rate of approximately 10 percent, over 14,300 units are available for occupancy in the three closest counties (Bureau of Census 1996).

2.2.8.2 Public Services

Potable water used in Oconee County is from both subsurface and surface sources and is used primarily for domestic and industrial uses. The county has four privately owned water systems, five municipal water systems, and a single sewer commission that serves the incorporated towns in the county and some selected rural areas. Table 2.8 shows source and capacity information on selected water supply systems in communities near ONS, as well as the area served by each. Both Seneca and Greenville are served with surface water from Lake Keowee, which is very high quality and has low concentrations of minerals and nutrients. Large areas of Oconee County are not served by public water supplies. According to the Oconee Community Facilities Plan, some supplies are threatened by incompatible development, including septic tanks around lakes and sedimentation and erosion from land-clearing activities. Both Seneca and Walhalla (which draws water from Coneross Creek, above Lake Keowee) have identified current plant capacity as inadequate for meeting future water demand. Seneca is searching for a location for a new treatment plant to meet future demand, while Walhalla is considering construction of a new treatment plant in the next 5 years, drawing on Lake Jocassee (reducing its need to depend on the limited capacity of Coneross Creek).

Availability of adequate wastewater collection is considered to be a current constraint on development in both Oconee and Pickens Counties. Public wastewater collection is provided in Oconee County by the municipalities of Seneca, Walhalla, and Westminster, while water treatment is provided by the Oconee County Sewer Authority (Oconee County Planning Commission 1997). Private treatment operators serve Chickasaw Point, Keowee Key, and Newry. The Authority operates the Coneross Waste Treatment Plant, which was expanded in capacity to 0.4 m3/s (7.8 million gpd). Average daily volume is only 0.14 m3/s (3 million gpd). While the difference allows considerable excess capacity for economic development within the area served by the system, there are large portions of the county not served, and there are institutional constraints that make serving the I-85 corridor a problem in Oconee County. Pickens County has limited excess capacity, and this constrains the county's ability to absorb or recruit manufacturing. Current excess capacity has been only about 0.02 m3/s (500,000 gpd), and a current $12 million upgrade is expected to primarily replace older, environmentally unacceptable capacity, expanding excess capacity to 0.04 m3/s (800,000 gpd).

Table 2-8. Major Public Water Supply Systems in Oconee County in 1997

Water System Source Maximum Daily Consumption
(Gallons)
Average Daily Consumption
(Gallons)
Area Served
Salem Water Department Two wells on SC Highway 130 Unavailable Unavailable City Limits
Seneca Light and Power Lake Keowee 5.914 million 4.406 million City of Seneca, with lines 16 km (10 mi) north and south
Walhalla Water Department Coneross Creek 2.2 million 1.42 million Walhalla city limits, Town of West Union, Surrounding area
Westminster Commission of Public Works Chauga River 3.62 million 2.314 million Unavailable, but generally along US 123 and US 76
Pioneer Water Systems Seneca and Westminster systems Unavailable Unavailable South portion of county, including Fair Play and Townville
Source: Oconee County Planning Commission 1997.

In 1996, there were approximately 49,600 students enrolled in schools in the Oconee-Pickens-Anderson County area (Knight 1997). Enrollment totals for the public schools were 10,056 in Oconee County, 26,187 in Anderson County, and 13,353 in Pickens County. Oconee County has 11 public elementary schools, four middle schools, four high schools, and four private schools. In Anderson County, there are 27 public elementary, 11 middle/junior high schools, 9 high schools, and 5 private schools. Pickens County has 15 public elementary schools, 5 middle schools, 5 high schools, and 8 private schools. Pickens and Anderson Counties have some post-secondary capability. Anderson County has Tri-County Technical College (enrollment 3,250), Forrest Junior College (enrollment 899), and Anderson College (a private, 4-year university with an enrollment of 245). Pickens County has Clemson University, with 16,526 enrollment, and Southern Wesleyan University, with an enrollment of 1,298. Economic development also benefits from the presence of technical college and university education in nearby Greenville, especially Greenville Tech.

The area has comparatively low student/teacher ratios, despite also having relatively low property taxes. For 1996, student/teacher ratios were 14.8/1 in Oconee County, 16.9/1 in Pickens County, and varied from 15.4/1 to 18.5/1 among the five school districts in Anderson County (Knight 1997). Property tax rates in 1997 were $1.99/$1000 in Oconee County (Knight 1998b), $2.04/$1000 in Pickens County, and $2.24/$1000 in Anderson County (an average of the range among 31 districts of $1.95 to $2.64).(6) Reflecting population growth, during the 1996-97 school year, the Oconee School District opened two new elementary schools, Fair Oak and Orchard Park, with a combined enrollment of over 1,100 students (Oconee County Planning Commission 1997). Fair Play Elementary School was closed and replaced by Fair Oak. All schools in the county except West Oak and Seneca High Schools received some expansion or upgrade. These two schools had received upgrades in recent years.

Oconee County is served by I-85 at its southeast corner, plus U.S. highways 76 and 123 and State highways 28 and Scenic 11. ONS is on a two-lane highway with service to the site being convenient from four main directions. Highway access remains adequate for the time being, but population growth in the county may create crowded conditions in the future, particularly at selected intersections.

Pickens County is not served by the Interstate Highway system, but has ready access to the I-85 corridor via U.S. 76 , 123, and 178. State Highways 8, 96, 135, 137, 124, and Scenic 11 complete the major road net. Highway 123 runs the length of Pickens County from east to west with four-lane service to Greenville. State Highway 133 (which runs north-south on the east side of Lake Keowee) and State Highway 183 from Pickens serve as commuting highways from Pickens County to ONS. Although several of the residential communities on both sides of Lake Keowee have long, narrow access roads, none of these roads has been identified as seriously congested.

The period from 1995 to 2015 has been projected by the State of South Carolina to be one of moderate population growth (1.1 percent per year). Oconee County is projected to grow at about the same rate as the state during that period, while Pickens and Anderson Counties are expected to grow at about 0.9 percent per year. At these rates, Oconee County would increase its current population by about 50 percent at the end of the license renewal period (see Section 2.2.8.1 and Knight 1998a). Significant upgrading of most arterial links and main highways is likely to be required to accommodate such growth. The population of the other two counties would grow by about 40 percent and also likely would require highway upgrades.

2.2.8.3 Offsite Land Use

Oconee and Pickens Counties both have land-use plans, but neither has zoning regulations (Talbert & Bright, Inc. 1996; interview with Pickens County Director of Planning, October 22, 1998). Industrial development is concentrated in the I-85, S.C. Route 123, Route 28, and Route 76 corridors in the two counties and in Anderson County. There are some restrictions on building practices, but these are not extensive. Industrial development has been limited in Pickens County by lack of sewer and water infrastructure. Oconee County has been relatively selective about the industry they target. Oconee County also has a sanitary landfill that is nearly at capacity and may constrain growth if it is not replaced (Oconee County Planning Commission 1997).

The continued availability of ONS and the associated tax base is an important feature in Oconee County's ability to continue to invest in infrastructure and to draw industry and new residents. In 1998-1999, the Oconee County Operational Budget was $26.2 million and the school operating budget $41.1 million, for a total of $67.4 million. Duke will pay $22.3 million in taxes on ONS in 1998-1999, or roughly a third of the county combined operational and school budget.(7) In Pickens County, continued presence of the plant will have less influence on development or land use, since the plant does not directly contribute to the tax base of the county. There is relatively little impact on land use in Anderson County from Oconee-related population. Duke helps with industrial recruiting in all three counties.

2.2.8.4 Visual Aesthetics and Noise

From the air, the principal visual features of the ONS region are Lakes Keowee, Jocasee, and Hartwell and the countryside, which is generally wooded or in small farms. The position of the plant relative to Lake Keowee is such that the ONS is only visible from the water within the first 1.6 km (1 mi) to the north. Further north, islands and the topography of the shoreline render the plant invisible. From the lake, the shoreline appears mostly wooded with upscale housing developments and boat launches.

Scenic resources inland from the lake have changed since ONS construction because of population growth. This growth has resulted in housing and some roadside development supplanting agricultural and wooded areas. However, South Carolina Highway 130, which follows the east side of Lake Keowee south of the plant and follows the west side of the lake to the north of the plant, mainly affords attractive views of the lake and surrounding hilly, wooded countryside with interspersed development and occasional agricultural lands. This is the main access route to the plant from either north or south. The view on South Carolina Highway 183 coming from either the east or west shows mainly woods and fields and does not reveal ONS until the traveler is within a hundred yards of the plant gate.

Because of woods and topography, noise from the ONS is generally not an issue. The only sounds heard offsite are the plant loudspeakers, which can be heard nearby on the lake.

2.2.8.5 Demography

The update to Duke's Final Safety Analysis Report (Duke 1998b) refers to Duke's emergency response plan, which had an estimated resident population as 65,423 within 16 km (10 mi) of ONS for 1990. This is only slightly different than Duke's current estimate of 64,405 (Duke 1999a). Seasonal resident population adds another 6,694, transient summer weekend visitors add 8,636 more, and on Clemson football weekends, there may be over 75,000 visitors to the area.

Tables 24.1 through 24.5 in Duke (1999a) estimated resident population for 1990 and each decade through the proposed ONS license renewal term (2010, 2020, 2030). The 2010 projections represent estimated population near the first year of license renewal for Unit 1 (2013), and the projections for the year 2030 represent populations after the end of the renewal term (2034 for Unit 3). Near the end of the license renewal term (2030), the population within 80 km (50 mi) of ONS is expected to be approximately 1.3 million, as compared with 990,000 in 1990 (Duke 1998b).

Data for 1990 are based on the 1990 Census of Population. Future population estimates were developed by combining information that was available from the 1990 Census(8) and resident population projections found in the GEIS, Vol. 2, page A-46.

The 1990 resident population distribution (by distance and directions) is found in Table 24.1 of Duke (1999a). Populations for the sectors(9) were calculated using population values at the census block level, the smallest enumeration level used by the Census Bureau. Census blocks whose geographic centroid was located within a sector were considered to lie within that sector. For each sector that is located within 80 km (50 mi) of the plant, the population numbers for the blocks within each sector were summed to give a total for that sector.

The projected population within the sectors for the years 2000, 2010, 2020, and 2030 was calculated by increasing the 1990 population for each sector by the percentage increases between the respective periods.

The projected 1990 population within 80 km (50 mi) of the Oconee Nuclear Station from the GEIS is 990,000 persons. The 1990 Census Bureau data for the year 1990 indicated 1,021,226 people living within 80 km (50 mi) of the plant. This difference (3.2 percent) was considered to be small. Therefore, Duke (1999a) used the predicted total population values found in the GEIS for the 80-km (50-mi) radius around the plant to extrapolate the 1990 population distribution data forward in time for the years 2010 and 2030. The total resident population within the 80-km (50-mi) radius for the year 2020 (not listed in the GEIS) was determined by using linear interpolation between the population totals for the years 2010 and 2030. This same procedure was applied by the staff to Duke's estimates to obtain the population by sector within 16 km (10 mi).

The estimated resident population within 16 km (10 mi) of ONS for the years 1990, 2010, 2020, and 2030 is listed in Tables 2-9 through 2-12. Figure 2-8 illustrates the 10-mile radius from ONS.

Between 1970 and 1990, the population within 16 km (10 mi) of ONS increased about 70 percent, from 37,831 (AEC 1972) to 64,405 (Duke 1999a). Current projections indicate that by the year 2010, the population within 16 km (10 mi) will be 73,789 (obtained from the FSAR [Duke 1998b]), which is about

39 percent higher than projected in the original FES (AEC 1972). The higher growth within the 16-km (10-mi) radius is primarily related to rapid population growth in Oconee County. Between 1980 and 1990, Oconee County grew half again as fast as the State (1.7 percent per year vs. 1.1 percent per year). According to agency projections, it is expected to grow at about the same rate as the state through the year 2015 (Knight 1998a). Factors stimulating growth in Oconee County include proximity to high-quality recreation and to Greenville. To these factors one could add relatively easy commutes to metropolitan areas (45-min to 1-hr commute by car), less development and lower taxes than those areas, and less stringent land use, zoning, and development regulations compared with some surrounding counties.

The estimated resident population distribution within 80 km (50 mi) of ONS for the years 1990, 2010, 2020, and 2030 is shown in Tables 2-13 through 2-16. Figure 2-9 illustrates the 80-km (50-mi) radius from ONS.

Between 1970 and 1990, the population within 80 km (50 mi) of ONS increased approximately 36 percent, from about 730,000 (AEC 1972) to about 1,020,000 (Table 2-14). Current population projections in the environmental report (ER) (Duke 1998a) indicate that by the year 2010, the population within 80 km (50 mi) will be approximately 1,170,000.

Table 2-17 lists the age distribution of Oconee County in 1990 compared to the U.S. population.

The transient population in the vicinity of ONS can be identified as daily or seasonal. Daily transients are associated with places where a large number of people gather regularly, such as local businesses, industrial facilities, and schools. Seasonal transients result from the use of weekend recreational areas such as Lakes Keowee, Jocasee, and Hartwell. It is estimated that seasonal transients increase the population within 16 km (10 mi) of ONS by approximately 10 percent during the summer months (Oconee Nuclear Station Emergency Response Plan, Duke 1999b). The daily and seasonal population associated with selected industry and recreation within 16 km (10 mi) of the station is listed in Table 2-18.

Table 2-9. Estimated Population Distribution in 1990 Within 16 km (10 mi) of ONS

Sector 0 to 1 Miles 1 to 2 Miles 2 to 3 Miles 3 to 4 Miles 4 to 5 Miles 5 to 10 Miles Total
N 0 0 0 8 3 143 154
NNE 0 0 30 64 9 186 288
NE 0 13 44 192 222 1,351 1,823
ENE 2 0 39 206 387 1,599 2,233
E 6 23 123 167 229 2,128 2,676
ESE 0 12 38 121 436 2,768 3,375
SE 0 103 158 84 144 6,825 7,314
SSE 0 0 0 0 105 14,858 14,963
S 0 8 6 0 202 3,823 4,038
SSW 0 5 5 4 86 10,989 11,090
SW 0 26 3 145 120 2,916 3,210
WSW 0 0 44 277 114 2,858 3,294
W 0 43 34 176 142 4,192 4,587
WNW 0 16 38 66 67 1,227 1,415
NW 0 14 62 661 35 1,514 2,285
NNW 0 40 110 364 140 1,007 1,660
Total 8 302 735 2,535 2,440 58,384 64,405
Source: U.S. Census Bureau - 1990 Census, File C90STF3A (DOC 1991)

Table 2-10. Estimated Population Distribution in 2010 Within 16 km (10 mi) of ONS

Sector 0 to 1 Miles 1 to 2 Miles 2 to 3 Miles 3 to 4 Miles 4 to 5 Miles 5 to 10 Miles Total
N 0 0 0 9 3 164 176
NNE 0 0 34 73 10 213 330
NE 0 15 51 220 254 1,548 2,089
ENE 2 0 45 236 443 1,831 2,558
E 7 26 141 192 262 2,438 3,066
ESE 0 14 43 139 500 3,171 3,867
SE 0 117 181 96 165 7,820 8,380
SSE 0 0 0 0 120 17,023 17,143
S 0 9 7 0 231 4,379 4,626
SSW 0 6 6 5 98 12,591 12,706
SW 0 30 4 166 137 3,342 3,678
WSW 0 0 51 318 131 3,274 3,774
W 0 50 39 202 163 4,802 5,255
WNW 0 19 44 75 77 1,406 1,621
NW 0 16 71 758 40 1,735 2,618
NNW 0 45 126 417 160 1,153 1,902
Total 9 346 842 2,905 2,796 66,891 73,789
Source: Computed from Table 2-14.

Table 2-11. Estimated Population Distribution in 2020 Within 16 km (10 mi) of ONS

Sector 0 to 1 Miles 1 to 2 Miles 2 to 3 Miles 3 to 4 Miles 4 to 5 Miles 5 to 10 Miles Total
N 0 0 0 9 4 174 187
NNE 0 0 36 78 11 226 350
NE 0 16 54 234 270 1,641 2,214
ENE 3 0 48 250 470 1,941 2,711
E 7 27 149 203 278 2,584 3,249
ESE 0 14 46 147 530 3,361 4,098
SE 0 124 192 102 175 8,288 8,881
SSE 0 0 0 0 127 18,041 18,168
S 0 9 7 0 245 4,641 4,903
SSW 0 6 6 5 104 13,344 13,466
SW 0 32 4 176 145 3,541 3,898
WSW 0 0 54 337 139 3,470 4,000
W 0 53 41 214 173 5,090 5,570
WNW 0 20 47 80 81 1,490 1,718
NW 0 17 75 803 42 1,839 2,775
NNW 0 48 134 442 170 1,223 2,016
Total 10 367 892 3,079 2,963 70,893 78,204
Source: Computed from Table 2-15.

Table 2-12. Estimated Population Distribution in 2030 Within 16 km (10 mi) of ONS

Sector 0 to 1 Miles 1 to 2 Miles 2 to 3 Miles 3 to 4 Miles 4 to 5 Miles 5 to 10 Miles Total
N 0 0 0 10 4 184 198
NNE 0 0 38 82 11 238 369
NE 0 17 57 247 285 1,733 2,338
ENE 3 0 51 264 496 2,050 2,864
E 8 29 158 214 294 2,730 3,433
ESE 0 15 48 156 560 3,550 4,329
SE 0 131 203 107 185 8,755 9,382
SSE 0 0 0 0 134 19,060 19,194
S 0 10 8 0 259 4,904 5,180
SSW 0 7 7 5 110 14,097 14,226
SW 0 33 4 186 154 3,741 4,118
WSW 0 0 57 356 147 3,666 4,225
W 0 56 43 226 183 5,377 5,884
WNW 0 21 49 84 86 1,574 1,815
NW 0 17 79 848 44 1,942 2,931
NNW 0 51 141 466 179 1,291 2,129
Total 11 388 942 3,252 3,130 74,893 82,615
Source: Computed from Table 2-16.

Figure 2-8. Oconee Nuclear Station - 16-km (10-mi) Radius

Table 2-13. Estimated Population Distribution in 1990 Within 80 km (50 mi) of ONS

  0-10 10-20 20-30 30-40 40-50  
Sector Miles Miles Miles Miles Miles Total
N 154 355 2,557 444 22,328 25,838
NNE 288 547 6,285 18,676 26,660 52,456
NE 1,823 4,692 4,331 4,631 41,165 56,642
ENE 2,233 13,845 34,721 46,169 36,182 133,150
E 2,676 29,511 112,819 117,286 30,134 292,426
ESE 3,375 5,678 25,609 14,078 12,455 61,195
SE 7,314 5,916 36,445 12,423 11,055 73,153
SSE 14,963 11,038 38,834 9,191 2,715 76,741
S 4,038 3,363 6,624 9,659 13,001 36,685
SSW 11,090 5,290 7,450 10,407 9,024 43,261
SW 3,210 6,814 8,155 5,772 6,847 30,798
WSW 3,294 4,722 13,914 13,605 20,881 56,416
W 4,587 3,070 2,403 3,427 3,540 17,027
WNW 1,415 1,017 4,945 3,116 4,151 14,644
NW 2,285 579 2,678 14,770 5,142 25,454
NNW 1,660 354 1,946 7,872 13,508 25,340
Total 64,405 96,791 309,716 291,526 258,788 1,021,226
Source: U.S. Census Bureau - 1990 Census, File C90STF3A (DOC 1991).

Table 2-14. Estimated Population Distribution in 2010 Within 80 km (50 mi) of ONS

  0-10 10-20 20-30 30-40 40-50  
Sector Miles Miles Miles Miles Miles Total
N 176 407 2,930 509 25,581 29,602
NNE 330 627 7,201 21,397 30,544 60,098
NE 2,089 5,376 4,962 5,306 47,162 64,894
ENE 2,558 15,862 39,779 52,895 41,453 152,548
E 3,066 33,810 129,255 134,372 34,524 335,027
ESE 3,867 6,505 29,340 16,129 14,269 70,110
SE 8,380 6,778 41,754 14,233 12,666 83,810
SSE 17,143 12,646 44,491 10,530 3,111 87,921
S 4,626 3,853 7,589 11,066 14,895 42,029
SSW 12,706 6,061 8,535 11,923 10,339 49,563
SW 3,678 7,807 9,343 6,613 7,844 35,285
WSW 3,774 5,410 15,941 15,587 23,923 64,635
W 5,255 3,517 2,753 3,926 4,056 19,508
WNW 1,621 1,165 5,665 3,570 4,756 16,777
NW 2,618 663 3,068 16,922 5,891 29,162
NNW 1,902 406 2,229 9,019 15,476 29,032
Total 73,788 110,892 354,836 333,996 296,489 1,170,000
Source: Duke 1999a.

Table 2-15. Estimated Population Distribution in 2020 Within 80 km (50 mi) of ONS

  0-10 10-20 20-30 30-40 40-50  
Sector Miles Miles Miles Miles Miles Total
N 187 431 3,105 539 27,111 31,373
NNE 350 664 7,631 22,677 32,371 63,693
NE 2,214 5,697 5,259 5,623 49,984 68,776
ENE 2,711 16,811 42,159 56,060 43,933 161,674
E 3,249 35,833 136,988 142,412 36,590 355,071
ESE 4,098 6,894 31,095 17,094 15,123 74,305
SE 8,881 7,183 44,252 15,084 13,423 88,824
SSE 18,168 13,403 47,153 11,160 3,297 93,181
S 4,903 4,083 8,043 11,728 15,786 44,544
SSW 13,466 6,423 9,046 12,636 10,957 52,529
SW 3,898 8,274 9,902 7,009 8,314 37,396
WSW 4,000 5,734 16,895 16,520 25,354 68,502
W 5,570 3,728 2,918 4,161 4,298 20,675
WNW 1,718 1,235 6,004 3,784 5,040 17,781
NW 2,775 703 3,252 17,934 6,244 30,907
NNW 2,016 430 2,363 9,558 16,402 30,769
Total 78,202 117,526 376,065 353,979 314,227 1,240,000
Source: Duke 1999a.

Table 2-16. Estimated Population Distribution in 2030 Within 80 km (50 mi) of ONS

  0-10 10-20 20-30 30-40 40-50  
Sector Miles Miles Miles Miles Miles Total
N 198 455 3,280 570 28,642 33,144
NNE 369 702 8,062 23,957 34,199 67,289
NE 2,338 6,019 5,556 5,941 52,805 72,659
ENE 2,864 17,760 44,539 59,224 46,413 170,801
E 3,433 37,856 144,721 150,451 38,655 375,116
ESE 4,329 7,284 32,851 18,059 15,977 78,499
SE 9,382 7,589 46,751 15,936 14,181 93,839
SSE 19,194 14,159 49,815 11,790 3,483 98,441
S 5,180 4,314 8,497 12,390 16,677 47,058
SSW 14,226 6,786 9,557 13,350 11,576 55,494
SW 4,118 8,741 10,461 7,404 8,783 39,507
WSW 4,225 6,057 17,848 17,452 26,786 72,369
W 5,884 3,938 3,083 4,396 4,541 21,842
WNW 1,815 1,305 6,343 3,997 5,325 18,785
NW 2,931 743 3,435 18,947 6,596 32,652
NNW 2,129 454 2,496 10,098 17,328 32,505
Total 82,617 124,161 397,295 373,961 331,966 1,310,000
Source: Duke 1999a.

Table 2-17. Estimated Age Distribution of Population in 1990(a)

Age Group Oconee County, South Carolina United States
  Number Percent Number Percent
Under 5 3,573 6.2 19,512,000 7.6
5-19 12,106 21.1 53,523,000 21.0
20-44 21,241 36.9 101,416,000 39.8
45-64 12,666 22.0 48,348,000 19.0
65 and Over 7,908 13.8 32,283,000 12.7
Total 57,494 100.0 255,082,000 100.0
(a) U.S. Bureau of the Census 1990, File STFIA (DOC 1991).

Figure 2-9. Oconee Nuclear Station - 80-km (50-mi) Radius

It should be noted that on most weekdays, a significant portion of the resident population is absent from Oconee County during daytime hours. According to the 1990 Census of Population, 25 percent of employed County residents (about 6700 people) commuted to jobs outside of Oconee County while over 4200 commuted into the county (Talbert & Bright 1996). With increased numbers of in-movers to Oconee County, the number of commuters likely has increased, although no post-1990 numbers are available.

Table 2-18. Transient Population Within 16 km (10 mi) of ONS(a)

Direction Seasonal Resident Population Winter Weekday Winter Weeknight Summer Weekend Clemson Football Weekend
N 25 20 0 392 20
NNE 39 0 0 0 0
NE 235 0 0 0 0
ENE 229 0 0 0 0
E 272 0 0 0 0
ESE 300 210 90 90 90
SE 491 468 322 2,515 378
SSE 738 1,486 1,294 1,133 73,688
S 383 100 60 60 0
SSW 848 597 447 797 457
SW 318 1,002 335 3,300 235
WSW 453 1,420 120 169 169
W 517 275 127 122 122
WNW 215 0 0 0 0
NW 715 0 8 0 50
NNW 687 8 0 0 8
Offsite 6,465 5,586 2,803 8,578 75,217
ONS   1395 698 698 698
Total   6,981 3,501 9276 75,915
(a) Source: Oconee Nuclear Station Emergency Response Plan (Duke 1999b), Revision 99-01, Figures J-3B to J-4E.

2.2.9 Historical and Archaeological Resources

This section discusses the cultural background and the known historical and archaeological resources at the ONS site and in the surrounding area.

2.2.9.1 Cultural Background

The area around ONS is rich in prehistoric and historic Native American and historic Euroamerican cultural resources. This part of northwestern South Carolina has an archaeological sequence that extends back to about 10,000 B.C., although human use of the area was probably limited until about 4,000 to 5,000 B.C. when numerous small campsites are evident in the archaeological record. By 1000 B.C., archaeological data suggest a shift from scattered campsites to a more sedentary settlement and a subsistence system that was concentrated on ravine settings. By A.D. 1000, the archeological evidence for ancestral Cherokee culture is present, beginning with the regional Pisgah Phase (A.D. 1000 to 1500) and the following contact period Qualla Phase (A.D. 1500 to 1850) (Dickens 1976; Keel 1976). Pisgah villages included upright wooden post houses encircled by a palisade. These villages were commonly located in the larger alluvial valleys where soils were suitable for horticulture. This general village pattern continued into the Early Qualla Phase with the Late Qualla Phase being characterized by the Europeanization of Native American technology, economy, and settlement patterns after A.D. 1820.

The Cherokee were first noted in the written record by Spanish explorers in 1540. During the Qualla historic period, the Cherokee Indian cultural group has been divided into three subgroups, based on cultural, linguistic, and environmental distinctions (Dickens 1979). Of these subgroups, the Lower Cherokee grouping occupied the foothills of the Appalachian Mountains near the upper reaches of the Savannah River system. The Keowee River valley, which includes ONS and the associated reservoir, was one of the principal riverine settings for Lower Cherokee settlements of this period. Other Lower Cherokee villages are documented from historical written references in this part of South Carolina (Sheriff 1994; Ross 1980). During the 18th century, Keowee was the most important of these villages (Harmon 1986). The Cherokee village of Keowee, which is today located beneath the waters of Lake Keowee about 8 km (5 mi) north of ONS, was partially excavated during a preimpoundment archaeological project sponsored by Duke from 1966 to 1968. Also investigated by this project was Fort Prince George, a garrison constructed across the river from Keowee Village by the British Government in 1753 to protect the Lower Cherokee from French intrusions into the area and to secure trade relations between the British and the Cherokees (Hembree and Jackson 1998; Williams 1998).

The Cherokee Indian presence throughout their former extensive homelands came to a close in the late 1700s through a series of treaties with the Colonies and the United States, culminating with the well-documented removal of the Cherokee and other southeastern tribes to Indian Territory in the West (Perdue and Green 1995). The part of South Carolina, including the Oconee project area, was included in a land cession treaty completed in May of 1777 (Royce 1884). A small number of Cherokee in North Carolina avoided the removal actions and today are recognized as the Eastern Band of Cherokee Indians, with their tribal headquarters at Cherokee, North Carolina, some 80 km (50 mi) north of ONS. Cherokees removed to the West are today known as the Cherokee Nation of Oklahoma.

Following the 1777 treaty, northwestern South Carolina was immediately occupied by land-hungry white settlers. The first deeds in the Keowee River valley date to 1784; by the turn of the century, most of the land along the Keowee and adjacent valleys had been deeded. Hembree and Jackson (1998) document the historical development of the Keowee River valley from initial settlement through construction of Duke's Keowee-Toxaway Project that transformed the entire river valley.

2.2.9.2 Historical and Archaeological Resources at ONS

Archaeological

As noted above, archaeological investigations were conducted throughout the Keowee-Toxaway Project area, basically the Keowee River valley from the present Keowee Dam and ONS north to include the inundated portion of Lake Keowee. This effort was conducted by personnel from the South Carolina State Department of Archaeology during which 39 archaeological sites were recorded. Of this total, 9 of the sites were archaeologically tested, and significant excavations were completed at 6 sites, including Keowee Indian village and Fort Prince George (Beuschel, no date). Although final reports of these activities were not issued following the fieldwork, recent documents have provided some detail (Harmon 1986; Williams 1998). Information gained about both the Cherokee occupation and the British operation of Fort Prince George is also presented in the interpretive displays at the Keowee-Toxaway State Park.

Archaeological site file searches at the South Carolina Department of Archives and History and the Institute of Archaeology and Anthropology, University of South Carolina, revealed the presence of four recorded Native American sites within a 1.6-km (1-mi) radius of ONS. Two of these sites were recorded during a field survey of the Oconee-Bad Creek 500 kV transmission line (Brockington 1978). Both of these archaeological sites, located northwest of the ONS, are low-density lithic tool scatter sites and were evaluated as not possessing characteristics that would make them eligible for the National Register of Historic Places. The other two archaeological sites are located southwest of the plant. Each of these sites is also categorized as a nondescript lithic scatter.

Historical

The preinundation archaeological project focused solely on the prehistoric and early historic Cherokee sites and Fort Prince George. The architecture and archaeology of historic Euroamerican period settlements in the overall project area were not documented and evaluated, including the Old Pickens townsite at the location of ONS. A number of cemeteries in the valley were relocated before inundation. Additionally, many historic structures were relocated by Duke, including residences, a girl's camp, two sawmills, and a covered wooden bridge.

The original town of Pickens on the west bank of the Keowee River was active between 1828 and 1868 as the courthouse town of Pickens District, which then included present-day Oconee and Pickens Counties (Hembree and Jackson 1998; Holder 1991). In 1868, the Keowee River was designated as the boundary line between the two newly formed counties. In response to this division, a new town, also called Pickens, was established about 24 km (15 mi) northeast to be the seat of Pickens County. Most of the buildings in the original town of Pickens were torn down or dismantled and moved to the new town of Pickens or to Walhalla, the new county seat of Oconee County.

The original townsite apparently included much of what became ONS. According to Hembree and Jackson (1998), "The Pickens townsite stretched from the bank of the Keowee, along what is now the Pickens-Walhalla Highway [Highway 183], west across the Duke construction and maintenance shops, and north over the site of the nuclear plant."

Today, the only standing structure at the Old Pickens townsite is a one-story brick building built between 1849 and 1851, commonly known as the "Old Pickens Presbyterian Church." A cemetery with over 200 marked graves surrounds the church, including the original cemetery associated with the church and relocated graves from 14 family or other cemeteries that were moved to Old Pickens in the late 1960s before Lake Keowee was filled. A complete listing of tombstone inscriptions from the original and relocated cemeteries is found in the Pendleton Chapter of South Carolina Genealogical Society (1983-84). The Old Pickens Presbyterian Church was nominated for inclusion in the National Register of Historic Places in 1994 and listed in 1996 (Sherard 1994).

No other historic period sites are currently recorded at ONS. While no historic structures are present, there is potential for either surface or buried historic archaeological remains (e.g., artifact scatters, privies, and refuse dumps) that could exist in areas that have not received substantial soil disturbance.

Any such remains could have been associated either with the Old Pickens townsite, with nearby homesteads along the river, or along Highways 183 and 130. According to the Keowee-Toxaway Project description, 17 houses were relocated in connection with development of ONS (Duke 1971).

For example, Hembree and Jackson (1998) illustrate a historic two-story home, known in the 1800s as the Pleasant Alexander House that once stood in the Oconee project area on the west bank of the Keowee River. During dam construction in the 1960s, Duke used the house as an office, after which it was moved to High Falls County Park where it continues to serve as park offices. In a 1968 aerial photograph of the ONS construction site, the house is clearly evident on the west bank, just below the damsite (Hembree and Jackson 1998). In the same view, two other then-extant historic houses can be seen along the north side of Highway 183, along the southern edge of the plant site. At the same location near the current access road into the plant from Highway 183, there is a small fenced cemetery on the knoll above the road. This cemetery has not been recorded and is not included in the listing of Oconee County historic cemeteries (Pendleton Chapter of South Carolina Genealogical Society 1983-84). Household artifacts in the vicinity of this cemetery indicate that a house was probably at one time associated with the graves.

2.2.10 Related Federal Project Activities

The Federal Power Commission, now the Federal Energy Regulatory Commission (FERC), issued a license (FERC Project No. 2503) to Duke Power on September 1, 1966, for the construction of the Keowee hydroelectric station and the Jocassee pumped storage project. Lake Keowee, from which the ONS draws cooling water, is formed by dams on the Keowee River and Little River. The Keowee hydroelectric station is located at the dam on the Keowee River. The station serves as the onsite emergency electric power source for ONS. The license for the Keowee and Jocassee hydroelectric projects will expire in 2016. Under current FERC rules, Duke will need to file a notice of intent with FERC by 2011 declaring whether it intends to seek a new license for the Keowee and Jocassee hydroelectric projects. At least 2 years before the license expires, Duke will need to file an application for a new license (relicense). FERC procedures for processing a new license are similar to those for an original license.

The staff reviewed the possibility that activities of other Federal agencies (including FERC) might impact the renewal of the operating license for the ONS. Any such activities could result in cumulative environmental impacts and the possible need for such a Federal agency to become a cooperating agency for preparation of the SEIS.

The staff determined that there were no Federal project activities in the vicinity of ONS that could result in cumulative environmental impacts or that would make it desirable for another Federal agency to become a cooperating agency for preparing the SEIS. The Natural Resources Conservation Service (NRCS), a division of the U.S. Department of Agriculture, was the only Federal agency to participate in the scoping process. NRCS submitted a letter stating that it has partnered with Duke in planning, implementing, and promoting environmental stewardship, such as the cooperative work to prevent and control soil erosion at work sites in the South Carolina mountains and foothills.


2.3 References


[ Prev | Next | Top of file ]

10 CFR Part 20, "Standards for Protection Against Radiation."

10 CFR 20.1301(d), "Dose limits for individual members of the public."

10 CFR 20.2002, "Method for obtaining approval of proposed disposal procedures."

10 CFR Part 20, Appendix B, Table 2, "Annual limits on intake (ALIs) and derived air concentrations (DACs) of radionuclides for occupational exposure; effluent concentrations; concentrations for Release to Sewerage."

10 CFR Part 50, Appendix I, "Numerical guides for design objectives and limiting conditions for operation to meet the criterion 'as low as is reasonably achievable' for radioactive material in light-water-cooled nuclear power reactor effluents."

10 CFR 51.53, "Postconstruction environmental reports."

10 CFR 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants."

10 CFR Part 61, "Licensing requirements for land disposal of radioactive waste."

10 CFR Part 71, "Packaging and transportation of radioactive material."

40 CFR 81.311, "Georgia."

40 CFR 81.334, "North Carolina."

40 CFR 81.341, "South Carolina."

40 CFR Part 81, Subpart D, "Identification of Mandatory Class I Federal Areas where Visibility is an Important Factor."

40 CFR Part 190, "Environmental radiation protection standards for nuclear power operations."

49 CFR Parts 171 through 177.

Atomic Energy Act of 1954, as amended, 42 USC 2011-2259, et seq.

Bailey, R.G. 1976. Ecoregions of the United States (map). Ogden, Utah: USDA Forest Service, Intermountain Region. 1:7,500,000.

Bailey, R.G. 1980. Descriptions of the Ecoregions of the United States. USDA Forest Service, Misc. Publication No. 1391.

Barwick, D.H., L.E. Miller, W.R. Geddings, and D.M. Rankin. 1995. Fish biomass and angler harvest from a South Carolina cooling reservoir. Proceedings of the Annual Conference of the Southeastern Association of Fish and Wildlife Agencies 49: 129-139.

Beuschel, L.L. No Date. Keowee Toxaway Reservoir Project: A Partial Account of the Archaeology. Draft report prepared for Duke Power Company, Charlotte, NC. Copy on file at the South Carolina Institute of Archaeology and Anthropology, University of South Carolina, Columbia, South Carolina.

Brockington, P.E. 1978. An Archaeological Survey of Duke Power's Oconee-Bad Creek 500 kV and Jocassee-Bad Creek 100 kV Transmission Lines, Oconee County, south Carolina. South Carolina Institute of Archaeology and Anthropology, Research Manuscript Series 130, Columbia, South Carolina.

Clean Air Act (CAA), as amended, 42 USC 7401, et seq.

Coastal Zone Management Act (CZMA), as amended, 33 USC 1455, et seq.

Dickens, R.S., Jr. 1976. Cherokee Prehistory. University of Tennessee Press, Knoxville, Tennessee.

Dickens, R.S., Jr. 1979. The Origins and Development of Cherokee Culture. In The Cherokee Indian Nation: A Troubled History, edited by Duane H. King, pp. 3-32. University of Tennessee Press, Knoxville, Tennessee.

Duke Energy Corporation. 1998a. Application for Renewed Operating Licenses Oconee Nuclear Station - Units 1, 2 and 3. Volume IV - Environmental Report.

Duke Energy Corporation. 1998b. Oconee Updated Final Safety Analysis Report (UFSAR). Charlotte, North Carolina.

Duke Energy Corporation. 1999a. Letter from M.S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Subject: License Renewal - Response to Requests for Additional Information, Oconee Nuclear Station. Dated March 4, 1999.

Duke Energy Corporation. 1999b. Oconee Nuclear Station Emergency Plan, Rev. 99-01. Charlotte, North Carolina.

Duke Power Company. 1971. Supplement to Environmental Quality Features of Keowee-Toxaway Project. Charlotte, North Carolina.

Duke Power Company. 1977. Oconee Nuclear Station Environmental Summary Report 1971-1976, Volumes 1 and 2. Duke Power Company Steam Production Department.

Duke Power Company. 1997. Oconee Nuclear Station Units 1 and 3, Annual Radiological Environmental Operating Report.

Edwards, T.J., W.H. Hunt, L.E. Miller, and J.J. Sevic. 1976. An evaluation of the impingement of fishes at four Duke Power Company steam-generating facilities. Pages 373-380 in Esch, G.W. and R.W. McFarlane (eds.). Thermal Ecology II. National Technical Information Service, U.S. Department of Commerce, Springfield, Virginia.

Federal Water Pollution Control Act (FWPCA), as amended, 33 USC 1251 et seq. (Also know as the Clean Water Act).

Greller, A.M. 1988. "Deciduous Forest." Pp. 287-316, In North American Terrestrial Vegetation, M.G. Barbour and W.D. Billings, eds., Cambridge University Press, New York.

Harmon, M.A. 1986. Eighteenth Century Lower Cherokee Adaptation and Uses of European Material Culture. South Carolina Institute of Archaeology and Anthropology, Volumes in Historical Archaeology 2, Columbia, South Carolina.

Hembree, M. and D. Jackson. 1998. Keowee: The Story of the Keowee River Valley in Upstate South Carolina. Fourth Printing, Revised. No publisher given.

Holder, F.C., Compiler. 1991. Historic Sites of Oconee County, SC: Part of the History of Oconee County Told Through Historic Preservation. Second Edition. Oconee County Historical Society.

Keel, B.C. 1976. Cherokee Archaeology. University of Tennessee Press, Knoxville, Tennessee.

Keowee-Toxaway Fishery Resources. 1996. Ten-Year Work Plan: January 1996-December 2005. South Carolina Department of Natural Resources and Duke Power Company.

Knight, H.T. (Ed.) 1997. 1997 Upstate Profile. Quality of Life of the S.C. Upstate. Part Three: Upstate Living, Upstate Leisure, Business Travel, and Tourism. South Carolina Appalachian Council of Governments, Greenville, South Carolina.

Knight, H.T. (Ed.) 1998a. 1998 Upstate Profile. Development of the SC Upstate. Part 1: Population, Income, and Housing. South Carolina Appalachian Council of Governments, Greenville, South Carolina.

Knight, H.T. (Ed.) 1998b. 1998 Oconee County Economic Profile. Comprehensive Overview of South Carolina's Golden Corner. South Carolina Appalachian Council of Governments, Greenvilee, South Carolina.

National Oceanic and Atmospheric Administration (NOAA). 1998. "1997 Local Climatological Data Annual Summary with Comparative Data, Greenville-Spartanburg (Greer), South Carolina." Asheville, North Carolina.

Oconee County Planning Commission. 1997. Oconee County Community Facilities Plan. Prepared by the Oconee County Planning Commission and the Appalachian Council of Governments, Walhalla, South Carolina., August 1997.

Pendleton Chapter of South Carolina Genealogical Society. 1983, 1984. Oconee County, South Carolina Cemetery Survey. 2 Vols. A Press, Greenville, South Carolina.

Perdue, T. and M.D. Green, Editors. 1995. The Cherokee Removal: A Brief History with Documents. Bedford Books, Boston, Massachusetts.

Resource Conservation and Recovery Act of 1976, 42 USC 6901.

Ross, L.W. 1980. A Short History of the Cherokee Indians in Oconee County, SC. No publisher given. Pamphlet, 8 pp.

Royce, C.C. 1884. Map of the Former Territorial Limits of the Cherokee "Nation of" Indians Exhibiting the Boundaries of the various Cessions of Land Made by them to the Colonies and to the United States by Treaty Stipulations, from the Beginnings of their Relations with the Whites to the Date of their Removal West of the Mississippi River. 1977 Reprint by the Museum of the Cherokee Indians, Cherokee, North Carolina.

Sherard, G.W., Compiler. 1994. National Register of Historic Places Registration Form: Old Pickens Presbyterian Church. Copy of file at South Carolina Department of Archives and History, Columbia, South Carolina.

Sheriff, A., Editor. 1994. Cherokee Villages in South Carolina, Including Information on Fort Prince George and Fort Rutledge. Second Edition. Forest Acres/McKissick Quest Program, Easley, South Carolina.

South Carolina Department of Health and Environmental Control (SCDHEC). 1997. Watershed Water Quality Assessment: Savannah and Salkehstchie River Basins, Technical Report No. 003-97. Columbia, South Carolina.

South Carolina Department of Health and Environmental Control (SCDHEC). 1998. South Carolina Air Quality Annual Report, Volume XVII 1997. Columbia, South Carolina.

South Carolina Office of Research and Statistical Services. 1998. South Carolina Statistical Abstract. South Carolina State Budget and Control Board. Published by the Office of Research and Statistics, Columbia, South Carolina.

Talbert & Bright, Inc. and Holland Consulting Planners, Inc. 1996. Oconee County, South Carolina 1996 Land Use Plan.

U.S. Atomic Energy Commission (AEC). 1972. Final Environmental Statement related to operation of Oconee Nuclear Station Units 1, 2 and 3. March 1972. Washington, D.C.

U.S. Bureau of the Census. 1988. County and City Data Book. Superintendent of Documents, U.S. Government Printing Office, Washington, D.C.

U.S. Bureau of the Census. 1996. Population Estimates Branch, Estimates of Housing Units and Households of Counties 1990-1996. U.S. Government Printing Office, Washington, D.C.

U.S. Bureau of the Census. 1999. County Population Estimates for July 1, 1998, and Population Change for July 1, 1997, to July 1, 1999, Population Estimates Program Population Division.

U.S. Department of Commerce (DOC). 1991. 1990 Census - Population and Housing; Public Law 94-171 Data. Bureau of the Census, Washington, D.C.

U.S. Fish and Wildlife Service. 1998. Letter from R.L. Banks (FWS, Charleston, South Carolina) to J. Huff (Duke Power, Charlotte, North Carolina) dated April 17, 1998. Letter provides a list of 9 species in Oconee and Pickens Counties.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1997. Letter from NRC to Framatome Technologies, Inc. Subject: Acceptance for Referencing of FCF Topical Report BAW-10186P "Extended Burnup Evaluation." Dated April 29, 1997.

U.S. Nuclear Regulatory Commission (NRC). 1998. Letter from NRC to Duke Energy Corporation. Subject: Request for Additional Information for the Review of the Oconee Nuclear Station Unit Nos. 1, 2, & 3 Environmental Report Associated with License Renewal - Environmental. Dated December 29, 1998.

U.S. Nuclear Regulatory Commission (NRC). 1999a. Letter from NRC to Duke Energy Corporation. Subject: Use of Framatome Cogema Fuels Topical Report on High Burnup - Oconee Nuclear Station, Units 1, 2, and 3. Dated March 1, 1999.

U.S. Nuclear Regulatory Commission (NRC). 1999b. Letter from NRC to Duke Energy Corporation. Subject: Determination of the Scope of Transmission Lines Impact Assessment for Oconee License Renewal. Dated May 10, 1999.

Williams, M.W. 1998. A Memoir of the Archaeological Excavation of Fort Prince George, Pickens County, South Carolina. South Carolina Institute of Archaeology and Anthropology Research, Research Manuscript Series 226, Columbia, South Carolina.


3.0 Environmental Impacts of Refurbishment


[ Prev | Next | Top of file ]

Environmental issues associated with refurbishment activities were discussed in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437 (NRC 1996). The GEIS included a determination of whether the analysis of the environmental issues could be applied to all plants and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristics

(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)

(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that did not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required.

License renewal actions may require refurbishment activities for the extended plant life. These actions may have an impact on the environment that requires evaluation, depending on the type of action and the plant-specific design. Environmental issues associated with refurbishment that were determined to be Category 1 issues are listed in Table 3-1.

Environmental issues related to refurbishment considered in the GEIS for which these conclusions could not be reached for all plants, or for specific classes of plants, are Category 2 issues. These are listed in Table 3-2.

The potential environmental effects of refurbishment actions would be identified, and the analysis would be summarized within this section, if such actions were planned. Duke indicated that it has performed an evaluation of structures and components pursuant to 10 CFR 54.21 to identify activities that are necessary to continue operation of ONS during the requested 20-year period of extended

Table 3-1. Category 1 Issues for Refurbishment Evaluation

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections

Surface-Water Quality, Hydrology, and Use (for all plants)

Impacts of refurbishment on surface-water quality 3.4.1
Impacts of refurbishment on surface-water use 3.4.1

Aquatic Ecology (for all plants)

Refurbishment 3.5

Groundwater Use and Quality

Impacts of refurbishment on groundwater use and quality 3.4.2

Land Use

Onsite land use 3.2
Human Health
Radiation exposures to the public during refurbishment 3.8.1
Occupational radiation exposures during refurbishment 3.8.2

Socioeconomics

Public services: public safety, social services, and tourism and recreation 3.7.4; 3.7.4.3

3.7.4.4; 3.7.4.6

Aesthetic impacts (refurbishment) 3.7.8

operation. These activities include replacement of certain components as well as new inspection activities and are described in Exhibit A of the Oconee Application for Renewed Operating Licenses (Duke 1998).

However, Duke stated that the replacement of these components and the additional inspection activities are within the bounds of normal plant component replacement and inspections; therefore, they are not expected to affect the environment outside the bounds of plant operations as evaluated in the final environmental statement (FES) (AEC 1972). In addition, Duke's evaluation of structures and components as required by 10 CFR 54.21 did not identify any major plant refurbishment activities or modifications necessary to support the continued operation of ONS beyond the end of the existing operating licenses. Therefore, refurbishment is not considered in this SEIS.

Table 3-2. Category 2 Issues for Refurbishment Evaluation

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section 10 CFR 51.53 (c)(3)(ii) Subparagraph
Terrestrial Resources
Refurbishment impacts 3.6 E
Threatened or Endangered Species (for all plants)
Threatened or endangered species 3.9 E
Air Quality
Air quality during refurbishment (non-attainment and maintenance areas) 3.3 F
Socioeconomics
Housing impacts 3.7.2 I
Public services: public utilities 3.7.4.5 I
Public services: education (refurbishment) 3.7.4.1 I
Offsite land use (refurbishment) 3.7.5 I
Public services, transportation 3.7.4.2 J
Historic and archaeological resources 3.7.7 K

Environmental Justice

Environmental justice

Not addressed

 


3.1 References


[ Prev | Next | Top of file ]

10 CFR Part 51, Subpart A, Appendix B, "Environmental effect of renewing the operating license of a nuclear power plant."

10 CFR 54.21, "Contents of application - technical information."

Duke Energy Corporation 1998. Application for Renewed Operating Licenses, Oconee Nuclear Station Units 1, 2, and 3. Volume IV - Environmental Report.

U.S. Atomic Energy Commission (AEC). 1972. Final Environmental Statement related to Operation of Oconee Nuclear Station Units 1, 2, and 3. March 1972. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC) 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.


4.0 Environmental Impacts of Operation


[ Prev | Next | Top of file ]

Environmental issues associated with operation during the renewal term were discussed in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437 (NRC 1996a; 1999a). The GEIS included a determination of whether the analysis of the environmental issues could be applied to all plants and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristics

(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)

(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that did not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required.

This chapter addresses those issues related to operation during the renewal term that are listed in 10 CFR Part 51, Subpart A, Appendix B, Table B-1 that are applicable to ONS. Section 4.1 addresses the Category 1 issues applicable to the ONS once-through cooling system, while Category 2 issues applicable to the ONS cooling system are discussed at greater length in Sections 4.1.1 through 4.1.4. Section 4.2 addresses Category 1 issues related to transmission lines and land use, while Category 2 issues are discussed in Sections 4.2.1 and 4.2.2. Section 4.3 addresses the radiological impacts of normal operation. There are no Category 2 issues related to radiological impacts of normal operation. Section 4.4 addresses the Category 1 issues related to the socioeconomic impacts of normal operation during the renewal term. Category 2 socioeconomic issues are discussed in Sections 4.4.1 through 4.4.6. Section 4.5 addresses the Category 1 issues related to groundwater use and quality. Category 2 groundwater use and quality issues are discussed in Sections 4.5.1 and 4.5.2. Section 4.6 discusses the impacts of renewal-term operations on threatened and endangered species, a Category 2 issue. Section 4.7 addresses new information that was raised during the scoping period. The results of the evaluation of environmental issues related to operation during the renewal term are summarized in Section 4.8. Finally, Section 4.9 lists the references for Chapter 4.


4.1 Cooling System


[ Prev | Next | Top of file ]

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to ONS cooling system operation during the renewal term are listed in Table 4-1. Duke stated in its environmental report (ER) (Duke 1998a) that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of the issues, the GEIS concluded that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, for each of these issues follows:

Table 4-1. Category 1 Issues Applicable to the Operation of the ONS Cooling System During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections

Surface Water Quality, Hydrology, and Use (for all plants)

Altered current patterns at intake and discharge structures 4.2.1.2.1; 4.3.2.2; 4.4.2
Altered thermal stratification of lakes 4.2.1.2.3; 4.4.2.2
Temperature effects on sediment transport capacity 4.2.1.2.3; 4.4.2.2.
Scouring caused by discharged cooling water 4.2.1.2.3; 4.4.2.2
Eutrophication 4.2.1.2.3; 4.4.2.2
Discharge of chlorine or other biocides 4.2.1.2.4; 4.4.2.2
Discharge of sanitary wastes and minor chemical spills 4.2.1.2.4; 4.4.2.2
Discharge of other metals in waste water 4.2.1.2.4; 4.3.2.2; 4.4.2.2
Water-use conflicts (plants with once-through cooling systems) 4.2.1.3

Aquatic Ecology (for all plants)

Accumulation of contaminants in sediments or biota 4.2.1.2.4; 4.3.3; 4.4.3; 4.4.2.2
Entrainment of phytoplankton and zooplankton 4.2.2.1.1; 4.3.3; 4.4.3
Cold shock 4.2.2.1.5; 4.3.3; 4.4.3
Thermal plume barrier to migrating fish 4.2.2.1.6; 4.4.3
Distribution of aquatic organisms 4.2.2.1.6; 4.4.3
Premature emergence of aquatic insects 4.2.2.1.7; 4.4.3
Gas supersaturation (gas bubble disease) 4.2.2.1.8; 4.4.3
Low dissolved oxygen in the discharge 4.2.2.1.9; 4.3.3; 4.4.3
Losses from predation, parasitism, and disease among organisms exposed to sublethal stresses 4.2.2.1.10; 4.4.3
Stimulation of nuisance organisms 4.2.2.1.11; 4.4.3

Human Health

Microbial organisms 4.3.6
Noise 4.3.7

Category 2 issues related to cooling system operation during the renewal term that are applicable to ONS are discussed in the sections that follow. These issues are listed in Table 4-2.

Table 4-2. Category 2 Issues Applicable to the Operation of the ONS Cooling System During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections 10 CFR 51.53(c)(3)(ii) Subparagraph SEIS Section

Aquatic Ecology (for plants with once-through and cooling pond heat dissipation systems)

Entrainment of fish and shellfish in early life stages 4.2.2.1.2; 4.4.3 B 4.1.1
Impingement of fish and shellfish 4.2.2.1.3; 4.4.3 B 4.1.2
Heat shock 4.2.2.1.4; 4.4.3 B 4.1.3
Microbiological organisms (human health) 4.3.6 G 4.1.4

4.1.1 Entrainment of Fish and Shellfish in Early Life Stages

For plants with once-through cooling systems, entrainment of fish and shellfish in early life stages into cooling water systems associated with nuclear power plants is considered a Category 2 issue, requiring a site-specific assessment before license renewal.

The staff reviewed NPDES Permit #SC0000515 (that governs the release of effluents by Oconee Nuclear Power Station into the receiving waters of Lake Keowee and to the Keowee Hydro Station's tailrace). The current permit was issued on September 29, 1999, and expires on September 30, 2003.

The EPA-issued NPDES permit effective February 18, 1975, required Oconee to implement a program to monitor entrainment through plant intake structures in accordance with Section 316(b) of the Federal Water Pollution Control Act (FWPCA), also known as the Clean Water Act. Rates of entrainment were studied and summarized in a letter report to the EPA on March 24, 1976 (letter from W.D. Adair, 1976, in Duke 1999a). The summary report, which Duke considers its 316(b) demonstration, indicated that no fish eggs or larvae were collected after extensive sampling that began in May 1973.

While no formal record of acceptance by the EPA of this 316(b) demonstration has been identified, the EPA did issue a modified NPDES permit on August 30, 1976, that deleted requirements to monitor entrainment through plant intake structures (Duke 1998a). No further studies or analyses were required in subsequent NPDES permits.

However, while the EPA was reviewing the 316(b) demonstration report, Duke was conducting additional larval entrainment studies weekly from March through August 1976 to document the efficiency of the skimmer wall to reduce entrainment of larval fish (Olmsted and Adair 1981). Standing crops of fish larvae in the intake canal and in Lake Keowee were compared to numbers of fish larvae entrained under the skimmer wall and through the condensers. Overall, the density of fish larvae entrained was always less than 1 percent of that noted in concurrent lake sampling at ONS. The difference in larvae densities between the lake and intake canal was attributed to the skimmer wall's depth being below the thermocline during the spawning season. Thus, this study served to reinforce the results of the 316(b) demonstration.

On March 2, 1979, the staff issued Amendments to the Licenses for Oconee Units 1, 2, and 3 that deleted the aquatic surveillance and special studies programs because the Environmental Impact Appraisal performed for this amendment concluded the impact of Oconee on the aquatic environment was within the bounds of the final environmental statement (FES) and that the special study programs were no longer necessary (letter from R.W. Reid, March 1979 in Duke 1999a).

The staff has reviewed the available information relative to potential impacts of the cooling water intake system's entrainment of fish and shellfish in early life stages. Based on this review, the staff has concluded that the potential impacts are SMALL, and mitigation is not warranted.

4.1.2 Impingement of Fish and Shellfish

For plants with once-through cooling systems, impingement of fish and shellfish on debris screens of cooling water systems associated with nuclear power plants is considered a Category 2 issue, requiring a site-specific assessment before license renewal. Impingement of shellfish is not an issue because there is no significant population of endemic shellfish species in the vicinity of ONS (Duke 1999b).

The staff reviewed NPDES Permit #SC0000515, which was issued on September 29, 1999, and expires on September 30, 2003. This permit governs the release of effluents by Oconee Nuclear Power Station into the receiving waters of Lake Keowee and to the Keowee River (at the location of the Keowee Hydro Station's tailrace).

An early EPA-issued NPDES permit effective February 18, 1975, required Oconee to implement a program to monitor impingement of fish on plant intake structures in accordance with Section 316(b) of the Clean Water Act. Rates of impingement were studied and summarized in a letter report to the EPA on March 24, 1976 (letter from W.D. Adair 1976 in Duke 1999a). The summary report indicated that

    ...impingement of game and sport fish has been low. Small bluegill and yellow perch were the fishes most commonly impinged prior to the introduction of threadfin shad into Lake Keowee. Since threadfin have become established, we have a situation which is typical of cooling reservoirs in the southeastern U.S. Threadfin comprise the majority of those fish impinged (over 90 percent on most occasions) and contribute most to seasonal trends - i.e., high impingement rates in winter and low in summer. In view of the species and number of fishes affected it is doubtful that impingement at Oconee exerts any significant impact on resident fish populations of Lake Keowee.

These findings on impingement were drawn largely from a study conducted by Duke (Edwards et al. 1976) that determined the number of finfish impinged on stationary screens at Oconee Nuclear Station between July 1974 and May 1975. Six screens (two screens per unit and 25 percent of total screen area) were removed and inspected at 2-week intervals. Over the entire study period, 241,697 fish were collected on representative screens.

Overall, species composition found impinged during the study included threadfin shad, Dorosoma petenense (49.3 percent), yellow perch, Perca flavescens (2.5 percent), and bluegill, Lepomis macrochirus (1.4 percent), even though threadfin shad were only introduced to Lake Keowee in February 1974 and did not show up in impingement samples until November 1974. Many fish collected during the study were unidentifiable (46.8 percent), but were suspected to be almost entirely threadfin shad (Duke 1998a, Attachment B), and the remainder were miscellaneous species that comprised an insignificant portion of the impingement samples.

SCUBA divers inspected all 24 screens at ONS between September 16 and 19, 1974, to ensure that impingement rates were similar for all screens and that subsampling at representative screens from each unit was realistic for estimating total impingement. Significant differences among screens was not apparent (Duke 1998a, Attachment B). Electrofishing, gill-net, and rotenone data were used to compare species composition throughout the lake to species found on intake screens. All species collected on the intake screens were represented in field collection samples, but 33 species collected in the field were not observed on intake screens. This suggests that susceptibility to impingement was, in part, species specific.

Impacts from impingement are determined relative to recreationally or commercially important species. A creel census conducted in 1973 indicated that largemouth bass (Micropterus salmoides), bluegill, and crappie (Pomoxis spp.) were the most important sport fish taken from Lake Keowee. Data on angler effort and harvest rates collected over a period from 1974 to 1993 (Barwick et al. 1995) confirmed that largemouth bass remained the most important sportfish in the reservoir and that sunfish (Lepomis spp., including bluegill) and crappie were the only other species that contributed in a significant way to the reservoir's sport fishery. Sampling conducted from 1972 to 1993 indicated that these species were also the most common sportfish in the reservoir (Duke 1995). Occasional impingement of these species is not expected to produce population-level effects. Again, only 1.4 percent of fish impinged in the 1974-75 study (Edwards et al. 1976) were bluegill. Other sunfish species, largemouth bass, and crappie were included in the "miscellaneous" category that made up less than 0.3 percent of the total fish impinged. Threadfin shad were the most frequently impinged species (49.3 percent). They are a forage fish species and are not considered important by either recreational or commercial standards.

Over the years, NPDES permits issued to Duke for ONS gradually reduced requirements for evaluating impingement because research indicated that important aquatic species were not being adversely impacted. No correspondence could be located indicating EPA's formal approval of the study. However, the EPA issued a modified NPDES permit on August 30, 1976, that deleted requirements to monitor impingement through plant intake structures (Duke 1998a). No further studies or analyses were required in subsequent NPDES permits. On March 2, 1979, the staff issued Amendments to the Licenses for Oconee Units 1, 2, and 3 that deleted the aquatic surveillance and special studies programs because the Environmental Impact Appraisal performed for this amendment concluded that the impact of Oconee on the aquatic environment was within the bounds of the FES and that the special study programs were no longer necessary (letter from R.W. Reid, March 1979 in Duke 1999a).

Although special studies were no longer required, additional impingement studies were performed from January through March 1990 (Barwick 1990). During this period of weekly sampling, only three fish species were found in impingement samples, none of which are considered important sportfish species. Threadfin shad comprised 91.5 percent of the total fish impinged, blueback herring (Alosa aestivalis) comprised 8.4 percent, and yellow perch comprised 0.1 percent. The numbers of fish impinged were 2.6 times the number of impinged fish that were reported by Edwards et al. (1976) and were estimated to represent 11.1 percent of the pelagic fish population in the Keowee Reservoir. Although threadfin shad are not commercially or recreationally important, the high rate of impingement merits some discussion. Mobile hydroacoustic surveys conducted during spring and fall 1989, 1990, 1996, and fall 1997 show a pattern in threadfin shad population dynamics that helps explain the high percentage of impinged fish (Duke 1999a).

Table 4-3 (Duke 1999a) shows the fluctuation in pelagic fish populations (approximately 51 percent threadfin shad and 49 percent blueback herring) between spring and fall surveys.

Table 4-3. Fluctuation in Pelagic Fish Populations Between Spring and Fall Surveys

Numbers of Small Pelagic Fish (millions) Date of Mobile Hydroacoustic Survey
3.0 March 1989
4.9 November 1989
2.6 March 1990
14.1 November 1990
12.5 March 1996
28.2 November 1996
3.7 November 1997

The estimated numbers of small pelagic fish are always lower in spring than fall, following a period of high winter mortality. Blueback herring are not overly susceptible to cold temperatures, but threadfin shad become stressed at temperatures less than 10C (50F) and exhibit complete mortality at 4C (39F) (Griffith 1978). Areas of Keowee Reservoir often drop below 10C (50F) during the winter, severely weakening large numbers of threadfin shad that die or become stressed and unable to resist intake currents. According to the seasonal study conducted by Edwards et al. (1976), 88 percent of all threadfin shad impingement at Oconee occurred between January and March. However, as indicated by the hydroacoustic survey results showing seasonal population fluctuations, threadfin shad have a high fecundity and generally expand their population considerably by fall so long as an adequate number of spawners survived the winter. Edwards et al. (1976) concluded that "the impingement of threadfin shad at (Oconee) does not appear to be a major cause of mortality but is rather an indication of natural mortality of the species."

Based on these data, the staff has reviewed the available information relative to potential impacts of the cooling water intake system on the impingement of fish and shellfish, and concludes that the potential impacts are SMALL, and mitigation is not warranted.

4.1.3 Heat Shock

For plants with once-through cooling systems, the effects of heat shock are listed as a Category 2 issue and require plant-specific evaluation before license renewal.

The staff reviewed NPDES Permit #SC0000515, which was issued on September 29, 1999, and expires on September 30, 2003 (as discussed in Section 4.1.1). This permit governs the release of effluents by Oconee Nuclear Power Station into the receiving waters of Lake Keowee and to the Keowee River at the location of the tailrace to the Keowee Hydro Station.

The staff also reviewed the results of a 316(a) demonstration that Duke submitted in January 1995 (Duke 1999a). Based on the study, the SCDHEC granted a 316(a) variance. Duke submitted a reapplication in March 1998 and supporting documentation in May 1998 to the SCDHEC requesting a continuation of the variance.

ONS complies with State standards and has an approved NPDES permit and 316(a) variance. Under such circumstances, pursuant to 10 CFR 51.53(c)(3)(ii)(B), no further assessment of heat shock is required. Thus, the staff concludes that potential heat shock impacts resulting from operation of the plant's cooling water discharge system to the aquatic environment on or in the vicinity of the site are SMALL, and mitigation is not warranted.

4.1.4 Microbiological Organisms (Human Health)

For plants discharging cooling water to cooling ponds, lakes, canals, or small rivers, the effects of microbiological organisms on human health are listed as a Category 2 issue and require plant-specific evaluation before license renewal.

ONS has a once-through cooling system that uses Lake Keowee as the cooling source. The Keowee and Little Rivers were impounded to form Lake Keowee. The combined flow rate for the Keowee and Little Rivers is lower than the 9 × 1010 m3 per year (3.15 × 1012 ft3 per year) specified in 10 CFR 51.53(c)(3)(ii)(G). This low flow rate raises a concern from the standpoint of the potential for enhancement of thermophylic microorganisms such as Naegleria fowleri. This type of organisms could be a potential health concern for members of the public swimming in the cooling source (Duke 1998a).

Although Lake Keowee is a popular site for water-based recreational activities, including swimming and water skiing, these activities are dispersed throughout the lake, rather than being concentrated in specific areas such as near the plant. In addition, the nearest private pier located on the Keowee River arm of the lake is 1300 m (4200 ft) from the discharge structure.

In a letter included with the ER (Duke 1998a), the State toxicologist at the SCDHEC indicated that there "seems to be no significant threat to off-site persons near such heated recreational waters [from operation of ONS] ."

Although there is a potential for deleterious thermophylic microorganisms to be associated with the cooling system, the actual hazard to public health has not been documented or substantiated. The results of analyses and evaluations, including the results of consultation with the State Public Health Department, indicate that the impact of deleterious microbiological organisms during continued operation of the plant during the renewal term are expected to be SMALL, and mitigation is not warranted.


4.2 Transmission Lines


[ Prev | Next | Top of file ]

The FES discussed five transmission lines with a total length of 528 km (330 mi) that connect the plant to the Duke Energy Transmission System. They were constructed concurrently with the construction of Oconee and the Keowee-Toxaway Project and connect both Oconee and the Keowee-Toxaway Project hydro plants to the Duke Energy Transmission System.

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to the ONS transmission lines are listed in Table 4-4. Duke stated in its ER that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of those issues, the GEIS concluded that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

Table 4-4. Category 1 Issues Applicable to the ONS Transmission Lines During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section
Terrestrial Resources
Power line right-of-way management (cutting and herbicide application) 4.5.6.1
Bird collisions with power lines 4.5.6.2
Impacts of electromagnetic fields on flora and fauna (plants, agricultural crops, honeybees, wildlife, livestock) 4.5.6.3
Floodplains and wetland on power line right-of-way 4.5.7
Air Quality
Air quality effects of transmission lines

4.5.2

Land Use
Onsite land use 4.5.3
Power line right-of-way 4.5.3

A brief description of the staff's review and GEIS conclusions, as codified in Table B-1, for each of these issues follows:

There is one Category 2 issue related to transmission lines, and another issue related to transmission lines is being treated as a Category 2 issue. These issues are listed in Table 4-5. They are discussed in Sections 4.2.1 and 4.2.2.

Table 4-5. Category 2 Issues Applicable to the ONS Transmission Lines During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section 10 CFR 51.53(c)(3)(ii) Subparagraph SEIS Section
Human Health
Electromagnetic fields, acute effects (electric shock) 4.5.4.1 H 4.2.1
Electromagnetic fields, chronic effects 4.5.4.2 NA 4.2.2

4.2.1 Electromagnetic Fields - Acute Effects

In the GEIS, the Commission found that without a review of the conformance of each nuclear plant transmission line with NESC criteria, it is not possible to determine the significance of the electric shock potential. Evaluation of individual plant transmission lines is necessary because the issue of electric shock safety was not addressed in the licensing process for some plants. For the other plants, some may have chosen to upgrade line voltage or land use in the vicinity of transmission lines that may have been changed. To comply with 10 CFR 51.53(c)(3)(ii)(H), the applicant must provide an assessment of the potential shock hazard if the transmission lines that were constructed for the specific purpose of connecting the plant to the transmission system do not meet the recommendations of the National Electric Safety Code (NESC) for preventing electric shock from induced currents.

In the ER, Duke stated that the transmission lines that connect Units 1 and 2 to the 230 kV switching station and the lines that connect Unit 3 to the 525 kV switching station meet the vertical clearance requirement specified in the 1997 edition of NESC (1997). Duke states further that the transmission lines constructed concurrently with the Oconee and the Keowee-Toxaway Project are part of the Duke Energy Transmission System. These transmission lines were constructed to the standards of NESC, 6th edition, published in November 1961. According to the ER, there have been no upgrades in line voltage on these transmission lines since they were constructed. Duke reviewed the vertical clearances of the 528 km (330 mi) of transmission lines attributed to Oconee in the FES (AEC 1972) using the 1997 edition of NESC and determined that all clearances exceeded the minimum requirements of the 1997 NESC (Duke 1999a).

Based on the above, the staff concludes that the impact of the potential for electrical shock is SMALL, and mitigation is not warranted.

4.2.2 Electromagnetic Fields - Chronic Effects

In the GEIS, the chronic effects of electromagnetic fields from power lines were given a finding of "not applicable" rather than a Category 1 or 2 designation until a scientific consensus is reached on the health implications of these fields.

The potential for chronic effects from these fields continues to be studied and is not known at this time. The National Institute of Environmental Health Sciences (NIEHS) directs related research through the U.S. Department of Energy (DOE). A recent report (NIEHS 1999) includes the following paragraph:

The NIEHS concludes that ELF-EMF [extremely low frequency-electromagnetic field] exposure cannot be recognized as entirely safe because of weak scientific evidence that exposure may pose a leukemia hazard. In our opinion, this finding is insufficient to warrant aggressive regulatory concern. However, because virtually everyone in the United States uses electricity and therefore is routinely exposed to ELF-EMF, passive regulatory action is warranted such as a continued emphasis on educating both the public and the regulated community on means aimed at reducing exposures. The NIEHS does not believe that other cancers or non-cancer health outcomes provide sufficient evidence of a risk to currently warrant concern.

This statement is not sufficient to cause the staff to change its position with respect to the chronic effects of electromagnetic fields. The staff considers the GEIS finding of "not applicable" still appropriate and will continue to follow developments on this issue.


4.3 Radiological Impacts of Normal Operations


[ Prev | Next | Top of file ]

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to ONS with regard to radiological impacts are listed in Table 4-6. Duke stated in its ER that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of those issues, the GEIS concluded that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

Table 4-6. Category 1 Issues Applicable to Radiological Impacts of Normal Operations During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section
Human Health
Radiation exposures to public (license renewal term) 4.6.2
Occupational radiation exposures (license renewal term) 4.6.3

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, for each of these issues follows:


4.4 Socioeconomic Impacts of Plant Operations During the License Renewal Period


[ Prev | Next | Top of file ]

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to socioeconomic impacts during the renewal term are listed in Table 4-7. Duke stated in its ER (Duke 1998a) that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of those issues, the GEIS concluded that the impacts are small, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

Table 4-7. Category 1 Issues Applicable to Socioeconomics During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections
Socioeconomics
Public services: public safety, social services, and tourism and recreation 4.7.3; 4.7.3.3; 4.7.3.4; 4.7.3.6
Public services: education (license renewal term) 4.7.3.1
Aesthetic impacts (license renewal term) 4.7.6
Aesthetic impacts of transmission lines (license renewal term) 4.5.8

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, for each of these issues follows:

Table 4-8 lists the Category 2 socioeconomic issues, which require plant-specific analysis and environmental justice, which was not addressed in the GEIS.

4.4.1 Housing Impacts During Operations

In determining housing impacts, the applicant chose to follow Appendix C of the GEIS (NUREG-1437), which presents a population characterization method that is based on two factors, "sparseness" and "proximity" (GEIS Section C.1.4). Sparseness measures population density within 32 km (20 mi) of the site, and proximity measures population density and city size within 80.5 km (50 mi). Each factor has categories of density and size (GEIS Table C.1), and a matrix is used to rank the population category as low, medium, or high (GEIS, Figure C.1). ONS was selected by the NRC to be evaluated as a potential socioeconomic case study site. The results of this evaluation, published in the GEIS, classifies the current ONS population as "medium" (GEIS Table C.2).

Table 4-8. Category 2 Issues Applicable to Socioeconomics During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section 10 CFR 51.53(c)(3)(ii) Subparagraph SEIS Section
Socioeconomics
Housing impacts 4.7.1 I 4.4.1
Public services: public utilities 4.7.3.5 I 4.4.2
Offsite land use (license renewal term) 4.7.4 I 4.4.3
Public Services, transportation 4.7.3.2 J 4.4.4
Historic and archaeological resources 4.7.7 K 4.4.5
Environmental Justice
Environmental Justice Not addressed   4.4.6

As described in Section 2.2.8, the Tri-County (Oconee, Pickens, and Anderson) area around ONS is not subject to growth control measures that effectively limit housing development, although Oconee County in particular is attempting to steer the growth toward the center of the county, where the infrastructure is most completely developed. In 10 CFR Part 51, Subpart A, Appendix B, Table B-1, NRC concluded that impacts on housing availability are expected to be of small significance at plants located in a "medium" population area where growth control measures are not in effect. ONS is located in a medium population area and is not located in an area where growth control measures limit housing development, so housing impacts would be expected to be small, even if there were plant-related increases in population.

Small impacts result when no discernable change in housing availability occurs, changes in rental rates and housing values are similar to those occurring statewide, and no housing construction or conversion occurs. Although significant housing impacts are expected in all three counties as a result of population growth, it will be difficult to discern the impact from license renewal activities. Although the GEIS assumed an additional staff of 180 permanent workers during the license renewal period, Duke, in the ER, indicated that they "have not identified any increases in staffing related to license renewal-related programs." The staff has reviewed the available information relative to housing impacts. Because Duke expects no increase in staffing levels, there should be no discernable change in housing availability. Therefore, there will be no impact on economic development from license renewal and the staff has concluded that the impact on housing during the license renewal period is SMALL, and mitigation is not warranted.

4.4.2 Public Services: Public Utility Impacts During Operations

Impacts on public utility services are considered small if there is little or no change in the ability of the system to respond to the level of demand, and thus there is no need to add capital facilities. Impacts are considered moderate if overtaxing of service capabilities occurs during periods of peak demand. Impacts are considered large if existing levels of service (e.g., water or sewer services) are substantially degraded, and additional capacity is needed to meet ongoing demands for services. The GEIS indicates that, absent new significant information to the contrary, the only impacts on public utilities that could be significant are impacts on public water supplies. The staff believes that, in view of the expected population increase in the three counties, there may be reason to add significant public services and infrastructure other than water supply during the next 40 years. None of the increase would be due to the impact of additional ONS workers because no need for additional workers has been identified.

Analysis of impacts to the public water supply system considered both plant demand and plant-related population growth. Section 2.2.2 describes the plant's permitted withdrawal rate and the plant's actual use of water. The applicant does not expect plant demand to have a direct effect on water resources.

As described in Section 2.2.8, Walhalla and Seneca in eastern Oconee County have some water plant capacity problems, but only Walhalla is actually limited by the water source (Coneross Creek). Walhalla is considering construction of a new water treatment plant. Seneca draws drinking water from Lake Keowee, which is considered adequate. Because ONS obtains its water from an adequate renewable surface water source, and no increase in population is expected as a result of the renewal of the ONS operating license, no impact is expected from license renewal on water supplies. The staff concludes that the impact on water supply is SMALL, and mitigation is not warranted.

4.4.3 Offsite Land Use During Operations

Land use in the vicinity of a nuclear power plant may change as a result of plant-related population growth. It is noted in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that significant changes in land use may be associated with population and tax revenue changes resulting from license renewal. However, Section 3.7.5 of the GEIS notes that if the plant-related increase in population is less than 5 percent of the study area's total population and if plant total tax payments are small relative to the community's total revenue, new population-driven and tax-driven land-use changes during the plant's license renewal term would be small, especially if the community has pre-established patterns of development and has provided adequate public services to support and guide development.

The analysis of offsite land use during the renewal term has two components, population-driven changes in offsite land use and tax-driven changes in offsite land use. No plant-related, population-driven changes in land use are expected during the license renewal term because no increase in employment is expected.

Oconee County is the only jurisdiction that taxes ONS directly, and it is the principal jurisdiction that receives direct tax revenue as a result of ONS's presence. Because there are no major refurbishment activities and no new construction as a result of the license renewal, no new sources of plant-related tax payments are expected that could significantly influence land use in Oconee County. However, continued operation of the plant would provide a significant continuing source of tax revenues to Oconee County. As discussed in Section 2.8, the applicant is expected to pay $22.3 million in property taxes to Oconee County in 1998-99. This payment represented about one-third of the county budget and has a substantial, positive impact on the fiscal condition of Oconee County.

The staff has determined that the significance of project-related tax payments are moderate if the payments to a jurisdiction are between 10 and 20 percent of the total tax revenue of the jurisdiction, and large if the percentage is greater than 20 percent (GEIS). Using these criteria, ONS tax payments, representing around 33 percent of the total Oconee County budget, are of large significance. If the tax-related revenues are medium to large relative to the jurisdiction's total revenue, tax-driven land-use changes would most likely be moderate if the community has no pre-established patterns of development (i.e., land-use plans or controls), or has not provided adequate public services to guide land-use changes in the past (GEIS). The staff defined the magnitude of land-use changes as follows:

Oconee County has experienced significant population growth and moderate land-use changes. The growth is not directly related to the presence of the ONS. Other factors, such as development of Lake Keowee recreational property, industrial growth, proximity to Greenville and Anderson, and less stringent land-use, zoning, and development regulations compared to surrounding counties clearly play a role. Oconee County has not adopted land codes or ordinances nor does it enforce a minimum housing code (Talbert & Bright 1996). However, Oconee County has well established patterns of development and has public services in place to support development, which is being directed toward the center of the county. In combination, these two factors would be expected to result in SMALL land-use impacts from ONS-related taxes.

Continuation of Oconee County's tax receipts from ONS keeps tax rates below what they otherwise would have to be to fund the county's government and also provides for a higher level of public infrastructure and services than otherwise would be possible. This enhances the county's attractiveness as a place to live and tends to accelerate the conversion of open space to residential and commercial uses. On the other hand, the presence of Duke's real estate arm as a major landowner has provided a considerable degree of discipline on development in the county.

Based on this review of the issues, the staff concludes that the net impact of plant-related population increases and tax receipts is likely to be SMALL. While the tax receipts are large enough to result in moderate impacts on land use, Oconee County has a conservative approach to providing water and sewer that limits upgrades and could slow future economic development except in areas already served. In addition, while the relatively low taxes and high levels of public service afforded by ONS-related tax receipts tend to draw population growth to the County, these same receipts make possible formal tax relief programs that favor open space or land-use control programs if such programs are deemed necessary in the future. Additional mitigation does not appear to be warranted.

4.4.4 Public Services: Transportation Impacts During Operations

On October 4, 1999, 10 CFR 51.53(c)(3)(ii)(J) and 10 CFR Part 51, Subpart A, Appendix B, Table B-1 were revised to clearly state that "Public Services: Transportation Impacts During Operations" is a Category 2 issue (see NRC 1999a for more discussion of this clarification). This issue is treated as such in this final SEIS.

Significant population growth is expected in all three counties in the study area by 2034, as was discussed in Section 2.2.8 of this report. However, none of this expected growth will be due directly to increases in employment at ONS. It may be argued that the industrial tax base afforded by ONS makes the county a more affordable and pleasant place to live and indirectly increases population, but even this indirect impact is likely to be fairly small and difficult to predict. Future general population increase likely will increase highway congestion at specific locations, but the expected magnitude of impact of ONS on this service degradation is SMALL and, thus, no mitigation is warranted.

4.4.5 Historical and Archaeological Resources

Because the Duke license renewal application (Duke 1998a) covering an additional 20 years of operation of the ONS does not include plans for future land disturbances or structural modifications beyond routine maintenance activities at the plant, there would be no identifiable adverse effects to known historical and archaeological resources. Consultation between the license renewal applicant and the South Carolina State Historic Preservation Office resulted in a determination by the State office that no known historical properties included in or eligible for inclusion in the National Register of Historic Places would be affected by the proposed action.

Continued operation of the power plant and protection of the natural landscape and vegetation within the site boundaries would have a beneficial effect in that either known or undiscovered resources would receive de facto protection for the term of the license renewal period, being located in an undisturbed area with secured access. Duke has assisted in conservation and security of the adjacent National Register property, the Old Pickens Church and cemetery. This assistance will continue to enhance long-term preservation of that property.

Notwithstanding that Duke does not plan future land disturbances or structural modifications beyond routine maintenance at the plant, there is a possibility that undiscovered and/or unrecorded prehistoric and historic period archaeological sites remain on the 210-ha (510-acre) plant site. Accordingly, additional care should be taken during normal operational or maintenance conditions to ensure that cultural resources are not inadvertently impacted. These activities may include not only operation of the plant itself, but also land management-related actions such as recreation, wildlife habitat enhancement, or maintaining/upgrading access roads throughout the plant site. To ensure that care is taken to protect cultural resources that may be encountered during construction or other land-disturbing activities, the ONS site environmental work practices have been revised. If archeological sites are identified during land-disturbing activities, land-disturbing activities will stop, and the State Historic Preservation Office will be contacted to determine the appropriate steps to be taken before resuming the activities.

The staff concludes that impacts on historical and archaeological resources is SMALL, and mitigation is not needed.

4.4.6 Environmental Justice

Environmental justice refers to a Federal policy in which Federal actions should not result in disproportionately high and adverse impacts on low-income or minority populations. A minority population is defined to exist if the percentage of minorities within the census blocks exceeds the percentage of minorities in the entire state of South Carolina by 10 percent, or if the percentage of minorities within the census block is at least 50 percent. For census blocks within the states of Georgia or North Carolina, the percentage of minorities is compared to the percentage of minorities in the respective state. Executive Order 12898 (59 FR 7629) directs Federal executive agencies to consider environmental justice under NEPA, and the Council on Environmental Quality (CEQ) has provided guidance for addressing environmental justice under NEPA (CEQ 1997). Although it is not subject to the executive order, the Commission has voluntarily committed to undertake environmental justice reviews. Specific guidance is provided in Attachment 4 to NRR (Nuclear Reactor Regulation) Office Letter No. 906, Revision 1: Procedural Guidance for Preparing Environmental Assessments and Considering Environmental Issues (NRC 1996b).

The scope of the review as defined in NRR Office Letter No. 906, Rev. 1 (NRC 1996b) should include an analysis of impacts on low-income and minority populations, the location and significance of any environmental impacts during operations on populations that are particularly sensitive, and any additional information pertaining to mitigation. The descriptions to be provided by this review should be of sufficient detail to permit subsequent staff assessment and evaluation of specific impacts, in particular whether these impacts are likely to be disproportionately high and adverse, and to evaluate the significance of such impacts.

Air, land, and water resources within about 80 km (50 mi) of ONS were examined. Within that area, a few potential environmental impacts could affect human populations; all of these were considered small. These include

To decide whether any of these impacts could be disproportionate, the staff examined the geographic distribution of minority and low-income populations recorded during the 1990 Census (DOC 1991), supplemented by field inquiries to the local planning departments in Oconee, Pickens, and Anderson Counties, and to social service agencies in the three counties. The staff focused this portion of the review on the geographic areas most likely to experience the impacts discussed above, i.e., the three closest surrounding counties. This area is referred to as the study area.

Generally speaking, minority populations are a small, dispersed, and declining proportion of the study area's population. Figure 4-1, taken from the 1990 Census (DOC 1991) shows the geographic distribution of minority populations within the 80-km (50-mi) radius of the plant. Minority populations are located primarily in Greenville and Anderson. However, a few scattered census block groups showed a significant concentration of minority individuals in the Seneca and Clemson areas. Figure 4-1 indicates that minority populations in general are either relatively well-mixed into the majority population, or concentrations of minority individuals are too small to be caught in the census detail. This is consistent with the results of field interviews.

Figure 4-2, also taken from the 1990 Census (DOC 1991) shows the geographic distribution of low-income populations within the 80-km (50-mi) radius of the plant. The cross-hatched census blocks show areas where the percentage of households below the poverty level is 10 percent or more greater than the percentage of households below the poverty level in the entire state of South Carolina for those census blocks within the state of South Carolina. It also includes census blocks where the percentage of households below the poverty level exceeds 50 percent. For census blocks within the states of Georgia or North Carolina, the percentage of households below the poverty level is compared to the percentage of households below the poverty level in the corresponding state. The largest concentrations of low-income populations within the 80-km (50-mi) radius are located in North Carolina. Some small groups are scattered throughout the three-county area, although none is within 16 km (10 mi) of ONS. Some of these individuals are known to be ex-sharecroppers effectively engaged in subsistence agriculture. The 1990 Census (DOC 1991) shows concentrations of low-income population at Seneca, Easley, and Clemson, the latter partly due to a large university student population. Low-income housing tends to be concentrated in the Seneca and Clemson area.

Figure 4-1. Geographic Distribution of Minority Populations (shown in shaded areas) Within 80 km (50 mi) of ONS

Examination of the various environmental pathways by which low-income and minority populations could be disproportionately affected reveals no unusual resource dependencies or practices through which these populations could be disproportionately affected. Specifically, no pathways were found through which subsistence agriculture was significantly affected. In general, the prevailing atmospheric transport direction from the ONS site is toward the northeast, thus missing most census blocks showing minority and low-income populations. Therefore, the impact is SMALL, and no special mitigation actions are warranted.

Figure 4-2. Geographic Distribution of Low-Income Populations (shown in shaded areas) Within 80 km (50 mi) of ONS


4.5 Groundwater Use and Quality


[ Prev | Next | Top of file ]

A Category 1 issue in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, is applicable to ONS groundwater use and quality and is listed in Table 4-9. Duke stated in its ER that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review.

Table 4-9. Category 1 Issue Applicable to Groundwater Use and Quality During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section
Groundwater Use and Quality
Groundwater use conflicts (potable and service water; plants that use <100 gpm). 4.8.1.1

Therefore, the staff concludes that there are no impacts related to this issue beyond those discussed in the GEIS. For this issue, the GEIS concluded that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, follows.

There are no Category 2 issues related to groundwater use and quality.


4.6 Threatened or Endangered Species


[ Prev | Next | Top of file ]

Threatened or endangered species is listed as a Category 2 issue in 10 CFR Part 51, Subpart A, Appendix B, Table B-1. The issue is listed in Table 4-10.

This issue requires consultation with appropriate agencies to determine whether threatened or endangered species are present and whether they would be adversely affected. Consultation under Section 7 of the Endangered Species Act was initiated by Duke during April 1998 with a request for information to FWS concerning species potentially occurring near ONS. The FWS identified (FWS 1998a) nine listed species known to occur in either Oconee or Pickens Counties and one species that could possibly occur in those counties (see Section 2.2.6). Subsequent to that letter, Duke performed a survey of all of the land within 1.6 km (1 mi) of ONS during May and June of 1998. No Federally listed, proposed, or candidate threatened or endangered species were identified during that survey. The results of the survey were documented for the FWS and the South Carolina Department of Natural Resources (SCDNR) (Duke 1998b; Duke 1998c).

Table 4-10. Category 2 Issue Applicable to Threatened or Endangered Species During the Renewal Term

ISSUE -- 10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Section 10 CFR 51.53(c)(3)(ii) Subparagraph SEIS Section
Threatened or Endangered Species (for all plants)
Threatened or endangered species

4.1

E 4.6

The FWS concurred with Duke's determination that the proposed action will have no effect on listed or proposed endangered or threatened species (FWS 1998b). The SCDNR also concurred with the findings presented in the report submitted by Duke (SCDNR 1998).

Four plant species of concern to the SCDNR were identified within the surveyed area (see Section 2.2.6, Table 2-3). These species were all confined to "natural areas" located toward the periphery of ONS, well away from areas used for normal plant operations.

Based on its review of the applicant's report and their independent analysis, the FWS(10) and the SCDNR concluded that continued operation of the plant under license renewal will have no effect on listed or proposed endangered or threatened species within the immediate vicinity of the ONS.

Federally-listed species are known to occur near the transmission line rights-of-way attributable to the ONS (see Section 2.2.6). Of these, the dwarf-flowered heartleaf and the bunched arrowhead occur within or very near the rights-of-way of the McGuire 525 kV line and the Tiger 230 kV lines, respectively.

The staff submitted a biological assessment to the FWS in a letter dated June 30, 1999 (NRC 1999b). The FWS reviewed the biological assessment and requested more information related to Duke's maintenance practices for the transmission lines and the location of five species: bunched arrowhead, dwarf-flowered heartleaf, smooth coneflower, Schwenitz's sunflower, and mountain sweet pitcher plant. The FWS was concerned about the potential effects from the proposed maintenance of the right-of-way. The FWS conducted field visits to portions of the project area and reviewed the supplemental information provided by Duke. Subsequently, in a letter dated November 4, 1999 (FWS 1999), the FWS concurred with the staff's determination that the renewal of the ONS licenses for a period of 20 years would likely not adversely affect listed species or critical habitat based on the practices and procedures Duke uses to maintain the transmission line rights-of-way. Therefore, it is the staff's determination that the impact on threatened or endangered species of an additional 20 years of maintenance activities for the transmission lines would be SMALL, and further mitigation is not warranted.


4.7 Evaluation of Potential New and Significant Information on Impacts of Operations During the Renewal Term


[ Prev | Next | Top of file ]

The staff has not identified new and significant information on environmental issues listed in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, related to operation during the renewal term. The staff reviewed the discussion of environmental impacts associated with operation during the renewal term in the GEIS and has conducted its own independent review, including the public scoping meetings, to identify issues with significant new information. Processes for identification and evaluation of new information are described in Section 1.0 under License Renewal Evaluation Process.


4.8 Summary of Impacts of Operations During the Renewal Term


[ Prev | Next | Top of file ]

Neither Duke nor the staff is aware of significant new information related to any of the applicable Category 1 issues associated with the ONS operation during the renewal term. Consequently, the staff concludes that the environmental impacts associated with these issues are bounded by the impacts described in the GEIS. For each of these issues, the GEIS concluded that the impacts would be SMALL and that "plant-specific mitigation measures are not likely to be sufficiently beneficial to warrant implementation."

Plant-specific environmental evaluations were conducted for 12 Category 2 issues applicable to ONS operation during the renewal term and for environmental justice. For all 12 issues and environmental justice, the staff concluded that the potential environmental impact of renewal term operations of ONS would be of SMALL significance in the context of the standards set forth in the GEIS and that mitigation would not be warranted.

In addition, the staff determined that a consensus has not been reached by appropriate Federal health agencies that there are adverse effects from electromagnetic fields. Therefore, no evaluation of this issue is required.


4.9 References


[ Prev | Next | Top of file ]

10 CFR 50.51, "Continuation of license."

10 CFR 51.53, "Postconstruction environmental reports."

10 CFR Part 51, Subpart A, Appendix B, "Environmental effect of renewing the operating license of a nuclear power plant."

Barwick, D.H. 1984. Role of fish distribution on estimates of standing crop in a cooling reservoir. North American Journal of Fishery Management 4:308-313.

Barwick, H. 1990. Fish impingement at Oconee Nuclear Station - 1990. Scientific Services, Duke Power Company, Huntersville, North Carolina.

Barwick, D.H., L.E. Miller, W.R. Geddings, and D.M. Rankin. 1995. Fish biomass and angler harvest from a South Carolina cooling reservoir. Proceedings of the Annual Conference of the Southeastern Association of Fish and Wildlife Agencies 49:129-139.

Council on Environmental Quality (CEQ). 1997. Environmental Justice: Guidance Under the National Environmental Policy Act. Council on Environmental Quality, Executive Office of the President, Washington, D.C.

Duke Power Company. 1977. Oconee Nuclear Station Environmental Summary Report 1971-1976, Volumes 1 and 2. Duke Power Company Steam Production Department.

Duke Power Company. 1995. Oconee Nuclear Station 316(a) Demonstration Report.

Duke Energy Corporation. 1998a. Application for Renewed Operating Licenses, Oconee Nuclear Station, Units 1, 2, & 3. Volume IV - Environmental Report.

Duke Power Company. 1998b. Letter from J. Huff, Duke Power, Charlotte, North Carolina, to Mr. R. L. Banks (FWS, Charleston, South Carolina) June 23, 1998, Conveys the Gaddy Report to FWS.

Duke Power Company. 1998c. Letter from J. Huff, Duke Power, Charlotte, North Carolina to R.E. Duncan, SCDNR. Dated June 23, 1998. Conveys the Gaddy Report to SCDNR.

Duke Energy Corporation. 1999a. Letter from M.S. Tuckman, Duke Energy Corporation to US Nuclear Regulatory Commission. Subject: License Renewal. Response to Requests for Additional Information, Oconee Nuclear Station. Dated March 4, 1999.

Duke Energy Corporation. 1999b. Letter from M.S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Subject: Followup to Staff's Request for Additional Information. Dated December 29, 1998, Related to the Environmental Position of the Review of the License Renewal Application for Oconee Units 1, 2, and 3. Dated May 13, 1999.

Edwards, T.J., W.H. Hunt, L.E. Miller, and J.J. Sevic. 1976. "An evaluation of the impingement of fishes at four Duke Power Company steam-generating facilities." Pages 373-380 in Esch, G.W. and R.W. McFarlane (eds.). Thermal Ecology II. National Technical Information Service, U.S. Department of Commerce, Springfield, Virginia.

Executive Order 12898, "Federal Actions to Address Environmental Justice in Minority and Low-Income Populations." 59 Federal Register 7629-7633 (1994).

Federal Water Pollution Control Act (FWPCA), as amended, 33 USC 1251-1387 (also known as Clean Water Act).

Griffith, J.S. 1978. Effects of low temperature on the survival and behavior of threadfin shad, Dorosoma petenense. Transactions of the American Fisheries Society. 107:63-70.

Hudson and Nichols. 1978. Relation between zooplankton migration and entrainment in a South Carolina cooling reservoir. Waste Heat Management and Utilization Conference, Miami Beach, Florida, December 4-6, 1978.

National Electrical Safety Code (NESC). 1997. Institute of Electrical and Electric Engineers, Inc., New York.

National Institute of Environmental Health Sciences (NIESH). 1999. NIESH Report on Health Effects from Exposure to Power Line Frequency and Electric and Magnetic Fields. NIH Publication No. 99-4493. National Institutes of Health, Research Triangle Park, North Carolina.

Oliver and Hudson. 1987. Thermal and dissolved oxygen characteristics of a South Carolina cooling reservoir. Water Resources Bulletin, American Water Resources Association, 23(2):257-269.

Olmsted, L.L. and W.D. Adair. 1981. Protection of fish larvae at two southeastern power plants using skimmer walls. Research Report PES/81-30. Duke Power Company, Huntersville, North Carolina.

South Carolina Department of Health and Environmental Control (SCDHEC). 1997. Watershed Water Quality Assessment, Savannah and Salkehatchie River Basins. Technical Report No. 003-97, SCDHEC, Columbia, South Carolina.

South Carolina Department of Health and Environmental Control (SCDHEC). 1999. Letter from R. Michael, Gandy, South Carolina. Department of Health and Environmental Control to U.S. Nuclear Regulatory Commission. Subject: status of NPDES and land disposal permits for Oconee Nuclear Station. Dated April 21, 1999.

South Carolina Department of Natural Resources (SCDNR). 1998. Letter from Robert E. Duncan (SCDNR) to Ms. Jennifer Huff (Duke Power). September 24, 1998.

Talbert, S. J. & Bright, Inc., and Holland Consulting Planners, Inc. 1996. Oconee County, South Carolina 1996 Land Use Plan.

U.S. Atomic Energy Commission (AEC). 1972. Final Environmental Statement Related to Operation of Oconee Nuclear Station units 1, 2, and 3. March 1972. Washington, D.C.

U.S. Department of Commerce (DOC). 1991. 1990 Census-Population and Housing; Public Law 94-171 Data, Bureau of the Census. Washington, D.C.

U.S. Fish and Wildlife Service. 1998a. Letter from R. L. Banks (FWS, Charleston, South Carolina) to J. Huff (Duke Power, Charlotte, North Carolina) dated April 17, 1998. Letter provides a list of 9 species in Oconee and Pickens Counties.

U.S. Fish and Wildlife Service. 1998b. Letter dated August 4, 1998 from the Acting Field Supervisor for the Charleston Field Office to Duke Power indicating that continued operation or refurbishment of the Oconee Nuclear Station will have no effect on listed or proposed endangered or threatened species.

U.S. Fish and Wildlife Service. 1999. Letter dated November 4, 1999, from Brian P. Cole to U.S. Nuclear Regulatory Commission. Subject: Biological Assessment for License Renewal at Oconee Nuclear Station.

U.S. Nuclear Regulatory Commission (NRC). 1996a. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1996b. Procedural Guidance for Preparing Environmental Assessments and Considering Environmental Issues, Attachment 4 to NRR Office Letter No. 906, Revision 1. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999a. Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Main Report, Section 6.3--Transportation, Table 9.1, Summary of Findings in NEPA issues for license renewal of nuclear power plants. NUREG-1437, Volume 1, Addendum 1. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999b. Letter from NRC to the U.S. Fish and Wildlife Service. Subject: Biological Assessment. Dated June 30, 1999, Washington, D.C.


5.0 Environmental Impacts of Postulated Accidents


[ Prev | Next | Top of file ]

Environmental issues associated with postulated accidents were discussed in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437 (NRC 1996). The GEIS included a determination of whether the analysis of the environmental issue could be applied to all plants and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristics

(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)

(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that do not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required.

This chapter describes the environmental impacts from postulated accidents that might occur during the license renewal term.


5.1 Postulated Plant Accidents


[ Prev | Next | Top of file ]

A Category 1 issue in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, is applicable to ONS postulated accidents and is listed in Table 5-1. Duke stated in its Environmental Report (ER) (Duke 1998a) that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to this issue beyond those discussed in the GEIS. For this issue, the GEIS concluded that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

Table 5-1. Category 1 Issue Applicable to Postulated Accidents During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections
Postulated Accidents
Design-Basis Accidents (DBAs)

5.3.2; 5.5.1

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, follows.

Design-Basis Accidents (DBAs): Based on information in the GEIS, the Commission found "The NRC staff has concluded that the environmental impacts of design basis accidents are of small significance for all plants." The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of DBAs beyond those discussed in the GEIS.

A Category 2 issue related to postulated accidents that is applicable to ONS is discussed in Table 5-2.

Severe Accidents: Based on information in the GEIS, the Commission found that "The probability weighted consequences of atmospheric releases fallout onto open bodies of water, releases to groundwater, and societal and economic impacts from severe accidents are small for all plants. However, alternatives to mitigate severe accidents must be considered for all plants that have not considered such alternatives."

The staff has not identified any significant new information with regard to the consequences from severe accidents during its independent review of the Duke ER, the Duke Final Safety Analysis Report (FSAR) (Duke 1998b), the staff's site visit, the scoping process, the review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of severe accidents beyond those discussed in the GEIS. However, in accordance with 10 CFR 51.53(c)(3)(ii)(L), the staff has reviewed severe accident mitigation alternatives (SAMAs) for ONS. The results of its review are discussed in Section 5.2.


5.2 Severe Accident Mitigation Alternatives


[ Prev | Next | Top of file ]

It is required in 10 CFR 51.53(c)(3)(ii)(L) that license renewal applicants provide a consideration of alternatives to mitigate severe accidents if the staff has not previously considered SAMAs for the applicant's plant in an EIS or related supplement or in an environmental assessment. The purpose of

Table 5-2. Category 2 Issue Applicable to Postulated Accidents During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections 10 CFR 51.53(c)(3)(ii) Subparagraph SEIS Section
Postulated Accidents
Severe Accidents 5.3.3; 5.3.3.2; 5.3.3.3; 5.3.3.4; 5.3.3.5; 5.4; 5.5.2 L 5.2

this consideration is to ensure that plant design changes with the potential for improving severe accident safety performance are identified and evaluated. SAMAs have not been previously considered for ONS; therefore, the remainder of Chapter 5 addresses those alternatives.

5.2.1 Introduction

Duke submitted an assessment of SAMAs for ONS as part of the ER (Duke 1998a). This assessment was based on Revision 2 of the ONS Probabilistic Risk Assessment (Duke 1997a). Revision 2 constitutes a full-scope Level 3 Probabilistic Risk Assessment (PRA) with the analysis of both internal and external events; the internal events analysis is an updated version of the Individual Plant Examination (IPE) model (Duke 1990), whereas the external events analysis is the same as the Individual Plant Examination for External Events (IPEEE) model (Duke 1995). In identifying and evaluating potential SAMAs, Duke took into consideration the insights and recommendations from earlier risk studies as well as several more recent risk studies. Duke concluded that none of the candidate SAMAs evaluated were cost effective for ONS.

Based on a review of the SAMA assessment, NRC issued a request for additional information (RAI) to Duke by letter dated December 29, 1998 (NRC 1998). Major issues concerned the process used by the license renewal applicant to identify potential SAMAs, the implementation status of numerous enhancements identified in previous studies, and the inclusion of averted onsite costs (AOSC) in Duke's value impact analysis. Duke submitted additional information by letter dated March 4, 1999 (Duke 1999), clarifying the SAMA identification process, the disposition of previously identified design enhancements, and the impact of AOSC on the cost-benefit analysis. This response provided additional clarification regarding the staff's concerns and reaffirmed that none of the SAMAs would be cost-beneficial even when averted onsite costs are included.

The staff's assessment of SAMAs for ONS is provided in Section 5.2.3.2.

5.2.2 Estimate of Risk for ONS

Duke's estimates of the offsite risk at ONS are summarized below. The summary is followed by the staff's review of Duke's risk estimates.

5.2.2.1 Duke Risk Estimates

The ONS PRA model, which forms the basis for the SAMA analysis, is a Level 3 risk analysis; i.e., it includes the treatment of core damage frequency, containment performance, and offsite consequences. The model, which Duke refers to as PRA, Revision 2, consists of an internal events portion, based on an updated version of the IPE (Duke 1990) and an external events portion, based on the current version of the IPEEE (Duke 1995). The calculated total core damage frequency for internal and external events in Revision 2 is 8.9E-5 per year.

Since the ONS PRA is a "living" PRA, the original version of the IPE is being continuously updated to reflect various design and procedural changes, such as those related to the improvements identified in the IPE, to incorporate comments from the "peer review certification" and to reflect up-to-date operational experience. A comparison of risk profiles between the original IPE PRA (which was reviewed by the staff) and the current version (internal events portion of PRA, Revision 2) indicated that there are no significant differences that could change the results of the SAMA analysis by impacting the approach used to identify potential SAMAs or the assessed risk reductions.

Since the issuance of the ONS PRA, Revision 2, report, the total core damage frequency has been recalculated. An IPEEE supplemental report (Duke 1997b) further evaluated the relay chatter issue and updated the seismic core damage frequency (CDF) to be 3.5E-5 per year. A high pressure injection (HPI) reliability study performed in response to an operational event (Duke 1997c) resulted in an updated core damage frequency of 4.3E-5 per year for all events, excluding seismic. Thus, by removing conservative assumptions related to the original seismic analysis and the HPI system, the net effect of these two studies would be to reduce the total CDF for ONS from 8.9E-5 per year to 7.8E-5 per year. Despite the availability of these later studies, the results of the ONS PRA, Revision 2, were used as the basis for the SAMA analysis since the later studies did not include Level 2 and Level 3 calculations and because the net impact of the changes was a small decrease in CDF.

Since Duke's PRA is based on ONS Unit 3, the licensee performed an analysis to determine the applicability of the PRA results to Units 1 and 2 and submitted the analysis as part of the IPE. This analysis concluded that inter-unit differences do not have a significant impact on the PRA results. Most mechanical and electrical systems of Units 1 and 2 are redundant and diverse from those of Unit 3. Those systems and structures that are shared affect all three units in a similar fashion during a severe accident scenario. Because civil structures of Units 1 and 2 are similar to those of Unit 3, external events impact structures and components similarly for each unit. Therefore, the results and insights of the ONS PRA are applicable to all three units.

The Level 2 (also called containment performance) portion of the ONS PRA model, Revision 2, including the plant damage state descriptors, the Containment Event Tree, and the source term binning and containment release categories, is essentially the same as the IPE Level 2 analysis. The offsite (or Level 3) consequence analyses were carried out using the NRC-developed Calculations of Reactor Accident Consequences Version 2 (CRAC2) code, and site-specific data for meteorology, population, and evacuation modeling.

Duke estimated the total CDF for internally and externally initiated events to be 8.9E-5 per year based on Revision 2 of the ONS PRA. The breakdown of the CDF is provided in Table 5-3. External event initiators represent about 71 percent of the total CDF and are dominated by seismic (44 percent of total CDF) and tornado initiators (16 percent of total CDF). External flood and fire initiators together account for about 11 percent of the total CDF. Internal event initiators represent about 29 percent of the total CDF and are dominated by internal flood (11 percent of total CDF), transient (9 percent of total CDF), and loss of coolant accident initiators (8 percent of total CDF). Remaining contributors together account for less than 2 percent of total CDF.

Duke estimated the dose to the population within 80 km (50 mi) of the ONS site from all initiators (internal and external) to be 0.0492 person-sievert (person-Sv) (4.92 person-rem) per year (Duke 1999). The breakdown of the total population dose by containment end-state is summarized in Table 5-4. Of the total risk from all initiators, about 80 percent is due to external events. Interfacing system loss-of-coolant accident (LOCA), containment isolation failure, and late containment failure dominate external event risk (Column 3 of Table 5-4) and total risk from all initiators (Column 4 of Table 5-4) with nearly equal contributions from each. Early containment failure accounts for approximately 10 percent of the total risk from all initiators, with the majority of this contribution coming from external events. Only about 20 percent of the total risk from all initiators is due to internal events, with the majority of this risk from late containment failure (Column 2 of Table 5-4). All other internal event contributors combined account for less than 10 percent of the total risk from all initiators.

5.2.2.2 Review of Duke's Risk Estimates

Duke's estimate of offsite risk at ONS is based on Revision 2 of the ONS PRA. For purposes of this review, the staff considered the ONS study in terms of the following major elements:

Table 5-3. ONS Core Damage Frequencies

Initiating Event Frequency (per year) % of Total CDF (Int+Ext)
External Initiators
Seismic 3.9E-5 44
Tornado 1.4E-5 16
External Flood 5.9E-6 6
Fire 4.5E-6 5
Total External 6.3E-5 71
Internal Initiators
Internal Flood 9.5E-6 11
Transients 8.2E-6 9
LOCAs (small, medium, large) 6.8E-6 8
RPV Rupture 1.0E-6 1
Steam Generator Tube Rupture 4.1E-7 <1
ATWS 1.7E-7 <1
Interfacing systems LOCA 6.9E-9 <1
Total Internal 2.6E-5 29
Total CDF (Internal + External) 8.9E-5 100

The staff reviewed each of these analyses to determine the acceptability of Duke's risk estimates for the SAMA analysis, as summarized below.

The staff's review of the ONS IPE is described in an evaluation report dated April 1, 1993 (NRC 1993). In that review, the staff evaluated the methodology, models, data, and assumptions used to estimate CDF and characterize containment performance and fission product releases. The staff concluded that Duke's analysis met the intent of Generic Letter 88-20 (NRC 1988); that is, the IPE was of adequate quality to be used to look for design or operational vulnerabilities. Although the staff reviewed certain aspects of the IPE in more detail than others, the review primarily focused on the licensee's ability to examine ONS for severe accident vulnerabilities and not specifically on the detailed findings or

Table 5-4. Breakdown of Population Dose by Containment End-State

(Total Dose = 4.92 person-rem per year)

Containment End-State % of Total Dose Internal Initiators % of Total Dose External Initiators % of Total Dose All Initiators
Steam Generator Tube Rupture 2.7 <0.1 2.8
Interfacing System LOCA 0.8 24.4 5.2
Containment Isolation Failure 0.5 22.0 22.5
Early Containment Failure 3.7 6.5 10.2
Late Containment Failure 9.4 22.8 32.2
Basemat Melt Through 2.2 4.6 6.8
No Containment Failure <0.1 0.2 0.3
Total 19.3 80.7 100

quantification estimates. However, ONS's risk profile and important IPE findings compare well to those of other Babcock & Wilcox plants (NUREG-1560) (NRC 1997a), and any differences are well understood. Overall, the staff believes that the ONS PRA is of adequate quality to be used as a tool in searching for areas with high potential for risk reduction and to assess such risk reductions, especially when the PRA models are used in conjunction with insights, such as those from risk importance, sensitivity, and uncertainty analyses.

The staff's review of the applicant's IPEEE is currently underway. The preliminary results did not identify any significant shortcomings or deficiencies. A limited review of the Duke submittal finds that the overall method, scope, and level of detail are generally comprehensive. The staff also notes that the Duke IPEEE has been subjected to both internal and external peer reviews. Based on these findings, the staff concludes that the external events portion of the ONS PRA provides an acceptable platform for identifying potential SAMAs and for assessing risk reductions.

The staff reviewed the process used by Duke to extend the containment performance (Level 2) portion of the IPE to the offsite consequence (Level 3) assessment. This included consideration of the source terms used to characterize fission product releases for each containment release category and the major input assumptions used in the offsite consequence analyses. This information is provided in Section 6.3 of Duke's IPE submittal. Duke used the Modular Accident Analysis Program code to analyze postulated accidents and develop radiological source terms for each of 35 containment release categories used to represent the containment end-states identified in Table 5-4. These source terms were incorporated as input to the CRAC2 analysis. The staff reviewed Duke's source term estimates for the major release categories and found these predictions to be in reasonable agreement with estimates of NUREG-1150 (NRC 1990a) for the closest corresponding release scenarios. The staff concludes that the assignment of source terms is acceptable.

The CRAC2 code has been superceded by the Melcor Accident Consequence Code System (MACCS), which, among other advancements, incorporates more recent models for calculating health effects (e.g., latent cancers). Although MACCS represents a significant improvement over CRAC2, both codes use a straight line Gaussian plume dispersion and transport model and, for the same input assumptions, provide comparable estimates of population dose (person-rem). Thus, the CRAC2 code is considered acceptable for purposes of estimating population dose for a severe accident.

The CRAC2 input in PRA, Revision 2, used site-specific meteorological data processed from measurements taken during the mid-1970s. To assess the impact that data from two different time periods may have on offsite dose, Duke obtained more recent data from the ONS site for the period January 1, 1997, through December 31, 1997. Re-analysis of the Level 3 portion of the PRA using the 1997 meteorological data (Duke 1999) shows that the risk results are only slightly impacted (reduced by about 2 percent). The staff therefore considers the meteorological data in PRA, Revision 2, to be representative of the climate for the site.

The population distribution used in Revision 2 of the PRA is based on 1990 census data. The impact of population increases was not included in Revision 2 since the purpose of the PRA was to understand the risk associated with current operation of the plant. Based on information contained in NUREG-1437 (NRC 1996), the population within an 80-km (50-mi) radius of the ONS site is projected to increase by about 33 percent between the years 1990 and 2030. Since the population dose is roughly proportional to the total population, use of the increased population value would result in an increase in the total risk from all initiators of approximately 1.6 person-rem per year. This increase is small in absolute terms and does not have a significant impact on the conclusions of the SAMA analysis, as discussed later.

Evacuation modeling is based on site-specific evacuation studies carried out by Duke. It was assumed that only 95 percent of the people within the emergency planning zone (determined by the plume exposure pathway) would participate in the evacuation. The remaining 5 percent would delay evacuation for 24 hours. This assumption is conservative relative to the NUREG-1150 (NRC 1990a) study, which assumed evacuation of 99.5 percent of the population within the emergency planning zone.

Site-specific economic data were used in the CRAC2 code. However, as discussed later, the applicant based their assessment of offsite costs on generic cost estimates rather than CRAC2 code calculations.

The staff concludes that the methodology used by Duke to estimate the CDF and offsite consequences for ONS provides an acceptable basis from which to proceed with an assessment of risk reduction potential for candidate SAMAs. Accordingly, the staff based its assessment of offsite risk on the CDF and offsite doses reported by Duke.

5.2.3 Potential Design Improvements

This section discusses the process for identifying potential design improvements, the staff's evaluation of this process, and the design improvements evaluated in detail by Duke.

5.2.3.1 Process for Identifying Potential Design Improvements

Duke's process for identifying potential plant improvements consisted of the following three elements:

This included a review of recommendations from the ONS IPE and IPEEE (those that had not been implemented), results of other plant-specific SAMA analyses, and insights from the staff's report on the individual plant examination (NRC 1997a) for possible inclusion of these concepts as additional SAMAs.

As a starting point for the core damage cutset review, Duke developed a listing of the top 100 cutsets (severe accident sequences) based on internal initiators and the top 100 cutsets for external initiators. These 200 sequences include all potential core damage sequences with at least a 0.06-percent contribution to the total CDF. Duke reviewed the cutsets to identify potential SAMAs that could reduce CDF. Cutoff values of 4.5E-7 per year and 8.5E-7 per year were used to screen internal and external events, respectively. To account for the cumulative effect of cutsets below these cutoff values, the basic events importance measure was also used to identify potential enhancements, as discussed below.

For each seismic initiator cutset, Duke calculated the associated offsite risk based on the person-rem risk and CDF for the plant damage states (PDSs) attributable to the seismic initiator. Duke conservatively assumed that the implementation of plant enhancements for seismic events would completely eliminate the seismic risk and calculated the present worth of the averted risk based on a $2000 per person-rem conversion factor, a discount factor of 7 percent, and a 20-year license renewal period. This process was repeated for each of the remaining seismic initiator cutsets above the cutoff frequency. The present worth of averted risk for all of the seismic cutsets combined was estimated to be about $51,000. Duke cited sensitivity studies performed previously as part of the IPEEE analysis, which show that most of the seismic upgrades to plant components would result in only a small reduction in CDF (less than 5E-6 per year). On the basis of the small risk reduction achievable and the large costs associated with substantial seismic upgrades, Duke eliminated seismic SAMAs from further consideration.

Duke reviewed the F-V Basic Event Importance Ranking presented in the ONS PRA report, Revision 2, and identified the top 30 basic events for further consideration. These included seismic-related events, initiating events, equipment failures, and human-error events. Seismic-related events were not evaluated further for reasons discussed above. Duke judged that all but one of the initiating events, such as tornado, dam failure, and fire events, could not be significantly impacted by SAMAs and that the remaining initiator (reactor trip initiator) is adequately addressed by their current ORAM-SENTINEL configuration management system. Based on a review of the remainder, Duke identified nine events/sequences and a potential plant enhancement to address each event. The list of the potential enhancements to reduce CDF are presented in Table 5-5.

Duke also considered potential alternatives to reduce containment failure modes of concern for ONS. These alternatives included nine containment-related improvements evaluated as part of the staff's assessment of severe accident mitigation design alternatives for Watts Bar (NRC 1995a) and five containment-related improvements derived from the staff's report on the individual plant examination program (NRC 1997a). Duke eliminated those alternatives that are either (1) not applicable to ONS (e.g., containment air return fans used only in ice condenser containments), (2) related to control of hydrogen combustion (since the Level 2 PRA shows the ONS containment is capable of withstanding large hydrogen burns), or (3) already implemented at ONS, e.g., by inclusion either in emergency operating procedures, severe accident management guidelines, or the operator training program. Based on the screening, Duke designated seven of the containment related SAMAs for further study. The list of the potential enhancements to improve containment performance is presented in Table 5-6.

5.2.3.2 Staff Evaluation

Duke's effort to identify potential SAMAs focused on areas found to be risk-significant in the ONS PRA. The list of SAMAs generally coincide with accident categories that are dominant CDF contributors or with issues that tend to have a large impact on a number of accident sequences at ONS. Duke made

Table 5-5. Value-Impact Results for Potentially Cost-Beneficial SAMAs that Prevent Core Damage

SAMA Sequences/Failures Addressed Percent Reduction Present Worth Cost of Enhancement
CDF(a) P-Rem(b)
Strengthen east and west penetration rooms and BWST(c) to withstand tornado winds Tornado strikes that damage penetration room and BWST 2.1 14.6 74,000 >$1M
Man SSF(d) 24 hours a day with a trained operator Operator failure to align SSF RCM(e) system in events with turbine building fire or failure of Jocassee Dam 1.4 10.0 49,500 >$5M
Install an automatic backup system to refill elevated water storage tank for HPI(f) cooling Operator failure to refill elevated water storage tank during turbine building flood 6.5 8.7 230,000 >$1M
Install automatic swap of HPI to spent fuel pool Operator failure to swap HPI to spent fuel pool during a flood 3.3 4.3 117,000 >$1M
Increase the height of the SSF flood barrier Failures of the Jocassee Dam that result in flood levels exceeding 5-ft flood barrier 2.9 1.6 103,000 $500K
Install protective barrier around upper surge tanks Tornado strikes that cause a LOCA(g) with failure of all power and upper surge tanks 6.0 8.1 212,000 >$1M
Upgrade 4160 switchgear in turbine building to withstand F4 intensity tornadoes Tornado strikes that cause a LOCA with failure of all power and upper surge tanks 6.0 8.1 212,000 >$1M
Install automatic swap from injection to high pressure recirculation Operator failure to initiate high pressure recirculation during LOCAs 4.6 6.3 163,000 >$1M
Replace reactor pressure vessel Spontaneous failure of the reactor vessel 1.1 <0.1 37,100 >$1M
(a) Total CDF = 8.9E-5/year.
(b) Total offsite dose = 4.92 person-rem/year.
(c) BWST = borated water storage tank.
(d) SSF = standby shutdown facility.
(e) RCM = reactor coolant makeup.
(f) HPI = high pressure injection.
(g) LOCA = loss of coolant accident.

Table 5-6. Value-Impact Results for Potentially Cost-Beneficial SAMAs that Improve Containment Performance

SAMA Sequences/FailuresAddressed Percent Reduction Present Worth Cost of Enhancement
CDF (a) P-Rem (b)
Install independent containment spray systems Late containment failure from over-temperature or steam over-pressure NA 43.7 46,200 >$1M
Install filtered containment vent system Late containment failure from over-pressure NA 43.7 46,200 >$1M
Install additional containment bypass instrumentation Inter-system LOCAs(c) that could be mitigated through improved detection capabilities NA 25.2 27,300 >$1M
Add independent source of feedwater to reduce induced SGTR(d) Induced steam generator tube failures in high pressure core melt sequences NA 2.8 3100 >$1M
Install reactor depressurization system Direct containment heating and induced steam generator tube failures in high pressure core melt sequences NA 10.9 14,300 >$1M
Install reactor cavity flooding system Basemat failure due to core-concrete interactions NA 6.7 7300 >$1M
Install core retention device Basemat failure due to core-concrete interactions NA 6.7 7300 >$1M
(a) Total CDF = 8.9E-5/year.
(b) Total offsite dose = 4.92 person-rem/year.
(c) LOCA = loss of coolant accident.
(d) SGTR = steam generator tube rupture.

a reasonable effort to use the ONS PRA to search for potential SAMAs and to review insights from other plant-specific risk studies and previous SAMA analyses for potential applicability to ONS. The staff notes that Duke identified a number of recommendations for reducing risk as a result of the ONS IPE and IPEEE, and that many of these plant improvements have been implemented or are planned and being tracked for resolution (Duke 1998c; Duke 1999). For those recommendations that were not implemented, Duke provided justification as to why these improvements are not warranted.

The staff reviewed the set of potential enhancements considered in Duke's SAMA identification process. These include improvements oriented toward reducing the CDF and risk from major contributors specific to ONS, improvements identified as part of the NRC containment performance improvement program, accident management strategies identified by NRC in Generic Letter 88-20, Supplement 2 (NRC 1990b), and improvements identified in the previous severe accident mitigation design alternative review for Watts Bar (NRC 1995a) that would be applicable to ONS. The SAMAs also include a filtered containment vent and a bed-core retention device for flooded rubble, which are cited specifically in NUREG-0660 (NRC 1980) for evaluation as part of Three Mile Island Task Action Plan Item II.B.8.

The staff notes that most of the SAMAs involve major modifications and significant costs and that less expensive design improvements and procedure changes could conceivably provide similar levels of risk reduction. However, lower cost improvements are not expected to offer significant risk reduction, given that external events account for the majority (80 percent) of the risk. Much of this risk is due to postulated earthquakes with ground accelerations significantly greater than the ONS design-basis earthquake. As such, SAMAs that would significantly reduce overall risk would involve substantial upgrades in the seismic ruggedness of the plant and would be very costly.

It should be noted that Duke has made extensive use of PRA methods to gain insights regarding severe accidents at ONS. Risk insights from various ONS risk assessments, such as the ONS IPE, the ONS IPEEE, the Keowee PRA, and ONS HPI reliability study, have been identified and implemented to improve both the design and operation of the plant. For example, using the IPE process, Duke identified and implemented modifications to procedures to (1) isolate the high pressure service water (HPSW) to the condenser circulating water (CCW) pumps during a turbine building flooding event to extend the time the elevated water storage tank (EWST) inventory would last, (2) power the SSF from the Unit 2 main feeder bus, (3) terminate containment sprays to conserve the BWST inventory to enhance long-term HPI cooling following a flooding event in the turbine building, and (4) cope with common cause failure of both HPI suction valves. Examples of plant improvements that resulted from IPEEE findings and whose implementation is being planned by Duke are (1) the mounting of the combustible storage locker near the SSF diesel to prevent combustible materials from being spilled around the diesel during a seismic event or knocked over by personnel, and (2) the replacement of the deluge (open head) sprinklers in the Cable and Equipment Rooms with closed head sprinklers to reduce water damage to equipment important to safety during a fire. The implementation

of such improvements reduced the risk associated with the major contributors identified by the ONS PRA and contributed to the reduced number of candidate SAMAs identified as part of Duke's application for license renewal.

The staff concludes that Duke has used a systematic process for identifying potential design improvements for ONS and that the set of potential design improvements identified by Duke is reasonably comprehensive and, therefore, acceptable.

5.2.4 Risk Reduction Potential of Design Improvements

Section 4.3 of the ER describes the process used by Duke to determine the risk reduction potential for each enhancement.

For each seismic initiator cutset, Duke calculated the associated offsite risk based on the person-rem risk and CDF for the PDSs attributable to the seismic initiator. Implementation of the plant enhancement was assumed to completely eliminate the seismic risk associated with the cutset. For each (non-seismic) sequence/enhancement, Duke assigned a PDS based on the type of plant damage and potential containment release characteristics. In general, where an alternative impacted more than one PDS, Duke used the PDS with the highest conditional person-rem risk to characterize the associated risk and assumed that implementation of the alternative would completely eliminate the risk. For each containment-related improvement, Duke assumed that all of the person-rem risk associated with the release categories impacted by the SAMA would be eliminated. For those alternatives that benefit more than one containment failure mode (i.e., independent containment spray system, reactor depressurization system, and filtered containment vent), the total person-rem dose for all affected failure modes was assumed to be completely eliminated by implementing the alternative.

The staff notes that Duke evaluated the risk reduction potential for each SAMA in a bounding fashion; i.e., each SAMA was assumed to completely eliminate all sequences that the specific enhancement was intended to address. As a result, the benefits are generally over estimated and conservative. Accordingly, the staff based its estimates of averted risk for the various SAMAs on Duke's risk reduction estimates.

5.2.5 Cost Impacts of Candidate Design Improvements

Duke's estimated costs for each potential design enhancement are provided in Tables 4-2 and 5-1 of Attachment K to the ER. For most of the SAMAs, Duke estimated the cost of implementation to be greater than $1 million based on cost estimates developed in previous industry studies. For three SAMAs, Duke developed plant-specific cost estimates because there was no readily available information on the estimated cost to implement similar alternatives and because the basic events associated with these alternatives were found to have a high importance in the ONS PRA. These SAMAs involve (1) increasing the height of the SSF flood barrier, (2) manning the SSF 24 hours a day with trained operators, and (3) installing a protective barrier for the upper surge tanks or upgrading the 4160 volt switchgear to withstand tornado winds. The costs to implement these SAMAs were estimated to be on the order of $500,000, $5 million, and $1 million, respectively. Because the safety benefits of the potential SAMAs were significantly less than their estimated implementation costs (by about a factor of five), none of the cost estimates were further refined.

The staff compared Duke's cost estimates with estimates developed elsewhere for similar improvements, including estimates developed as part of the evaluation of severe accident mitigation design alternatives for operating reactors and advanced LWRs. The staff notes that Duke's estimated implementation costs of $1 million dollars or greater are consistent with the values reported in previous analyses for changes of similar scope and are not unreasonable for the SAMAs under consideration, given that these enhancements involve major hardware changes and impact safety-related systems.

Although the applicant did not provide the underlying bases for its cost estimates, the staff views their cost estimates as reasonable for evaluating the SAMAs because the estimates are consistent with those developed by others and because the spread between the estimated costs and benefits is significant. Accordingly, the staff adopted Duke's cost estimates for the various candidate improvements.

5.2.6 Cost-Benefit Comparison

The following sections describe Duke's cost-benefit comparison and the staff's evaluation of the cost-benefit analysis.

5.2.6.1 Duke Evaluation

In the analysis provided in the ER, Duke did not include the following factors in its cost-benefit evaluation: averted onsite cleanup and decontamination cost, replacement power cost, and averted offsite property damage cost. In view of the significant impact of these averted costs on the estimated benefit for a SAMA, the staff requested that Duke include these factors in their cost-benefit analysis for each affected SAMA. In their response to the request for additional information, Duke updated the benefit estimates to include these factors for all SAMAs that reduce CDF. The methodology used by Duke was based primarily on NRC's guidance for performing cost-benefit analysis, i.e., NUREG/BR-0184, Regulatory Analysis Technical Evaluation Handbook (NRC 1997b), and NUREG/BR-0058, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission (NRC 1995b). The guidance involves determining the net value for each SAMA according to the following formula:

Net Value = (APE + AOC + AOE + AOSC) - COE

where APE = present value of averted public exposure ($)
AOC = present value of averted offsite property damage costs ($)
AOE = present value of averted occupational exposure ($)
AOSC = present value of averted onsite costs ($)
COE = cost of enhancement ($)

If the net value of a SAMA is negative, the cost of implementing the SAMA is larger than the benefit associated with the SAMA and is not considered beneficial. Duke's derivation of each of the associated costs is summarized below.

Averted Public Exposure (APE)

Averted public exposure costs were calculated using the following formula:

APE = Annual reduction in public exposure (person-rem/reactor-year)
x monetary equivalent of unit dose
x present value conversion factor

Duke estimated the annual reduction in public exposure for each SAMA as discussed previously. The reduction in public exposure (person-rem per year) was converted to a monetary equivalent by applying NRC's conversion factor of $2000 per person-rem and then discounting the monetary equivalent to present value. A 20-year period for the license renewal period and a 7-percent real discount rate was assumed, resulting in a present value conversion factor of 10.76.

As stated in NUREG/BR-0184 (NRC 1997b), it is important to note that the monetary value of the public health risk after discounting does not represent the expected reduction in public health risk due to a single accident. Rather, it is the present value of a stream of potential losses extending over the remaining lifetime (in this case, the renewal period) of the facility. Thus, it reflects the expected annual loss due to a single accident, the possibility that such an accident could occur at any time over the renewal period, and the effect of discounting these potential future losses to present value.

Averted Offsite Property Damage Costs

Averted offsite property damage costs were calculated using the following formula:

AOC = Annual CDF reduction
x offsite economic costs associated with a severe accident (on a per event basis)
x present value conversion factor

Duke determined the offsite economic costs for a severe accident based on the weighted costs for offsite property damage for the five NUREG-1150 plants (reported in Table 5.6 of NUREG/BR-0184). These costs were inflated to year 2000 dollars based on a 4-percent inflation rate, yielding a value of $364 million. Calculated values for offsite economic costs were discounted to present value in the same manner as for averted public exposure.

Averted Occupational Exposure

Averted occupational exposure was calculated using the following formula:

AOE = Annual CDF reduction
x occupational exposure per core-damage event
x present value conversion factor

Duke derived the values for averted occupational exposure based on information provided in Section 5.7.3 of the regulatory analysis handbook (NRC 1997b). Best estimate values provided for immediate occupational dose (3,300 person-rem) and long-term occupational dose (20,000 person-rem over a 10-year cleanup period) were used. The present value of these doses was calculated using equations provided in the handbook in conjunction with a monetary equivalent of unit dose of $2000 per person-rem, a real discount rate of 7 percent, and a time period of 20 years to represent the license renewal period.

Averted Onsite Costs

AOSC includes averted cleanup and decontamination costs and averted power replacement costs. Duke derived the values for AOSC based on information provided in Section 5.7.6 of the regulatory analysis handbook (NRC 1997b).

Averted cleanup costs are calculated using the following formula:

ACC = Annual CDF reduction
x present value of cleanup costs per core-damage event
x present value conversion factor

The net present value for cleanup and decontamination of a severe accident (discounted over 10 years) is given as $1.1 billion in the handbook (NRC 1997b). Use of a discount factor of 10.76 to account for the 20-year license renewal period yields an integrated cleanup cost of $12 billion. This value was multiplied by the annual reduction in core damage frequency to obtain the averted cleanup costs portion of the AOSC.

Long-term replacement power costs (URP) are calculated as

URP = Annual CDF reduction
x present value of replacement power for a single event
x factor to account for remaining service years for which replacement power is required

In accordance with guidance provided in Section 5.7.6.2 of the handbook (NRC 1997b), Duke estimated the net present value of replacement power for a single event to be $1.23 billion, based on a replacement power cost for each ONS unit of $152 million (year 2000 dollars), a real discount rate of 7 percent, and a 20-year license renewal period. This value was multiplied by a factor of 8.1 to obtain a summation of the single-event costs over the entire license renewal period, yielding a replacement power cost of $10.0 billion. This value was multiplied by the annual reduction in core damage frequency to obtain the averted replacement costs portion of the AOSC.

The value-impact results for the 16 SAMAs are presented in Tables 5-5 and 5-6. All of the SAMAs have a negative net value, even when bounding risk reduction benefits are assumed, and AOSC is included. Duke concluded that implementation of SAMAs is not justified since the cost of implementation far exceeds the benefit of these SAMAs. As such, Duke has decided not to pursue any of these SAMAs further.

5.2.6.2 Staff Evaluation

The updated cost-benefit analysis provided by Duke (Duke 1999) was based primarily on NRC's Regulatory Analysis Technical Evaluation Handbook (NRC 1997b). The only noted deviation from the regulatory guidance was the omission of the averted offsite property damage cost component for those SAMAs that impact only containment performance. (A reduction in offsite consequences results in both averted public exposure and averted offsite property damage. Duke appropriately considered averted offsite property damage costs for the SAMAs that prevent core damage, but failed to include these averted costs for the SAMAs that improve containment performance.) The staff has evaluated the averted offsite property damage cost component for these SAMAs and found it to be small (less than $100,000 for the most effective mitigative SAMA identified) and well below the cost of the enhancements. Thus, the total present worth benefit for any of the containment-related SAMAs would be less than $150,000.

The staff concludes that the cost of implementing any of the 16 SAMAs would far exceed the estimated benefit, with a margin of about a factor of five. Based on its review, the staff notes the following:

5.2.7 Conclusions

Duke completed a comprehensive effort to identify and evaluate potential cost-beneficial plant enhancements to reduce the risk associated with severe accidents at ONS. As a result of this assessment, Duke concluded that no additional mitigation alternatives are cost-beneficial and warrant implementation at ONS.

Based on its review of SAMAs for ONS, the staff concurs that none of the candidate SAMAs are cost beneficial. This conclusion is consistent with the low residual level of risk indicated in the ONS PRA and the fact that Duke has already implemented many plant improvements identified from previous plant-specific risk studies. Both the conditional probability of an early release of fission products and the total offsite risk at ONS are already quite small (less than 4 percent and 5 person-rem per year, respectively). External events account for the majority (80 percent) of the risk, with much of this from postulated earthquakes with ground accelerations significantly greater than the ONS design-basis earthquake. Given the low level of residual risk and the large cost of seismic-related enhancements necessary to substantially reduce risk, cost-beneficial enhancements that can significantly reduce risk are unlikely and have not been identified. The margins in the analysis are considered ample to cover uncertainties in risk and cost estimates given that, in general, estimates for these factors were conservatively evaluated.


5.3 References


[ Prev | Next | Top of file ]

10 CFR 51.53, "Postconstruction environmental reports."

10 CFR Part 51, Subpart A, Appendix B, "Environmental effect of renewing the operating license of a nuclear power plant."

Duke Energy Corporation. 1990. Letter from Tuckman, Duke Energy Corporation. Subject: Transmitting Individual Plant Examination. Dated November 30, 1990.

Duke Energy Corporation. 1995. Letter from Hampton, Duke Energy Corporation. Subject: Transmitting Individual Plant Examination for External Events. Dated December 28, 1995.

Duke Energy Corporation. 1997a. Letter from Hampton, Duke Energy Corporation. Subject: Transmitting Oconee Probabilistic Risk Assessment. Dated February 13, 1997.

Duke Energy Corporation. 1997b. Letter from McCollum, Duke Energy Corporation. Subject: Transmitting Oconee Supplemental Individual Plant Examination for External Events Submittal Report. Dated December 18, 1997.

Duke Energy Corporation. 1997c. Letter from McCollum, Duke Energy Corporation. Subject: Transmitting High Pressure Injection Reliability Study. Dated December 18, 1997.

Duke Energy Corporation. 1998a. Application for Renewed Operating Licenses, Oconee Nuclear Station-Units 1, 2, and 3. Volume IV-Environmental Report.

Duke Energy Corporation. 1998b. Final Safety Analysis Report (Oconee Updated FSAR). Charlotte, North Carolina.

Duke Energy Corporation. 1998c. Letter from McCollum, Duke Energy Corporation, Subject: SQUG Resolution of USI A-46 (Generic Letter 87-02) Expected Completion of SQUG Outliers. Oconee Supplemental IPEEE Submittal Report. Dated June 30, 1998.

Duke Energy Corporation. 1999. Letter from M. S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Subject: License Renewal - Response to Requests for Additional Information, Oconee Nuclear Station. Dated March 4, 1999.

U.S. Nuclear Regulatory Commission (NRC). 1980. NRC Action Plan Developed As a Result of TMI-2 Accident. NUREG-0660. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1988. Generic Letter 88-20, "Individual Plant Examination for Severe Accident Vulnerabilities." November 23, 1988.

U.S. Nuclear Regulatory Commission (NRC). 1990a. Severe Accident Risks - An Assessment for Five U.S. Nuclear Power Plants. NUREG-1150. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1990b. Letter from J. G. Partlow, U.S. NRC, to All Holders of Operating Licenses and Construction Permits for Nuclear Power Reactor Facilities. April 4, 1990. Subject: Accident Management Strategies for Consideration in the Individual Plant Examination Process - Generic Letter 88-20, Supplement No. 2.

U.S. Nuclear Regulatory Commission (NRC). 1993. Weins (NRC) letter dated 4/1/93 transmitting Evaluation of the Oconee 1, 2, and 3 Individual Plant Examination (IPE) - Internal Events.

U.S. Nuclear Regulatory Commission (NRC). 1995a. Final Environmental Statement Related to the Operation of Watts Bar Nuclear Plant Units 1 and 2. NUREG-0498, Supplement 1. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1995b. Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission. NUREG/BR-0058, Revision 2. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants (GEIS), NUREG-1437. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1997a. Individual Plant Examination Program: Perspectives on Reactor Safety and Plant Performance. NUREG-1560. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1997b. Regulatory Analysis Technical Evaluation Handbook. NUREG/BR-0184. U.S. Nuclear Regulatory Commission, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1998. Letter from NRC to Duke Energy Corporation. Subject: Request for Additional information for the Review of the Oconee Nuclear Station Unit Nos. 1, 2, & 3 Environmental Report Associated with License Renewal - Environmental. Dated December 29, 1998.


6.0 Environmental Impacts of the Uranium Fuel Cycle and Solid Waste Management


[ Prev | Next | Top of file ]

Environmental issues associated with the uranium fuel cycle and solid waste management were discussed in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437 (NRC 1996; NRC 1999(11)). The GEIS included a determination of whether the analysis of the environmental issue could be applied to all plants and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristics
(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)
(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that do not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required.

This chapter addresses those issues that are related to the uranium fuel cycle and solid waste management during the license renewal term that are listed in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to ONS. The generic potential impacts of the radiological and non-radiological environmental impacts of the uranium fuel cycle and transportation of nuclear fuel and wastes are described in detail in the GEIS based on the generic impacts provided in 10 CFR 51.51(b), Table S-3, "Table of Uranium Fuel Cycle Environmental Data," and in 10 CFR 51.52(c), Table S-4, "Environmental Impact of Transportation of Fuel and Waste to and from One Light-Water-Cooled Nuclear Power Reactor." The GEIS also addresses the impacts from radon and technetium. There are no Category 2 issues for the uranium fuel cycle and solid waste management.


6.1 The Uranium Fuel Cycle


[ Prev | Next | Top of file ]

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to ONS from the uranium fuel cycle and solid waste management are listed in Table 6-1. Duke stated in its environmental report (ER) (Duke 1998) that it is not aware of any new and significant information

Table 6-1. Category 1 Issues Applicable to the Uranium Fuel Cycle and Solid Waste Management During the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections
Uranium Fuel Cycle and Waste Management
Offsite radiological impacts (individual effects from other than the disposal of spent fuel and high level waste) 6.1; 6.2.1; 6.2.2.1; 6.2.2.3; 6.2.3; 6.2.4; 6.6
Offsite radiological impacts (collective effects) 6.1; 6.2.2.1; 6.2.3; 6.2.4
Offsite radiological impacts (spent fuel and high level waste disposal) 6.1; 6.2.2.1; 6.2.3; 6.2.4
Nonradiological impacts of the uranium fuel cycle 6.1; 6.2.2.6; 6.2.2.7; 6.2.2.8; 6.2.2.9; 6.2.3; 6.2.4; 6.6
Low-level waste storage and disposal 6.1; 6.2.2.2;6.4.2; 6.4.3; 6.4.3.1; 6.4.3.2; 6.4.3.3; 6.4.4; 6.4.4.1; 6.4.4.2; 6.4.4.3; 6.4.4.4; 6.4.4.5; 6.4.4.5.1; 6.4.4.5.2; 6.4.4.5.3; 6.4.4.5.4; 6.4.4.6
Mixed waste storage and disposal 6.4.5.1; 6.4.5.2; 6.4.5.3; 6.4.5.4; 6.4.5.5; 6.4.5.6; 6.4.5.6.1; 6.4.5.6.2; 6.4.5.6.3; 6.4.5.6.4
On-site spent fuel 6.1; 6.4.6; 6.4.6.1; 6.4.6.2; 6.4.6.3; 6.4.6.4; 6.4.6.5; 6.4.6.6; 6.4.6.7; 6.6
Nonradiological waste 6.1; 6.5; 6.5.1; 6.5.2; 6.5.3; 6.6
Transportation 6.1; 6.3.1; 6.3.2.3; 6.3.3; 6.3.4; 6.6

associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of those issues, the staff concluded in the GEIS that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

A brief description of the staff review and the GEIS conclusions, as codified in Table B-1, for each of these issues follows:

  •  
Offsite radiological impacts (individual effects from other than the disposal of spent fuel and high level waste): Based on information in the GEIS, the Commission found that
   Offsite impacts of the uranium fuel cycle have been considered by the Commission in Table S-3 of this part [10 CFR 51.51(b)]. Based on information in the GEIS, impacts on individuals from radioactive gaseous and liquid releases, including radon-222 and technetium-99 are small.
The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no offsite radiological impacts of the uranium fuel cycle during the renewal term beyond those discussed in the GEIS.
  •  
Offsite radiological impacts (collective effects): Based on information in the GEIS, the Commission found that
The 100-year environmental dose commitment to the U.S. population from the fuel cycle, HLW, and spent fuel disposal is calculated to be about 14,800 person rem [148 person Sv], or 12 cancer fatalities, for each additional 20-year power reactor operating term. Much of this, especially the contribution of radon releases from mines and tailing piles, consists of tiny doses summed over large populations. This same dose calculation can theoretically be extended to include many tiny doses over additional thousands of years as well as doses outside the United States. The result of such a calculation would be thousands of cancer fatalities from the fuel cycle, but this result assumes that even tiny doses have some statistical adverse health effect which will not ever be mitigated (for example no cancer cure in the next thousand years), and that these doses projected over thousands of years are meaningful. However, these assumptions are questionable. In particular, science cannot rule out the possibility that there will be no cancer fatalities from these tiny doses. For perspective, the doses are very small fractions of regulatory limits and even smaller fractions of natural background exposure to the same populations.
Nevertheless, despite all the uncertainty, some judgement as to the regulatory NEPA implications of these matters should be made, and it makes no sense to repeat the same judgement in every case. Even taking the uncertainties into account, the Commission concludes that these impacts are acceptable in that these impacts would not be sufficiently large to require the NEPA conclusion, for any plant, that the option of extended operation under 10 CFR Part 54 should be eliminated. Accordingly, while the Commission has not assigned a single level of significance for the collective effects of the fuel cycle, this issue is considered Category 1.
The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no collective impacts of the uranium fuel cycle during the renewal term beyond those discussed in the GEIS.
  •  
Offsite radiological impacts (spent fuel and HLW disposal): Based on information in the GEIS, the Commission found that
For the high level waste and spent fuel disposal component of the fuel cycle, there are no current regulatory limits for offsite releases of radioactive nuclides for the current candidate repository site. However, if we assume that limits are developed along the lines of the 1995 National Academy of Sciences (NAS) report, "Technical Bases for Yucca Mountain Standards," and that in accordance with the Commission's Waste Confidence Decision, 10 CFR 51.23, a repository can and likely will be developed at some site that will comply with such limits, peak doses to virtually all individuals will be 100 millirem (1 mSv) per year or less. However, while the Commission has reasonable confidence that these assumptions will prove correct, there is considerable uncertainty since the limits are yet to be developed, no repository application has been completed or reviewed, and uncertainty is inherent in the models used to evaluate possible pathways to the human environment. The NAS report indicated that 100 millirem (1 mSv) per year should be considered as a starting point for limits for individual doses, but notes that some measure of consensus exists among national and international bodies that the limits should be a fraction of the 100 millirem (1 mSv) per year. The lifetime individual risk from 100 millirem (1 mSv) annual dose limit is about is about 3×10-3.
Estimating cumulative doses to populations over thousands of years is more problematic. The likelihood and consequences of events that could seriously compromise the integrity of a deep geologic repository were evaluated by DOE in the "Final Environmental Impact Statement: Management of Commercially Generated Radioactive Waste," October 1980 [DOE 1980]. The evaluation estimated the 70-year whole-body dose commitment to the maximum individual and to the regional population resulting from several modes of breaching a reference repository in the year of closure, after 1,000 years, after 100,000 years, and after 100,000,000 years. Subsequently, the NRC and other federal agencies have expended considerable effort to develop models for the design and for the licensing of a HLW repository, especially for the candidate repository at Yucca Mountain. More meaningful estimates of doses to population may be possible in the future as more is understood about the performance of the proposed Yucca Mountain repository. Such estimates would involve very great uncertainty, especially with respect to cumulative population doses over thousands of years. The standard proposed by the NAS is a limit on maximum individual dose. The relationship of the potential new regulatory requirements, based on the NAS report, and cumulative population impacts has not been determined, although the report articulates the view that protection of individuals will adequately protect the population for a repository at Yucca Mountain. However, EPA's generic repository standards in 40 CFR Part 191 generally provide an indication of the order of magnitude of cumulative risk to population that could result from the licensing of a Yucca Mountain repository, assuming the ultimate standards will be within the range of standards now under consideration. The standards in 40 CFR Part 191 protect the population by imposing "containment requirements" that limit the cumulative amount of radioactive material released over 10,000 years. Reporting performance standards that will be required by EPA are expected to result in releases and associated health consequences in the range between 10 and 100 premature cancer deaths with an upper limit of 1,000 premature cancer deaths worldwide for a 100,000 metric tonne (MTHM) repository.
Nevertheless, despite all the uncertainty, some judgement as to the regulatory NEPA implications of these matters should be made, and it makes no sense to repeat the same judgement in every case. Even taking the uncertainties into account, the Commission concludes that these impacts are acceptable in that these impacts would not be sufficiently large to require the NEPA conclusion, for any plant, that the option of extended operation under 10 CFR Part 54 should be eliminated. Accordingly, while the Commission has not assigned a single level of significance for the impacts of spent fuel and high-level waste disposal, this issue is considered Category 1.
The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no collective impacts of the uranium fuel cycle during the renewal term beyond those discussed in the GEIS.
  •  
Nonradiological impacts of the uranium fuel cycle: Based on information in the GEIS, the Commission found that " The nonradiological impacts of the uranium fuel cycle resulting from the renewal of an operating license for any plant are found to be small." The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no nonradiological impacts of the uranium fuel cycle during the renewal term beyond those discussed in the GEIS.
  •  
Low-level waste storage and disposal: Based on information in the GEIS, the Commission found that
The comprehensive regulatory controls that are in place and the low public doses being achieved at reactors ensure that the radiological impacts to the environment will remain small during the term of a renewed license. The maximum additional onsite land that may be required for low-level waste storage during the term of a renewed license and associated impacts will be small. Nonradiological impacts on air and water will be negligible. The radiological and nonradiological environmental impacts of long-term disposal of low-level waste from any individual plant at licensed sites are small. In addition, the Commission concludes that there is reasonable assurance that sufficient low-level waste disposal capacity will be made available when needed for facilities to be decommissioned consistent with NRC decommissioning requirements.
The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of low-level waste storage and disposal associated with the renewal term beyond those discussed in the GEIS.
Mixed waste storage and disposal: Based on information in the GEIS, the Commission found that
The comprehensive regulatory controls and the facilities and procedures that are in place ensure proper handling and storage, as well as negligible doses and exposure to toxic materials for the public and the environment at all plants. License renewal will not increase the small, continuing risk to human health and the environment posed by mixed waste at all plants. The radiological and nonradiological environmental impacts of long-term disposal of mixed waste from any individual plant at licensed sites are small. In addition, the Commission concludes that there is reasonable assurance that sufficient mixed waste disposal capacity will be made available when needed for facilities to be decommissioned consistent with NRC decommissioning requirements.
The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of mixed waste storage and disposal associated with the renewal term beyond those discussed in the GEIS.
  •  
On-site spent fuel: Based on information in the GEIS, the Commission found that " The expected increase in volume of spent fuel from an additional 20 years of operation can be safely accommodated on site with small environmental effects through dry or pool storage at all plants if a permanent repository or monitored retrievable storage is not available." The onsite spent fuel impacts were determined to be SMALL. The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of onsite spent fuel associated with license renewal beyond those discussed in the GEIS.
  •  
Nonradiological waste: Based on information in the GEIS, the Commission found that " No changes to generating systems are anticipated for license renewal. Facilities and procedures are in place to ensure continued proper handling and disposal at all plants." The nonradiological waste impacts were determined to be SMALL. The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no nonradiological waste impacts during the renewal term beyond those discussed in the GEIS.
  •  
Transportation: Subsequent to the issuance of the draft SEIS, the Commission promulgated a final rule to amend the regulations governing the transportation issues of the environmental review requirements for renewal of nuclear power plant operating licenses. This transportation issue had been considered a Category 2 issue and was discussed in Section 6.1.1 of the draft SEIS. It is no longer considered a Category 2 issue and, therefore, Section 6.1.1 has been deleted. Based on information contained in the GEIS, the Commission found that
The impacts of transporting spent fuel enriched up to 5 percent uranium-235 with average burnup for the peak rod to current levels approved by NRC up to 62,000 MWd/MTU and the cumulative impacts of transporting high-level waste to a single repository, such as Yucca Mountain, Nevada are found to be consistent with the impact values contained in 10 CFR 51.52(c), Summary Table S-4--Environmental Impact of Transportation of Fuel and Waste to and from One Light-Water-Cooled Nuclear Power Reactor. If fuel enrichment or burnup conditions are not met, the applicant must submit an assessment of the implications for the environmental impact values reported in §51.52.
The transportation impacts were determined to be SMALL if fuel enrichment and burnup conditions set forth in the Addendum 1 to the GEIS are met. ONS meets the fuel enrichment and burnup conditions. The staff has not identified any significant new information during its independent review of the Duke ER, the staff's site visit, the scoping process, its review of public comments on the draft SEIS, or its evaluation of other available information. Therefore, the staff concludes that there are no impacts of transportation associated with license renewal beyond those discussed in the GEIS.


6.2 References


[ Prev | Next | Top of file ]

10 CFR Part 51, "Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions."

10 CFR 51.23, "Temporary storage of spent fuels after cessation of reactor operation--generic determination of no significant environmental impact."

10 CFR 51.51(b), Table S-3, "Uranium fuel cycle environmental data."

10 CFR 51.52(c), Table S-4, "Environmental effects of transportation of fuel and waste.

10 CFR Part 51, Subpart A, Appendix B, "Environmental effects of renewing the operating license of a nuclear power plant."

10 CFR Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants."

40 CFR Part 191, "Environmental Radiation Protection Standards for Management and Disposal of Spent Nuclear Fuel, High-Level and Transuranic Radioactive Waste."

Duke Energy Corporation. 1998. Application for Renewed Operating Licenses. Oconee Nuclear Station Units 1, 2, and 3. Volume IV Environmental Report.

National Academy of Sciences (NAS). 1995. Technical Bases for Yucca Mountain Standards, Washington, D.C.

U.S. Department of Energy (DOE). 1980. Final Environmental Impact Statement: Management of Commercially Generated Radioactive Waste, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plant (GEIS), NUREG-1437, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999. Generic Environmental Impact Statement to License Renewal of Nuclear Plants Main Report, Section 6.3--Transportation, Table 9.1, Summary of findings on NEPA issues for license renewal of nuclear power plants. NUREG-1437, Volume 1, Addendum 1. Washington, D.C.


7.0 Environmental Impacts of Decommissioning


[ Prev | Next | Top of file ]

Environmental issues associated with decommissioning resulting from continued plant operation during the renewal term were discussed in the Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants, NUREG-1437 (NRC 1996). The GEIS included a determination of whether the analysis of the environmental issue could be applied to all plants and whether additional mitigation measures would be warranted. Issues were then assigned a Category 1 or a Category 2 designation. As set forth in the GEIS, Category 1 issues are those that meet all of the following criteria:

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristics
(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)
(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are not likely to be sufficiently beneficial to warrant implementation.

For issues that meet the three Category 1 criteria, no additional plant-specific analysis is required unless new and significant information is identified.

Category 2 issues are those that do not meet one or more of the criteria of Category 1, and therefore, additional plant-specific review for these issues is required. There are no Category 2 issues related to decommissioning at ONS.

Category 1 issues in 10 CFR Part 51, Subpart A, Appendix B, Table B-1, that are applicable to ONS decommissioning following the renewal term are listed in Table 7-1. Duke stated in its Environmental Report (ER) (Duke 1998) that it is not aware of any new and significant information associated with the renewal of the Oconee operating licenses. No significant new information has been identified by the staff in the review process and in the staff's independent review. Therefore, the staff concludes that there are no impacts related to these issues beyond those discussed in the GEIS. For all of those issues, the staff concluded in the GEIS that the impacts are SMALL, and plant-specific mitigation measures are not likely to be sufficiently beneficial to be warranted.

Table 7-1. Category 1 Issues Applicable to the Decommissioning of the ONS Following the Renewal Term

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 GEIS Sections
Decommissioning
Radiation Doses 7.3.1; 7.4
Waste Management 7.3.2; 7.4
Air Quality 7.3.3; 7.4
Water Quality 7.3.4; 7.4
Ecological Resources 7.3.5; 7.4
Socioeconomic Impacts 7.3.7; 7.4

A brief description of the staff's review and the GEIS conclusions, as codified in Table B-1, for each of the issues follows:


7.1 References


[ Prev | Next | Top of file ]

10 CFR Part 51, Subpart A, Appendix B, "Environmental effect of renewing the operating license of a nuclear power plant."

Duke Energy Corporation. 1998. Application for Renewed Operating Licenses--Oconee Nuclear Station, Units 1, 2 and 3. Volume IV-Environmental Report.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plant (GEIS), NUREG-1437. Washington, D.C.


8.0 Environmental Impacts of Alternatives to License Renewal


[ Prev | Next | Top of file ]

This chapter examines the potential environmental impacts associated with denying a renewed operating license (i.e., the no-action alternative); the potential environmental impacts from electric generating sources other than renewal of the ONS operating licenses; the potential impacts from instituting additional conservation measures to reduce the total demand for power; and the potential impacts from power imports. The impacts are evaluated using a three-level standard of significance--SMALL, MODERATE, or LARGE--based on Council on Environmental Quality (CEQ) guidelines. These significance levels are as follows:

   SMALL: Environmental effects are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.
MODERATE: Environmental effects are sufficient to alter noticeably, but not to destabilize important attributes of the resource.
LARGE: Environmental effects are clearly noticeable and are sufficient to destabilize important attributes of the resource.


8.1 No-Action Alternative


[ Prev | Next | Top of file ]

For license renewal, the no-action alternative refers to a scenario in which NRC would not renew the ONS operating licenses, and the applicant would then decommission ONS when plant operations cease. Replacement of ONS electricity generation capacity would be met either by demand-side management and energy conservation (perhaps supplied by an energy service company), imported power, some generating alternative other than ONS, or some combination of these. However, due to the influence of the ongoing deregulation of the retail market, Duke might not be the ultimate power supplier.

Duke will be required to comply with NRC decommissioning requirements whether or not the operating licenses are renewed. If the ONS operating licenses are renewed, decommissioning activities may be postponed for up to an additional 20 years. If the licenses are not renewed, then Duke would begin decommissioning activities when plant operations cease, beginning in 2013 or perhaps sooner. The impacts of decommissioning would occur concurrently with the impacts of supplying replacement power. The GEIS (NRC 1996) and the Final Generic Impact Statement on Decommissioning of Nuclear Facilities, NUREG-0586 (NRC 1988) provide a description of decommissioning activities.

The environmental impacts associated with decommissioning under the no-action alternative would be bounded by the discussion of impacts in Chapter 7 of the GEIS, Chapter 7 of the SEIS, and NUREG-0586 (NRC 1988). The impacts of decommissioning after 60 years of operation generally would not be significantly different from those occurring after 40 years of operation.

  •  
Socioeconomic: When ONS ceases operation, there will be a decrease in employment and tax revenues associated with the closure. This impact would be concentrated in Oconee County and to a lesser degree in Pickens, Anderson, and Greenville counties. Most secondary employment impacts and impacts on population would also be expected in these counties. Table 2.5 shows the current geographic distribution of the residences of ONS employees by county. Most of the tax revenue losses would occur in Oconee County. The no-action alternative results in the loss of these taxes and payrolls 20 years earlier than if the licenses are renewed (Table 8-1). Duke pays taxes on ONS of about $22 million per year to Oconee County, as stated in Section 2.2.8. This tax base would be lost in the no-action alternative. It is expected that energy costs in the area would also be higher in a regulated utility environment. It is not clear from the staff's interviews with local real estate agents and appraisers whether there would be a significant adverse impact on housing values as a result of closing ONS. While the loss of payrolls and workers would be substantial, particularly in Oconee County, future real estate values may be driven more by vacation/retirement home demand and the suburban growth surrounding Greenville.

Table 8-1. Summary of Environmental Impacts from No-Action Alternative

Impact Category Impact Comment
Socioeconomic MODERATE to LARGE Decrease in employment and tax revenues
Archaeological and Historical Resources SMALL to LARGE Sale or transfer of land within plant site leads to changes in land-use pattern
Environmental Justice SMALL to MODERATE Loss of employment opportunities and social programs
It is not clear that Duke's industrial recruitment efforts in the Tri-County region or their success would be maintained after closure of the Oconee plant. Duke's power costs would be expected to be higher without the plant, and there would be fewer incentives for Duke to assist in recruiting outside businesses into the region if its presence is significantly diminished.
The recreational property, lake, and hydroelectric facilities associated with the Keowee-Toxaway project are not likely to be affected by the closure of Oconee. However, there is one potential change that could be significant. In part, because of the need for clean water at the ONS, Duke has provided aggressive corporate, political, and technical leadership in maintaining high water quality in Jocasee and Keowee Lakes. Hydroelectric facilities can tolerate much lower water quality and Crescent Resources (the real estate division of Duke Energy Corporation) may have divested enough holdings by 2013 that Duke will have fewer corporate incentives to keep water quality exceptionally high if ONS closes. Therefore, the corporate and technical leadership and assistance that Duke voluntarily provides in the area of water quality monitoring may be less readily available.
  •  
Archaeological and Historical Resources: The potential for future adverse impacts to known or unrecorded cultural resources at the ONS following decommissioning will depend on the future land use of the site. Known resources and activities include the current visitors' center and associated interpretative efforts that are funded and maintained by Duke. Eventual sale or transfer of the land within the plant site could result in adverse impacts to these resources should the land-use pattern change dramatically.
  •  
Environmental Justice for No-Action: Current operations at ONS do not have disproportionate impacts on low-income and minority populations of the surrounding counties, and no environmental pathways have been identified that would cause disproportionate impacts. Since closure would result in a decrease in employment and tax revenues in Oconee County, it is possible that the county's ability to maintain social services could be reduced at the same time as diminished economic conditions reduce employment prospects for the low-income or minority populations. There is some possibility of negative and disproportionate impacts on low-income or minority populations from this source under the no-action alternative.


8.2 Alternative Energy Sources


[ Prev | Next | Top of file ]

Nuclear power plants are commonly used for base-load generation; the GEIS indicates that coal-fired and gas-fired generation capacity are the feasible alternatives to nuclear power generating capacity, based on current (and expected) technological and cost factors. The alternatives of coal-fired generation and gas-fired generation are presented (Sections 8.2.1 and 8.2.2, respectively) as if such plants were constructed at the ONS site, using the existing water intake and discharge structures, switchyard, and transmission lines, or at an alternate location that could be either a current industrial site or an undisturbed, pristine site requiring a new generating building and facilities, new switchyard, and at least some new transmission lines. For purposes of this SEIS, a "greenfield" site is assumed to be an undisturbed, pristine site.

Depending on the location of an alternative site, it might also be necessary to provide a connection to the nearest gas pipeline (in the case of natural gas) or rail connection (in the case of coal). The requirement for these additional facilities also likely would increase the environmental impacts relative to those that would be experienced at the ONS site, although this is less certain.

The cooling water needs of a fossil-fired plant of equal capacity to the ONS facility would require the use of either a once-through cooling system located on a large body of water such as Lake Keowee or a closed cycle system using cooling towers.

The potential for using imported power is discussed in Section 8.2.3. Imported power is considered feasible, but would result in the transfer of environmental impacts from the current region in South Carolina to some other location in South Carolina, another state, or a Canadian province. Several other technologies were considered, but were determined not to be reasonable replacements for a nuclear power plant. These options included wind, solar, hydropower, geothermal, wood energy, municipal solid waste, oil, advanced nuclear, fuel cells, delayed retirement of other generating units, and utility-sponsored conservation as discussed in Section 8.2.4.

Some of the alternatives in this section are not inherently infeasible, but could not provide enough power on their own to replace the power from ONS. The final subsection considers the environmental consequences of a mix of alternatives. These impacts are the same or larger than the environmental consequences of relicensing.

8.2.1 Coal-Fired Generation

It was assumed that it would take 2500 MW(e) of coal-fired generation capacity to replace the approximately 2500-MW(e) ONS. The typical size [MW(e)] and configuration used by the electrical power industry in the application of coal-fired generation technology varies.

8.2.1.1 Once-Through Cooling System

Section 8.2.1.1 sets forth the environmental impacts of converting the current ONS site to a coal-fired generation facility with once-through cooling and building a similar facility on a greenfield site. Differences in impacts with closed-cycle cooling are covered in Section 8.2.1.2. Land use in the discussion that follows was based on two of Duke's current coal-fired generating plants: the four-unit, 2090-MW(e) Marshall Steam Station in Catawba County, North Carolina, which occupies 650 ha (1600 acres), and the 2-unit, 2370-MW(e) Belews Creek Steam Station in Stokes County, North Carolina, which occupies 280 ha (700 acres) (Duke 1999a). Environmental impacts were based on data in EPA (1995). The impacts are summarized in Table 8-2.

Construction of the coal-fired alternative would take approximately 5 years. The workforce during the construction period would be expected to average 1500, with a peak of 2500 (GEIS, adjusted for the larger scale of the ONS replacement plant) and during operations to average 500 (Duke 1998).

Additional water would be needed for controlling wet-scrubber sulfur dioxide emissions and for boiler makeup.

  •  
Land Use
Based on Duke's operating experience, approximately 900,000 MT (1,000,000 tons) of solid waste per year would be generated, including 630,000 MT (700,000 tons) of flyash and bottom ash, selective catalytic reduction (SCR) catalyst (used for nitrogen oxides control), and sulfur oxide scrubber sludge/waste. Approximately 90 percent of the 630,000 MT (700,000 tons) of this ash would be flyash, and the remaining 10 percent would be bottom ash, depending on the type of coal burned and the type of emission control equipment used. The SCR catalyst would generate approximately 230 m3 (8000 ft3) of spent catalyst material per year. This catalyst material would have high concentrations of metals that are removed from the fly ash. A new coal-fired facility would also require sulfur oxides scrubbers to be installed as emission control equipment. This would result in the generation of approximately 350,000 MT (387,000 tons) per year of scrubber sludge. Facilities would be constructed to control and treat leachate from ash and scrubber waste

Table 8-2. Summary of Environmental Impacts from Coal Alternative--Once-Through Cooling

  Oconee Site Alternative "Greenfield" Site
Impact Category Impact Comments Impact Comments
Land Use MODERATE Uses another 220 ha (550 acres) within or adjacent to ONS site, plus 25 ha (60 acres) for 13-16 km (8-10  mi) rail line MODERATE to LARGE 200 ha (500 acres) to 800 ha (2000 acres), including transmission lines
Ecology MODERATE Uses undeveloped areas in current ONS site plus other nearby land, plus rail corridor MODERATE to LARGE Impact will depend on ecology of site
Water Use and Quality        
- Surface Water SMALL Uses existing intake and discharge structures

Volume 1 m3/sec (16,000) gpm and temperature rise same as ONS

SMALL to MODERATE Impact will depend on volume and other characteristics of receiving water
- Groundwater SMALL Little groundwater is currently used at ONS. This practice likely would continue SMALL to LARGE Impact will depend on site characteristics and availability of groundwater
Air Quality MODERATE Sulfur oxides MODERATE Same impacts as Oconee site, although pollution control standards may vary
    -11,800 MT (13,000 tons)/yr    
    -allowances required    
    Nitrogen oxides    
    -11,800 MT (13,000 tons)/yr    
    -allowances required    
    Particulate    
    -1600 MT (1800 tons)/yr    
    Carbon monoxide    
    -1600 MT (1800 tons)/yr    
    Carbon dioxide    
    -16 million MT (18 million tons)/yr    
    VOC    
    -190 MT (210 tons)/yr    
    Trace amounts of mercury, arsenic, chromium, beryllium, selenium    
Waste MODERATE Total waste volume would be 900,000 MT (1,000,000 tons)/yr of ash and scrubber sludge MODERATE Same impacts as Oconee site; waste disposal constraints may vary
Human Health SMALL Impacts considered minor SMALL Same impact as Oconee site
Socioeconomics MODERATE 1500 to 2500 additional workers during 5-year construction period, followed by reduction from current 1700 workforce to 500 persons MODERATE TO LARGE Construction impacts would be relocated. Community near ONS would still experience reduction from 1700 persons to 0 persons
Aesthetics MODERATE to LARGE Visual impact of large industrial facility and stacks would be significant MODERATE to LARGE Alternate locations could reduce aesthetic impact if siting is in an industrial area
Archeological and Historical Resources SMALL Affects previously developed parts of current ONS site, nearby land, and 13-16 km (8-10-mi) rail corridor SMALL Alternate location would necessitate cultural resource studies
Environmental Justice MODERATE Impacts on low income and minority communities should be similar to those experienced by the population as a whole. Some impacts on housing are likely. SMALL to LARGE Impacts will vary depending on population distribution and make up
disposal areas and runoff from coal storage areas. These facilities are included in the land-use estimates. The existing switchyard and transmission system would be used. Duke assumed that between 220 ha (550 acres) and 800 ha (2000 acres) would be required based on the Marshall and Belews Creek Duke coal-fired power plants. It is assumed that coal-fired generation structures and facilities, including coal storage and waste disposal, would be located in one or more of the unused areas of the Oconee site and on adjacent Duke-owned land.
As described above, the coal-fired generation alternative would necessitate converting roughly an additional 220 ha (550 acres) of the Duke-owned land across Highway 130 or 183 from the ONS (the current site is only 207 ha [512 acres]) to industrial use (plant, coal storage, and ash and scrubber sludge disposal), expanding the altered area at the site from 200 ha (500) acres to over 400 ha (1000 acres). The land surrounding ONS is owned by one of Duke's subsidiaries and could most likely be made available.
In addition, a new rail line would have to be built between Newry and the ONS site (13 to 16 km [8 to 10 mi]) requiring approximately 25 ha (60 acres) to bring the coal to the site. The impact of coal-fired generation on land use is best characterized as MODERATE; its impact would be greater than the proposed action.
In contrast, land use for a coal-fired generation alternative using once-through cooling at an alternative greenfield site would require 4 ha (10 acres) for offices, roads, etc. This is in addition to up to 800 ha (2000 acres) for generating facilities and cooling structures, coal storage ash basin, and flyash disposal discussed previously. Additional land might be needed for transmission lines, depending on the location of the site relative to the nearest intertie connection. Depending on the transmission line routing, these alternatives could result in MODERATE or LARGE land-use impacts consistent with the GEIS characterization of land use at a greenfield site.
  •  
Ecology
Locating an alternate energy source at the existing ONS site would noticeably alter ecological resources because of using additional undeveloped areas and modifying the existing intake and discharge system. The impact to the Lake Keowee ecology would be expected to remain unchanged because the once-through cooling system at ONS has not shown significant negative impact to the lake. The appropriate characterization of coal-fired generation ecological impacts of the ONS site would be MODERATE; its impact would be greater than the proposed action.
Constructing a coal-fired plant at a greenfield site, particularly one sited in a rural area with considerable natural habitat, would certainly alter the ecology and could impact any endangered or threatened species present at the site. These ecological impacts could be MODERATE to LARGE, consistent with the GEIS characterization of ecological impacts at a greenfield site.
  •  
Water Use and Quality
Surface Water. The coal-fired generation alternative is assumed to use the existing ONS intake and discharge structures as part of a once-through cooling system. This alternative would minimize environmental impacts since minimal construction would be required to adapt the system to the coal-fired alternative. It is assumed that the coal-fired alternative cooling water volume (1 m3/sec [16,000 gpm]) and temperature rise would be approximately the same as for the current nuclear plant. This temperature rise would comply with the existing ONS National Pollutant Discharge Elimination System (NPDES) permit. The GEIS analysis determined that surface water quality, hydrology, and use impacts for license renewal would be SMALL. Because the coal-fired generation alternative is assumed to have the same discharge characteristics as ONS, surface water impacts are expected to remain SMALL; the impacts would be so minor that they would not noticeably alter any important attribute of the resource.
For alternative greenfield sites, the impact to the surface water would depend on the volume associated with the cooling system and characteristics of the receiving body of water. The impacts would be SMALL or MODERATE.
Groundwater. No variation would be expected in the amount of groundwater used, since groundwater wells only are used to supply water for drinking and the restroom facility at the station baseball field, as well as to supply irrigation water for site landscaping during the summer months (June through September). However, the leachate from ash and scrubber waste disposal areas and runoff from coal storage areas would have to be controlled to avoid groundwater and surface water contamination. For this reason, the appropriate characterization of coal-fired generation groundwater impacts would be SMALL; the impacts would be so minor that they would not noticeably alter any important attribute of the resource.
For alternative greenfield sites, the impact to the groundwater would depend on the site characteristics, including the amount of groundwater available. The impacts would range between SMALL and LARGE.
  •  
Air Quality
Air quality impacts of coal-fired generation vary considerably from those of nuclear power due to emissions of sulfur oxides, nitrogen oxides, particulates, and carbon monoxide. Although the entire State of South Carolina and the nearby areas of North Carolina and Georgia are currently in attainment for meeting National Ambient Air Quality Standards, the Oconee site is within 80 km (50 mi) of two Prevention of Significant Deterioration Class I areas (Great Smoky Mountains National Park and Shining Rock Wilderness Area) that would be of concern for a major coal-fired plant. Also, future economic and population growth may make future compliance more difficult.
Sulfur oxides emissions. Using current control technology for sulfur oxides emissions, the total annual stack emissions would include approximately 11,800 MT (13,000 tons) of sulfur oxides, most of which would be sulfur dioxide. Additional reductions could become necessary. The acid rain provision of the Clean Air Act (CAA) (Sections 403 and 404) capped the nation's sulfur dioxide emissions from power plants. Under the Act, affected fossil-fired steam units are allocated a number of sulfur dioxide emission allowances. To achieve compliance, each utility must hold enough allowances to cover its sulfur dioxide emissions annually or be subject to certain penalties. If the utility's sulfur dioxide emissions are less than its annually allocated emission allowances, then the utility may bank the surplus allowances for use in future years. A sulfur dioxide allowances market has been established for the buying and selling of allowances. Duke has sulfur dioxide allowances for its existing coal-fired plants; however, Duke would have to purchase additional allowances to operate an additional coal-fired plant (Duke 1999b). Because of allowances, any major new combustion facility in South Carolina would not add sulfur dioxide impacts on a regional basis, though it might do so locally.
Nitrogen oxides emissions. Using currently available control technology, the total annual nitrogen oxides emission would be approximately 11,800 MT (13,000 tons). Section 407 of the CAA establishes an annual reduction program for the nitrogen oxides emissions program. The new EPA 8-hour ozone standard, the new EPA PM2.5 particulate standard, and Regional Haze rules create additional burdens on coal use. To cite one example, the South Carolina Department of Health and Environmental Control (SCDHEC) has identified several counties that may be impacted, including Anderson and Greenville Counties, as well as counties of concern, including Oconee and Anderson Counties (South Carolina Air Quality Annual Report Volume XVII, 1997 [SCDHEC 1998]). To implement a coal-fired alternative, Duke might be required to offset its corporate nitrogen oxides emissions through further reductions in nitrogen oxides emissions elsewhere by shutting other sources down or by back-fitting to reduce nitrogen oxides formation (e.g., installing over-fired air, low nitrogen oxides burners, flue gas re-circulation, and selective non-catalytic and catalytic reduction systems). Alternatively, offsets might be available for purchase on the open market. A major new combustion facility would not add to net regional emissions, although it might do so locally.
Particulate emissions. The total estimated annual stack emissions would include 1600 MT (1800 tons) of particulate matter having a diameter of 10 microns or less (PM10). In addition, coal handling equipment would introduce fugitive particulate emissions.
Carbon monoxide emissions. The total carbon monoxide emissions would be approximately 1600 MT (1800 tons) per year.
Carbon dioxide emissions. The total carbon dioxide emissions would be approximately 16 million MT (18 million tons) per year.
Mercury. Coal-fired boilers account for nearly a third of mercury emissions in the United States. Technologies available to control mercury emissions have varying degrees of success. In response to growing concerns with mercury, the CAA Amendments of 1990 have required the EPA to identify mercury emission sources, evaluate the contributions of power plants and municipal incinerators, identify control technologies, and evaluate the toxicological effects from the consumption of mercury-contaminated fish. It is likely that these studies will lead to additional restrictions concerning mercury emissions associated with coal-fired power plants, as well as other sources of mercury emissions. Recent studies by the Maryland Power Plant Research Program have indicated that although coal-fired power plants contribute to mercury emissions, the resulting concentrations are not high enough to adversely affect humans or other organisms (Maryland Department of Natural Resources 1999). Therefore, the probable effect of trace mercury emissions on human health would be SMALL.
The GEIS analysis did not quantify coal-fired emissions, but implied that air impacts would be substantial and mentioned global warming and acid rain as potential impacts. Adverse human health effects from coal combustion have led to important Federal legislation in recent years, and public health risks, such as cancer and emphysema, have been associated with the products of coal combustion. Federal legislation and large-scale concerns, such as acid rain and global warming, are indications of concerns about air resources. Sulfur oxide emission allowances, nitrogen oxide emission offsets, low nitrogen oxide burners, overfire air, selective catalytic reduction, fabric filters or electrostatic precipitators, and scrubbers may be required as mitigation measures. As such, the appropriate characterization of coal-fired generation air impacts would be MODERATE. The impacts would be clearly noticeable, but would not destabilize air quality.
Siting the coal-fired generation elsewhere would not significantly change air quality impacts, although it could result in installing more or less stringent pollution control equipment to meet applicable standards. Therefore, the impacts would be MODERATE.
  •  
Waste
Coal combustion generates waste in the form of ash, and equipment for controlling air pollution generates additional ash and scrubber sludge. Based on Duke experience at two coal-fired plants, approximately 900,000 MT (1,000,000 tons) of this waste would be generated annually for 40 years and disposed of onsite, accounting for between 60 percent and 40 percent of land used at the site (120 out of 200 ha to 160 out of 800 ha [300 out of 500 acres to 400 out of 2000 acres]). While only half of these values are directly attributable to the alternative to a 20-year ONS license renewal, the total values are pertinent as a cumulative impact. This impact could extend well after the 40-year operation life because revegetation management and groundwater monitoring for leachate contaminant impacts could be a permanent requirement.
The GEIS analysis concluded that large amounts of fly ash and scrubber sludge would be produced and would require constant management. Disposal of this waste could noticeably affect land use and groundwater quality, but with appropriate management and monitoring, it would not destabilize any resources. After closure of the waste site and revegetation, the land would be available for other uses, and regulatory requirements would ensure groundwater protection. For these reasons, the appropriate characterization of impacts from waste generated from burning coal would be MODERATE; the impacts would be clearly noticeable, but would not destabilize any important resource.
Siting the facility on an alternate greenfield site would not alter waste generation, although other sites might have more constraints on disposal locations. Therefore, the impacts would be MODERATE.
  •  
Human Health
Coal-fired power generation introduces worker risks from fuel and lime/limestone mining and worker and public risks from fuel and lime/limestone transportation and stack emissions inhalation. Stack impacts can be very widespread and health risks difficult to quantify. This alternative also introduces the risk of coal-pile fires and attendant inhalation risks.
The GEIS analysis noted that there could be human health impacts (cancer and emphysema) from inhalation of toxins and particulates, but did not identify the significance of this impact. Regulatory agencies, such as the EPA and SCDHEC, focus on air emissions and revise regulatory requirements or propose statutory changes, based on human health impacts. Such agencies also impose site-specific emission permit limits as needed to protect human health. Thus, human health impacts from inhaling toxins and particulates generated by burning coal would be SMALL.
Using the same logic, siting the facility at an alternate greenfield site would not alter the expected human health effects. Therefore, the impacts would be SMALL.
  •  
Socioeconomics
Construction of the coal-fired alternative would take approximately 5 years. It is assumed that construction would take place concurrently while ONS continues operation and would be completed at the time ONS would cease operations. Thus, the workforce would be expected to average 1500 with a peak of 2500 additional workers during the 5-year construction period, based on estimates given in the GEIS (NRC 1996) and scaled for the large plant size. The surrounding communities would experience demands on housing and public services that could have large impacts. After construction, the communities would be impacted by the loss of jobs; construction workers would leave, the nuclear plant workforce (1700) would decline through a decommissioning period to a minimal maintenance size, and the coal-fired plant would introduce only 500 new jobs.
The GEIS analysis concluded that socioeconomic impacts at a rural site would be larger than at an urban site because more of the 1200 to 2500 peak construction workforce would need to move to the area to work. While the site is not rural within the meaning of the GEIS, the facility is roughly twice the size examined in the GEIS. Operational impacts could result in moderate socioeconomic benefits in the form of several hundred additional jobs, substantial tax revenues, and plant expenditures.
The size of the construction workforce for a coal-fired plant and plant-related spending during construction would be noticeable. However, due to the site's proximity to large labor pools in the Greenville and Spartanburg areas, significant numbers of construction workers would not be expected to move to the ONS area. Operational impacts would include an eventual loss of approximately 1200 jobs (1700 for three nuclear units down to 500 for the coal-fired plant), with a commensurate reduction in demand on socioeconomic resources and contribution to the regional economy. The area's rapid population growth and the replacement industrial tax base resulting from the coal-fired power plant would prevent any destabilization of socioeconomic resources. For these reasons, the appropriate characterization of socioeconomic impacts for a coal-fired plant would be MODERATE; the impacts would be clearly noticeable, but would not destabilize any important resource.
Construction at another site would relocate some socioeconomic impacts, but would not eliminate them. The community around ONS would still experience the impact of ONS operational job loss, and the communities around the new site would have to absorb the impacts of a large, temporary workforce and a moderate, permanent workforce. Therefore, the impacts are MODERATE to LARGE, based on the adverse effects on the employment and the tax base in Oconee County, which would be similar to those of the no-action alternative.
  •  
Aesthetics
Plant structures (the stacks) would be visible over intervening trees for kilometers around, particularly along Lake Keowee. This view would contrast strongly with what is otherwise a natural-appearing vacation-home and rural area, with woods and farming areas. Coal-fired generation would also introduce additional mechanical sources of noise (e.g., induced-draft fans and coal-handling equipment) that may be audible offsite due to their proximity to Lake Keowee.
The GEIS concluded that aesthetic impacts from such a large construction effort in a rural area could be substantial. Industrial structures that would be located at the Oconee site would tower above area vegetation and create a noticeable visual impact for a large area. Aesthetics is a significant attribute of Lake Keowee, given the predominantly natural-appearing rural viewscape from the lake and shoreline. A coal-fired generating station would contrast strongly with the existing resource. The aesthetics impacts would be MODERATE to LARGE, noticeable but not destabilizing.
Alternative locations could reduce the aesthetic impact of coal-fired generation if siting were in an area that was already industrialized. In such a case, however, the introduction of such tall stacks and cooling towers would probably still have a MODERATE incremental impact. Other sites could show a LARGE impact.
  •  
Archaeological and Historical Resources
The GEIS analysis concluded that impacts to cultural resources would be relatively SMALL unless important site-specific resources were affected. Under this alternative, cultural resource inventories would be required for any lands that have not been previously disturbed to the extent that no archaeological or historical resources might remain. Other lands that are purchased to support the facility would also require an inventory of field cultural resources, identification and recording of extant archaeological and historical resources, and possible mitigation of adverse effects from subsequent ground-disturbing actions related to physical expansion of the plant site. Therefore, the impacts would be SMALL.
Construction at another site would necessitate studies to identify, evaluate, and mitigate potential impacts of new plant construction on cultural resources. This would be required for all areas of potential disturbance at the proposed plant site and along associated corridors where new construction would occur (e.g., roads, transmission corridors, or other rights-of-way). Impacts can generally be managed and maintained as SMALL.
  •  
Environmental Justice
No environmental pathways have been identified that would result in disproportionately high and adverse environmental impacts on low-income and minority populations if a replacement coal-fired plant were built at the ONS site. Some impacts on housing availability and prices during construction might occur, and this could disproportionately affect the low-income and minority populations. Impacts at other sites would depend upon the site chosen. These impacts would be MODERATE.
If the replacement plant were built in Oconee County, the county's tax base would be largely maintained, and some potential negative socioeconomic impacts on the low-income or minority populations would be avoided. If the plant were built elsewhere, environmental justice impacts would be SMALL to LARGE, depending on the plant location and nearby population distribution.

8.2.1.2 Closed-Cycle Cooling System

This section describes the differences in impacts of using a mechanical draft closed-cycle cooling system at a coal-fired power plant that would replace ONS. These differences would be roughly the same at both the Oconee site and other greenfield sites. Mechanical draft cooling towers are 15 m (50 ft) to 30 m (100 ft) tall. Based on Duke's experience with similar cooling towers at the Catawba Nuclear Station, cooling water consumption would be approximately 1.5 m3/s (24,000 gpm) (Duke 1999a) and land-use requirements would be 10 to 12 ha (25 to 30 acres). The closed-cycle cooling system would introduce cooling tower blowdown that would be much higher in dissolved solids in comparison to Lake Keowee. Cooling tower operation would require more electrical power than the once-through cooling system due to the modified pumping systems. The towers would discharge a plume of water vapor and a measurable amount of cooling tower drift.

The changes in environmental impacts from redesigning the site for cooling towers are listed in Table 8-3. The overall impacts are also discussed below.

  •  
Land Use
A closed-cycle cooling system alternative would impact an additional 10 to 12 ha (25 to 30 acres) for cooling tower construction at either the greenfield site or the ONS site (Duke 1999). These alternatives would result in a minor to moderate change above those already considered for the once-through cooling alternative. The overall impact would be MODERATE at ONS, MODERATE to LARGE elsewhere.

Table 8-3. Summary of Environmental Impacts from Alternate Cooling System
(Cooling Towers with Closed-Cycle Cooling)

Impact Category Change in Impact from ONS Once-Through Cooling Comments
Land Use Minor to moderate change 10-12 additional ha (25-30 acres) required
Ecology Minor change Additional impact to terrestrial ecology from cooling tower drift

Reduced impact to aquatic ecology

Water Use and Quality    
Surface Water Minor change Blowdown has higher dissolved solids

Reduced flow/Less thermal load

Groundwater No change None
Air Quality No change None
Waste No change None
Human Health No change None
Socioeconomics No change None
Aesthetics Small change Addition of 30-m (100-ft) high cooling towers

Noise from mechanical draft towers and vapor plume

Archaeology and Historical Resources Minor change Minimal cultural studies possibly required
Environmental Justice No change None
  •  
Ecology
The closed-cycle cooling system alternative would further reduce operational aquatic ecology impacts, but would introduce risk to vegetation from salt drift. However, these ecological impacts result in minor changes above those for the once-through cooling alternative, resulting in MODERATE overall impacts at ONS and MODERATE to LARGE impacts elsewhere.
  •  
Water Use and Quality
Surface Water. Although surface water impacts are expected to remain small, the closed-cycle cooling system alternative would introduce cooling tower blowdown that would have higher dissolved solids. However, because of the reduced flow, changes that impact surface water quality would result in minor changes above those already considered for the once-through cooling alternative. Thermal load would be less than with a once-through cooling system. The overall impact would be SMALL at ONS.
For alternative greenfield sites, the impact to the surface water would depend on the volume associated with the cooling system and characteristics of the receiving body of water. The impacts would be SMALL or MODERATE.
Groundwater. The facility's use of groundwater would not be impacted as a result of the variation between a once-through cooling system and a cooling tower-based system. Overall impacts would be SMALL at ONS.
For alternative greenfield sites, the impact to the groundwater would depend on the site characteristics, including the amount of groundwater available. The impacts would range between SMALL and LARGE.
  •  
Air Quality
The air quality would be the same whether a cooling tower-based closed-cycle cooling system or a once-through cooling system was used. Overall impacts would be MODERATE at all locations.
  •  
Waste
The amount of waste and impacts resulting from waste disposal would be the same whether a cooling tower-based closed-cycle cooling system or a once-through cooling system was used. Overall impacts would be MODERATE at all locations.
  •  
Human Health
Human health effects would be the same whether a cooling tower-based closed-cycle cooling system or a once-through cooling system was used. Overall impacts would be SMALL at all locations.
  •  
Socioeconomics
Socioeconomic impacts would be the same whether a cooling tower-based closed-cycle cooling system or a once-through cooling system was used. Overall impacts would be MODERATE at Oconee, MODERATE to LARGE elsewhere.
  •  
Aesthetics
The closed-cycle cooling system alternative would add 15-m (50-ft) to 30-m (100-ft) tall mechanical draft towers and associated plumes. Mechanical draft towers introduce another noise source. This would be a small incremental change. Overall impacts would be MODERATE to LARGE at all locations.
  •  
Archaeological and Historical Resources
Minimal amounts of additional cultural resource studies would be required before construction of cooling towers. If towers were constructed on land that had already had cultural resource studies, further studies would not be necessary. This would be a minor incremental change. Overall impacts would be SMALL at all locations.
  •  
Environmental Justice
Environmental justice impacts would be the same whether a cooling tower-based closed-cycle cooling system or a once-through cooling system was used. Overall impacts are MODERATE at ONS, SMALL to MODERATE elsewhere.

8.2.2 Gas-Fired Generation

It was assumed that a replacement natural gas-fired plant would use combined cycle technology. In the combined cycle unit, hot combustion gases in a combustion turbine rotate the turbine to generate electricity. Waste combustion heat from the combustion turbine is routed through a heat-recovery steam generator to generate additional electricity. The size, type, and configuration of gas-fired generation units and plants currently operational in the United States vary and include simple-cycle combustion and combined-cycle units that range in size from 25 MW to 600 MW (EPA 1994). As with coal-fired technology, units may be configured and combined at a location to produce the desired amount of megawatts, and construction can be phased to meet electrical power needs.

Section 8.2.2.1 discusses the environmental impacts of converting the current ONS site to a natural gas-fired generation facility with once-through cooling and building a similar facility on a greenfield site. Differences in impacts with closed-cycle cooling are discussed in Section 8.2.2.2.

8.2.2.1 Once-Through Cooling System

Providing 2500 MW of replacement power with a combined cycle would require a minimum of 5 units. Natural gas typically has an average heating value of 3.7 × 107 J/m3 (1,000 Btu per cubic foot) (DOE 1996; EPA 1993), and it would be the primary fuel; the gas-fired alternative plant would burn approximately 1.24 J/m3-s (100 billion cubic feet per year). Low-sulfur No. 2 fuel oil would be the backup fuel (Duke 1998), but due to the relatively high cost of fuel oil, would not be the primary fuel for this technology. The discussion in this section addresses some of the differences in the impacts between gas- and oil-fired combustion turbine/combined cycle power plants.

As a surrogate for a similar-sized gas-fired alternative plant, the staff used Baltimore Gas and Electric's Perryman Power Plant and Polk Power Plant (BGE 1989; EPA 1984). The staff assumes that each unit would be less than 30 m (100 feet) high and would be designed with dry, low nitrogen oxides combusters, water injection, and selective catalytic reduction.

Each unit would exhaust through a 70-m (230-foot) stack after passing through heat-recovery steam generators. This stack height is consistent with EPA regulations (40 CFR 51.100), which address requirements for determining the stack height of new emission sources.

Natural gas would have to be delivered via pipeline. Approximately 60 ha (150 acres) would be disturbed during pipeline construction. The nearest gas pipeline large enough to support a new combined cycle plant is at Anderson, near Interstate 85, approximately 40 km (25 mi) from the Oconee site. Construction cost of installing a gas line to Oconee averages approximately $1 million per mile (Duke 1999b). Duke believes that the installation of a gas line to the Oconee site would not be economical and would require an additional 60 ha (150 acres) of land (Duke 1999b). To the degree existing rights-of-way could be used, the level of impact could be reduced.

Environmental impacts of conversion to the gas-fired generation option at both ONS and a "greenfield" site are summarized in the following text and are listed in Table 8.4.

  •  
Land Use
Gas-fired generation at the Oconee site would require converting a minimum additional 24 ha (60 acres) of the site and adjacent land to industrial use. Almost all would be used for the power block. Some, if not all of the land, would require clearing of wooded or vegetated areas since the existing industrial wooded area on the site is too small to accommodate the entire facility. An additional 60 ha (150 acres) would be disturbed during pipeline construction. Some additional land would also be required for backup oil storage tanks. Gas-fired generation land-use impact at the existing ONS site is MODERATE; the impact would noticeably alter habitat, but it would not destabilize any important attribute of the resource.

Table 8-4. Summary of Environmental Impacts from Gas-Fired Generation-Once-Through Cooling Alternative

  Oconee Site Alternative "Greenfield" Site
Impact Category Impact Comments Impact Comments
Land Use MODERATE Additional 24 ha (60 acres) required for power block

Additional 60 ha (150 acres) disturbed for pipeline construction

Additional land for backup oil storage tanks

SMALL to MODERATE Up to 200 ha (500 acres) required for site pipelines and an estimated 16-km (10-mi) transmission line connection.

Additional land for backup oil storage tanks

Ecology MODERATE Constructed on land adjacent to Oconee site. Significant habitat loss due to pipeline construction SMALL to MODERATE Impact depends on location and ecology of the site
Water Use and Quality        
Surface Water SMALL 70% reduction in water flow SMALL to MODERATE Impact depends on volume and characteristics of receiving body of water
Groundwater SMALL Reduced groundwater withdrawals due to reduced workforce SMALL to LARGE Groundwater would be used for potable water only
Air Quality MODERATE Primarily nitrogen oxides MODERATE Same impacts as for Oconee site
-4300 MT/yr (4,700 tons/yr) with gas
-11,800 MT/yr (13,000 tons/yr) with fuel oil
Sulfur dioxide
-3600 MT/yr (4,000 tons per yr) with fuel oil, none with gas
Particulates
-2300 MT/yr (2,500 tons/yr) with fuel oil
-280 MT/yr (310 tons/yr) with gas
Carbon dioxide
-11 million MT/yr (12.5 million tons/yr) with fuel oil
-8 million MT/yr (9.2 million tons/yr) with gas
Waste SMALL Waste generation is 230 m3/yr, 2500 (ft3/yr) of spent catalyst with fuel oil, minor with gas SMALL Same impacts as for Oconee site
Human Health SMALL Impacts considered to be minor SMALL Same impacts as for Oconee site
Socioeconomics SMALL to MODERATE 500 to 750 additional workers during 3-year construction period; followed by reduction from 1700 persons to 300 persons (400 if fuel oil is used) MODERATE to LARGE Construction impacts would be relocated. Community near ONS would still experience reduction from 1700 persons to 0 persons.
Aesthetics SMALL to MODERATE Visual impact of stacks and equipment would be noticeable, but not as significant as coal option SMALL to MODERATE Alternate locations could reduce the aesthetic impact if siting is in an industrial area.
Archaeological and Historical Resources SMALL Only previously disturbed and adjacent areas would likely be affected SMALL Alternate location would necessitate cultural resource studies
Environmental Justice SMALL to MODERATE Impacts on low-income and minority populations should be similar to those experienced by the population as a whole. Impacts on housing are possible. SMALL to MODERATE Impacts vary depending on population distribution and makeup

Construction at a greenfield site would impact approximately 8 ha (20 acres) to 20 ha (50 acres) for offices, roads, parking areas, and a switchyard. The power block would require 25 ha (60 acres). Some additional land would also be required for backup oil storage. In addition, it is assumed that another 170 ha (424 acres) would be necessary for transmission lines (assuming the plant is sited 16 km [10 mi] from the nearest intertie connection), although this is uncertain and would depend on the actual plant location. Plants of this type are usually built very close to existing natural gas pipelines. Including the land required for pipeline construction, a greenfield site would require approximately 200 ha (500 acres). Depending on the transmission line routing, the greenfield site alternative could result in SMALL to MODERATE land-use impacts.

The GEIS estimated that land-use requirements for a 1000-MW gas-fired plant at a greenfield site would be SMALL (approximately 45 ha [110 acres] for the plant site), and that co-locating with a retired nuclear plant would reduce these impacts. The Duke land-use estimate is about the same as the GEIS, even though the plant is larger. The land-use change should not noticeably alter the overall site pattern for natural land use. Therefore, the impacts would be SMALL to MODERATE, depending on the length and routing of required pipelines and transmission lines.

  •  
Ecology
Siting gas-fired generation at the existing ONS site would have MODERATE ecological impact because the facility would be constructed partly on previously disturbed areas and would disturb relatively little acreage at the site. However, significant habitat (60 ha [150 acres]) would be disturbed by 40 km (25 miles) of pipeline construction (Duke 1999b). To the extent that existing rights-of-way could be used, the impact would be reduced. Ecological impacts would also be minimized by using the existing intake and discharge system. Past operational monitoring of the effects of once-through cooling at ONS have not shown significant negative impacts to Lake Keowee ecology, and this would be expected to remain unchanged. At the existing site, adding gas-fired generation would introduce construction impacts and new, albeit incremental, operational impacts.
The GEIS noted that land-dependent ecological impacts from construction would be SMALL unless site-specific factors should indicate a particular sensitivity and that operational impacts would be smaller than for other fossil fuel technologies of equal capacity. The staff has identified the gas pipeline as a site-specific factor that would make gas-fired alternative ecological impacts larger than for the license renewal. Therefore, in this case, the appropriate characterization of gas-fired generation ecological impacts would be MODERATE.
Construction at a greenfield site could alter the ecology of the site and could impact threatened and endangered species. These ecological impacts could be SMALL to MODERATE.
  •  
Water Use and Quality
Surface Water. The plant would use the existing ONS intake and discharge structures as part of a once-through cooling system; however, because cooling requirements would be less (70 percent reduction; EPA 1994), water quality impacts would continue to be SMALL.
Water quality impacts from sedimentation during construction was another land-related impact that the GEIS categorized as SMALL. The GEIS also noted that operational water quality impacts would be similar to, or less than, those from other centralized generating technologies. The staff has concluded that water quality impacts from coal-fired generation would be SMALL, and gas-fired alternative water usage would be less than that for coal-fired generation. Surface water impacts would remain SMALL; the impacts would not be detectable or be so minor that they would not noticeably alter any important attribute of the resource.
For alternative greenfield sites, the impact on surface water would depend on the volume and other characteristics of the receiving body of water. The impacts would be SMALL to MODERATE.
Groundwater. No variation would be expected in the amount of groundwater used since groundwater wells only are used to supply water for drinking and the restroom facility at the station baseball field as well as to supply irrigation water for site landscaping during the summer months (June through September). The groundwater impacts would be SMALL; the impacts would be so minor that they would not noticeably alter any important resource.
For alternative greenfield sites, the impact to the groundwater would depend on the site characteristics, including the amount of groundwater available. The impacts would range between SMALL and LARGE.
  •  
Air Quality
Natural gas is a relatively clean-burning fuel. Because the ONS is not or not nearly a nonattainment area for ozone, air quality impacts of gas-fired generation would not be of concern. Nitrogen oxides emissions from the gas-fired alternative would be 4300 MT (4700 tons) with gas to 11,800 MT (13,000 tons) with fuel oil per year.
The GEIS noted that gas-fired air quality impacts are less than other fossil technologies because fewer pollutants are emitted, and sulfur dioxide is not emitted at all. Emissions from the gas-fired alternative would be less than emissions from the coal-fired alternative. However, the gas-fired alternative would contribute nitrogen oxides emissions to an area that in the future may become a nonattainment area for ozone. Because nitrogen oxides contribute to ozone formation, the reduced nitrogen oxides emissions are still of future concern, and low nitrogen oxides combusters, water injection, and selective catalytic reduction could become regulatory-imposed mitigation measures.
For these reasons, the appropriate characterization of air impacts from a gas-fired plant would be MODERATE; the impacts, primarily nitrogen oxides, would be clearly noticeable, but would not be sufficient to destabilize air resources as a whole.
Siting the gas-fired plant elsewhere would not significantly change air quality impacts because the site could also be located in a greenfield area that was not a serious nonattainment area for ozone. In addition, the location could result in installing more or less stringent pollution control equipment to meet the regulations. Therefore, the impacts would be MODERATE.
  •  
Waste
There will be only small amounts of solid waste products (i.e., ash) from burning natural gas fuel. The GEIS concluded that waste generation from gas-fired technology would be minimal. Gas-firing results in very little combustion byproducts because of the clean nature of the fuel. Waste generation would be limited to typical office wastes. This impact would be SMALL; waste generation impacts would be so minor that they would not noticeably alter any important resource attribute.
Siting the facility at an alternate greenfield site would not alter the waste generation; therefore, the impacts would continue to be SMALL.
  •  
Human Health
The GEIS analysis mentions potential gas-fired alternative health risks (cancer and emphysema). The risk may be attributable to nitrogen oxides emissions that contribute to ozone formation, which in turn contributes to health risks. As discussed in Section 8.2.1 for the coal-fired alternative, legislative and regulatory control of the nation's emissions and air quality are protective of human health, and the appropriate characterization of gas-fired generation human health impacts would be SMALL; that is, human health effects would not be detectable or would be so minor that they would neither destabilize nor noticeably alter any important attribute of the resource.
Siting of the facility at an alternate greenfield site would not alter the human health effects that would be expected. Therefore, the impacts would be SMALL.
  •  
Socioeconomics
It is assumed that gas-fired construction would take place while ONS continues operation, with completion at the time that the nuclear plant would halt operations. Construction of the gas-fired alternative would take much less time than constructing other plants (NRC 1996). During the time of construction, the surrounding communities would experience demands on housing and public services that could have moderate impacts. After construction, the communities would be impacted by the loss of jobs; construction workers would leave, the nuclear plant workforce (1700) would decline through a decommissioning period to a minimal maintenance size, and the gas-fired plant would introduce a replacement tax base and about 300 (or for an oil-fired plant, 400) new jobs.
The GEIS concluded that socioeconomic impacts from constructing a gas-fired plant would not be very noticeable and that the small operational workforce would have the lowest socioeconomic impacts (local purchases and taxes) of any nonrenewable technology. Compared to the coal-fired alternative, the smaller size of the construction workforce, the shorter construction time frame, and the smaller size of the operations workforce would all reduce some of the socioeconomic impacts. For these reasons, gas-fired generation socioeconomic impacts would be SMALL to MODERATE; that is, depending on other growth in the area, socioeconomic effects could be noticed, but they would not destabilize any important attribute of the resource.
Construction at another site would relocate some socioeconomic impacts, but would not eliminate them. The community around the ONS site would still experience the impact of the loss of ONS operational jobs and the tax base. The communities around the new site would have to absorb the impacts of a moderate, temporary workforce and a small, permanent workforce. Therefore, the impacts would be MODERATE to LARGE, based on net job and tax base losses in the Oconee area. This impact is about the same in the Oconee area under the no-action alternative.
  •  
Aesthetics
The combustion turbines and heat-recovery boilers would be relatively low structures and would be screened from most offsite vantage points by intervening woodlands. The steam turbine building would be taller, approximately 30 m (100 feet) in height, and together with 70-m (230-foot) exhaust stacks, would be visible offsite.
The GEIS analysis noted that land-related impacts, such as aesthetic impacts, would be small unless site-specific factors indicate a particular sensitivity. As in the case of the coal-fired alternative, aesthetic impacts from the gas-fired alternative would be noticeable. However, because the gas-fired structures are shorter than the coal-fired structures and more amenable to screening by vegetation, the staff determined that the aesthetic resources would not be destabilized by the gas-fired alternative. For these reasons, the appropriate characterization of aesthetic impacts from a gas-fired plant would be SMALL to MODERATE; the impacts would be clearly noticeable, but would not destabilize this important resource.
Alternative locations could reduce the aesthetic impact of gas-fired generation if siting were in an area that was already industrialized. In such a case, however, the introduction of the steam generator building, stacks, and cooling tower plumes would probably still have a SMALL to MODERATE incremental impact.
  •  
Archaeological and Historical
The GEIS analysis noted, as for the coal-fired alternative, that gas-fired alternative cultural resource impacts would be small unless important site-specific resources were affected. Gas-fired alternative construction at the ONS site would affect a smaller area within the footprint of the coal-fired alternative. As discussed in 8.2.1, site knowledge minimizes the possibility of cultural resource impacts. Cultural resource impacts would be SMALL; that is, cultural resource effects would not be detectable or would be so minor that they would neither destabilize nor noticeably alter any important attribute of the resource.
Construction at another site could necessitate instituting cultural resource preservation measures, but impacts can generally be managed and maintained as SMALL. Cultural resource studies would be required for the pipeline construction and any other areas of ground disturbance associated with this alternative.
  •  
Environmental Justice
No environmental pathways have been identified that would result in disproportionately high and adverse environmental impacts on low-income and minority populations if a replacement gas-fired plant were built at the ONS site. Some impacts on housing availability and prices during construction might occur, and this could disproportionately affect the low-income or minority populations. The impacts would be SMALL to MODERATE. Impacts at other sites would depend upon the site chosen. If the replacement plant were built in Oconee County, the county's tax base would be largely maintained, and some potential negative socioeconomic impacts on the low-income or minority populations would be avoided. If the plant were built elsewhere, environmental justice impacts would be SMALL to MODERATE, depending on the population distribution.

8.2.2.2 Closed-Cycle Cooling System

Cooling for the gas-fired facility could also be accomplished by a closed-cycle system, which would also use the existing intake and discharge structures, but flow requirements would be 90 percent less than the once-through cooling system (Gilbert/Commonwealth 1996). This alternative would use mechanical draft cooling towers that are 15-m (50-ft) to 30-m (100-ft) tall. Based on Duke's experience with similar cooling towers at the Catawba Nuclear Station, cooling water consumption would be approximately 1.5 m3/s (24,000 gpm) (Duke 1999a) and land-use requirements for the towers would be 10 to 12 ha (25 to 30 acres). The closed-cycle cooling system alternative would introduce a cooling tower blowdown that would be higher in dissolved solids in comparison to Lake Keowee. Cooling tower operation would require more electrical power than the once-through alternative due to the modified pumping systems. Cooling towers would discharge a plume of water vapor and a small amount of cooling tower drift. Thermal rise would be less than with once-through cooling.

The incremental environmental impacts of converting to a closed-cycle cooling system at a gas plant are essentially the same incremental impacts of converting to a closed-cycle cooling system at a coal-fired plant. The impacts are discussed in Section 8.2.1.2 and are listed in Table 8-5.

8.2.3. Imported Electrical Power

"Imported power" means power purchased and transmitted from electric generation plants that the applicant does not own and that are located elsewhere within the region, nation, or Canada. Duke purchases substantial amounts of capacity on the wholesale market. For example, requests for proposals in 1995 yielded numerous short- and long-term proposals, from which Duke purchased options for 250 MW of capacity from PECO Energy for the period 1998 through 2001 (Duke 1998). In theory, importing (purchasing) additional power is a feasible alternative to ONS license renewal.

Table 8-5. Summary of Environmental Impacts of Gas-Fired Generation with Alternate
Cooling System (Cooling Towers with Closed-Cycle Cooling)

Impact Category Change in Impact Oconee Once-Through Cooling Comments
Land Use Minor change Uses an additional 10 to 12 ha (25 to 30 acres) for cooling tower construction
Ecology Minor change Additional impact to terrestrial ecology from cooling tower drift;

Reduced impact to aquatic ecology

Water Use and Quality    
Surface Water Minor change Blowdown has higher dissolved solids ; Reduced flow
Groundwater No change None
Air Quality No change None
Waste No change None
Human Health Small Impacts considered minor
Socioeconomics No change None
Aesthetics Minor change Addition of 30-m (100-ft) high draft towers including noise and vapor plume
Archaeology and Historical Resources Minor change Minimal studies (if necessary) before construction of cooling towers
Environmental Justice No change None

However, Duke points out that there is no assurance that sufficient capacity or energy would be available in the 2013 through 2034 time frame to replace the 2500 MW(e) base load generation. More importantly, regardless of the technology used to generate imported power, the generating technology would be one of those described in this SEIS and in the GEIS (probably coal, natural gas, nuclear, or Canadian hydroelectric). The GEIS, Chapter 8, description of the environmental impacts of other technologies is representative of the imported electrical power alternative to ONS license renewal.

According to the Energy Information Administration's (EIA's) International Energy Outlook 1998 (EIA 1997),

   Hydro Quebec has targeted the U.S. market for future sales growth. Hydro Quebec currently owns Vermont Gas and has signed a deal with Enron to market electricity in the Northeast while selling Enron's gas in Quebec. In April 1997, Hydro Quebec petitioned the FERC (Federal Energy Regulatory Commission) to sell electricity in the United States. In return, it would allow U.S. competitors to wheel electricity into Quebec. In November 1997, Hydro Quebec received FERC approval to sell power in the United States at market-based rates.

Depending on transmission availability, relative power costs, whether Canadian environmental and aboriginal rights controversies over the hydroelectric James Bay Project in Northern Quebec could be solved, and appropriate transmission agreements and facilities could be put in place, Hydro Quebec could be a future source of imported power. However, there would be significant environmental impacts in Northern Quebec.

8.2.4 Other Alternatives

This section identifies alternatives to ONS license renewal that are not feasible as direct replacements for ONS and describes why the alternatives are not considered feasible.

8.2.4.1 Wind

Wind power in the northwest area of South Carolina averages less than 100 w/m2 (9.3 w/ft2) at 10 m (33 ft) elevation or 200 w/m2 (18.6 w/ft2) at 50 m (164 ft) per hour. This is the lowest class on the 7-point scale (Wind Energy Resource Atlas, PNL-3195 [Zabransky et al. 1981]). The National Wind Technology Center, a branch of the U.S. Department of Energy, classifies potential wind farm resource areas from Power Class 1 through Power Class 7. Areas designated as Class 4 or higher are considered as areas of potential wind farm development using advanced wind turbine technology under development today. Power Class 3 areas may be suitable for future generation technology. The average annual capacity factor was estimated by the applicant at 21 percent in 1995 and projected at 29 percent in 2010 (Duke 1998). This low capacity factor compared with current base load technologies (Oconee's capacity factor is 78 percent) results from the intermittency of the wind resource (DOE/EIA-0561). Current energy storage technologies are too expensive to permit wind power to serve as a large base load. Based on the GEIS land-use estimate for wind power (the GEIS, Section 8.3.1, estimates 60,750 ha [150,000 acres] per 1000 MW(e) for wind power), replacement of ONS generating capacity, even assuming ideal wind conditions, would require dedication of almost 150,000 ha (375,000 acres) in the area in which ONS is located. Given the amount of land required, a large greenfield site would be necessary, which would result in a LARGE environmental impact.

8.2.4.2 Solar

Solar power technologies, photovoltaic and thermal, cannot currently compete with conventional fossil-fueled technologies in grid-connected applications due to high costs per kilowatt of capacity (DOE 1995). The average capacity factor of photovoltaic cells is about 25 percent, and the capacity factor for solar thermal systems is about 25 percent to 40 percent. Energy storage requirements prevent the use of solar energy systems as base load. According to the GEIS, land requirements are also high-- 14,000 ha (35,000 acres) per 1000 MW(e) for photovoltaic and 6000 ha (14,000 acres) per 1000 MW(e) for solar thermal systems. Neither type of solar electric system would fit at the ONS site, and either would have large environmental impacts at a greenfield site.

8.2.4.3 Hydropower

Hydroelectric power has an average annual capacity factor of 46 percent. As GEIS, Section 8.3.4, points out, hydropower's percentage of the country's generating capacity is expected to decline because hydroelectric facilities have become difficult to site as a result of public concern over flooding, destruction of natural habitat, and destruction of natural river courses. GEIS, Section 8.3.4, estimates land use of 400,000 ha (1 million acres) per 1000 MW(e) for hydroelectric power. Based on this estimate, replacement of ONS generating capacity would require flooding more than 6700 km2 (2600 mi2), a LARGE impact on land use. Due to the lack of locations for siting a hydroelectric facility large enough to replace ONS, local hydropower is not a feasible alternative to ONS license renewal on its own. See Section 8.2.3 for a discussion of Canadian hydropower.

8.2.4.4 Geothermal

Geothermal has an average capacity factor of 90 percent and can be used for baseload power where available. However, as illustrated by the GEIS, Figure 8.4, geothermal plants might be located in the western continental United States, Alaska, and Hawaii where hydrothermal reservoirs are prevalent, but there is no feasible location for 2500 MW(e) of geothermal capacity to serve as an alternative to ONS license renewal.

8.2.4.5 Wood Energy

A wood burning facility can provide base load power and operate with an average annual capacity factor of around 70 to 80 percent and with 20 to 25 percent efficiency (GEIS, Section 8.3.6). The fuels required are variable and site-specific. A significant barrier to the use of wood waste to generate electricity is the high delivered fuel cost. States with significant wood resources, such as California, Maine, Georgia, Minnesota, Oregon, Washington, and Michigan, benefit from using local resources. The pulp, paper, and paperboard industries, which consume large quantities of electricity, are the largest consumer of wood and wood waste for energy, benefitting from the use of waste materials that could otherwise represent a disposal problem. The larger wood waste power plants are only 40 to 50 MW(e) in size. Estimates in the GEIS suggest that the overall level of construction impact should be approximately the same as that for a coal-fired plant, although facilities using wood waste for fuel would be built at smaller scales. Like coal-fired plants, wood-waste plants require large areas for fuel storage and processing and involve the same type of combustion equipment. Duke estimates that a rough construction cost for a 2500 MW(e) plant in the Oconee area would be about $2400/KW, which would not be competitive for baseload power (Duke 1998).

8.2.4.6 Municipal Solid Waste

The initial capital costs for municipal solid waste plants are greater than for comparable steam turbine technology at wood waste facilities. This is due to the need with municipal solid waste for specialized waste separation and handling equipment. The decision to burn municipal waste to generate energy is usually driven by the need for an alternative to landfills rather than by energy considerations. The use of landfills as a waste disposal option is likely to increase in the near term; however, it is unlikely that many landfills will begin converting waste to energy because of unfavorable economics, particularly with electricity prices declining (DOE 1995). Therefore, municipal solid waste would not be a feasible alternative to ONS license renewal, particularly at the scale required.

8.2.4.7 Other Biomass-Derived Fuels

In addition to wood and municipal solid waste fuels, there are several other concepts for fueling electric generators, including burning energy crops, converting crops to a liquid fuel such as ethanol (ethanol is primarily used as a gasoline additive for automotive fuel), and gasifying energy crops (including wood waste). The GEIS points out that none of these technologies has progressed to the point of being competitive on a large scale or of being reliable enough to replace a baseload plant such as ONS. For these reasons, such fuels do not offer a feasible alternative to ONS license renewal. In addition, these systems have LARGE impacts on land use.

8.2.4.8 Oil

Oil is not considered a stand-alone fuel because it is not cost-competitive when natural gas is available. The cost of oil-fired operation is about eight times as expensive as nuclear and coal-fired operation. In addition, future increases in oil prices are expected to make oil-fired generation increasingly more expensive than coal-fired generation (DOE 1996). For these reasons, oil-fired generation is not a feasible alternative to ONS license renewal nor is it likely to be included in a mix with other resources, except as a back-up fuel.

8.2.4.9 Advanced Nuclear Power

Work on advanced reactor designs has continued, and nuclear plant construction continues overseas. However, the cost of building a new nuclear plant and the political uncertainties that have historically surrounded many nuclear plant construction projects are among the factors that have led energy forecasters such as EIA to predict no new domestic orders for the duration of current forecasts (through the year 2010 [DOE 1996]). For these reasons, new nuclear plant construction is not considered a feasible alternative to ONS license renewal.

8.2.4.10 Fuel Cells

Phosphoric acid fuel cells are the most mature fuel cell technology, but they are only in the initial stages of commercialization. Two-hundred turnkey plants have been installed in the United States, Europe, and Japan. Recent estimates suggest that a company would have to produce about 100 MW of fuel cell stacks annually to achieve a price of $1000 to $1500 per kilowatt (DOE 1999). However, the current production capacity of all fuel cell manufacturers only totals about 60 MW per year. Therefore, the staff considers fuel cells not to be a feasible alternative to license renewal at this time.

8.2.4.11 Delayed Retirement

Duke's 1997 Integrated Resource Plan (IRP) (Duke 1998) discusses the strategy for meeting overall energy needs for the next 15 years. The IRP discusses decision dates (as opposed to retirement dates) for the following proposed combustion turbine generating requirements: 303 MW(e) in 2004; 88 MW(e) in 2005; 85 MW(e) in 2006. The IRP also discusses retirement of the following fossil generation: 276 MW(e) in 2010 and 438 MW(e) in 2011. The period of time evaluated for the IRP does not extend to the retirement dates for Oconee.

However, the delayed retirement of the above generation resources could not be used to replace the 2500 MW(e) generated at Oconee. In part because of their high operating cost, combustion turbines and small fossil units are used for peaking and intermediate generation. Therefore, it would not be feasible for the combustion turbines and small fossil plants listed above to replace base load generation. Additionally, it is unlikely that these fossil units could operate economically for an additional 20 years after the current decision dates. Duke does not have any plans to retire any of its base load units. Therefore, delayed retirement of base load fossil units could not be used as an alternative to license renewal.

8.2.4.12 Utility-Sponsored Conservation

Demand-side measures have been included in the past IRPs, and Duke currently has several general demand-side actions in their current plan (Duke 1998). These measures are discussed below.

   Focus on Education - to help maintain competitive electricity rates, Duke is shifting the energy efficiency focus from an emphasis on energy efficiency options that are large, high-cost, and incentive-based to less costly education-based options.
Implementation of Demand-Side Competitive Bidding - Duke assessed the potential benefits of paying a third-party or customer to design and/or market demand-side resource options. Duke has entered into contracts with four bidders for a total projected resource of 4.7 MW(e).

Demand-side options currently used at Duke include the following:

   Energy efficiency - High energy (HE) compressed air systems and HE motor systems and replacements
Interruptibles - Residential load control ride: A/C and water heating, power service rider, generator control rider
Load shifts - Residential water heating, controlled/submerged
Strategic Sales - Electrotechnology strategy, HE food service appliance, nonresidential space heating
Energy Efficiency and Strategic Sales - New residential housing program, existing residential housing program, and nonresidential heat pump program.

Currently, the demand side measures are expected to account for 950 MW(e) in 1999. This number is projected to decrease to 750 MW(e) in 2004. In addition, the demand side measures already are included in the applicant's growth projections. The applicant considers it unlikely that another cost-effective 2500 MW(e) can be found to replace ONS. Therefore, the conservation option is not considered a reasonable replacement for the license renewal alternative.

8.2.4.13 Combination of Alternatives

Even though individual alternatives to ONS might not be sufficient on their own to replace ONS due to the small size of the resource (hydro) or lack of cost-effective opportunities (e.g., for conservation), it is conceivable that a mix of alternatives might be cost-effective. For example, if some additional cost-effective conservation opportunities could be found and combined with a smaller imported power or natural gas-fired alternative, it might be possible to reduce some of the key environmental impacts of alternatives. However, it is unlikely that the environmental impact of such a hypothetical mix could be reduced below SMALL (see Table 8-6). In comparison, the impacts of renewing the ONS licenses are SMALL on all dimensions.

Table 8-6. Summary of Environmental Impacts of 500 MW(e) Demand-Side Measures, Plus 1200 MW(e) Gas-Fired Generation (Once-Through Cooling)

  Oconee Site Alternative "Greenfield" Site
Impact Category Impact Comments Impact Comments
Land Use SMALL Additional 24 ha (60 acres) required for power block

Additional 60 ha (150 acres) disturbed for pipeline construction

Additional land for backup oil storage

SMALL to MODERATE Up to 200 ha (500 acres) required for site plus transmission line, backup fuel tanks, pipeline
Ecology SMALL Constructed on land adjacent to Oconee site. Significant habitat loss due to pipeline construction SMALL to MODERATE Impact depends on location and ecology of the site
Water Use and Quality        
Surface Water SMALL >70% reduction in water flow SMALL to MODERATE Impact depends on receiving body of water
Groundwater SMALL Reduced groundwater withdrawals due to reduced workforce SMALL to MODERATE Groundwater would be used for potable water only
Air Quality SMALL to MODERATE Primarily nitrogen oxides SMALL to MODERATE Same impacts as for Oconee site
Waste SMALL Minor waste generation with gas (oil not evaluated) SMALL Same impacts as for Oconee site
Human Health SMALL Impacts considered to be minor (see discussion of gas-fired alternative) SMALL Same impacts as for Oconee site
Socioeconomics SMALL to MODERATE 500 to 750 additional workers during 3-year construction period; followed by a reduction in employment from 1700 persons at ONS to 300 persons (499 if fuel oil is used) MODERATE to LARGE Construction impacts would be relocated. Community near ONS would still experience reduction from 1700 workers to 0. Other community gains 300 workers
Aesthetics SMALL to MODERATE Visual impact of stacks would be noticeable, but less so than for the gas-fired alternative SMALL to MODERATE Alternate locations could reduce aesthetic impact if siting is in an industrial area
Archaeological and Historic Resources SMALL Only previously disturbed and adjacent areas would likely be affected SMALL Alternate location would necessitate cultural resource studies
Environmental Justice SMALL to MODERATE Impacts on low-income and minority populations should be similar to those experienced by the population as a whole. Impacts on housing are possible. SMALL to MODERATE Impacts vary depending on population distribution and makeup


8.3 References


[ Prev | Next | Top of file ]

40 CFR 50.9, "National primary and secondary ambient air quality standard for nitrogen dioxide."

40 CFR 50.10, "Postconstruction environmental reports."

40 CFR 51.100, "Definitions."

Baltimore Gas and Electric (BGE). 1989. Perryman Power Plant Certification of Public Convenience and Necessity, Environmental Review Document, Vol-2, Baltimore Gas and Electric, Baltimore, Maryland.

Clean Air Act (CAA), as amended, 42 USC, 7401 et seq.

Duke Energy Corporation. 1998. Application for Renewed Operating Licenses - Oconee Nuclear Station, Units 1, 2 and 3. Volume IV - Environmental Report.

Duke Energy Corporation. 1999a. Letter from M. S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Subject: License Renewal-Response to Requests for Additional Information. Oconee Nuclear Station. Dated March 4, 1999.

Duke Energy Corporation. 1999b. Letter from M. S. Tuckman, Duke Energy Corporation to U.S. Nuclear Regulatory Commission. Follow-up to Staff's Request for Additional Information Dated December 29, 1998, Related to the Environmental Portion of the Review of the License Renewal Application for Oconee Units 1, 2, and 3.

Energy Information Administration (EIA). 1997. Annual Energy Outlook 1998, Table A2. DOE/EIA-0383 (98), Washington, D.C.

Gilbert/Commonwealth. 1996. Update to Calvert Cliffs Nuclear Power Plant Units 1 and 2 Cooling Tower System Study.

Maryland Department of Natural Resources (MDNR). 1999. Maryland Power Plants and the Environment: A review of the impacts of power plants and transmission has on Maryland's natural resources. PRRP-CEIS-10, Maryland Power Plant Research Program, Annapolis, Maryland.

South Carolina Department of Health and Environmental Control (SCDHEC). 1998. South Carolina Air Quality Annual Report, Volume XVII 1997. Columbia, South Carolina.

U.S. Department of Energy (DOE). 1993. Renewable Resources in the U.S. Electricity Supply. DOE/EIA-0561, U.S. Department of Energy, Energy Information Administration, Washington, D.C.

U.S. Department of Energy (DOE). 1995. Electric Power Annual. U.S. Department of Energy, Energy Information Administration, Washington, D.C.

U.S. Department of Energy (DOE). 1996. Annual Energy Outlook; 1996 with Projections to 2015. DOE/EIA-0383(96), U.S. Department of Energy, Energy Information Administration, Washington, D.C.

U.S. Department of Energy Information Administration (EIA). 1997. Annual Energy Outlook 1998, Table A2, DOE/EIA-0383(98), U.S. Department of Energy, Washington, D.C.

U.S. Department of Energy (DOE). 1999. Advanced Fuel Cell Systems - A Revolutionary Power Technology, U.S. Department of Energy/Fossil Energy-Fuel Cell Power Systems overview. http://www.fe.doe.gov/coal-power/fc_sum.html. (Accessed August 4, 1999).

U.S. Environmental Protection Agency (EPA). 1993. Air Pollutant Emission Factors, Volume I: Stationary Point and Area Sources. EPA, AP-42, U.S. Environmental Protection Agency, Washington, D.C.

U.S. Environmental Protection Agency (EPA). 1994. Final Environmental Impact Statement, Volume I: Tampa Electric Company - Polk Power Station. EPA 904/9-94, U.S. Environmental Protection Agency, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1988. Final Generic Impact Statement on Decommissioning of Nuclear Facilities. NUREG-0586, U.S. Environmental Protection Agency, Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS). NUREG-1437, U.S. Environmental Protection Agency, Washington, D.C.

Zabransky, J., J. M. Vilardo, J. T. Schakenback, D. L. Elliott, W. R. Barchet, and R. L. George. 1981. Wind Energy Resource Atlas: Volume 6-The Southeast Region. PNNL-3195 WERA-6, Pacific Northwest Laboratory, Richland, Washington.


9.0 Summary and Conclusions


[ Prev | Next | Top of file ]

By letter dated July 7, 1998, Duke Energy Corporation (Duke 1998) submitted an application to the NRC to renew the Oconee Nuclear Station (ONS) Units 1, 2, and 3 operating licenses for an additional 20-year period. If the operating licenses are renewed, Federal (other than NRC) decisionmakers, State regulatory agencies, and the owners of the plant will ultimately decide whether the plant will continue to operate based on factors such as the need for power or other matters within the State's jurisdiction or the purview of the owners. If the operating licenses are not renewed, the plant will be shut down at or before the expiration of the current operating licenses, which are February 6, 2013, for Unit 1, October 6, 2013, for Unit 2, and July 19, 2014, for Unit 3.

Under the National Environmental Policy Act (NEPA) (42 USC 4321-4370d), an environmental impact statement (EIS) is required for major Federal actions significantly affecting the quality of the human environment. The NRC has implemented Section 102 of NEPA in 10 CFR Part 51. In 10 CFR 51.20(b)(2), the Commission requires preparation of an EIS or a supplement to an EIS for renewal of a reactor operating license; 10 CFR 51.95(c) states that the EIS prepared at the operating license renewal stage will be a supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS),(12) NUREG-1437 (NRC 1996, 1999a).

Upon acceptance of the Duke application, the NRC began the environmental review process described in 10 CFR Part 51 by publishing a notice of intent to prepare an EIS and conduct scoping (63 FR 50257). The staff visited the ONS site in October 1998 and held public scoping meetings on October 19, 1998, in Clemson, South Carolina (NRC 1999b). The staff reviewed the Duke environmental report (ER) and compared it to the GEIS, consulted with other agencies, and conducted an independent review of the issues following the guidance set forth in the draft Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal (NRC 1999c).

The staff then issued a draft of the supplemental environmental impact statement (SEIS) for public comment on May 24, 1999, which contained the preliminary results of its evaluation and recommendation. In addition, the staff held two public meetings during the comment period for this report on July 8, 1999. When the comment period ended on August 16, 1999, the staff considered and dispositioned all of the comments received, as discussed in Appendix A of this report. Modifications were made to this report to address certain comments, where appropriate, as described in Appendix A.

This SEIS presents the staff's analysis of the environmental impacts of renewal of the ONS operating licenses. The analysis considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's final recommendation regarding the proposed action.

The Commission has adopted the following statement of purpose and need for license renewal from the GEIS:

   The purpose and need for the proposed action (renewal of an operating license) is to provide an option that allows for power generation capability beyond the term of a current nuclear power plant operating license to meet future system generating needs, as such needs may be determined by State, utility, and, where authorized, Federal (other than NRC) decisionmakers.

The goal of the staff's environmental review, as defined in 10 CFR 51.95(c)(4) and the GEIS, is to determine:

   ... whether or not the adverse environmental impacts of license renewal are so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable.

Both the statement of purpose and need and the evaluation criterion implicitly acknowledge that there are factors, in addition to license renewal, that will ultimately determine whether an existing nuclear power plant continues to operate beyond the period of the current operating licenses.

NRC regulations [10 CFR 51.95(c)(2)] contain the following statement regarding the content of SEISs prepared at the license renewal stage:

   The supplemental environmental impact statement for license renewal is not required to include discussion of need for power or the economic costs and economic benefits of the proposed action or of alternatives to the proposed action except insofar as such benefits and costs are either essential for a determination regarding the inclusion of an alternative in the range of alternatives considered or relevant to mitigation. In addition, the supplemental environmental impact statement prepared at the license renewal stage need not discuss other issues not related to the environmental effects of the proposed action and the alternatives, or any aspect of the storage of spent fuel for the facility within the scope of the generic determination in § 51.23(a) ["Temporary storage of spent fuel after cessation of reactor operations-generic determination of no significant environmental impact"] and in accordance with § 51.23(b).(13)

The GEIS contains the results of a systematic evaluation of the consequences of renewing an operating license and operating a nuclear power plant for an additional 20 years. It evaluates 92 environmental issues using the following three-level standard of significance--SMALL, MODERATE, or LARGE--based on Council on Environmental Quality guidelines:

   SMALL: Environmental effects are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.
MODERATE: Environmental effects are sufficient to alter noticeably, but not to destabilize, important attributes of the resource.
LARGE: Environmental effects are clearly noticeable and are sufficient to destabilize important attributes of the resource.

For 69 of the 92 issues considered in the GEIS, the analysis in the GEIS shows

(1) the environmental impacts associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other plant or site characteristics
(2) a single significance level (i.e., SMALL, MODERATE, or LARGE) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from HLW and spent fuel disposal)
(3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are likely not to be sufficiently beneficial to warrant implementation.

These 69 issues were identified in the GEIS as Category 1 issues. In the absence of significant new information, the staff relied on conclusions as amplified by supporting information in the GEIS for issues designated Category 1 in 10 CFR Part 51, Subpart A, Appendix B, Table B-1.

Of the 23 issues not meeting the criteria set forth above, 21 are classified as Category 2 issues requiring analysis in a plant-specific supplement to the GEIS. The remaining two issues, environmental justice and chronic effects of electromagnetic fields, were not categorized. Environmental justice was not evaluated on a generic basis and must also be addressed in a plant-specific supplement to the GEIS. Information on the chronic effects of electromagnetic fields was not conclusive at the time the GEIS was prepared.

This SEIS documents the staff's evaluation of all 92 environmental issues considered in the GEIS. The staff considered the environmental impacts associated with alternatives to license renewal and compared the environmental impacts of license renewal and the alternatives. The alternatives to license renewal that were considered include the no-action alternative (not renewing the ONS operating licenses) and alternative methods of power generation. Among the alternative methods of power generation, coal-fired and gas-fired generation appear the most likely if the power from ONS is replaced. These alternatives are evaluated assuming that the replacement power generation plant is located at either the ONS site or an unspecified "greenfield" site.


9.1 Environmental Impacts of the Proposed Action - License Renewal


[ Prev | Next | Top of file ]

Duke and the staff have established independent processes for identifying and evaluating the significance of any new information on the environmental impacts of license renewal. Neither Duke nor the staff has identified any significant new information related to Category 1 issues that would call into question the conclusions in the GEIS. Similarly, neither Duke nor the staff has identified any new issue applicable to the ONS that has a significant environmental impact. Therefore, the staff relies upon the conclusions of the GEIS for all 69 Category 1 issues.

Duke's license renewal application presents analyses of the Category 2 issues. The staff has reviewed the Duke analysis for each issue and has conducted an independent review of each issue. Five Category 2 issues are not applicable because they are related to plant design features or site characteristics not found at ONS. Four Category 2 issues are not discussed in this SEIS because they are specifically related to refurbishment. Duke (1998) has stated that their evaluation of structures and components as required by 10 CFR 54.21 did not identify any major plant refurbishment activities or modifications as necessary to support the continued operation of Oconee beyond the end of the existing operating licenses. In addition, any replacement of components or additional inspection activities are within the bounds of normal plant component replacement and therefore are not expected to affect the environment outside of the bounds of the plant operations evaluated in the FES for ONS.

Twelve Category 2 issues, as well as environmental justice and chronic effects of electromagnetic fields, are discussed in detail in this SEIS. Four of the Category 2 issues apply to both refurbishment and to operation during the renewal term and are only discussed in this SEIS in relation to operation during the renewal term. For all 12 Category 2 issues and environmental justice, the staff concludes that the potential environmental effects are of SMALL significance in the context of the standards set forth in the GEIS. In addition, the staff determined that a consensus has not been reached by appropriate Federal health agencies that there are adverse effects from electromagnetic fields. Therefore, no further evaluation of this issue is required. For severe accident mitigation alternatives (SAMAs), the staff concludes that a reasonable, comprehensive effort was made to identify and evaluate SAMAs. Based on its review of the SAMAs for ONS, the staff concludes that none of the candidate SAMAs are cost-beneficial.

Mitigation measures were considered for each Category 2 issue. Current measures to mitigate environmental impacts of plant operation were found to be adequate, and no additional mitigation measures were deemed sufficiently beneficial to be warranted.

The following subsections discuss unavoidable adverse impacts, irreversible or irretrievable commitments of resources, and the relationship between local short-term use of the environment and long-term productivity.

9.1.1 Unavoidable Adverse Impacts

An environmental review conducted at the license renewal stage differs from the review conducted in support of a construction permit because the plant is in existence at the license renewal stage and has operated for a number of years. As a result, adverse impacts associated with the initial construction have been avoided, have been mitigated, or have occurred. The environmental impacts to be evaluated for license renewal are those associated with refurbishment and continued operation during the renewal term.

The adverse impacts identified are considered to be of SMALL significance, and none warrants implementation of additional mitigation measures. The adverse impacts of likely alternatives in the event that ONS ceases operation at or before the expiration of the current operating license will not be smaller than those associated with continued operation of ONS, and they may be greater for some impact categories in some locations.

9.1.2 Irreversible or Irretrievable Resource Commitments

The commitment of resources related to construction and operation of the ONS during its current license period was made when the plant was built. The resource commitments to be considered in this SEIS are associated with continued operation of the plant for an additional 20 years. These resources include materials and equipment required for plant maintenance and operation, the nuclear fuel used by the reactors, and ultimately, permanent offsite storage space for the spent fuel assemblies.

The most significant resource commitments related to operation during the renewal term are the fuel and the permanent storage space. The ONS replaces approximately 60 fuel assemblies in each of the three units during every refueling outage, which occurs on an 18-month cycle. Assuming no change in use rate, about 2400 spent fuel assemblies would be required for operation during a 20-year license renewal period.

The likely power generation alternatives in the event ONS ceases operation on or before the expiration of the current operating licenses will require a commitment of resources for construction of the replacement plants as well as for fuel to run the plants.

9.1.3 Short-Term Use Versus Long-Term Productivity

An initial balance between short-term use and long-term productivity of the environment at the ONS site was set when the plants were approved and construction began. That balance is now well established. Renewal of the ONS operating licenses and continued operation of the plants will not alter the existing balance, but it may postpone the availability of the site for other uses. Denial of the application to renew the operating licenses will lead to shutdown of the plants and will alter the balance in a manner that depends on subsequent uses of the site. For example, the environmental consequences of turning the ONS site into a park or an industrial facility are quite different.


9.2 Relative Significance of the Environmental Impacts of License Renewal and Alternatives


[ Prev | Next | Top of file ]

The proposed action is renewal of the operating licenses for Oconee Nuclear Station Units 1, 2, and 3. Chapter 2 describes the ONS and the environment in the vicinity of the plant. Chapters 4 through 7 discuss environmental issues associated with renewal of the operating licenses. Environmental issues associated with the no-action alternative, and alternatives involving power generation are discussed in Chapter 8.

The significance of the environmental impacts from the proposed action (approval of the application for renewal of the operating licenses), the no-action alternative (denial of the application), alternatives involving coal and gas-fired generation of power at the ONS site and an unspecified "greenfield site," and a combination of alternatives are compared in Table 9-1. Continued use of the ONS once-through cooling system is assumed for Table 9-1. Substitution of a cooling tower for the once-through cooling system in the evaluation of the coal-fired and gas-fired generation alternatives would result in somewhat greater environmental impacts in some impact categories.

Table 9-1 shows that the significance of the environmental effects of the proposed action are SMALL for all impact categories. The alternative actions, including the no-action alternative, may have environmental effects in at least some impact categories that reach MODERATE or LARGE significance.


9.3 Staff Conclusions and Recommendations


[ Prev | Next | Top of file ]

Based on (1) the analysis and findings in the Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants, NUREG-1437, (2) the ER submitted by Duke, (3) consultation with other Federal, State, and local agencies, (4) the staff's own independent review, and (5) the staff's consideration of public comments, the staff recommends that the Commission determine that the adverse environmental impacts of license renewal for Oconee Nuclear Station Units 1, 2, and 3 are not so great that preserving the option of license renewal for energy planning decisionmakers would be unreasonable.

Table 9-1. Summary of Environmental Significance of License Renewal, the No-Action Alternative, and Alternative Methods of Generation (Including a Combination of Alternatives) Assuming a Once-Through Cooling System

  Proposed Action No-Action Alternative Coal-Fired Generation Gas-Fired Generation Combination
Impact Category License Renewal Denial of Renewal ONS Site "Greenfield Site" ONS Site "Greenfield Site" ONS Site "Greenfield Site"
Land Use SMALL SMALL MODERATE MODERATE to LARGE MODERATE SMALL to MODERATE SMALL SMALL to MODERATE
Ecology SMALL SMALL MODERATE MODERATE to LARGE MODERATE SMALL to MODERATE SMALL SMALL to MODERATE
Water Quality -- Surface Water SMALL SMALL SMALL SMALL to MODERATE SMALL SMALL to MODERATE SMALL SMALL to MODERATE
Water Quality -- Groundwater SMALL SMALL SMALL SMALL to LARGE SMALL SMALL to LARGE SMALL SMALL to MODERATE
Air Quality SMALL SMALL MODERATE MODERATE MODERATE MODERATE SMALL to MODERATE SMALL to MODERATE
Waste SMALL SMALL MODERATE MODERATE SMALL SMALL SMALL SMALL
Human Health SMALL SMALL SMALL SMALL SMALL SMALL SMALL SMALL
Socioeconomics SMALL MODERATE to LARGE MODERATE MODERATE to LARGE SMALL to MODERATE MODERATE to LARGE SMALL to MODERATE MODERATE to LARGE
Aesthetics SMALL SMALL MODERATE to LARGE MODERATE to LARGE SMALL to MODERATE SMALL to MODERATE SMALL to MODERATE SMALL to MODERATE
Archaeological and Historical Resources SMALL SMALL to LARGE SMALL SMALL SMALL SMALL SMALL SMALL
Environmental Justice SMALL SMALL to MODERATE MODERATE SMALL to LARGE SMALL to MODERATE SMALL to MODERATE SMALL to MODERATE SMALL to MODERATE


9.4 References


[ Prev | Next | Top of file ]

10 CFR Part 51, "Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions."

10 CFR 51.20, "Criteria for and identification of licensing and regulatory actions requiring environmental impact statements."

10 CFR 51.23, "Temporary storage of spent fuel after cessation of reactor operation--generic determination of no significant environmental impact."

10 CFR 51.71, "Draft environmental impact statement--contents."

10 CFR 51.95, "Supplement to final environmental impact statement."

10 CFR Part 51, Subpart A, Appendix B, Table B-1, "Environmental effect of renewing the operating license of a nuclear power plant."

10 CFR 54.21, "Contents of application-technical information."

63 FR 50257, "Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process." September 21, 1998.

Duke Energy Corporation. 1998. Application for Renewed Operating Licenses - Oconee Nuclear Station, Units 1, 2 and 3. Volume IV, Environmental Report.

National Environmental Policy Act of 1969, as amended, 42 USC 4321-4370d.

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999a. Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Main Report, Section 6.3 - Transportation, Table 9.1, Summary of findings on NEPA issues for license renewal of nuclear power plants. NUREG-1437, Vol. 1, Addendum 1. Washington, D.C. National Environmental Policy Act of 1969, as amended, 42 USC 4321-4370d.

U.S. Nuclear Regulatory Commission (NRC). 1999b. Environmental Impact Statement Scoping Progress: Summary Report-Oconee Nuclear Station Units 1, 2, and 3. Oconee County, South Carolina. Washington, D.C.

U.S. Nuclear Regulatory Commission (NRC). 1999c. Standard Review Plans for Environmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal, NUREG-1555, Supplement 1. Washington, D.C.


Appendix A : Discussion of Comments on the Draft Supplement


[ Prev | Next | Top of file ]

Pursuant to 10 CFR Part 51, the staff transmitted the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Oconee Nuclear Station, Draft Report for Comment (NUREG-1437, Supplement 2, referred to as the draft SEIS) (NRC 1996) to Federal, State, and local government agencies as well as interested members of the public. As part of the process to solicit public comments on the draft SEIS, the staff

During the comment period, the staff received a total of 10 comment letters and e-mail messages in addition to the comments received during the public meetings.

The staff has reviewed the public meeting transcripts and the 10 comment letters and e-mail messages that are part of the docket file for the application, all of which are available in the NRC Public Document Room. Excerpts of the transcripts that contained comments or questions are reproduced in this appendix along with each of the 10 comment letters and e-mail messages. No written statements were provided by members of the public during the public meetings. Table A-1 lists (1) the speakers at the meetings in speaking order along with the page of the transcript excerpts in this report on which the comment appears (these comments are identified by the letter "A" followed by a number that identifies each comment in the chronological order the comments were made), and (2) the authors of the comment letters or e-mail messages. The comment letters and e-mail messages are identified by letters "B" through "K." An additional alpha-numeric identifier distinguishes among comments within a letter.(14) The staff response for each issue is provided in Section A.1 of this report. Related issues have been grouped together.

The staff addressed each comment by considering whether it was

(1) a comment about a Category 1 issue, and whether it

(a) provided significant new information that required evaluation during the review, or

(b) provided no new information

(2) a comment about a Category 2 issue, and whether it

(a) provided information that required evaluation during the review, or

(b) provided no such information

(3) a comment that raised an environmental issue not addressed in the GEIS or the draft SEIS

(4) a comment on safety issues pertaining to 10 CFR Part 54, or

(5) a comment outside the scope of license renewal (not related to 10 CFR Parts 51 or 54).

There was no significant, new information on Category 1 issues [(1)(a) above]. If the comment provided new information for a Category 2 issue [(2)(a)], then the staff evaluated the information and modified the SEIS, as appropriate. If the comment provided no new information for either Category 1 or 2 issues [(1)(b) or (2)(b)], then the GEIS and draft SEIS remained valid and bounding, and no further evaluation was performed.

Comments without a supporting technical basis or that did not provide any new information are addressed in this Appendix, providing relevant references that address the issues within the regulatory authority of the NRC, where appropriate. These references can be obtained from the NRC Public Document Room.

Subsections A.1.1 through A.1.18 correspond generally to the subject matter in the text of the supplement (purpose and scope, conclusions, site description, refurbishment, ecology, human health, socioeconomics, archaeology and historic resources, postulated accidents, uranium fuel cycle and solid waste management, decommissioning, alternatives to the proposed action, and summary and conclusions). Within each section, similar comments are grouped together for ease of reference, and a summary description of the comments is given, followed by the staff's response. Where the comment or question resulted in a change in the text of the draft report, the corresponding response refers the reader to the appropriate section of this report where the change was made. All revisions to the text, whether substantive (including those made in response to comments) or editorial, are designated by vertical lines beside the text.

Section A.2 provides relevant portions of the public meeting transcripts and the 10 letters and e-mail messages that were received in response to the draft SEIS. Each comment identified by the staff was assigned a specific alpha-numeric identifier (marker). That identifier is typed in the margin of the transcript, letter, or e-mail message at the beginning of the discussion of the comment. In addition, to assist the reader in finding the response to the comment, the section number(s) where the comment is addressed in Section A.1 of this report is also listed in the margin next to the identifier. A cross-reference of the alpha-numeric identifiers, the speaker or author of the comment, the page where the comment can be found, and the section(s) of this report in which the comment is addressed is provided in Table A-1.

Table A-1. Oconee Nuclear Station SEIS Comment Log



No. Speaker or Author Source Page of Comment Section(s) Where Addressed
A1 C. Tims Afternoon Meeting Transcript (7/8/99) A-35 A.1.4
A2 C. Tims Afternoon Meeting Transcript (7/8/99) A-35 A.1.17
A3 M. Thompson Afternoon Meeting Transcript (7/8/99) A-36 A.1.17
A4 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.15
A5 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.15
A6 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.15
A7 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.14
A8 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.14
A9 B. Williams Afternoon Meeting Transcript (7/8/99) A-37 A.1.4
A10 B. Williams Afternoon Meeting Transcript (7/8/99) A-38 A.1.4
A11 B. Williams Afternoon Meeting Transcript (7/8/99) A-39 A.1.4
A12 C. Tims Afternoon Meeting Transcript (7/8/99) A-39 A.1.17
A13 M. Thompson Afternoon Meeting Transcript (7/8/99) A-40 A.1.8
A14 J. Cudworth Afternoon Meeting Transcript (7/8/99) A-40 A.1.10
A15 D. Wehmire Afternoon Meeting Transcript (7/8/99) A-41 A.1.19
A16 D. Wehmire Afternoon Meeting Transcript (7/8/99) A-41 A.1.12
A17 N. Stancill Afternoon Meeting Transcript (7/8/99) A-42 A.1.14
A18 F. Plotnik Afternoon Meeting Transcript (7/8/99) A-43 A.1.4
A19 W. McCollum Afternoon Meeting Transcript (7/8/99) A-43 A.1.3
A20 D. Wehmire Afternoon Meeting Transcript (7/8/99) A-44 A.1.19
A21 D. Wehmire Afternoon Meeting Transcript (7/8/99) A-44 A.1.1
A22 D. Walters Afternoon Meeting Transcript (7/8/99) A-44 A.1.1
A23 D. Walters Afternoon Meeting Transcript (7/8/99) A-44 A.1.1
A24 T. Harper Afternoon Meeting Transcript (7/8/99) A-45 A.1.8
A25 N. Haylor Evening Meeting Transcript (7/8/99) A-47 A.1.4
A26 N. Haylor Evening Meeting Transcript (7/8/99) A-47 A.1.4
A27 N. Haylor Evening Meeting Transcript (7/8/99) A-47 A.1.4
A28 D. Sanders Evening Meeting Transcript (7/8/99) A-48 A.1.17
A29 D. Sanders Evening Meeting Transcript (7/8/99) A-48 A.1.17
A30 D. Mangrum Evening Meeting Transcript (7/8/99) A-49 A.1.4
A31 N. Haylor Evening Meeting Transcript (7/10/99) A-49 A.1.6
A32 N. Haylor Evening Meeting Transcript (7/8/99) A-49 A.1.4
A33 N. Haylor Evening Meeting Transcript (7/8/99) A-50 A.1.4
A34 N. Haylor Evening Meeting Transcript (7/8/99) A-50 A.1.15
A35 N. Haylor Evening Meeting Transcript (7/8/99) A-50 A.1.13
A36 N. Haylor Evening Meeting Transcript (7/8/99) A-50 A.1.15
A37 N. Haylor Evening Meeting Transcript (7/8/99) A-51 A.1.15
A38 N. Haylor Evening Meeting Transcript (7/8/99) A-51 A.1.15
A39 N. Haylor Evening Meeting Transcript (7/8/99) A-51 A.1.14
A40 N. Haylor Evening Meeting Transcript (7/8/99) A-51 A.1.14
A41 N. Haylor Evening Meeting Transcript (7/8/99) A-51 A.1.14
A42 N. Haylor Evening Meeting Transcript (7/8/99) A-52 A.1.14
A43 N. Haylor Evening Meeting Transcript (7/8/99) A-52 A.1.14
A44 N. Haylor Evening Meeting Transcript (78/99) A-52 A.1.13
A45 D. Sanders Evening Meeting Transcript (7/8/99) A-53 A.1.14
A46 N. Haylor Evening Meeting Transcript (7/8/99) A-55 A.1.16
A47 N. Haylor Evening Meeting Transcript (7/8/99) A-55 A.1.16
A48 N. Haylor Evening Meeting Transcript (7/8/99) A-56 A.1.9
A49 M. Thompson Evening Meeting Transcript (7/8/99) A-57 A.1.8
A50 M. Thompson Evening Meeting Transcript (7/8/99) A-57 A.1.8
A51 M. Thompson Evening Meeting Transcript (7/8/99) A-58 A.1.5
A52 N. Haylor Evening Meeting Transcript (7/8/99) A-59 A.1.4
A53 N. Haylor Evening Meeting Transcript (7/8/99) A-59 A.1.4
A54 G. Robison Evening Meeting Transcript (7/8/99) A-60 A.1.3
A55 D. Walters Evening Meeting Transcript (7/8/99) A-61 A.1.16
A56 D. Walters Evening Meeting Transcript (7/8/99) A-61 A.1.1
A57 D. Walters Evening Meeting Transcript (7/8/99) A-61 A.1.4
A58 D. Walters Evening Meeting Transcript (7/8/99) A-62 A.1.1
A59 D. Walters Evening Meeting Transcript (7/8/99) A-62 A.1.1
B N. Brock May 27, 1999 Letter A-65 A.1.11
C P.S. League August 12, 1999 Letter A-65 A.1.17
D1 H.J. Mueller August 16, 1999 Letter A-67 A.1.19
D2 H.J. Mueller August 16, 1999 Letter A-67 A.1.4
D3 H.J. Mueller August 16, 1999 Letter A-67 A.1.16
D4 H.J. Mueller August 16, 1999 Letter A-67 A.1.9
E J.H. Lee July 19, 1999 Letter A-68 A.1.17
F V. Autry, SCDHEC August 11, 1999 Letter A-68 A.1.8
G1 C.L. Gilbert, Jr. August 13, 1999 Letter A-69 A.1.2
G2 C.L. Gilbert, Jr. August 13, 1999 Letter A-69 A.1.13
G3 C.L. Gilbert, Jr. August 13, 1999 Letter A-69 A.1.17
H W.F. Squires July 9, 1999 E-mail Message A-72 A.1.1
I R. Carnes July 10, 1999 E-mail Message A-72 A.1.1
J J. Cudworth July 12, 1999 E-mail Message A-73 A.1.7
K Duke Energy August 17, 1999 Letter A-75 to A-86 A.1.3., A.1.7, A.1.8, A.1.18, A.1.19, Table A.2


A.1 Comments and Responses


[ Prev | Next | Top of file ]

A.1.1 General Comments in Support of Nuclear Energy and License Renewal

The record of the public meetings and comment letters contains eight comments that express general support for license renewal (A21, A22, A23, A56, A58, A59, H, and I). Four of the comments express support in general (A22, A23, A56, and A59), and four specifically mention Oconee Nuclear Station (A21, A58, H and I). Reasons for supporting license renewal included

These comments are general in nature and do not provide new information. Therefore, no further evaluation was required, and no changes to the SEIS were made as a result of these comments.

A.1.2 General Comments in Opposition to License Renewal

The record contains one comment that expressed general opposition to nuclear power and license renewal (G1). Reasons for opposing license renewal include

This comment is general in nature and does not provide new information. Therefore, no further evaluation was required, and no changes to the SEIS were made as a result of this comment.

A.1.3 General Comments on Adequacy of the Review and Analysis

The record contains three comments that expressed general opinions related to the staff's environmental review that was summarized in the draft SEIS, NUREG-1437, Supplement 2, Draft for Comment (A19, A54, and Ka). Two of the comments (A19 and A54) reflected positively on the draft SEIS. One comment (Ka) agreed with the conclusions stated in the draft SEIS that "Current measures to mitigate environmental impacts of plant operation were found to be adequate, and that no additional mitigation measures were deemed sufficiently beneficial to be warranted," and that "...the adverse impacts of likely alternatives will not be smaller than those associated with continued operation of ONS."

These comments are general in nature, and do not provide new information. Therefore, no further evaluation was required, and no changes to the SEIS were made as a result of these comments.

A.1.4 License Renewal Review Process

The record contains 15 comments and questions related to the license renewal process (A1, A9, A10, A11, A18, A25, A26, A27, A30, A32, A33, A52, A53, A57, and D2). One comment (A57) described the open nature of the review process. Two questions are related to the process that would occur after a determination is made about whether or not to renew the licenses (A1 and A18). Four questions are related to the schedule for the final inspection and the Commission's decision on license renewal (A25, A26, A27, and A30). Four comments were also made regarding the standing of the public and the Chattooga Watershed Coalition (A10, A11, A32, and A53). One comment related to the status and timing of the National Pollutant Discharge Elimination System (NPDES) permit renewal (A50). One comment related to the staff's consideration of public comments (A52). One question related to the involvement of the public during scoping or comment meetings (D2). Two comments stated that either issues were only partially being resolved through the relicensing process or that they were not being resolved and that it was unfair to the public and almost certainly illegal to proceed to a decision regarding license renewal in the absence of having answers to many open ended questions (A9 and A33).

The adequacy of the license renewal process is not within the scope of the environmental review related to the ONS license renewal. The license renewal process was established by rulemaking that included public notice and comment. Any new challenge to the process is outside the scope of this plant-specific environmental review.

The specific comments are addressed below.

Comment

Two of the comments were specific questions related to the license review process. One of the questions (A1) related to the process following the denial or refusal of the application (or in cases where the licensee does not apply for a license renewal). Another (A18) asked about the process that would be used if the license extension were granted, but then unanticipated problems developed at the site during the 15 years before the initial license period had expired.

Response

In the event that the license renewal application is denied, the current license will continue in effect until it expires. The Commission's regulations limit the duration of the operating license for a nuclear power facility to 40 years. Regulations require that upon the expiration of the original license, the utility has to initiate the decommissioning process. Decommissioning must be completed before the facility's license can be terminated. Decommissioning is defined as the safe removal of a facility from service and reduction of residual radioactivity to a level that permits termination of the NRC license.

The process that is being used by the NRC to monitor and oversee the current operating license will continue to be used if the license is renewed. If, at any time, a concern arises which affects the public health and safety, the NRC has the authority to issue orders which would require the licensee to take action to resolve that concern.

These comments did not result in modification of the SEIS text.

Comment

Three comments were related to the timing of the final inspection (A25, A26, and A27) in relationship to the final decision on the license renewal. One comment was related to the timing of the actual vote by the Commissioners to renew the license (A30).

Response

The license renewal inspection program consists of three separate inspections to support the decision on an application for license renewal. At a minimum, a scoping inspection and aging management inspection are conducted. An optional third inspection will be performed, if needed, to verify items identified by the staff, Advisory Committee on Reactor Safeguards, and regional administrator that are needed to close open items from the technical review of the application or previous inspections. This final inspection would be performed prior to the staff's recommendation regarding the approval or disapproval of the application. The inspection reports will be available to the public through the NRC's Public Document Room in Washington, D.C. before the Commission makes its decision. The Commission's decision on the renewal application is scheduled to be made by August 2000. The transcript of any Commission meetings on the application will also be available.

These comments did not result in modification of the SEIS text.

Comment

Four comments (A10, A11, A32, and A53) related to the standing or participation of the Chattooga River Watershed Coalition.

Response

The Chattooga River Watershed Coalition was the only organization that petitioned to intervene in a proceeding related to the Oconee license renewal application. The Atomic Safety and Licensing Board found that the Coalition had standing to intervene in the proceeding (that is, the action of renewing the operating license for the Oconee plants). However, the issues presented by the Chattooga River Watershed Coalition were not considered by the Atomic Safety and Licensing Board to be admissible as contentions. Upon appeal, the Commission came to the same conclusion. Nonetheless, the Commission has acknowledged the concerns that were expressed by the Chattooga River Watershed Coalition, and the staff is considering them during its review.

These comments did not result in modification of the SEIS text.

Comment

One comment (A52) related to the staff's consideration of public comments.

Response

The staff has listened to and is addressing the concerns that the public brought forth as comments on the draft SEIS for license renewal just as it did for comments provided during the scoping phase. The comments that were presented during the public meetings or by e-mail or letter are addressed in this Appendix. Comments received after the comment period ended were accommodated in this Appendix as time constraints allowed. Members of the public who do not believe that their concerns have been adequately addressed are always free to communicate their concerns to the NRC.

This comment did not result in modification of the SEIS text.

Comment

One comment (D2) noted the Notice of Availability for related documents available to the public, but asked whether public meetings would be held within the affected communities.

Response

Two public scoping meetings were held in Clemson, South Carolina, on October 19, 1998. Two additional meetings presenting the draft SEIS were held in Clemson, South Carolina, on July 8, 1999. The complete transcripts for these meetings can be found in meeting summaries issued on November 5, 1998, and August 27, 1999. A partial transcript of the July 8, 1999, meetings and the response to questions and comments made at those meetings are given in this Appendix. Clemson, South Carolina was selected as the location for these meetings because of its geographical proximity to the effected communities.

All of these meetings were announced in the Federal Register, in an NRC press release, on the NRC web page, and in posters placed on community bulletin boards in commercial establishments in the vicinity of ONS.

This comment did not result in modification of the SEIS text.

Comment

One comment (A57) commended the NRC for the open and thorough public process that was used to develop the generic environmental impact statement, which helps ensure that the process that was used during license renewal did not overlook or leave unexplored important issues and also makes the process more efficient and effective.

Response

This comment did not result in modification of the SEIS text.

Comment

Two comments (A9 and A33) stated that some concerns (related to plant operation for the reactor coolant system and not specifically defined) are still unresolved at this point and that it is unfair to the public and almost certainly illegal to proceed to a decision regarding license renewal in the absence of having answers to many open-ended questions.

Response

This SEIS addresses the environmental impact of the renewal of the licenses for the ONS units. There are no open issues in the environmental area. Concerns related to the safety aspects of the license renewal process are outside the scope of the staff's review of the environmental effects; therefore, they have been referred to the NRC license renewal safety project manager for disposition. The staff's review of the safety aspects of the renewal application is ongoing, and the staff's conclusions will be documented in the staff's safety evaluation. The comments regarding current operation are also outside the scope of license renewal. However, these concerns have been referred to the NRC Project Manager for the ONS.

These comments did not result in modification of the SEIS text.

A.1.5 Refurbishment

The transcript contains one comment related to refurbishment (A51).

Comment

The comment asked for an explanation of the difference between component replacement and refurbishment and further asked if the public would get information about component replacement.

Response

For the purpose of the environmental impact review, refurbishment describes an activity or change in a facility that is needed to support operations during the renewal term, but that was not previously considered in an environmental document. Duke's evaluation of structures and components as required by 10 CFR 54.21 did not identify any major plant refurbishment activities or modifications necessary to support the continued operation of ONS beyond the end of the existing term of the operating licenses.

Refurbishment in the context of license renewal does not refer to routine activities at the component level, such as repairs, replacement, or reconditioning of individual components, pipe segments, and concrete walls. These activities will continue during the initial license period and are anticipated to occur during the 20-year license renewal period.

Information on component replacement must be made publicly available only in certain circumstances under NRC rules and regulations. To the extent licensees are required to discuss component replacement when requesting NRC approval of plant changes pursuant to 10 CFR 50.90 or 50.92, such information will be available to the public. However, there is no requirement for a licensee to routinely provide information to the public about component replacement.

This comment did not result in the modification of the SEIS text.

A.1.6 Ecology

The record contains one comment related to ecology (A31).

Comment

One comment (A31) was a statement that in the event of a major radiological accident at the ONS, the Chattooga Watershed, which lies within the 50-mile evacuation zone, would be greatly impacted.

Response

The staff recognizes that a major radiological accident at a nuclear power plant would have the potential to greatly impact the population living near and the environment surrounding the nuclear facility. For this reason, the NRC requires a number of safety systems that will either prevent or mitigate the consequences of a major accident. In addition, a 16-km (10-mile) and an 80-km (50-mile) radius surrounding each nuclear facility are designated as emergency planning zones in the event of an accident. Emergency planning zones are defined as the areas for which planning is needed to ensure that prompt and effective actions can be taken to protect the public in the event of an accident.

The consequences of design basis accidents have been evaluated in the staff's safety evaluation supporting initial licensing of ONS.

This comment did not result in modification of the SEIS text.

A.1.7 Transmission Lines

The record contains three comments related to the level of review of the impacts of the transmission lines (J, Kb, and K24).

Comment

Three comments (J, Kb, and K24) indicated that the transmission lines that should be considered within the scope of the proposed action are those that run from the Oconee Turbine Building to the 230 kV and 525 kV switchyards. One comment (J) further suggested that the section on transmission line impacts should be deleted because the proposed action has no impact on electric shock since the lines will remain energized whether or not the Oconee licenses are renewed.

Response

The staff is required under the regulations in 10 CFR 51.53(c)(3)(ii)(H) to review the environmental impacts from transmission lines for the Category 2 issue concerning electric shock. The transmission lines to be evaluated are those that were constructed for the specific purpose of connecting the plant to the transmission system. The NRC staff identified these lines by reviewing Duke Power Company's original environmental report, Environmental Quality Features of Keowee-Toxaway Project, submitted to the Atomic Energy Commission (AEC), NRC's predecessor, on July 10, 1970, and supplemented in October 1971.

The staff has documented their position related to the scope of the transmission line impact assessment in a May 10, 1999, letter to Duke Energy (Subject: Determination of the scope of transmission line impact assessment for Oconee License Renewal). The comments provide no information that was not previously considered by the NRC staff that led to the determination in the May 10, 1999, letter. Therefore, the staff's position remains unchanged.

Because the basis for determining the scope of transmission lines is defined as those lines originally constructed for the specific purpose of connecting the plant to the transmission system, the statement that the transmission lines will remain energized irrespective of Oconee operation is not germane.

These comments did not result in modification of the SEIS text.

A.1.8 Water Quality and Use

The record contains ten comments related to water quality and use (A13, A24, A49, A50, F, K3, K6, K30, K40, and K79 ). The staff's responses to these comments follow.

Comment

Nine of the comments (A13, A49, A50, F, K3, K6, K30, K40, and K79) relate to the current status of the NPDES permit.

Response

The draft SEIS discussed the NPDES permit as "currently being renewed" by the South Carolina Department of Health and Environmental Control (SCDHEC). At the time that the draft SEIS was written and at the time of the public meetings in July, 1999, a toxicity compliance issue was outstanding and required completion before final approval and issuance of the NPDES permit. The compliance issue was resolved, and the SCDHEC issued the NPDES permit to Duke Energy on September 29, 1999. The current permit expires on September 30, 2003. A copy of the front page of the permit is contained in Appendix E of this report.

These comments did not result in modification of the SEIS text. However, the text of the SEIS has been changed to be consistent with the issuance of the current NPDES permit.

Comment

One comment (A24) requested the licensee make a strong commitment to making available a site on Lake Jocassee for a source of drinking water.

Response

The NRC's obligation under NEPA is specific to the action that is being taken and requires mitigative actions be taken only when such actions are required. In this case, there is no technical reason resulting from operation of ONS that would preclude municipalities from using water in Lake Keowee, such that they need to consider the use of an alternate location (such as Lake Jocassee) for drinking water intakes.

This comment did not result in a modification of the SEIS text.

A.1.9 Human Health

There are two comments in the record related to human health (A48 and D4). The staff's responses to these comments follow.

Comment

One comment (A48) requested information on nationwide systematic studies of the potential health effects within a specific radius around U.S. nuclear power plants. The comment specifically asked if the Centers for Disease Control (CDC) had ever done a study.

Response

The staff is not aware of any studies conducted by the CDC concerning potential health effects within a specific radius around U.S. nuclear power plants. However, the National Cancer Institute published a study, "Cancer in Populations Living Near Nuclear Facilities," in 1990, that examined cancer mortality between 1950 and 1984 at 62 nuclear facilities (Jablon 1990). The study did not find higher risks of leukemia or other cancers.

This comment did not result in a modification of the SEIS text.

Comment

The second comment (D4) specifically addressed the radiological impacts of the uranium fuel cycle on human populations and the definition of "tiny" doses referred to in Section 6.1, Page 6-3, as well as the type of impact that these doses may have on human populations. The comment suggested that the NRC provide clarification of the collective impact that these doses may have on human populations and requested a definition for "tiny."

Response

The comment discussed a section of the draft SEIS that quotes the findings in the Generic Environmental Impact Statement (GEIS) for License Renewal (NRC 1996). The statement was made that science cannot rule out the possibility that there will be no cancer fatalities from tiny doses. The same paragraph previously stated that tiny doses have some statistical adverse health effects. The quote from the GEIS indicates that "tiny" doses are "very small fractions of the regulatory limits and even smaller fractions of natural background exposure to the same populations." For the purposes of assessing radiological impacts, the Commission in the GEIS for license renewal (NRC 1996) has concluded that impacts are of small significance if doses and releases do not exceed permissible levels in the Commission's regulations. This determination of "small" applies to occupational doses as well as to doses to individual members of the public.

This comment did not result in a modification of the SEIS text.

A.1.10 Socioeconomics

The record contains one question related to the socioeconomic analysis that was conducted for the draft SEIS (A14). The comment is addressed below.

Comment

The comment asked what types of questions were asked and what kind of information was conveyed in the meetings with county, State, and Federal agencies during the staff's site visit in October 1999.

Response

The team met with the economic development departments of Seneca, Anderson, and Pickens Counties in South Carolina and asked questions regarding the transportation systems, public infrastructure concerns or problems, and the location and make-up of minority or low-income populations for Oconee County. They also discussed the tax base provided by ONS and the importance of that tax base to the Counties' finances. Finally, they discussed the likelihood of the Counties attracting new economic activity to the area.

The meetings with State and Federal agencies were specific to the issues that were under the purview of those agencies. For instance, discussions with the South Carolina State Historic Preservation Office related directly to historical and archaeological resources in and around the ONS. The discussions with the U.S. Fish and Wildlife Service addressed environmental issues and, specifically, endangered and threatened species.

This comment did not result in modification of the SEIS text.

A.1.11 Archaeology and Human Resources

The record contains one comment (B) related to archaeology and historic resources. The comment is addressed below.

Comment

The South Carolina State Historic Preservation Office states that relicenses with no new construction or land disturbance should have no effect on any properties included in or eligible for inclusion in the National Register of Historic Places. However, there might be unidentified archaeological sites within the plant area, and any future construction or land management activities could affect archaeological sites. The licensee may want to address the issue of future identification and management of cultural resources in the plant area as part of its continued operation.

Response

Duke, in their comment letter dated August 17, 1999 (Duke 1999), recommended that the following statement be added into the SEIS in Section 4.4.5:

To ensure that care is taken to protect cultural resources that may be encountered during construction or other land disturbing activities, the ONS site environmental work practices have been revised. If archaeological sites are identified during land disturbing activities, land disturbing activities will stop and the State Historic [P]reservation Office will be contacted to determine the appropriate steps to be taken prior to resuming the activities.

This statement has been added to the SEIS in Section 4.4.5.

A.1.12 Severe Accident Mitigation Alternatives

The record contains one comment related to severe accident mitigation alternatives (SAMAs) (A16). The comment is addressed below.

Comment

The comment asked whether any relative comparisons in the SAMA section were made, such as comparing the risk from ONS to driving a mile on a highway?

Response

No relative comparisons, such as relating the risk from ONS to driving on highways, were included in the draft SEIS. However, the Commission has established a policy statement ("Safety Goals for the Operation of Nuclear Power Plants; Policy Statement," 51 FR 30028) related to safety goals for the operation of nuclear power plants that provides qualitative and quantitative safety goals. As part of the policy statement, there were two quantitative objectives established to be used in determining achievement of the Commission's safety goals: (1) the risk of prompt fatality to an average individual in the vicinity of a nuclear power plant that might result from reactor accidents should not exceed 1/10 of 1% of the sum of prompt fatality risks resulting from other accidents to which members of the population are generally exposed, and (2) the risk to the population in the area near the nuclear power plant of cancer fatalities that might result should not exceed 1/10 of 1% of the sum of cancer fatality risks from all other causes. Based on the Oconee Probabilistic Risk Assessment and the Oconee Individual Plant Examination, the plant, by nature of its low estimated core damage frequency and robust containment design, meets these objectives. Thus, the risk associated with operation of the Oconee plant would represent less than 1/10th of 1percent of the risk to the public from all other causes.

This comment did not result in modification of the SEIS text.

A.1.13 Operational Safety Issues

The record contains three comments related to operational safety issues (A35, A44, and G2). The issues relate to (1) the temperature limits in the spent fuel pool and whether they minimize the probability of cracking of the spent fuel pool and subsequent leakage of the pool water into the groundwater and (2) the problems and inadequacies in the operation of the reactor cooling systems. These comments involve concerns that are relevant to current ONS operation. In accordance with 10 CFR 54.30, these issues are outside the scope of license renewal. They have been referred to the NRC operating plant project manager for disposition. These comments did not result in modification of the SEIS text.

A.1.14 Age-Related Safety Issues

The record contains eight comments associated with age-related safety issues (A7, A8, A17, A39, A40, A41, A42, and A43). A ninth comment was made that the SEIS does not appear to be the place for safety-related comments, but inquired as to where safety issues were addressed (A45). Five of the comments (A7, A39, A40, A41, and A43) specifically address embrittlement, fatigue, or toughness of key systems. One comment was related to embrittlement of the reactor vessel and internals (A17). Two comments (A8 and A42) dealt with the reactor building cooling units and their ability to remove heat due to degradation of the system from aging. These age-related safety issue comments are outside of the scope of the staff's review of the environmental effects of renewing the ONS licenses. However, they involve concerns that are relevant to the extended operation of the facility and have been referred to the NRC license renewal safety project manager for disposition. These comments did not result in modifications of the SEIS text.

A.1.15 Spent Nuclear Fuel

The record includes seven comments related to spent nuclear fuel storage or transportation (A4, A5, A6, A34, A36, A37, and A38). Five of the comments (A4, A6, A34, A37, and A38) address high-level waste (HLW) storage and disposal and the associated environmental impacts. The remaining two comments (A5 and A36) relate to the lack of a site-specific review of environmental impacts of transportation of HLW. The comments are addressed below.

Comment

The record contains five comments (A4, A6, A34, A37, and A38) that address offsite HLW storage and disposal and the environmental impacts and cost of offsite HLW disposal.

Response

Onsite storage of spent nuclear fuel is a Category 1 issue. The comments provide no new and significant information.

The environmental effects of long-term storage of spent fuel onsite have been evaluated by the NRC. As set forth in the Waste Confidence Rule (see 10 CFR 51.23), the NRC generically determined that such storage can be accomplished without significant environmental impact. In the Waste Confidence Rule, the Commission determined that spent fuel can be stored onsite for at least 30 years beyond the licensed operating life, which may include the term of a renewed license.

Siting of a HLW repository is a separate regulatory action involving the U.S. Department of Energy (DOE). Characterization of the site under review is projected to be complete by 2002, and a geologic repository is not expected to be ready before 2010 (NRC 1996). In the interim, onsite spent fuel storage in pools and in dry cask storage facilities continues in accordance with NRC regulations. NRC has a certification process for such casks, as set forth in 10 CFR Part 72. Consequently, these comments did not result in modification of the SEIS text.

Comment

There were two comments or questions (A5 and A36) related to the review of the environmental impacts of transportation of HLW and the fact that there was no site-specific review of the environmental impacts of transportation of HLW.

Response

The NRC addressed the questions concerning the status and background behind the change in classification of HLW transportation from a Category 2 issue to a Category 1 issue at the July 8, 1999, public meeting. The staff indicated that the proposed rule was an NRC initiative. The draft SEIS addressed this issue in Section 6.1.1, "Transportation of Radiological Waste," because the rule had not been finalized. Now that the rule has been amended, as discussed in detail below, the issue is a Category 1 issue and, therefore, need not be addressed on a plant-specific basis. Section 6.1 of this report now reflects this reclassification.

The Commission previously revised its environmental protection regulations (10 CFR Part 51) for license renewal on December 18, 1996 (61 FR 66537). The amendment was based on the analyses and conclusions reported in NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants" (NRC 1996). In response to the comments received on a proposed version of the rule published on June 5, 1996 (61 FR 28467), the Commission made the following statement:

As part of its effort to develop regulatory guidance for this rule, the Commission will consider whether further changes to the rule are desirable to generically address: (1) the issue of cumulative transportation impacts and (2) the implications that the use of higher burnup fuel have for the conclusions in Table S-4. After consideration of these issues, the Commission will determine whether the issue of transportation impacts should be changed to Category 1.

In SECY-97-279, entitled "Generic and Cumulative Environmental Impacts of Transportation of High-Level Waste (HLW) in the Vicinity of a HLW Repository," dated December 3, 1997, the NRC staff informed the Commission that it was the staff's preliminary view that the supplemental analyses of the generic and cumulative impacts of the transportation of HLW and of the implications of higher fuel burnup for transportation impacts supports a reasonable technical and legal determination that transportation of HLW is a Category 1 issue and may be generically resolved and adopted in a license renewal application. In a Staff Requirements Memorandum (SRM) dated January 13, 1998, the Commission directed the NRC staff to proceed with rulemaking to amend 10 CFR 51.53(c)(3)(ii)(M) to categorize the impacts of transportation of HLW as a Category 1 issue. In a memorandum dated July 1, 1998, the NRC staff informed the Commission of its plans for amending 10 CFR Part 51.

The Commission published the proposed rule for a 60-day public comment period on February 26, 1999 (64 FR 9884). The Commission also published a Notice of Availability of NUREG-1437, Vol. 1, Addendum 1, "Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants: Main Report Section 6.3 - 'Transportation,' Table 9.1 'Summary of findings on NEPA issues for license renewal of nuclear power plants,' Draft for Comment," (February 1999) (64 FR 9889) (Addendum 1 to the GEIS). Although the public comment period for the proposed rule and the draft addendum to the GEIS ended on April 27, 1999, the staff considered comments dated as late as June 25, 1999, (and received in early July 1999) in developing the final rule and final version of Addendum 1 to the GEIS. The staff made this accommodation in response to concerns expressed by stakeholders about the length of the comment period.

In the SRM to SECY-99-202, "Final Rule - Changes to Requirements for Environmental Review for Renewal of Nuclear Power Plant Operating Licenses (10 CFR Part 51)," dated August 3, 1999, the Commission approved issuance of the final rule and release of the supporting Addendum 1 to the GEIS. The Commission revised the environmental protection regulations on September 3, 1999 (64 FR 48496), and the rule became effective on October 4, 1999. The Notice of Filing of the Final Addendum 1 to the GEIS was published on September 17, 1999 (64 FR 50507). Accordingly, the Commission has resolved these issues on a generic basis, and no site-specific analysis is necessary in the absence of new and significant information.

These comments did not result in modification of the SEIS text. However, the text of the SEIS has been changed to be consistent with the final rule.

A.1.16 Alternatives

The record contains four comments directly related to alternatives (A46, A47, A55, and D3). Two of the comments (A46 and A55) related to the consideration of combinations of alternative energy sources. One comment (A47) was a question about whether energy reduction (conservation) measures had been considered. The fourth comment (D3) indicated appreciation that all reasonable energy resource alternatives had been evaluated.

These comments are addressed below:

Comment

One comment (A46) questioned whether a combination of alternative energy sources had been considered as an alternative to ONS license renewal. A second comment (A55) responded to the first comment.

Response

A combination of alternatives had not been discussed in the draft SEIS. Even though individual alternatives to ONS might not be sufficient on their own to replace ONS due to the small size of the resource (a hydroelectric power plant) or lack of cost-effective opportunities (e.g., for conservation), it is conceivable that a mix of alternatives might be cost-effective. For example, if some additional cost-effective conservation opportunities could be found and combined with a smaller imported power or natural gas-fired power plant alternative, it might be possible to reduce some of the key environmental impacts of alternatives. However, it is unlikely that the environmental impact of such a hypothetical mix could be reduced so that they are SMALL (that is the environmental effects are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resources). The impacts of renewing the ONS licenses are SMALL in all aspects. Therefore, the combination of alternatives would likely not reduce environmental impacts below those of the proposed action.

As a result of these comments, a new section (Section 8.2.4.13) was added to appropriately discuss the impacts of a combination of alternatives.

Comment

The question was asked (A47) whether energy-reduction measures and conservation measures were included in the SEIS analysis.

Response

Section 8.2.4.12 of both the draft and the final ONS SEIS discuss utility-sponsored conservation.

This comment did not result in modification of the SEIS text.

Comment

One comment (D3) expressed appreciation for the consideration of all reasonable energy resource alternatives in addition to relicensing and the no-action alternative

Response

This comment did not result in modification of the SEIS text.

A.1.17 Miscellaneous

The record contains eight comments that do not fall within any of other categories (A2, A3, A12, A28, A29, C, E, and G3). One of the comments asked about the makeup of the Commission (A2). One was related to the location of the public document rooms (A3). One requested the educational background and employment history of the NRC project manager (A12). Three were questions about MOX fuel (A28, A29, and G3). One was a request to submit comments after the date given in the Federal Register Notice (C) and one (E) was a statement that they had no comments on the draft SEIS.

These comments are addressed below:

Comment

One comment (A2) asked about the makeup of the Commission and specifically who the members were, if they were appointed by the President, if they are approved by the House or the Senate, and how long the terms of the appointments are.

Response

Commissioners are nominated by the President and confirmed by the Senate for an appointment of up to 5 years. The current Commission makeup consists of Chairman Meserve and Commissioners Dicus, Diaz, McGaffigan, and Merrifield. Additional information can be found at the NRC website: http://www.nrc.gov/NRC/contents.

This comment did not result in modification of the SEIS text.

Comment

Comment (A3) requested the location of the public document room in the vicinity of the ONS site.

Response

When this issue was raised at the public meeting, the staff responded that the NRC local public document room (LPDR) for the Oconee plant was the Public Library at 501 West South Broad Street, Walhalla, South Carolina. On November 1, 1999, the NRC implemented a nationwide electronic records architecture and discontinued support for LPDRs. Nevertheless, the staff understands that the Oconee-related material already in the library in Walhalla will be maintained. However, there have been no acquisitions related to Oconee after November 1, 1999. This SEIS will be forwarded to the public library to ensure that the complete environmental record is available at the former LPDR.

This comment did not result in modification of the SEIS text.

Comment

A question was asked (A12) at the public meeting regarding the educational background and employment history of the NRC Project Manager for the environmental review.

Response

The Project Manager responded at the public meeting and provided a description of his 20 years involvement in environmental matters at the NRC.

This comment did not result in modification of the SEIS text.

Comment

Three comments (A28, A29, and G3) related to questions regarding mixed-oxide (MOX) fuel and expressed concerns regarding the environmental impact of reprocessing the MOX fuel or asked whether MOX fuel was a factor in the relicensing process or whether the public could give input on the process for making decisions on the MOX fuel.

Response

MOX fuel is not currently being used at ONS. Any licensee seeking to use MOX fuel, whether during the current license term or during the license renewal term, will need to seek NRC approval for such use by submitting a license amendment pursuant to 10 CFR 50.90 to 50.92. An opportunity for a hearing would be associated with any such amendment.

These comments are outside of the scope of the staff's review of the environmental effects of renewing the ONS licenses. Therefore, these comments did not result in modification of the SEIS text.

Comment

One comment (C) was a request to submit comments after the date given in the Federal Register Notice. The NRC staff informed the commenter that the NRC would consider additional comments, if it was practical to do so. No further comments were received from the commenter. A second letter (E) indicated that the author had no comments. These comments did not result in modification of the SEIS text.

A.1.18 Technical Clarifications and Corrections

The list of specific comments included with Comment Letter K includes 54 comments that are technical enhancements or correction of information such as plant dimensions, document dates, and plant-specific terminology. Of the specific comments provided, those in the following list fit this category (K1, K2, K4, K5, K13, K14, K15, K16, K17, K18, K19, K20, K21, K22, K23, K25, K26, K27, K28, K31, K32, K33, K34, K35, K39, K41, K42, K43, K44, K45, K47, K50, K53, K56, K57, K58, K59, K60, K61, K62, K63, K64, K65, K66, K67, K68, K69, K70, K71, K72, K76, K77, K78, and K80).

A separate log of Duke's specific comments and the NRC responses is attached as Table A.2.

A.1.19 Format and Presentation (Spelling, Grammar, References, Clarity, etc.)

There were 18 comments that suggested changes for clarification or accuracy and correction of typographical errors (A15, A20, D1, K7, K8, K10, K11, K12, K29, K38, K51, K52, K54, K55, K73, K74, K75, and K82). Two comments related to the format of the document (A15 and A20), specifically to the location of the conclusions. One comment (D1) related to the title of the document. The specific comments from Duke and the NRC responses are included in Table A.2. The remaining three comments are addressed as follows:

Comment

Two comments (A15 and A20) either requested clarification of the location of the conclusion in the EIS or recommended that the conclusions be placed closer to the front of the report and made clearer.

Response

While the conclusions are given in Chapter 9 of the report, they are repeated both in the Executive Summary and in the Abstract that are presented at the front of the report.

This comment did not result in modification of the SEIS text.

Comment

One comment (D1) stated that the word "Generic" in this document is misleading since the document is site-specific to the Oconee Nuclear Station relicensing application.

Response

Under the National Environmental Policy Act (NEPA), an environmental impact statement (EIS) is required for major Federal actions significantly affecting the quality of the human environment. The NRC has implemented Section 102 of NEPA in 10 CFR Part 51. In 10 CFR 51.20(b)(2), the Commission requires preparation of an EIS or a supplement to an EIS for renewal of a reactor operating license. Furthermore, 10 CFR 51.95(c) states that the EIS prepared at the operating license renewal stage will be a supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Moreover, the NRC staff is obliged to integrate its conclusions as amplified in the GEIS for all issues. Every supplement relies upon the conclusions in the GEIS and efficiencies are realized using this consistent regulatory framework. Therefore, the title of this document retains the original title of the GEIS, but includes the statement that it is the supplement that pertains to Oconee Nuclear Station (in this case, Supplement 2).

This comment did not result in modification of the SEIS text.

Table A-2. Duke's Comments and Staff Response

No. Page Line Nos. Comment(a) Disposition
1. xvii 14 CCW should be "Condenser Circulating Water" Corrected as suggested
2. 1-8 Table 1-1 The following permit should be added (Reference ER Table 7.2-1):
Agency: SCDHECAuthority: RCRA, Section 3005
Requirement: Permit
Permit Number: SCD043979822
Permit Issued: 3/9/1998
Activity Covered: Part A Hazardous Waste Permit,
Interim Storage Facility for Mixed Wastes
Permit information added
3. 1-8 11 Current NPDES permit is being in the process of being renewed.
Line 11 should be revised to state:
"The permit is currently being renewed."(a)
This item is discussed in Section A.1.8
4. 1-8 8 "ONS has two permits for drinking water wells in protected area" is not a correct statement. ONS has one drinking water well for the restroom facilities at the Site Softball Field. The permit number for this well is 202098AI. (Note that the Duke ER had supplied the information on the wells. During the review of this draft SEIS, Duke found that the site has only one well permitted as a drinking water well). Clarified as suggested.
5. 1-8 11 Permit Number for SCDHEC FWPCA is incorrect. The correct permit number is SC0000515. Clarified as suggested
6. 1-8 40 Revise footnote (a) to state:
"A NPDES permit renewal application was submitted by Duke on March 27, 1998. The draft permit will be issued in mid-August for a 30-day public comment period. See Section 2.2.3."
This item is discussed in Section A.1.8
7. 2-1 9 Should be "Babcock & Wilcox." Corrected
8. 2-5 1 Revise sentence to state: "ONS is located on the shores of Lake Keowee. The main bodies of the lake lie to the north and to the southwest of the site." Clarified as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
9. 2-5 32 Several of the amenities at the Visitor's Center (lakeside picnic center and landscaped grounds) are mentioned, but the nice nature trail is not mentioned. This trail is used extensively by civic organizations and schools and is a great place for wildflower tours. Clarified as suggested
10. 2-6 Figure 2-4 Figure 2-4 appears to list the ONS 525 kV switchyard as the "825 kv Switchyard." Also the standard abbreviation for kilovolt is kV, not kv, as is used in this figure. Corrected
11. 2-7 12 Line 12 should be revised to state: "But because of their distance from the site, these zones …" Clarified as suggested
12. 2-7 29 Should be "Babcock & Wilcox." Corrected
13. 2-7 34 ONS can use fuel up to 5% enrichment.
Line should be revised to state: "ONS fuel is low enriched (up to 5 percent by weight)…"
Clarified as suggested
14. 2-8 23-25 Oconee License Renewal SER Section 2.2.3.6.3.2.1 (Page 2-102) Intake Structure within Scope of License Renewal and Subject to an Aging Management Review states that:
"...the licensing basis does not rely on the underwater weir nor recirculation of the intake canal water for decay heat removal after a loss of Lake Keowee event. Based on the above documentation, the staff agrees with the applicant's determination that the underwater weir is not within the scope of license renewal."
Therefore, the description of the function of this weir on Lines 23-25 is not applicable. It is appropriate to describe the weir and its location, but the description of the function should be deleted. Delete the sentence beginning: "The purpose of this dam is to retain…"
Clarified as suggested
15. 2-8 27 The sentence refers to Figure 2-4, showing the location of such intake features like the skimmer wall, intake structure, submerged dam, and the outfall. The location of the submerged dam is not shown on the figure. Clarified as suggested
16. 2-9 19 Evaporation is not a waste processing method; therefore, evaporator concentrates are not produced. Clarified as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
17. 2-10 18 - 20 The Radwaste Facility processes high-activity wastes, low-activity wastes, and miscellaneous wastes from the Auxiliary Building, not the opposite as currently stated in lines 18 through 20. Clarified as suggested
18. 2-10 26 Dilution is not considered part of processing. The waste is released prior to any dilution. However, hydro dilution flow is used in determining the release rate.
Delete statement: "(diluted to meet the permissible concentration limits for discharge)…."
Clarified as suggested
19. 2-10 35 The value "28,343 m3 (944,773 ft3) per year" is the potential waste generation rate. The liquid waste holdup capacity is approximately 80,000 gallons. Corrected
20. 2-11 10 Gases are also produced in tanks and piping other than those holding liquid wastes (e.g., Letdown Storage Tank, Core Flood Tank).
Line should be revised to state: "…by the evolution of gases in liquids contained in tanks and piping."
Clarified as suggested
21. 2-11 30 The word "limit" should be inserted after "rate." Clarified as suggested
22. 2-12 14-15 Change to "reactor coolant system make-up water, steam generator make-up water…" Clarified as suggested
23. 2-12 15 - 18 These lines should be changed to state:
"… and deborating demineralizers. Non-sanitary, nonradioactive wastes are neutralized and sent to the holding ponds, eventually being discharged to the Keowee River, downstream from the Keowee Hydroelectric Station. Sanitary wastes are routed to an aerated sewage lagoon. The effluents are treated by chlorination. Prior to discharge, the treated effluents from the sanitary waste treatment system are dechlorinated."
Clarified as suggested
24. 2-13 7-28 As stated in the Duke response to RAI 11, the lines that were constructed for the specific purpose of connecting the plant to the transmission system are those lines that run from the Oconee Turbine Building to the 230 kV and 525 kV switchyards. Discussed in Section A.1.7
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
25. 2-15 32-33 Revise line to state: "…provide once-through condenser circulating water (CCW)." Clarified as suggested
26. 2-15 35 The amount of water supplied from the Seneca water treatment plant and used for potable water is 120 m3/d [0.03 million gpd].
Revise line to state: "…treatment plant (120 m3/d [0.3 million gpd]) is used for potable water."
Corrected
27. 2-16 Figure 2-7 The average flow through Keowee Hydroelectric Station is listed as 1632 cfs. The correct value is 1032 cfs. Corrected
28. 2-16 8-12 Revise to state:
"There are a total of seven groundwater wells at the Oconee site. One of these wells is used to supply the site baseball field with drinking water and with water for a restroom facility. This well is also used for seasonal irrigation at the site baseball field and has a pumping capacity of 0.0019m3/s (30 gpm). The well at the baseball field is the only groundwater well on site permitted to supply drinking water. There are two groundwater wells used to supply seasonal irrigation for landscaping at a training building and an office complex. The other four wells are used infrequently as low volume, non-potable water sources. The estimated combined pumping rate for all groundwater wells at the Oconee site is less than 0.068 m3/s (100 gpm)."
Revised as suggested
29. 2-17 24 Insert "state" in front of agency. Clarified as suggested
30. 2-17 26 The 1998 toxicity issue has been resolved. The sentence referring to this issue should be deleted. Line 26 should be revised to state:
"The permit is currently being renewed. A NPDES permit renewal application was submitted by Duke on March 27, 1998. The draft permit will be issued in mid-August for a 30-day public comment period."
Discussed in Appendix A.1.8
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
31. 2-18 18 Add footnote stating:
"In May 1999 the Federal Court of Appeals (D.C. Circuit) remanded EPA's revisions to the ground-level ozone and particulate matter standards. The court held that there was no basis for either revision, and that the revised ozone standard was unconstitutional. Therefore, future implementation of revisions to these standards is uncertain."
Paragraph deleted. Footnote not necessary
32. 2-18 23-24 Add Ellicott Rock Wilderness Area and Middle Prong Wilderness Areas. No change. Areas not listed in 40 CFR Part 81, Subpart D
33. 2-19 16 Delete the word "aquatic." Clarified as suggested
34. 2-23 10 Insert "Hartwell Reservoir" following "Lake Keowee" in the list of aquatic environments. Clarified as suggested
35. 2-41 7 - 10 The reference to the location of these sites should be deleted to protect these areas from unauthorized excavation. It should be sufficient to mention that two sites exist, southwest of the plant and that these sites are categorized as having nondescript lithic scatter. Deleted as suggested
36. 3-3 14 This line lists "Public services: public utilities." This appears to be a single issue. 10 CFR Part 51, Subpart A, Table B-1 lists these as two separate issues. This should be corrected by listing these two issues separately. No change made
37. 3-3 20 This table lists Environmental Justice as a Category 2 issue related to refurbishment.
GEIS Table 9.1 does not list Environmental Justice as a Category 2 issue. The footnote used in GEIS Table 9.1 should be referenced to this issue in Table 3.2.
No change made
38. 4-2 12 The appropriate GEIS reference sections for the issue "Altered thermal stratification of lakes" are sections 4.2.1.2.3 and 4.4.2.2. Line 12 incorrectly lists GEIS Section 4.2.1.2.2 as a reference section. This should be corrected. Revised as suggested
39. 4-8 2 It is stated that the NPDES permit governs the release of effluents by Oconee Nuclear Station into the receiving waters of "Lake Keowee." The permit also governs discharges that go into Keowee Hydro's tailrace. Therefore it is recommended that the wording be changed to also include "and to the Keowee Hydro Station's tailrace." Clarified as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
40. 4-8 4 The 1998 toxicity issue has been resolved. The sentence referring to this issue should be deleted. Line 4 should be revised to state: "The permit is currently being renewed. The draft permit will be issued in mid-August for a 30 day public comment period." Discussed in A.1.8
41. 4-9 7 It is stated that the NPDES permit governs the release of effluents by Oconee Nuclear Station into the receiving waters of "Lake Keowee." The permit also governs discharges that go into Keowee Hydro's tailrace. Therefore it is recommended that the wording be changed to also include "and to the Keowee Hydro Station's tailrace." Clarified as suggested
42. 4-10 18 Draft states "Although the 316(b) demonstration was not formally approved…." Duke is not aware of any correspondence indicating that the 316(b) demonstration was not formally approved.
This portion of the sentence should be deleted or the sentence should be revised to state "No correspondence could be located indicating EPA's formal approval of the study. However, the EPA issued a modified NPDES permit on August 30, 1976, that deleted…"
Clarified as suggested
43. 4-11 37 It is stated that Duke submitted a reapplication in "April" 1998. This should be replaced to state "March, 1998." Revised as suggested
44. 4-12 9 10 CFR 51.53(c)(3)(ii)(G) states 9 x 1010 m3 /year, not 9 x 1012 m3 /year as stated in the document.
Revise Line 9 to state: "that is lower than the 9 x 1010m3 per year…"
Corrected
45. 4-12 8 - 12 The following revision is suggested:
"The combined flow rate for the Keowee and Little Rivers is lower than the 9 x 1010 m3/year (3.15 x 1012 ft3/year) specified in the 10 CFR 51.53 (c)(3)(ii)(G). This low flowrate raises a concern from the standpoint of the potential for enhancement of thermophylic microorganisms such as Naegleria fowleri. These type of organisms could be a potential health concern for members of the public swimming in the cooling source (Duke 1998a)."
Clarified as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
46. 4-15 41 The conclusion for GEIS Section 4.5.4.2.3 states:
"If NRC finds that a consensus has been reached by appropriate federal health agencies that there are adverse health effects, all license renewal applicants will have to address the health effects in the license renewal process."
SEIS Section 4.2.2 states that on this issue "evidence is inconclusive."
To ensure closure on this issue, Line 41 should be revised to add: "Therefore, no further review is required for this issue in this SEIS."
Revised based on a recent report by the National Institute of Environmental Health Sciences
47. 4-22 26 Lines 22 through 26 discuss the need to take additional care during normal operation and maintenance activities on site to protect cultural resources. To ensure this protection occurs, Duke has revised the ONS site work practices on land disturbing activities.
Revise Line 26 to add:
"To ensure that care is taken to protect cultural resources that may be encountered during construction or other land disturbing activities, the ONS site environmental work practices have been revised. If archeological sites are identified during land disturbing activities, land disturbing activities will stop and the State Historic preservation Office will be contacted to determine the appropriate steps to be taken prior to resuming the activities."
Clarified as suggested
48. 4-28 23-31 References to "preliminary" analysis and "preliminary" determination should be changed to final once the USFWS concurs with the NRC staff biological assessment conclusions, if that occurs prior to the issuance of the Final SEIS. Revised based on current status of consultation with FWS
49. 4-28 28 Line should be revised to state: "conducting surveys of sensitive habitats prior to initiation of construction activities for new transmission lines." Sentence in question was deleted based on current status of consultation with FWS
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
50. 4-29 22 The following statement should be added at the end of Line 22: "Therefore, no evaluation of this issue is required." Clarified as suggested
51. 4-29 35 The citation reference "(Should come with RAI)", needs to be clarified. Parenthetical statement deleted
52. 4-30 20 The correct reference is "Letter from M.S. Tuckman…" Corrected
53. 5-13 24 "component cooling water" should be changed to "condenser circulating water" Corrected as suggested
54. 6-6 18 Reference is made to the Baltimore Gas and Electric (BGE) ER. This Draft SEIS is written for Duke Energy Corporation's Oconee plant. The correct reference is "the Oconee ER." Corrected
55. 6-6 29 Reference for identification of new and significant information is made to the BGE ER. This Draft SEIS is written for Duke Energy Corporation's Oconee plant. The correct reference is "the Oconee ER." Corrected
56. 8-2 40-43 Water quality on Lake Keowee is affected by many factors other than the factors that Duke has an influence over by the operation of the Duke plants or by the operation of its subsidiaries.
Duke is proud to provide corporate and technical assistance to various entities in the region concerned with water quality issues. However, SCDHEC is the state agency responsible for water quality on South Carolina lakes, rivers, and streams.
Revise Line 40 to state:
"... exceptionally high if Oconee closes. Therefore, the corporate and technical leadership and assistance that Duke voluntarily provides in the area of water quality monitoring may be less readily available."
Delete the sentence beginning:" If water quality begins to decline,…"
Clarified as suggested
57. 8-4 22 Revise to state "sulfur dioxide emissions …" Clarified as suggested
58. 8-4 30 Line should be clarified by revising to state: "Approximately 90 percent of the 700,000 tons of ash would be flyash, and the remaining 10 percent would be bottom ash." Clarified as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
59. 8-4 36 Revise to state: "Facilities would be constructed to control and treat leachate from ash and scrubber waste disposal areas and runoff from coal storage areas." Clarified as suggested
60. 8-5 15 Revise to state: "Total waste volume would be 900,000 MT (1,000,000 tons)/yr. of ash and scrubber sludge." Clarified as suggested
61. 8-7 31 Revise line to state: "However, leachate from ash and scrubber waste disposal areas and runoff from coal storage areas would have to be controlled to avoid groundwater and surface water contamination." Clarified as suggested
62. 8-9 36 Revise to state "approximately 900,000 MT (1,000,000 tons)/yr. of this waste…" Clarified as suggested
63. 8-12 33 The Duke ER supplied information on use of forced draft cooling towers. Duke would not likely use natural draft cooling towers due to the aesthetic difference between natural draft and forced draft cooling towers. Recommend removing the first sentence. Clarified as suggested
64. 8-12 37-38 This line reads as if Catawba has a natural draft cooling tower. Catawba has forced draft cooling towers. Duke would not likely use natural draft cooling towers. Corrected as suggested
65. 8-13 1 Remove first sentence. Duke does not consider natural cooling towers as an option. Corrected as suggested
66. 8-13 29 Add "Addition of 30 M (100 ft) tall cooling towers or…." Corrected as suggested
67. 8-15 13 Duke would not likely use natural draft cooling towers due to the aesthetic difference between natural draft and forced draft cooling towers. Remove reference to natural draft cooling towers. Corrected as suggested
68. 8-17 23 Units for waste should be units of volume, not area. Duke estimates the volume for this waste would be "2500 ft3/yr of spent catalyst…." Corrected as suggested
69. 8-22 23-26 Duke would not likely use natural draft cooling towers due to the aesthetic difference between natural draft and forced draft cooling towers. Remove this sentence and reference.
Catawba uses forced draft cooling towers.
Corrected as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
70. 8-23 23 Add statement: "Addition of 30-M (100-ft) high mechanical draft cooling towers." Corrected as suggested
71. 8-29 1 The date of the reference is May 13, 1999. The letter is from M. S. Tuckman. Corrected as suggested
72. 9-3 25 Add statement: "Therefore, no further analysis of the chronic effects of electromagnetic fields is required." Clarified as suggested
73. 9-4 13 The fifth word on the line reads 'bonds.' This should be revised to "bounds." Corrected
74. 9-6 16 Wording "preliminary" should be deleted upon release of final document. Revised
75. C-2 5 The date of the reference is May 13, 1999. The letter is from M. S. Tuckman. Corrected
76. D-2 11 Should be Asheville, not Charlotte. Corrected as suggested
77. D-2 13 Should be Charleston, not Columbia. Corrected as suggested
78. E-2 Table E-1 The following permit should be added (Reference ER Table 7.2-1):
Agency: SCDHECAuthority: RCRA, Section 3005
Requirement: Permit
Permit Number: SCD043979822
Activity Covered: Part A Hazardous Waste Permit,
Interim Storage Facility for Mixed Wastes
Included as suggested
79. E-2 16 Add footnote to Line 16. Line 16 should state:
"being revised"(a)
Footnote (a) should be added to end of Table E-1 to state:
"A NPDES permit renewal application was submitted by Duke on March 27, 1998. The draft permit will be issued in mid-August for a 30 day public comment period. See Section 2.2.3."
This item is discussed in Section A.1.8
(a) The comments in this column were extracted directly from Comment Letter K from Duke.
80. E-2 30 "ONS has two permits for drinking water wells in protected area" is not a correct statement. ONS has one drinking water well for the restroom facilities at the Site Softball Field. The permit number for this well is 202098AI. (Note that the Duke ER had supplied the information on the wells. During the review of this draft SEIS, Duke found that the site has only one well permitted as a drinking water well). Clarified as suggested
81. F-1, F-2 N/A The GEIS issues related to impacts from refurbishment activities are not listed in this section. There are nine Category 1 issues and nine Category 2 issues that are related to refurbishment activities (Reference Table 3-1 and 3-2). These should be repeated in this table.
An alternative to listing these issues in Appendix F would be to change the title to "Appendix F GEIS Environmental Issues Not Applicable to the Oconee Nuclear Station Because of Plant or Site Characteristics."
No change
82. F-1 28 The appropriate GEIS reference sections for the issue listed on lines 28 - 30 is 4.8.1.3. Lines 28 - 29 incorrectly list GEIS Sections 4.3.2.1 and 4.4.2.1 as the GEIS sections for this issue. Corrected as suggested
(a) The comments in this column were extracted directly from Comment Letter K from Duke.


A.2 Public Meeting Transcript Excerpts and Comment Letters


[ Prev | Next | Top of file ]

Letter A (Transcript)

transcript (pdf)

Letter B

B-1

Letter C

C-1

C-2

Letter D

D-1

D-2

D-3

Letter E

E-1

Letter F

F-1

F-2

Letter G

G-1

G-2

G-3

G-4

G-5

Letter H

H-1

Letter I

I-1

Letter J

J-1

J-2

J-3

J-4

Letter K

K-1

K-2

K-3

K-4

Attachment 1

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20


Appendix B : Contributors to the Supplement


[ Prev | Next | Top of file ]

The overall responsibility for the preparation of this supplement was assigned to the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission (NRC). The statement was prepared by members of the Office of Nuclear Reactor Regulation with assistance from other NRC organizations and the Pacific Northwest National Laboratory.

Name Affiliation Function or Expertise
Nuclear Regulatory Commission
James H. Wilson Nuclear Reactor Regulation Project Manager, Ecology
Thomas Kenyon Nuclear Reactor Regulation Project Management
Barry Zalcman Nuclear Reactor Regulation Section Chief and Technical Monitor
Cynthia Sochor Nuclear Reactor Regulation Environmental Engineer
Ralph Architzel Nuclear Reactor Regulation Technical Assistant
Claudia Craig Nuclear Reactor Regulation Environmental Engineer
Kimberly Leigh Nuclear Reactor Regulation Environmental Scientist
James G. Luehman Nuclear Reactor Regulation Project Management
Robert Jolly Nuclear Reactor Regulation Environmental Engineer
Thomas H. Essig Nuclear Reactor Regulation Health Physics
Robert Palla Nuclear Reactor Regulation Severe Accident Mitigation Alternatives
John Monninger Nuclear Reactor Regulation Severe Accident Mitigation Alternatives
Sid Feld Nuclear Regulatory Research Severe Accident Mitigation Alternatives
Nicholas Saltos Nuclear Reactor Regulation Severe Accident Mitigation Alternatives
Pacific Northwest National Laboratory(a)
Rebekah Harty   Task Leader
Eva Eckert Hickey   Deputy Task Leader/Radiation Protection
James V. Ramsdell, Jr.   Air Quality
Michael J. Scott   Socioeconomics
Duane A. Neitzel   Aquatic Ecology
Susan L. Blanton   Aquatic Ecology
Charles A. Brandt   Terrestrial Ecology
Michael R. Sackschewsky   Terrestrial Ecology
Paul R. Nickens   Cultural Resources
Paul L. Hendrickson   Land Use
Lance W. Vail   Water Use, Hydrology
Wayne C. Cosby   Technical Editor

(a) Pacific Northwest National Laboratory is operated for the U.S. Department of Energy by Battelle Memorial Institute.


Appendix C : Chronology of NRC Staff Environmental Review Correspondence Related to the Duke Application for License Renewal of Oconee Nuclear Station, Units 1, 2, and 3


[ Prev | Next | Top of file ]

This appendix contains a chronological listing of correspondence between the NRC and Duke Energy Corporation (Duke) and other correspondence related to the NRC staff's environmental review, under 10 CFR Part 51, of Duke's application for renewal for the Oconee Nuclear Station (ONS) Units 1, 2, and 3 operating licenses. All documents, with the exception of those containing proprietary information, have been placed in the Commission's Public Document Room, the Gelman Building, 2120 L Street, NW., Washington, D.C., and the Oconee County Library, 501 West Broad Street, Walhalla, SC 29691.

July 6, 1998 Letter from Duke Energy Corporation to NRC forwarding the application for renewal of operating licenses for the Oconee Nuclear Station, Units 1, 2, and 3, requesting extension of operating licenses for an additional 20 years
July 31, 1998 Letter from C. Grimes, NRC, to Duke Energy Corporation transmitting proposed NRC review schedule for Duke Energy Corporation application for renewal of operating licenses for Oconee Nuclear Station, Units 1, 2, and 3
August 5, 1998 Letter from J. Roe, NRC, to Duke Energy Corporation, transmitting Federal Register Notice of Acceptance for Docketing of the Application and Notice of Opportunity for a Hearing Regarding Renewal of Licenses Nos. DPR-38, DPR-47, and DPR-55
August 26, 1998 Letter from Duke Energy Corporation to NRC forwarding letter from U.S. Fish and Wildlife Service that concurs with the utility's determination contained in its environmental report that proposed action will have no effect on listed or proposed threatened or endangered species
September 14, 1998 Letter from T. Essig, NRC, to Duke Energy Corporation transmitting Federal Register Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process in support of the review of the application for renewal of the Oconee Nuclear Station, Units 1, 2, and 3 operating licenses for an additional 20 years
September 21, 1998 Letter from M. Bunch, Wildlife Diversity of the South Carolina Department of Natural Resources (SC DNR), to NRC commenting on license renewal of the Oconee Nuclear Station
October 8, 1998 Letter from Duke Energy Corporation to NRC forwarding the South Carolina Department of Natural Resources letter which concurred with the licensee's report regarding impacts of license renewal to threatened and endangered species
October 9, 1998 Meeting notice for October 19, 1998, scoping meeting in support of the environmental review for Oconee Nuclear Station license renewal
October 14, 1998 Letter from R. Keck, National Wild Turkey Federation, to NRC commenting on license renewal of the Oconee Nuclear Station, Units 1, 2, and 3
October 30, 1998 Letter from R. Nash, Appalachian Council of Governments, to NRC in support of Oconee license renewal
November 5, 1998 Memorandum from J. Wilson, NRC, to T. Essig, NRC, summarizing the Oconee Nuclear Station scoping meeting held in support of the review of Oconee's license renewal application
November 6, 1998 Letter from A. Viney, South Carolina Wildlife Federation, to the NRC regarding the environmental scoping process for Oconee Nuclear Station license renewal
November 9, 1998 Memorandum from J. Wilson, NRC, to T. Essig, NRC, summarizing the Oconee Nuclear Station site visit in support of the environmental review for the license renewal application.
November 10, 1998 Letter from D. Bauknight, Natural Resources Conservation Service, to NRC regarding the environmental scoping process for Oconee license renewal
November 10, 1998 Letter from C. Gilbert to NRC expressing his view that the Oconee license renewal application should be denied
November 20, 1998 Letter from J. Wilson, NRC, acknowledging receipt of written comments during the scoping process regarding Oconee license renewal
November 30, 1998 Letter from T. Essig, NRC, to United Keetowah Band of Cherokee inviting comment on Oconee license renewal
December 7, 1998 Letter from T. Essig, NRC, to M. Bunch, Wildlife Diversity of the SCDNR, regarding the scope of review for threatened and endangered species
December 29, 1998 Letter from J. Wilson, NRC, to Duke Energy Corporation forwarding requests for additional information (RAI) for the review of the Oconee Nuclear Station license renewal application regarding severe accident mitigation alternatives
December 29, 1998 Letter from J. Wilson, NRC, to Duke Energy Corporation forwarding RAIs for the review of the Oconee Nuclear Station Environmental Report associated with license renewal
January 15, 1999 Letter from Duke Energy Corporation to NRC stating that environmental RAI responses would be provided on or before March 4, 1999 and severe accident mitigation alternative RAIs would be provided by March 12, 1999
January 20, 1999 Letter from J. Wilson, NRC, forwarding environmental scoping summary report to scoping participants and other interested parties
March 1, 1999 Letter from J. Wilson, NRC, to South Carolina Department of Health and Environmental Control (SCDHEC) requesting information on the current status of the National Pollutant Discharge Elimination System and land disposal permits, and any water quality issues
March 1, 1999 Letter from J. Wilson, NRC, to Federal Energy Regulatory Commission (FERC) requesting information on the current status of the FERC license for Keowee dam and hydro-electric station and any other information that NRC should be aware of regarding future operation
March 4, 1999 Letter from M.S. Tuckman, Duke Energy Corporation, to the NRC transmitting the response to the requests for additional information
April 21, 1999 Letter from R. Gandy, of SCDHEC, to NRC stating that Oconee has been assigned an NPDES permit number and that resolution of toxicity testing issues and the public comment period must be completed before issuance of a permit.
April 29, 1999 Letter from J. Wilson, NRC, to Duke Energy Corporation forwarding followup to request for additional information dated December 29, 1998, related to the environmental portion of the review of the license renewal application for Oconee Nuclear Station.
May 10, 1999 Letter from C. Carpenter, NRC, to Duke Energy Corporation transmitting NRC staff's determination of the scope of transmission lines for the review of Duke Energy's license renewal application.
May 13, 1999 Letter from M.S. Tuckman, Duke Energy Corporation, to NRC transmitting the response to the followup to the request for additional information related to the environmental portion of the review of the license renewal application for Oconee Nuclear station.
May 17, 1999 Memorandum from J. Wilson, NRC, to B. Zalcman, NRC, regarding NRC engagement of discussion with the U.S. Fish and Wildlife Service in support of the environmental review for license renewal
May 20, 1999 Letter from J. Wilson, NRC, to Duke Energy Corporation forwarding the Oconee plant-specific draft supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS)
May 18, 1999 Letter from D. Matthews, NRC, to Duke Energy Corporation forwarding the Federal Register Notice of Availability of the draft supplements to the GEIS
May 27, 1999 Letter from N. Brock, SC State Historic Preservation Office, to NRC commenting on the impact of Oconee license renewal to historic properties
June 22, 1999 Memorandum from J. Wilson, NRC, to C. Carpenter, NRC, announcing a

July 7, 1999, public meeting in Clemson, SC to obtain comments on the draft supplement to the GEIS

June 30, 1999 Letter from C. Carpenter, NRC, to R. Banks, Fish and Wildlife Service, forwarding biological assessment to evaluate whether proposed renewal of Oconee Nuclear Station operating licenses would have adverse effects on listed species
July 19, 1999 Letter from J. Lee, Department of Interior (DOI), to NRC providing no comment on the draft supplement to the GEIS
July 9, 1999 E-mail from W. Squires to NRC providing comment in support of Oconee Nuclear Station license renewal
July 10, 1999 E-mail from R. Carnes to NRC providing comment in support of Oconee Nuclear Station license renewal
August 12, 1999 Letter from P. League, SCDNR, to NRC regarding its intention to submit comments on the draft supplement to the GEIS
August 17, 1999 Letter from Duke Energy Corporation to NRC forwarding Duke's comments on the draft supplement to the GEIS
August 27, 1999 Memorandum from J. Wilson, NRC, to C. Carpenter, NRC, providing the meeting summary for the public meeting on the draft supplement to the GEIS held in Clemson, South Carolina on July 8, 1999
September 2, 1999 Letter from R. Banks, DOI, to C. Carpenter, NRC, providing comments on the biological assessment submitted regarding license renewal at Oconee Nuclear Station
November 4, 1999 Letter from B. Cole, FWS to C. Carpenter, NRC, concurring on the staff's June 30, 1999, biological assessment for Oconee Nuclear Station license renewal


C.1 Reference


[ Prev | Next | Top of file ]

10 CFR Part 51, "Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions."


Appendix D : Organizations Contacted


[ Prev | Next | Top of file ]

During the course of the staff's independent review of environmental impacts from operations during the renewal term, the following Federal, State, regional, and local agencies were contacted:

Anderson County, Department of Economic and Community Development, Anderson County, Clemson, South Carolina

Appalachian Council of Governments, Economic Development/Planning Services, Greenville, South Carolina

Bureau of Water, SC Department of Health and Environmental Control, Columbia, South Carolina

Coldwell Banker (Appraiser), Anderson, South Carolina

Federal Energy Regulatory Commission, Office of Hydropower Licensing, Washington, DC

HITT & Associates (Appraiser), Pickens, South Carolina

Institute of Earth Science, University of South Carolina, Columbia, South Carolina

Keowee-Toxaway State Park, Sunset, South Carolina

Knight Realty & Appraisals, Pickens, South Carolina

Landrith and Associates (Appraisers), Seneca, South Carolina

Luther Fields (Appraiser), Clemson, South Carolina

Moss and Associates (Appraiser), Walhalla, South Carolina

Museum of the Cherokee Indians, Cherokee, North Carolina

North Carolina Department of Parks and Recreation, Natural Heritage Program, Raleigh, North Carolina

Oconee County, Department of Economic Development, Oconee County, Walhalla, South Carolina

Old Pickens Presbyterian Church, Perpetual Care Committee, Salem, South Carolina

Pickens County, Economic Development and Planning Department, Pickens County, Pickens, South Carolina

Pickens County Museum, Pickens, South Carolina

Planner for Oconee County Social Services, Oconee County, Walhalla, South Carolina

Secretary for the Oconee County Planning Commission, Walhalla, South Carolina

South Carolina Department of Natural Resources, Wildlife Diversity office

South Carolina Institute of Archaeology and Anthropology (State Archaeologist), University of South Carolina, Columbia, South Carolina

South Carolina State Historic Preservation Office, Columbia, South Carolina

State Toxicologist, South Carolina Department of Health and Environmental Control, Columbia South Carolina

U.S. Fish and Wildlife Service, Asheville, North Carolina

U.S. Fish and Wildlife Service, Charleston, South Carolina


Appendix E : Duke Compliance Status and Consultations


[ Prev | Next | Top of file ]

As part of Duke Energy Corporation's (Duke's) application for renewal of their operating licenses for Oconee Nuclear Station (ONS) Units 1, 2, and 3, they prepared a list of licenses, permits, consultations, and other approvals obtained from Federal, State, regional, and local authorities pertinent to ONS operations. The list, with minor changes to reflect the current status of these documents, is shown in Table E-1.

Correspondence from Federal and State agencies acknowledging Duke's permits and status compliance with requirements is also attached, including

Table E-1. Oconee Environmental Permits and Compliance Status

Oconee Environmental Permits Federal Act Federal, State or Local Permitting Agency Date Permit Issued or Expired/Compliance Status
Operating Licenses DPR-38, DPR-47, and DPR-55 Atomic Energy Act, 10 CFR Part 50 NRC Expires February 6, 2013; October 6, 2013; and July 19, 2014
Independent Spent Fuel Storage Installation, Materials License No. SNM-2503 Atomic Energy Act, 10 CFR Part 72 NRC Expires January 31, 2010
FERC Project

No. 2503

Federal Power Act, Section 4(e) Federal Energy Regulatory Commission Expires 2016
NPDES Permit # SC0000515 Federal Water Pollution Control Act (FWPCA) Section 402 SCDHEC Issued September 29, 1999
Expires September 30, 2003
Part A Hazardous Waste Permit #SCD043979822 Interim Storage Facility for Mixed Wastes Resource Conservation and Recovery Act (RCRA) Section 3005 SCDHEC Issued March 9, 1988 -
In compliance
Operating Permit #1820-0041 Air Quality Clean Air Act - Section 112 SCDHEC Issued April, 22 1997 -
In compliance
Landfill Permit #373303-1601 RCRA Subtitle D SCDHEC Issued January, 11 1995 -
In compliance
Drinking Water Well Permit #202098AI Safe Drinking Water Act 42, U.S.C. 1412 SCDHEC In compliance
General Stormwater Permit SCR000000 FWPCA Section 402 SCDHEC Issued October 10, 1992 -
In compliance
Infectious Waste Permit #SC37-0051G N/A SCDHEC Issued May 6, 1992 -
In compliance
Environmental Laboratory Certification #37756001 N/A SCDHEC Issued May 6, 1992 -
In compliance
Underground Storage Tank #06673 RCRA Subtitle I SCDHEC Issued January 1, 1982 -
In compliance
Underground Storage Tank Permit #11174 RCRA Subtitle I SCDHEC Issued November 3, 1988 -
In compliance
Underground Storage Tank Permit #11843 RCRA Subtitle I SCDHEC Issued November 3, 1989 -
In compliance
Endangered Species Endangered Species Act, Section 7 - Consultation FWS Consultation
Historic Preservation National Historic Preservation Act, Section 106 South Carolina Historic Preservation Office Consultation
Part A Hazardous Waste Permit, Interim Storage Facility for Mixed Wastes #SCD043979822 RCRA, Section 3005 SCDHEC Issued March 9, 1998


E.1 References


[ Prev | Next | Top of file ]

10 CFR Part 50, "Domestic Licensing of Production and Utilization Facilities."

10 CFR Part 72, "Licensing Requirements for the Independent Storage of Spent Nuclear Fuel and High-level Radioactive Waste."

Atomic Energy Act of 1954, as amended, 42 USC 2011, et seq.

Clean Air Act (CAA), as amended, 42 USC 7401, et seq.

Endangered Species Act, as amended, 16 USC 1531 et seq.

Federal Power Act of 1935, 16 U.S.C. 791a-825u.

Federal Water Pollution Control Act (FWPCA), as amended, 33 USC 1251 et seq. (Also known as the Clean Water Act).

National Historic Preservation Act, as amended, 16 USC 470 et seq.

Resource Conservation and Recovery Act (RCRA) of 1976, as amended, 42 USC 6901, et seq.

Safe Drinking Water Act of 1996, as amended, 42 U.S.C. 1412, et seq.


Appendix F : GEIS Environmental Issues Not Applicable to the Oconee Nuclear Station


[ Prev | Next | Top of file ]

The following table lists those environmental issues listed in the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS) (NRC 1996) and 10 CFR Part 51, Subpart A, Appendix B ,Table B-1, that are not applicable to the Oconee Nuclear Station (ONS) because of plant or site characteristics.

ISSUE--10 CFR Part 51, Subpart A, Appendix B, Table B-1 Category GEIS Sections Comment
Surface Water Quality, Hydrology, and Use (for all plants)
Altered salinity gradients 1 4.2.1.2.2

4.4.2.2

ONS cooling system does not discharge to an estuary. Lake Keowee is freshwater.
Water-use conflicts (plants with cooling ponds or cooling towers using makeup water from a small river with low flow) 2 4.3.2.1

4.4.2.1

This issue is related to heat- dissipation systems that are not installed at ONS.
Aquatic Ecology (for plants with cooling-tower-based heat-dissipation systems)
Entrainment of fish and shellfish in early life stages 1 4.3.3 This issue is related to heat- dissipation systems that are not installed at ONS.
Impingement of fish and shellfish 1 4.3.3 This issue is related to heat- dissipation systems that are not installed at ONS.
Heat shock 1 4.3.3 This issue is related to heat- dissipation systems that are not installed at ONS
Groundwater Use and Quality
Groundwater-use conflicts (potable and service water, and dewatering; plants that use >100 gpm) 2 4.8.1.1

4.8.2.1

ONS uses < 100 gpm of groundwater.
Groundwater-use conflicts (plants using cooling towers withdrawing makeup water from a small river) 2 4.8.1.3

4.4.2.1

This issue is related to heat- dissipation systems that are not installed at ONS or are operated on bodies of water that are much smaller than Lake Keowee.
Groundwater-use conflicts (Ranney wells) 2 4.8.1.4 ONS does not have or use Ranney wells.
Groundwater quality degradation (Ranney wells) 1 4.8.2.2 ONS does not have or use Ranney wells.
Groundwater quality degradation (saltwater intrusion) 1 4.8.2.1 ONS is located on Lake Keowee, a freshwater lake.
Groundwater quality degradation (cooling ponds in salt marshes) 1 4.8.3 This issue is related to a heat- dissipation system that is not installed at ONS.
Groundwater quality degradation (cooling ponds at inland sites) 2 4.8.3 This issue is related to a heat- dissipation system that is not installed at ONS.
Terrestrial Resources
Cooling tower impacts on crops and ornamental vegetation 1 4.3.4 This issue is related to a heat- dissipation system that is not installed at ONS.
Cooling tower impacts on native plants 1 4.3.5.1 This issue is related to a heat- dissipation system that is not installed at ONS.
Bird collisions with cooling towers 1 4.3.5.2 This issue is related to a heat- dissipation system that is not installed at ONS.
Cooling pond impacts on terrestrial resources 1 4.4.4 This issue is related to a heat- dissipation systems that is not installed at ONS.


F.1 References


[ Prev | Top of file ]

10 CFR Part 51, Subpart A, Appendix B, Table B-1, "Environmental effect of renewing the operating license of a nuclear power plant."

U.S. Nuclear Regulatory Commission (NRC). 1996. Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437. Washington, D.C.


[ Top of file ]

1. The GEIS was originally issued in 1996. Addendum 1 to the GEIS was issued in 1999. Hereinafter, all references to the "GEIS" include the GEIS and its Addendum 1.

2. Duke Energy Corporation has held the license for the ONS Units 1, 2, and 3 since September 16, 1997. Before that date, Duke Power Company held the license. Duke Power Company remains a division of Duke Energy Corporation.

3. The GEIS was originally issued in 1996. Addendum 1 to the GEIS was issued in 1999. Hereafter, all references to the "GEIS" include the GEIS and its Addendum 1.

4. Naturally occurring uranium contains several forms of uranium, including approximately 0.7 percent uranium-235, the form that a nuclear reactor uses. The nuclear fuel manufacturing process removes some of the other forms, resulting in a slightly higher percentage ("enrichment") of uranium-235.

5. "Burn-up" is the length of use of, or total energy generated by, the nuclear fuel and is measured as megawatt-days per metric ton uranium.

6. Personal contact, Hara T. Knight, South Carolina Appalachian Council of Governments, March 1999.

7. Letter to Michael J. Scott, Staff Scientist, Pacific Northwest National Laboratory from Phyllis E. Lombard, Finance Director, Oconee County, October 22, 1998.

8. US Census Bureau C90STF3A

9. A sector is identified by a combination of its compass direction and the distance of its outer edge from the plant. For instance, the sector that is between 11.25 and 33.75 degrees and 64 km (40 mi) and 80 km (50 mi) from a plant is identified as NNE50.

10. U.S. Fish and Wildlife Service. 1998. Letter dated August 4, 1998, from the Acting Field Supervisor for the Charleston Field Office to Duke Power indicating that continued operation or refurbishment of ONS will have no effect on listed or proposed endangered or threatened species.

11. The GEIS was originally issued in 1996. Addendum 1 to the GEIS was issued in 1999. All references to the "GEIS" include the GEIS and its Addendum 1.

12. The GEIS was originally issued in 1996. Addendum 1 to the GEIS was issued in 1999. All references to the "GEIS" include the GEIS and its Addendum 1.

13. The title of 10 CFR 51.23 is "Temporary storage of spent fuel after cessation of reactor operations-generic determination of no significant environmental impact."

14. Comments provided by Duke in Letter K were already numbered 1 through 82; therefore, the two comments appearing in the cover letter were given the designation Ka and Kb.



Privacy Policy | Site Disclaimer
Tuesday, April 24, 2007