Accelerator Physics Group Meeting March 15, 2001 Present: Jie Wei, John Galambos, Weishie Wan, Marc Doleans, Sang ho Kim, Slava Danilov, Sasha Aleksandrov, Dong O Jeon, Eugene Tanke, Saeed Assadi Jie mentions that a PCR would be done to fix the energy at 1 GeV. We need to stay within the present baseline hardware limits (i.e. power supply capability). We will assume success in the e-polishing of the cavities - namely higher gradients.We need to look at different configurations, and their merits such as stability considerations. A pencil beam is being considered with 10-20% of the nominal emittance for linac commisioning. This would operate at a reduced duty factor, with something like a 100 micro-sec pulse. Also a linac power supply budget needs to be constructed including effects such as Lorentz detuning, micro-phonics, missing cavity operation, reference line temperature changes, etc. The ring PCRs had some confusion, but $2.4 M remain unapproved. We should write notes on our work. The loss source term work on the linac was discussed. The gas stripping term dominates at low energy. Slava noted that we may be near the threshld of the longitudinal instability regarding the injection foil assembly, but the very high Q used in the estimate is likely unrealistic. However the transverse stability is still likely a problem. Jeff reported on the beta beat studies in the ring, from non-systematic errors in the large bore quads. about a 0.4% error produces a 10% beta beat.