skip navigation links 
 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page

Morning Report for January 10, 2001

                       Headquarters Daily Report

                         JANUARY 10, 2001

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I            X                                      
REGION II                              X                   
REGION III                             X                   
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION I  JANUARY 10, 2001

Licensee/Facility:                     Notification:

Entergy Nuclear Generation Company     MR Number: 1-01-0001
Pilgrim 1                              Date: 01/05/01
Plymouth,Massachusetts                 RI PC                              
Dockets: 50-293
BWR/GE-3                              

Subject: THIRD PARTY DEDICATOR (TRENTEC) MISSED IDENTIFICATION OF        
         INCORRECTLY ASSEMBLED JOSLYN CLARK TIME DELAY RELAYS            


Discussion:

On January 2, 2001, the licensee identified improperly configured relays 
installed in the B-6 (480 volt AC) emergency load center transfer logic  
scheme. The specific application required a time delay function on four  
contacts in the relays, however, the installed relays had a time delay   
function on only two of the four contacts as specified.                  
                                                                         
The licensee had installed the 125 volt DC time delay relays for the B-6 
load center during RFO-12 (5/8/99 - 7/13/99). A total of five relays,    
manufactured by Joslyn Clark Controls, were purchased commercially and   
dedicated by a third party vendor (Trentec) for the safety-related       
application in the plant. The relays can be configured for different     
applications specified by the purchaser. In this case, the relays        
required a time delay on four contacts. The relays were delivered,       
labeled to indicate that the time delay was installed on the specified   
contacts (indicated by an "E" suffix on the part number X 714UPD E).     
Trentec, Inc., performed the dedication of the relays, however, the      
functional testing did not physically verify the time delay functionality
for all four contacts. As a result, the dedication process did not reveal
that four of the five relays were missing the right hand time pole       
contact opening link (part KPMT-1), which provides the time delay        
function on two of the four contacts. The licensee subsequently installed
two of the relays that were improperly configured in the B-6 load center 
transfer logic.                                                          
                                                                         
This configuration could have resulted in load center B-6 remaining      
de-energized on certain loss of offsite power (LOOP) sequences. In turn, 
this could have caused a loss of low pressure coolant injection (LPCI),  
since load center B-6 powers several LPCI supply valves.                 
                                                                         
As an immediate corrective action, the licensee declared LPCI inoperable 
and tagged open one of two vital bus feeder breakers to the B-6 load     
center to prevent the improperly configured relays from having the       
potential to cause a loss of load center B-6 on a LOOP. On January 7,    
2001, the licensee installed the missing piece for the relays and        
successfully tested the relays to show the plant design was met. The     
licensee is reviewing the issue for reportability under 10 CFR 21.       

Regional Action:

For information only.                                                    

Contact:  James Linville             (610)337-5129
          Russell Arrighi            (508)747-0565
_