Risk Management Series Designing for Earthquakes A Manual for Architects FEMA 454 / December 2006 EXISTING BUILDINGS--EVALUATION AND RETROFIT BY WILLIAM HOLMES 8.1 INTRODUCTION It is widely recognized that the most significant seismic risk in this country resides in our existing older building stock. Much of the country has enforced seismic design for new buildings only recently; even on the West Coast, seismic codes enforced in the 1960s and even into the 1970s are now considered suspect. Although there are sometimes difficulties in coordinating seismic design requirements with other demands in new construction, the economical, social, and technical issues related to evaluation and retrofit of existing buildings are far more complex. 8.1.1 Contents of Chapter This chapter describes the many issues associated with the risk from existing buildings, including common building code provisions covering older buildings, evaluation of the risks from any one given building and what levels of risk are deemed acceptable, and methods of mitigation of these risks through retrofit. A FEMA program to provide methods to mitigate the risk from existing buildings has been significant in advancing the state of the art, and this program is described in some detail, particularly the model building types used in most, if not all, of the FEMA documents. 8.1.2 Reference to Other Relevant Chapters The basic concepts used for seismic design or estimation of seismic performance are the same for any building. Thus, the principles described in Chapters 4, 5, and 7 are applicable for older, potentially hazardous buildings. The development of seismic systems as seen through examples of buildings in the San Francisco Bay Area is particularly relevant to the issues covered in this chapter, because systems typically evolved due to poor performance of predecessors. Nonstructural systems in buildings create the majority of dollar loss from buildings in earthquakes, although the quality of structural performance affects the level of that damage. Seismic protection of nonstructural systems, both for design of new buildings and for consideration in older buildings, is covered in Chapter 9. 8.2 BACKGROUND In every older building, a host of “deficiencies” is identified as the state of the art of building design and building codes advances. Code requirements change because the risk or the expected performance resulting from the existing provisions is deemed unacceptable. Deficiencies are commonly identified due to increased understanding of fire and life safety, disabled access, hazardous materials, and design for natural hazards. Thus, it is not surprising that many of the older buildings in this country are seismically deficient, and many present the risk of life-threatening damage. It is not economically feasible to seismically retrofit every building built to codes with no or inadequate seismic provisions, nor is it culturally acceptable to replace them all. These realities create a significant dilemma: How are the buildings that present a significant risk to life safety identified? How is the expected performance predicted for older buildings of high importance to businesses or for those needed in emergency response? How can we efficiently retrofit those buildings identified as high risk? The term seismic deficiency is used in this chapter as a building characteristic that will lead to unacceptable seismic damage. Almost all buildings, even those designed to the latest seismic codes, will suffer earthquake damage given strong enough shaking; however, damage normally considered acceptable should not be expected in small events with frequent occurrence in a given region, and should not be life threatening. Damage may be judged unacceptable due to resulting high economic cost to the owner or due to resulting casualties. Therefore, conditions that create seismic deficiencies can vary from owner to owner, from building to building, and for different zones of seismicity. For example, unbraced, unreinforced brick masonry residential chimneys are extremely vulnerable to earthquake shaking and should be considered a deficiency anywhere that shaking is postulated. On the other hand, unreinforced brick masonry walls, infilled between steel frame structural members, are expected to be damaged only in moderate to strong shaking and may not be considered a deficiency in lower seismic zones. Seismic deficiencies identified in this chapter generally will cause premature or unexpected damage, often leading to threats to life safety, in moderate to strong shaking. Buildings in regions of lower seismicity that expect Modified Mercalli Intensity (MMI) levels of not more than VII, or peak ground accelerations (PGA) of less than 0.10g (g = acceleration of gravity), may need special consideration. Of course, every building with completed construction is “existing.” However, the term existing building has been taken to mean those buildings in the inventory that are not of current seismic design. These groups of buildings, some of which may not be very old, include buildings with a range of probable performance from collapse to minimal damage. In this chapter, the term “existing building” is used in this context. 8.2.1 Changes in Building Practice and Seismic Design Requirements Resulting in Buildings that are Currently Considered Seismically Inadequate Chapter 7 documents in detail how building systems have evolved in the San Francisco Bay Area. This evolution was probably driven more by fire, economic, and construction issues than by a concern for seismic performance, at least in the first several decades of the twentieth century, but many changes took place. Similarly, Chapter 6 gives a brief history of the development of seismic codes in the United States. It is clear that for many reasons, building construction and structural systems change over time. In the time frame of the twentieth century, due to the rapid increase in understanding of the seismic response of buildings and parallel changes in code requirements, it should be expected that many older buildings will now be considered seismically deficient. Seismic codes in this country did not develop at all until the 1920s, and at that time they were used voluntarily. A mandatory code was not enforced in California until 1933. Unreinforced masonry (URM) buildings, for example, a popular building type early in the twentieth century and now recognized as perhaps the worst seismic performer as a class, were not outlawed in the zones of high seismicity until the 1933 code, and continued to be built in much of the country with no significant seismic design provisions until quite recently. Figure 8-1 shows an example of typical URM damage. The first modern seismic codes were not consistently applied until the 1950s and 1960s, and then only in the known regions of high seismicity. Of course, not all buildings built before seismic codes are hazardous, but most are expected to suffer far more damage than currently built buildings Even buildings designed to “modern” seismic codes may be susceptible to high damage levels and even collapse. Our understanding of seismic response has grown immensely since the early codes, and many building characteristics that lead to poor performance were allowed over the years. For example, concrete buildings of all types were economical and popular on the West Coast in the 1950s and 1960s. Unfortunately, seismic provisions for these buildings were inadequate at the time, and many of these buildings require retrofit. Highlights of inadequacies in past building codes that have, in many cases, created poor buildings are given below. Changes In Expected Shaking Intensity and Changes in Zoning Similar to advancements in structural analysis and the understanding of building performance, enormous advancements have been made in the understanding of ground motion, particularly since the 1950s and 1960s. The seismicity (that is, the probability of the occurrence of various-sized earthquakes from each source) of the country, the likely shaking intensity from those events depending on the distance from the source and the local soil conditions, and the exact dynamic nature of the shaking (the pattern of accelerations, velocities, or displacements) are all far better understood. These advancements have caused increases in seismic design forces from a factor of 1.5 in regions very near active faults (on the West Coast) to a factor of 2 to 3 in a few other areas of the country (e.g. Utah; Memphis, Tennessee). The damage to the first Olive View Hospital (Figure 8-2), in addition to other issues, was a result of inadequate zoning. Changes in Required Strength or Ductility As discussed in Chapter 4, the required lateral strength of a seismic system is generally traded off with the ductility (the ability to deform inelastically—normally controlled by the type of detailing of the components and connections) of the system. Higher strength requires lower ductility and vice versa. The most significant changes in codes—reflecting better understanding of minimum requirements for life safety—are general increases in both strength and ductility. Many building types designed under previous seismic provisions, particularly in the 1950s, 1960s, and 1970s, are now considered deficient, including most concrete-moment frames and certain concrete shear walls, steel- braced frames, and concrete tilt-ups. Other buildings designed with systems assumed to possess certain ductility have been proven inadequate. Figure 8-3 shows typical steel moment-frame damage in the Northridge earthquake caused by brittle behavior in a structural system previously thought to be of high ductility. Recognition of the Importance of Nonlinear Response Historically, a limited amount of damage that absorbed energy and softened the building, thus attracting less force, was thought o reduce seismic response. Although this is still true, it is now recognized that the extent and pattern of damage must be controlled. Early codes required the design of buildings for forces three to six times less than the elastic demand (the forces that the building would see if there was no damage), assuming that the beneficial characteristics of damage would make up the difference. Unfortunately, buildings are not uniformly damaged, and the change in structural properties after damage (nonlinear response) often will concentrate seismic displacement in one location. For example, if the lower story of a building is much more flexible or weaker than the stories above, damage will concentrate at this level and act as a fuse, never allowing significant energy absorption from damage to the structure above. This concentrated damage can easily compromise the gravity load-carrying capacity of the structure at that level, causing collapse. Similarly, concrete shear walls were often “discontinued” at lower floors and supported on columns or beams. Although the supporting structure was adequately designed for code forces, the wall above is often much stronger than that and remains undamaged, causing concentrated and unacceptable damage in the supporting structure. A final example of this issue can be seen by considering torsion. As explained in Chapter 4, Section 4.11, torsion in a building is a twisting in plane caused by an imbalance in the location of the mass and resisting elements. Older buildings were often designed with a concentration of lateral strength and stiffness on one end—an elevator/stair tower, for example—and a small wall or frame at the other end to prevent torsion. However, when the small element is initially damaged, its strength and stiffness changes, and the building as a whole may respond with severe torsion. Current codes contain many rules to minimize configurations that could cause dangerous nonlinear response, as well as special design rules for elements potentially affected (e.g., columns supporting discontinuous shear walls). Olive View Hospital featured a weak first story in the main building, causing a permanent offset of more than one foot and near collapse; discontinuous shear walls in the towers caused a failure in the supporting beam and column frame, resulting in complete overturning of three of the four towers. Figure 8-4 shows a typical “tuck-under” apartment building in which the parking creates a weak story. 8.2.2 Philosophy Developed for Treatment of Existing Buildings Building codes have long contained provisions to update life-safety features of buildings if the occupancy is significantly increased in number or level of hazard (transformation of a warehouse to office space, for example). As early as the mid-1960s, this concept started to be applied to seismic systems. Many older buildings contained entire structural systems no longer permitted in the code (e.g., URM, poorly reinforced concrete walls), and it quickly became obvious that 1) these components could not be removed, and 2) it was impractical and uneconomical to replace all older buildings. The “new” code could therefore not be applied directly to older buildings, and special criteria were needed to enable adaptive reuse while meeting the need to protect life safety of the occupants. In some cases, an entirely new and code-complying lateral system was installed, while leaving existing, now prohibited, construction in place. (This procedure was used in many school buildings in California after the Field Act was passed in 1933—up until the school seismic safety program was essentially completed in the 1960s.) This procedure proved very costly and disruptive to the building and was thought to discourage both improved seismic safety and general redevelopment. A philosophy quickly developed suggesting that existing buildings be treated differently from new buildings with regard to seismic requirements. First, archaic systems and materials would have to be recognized and incorporated into the expected seismic response, and secondly, due to cost and disruption, seismic design force levels could be smaller. The smaller force levels were rationalized as providing minimum life safety, but not the damage control of new buildings, a technically controversial and unproven concept, but popular. Commonly existing buildings were then designed to 75% of the values of new buildings—a factor that can still be found, either overtly or hidden, in many current codes and standards for existing buildings. Occasionally, early standards for existing buildings incorporated a double standard, accepting a building that passed an evaluation using 75% of the code, but requiring retrofits to meet a higher standard, often 90% of the code. 8.2.3 Code Requirements Covering Existing Buildings As the conceptual framework of evaluation and retrofit developed, legal and code requirements were also created. These policies and regulations can be described in three categories; active, passive, and post-earthquake. Active policies require that a defined set of buildings meet given seismic criteria in a certain time frame—without any triggering action by the owner. For example, all bearing- wall masonry buildings in the community must meet the local seismic safety criteria within ten years. Passive policies require minimum seismic standards in existing buildings only when the owner “triggers” compliance by some action— usually extensive remodeling, reconstruction, or addition. Post-earthquake policies developed by necessity after several damaging earthquakes, when it became obvious that repairing an obviously seismically poor building to its pre- earthquake condition was a waste of money. It then became necessary to develop triggers to determine when a building could simply be repaired and when it had to be repaired and retrofitted as well. Passive Code Provisions As noted above, the development of requirements to seismically update a building under certain conditions mimicked economic and social policies well-established in building codes. Namely, the concept crystallized that if sufficient resources were spent to renew a building, particularly with a new occupancy, then the building should also be renewed seismically. Seismic “renewal” was defined as providing life safety, but not necessarily reaching the performance expected from a new building. A second kind of trigger—that could be termed “trigger of opportunity”—has also been used in some communities. These policies try to take advantage of certain conditions that make seismic improvements more palatable to an owner, such as retrofit of single-family dwellings at point of sale or requiring roof diaphragm upgrades at the time of re-roofing. Triggers based on alterations to the building are by far the most common and will be discussed further here. These policies are somewhat logical and consistent with code practice, but they created two difficult socioeconomic- technical issues that have never been universally resolved. The first is the definition of what level of building renewal or increase in occupancy-risk triggers seismic upgrading. The second is to establish the acceptable level of seismic upgrading. Most typically, the triggering mechanisms for seismic upgrade are undefined in the code and left up to the local building official. The Uniform Building Code, the predecessor to the IBC in the western states, waffled on this issue for decades, alternately inserting various hard triggers (e.g., 50% of building value spent in remodels) and ambiguous wording that gave the local building official ultimate power. The use of this mechanism, whether well defined in local regulation or placed in the hands of the building official, ultimately reflects the local attitude concerning seismic safety. Aggressive communities develop easily and commonly triggered criteria, and passive or unaware communities require seismic upgrade only in cases of complete reconstruction or have poorly defined, easily negotiated triggers. For more specific information on seismic triggers in codes, see the accompanying sidebar. Box 1 Seismic Triggers in Codes Events or actions that require owners to seismically retrofit their buildings are commonly called triggers. For example, in many communities, if an owner increases the occupancy risk (as measured by number of occupants, or by use of the building), they must perform many life-safety upgrades, including seismic ones. However, for practical and economic reasons, seldom does this trigger require conformance with seismic provision for new buildings, but rather with a special life-safety level of seismic protection, lower than that used for new buildings. The code with the longest history in high-seismic regions, the Uniform Building Code (UBC), has long waffled on this issue. Besides the traditional code life- safety trigger based on clear-cut changes in occupancy, this code over the years has included provisions using hard triggers based on the cost of construction, and soft language that almost completely left the decision to the local building official. The last edition of this code, the 1997 UBC, basically allowed any (non-occupancy related) alteration as long as the seismic capacity was not made worse. The codes and standards that will replace the UBC are based on a federally funded effort and published by FEMA as the NEHRP Provisions. These codes include the International Building Code (IBC), the National Fire Protection Agency (NFPA) and ASCE 7, a standard covering seismic design now ready for adoption by the other codes. This family of regulations has a common limit of a 5% reduction in seismic capacity before “full compliance” is required. This reduction could be caused by an increase in mass (as with an addition) or a decrease in strength (as with an alteration that places an opening in a shear wall). Full compliance in this case is defined as compliance with the provisions for new buildings that do not translate well to older buildings. It is unclear how this will be interpreted on the local level. Many local jurisdictions, however, have adopted far more definitive triggers for seismic retrofit. San Francisco is a well-known example, perhaps because the triggers are fairly elaborately defined and because they have been in place for many years. In addition to the traditional occupancy-change trigger, San Francisco requires conformance with seismic provisions specially defined for existing buildings when substantial nonstructural alterations are done on 2/3 or more of the number of stories within a two-year period, or when substantial structural alterations, cumulative since 1973, affect more than 30% of the floor and roof area or structure. The City of Portland, Oregon requires a seismic upgrade of URMs when the cost of construction exceeds $30/sf for a one story building, or $40/sf for buildings greater than two stories. Although most jurisdictions leave this provision purposely loose, some also have adopted definitive triggers based on cost of construction, on the particular building type, and on various definitions of significant structural change. Government, in some cases, has been much more aggressive in setting triggers to activate seismic retrofit, perhaps to create a lawful need for funds which otherwise would be difficult to obtain. The state of California has set a definitive list of seismic triggers for state-owned buildings: a) alteration cost exceeding 25% of replacement cost; b) change in occupancy; c) reduction of lateral load capacity by more than 5% in any story; d) earthquake damage reducing lateral load capacity by more than 10% at any story. The federal government likewise, in RP 6, [NIST, 2002], also has definitive triggers: a) change in occupancy that increases the building’s importance or level of use; b) alteration cost exceeding 50% of replacement cost; c) damage of any kind that has significantly degraded the lateral system; d) deemed to be a high seismic risk; and e) added to federal inventory though purchase or donation. The regulations and policies governing any building, private or public, which will be significantly altered, should be researched in the planning stage to understand the effective seismic triggers, written or understood. When seismic improvement is triggered, the most common minimum requirement is life safety consistent with the overall code intent. However, the use of performance-based design concepts to establish equivalent technical criteria is a recent development and is not yet universally accepted. As indicated in the last section, the initial response to establishing minimum seismic criteria was to use the framework of the code provisions for new buildings with economic and technical adjustments as required. These adjustments included a lower lateral force level (a pragmatic response to the difficulties of retrofit), and special consideration for materials and systems not allowed by the provisions for new buildings. (Unreinforced masonry, for example, was not only prohibited as a structural system in zones of high seismicity, but also could not be used in a building at all.) Use of a lateral force level of 75% of that required for new buildings became fairly standard, but the treatment of archaic materials is highly variable from jurisdiction to jurisdiction. Many local retrofit provisions are gradually being replaced by national guidelines and standards for seismic evaluation and retrofit (e.g. ASCE 31, 2003; FEMA 356, 2000, etc.). In addition, performance based seismic design is enabling a more direct approach to meeting a community’s minimum performance standards—although this requires the policy-makers to decide what the minimum performance standard should be, a difficult task that crosses social, economic, and technical boundaries. In summary, both the passive triggers for seismic retrofit and the design or performance criteria are often ill-defined and, at best, highly variable between jurisdictions. Design professionals should always determine the governing local, state, or federal regulations or policies when designing alterations or remodels on existing buildings. Active Code Provisions Active code provisions result from policy decisions of a jurisdiction to reduce the community seismic risk by requiring seismic upgrading of certain buildings known to be particularly vulnerable to unacceptable damage. For the most part, these provisions are unfunded mandates, although low-interest loan programs have been developed in some cases. These risk reduction programs usually allow owners a lengthy period to perform the retrofit or to demolish the buildings—ten years or more. The standard for retrofit is also normally included in the law or regulation and is typically prescriptive, although performance-based design options are becoming more acceptable. Two large-scale examples of active seismic code provisions were started by the state of California. The first was a program to reduce the risk from URM buildings. The state legislature, lacking the votes to simply require mitigation throughout the state, instead passed a law (SB 547-1986) that required local jurisdictions to develop inventories of these buildings in their area, to notify the owners that their building was considered hazardous, and to develop a community-wide hazard reduction plan. Although not required to do so, most jurisdictions chose as their hazard reduction plan to pass active code ordinances giving owners of the buildings ten or so years to retrofit them. Over 10,000 URM buildings have been brought into compliance with these local ordinances, most by retrofit, but some by demolition (SSC, 2003). The second program, created by SB 1953 in 1994 following the Northridge earthquake, gave California hospital owners until 2030 to upgrade or replace their hospitals to comply with state law governing new hospital buildings. The program’s intention is to enable buildings to be functional following an earthquake. This law affected over 500 hospitals and over 2,000 buildings (Holmes, 2002). Although compliance is ongoing, this law has been problematic due to the high cost and disruption associated with retrofitting hospital buildings, and the highly variable economic condition of the health system as well as individual facilities. Other examples include local ordinances to retrofit tilt-up buildings, less controversial because of the clear high vulnerability and low retrofit cost of these buildings. Similar to investigating local regulations regarding triggers, it is also wise to determine if any existing building planned for alterations is covered by (or will be covered in the foreseeable future) a requirement to retrofit. It is generally acknowledged that seismic improvements are easier to implement when done in association with other work on the building. Post-Earthquake Code Provisions Following a damaging earthquake, many buildings may be closed pending determination of safety and necessary repairs. A lack of clear repair standards and criteria for re-occupancy has created controversy and denied owners use of their buildings after most damaging earthquakes. Assuming that the earthquake itself is the ultimate judge of seismic acceptability, many communities may take the opportunity in the post-earthquake period to require strengthening of buildings that are apparently seismically deficient due to their damage level. However, implementation of this theory incorporating conservative policies that require many retrofits may delay the economic recovery of the community. On the other hand, standards for repair and/or strengthening which are not conservative could lead to equal or worse damage in the next earthquake. It has also been observed that owners of historic, rent-controlled, or otherwise economically controlled buildings may have an incentive to demolish damaged buildings to the detriment of the community at large. Traditionally, communities (building departments) have used color codes for several or all of the following categories of buildings following an earthquake: A. Undamaged; no action required. If inspected at all, these buildings will be Green-tagged. B. Damaged to a slight extent that will only require repair of the damage to the original condition. These buildings will generally be Green-tagged, but the category could also include some Yellow-tags. C. Damaged to a greater extent that suggests such seismic weaknesses in the building that the overall building should be checked for compliance with minimum seismic standards. This will often require overall retrofit of the building. These buildings will generally be Red-tagged, but the category could also include some Yellow tags. C1. (A subcategory of C). Damaged to an extent that the building creates a public risk that requires immediate mitigation, either temporary shoring or demolition. The ultimate disposition of these buildings may not be determined for several months. These buildings will all be Red-tagged. The most significant categorization is the differentiation between B and C. The difference to an owner between being placed in one category or the other could be an expense on the order of 30%-50% of the value of the building, reflecting the added cost of retrofit to that of repair. Earthquakes being rare, few communities have been forced to create these policies, but a few have. Oakland, California, prior to the Loma Prieta earthquake, set a trigger based on the loss of capacity caused by the damage. If the damage was determined to have caused a loss of over 10% of lateral force capacity, then retrofit was triggered. Los Angeles and other southern California communities affected by the Northridge earthquake used a similar standard, but the 10% loss was applied to lines of seismic resistance rather than the building as a whole. These code regulations, although definitive, are problematic because of the technical difficulty of determining loss of capacity, particularly to the accuracy of 1% (a 1% change can trigger a retrofit). The importance of this issue has been magnified by interpretation of federal laws that creates a tie between reimbursement of the cost of repair of certain local damage to the pre-existence and nature of these local damage triggers. Owners and designers of older existing buildings should be aware of such triggers that could affect them should they suffer damage from an earthquake. In some cases, it may be prudent for an owner to voluntarily retrofit a vulnerable building to avoid the possibility of being forced to do it in a post-earthquake environment as well as to possibly avoiding a long closure of the building. 8.3 THE FEMA PROGRAM TO REDUCE THE SEISMIC RISK FROM EXISTING BUILDINGS In 1985, the Federal Emergency Management Agency (FEMA) recognized that the principal seismic risk in this country came from the existing building stock, the majority of which was designed without adequate seismic provisions. Following a national workshop that identified significant issues and potential educational and guideline projects that FEMA could lead, a program was launched that is still ongoing. In addition to providing education and technical guidelines in the area of high-risk existing buildings, other FEMA programs were also significant in enabling communities to understand and mitigate their seismic risk, most notably the development of the regional loss-estimating computer program, HAZUS. Most of these activities are documented as part of the FEMA “yellow book” series (so known because of its distinctive yellow covers), well known to engineers in this country and, in fact, around the world. Unfortunately, these documents are less known to architects, although many of them contain useful insights into not only the issues surrounding seismic evaluation and retrofit of existing buildings, but also into all aspects of seismic design. 8.3.1 FEMA-Sponsored Activity for Existing Buildings Following is a summary of selected FEMA-sponsored projects beginning in the late 1980s. A full listing is given in FEMA 315, Seismic Rehabilitation of Buildings, Strategic Plan 2005. Rapid Visual Screening FEMA 154: Rapid Visual Screening of Buildings for Potential Seismic Hazards, 1988, updated 2001 A method to enable an efficient first sorting of selected buildings into an adequately life-safe group and a second group that will require further evaluation. The evaluation was intended to be performed on the street in an hour or less per building. The first task is to assign the building to a predefined model building type and then identify additional characteristics that could refine the seismic vulnerability. The method has proven useful to efficiently generate an approximate mix of buildings that will properly characterize a community’s vulnerability, but not to definitely rate individual buildings, due to the difficulty of identifying significant features from the street. Generally it is necessary to obtain access to the interior of a building, or, more commonly, it is even necessary to review drawings to confidently eliminate older buildings as potentially hazardous. Evaluation of Existing Buildings FEMA 178: NEHRP Handbook for Seismic Evaluation of Existing Buildings, 1989 and FEMA 310: Handbook for the Seismic Rehabilitation of Buildings: a Prestandard. A widely used guide to determine if individual buildings meet a nationally accepted level of seismic life safety. This method requires engineering calculations and is essentially prescriptive, which facilitates consistency and enables enforceability. This life-safety standard was adopted by, among others, the federal government and the state of California in certain programs. The prescriptive bar may, however, have been set too high, because very few older buildings pass. Since its original development, FEMA 178 has been refined and republished as FEMA 310, and finally was adopted as a Standard by the American Society of Civil Engineers as ASCE 31 in 2003. Techniques Used in Seismic Retrofit FEMA 172: NEHRP Handbook of Techniques for Seismic Rehabilitation of Existing Buildings, 1992 In recognition of the lack of experience in seismic upgrading of buildings of most of the country’s engineers and architects, this document outlined the basic methods of seismically strengthening a building, including conceptual details of typically added structural elements. The material recognizes the FEMA model building types, but is primarily organized around strengthening of structural components, perhaps making the material less directly accessible.The document also preceded by several years the publication of the analytical tools to design retrofits (FEMA 273, see below). For whatever reason, the publication went relatively unused, despite the fact that it contains useful information, particularly for architects unfamiliar with seismic issues. Financial Incentives FEMA 198: Financial Incentives for Seismic Rehabilitation of Hazardous Buildings, 1990 To encourage voluntary seismic upgrading, this document described the financial incentives to do so, ranging from tax benefits to damage avoidance. Development of Benefit-Cost Model FEMA 227: A Benefit-Cost Model for the Seismic Rehabilitation of Buildings, 1992 Due to the expected high cost of seismic rehabilitation, the need to provide a method to calculate the benefit-cost ratio of seismic retrofit was identified early in the program. This requires estimation of financial losses from earthquake damage resulting from a full range of ground-shaking intensity. Financial losses include direct damage to structural and nonstructural systems as well as business interruption costs. A controversial feature was the optional inclusion of the value of lives lost in the overall equation. The project was primarily to develop the model rather than to provide new research into expected damage or casualty rates. Thus, approximate relationships available at the time were used. However, the documentation concerning contributing factors to a benefit-cost analysis is quite complete, and a computerized functional spreadsheet version of the method was developed. Although the use of benefit-cost analysis never became popular in the private sector, trials of the method indicated that very low retrofit costs, high business-interruption losses, or high exposure-to-casualty losses are required to result in a positive benefit-cost ratio. For example rehabilitation of tilt-up buildings is usually fairly inexpensive and usually proves cost effective. Similarly, buildings with high importance to a business or with high occupancy in areas of high seismicity also result in positive results. Despite the apparent overall results from this program, considerable rehabilitation activity continued, both in conditions expected to yield a positive benefit-cost and in other conditions (in many cases due to extreme importance given to life safety). Typical Costs of Seismic Rehabilitation FEMA 156: Typical Costs for Seismic Rehabilitation of Existing Buildings, 1988, 2nd edition, 1994. The second edition of this document collected case histories of constructed rehabilitation and completed reports judged to have realistic costs. A database was created to separate costs by primary influence factors: model building types, rehabilitation performance objectives, and seismicity. A serious difficulty in collection of accurate data was the inevitable mixing of pure rehabilitation costs and associated costs such as life-safety upgrades, the American Disabilities Act (ADA), and even remodels. Although a large amount of data was collected, there was not nearly enough to populate all combinations of the factors. Nevertheless, a method was developed to use the data to make estimates of costs for given situations. The major problem was that the coefficient of variation of rehabilitation costs, for any given situation, is very high due to high variability in the extent of seismic deficiencies. The information collected is probably most useful to estimate costs for large numbers of similar buildings where variations will average out. Use of the method to accurately estimate the cost of a single building is not recommended, although even the ranges given could be useful for architects and engineers not familiar with retrofit issues. Technical Guidelines for Seismic Rehabilitation FEMA 273: NEHRP Guidelines for the Seismic Rehabilitation of Buildings, 1997 and FEMA 356 Prestandard and Commentary for the Seismic Rehabilitation of Buildings. This document, developed over five years by over 70 experts, was the culmination of the original program. Previously, the most common complaint from engineers and building officials was the lack of criteria for seismic retrofit. FEMA 273 incorporated performance-based engineering, state-of-the-art nonlinear analysis techniques, and an extensive commentary to make a significant contribution to earthquake engineering and to focus laboratory research on development of missing data. The document broke away from traditional code methods and in doing so, faced problems of inconsistency with the design of new buildings. Improvements were made in a follow-up document, FEMA 356, but the practical results from use of the method indicate that considerable judgment is needed in application. Work is continuing to improve analysis methods and in methods to predict the damage level to both components of a building and to the building as a whole. Even given these difficulties, the document has become the standard of the industry. Development of a Standardized Regional Loss Estimation Methodology—HAZUS National Institute of Building Sciences, Earthquake Loss Estimation Methodology, Technical Manual (for latest release). A good summary of this development is contained in a paper by Whitman, et al. in EERI Earthquake Spectra, vol 13, no 4. FEMA also maintains a HAZUS website, www.fema.gov/hazus. The development of a standardized regional loss estimation methodology was not in the original FEMA plan to reduce risks in existing buildings. However, this development has had a major impact in educating local officials about their seismic risks and estimating the level of risk around the country in a standard and comparable way. In 1990, when the development of HAZUS began, the primary goals were to raise awareness of potential local earthquake risks, to provide local emergency responders with reasonable descriptions of post-earthquake conditions for planning purposes, and to provide consistently created loss estimates in various regions to allow valid comparison and analysis. The loss estimation methodology was intended to be comprehensive and cover not only building losses, but also damage to transportation systems, ports, utilities, and critical facilities. A technically defensible methodology was the goal, not necessarily an all- encompassing software package. When it became obvious that the methodology was far more useful and could be more consistently applied as software, HAZUS was born. The program uses census data and other available physical and economic databases to develop, on a first level of accuracy, a model of local conditions. Expected or speculated seismic events can be run and losses estimated. Losses include direct damage, business interruption, and casualties, as well as loss of utilities, loss of housing units, and many other parameters of use to emergency planners. The building inventory uses the FEMA model building types and an analysis method closely tied to FEMA 273, linking HAZUS to other FEMA-sponsored work regarding existing buildings. Subsequent to the original development activity, HAZUS was expanded to create loss estimates for wind and flood. Incremental Rehabilitation FEMA 395, Incremental Seismic Rehabilitation of School Buildings (K-12), 2003. This is the first in a series of manuals that FEMA (U.S. Department of Homeland Security) intends to develop for various occupancy types including, for example, schools, hospitals, and office buildings. The concept is based on the fact that seismic strengthening activities are more efficiently accomplished in conjunction with other work on the building, and such opportunities should be identified and exploited even if only part of a complete rehabilitation is accomplished. This is perhaps most applicable to K-12 school buildings because of their relatively small size and ongoing maintenance programs. FEMA model building types are again used to categorize potential opportunities in different conditions. As is pointed out in the manual, this technique has to be applied with care to avoid an intermediate structural condition that is worse than the original. 8.3.2 The FEMA Model Building Types Most of these developments were part of the integrated plan developed in 1985. As such, FEMA coordinated the projects and required common terminology and cross-references. The most successful and virtually standard-setting effort was the creation of a set of model building types to be used for the characterization of existing buildings. The model building types are based primarily on structural systems rather than occupancy, but have proven extremely useful in the overall program. Model building types are defined by a combination of the gravity-load carrying system and the lateral-load carrying system of the building. Not every building type ever built in the country and certainly not the world is represented, but the significant ones are, and the relative risks of a community can well be represented by separating the local inventory into these types. Of course, there was no attempt to represent every “modern” building type because they are not considered hazardous buildings. However, with minor sub-categorization that has occurred with successive documents, the majority of buildings, new or old, now can be assigned a model building type. The test of the usefulness came with the successful development of HAZUS using the model building type because this program needed a reasonably simple method to characterize the seismic vulnerability of inventories of buildings across the country. Currently, no single FEMA document contains a graphic and clear description of the model building types, although engineers can generally determine the correct category. Because of the ubiquitous FEMA-developed documents, guidelines, and standards regarding existing buildings, and their common use by engineers, such descriptions are included here to facilitate communication with architects. The types are illustrated on pages 8-23 through 8-31. Table 8-3, at the end of the chapter, presents a summary of the performance charactoristics and commom rehabilitation techniques. 8.4 SEISMIC EVALUATION OF EXISTING BUILDINGS Not all older buildings are seismically at risk. If they were, the damage from several earthquakes in this country, including the 1971 San Fernando and the 1984 Northridge events, would have been devastating, because much of the inventory affected was twenty or more years old. Often, strong ground shaking from earthquakes significantly damages building types and configurations well known to be vulnerable, and occasionally highlights vulnerabilities previously unrealized. For example, the Northridge earthquake caused damage to many wood- frame buildings—mostly apartments—and relatively modern steel moment-frame buildings, both previously considered to be of low vulnerability. It is natural to catalogue damage after an earthquake by buildings with common characteristics, the most obvious characteristic being the construction type, and the secondary characteristic being the configuration. Both of these parameters are central to processes developed to identify buildings especially vulnerable to damage before the earthquake. In fact, the categorization of damage by building type is primarily what led to the development of the FEMA Model Building Types discussed in Section 8.3.2. However, only in the most vulnerable building types does damage occur relatively consistently. For example, at higher levels of shaking, the exterior walls of unreinforced masonry bearing-wall buildings have relatively consistently fallen away from their buildings in many earthquakes, ever since this building type was built in large numbers in the late 19th century. More recently, a high percentage of “pre-Northridge” steel moment-frame buildings have received damage to their beam-column connections when subjected to strong shaking. Even in these cases, the damage is not 100% consistent and certainly not 100% predictable. In building types with less vulnerability, the damage has an even higher coefficient of variation. Engineers and policymakers, therefore, have struggled with methods to reliably evaluate existing buildings for their seismic vulnerability. As discussed in Section 8.2, the initial engineering response was to judge older buildings by their capacity to meet the code for new buildings, but it became quickly apparent that this method was overly conservative, because almost every building older than one or two code-change cycles would not comply—and thus be considered deficient. Even when lower lateral force levels were used, and the presence of archaic material was not, in itself, considered a deficiency, many more buildings were found deficient than was evidenced in serious earthquake damage. Thus, policymakers have generally been successful in passing active retrofit provisions (see Section 8.2.3) only in the most vulnerable buildings, such as URM and tilt-ups, where damage has been significant and consistent, and individual building evaluation is not particularly significant. The evaluation of existing buildings typically starts with identification of the building type and damaging characteristics of configuration (e.g., soft story). This can be done rapidly and inexpensively but, except for a few vulnerable building types, is unreliable when taken to the individual building level. Engineers and code writers have also developed intermediate levels of evaluation in which more characteristics are identified and evaluated, many by calculation. In the last decade, more sophisticated methods of analysis and evaluation have been developed that consider the nonlinear response of most structures to earthquakes and very detailed material and configuration properties that will vary from building to building. 8.4.1 Expected Performance by Building Type As previously mentioned, damage levels after earthquakes are collected and generally assigned to bins of common characteristics, most commonly the level of shaking, building material and type, and configuration. Combined with numerical lateral-force analysis of prototype buildings, this information can be analyzed statistically. The three primary parameters - building type, shaking level, and damage level - are often displayed together in a damage probability matrix similar to Table 8-1. The variability of damage is such that for any shaking level, as shown in the columns, there is normally a probability that some buildings will be in each damage state. The probabilities in these tables can be interpreted as the percentage of a large number of buildings expected to be in each damage state, or the chances, given the shaking level, that an individual building of this type with be damaged to each level. Statistical information such as this is used in several ways: Identification of clearly vulnerable or dangerous buildings to help establish policies of mitigation Many extremely vulnerable building types or components can be identified by observation without statistical analysis, including URM, soft-story “tuck-under” apartment buildings, the roof-to-wall connection in tilt-up buildings, residences with cripple wall first-floor construction, and connections of pre- Northridge steel moment-frames. The clearly and more consistently dangerous building types have often generated enough community concern to cause the creation of policies to mitigate the risks with retrofit. For a combination of reasons, URMs and tilt-ups currently are the targets of the most active mitigation policies. Earthquake Loss Estimation Regional earthquake loss estimates have been performed for forty or more years to raise awareness in the community about the risks from earthquakes and to facilitate emergency planning. Given an approximate distribution of the building inventory and a map of estimated ground motion from a given earthquake, damage-probability matrices (or similar data) can be used to estimate damage levels to the building stock. From the damage levels, economic loss, potential casualties, and business interruption in a community can be estimated. Starting in 1991, FEMA began a major program to develop a standard way of performing such loss estimations to facilitate comparative loss estimates in various parts of the country. This program resulted in a computer program, HAZUS, described briefly in Section 8.3.1. Formal Economic Loss Evaluations (e.g. Probable Maximum Loss or PML) Since consensus loss relationships became available (ATC, 1985), a demand has grown to include an estimate of seismic loss in “due-diligence” studies done for purchase of buildings, for obtaining loans for purchase or refinance, or for insurance purposes. An economic loss parameter, called Probable Maximum Loss, has become the standard measuring stick for these purposes. The PML for a building is the pessimistic loss (the loss suffered by the worst 10% of similar buildings) for the worst shaking expected at the site (which gradually became defined as the shaking with a 500-year return period, similar to the code design event). Although a detailed analysis can be performed to obtain a PML, most are established by building type and a few observable building characteristics. Because of the high variability in damage and the relatively incomplete statistics available, PMLs are not very reliable, particularly for an individual building. Rapid Evaluation As foreseen by FEMA’s original plan for the mitigation of risks from existing buildings, a rapid evaluation technique should be available to quickly sort the buildings into three categories: obviously hazardous, obviously acceptable, and uncertain. The intent was to spend less than two hours per building for this rapid evaluation. Under the plan, the uncertain group would then be evaluated by more detailed methods. The results of FEMA’s development efforts, FEMA 154 (Section 8.3.1) is fairly sophisticated but, because of the large amount of unknown building data that is inherent in the system, for an individual building, is unreliable. The sorting method is probably quite good for estimating the overall vulnerability of a community because of the averaging effect when estimating the risk of many buildings. 8.4.2 Evaluation of Individual Buildings Engineers have been seismically evaluating existing buildings for many years, whether by comparing the conditions with those required by the code for new buildings, by using some local or building-specific standard (e.g. URMs), or by using their own judgment. These methods are still used, as well as very sophisticated proprietary methods developed within private offices, but the majority of evaluations are now tied in some way to the general procedures of ASCE 31-03, Seismic Evaluation of Existing Buildings (ASCE, 2003), that in 2003 became a national standard. There are three levels of evaluation in the standard called tiers, which, not accidentally, are similar to the standard of practice prior to the standardization process. These levels of evaluation are briefly described below, as well as similar methods that fall in the same categories. However, before beginning a seismic evaluation, particularly of a group of buildings, it is logical to assume that buildings built to modern codes must meet some acceptable standard of life safety. Due to the large number of older buildings, the effort to eliminate some from consideration resulted in several well-known milestone years. First it was compliance with the 1973 Uniform Building Code (UBC) or equivalent. After study and reconsideration of relatively major changes made in the 1976 UBC, this code was used as a milestone. Primarily caused by life-threatening damage to various building types in the 1994 Northridge earthquake and subsequent code changes, a relatively complex set of milestone years was developed. ASCE 31 contains such a set of code milestone years for each of the several codes used in this country over the last thirty years. Although ASCE 31 suggests that compliance with these codes is only a recommended cut-off to not require evaluations for life safety, in all but very unusual situations, the table can be accepted. This table, Table 3-1 of ASCE 3,1 is reproduced as Figure 8-7. Initial Evaluation (ASCE 31 Tier 1) The ASCE Tier 1 evaluation is similar to FEMA’s Rapid Evaluation in that it is based on the model building type and certain characteristics of the building. The significant difference is that structural drawings, or data equivalent to structural drawings, are required to complete the evaluation, and the evaluation will take several days rather than several hours. After identifying the appropriate FEMA Building Type, a series of prescriptive requirements are investigated, most of which do not require calculations. If the building is found to be noncompliant with any requirement, it is potentially seismically deficient. After completing the investigation of a rather exhaustive set of requirements, the engineer reviews the list of requirements with which the building does not comply, and decides if the building should be categorized as noncompliant or deficient. A conservative interpretation of the method is that any single noncompliance is sufficient to fail the building, but most engineers exercise their judgement in cases of noncompliance with only a few requirements. Historically, this method has developed with the pass/fail criterion of life safety, but the final ASCE Standard includes criteria for both Life Safety and Immediate Occupancy, a performance more closely related to continued use of the building. Because of the importance associated with the Immediate Occupancy performance level, a building cannot pass these requirements with only a Tier 1 analysis. Intermediate Evaluation (ASCE 31 Tier 2) The ASCE intermediate level of evaluation, called Tier 2, is similar in level of effort of historical nonstandardized methods. Normally, an analysis of the whole building is performed and the equivalents of stress checks are made on important lateral force-resisting components. This analysis is done in the context and organization of the set of requirements used in Tier 1, but the process is not unlike seismic analysis traditionally performed for both evaluation and design of new buildings. ASCE 31 includes the requirements for both the LifeSafety and Immediate Occupancy performance levels for a Tier 2 Evaluation. Detailed Evaluation (ASCE 31 Tier 3) The most detailed evaluations are somewhat undefined because there is no ceiling on sophistication or level of effort. The most common method used in Tier 3 is a performance evaluation using FEMA 356, Prestandard and Commentary for the Seismic Rehabilitation of Buildings (FEMA, 2000), based on simplified nonlinear analysis using pushover analysis (see Chapter 6). This method approximates the maximum lateral deformation that the building will suffer in a design event, considering the nonlinear behavior created by yielding and damage to components. The level of deformation of individual components is compared with standard deformations preset to performance levels of Collapse Prevention, Life Safety, and Immediate Occupancy, with the probable damage state of the building as a whole set at that level of the worst component. Efforts are being made to more realistically relate the damage states of all the components to a global damage state. This method can be used either to determine the probable damage state of the building for evaluation purposes, or to check the ability of a retrofit scheme to meet a target level. With the advancement of computer capability and analysis software, nonlinear analysis techniques are constantly being improved. The ultimate goal, although not expected to be an everyday tool in the near future, is to simulate the movements of the full buildings during an entire earthquake, including the constantly changing properties of the structural components due to yielding and damage. The overall damage to various components is then accumulated and the global damage state thereby surmised. 8.4.3 Other Evaluation Issues There are several other issues associated with seismic evaluation that should be recognized. Only three will be discussed here. First is the data required to perform competent evaluations at the various levels, as discussed above. Second, it is important to understand the performance expectation of the pass- fail line for various evaluation methodologies. Last, the reliability (or lack thereof) of the methods and of evaluation and/or performance prediction in general,should be recognized. Data Required for Seismic Evaluation Obviously, for methods depending on the FEMA building type, the building type must be known. In fact, there are other similar classifications of building types also used to define building performance at the broadest level. Using data as discussed in paragraph 8.4.1, crude expectations of performance and therefore comparative evaluation can be completed. Most such systems, however, are refined by age, physical condition of the building, configuration, and other more detailed data, when available. Most “rapid” evaluation methods, based on building type and very basic building characteristics, do not require structural drawings. Responsible evaluators will insist on a site visit (in many cases to make sure the building is still there, if nothing else). The more standardized evaluation methods discussed in paragraph 8.4.2 essentially require drawings. If detailed structural drawings are not available, simple evaluations of some model building types (wood buildings, tilt-ups, and sometimes URM) can be performed based on layout drawings or from data prepared from field visits. However, when reinforced concrete, reinforced masonry, or structural steel is a significant part of the structure, it is most often economically infeasible to reproduce “as-built” drawings. Practically in those cases, with rare exceptions, the building is deduced to be in nonconformance and, as a retrofit, a new seismic system is introduced to render the unknowns of the existing structure insignificant. Even in those cases, however, extensive field work is necessary to produce enough structural data to create a reasonable set of construction documents. If original structural drawings are available that are confirmed to be reasonably accurate from spot checks in the field, most evaluation techniques can be employed. However, material properties are often not included on the drawings and must be deduced from the era of construction. Deterioration can also affect the material properties of several building types. Often the potential variability in the analysis due to different possible combinations of material properties requires in-situ testing of material properties. The techniques for this testing are well established, but cost and disruption to tenants are often an issue. As explained in Chapter 3, “Site Evaluation and Selection”, many areas of the country are mapped in detail for seismic parameters related to design, although such parameters continue to be investigated and updated. When warranted, site- specific studies can be performed to obtain timely and locally derived data. However, other seismic site hazards, such as liquefaction, landslide, and potential surface fault rupture, are less well mapped and may require a site- specific study, if there is reason to suspect their potential at a site. Perhaps a less obvious important characteristic of a site is the detail of adjacent structures. Particularly in urban settings, adjacent buildings often have inadequate separation or are even connected to the building to be evaluated. Although legal issues abound when trying to deal with this issue, it is unrealistic to analyze and evaluate such a building as if it were freestanding. Formal evaluation techniques, such as ASCE 31, have addressed this issue, at least for buildings that are not connected, by highlighting the conditions known to potentially produce significant damage. First, if floors do not align between adjacent buildings and pounding is expected, the stiff floor from one building could cause a bearing wall or column in the adjacent building to collapse. Secondly, if buildings are of significantly different height, the interaction from pounding has been observed to cause damage. See Figure 8-8. Performance Objectives and Acceptability Traditionally, evaluation techniques have been targeted at determining if a building is adequately life safe in an earthquake, similar to code goals for new buildings. However, as discussed in section 8.2.2, a standard different and less than that used for new buildings evolved, but was still termed life safety. Only with the development of performance-based engineering did evaluation methods aimed at other performance standards emerge. Even life safety has proven to be amorphous over the years and often has been defined by the evaluation technique du jour. Seismically, life safety is a difficult concept, due to the huge potential variation in ground motion and the many sources of damage that could cause injury or death. However, the term is well embedded in public policy and continues to persist in seismic codes and standards. FEMA, in sponsoring the development of FEMA 273 (and later FEMA 356), wanted a more specific definition of a suitable goal for seismic safety, and thus the Basic Safety Objective (BSO) was defined. This performance objective consists of two requirements: the building would provide life safety for the standardized code event and, in addition, the building would not collapse in the Maximum Considered Event (MCE), a very rare event now defined by code. Since these FEMA documents are non-mandatory (unless locally adopted), the BSO has not become a widely accepted standard (the BSO also includes mandatory nonstructural minimum requirements, which also may delay its wide acceptance). Chapter 6 contains a detailed discussion of performance-based engineering, which is gaining acceptance for evaluations at any level. But performance characterization in various forms has been used for some time, primarily to set policy. Such policies require descriptions of various performance levels, even if the technical ability to define or predict the various levels often lagged behind. Table 8-2 shows several such performance descriptions, many developed decades ago, which have been used to set policy—most concentrating on life safety. The table is set up to approximately equilibrate levels of performance across horizontal lines. The first columns in Table 8-2 describe a system used by the University of California. GOOD, the best performance, is defined as the equivalent life safety as that provided by the code for new buildings—but without consideration of monetary damage. The next level below was set at the acceptable level for evaluation, while retrofits are required to meet the GOOD level. The next column, labeled “DSA”, is a Roman numeral system developed by the California Division of the State Architect for use with state-owned buildings. Each level has a description of damage and potential results of damage (“building not reocccupied for months”) but no reference to engineering parameters. The state used an acceptance level of IV, but set the goal for retrofits to III. The levels described in the next columns come from one of the early developments of performance based earthquake engineering, Vision 2000, developed by the Structural Engineers Association of California. It is a relatively comprehensive scale using five primary descriptions of damage, each with a “plus” and “minus”, resulting in ten levels. Finally, to indicate a perhaps more commonly recognized standard of performance, are the three occupancy tagging levels of Red, Yellow, and Green used for emergency evaluation immediately after damaging earthquakes. Reliability of Seismic Evaluations The most significant characteristic in the design of buildings for earthquakes is the variability of ground motions. Not only do magnitudes and locations vary, but also the effects of fault rupture, wave path, and local site soils create a literally infinite set of possible time histories of motion. Studies have shown that time histories within a common family of parameters used for design (response spectrum) can produce significantly different responses. This variation normally dominates over the scatter of results from analysis or evaluation techniques. However, codes for new buildings can require many limitations of material, lateral system, configuration, and height that will reasonably assure acceptable performance, particularly the prevention of collapse. These same limitations can seldom be applied to existing buildings, so the variation of actual performance is expected to be much larger. In addition, the cost of retrofit is often high, and attempts have been made to avoid unnecessary conservatism in evaluation methodologies. It is probable, therefore, that a significant number of buildings may fail to perform as evaluated, perhaps in the range of 10% or more. No comprehensive study has been made to determine this reliability, but ongoing programs to further develop performance-based seismic engineering are expected to estimate the variability of evaluation results and refine the methods accordingly. 8.5 SEISMIC REHABILITATION OF EXISTING BUILDINGS There are many reasons why buildings might be seismically retrofitted, including renovations that trigger a mandatory upgrade, a building subjected to a retroactive ordinance, or the owner simply wanting (or needing) improved performance. The reason for the upgrade may influence the technique and thoroughness of the work, because owners faced with mandatory upgrade may seek out the least expensive, but approvable, solution, whereas an owner needing better performance will more likely be willing to invest more for a solution that addresses their particular concerns. There are many other factors that shape a retrofit solution, such as the type of deficiency present, if the building is occupied, and the future use and aesthetic character of the building. The continuing improvement of analysis techniques and the emergence of performance-based design are also having a large effect on retrofit schemes, by enabling engineers to refine their designs to address the specific deficiencies at the desired performance level. In many cases, however, the retrofits are becoming controlled by the brittleness of existing components that must be protected from excess deformation with systems that may be stronger and/or stiffer than those used for new buildings. Some older retrofits, done to prescriptive standards or using now-outdated strengthening elements borrowed from new building designs, may themselves be deficient, depending on the desired performance. Seismic retrofit analysis, techniques, and components, similar to new building technology, are not static, and applications should be regularly reviewed for continued effectiveness. 8.5.1 Categories of Rehabilitation Activity In most cases, the primary focus for determining a viable retrofit scheme is on vertically oriented components (e.g. column, walls, braces, etc.) because of their significance in providing either lateral stability or gravity-load resistance. Deficiencies in vertical elements are caused by excessive inter- story deformations that either create unacceptable force or deformation demands. However, depending on the building type, the walls and columns may be adequate for seismic and gravity loads, but the building is inadequately tied together, still forming a threat for partial or complete collapse in an earthquake. It is imperative to have a thorough understanding of the expected seismic response of the existing building, and all of its deficiencies to design an efficient retrofit scheme. There are three basic categories of measures taken to retrofit a building: 1) Modification of global behavior, usually decreasing deformations (drifts); 2) Modification of local behavior, usually increasing deformation capacity; 3) Connectivity, consisting of assuring that individual elements do not become detached and fall, assuring a complete load path, and assuring that the force distributions assumed by the designer can occur. The types of retrofit measures often balance one another, in that employing more of one will mean less of another is needed. It is obvious that providing added global stiffness will require less deformation capacity for local elements (e.g. individual columns), but it is often less obvious that careful placement of new lateral elements may minimize a connectivity issue such as a diaphragm deficiency. Important connectivity issues such as wall-to-floor ties, however, are often independent and must be adequately supplied. Modification of Global Behavior Modification to global behavior normally focuses on deformation, although when designing to prescriptive standards, this may take the form of adding strength. Overall seismic deformation demand can be reduced by adding stiffness in the form of shear walls or braced frames. Addition of moment frames is normally ineffective in adding stiffness. New elements may be added or created from a composite of new and old components. Examples of such composites include filling in openings of walls and using existing columns for chord members for new shear walls or braced frames. Particular ground motions have a very specific deformation demand on structures with various periods, as discussed in Chapter 4. Given an equal period of vibration, this deformation will occur, whether distributed over the height of the building or concentrated at one floor. If one or more inter-story drifts are unacceptable, it may be possible to redistribute stiffness vertically to obtain a more even distribution of drift. A soft or weak story is an extreme example of such a problem. Such stories are usually eliminated by adding strength and stiffness in such a way as to more closely balance the stiffness of each level, and thus evenly spread the deformation demand over the height of the structure. Seismic isolation is the supreme example of the concept of redistribution of deformation. Essentially all deformation is shifted to bearings, placed at the isolation level, that are specifically designed for such response. The bearings limit the response of the superstructure, which can be designed to remain essentially undamaged for this maximum load. The feasibility of providing isolation bearings that limit superstructure accelerations to low levels not only facilitates design of superstructures to remain nearly elastic, but also provides a controlled environment for design of nonstructural systems and contents. Global deformations can also be controlled by the addition of passive energy dissipation devices, or dampers, to the structure. Although effective at controlling deformations, large local forces may be generated at the dampers that must be transferred from the device to structure and foundation, and the disruptive effect of these elements on the interior of the building is no different than a rigid brace. Modification of Local Behavior Rather than providing retrofit measures that affect the entire structure, deficiencies also can be eliminated at the local component level. This can be done by enhancing the existing shear or moment strength of an element, or simply by altering the element in a way that allows additional deformation without compromising vertical-load carrying capacity. Given that in most cases, that certain components of the structure will yield (i.e., become inelastic), some yielding sequences are almost always benign: beams yielding before columns, bracing members yielding before connections, and bending yielding before shear failure in columns and walls. These relationships can be determined by analysis and controlled by local retrofit in a variety of ways. Columns in frames and connections in braces can be strengthened, and the shear capacity of columns and walls can be enhanced to be stronger than the shear that can be delivered. Concrete columns can be wrapped with steel, concrete, or other materials to provide confinement and shear strength. Concrete and masonry walls can be layered with reinforced concrete, plate steel, and other materials. Composites of glass or carbon fibers and epoxy are becoming popular to enhance shear strength and confinement in columns, and to provide strengthening to walls. Another method to protect against the collapse risk posed by excess drift is to provide a supplementary gravity support system for elements that might be unreliable at expected high-deformation levels. For example, supplementary support for concentrated wall-supported loads is a requirement in California standards for retrofit of unreinforced masonry buildings. In several cases, supplementary support has also been used in concrete buildings. Lastly, deformation capacity can be enhanced locally by uncoupling brittle elements from the deforming structure, or by removing them completely. Examples of this procedure include placement of vertical saw cuts in unreinforced masonry walls to change their behavior from shear failure to a more acceptable rocking mode, and to create slots between spandrel beams and columns to prevent the column from acting as a “short column” prone to shear failure. Connectivity Connectivity deficiencies are within the load path: wall out-of-plane connection to diaphragms; connection of diaphragm to vertical lateral force-resisting elements; connection of vertical elements to foundation; connection of foundation to soil. A complete load path of some minimum strength is always required, so connectivity deficiencies are usually a matter of degree. A building with a complete but relatively weak or brittle load path might be a candidate for retrofit by seismic isolation to simply keep the load below the brittle range. The only location in the connectivity load path at which yielding is generally allowed is the foundation/structure interface. Allowing no movement at this location is expensive and often counterproductive, as fixed foundations transfer larger seismic demands to the superstructure. Most recently developed retrofit guidelines are attempting to provide simplified guidance to the designer on how to deal with this difficult issue and minimize foundation costs. 8.5.2 Conceptual Design of a Retrofit Scheme for an Individual Building There are many specific methods of intervention available to retrofit designers, as previously discussed. The selection of the specific type of element or system is dependent on local cost, availability, and suitability for the structure in question. Any system used to resist lateral load in new buildings can also be used for retrofit. It is thus an extensive task to develop guidelines for such selection. In addition, as in the design of a new building, there is usually a choice of where to locate elements, although it is generally more restrictive in existing buildings. However, in the end, there are nonseismic issues associated with each building or project that most often control the specific scheme to be used. The solution chosen for retrofit is almost always dictated by building user- oriented issues rather than by merely satisfying technical demands. There are five basic issues that are always of concern to building owners or users: seismic performance, construction cost, disruption to the building users during construction (often translating to a cost), long-term affect on building space planning, and aesthetics, including consideration of historic preservation. All of these characteristics are always considered, but an importance will eventually be put on each of them, either consciously or subconsciously, and these weighting factors invariably will determine the scheme chosen. Seismic performance Prior to the emphasis on performance-based design, perceived qualitative differences between the probable performance of difference schemes were used to assist in choosing a scheme. Now, specific performance objectives are often set prior to beginning development of schemes. Objectives that require a very limited amount of damage or “continued occupancy” will severely limit the retrofit methods that can be used and may control the other four issues. Construction cost Construction cost is always important and is balanced against one or more other considerations deemed significant. However, sometimes other economic considerations, such as the cost of disruption to building users, or the value of contents to be seismically protected, can be orders of magnitude larger than construction costs, thus lessening its importance. Disruption to the building users during construction Retrofits are often done at the time of major building remodels, and this issue is minimized. However, in cases where the building is partially or completely occupied, this parameter commonly becomes dominant and controls the design. Long-term effect on building space planning This characteristic is often judged less important that the other four and is therefore usually sacrificed to satisfy other goals. In many cases, the planning flexibility is only subtly changed. However, it can be significant in building occupancies that need open spaces, such as retail spaces and parking garages. Aesthetics In historic buildings, considerations of preservation of historic fabric usually control the design. In many cases, even performance objectives are controlled by guidelines imposed by preservation. In non historic buildings, aesthetics is commonly stated as a criterion, but in the end is often sacrificed, particularly in favor of minimizing cost and disruption to tenants. These parameters can merely be recognized as significant influences on the retrofit scheme or can be used formally to compare schemes. For example, a comparison matrix can be developed by scoring alternative schemes in each category and then applying a weighting factor deduced from the owner’s needs to each category. Figure 8-9 describes the evolution of a retrofit scheme based on several changes in the owner’s weighting of these five characteristics. 8.5.3 Other Rehabilitation Issues Inadequate recognition of disruption to occupants It is unfortunately common for the extent of interior construction and disruption to be underestimated. In many cases, occupants who were originally scheduled to remain in place are temporarily moved—at a significant increase in cost of the project—or the work is required to be done in off-hours, also a premium cost. Figures 8-10 and 8-11 indicate the level of construction intensity often required in retrofit. Similarly, “exterior solutions,” where strengthening elements are placed on the outside of the building are often more disruptive and noisier than anticipated and often require collector members to be placed on each floor within the building. Figure 8-12 shows the result of an exterior retrofit of adding towers on the outside of a building that, in fact, did not cause a single lost day of occupancy. High-strength steel rods were epoxied into horizontal cores, drilled twenty feet into the existing concrete beams to form the needed collectors. Collateral required work As previously mentioned, retrofit work is often performed in conjunction with other remodeling or upgrading activities in a building. Such work normally triggers other mandatory improvements to the building, such as ADA compliance or life safety updating—all of which add cost to the project. However, even when seismic retrofit is undertaken by itself, the costs of ADA compliance, removal of disturbed hazardous material, and possibly life safety upgrades must be considered. 8.5.4 Examples It is impossible to include examples that show the full range of structural elements and configurations used in seismic retrofit. There are definitely patterns, usually driven by economics or avoidance of disruption to occupants, but depending on the particular mix of owner requirements, as discussed in Section 8.5.2, thoughtful architects and engineers will always come up with a new solution. Photographs of retrofit buildings, although often interesting, seldom can tell the full story of the development of the scheme, and if the majority of retrofit elements are inside or hidden, tell almost nothing. Some photos are shown here, but are not intended to demonstrate the full range of buildings that have successfully undergone seismic retrofit or the full range of solutions to individual problems. In addition, due to limited space, only one or two points are made with each photo, rather than a full case study. 8.6 SPECIAL ISSUES WITH HISTORIC BUILDINGS Seismic evaluation and retrofit of historic buildings generate complex public policy issues for which few general rules can be identified. Restoration, or renovations of large and important historic buildings usually have considerable public and jurisdictional oversight, in addition to employing an experienced design team that includes a special historic preservation consultant. The control and oversight for less important buildings that have historic status at some level, or that may qualify for such status, are highly variable. Designers are cautioned to locally investigate approval procedures for alterations on such buildings as well as seismic requirement, for them. 8.6.1 Special Seismic Considerations It has been recognized in most areas of high seismicity that local public policy concerning seismic retrofit triggers must include special considerations for historic buildings. As discussed in Section 8.2, initial seismic safety criteria for existing buildings were focused on requirements for new buildings, which were marginally appropriate for most older buildings, but completely inappropriate for historic buildings. Special allowances were therefore created for archaic materials that were not allowed in new buildings, and the overall seismic upgrade level was lowered to reduce work that could compromise historic integrity and fabric. These kinds of technical criteria issues have been somewhat mitigated by the completion of FEMA 356 and the emergence of performance-based earthquake engineering, because consideration of archaic materials and fine-tuning of performance levels are now part of the normal lexicon. 8.6.2 Common Issues of Tradeoffs Many buildings in this country that qualify for historic status are not exceptionally old and can be made commercially viable. The changes that are needed for successful adaptive reuse will often conflict with strict preservation guidelines, and compromises are needed in both directions to achieve a successful project that, in the end, could save the building from continuing decay and make it more accessible to the public. These tradeoffs occur in many areas of design, but seismic upgrading work often requires interventions that are not needed for any other reason. These interventions often fall under historic preservation guidelines that call for clear differentiation of new structural components, or that discourage recreation of historic components that are removed. As previously indicated, there are no rules for these conditions, and the most appropriate solution for each case must be determined individually. Another common conflict is between current preservation of historic fabric and future preservation of the building due to the chosen seismic performance level. Typically, a better target performance in the future, possibly preventing unrecoverable damage, requires more seismic renovation work now. Most historic preservation codes allow lower expected seismic performance to reduce construction work and minimize damage. Like many seismic policies, there have not been enough earthquakes with seismically damaged historic buildings to test this general philosophy. In an ever-growing number of cases of important buildings, this dilemma has been addressed using seismic isolation—which by reducing loading to the superstructure, reduces required construction work and also reduces expected damage in future earthquakes. Typically, however, installing isolation into an existing building is expensive and may require a significant public subsidy to make viable. Several high-profile city hall buildings such as San Francisco, Oakland, Berkeley (after the 1989 Loma Prieta earthquake), and Los Angeles (after the 1994 Northridge earthquake) have been isolated, with FEMA assistance as part of post earthquake damage repairs. 8.6.3 Examples of Historical Buildings The following illustrations show samples of seismic retrofit of historic buildings with brief descriptive notes. Complete discussion of the preservation issues and rehabilitation techniques of each case would be extensive and cannot be included here. 8.7 Conclusion Table 8-3 summarizes common seismic deficiencies stemming from various site and configuration characteristics as well as those that might be expected in each FEMA model building type. See Section 8.2 for a discussion of “seismic deficiency” as used in this chapter and this table. Also included in Table 8-3 are retrofit measures that are often used for each situation. 8.8 References 8.8.1 References from Text American Society of Civil Engineers (ASCE), Seismic Evaluation of Existing Buildings, ASCE 31-03, 2003. Applied Technology Council (ATC), Earthquake Damage Evaluation Data for California, ATC 13, 1985. California Seismic Safety Commission (CSSC), Status of the Unreinforced Masonry Builidng Law, 2003 Report to the Legislature, SSC 2003-03, 2003. Federal Emergency Management Agency (FEMA), Prestandard and Commentary for the Seismic Rehabilitation of Buildings, FEMA 356, 2000. Holmes, William T., Background and History of the California Hospital Seismic Safety Program, Proceedings, Seventh National Conference on Earthquake Engineering, Boston, 2002, Earthquake Engineering Research Institute. Hoover, Cynthia A., Seismic Retrofit Policies: An Evaluation of Local Practices in Zone 4 and Their Application to Zone 3, 1992, Earthquake Engineering Research Institute. National Institute of Standards and Technology (NIST), Standards of Seismic Safety for Existing Federally Owned or Leased Buildings, ICSSC RP 6, 2002. U. S. Department of Interior (Interior a), The Secretary of the Interior’s Standards for Rehabilitation, Department of Interior Regulations, 36 CFR 67, U. S Department of the Interior, National Park Service, Preservation Assistance Division, Washington, D.C. U. S. Department of Interior (Interior b), Guidelines for Rehabilitating Historic Buildings, U. S Department of the Interior, National Park Service, Preservation Assistance Division, 1977, Washington, D.C. 8.8.2 To Learn More Applied Technology Council, Seismic Evaluation and Retrofit of Concrete Buildings, Report No. SSC 96-01, California Seismic Safety Commission, 1996. A contemporary of FEMA 356 that features many of the same methods and performance terminology. This document contains a good description of retrofit strategies. Earthquake Engineering Research Institute Ad Hoc Committee on Seismic Performance, Expected Seismic Performance of Buildings, SP 10, Earthquake Engineering Research Institute, 1994. This document was published slightly before FEMA 356 and thus contains slightly different performance terminology. However, photo examples and extensive description of damage states are contained. In addition, estimates are given for the approximate number of various buildings that would be expected to be in various damage states for different ground motion intensities. Federal Emergency Management Agency, Region 1, Safeguarding Your Historic Site, Boston, MA. This document contains an extensive bibliography covering renovation and repair of existing buildings. Freeman, John R. Earthquake Damage and Earthquake Insurance. McGraw-Hill Book Company, Inc., 1932, New York. Extremely interesting from a history standpoint, this book Includes discussion of seismology, geotechnical engineering, structural engineering, codes, and loss estimation, and excellent history and available data on earthquakes up to 1932. Holmes, William T., Risk Assessment and Retrofit of Existing Buildings, Proceedings Twelve World Conference on Earthquake Engineering, Auckland, New Zealand, 2000. This paper contains a more technically oriented description of the methods of FEMA 356 and strategies for design of retrofit systems. [End of Chapter 8]