From this point until launch, time involving final preparation of the Orbiter for flight is rigidly controlled. Payloads-related activities are kept to an absolute minimum, and physical access to the cargo bay is limited.
Following payload installation, a payload-to-Orbiter interface verification test is performed. An optional end-to-end communications test may be performed between a payload and its POCC. This test can include uplink and downlink data and voice communication to verify payload-to-POCC compatibility.
In support of the above tests, a payload console is provided and operated by KSC in the Launch Control Center (LCC) to monitor and control specific Spacelab and payload functions. Once again, from the user room in the O&C Building, you are able to monitor payload data transmitted by means of the Spacelab high-rate multiplexer.
At the conclusion of this testing, final payload close-out operations are conducted. This consists of activities such as final instrument service, film and tape loading, storage, final inspection. Payload operations in the OPF can require experimenter-furnished GSE. Space and electrical power are reserved for a limited amount of such equipment. For GSE access to the payload bay sill area, folddown platforms flank the open bay at door hinge height. Personnel may also access the payload bay interior by means of support platforms lowered from overhead workstands. Due to the nature of the flight equipment involved, KSC personnel will normally conduct any payload operations in the OPF.
Return to NASA Home Page Return to KSC Home Page