Comments for Review of NuMI Horn power supply Aug 13, 2001 from Robert Trendler ------------------------ 1. Overall Remarks The review was on target for the power supply, but too soon for the transmission line. The power supply is well designed and will meet the system requirements. Ken Bourkland and his colleagues are to be congratulated. Continued testing should shake out any anomalies, e.g. the capacitor connection failures described by Ken. It was clear from the discussion that work on the transmission line is at an early stage. However, important design decisions have been made and tested in the prototype installation. It appears that the design is on track and when complete will meet requirements. 2. Itemized suggestions, questions and concerns (1) While it appears that the transmission line design effort is only now fully underway, the design effort appears too fragmented. Overall design coordination is important to ensure that the whole design team is working with the same design criteria and with tools that each can utilize. (2) It is critical to ensure that the ultimate goal of being able to replace a horn is not lost in the details of the transmission line design specifics; flexible connection, quick disconnects, etc. As brought out at the review, the connection and disconnection for the replacement of a horn, while not yet addressed in detail, is likely to be a difficult process requiring great care to accomplish. It is important that all component designs address this issue. (3) Prototype testing of the connections (quick disconnect) should be done. Alignment of connector may be difficult to accomplish in the final configuration.