For additional information contact Rhea DoBosh at (907) phone 257-1338, fax 646-5014
Surveillances –
Mainline integrity investigation
Pipeline Milepost 211.12. Ref
FBU-05-S-070 – 072, 076
Mainline integrity investigation
Pipeline Milepost 215.59. Ref
FBU-05-S-078
Section 29, Alaska Native Utilization
Agreement recruiting. Ref FBU-05-S-087
Exercises –
Staff observed a “source
control” exercise using the hydraulic clamp as well as the source control
training held in preparation of the exercise.
The clamp resulted from recommendations for improvement after the
Milepost 400 bullet hole incident in 2001. A portable pipeline was set up to a small
bladder farm to demonstrate the ability to control the evacuation of crude oil
from the line. Supporting equipment included
fire foam skids and appropriate personal protection.
Staff also observed a live fire
session at the
TAPS Strategic Reconfiguration
(SR) –
Surveillances –
Concrete grout strength for Pump
Station (PS) 5 pilings. Reference FBU-05-S-073
Verify work site safety
associated with pilings for new modules.
Ref FBU-05-S-061
Aerial
surveillance of right-of-way north of PS 3. Ref FBU-04-S-068
Aerial
surveillance of right-of-way north of PS 4. Ref FBU-04-S-074
Aerial
surveillance of right-of-way north of PS 5. Ref FBU-05-S-075
Environmental issues associated
with PS 4 piling work. Ref FBU-05-S-069
Environmental issues associated
with PS 9 piling work. Ref FBU-05-S-085
Site specific
safety plan for PS 9 piling installation. Ref FBU-05-S-086
Mainline pump motor testing for SR
–
Staff from the JPO
observed the factory testing of the new variable speed 6500 HP motors which
will drive the pipeline pumps at Pump Stations 1, 3, 4, and 9. These pumps and motors will move the oil
through the pipeline after the strategic reconfiguration; they will replace the
existing turbine driven pumps.
The
motors were tested to insure safe operation in the new pump buildings which
could contain farmable gases or vapors during abnormal or upset conditions. The motors passed the tests with substantial
margin; there were no outstanding issues from these tests.
The
motor will now be completed and shipped to the pump manufacturer in
SR Notice to Proceed Reviews are
being performed -
PS 1 Piling
PS 4 inside work – existing buildings
State fire safety regulations -
PS 1, 3, and 4 cyclone turbine generator buildings and turbine generator
installation
State fire safety regulations –
PS 4 module installation and tie-in
Combustion gas turbine &
electrical generator
The
Alaska Natural Gas Development Authority (ANGDA) application for a natural gas
spur line from Glennallen to Palmer is available on-line at www.jpo.doi.gov.
- end –
To
receive weekly reports via e-mail, contact Rhea DoBosh at RDOBOSH@jpo.doi.gov.
The
Joint Pipeline Office is a consortium of six State and six Federal agencies
with oversight responsibilities for the Trans-Alaska Pipeline System and other
oil and gas pipelines in